160908 harvie passage project update sept 2016 · 2019. 1. 2. · harvie passage 2013 flood damage...

2
HARVIE PASSAGE 2013 FLOOD DAMAGE REPAIR PROJECT UPDATE Welcome to the September 2016 update for the Harvie Passage 2013 Flood Damage Repair project. As the project advances through construcƟon and commissioning, we will keep you informed via this newsleƩer. September 2016 Final Engineering Complete and ConstrucƟon Started We would like to thank all stakeholders who parƟcipated in the development of the nal design and the tendering of the Harvie Passage 2013 Flood Damage Repair Project. Final design of Harvie Passage included: comprehensive numeric hydraulic modelling of the Low Water Channel (LWC); computergenerated earthwork design of the High Water Channel (HWC) and LWC; development of construcƟon drawings and technical specicaƟons; landscape design of the LWC and the divide island between the HWC and LWC was completed by O2 Planning + Design; preparing and supporƟng regulatory applicaƟons; preparing construcƟon cost esƟmates and preparaƟon of construcƟon tender documents. The construcƟon tender documents were completed in June 2016, tendering occurred in June and July, and the construcƟon contract awarded to Bluebird ContracƟng Services Ltd. of Calgary, Alberta on July 29, 2016. Throughout the nal engineering and regulatory approval process stakeholder input was solicited at key junctures. Several meeƟngs and conversaƟons with representaƟves from Alberta TransportaƟon; Alberta Environment and Parks; City of Calgary’s Water Resources, Parks, and Fire Department; Department of Fisheries and Oceans Canada; Transport Canada; Calgary River Users Alliance; Harvie Passage Alliance; and Calgary River Valleys. Next Stage – ConstrucƟon The next stage of the Project is construcƟon. The construcƟon contractor, Bluebird ContracƟng Services Ltd., mobilized to site in late August and started instream work on August 30, 2016. Work this fall will focus on rehabilitaƟng HWC Drops #3L, #3R, and #4. Depending on construcƟon progress, work will shut down over the winter and start up again in March 2017. The construcƟon of the new LWC is planned from April to October 2017. Instream hydraulic performance tesƟng of the new LWC is scheduled in August 2017. ConstrucƟon of the enƟre Project is scheduled to be completed by June 2018. Project Status Coerdam ConstrucƟon September 1, 2016 Low Water Channel—Landscape Design Concept

Upload: others

Post on 23-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 160908 Harvie Passage Project Update Sept 2016 · 2019. 1. 2. · HARVIE PASSAGE 2013 FLOOD DAMAGE REPAIR PROJECT UPDATE Welcome to the September 2016 update for the Harvie Passage

HARVIE PASSAGE 2013 FLOOD DAMAGE REPAIR PROJECT UPDATE

Welcome to the September 2016 update for the Harvie Passage 2013 Flood Damage Repair project. As the project advances through construc on and commissioning, we will keep you informed via this newsle er.

September 2016

Final Engineering Complete and Construc on Started We would like to thank all stakeholders who par cipated in the development of the final design and the tendering of the Harvie Passage 2013 Flood Damage Repair Project.

Final design of Harvie Passage included: comprehensive numeric hydraulic modelling of the Low Water Channel (LWC); computer‐generated earthwork design of the High Water Channel (HWC) and LWC; development of construc on drawings and technical specifica ons; landscape design of the LWC and the divide island between the HWC and LWC was completed by O2 Planning + Design; preparing and suppor ng regulatory applica ons; preparing construc on cost es mates and prepara on of construc on tender documents. The construc on tender documents were completed in June 2016, tendering occurred in June and July, and the construc on contract awarded to Bluebird Contrac ng Services Ltd. of Calgary, Alberta on July 29, 2016.

Throughout the final engineering and regulatory approval process stakeholder input was solicited at key junctures. Several mee ngs and conversa ons with representa ves from Alberta Transporta on; Alberta Environment and Parks; City of Calgary’s Water Resources, Parks, and Fire Department; Department of Fisheries and Oceans Canada; Transport

Canada; Calgary River Users Alliance; Harvie Passage Alliance; and Calgary River Valleys.

Next Stage – Construc on The next stage of the Project is construc on. The construc on contractor, Bluebird Contrac ng Services Ltd., mobilized to site in late August and started instream work on August 30, 2016. Work this fall will focus on rehabilita ng HWC Drops #3L, #3R, and #4. Depending on construc on progress, work will shut down over the winter and start up again in March 2017. The construc on of the new LWC is planned from April to October 2017. Instream hydraulic performance tes ng of the new LWC is scheduled in August 2017. Construc on of the en re Project is scheduled to be completed by June 2018.

Project Status

Cofferdam Construc on ‐ September 1, 2016

Low Water Channel—Landscape Design Concept

Page 2: 160908 Harvie Passage Project Update Sept 2016 · 2019. 1. 2. · HARVIE PASSAGE 2013 FLOOD DAMAGE REPAIR PROJECT UPDATE Welcome to the September 2016 update for the Harvie Passage

Project Team Facility Owner and Operator:

Alberta Environment and Parks

Project Manager:

Alberta Transporta on

Engineering Consultants:

Klohn Crippen Berger Ltd   Project management, civil design and construc on 

Northwest Hydraulics Consultant Ltd   Physical and numeric hydraulics and river morphology 

Recrea on Engineering and Planning Recrea onal hydraulics

SG1 Water Consul ng Ltd   Hydraulics and recrea onal hydraulics 

Mr. Charles Walbridge   Aqua c safety specialist 

O2 Planning + Design

  Landscape Design 

Harvie Passage 2013 Flood Damage Repair Project Update September 2016

Project Goals

The goal for the rehabilita on of Harvie

Passage is to reinstate the pre‐flood func onal

intent of the Project.

The key aspects of this goal are:

Safety – Allow for safer passage for all types of

water cra and fish.

Structure integrity – Design to withstand a 1 in

100 year flood with reasonable levels of

maintenance.

Recrea on – Provide a variety of features for

recrea onal and educa onal use.

For More Informa on An open dialogue with all stakeholders is always important to us. If you have any queries or comments about the Harvie Passage 2013 Flood Damage Repair Project we encourage you to contact Chuck Slack, at 403‐730‐6848 or [email protected].

Project Schedule Dates are subject to change.