    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National CycloneRisk Mitigation Project (NCRMP)

  • 7/31/2019 1.September MPR 2011

    2/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National CycloneRisk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Review meetings and Major Events of this Month 3

    4.0 Status of TPQA Visits 4

    5.0 Progress of NCRMP works 5

    6.0 District wise status of tests conducted by TPQA 16

    7.0 Details of Audit Reports Submitted during this Month 17

    8.0 Observations of Submitted Reports 17

    9.0 Details of Social & Environmental Reports Submitted in this Month 25

  • 7/31/2019 1.September MPR 2011

    3/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National CycloneRisk Mitigation Project (NCRMP)

    1.0 Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belt in India. Out of 67,362 Km of road network in the state, the

    nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December,

    cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are

    increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging

    from 1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due

    to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on

    experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

    existing facilities available in the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

    Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

    proceeds to payments for goods, works, related services and consulting services under this Project.

    National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

    Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

    Audit for 9 coastal districts namely Srikakulam, Vijayanagarm, Visakhapatnam, East Godavari, West Godavari, Krishna,

    Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

    Shelters, Roads to habitations and Roads & Bridges under NCRMP is funded by International Development

    Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

    implemented by various line departments working under PIU. The number of works under progress / for which

    agreements are concluded in each district is shown in the table below.

  • 7/31/2019 1.September MPR 2011

    4/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National CycloneRisk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

    with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st

    May20 11, the Contract for Consultancy Service was signedbetween The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

    0246

    8101214161820

    Total no. of works Not Started

    Total no. of works Progress

    Details of works

  • 7/31/2019 1.September MPR 2011

    5/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National CycloneRisk Mitigation Project (NCRMP)

    DM, followed by works inspectionGuntur works by PD, NCRMP,Hyderabad.

    by PD, NCRMP.

    5Guntur, Hotel Sinduri One day State level workshop for

    contractors on World Bankprocurement guidelines organizedby PIU, NCRMP

    20.09.2011 All the contractors, DepartmentOfficers from R&B and PR of West Godavari, Krishna,Guntur, Prakasham andNellore along with TPQA and

    PMC of NCRMP hadparticipated in the workshop.

    6VisakhapatnamNCRMP worksinspection

    Inspection of NCRMP works of Visakhapatnam by SE, PIU,NCRMP and EE, PIU, NCRMP,Hyderabad.

    21.09.2011 Following Three works wereinspected. 1. Road fromVempadu to Patimeeda, 2.Road from R&B road toMulaparra upto Beach end, 3.Road from R & B road to

    Venkayyapalem

    7Visakhapatnam, HotelMeghalaya

    One day State level workshop for contractors on World Bankprocurement guidelines organizedby PIU, NCRMP

    22.09.2011 All the contractors, DepartmentOfficers from R&B and PR of East Godavari,Visakhapatnam, Vizainagram,and Srikakulam along withTPQA and PMC of NCRMPhad participated in the

    workshop

    4 0 Status of TPQA Visits:

  • 7/31/2019 1.September MPR 2011

    6/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National CycloneRisk Mitigation Project (NCRMP)

    5.0 Progress of NCRMP works:

    The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

    agreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of ActivitiesAgreements for Packages Status of works

    0

    1020

    30

    40

    50

    60

    70

    80

    In Sept.'2011

    Up to Aug'2011

    No. of Visits by TPQA

  • 7/31/2019 1.September MPR 2011

    7/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with6

    Status of works in Srikakulam District up to 30.09.2011

    Category Packages allotted underPhase - 1 Names of works under each packageAgreement No. /Date DHS DFC

    Progress up to30.09.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&B road toUddandapalem

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12

    Earthwork & CDworks &GSB

    Road from K. Umilada Junction to Koduru(Link Road)

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12

    Earthwork & CDworks &GSB

    Road from Borubhadra, Malagam toKollipadu via Seepuram, Gantapeta

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12

    Earthwork & CDworks &GSB

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B road Mobagam toDuubakavanipeta via Gajapathinagaram

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12

    Earthwork & CDworks &GSB

    Road from Talasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12

    Earthwork & CDworks &GSB

    NCRMP/B-

    W/AP/RHB/PRED/01/Polaki/005

    Road from R&B road Edulavalasa - Killamto Jonnam via Talasamudram

    /2011-12, Dt.30.04.2011 30.04.11 31.01.12

    Earthwork & CDworks &GSB

    Bridges

    NCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

    Construction of bridge at Km 11/6-8 of NH-5 to Patnavanipeta ConnectingSundarapalem

    46/2011, Dt.17.12.2010 17.12.10 17.06.12

    Foundation uptowell caping

    NCRMP/B-W/AP/Br/R&B/01/Surampeta/003

    Construction of Minor Bridge at Km 12/2-4of NH-5 to Surampeta Road via Naruva,mentada

    45/2010-2011,Dt17.12.2010 17.12.10 17.03.12

    Completion uptobelow the Deckslab.

    NCRMP/B-W/AP/Br/R&B/01/Bendigedda/004

    Construction of High level bridge acrossBendi gedda at KM 4/10 of Pundi-Parlakimidi road in Srikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.11.10 11.05.12

    Foundation uptowell caping

    Roads

    NCRMP/B-

    W/AP/RD/R&B/01/Nowpada/006)

    Improvesments Naupada-Venkatapuram

    road from 0/0to15/0km43/2010-11,17.12.2010 17.12.10 17.03.12

    WMM Shoulders inprogress

  • 7/31/2019 1.September MPR 2011

    8/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with7

    Status of works in Vizianagaram District up to 30.09.2011

    Category Packages allotted underPhase - 1Names of works under each

    packageAgreement No./

    Date DHS DFCProgress up to

    30.09.2011

    Bridges

    NCRMP/ B-W/ AP/ Br/ R&B/02/ Puligadda/ 007

    Construction of Minor Bridge at Km. 7/2near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P. Road)

    31/2010-2011Dt. 1.12.2010 01.12.10 31.05.12

    30.96% of workcompleted

    NCRMP/ B-W/ AP/ Br/ R&B/

    02/ Chakaligadda / 008

    Construction of Minor Bridge at Km 15/2near Chakaligedda of KonadaRamatheertham R&B road toKonatalapalem (via) Yerukonda,Pasupam, Kollayavalasa (ZP Road)

    34/2010-2011

    Dt. 8.12.201008.12.10 07.06.12 55.19% of work

    completed

    Road (R&B) NCRMP/B-W/AP/RD/R&B/02/ Konada/009

    Improvements to Road from KonadaRamatheertham (R&B) Road toKonathalapalem (Via) Pasupam,Yerukonda, Kollayavalasa from Km 12/0to 16/5 (Km 0/0 to 4/0 i.e. upto NH-5crossing)

    33/2010-2011Dt. 8.12.2010 08.12.10 07.03.12

    95% of workcompleted

  • 7/31/2019 1.September MPR 2011

    9/31

  • 7/31/2019 1.September MPR 2011

    10/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with9

    Status of works in East Godavari District up to 30.09.2011

    Category Packages allotted underPhase - 1Names of works under each

    package Agreement No. / Date DHS DFCProgress up to

    30.09.2011

    RHB

    NCRMP/B-W/ AP/RCS/PRED/04/

    KARAPA/001

    ROAD FROM APPROCH ROADTO CYCLONE SHELTER AT

    ADAVIPUDI IN E.G.Dt./2011-12, Dt.20.05.2011 20.05.11 19.02.2012

    20% of workCompleted

    ROAD FROM GURAJANAPALLITO BANDULAVARIPALEM /2011-12, Dt.27.04.2011 27.04.11 26.01.2012

    10% of workCompleted

    NCRMP/B-W/ AP/RHB/PRED/04/KATRENIKONA/003

    ROAD FROM PR ROAD TO

    DASARIVANIPETA AND TOCYCLONE SHELTER /2011-12, Dt.27.04.2011 27.04.11 26.01.2012 30% of workCompleted

  • 7/31/2019 1.September MPR 2011

    11/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with10

    Status of works in West Godavari District up to 30.09.2011

    Category Packages allotted underPhase - 1 Names of works under each packageAgreement No.

    / Date DHS DFCProgress upto 30.09.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/05/Mogalthuru/001

    Road from NH 214 A at Ranga Statue center toHarijanawada of Kalipatnam (E) (Mogalthuru Mandal

    W.G.Dist.)

    /2011-12 , Dt.27.04.2011 27.04.11 26.07.2012

    Works notstarted

    R&B road at Panchayat Office to Pulaparthivarithotavia Badava (Mogalthuru Mandal W.G.Dist.)

    Mogalthuru Vempa R&B Road at Uchintha KalavaBridge to Gogulamma Harijanapeta (Mogalthuru

    Mandal W.G.Dist.)

    From Narsapur Mogalthur R&B road toDayadaldaspeta via Venkateswara Swamy temple(Mogalthuru Mandal W.G.Dist.)

    Road from NH 214 A road to Harijanapeta of Kothota(Mogalthuru Mandal W.G.Dist.)

    NCRMP/B-W/AP/RHB/PRED/05/Nasapur/002

    R&B Road to indira nagar (via) Pochamma temple(Nasapur Mandal W.G.Dist.)

    /2011-12 , Dt.09.05.2011 09.05.11 08.05.2012

    Works notstarted

    Road from R&B road to Pedalanka (Nasapur MandalW.G.Dist.)

    Road from LB Cheria CC road to Chillapalem of LBCheria (Nasapur Mandal W.G.Dist.)

    NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

    From A-U R&B Road to Satyanarayanapuram, (KallaMandal W.G.Dist.) /2011-12 , Dt.

    26.05.2011 26.05.11 25.02.2012Works not

    startedFrom A-U R&B Road to Mekaladibba

  • 7/31/2019 1.September MPR 2011

    12/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with11

    Status of works in Krishna District up to 30.09.2011

    CategoryPackages allotted under Phase

    - 1Names of works under each

    packageAgreement No. /

    Date DHS DFCProgress up to

    30.09.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001

    Road connecting R&B roadthrough Gantalammapalem /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    Jungle clearanceand earth work inprogress

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002

    Road from R & B Road to B.VThota

    /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    Jungle clearanceand earth work inprogress

    Road from Potlapalem Z.P roadto Chikativanipalem

    Jungle clearanceand earth work in

    progress

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road toRangaraopet

    /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    Jungle clearanceand earth work inprogress

    Road from R&B road to CycloneShelter at Chandala

    Jungle clearanceand earth work inprogress

  • 7/31/2019 1.September MPR 2011

    13/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with12

    Status of works in GUNTUR District up to 30.09.2011

    CategoryPackages allotted under

    Phase - 1 Names of works under each packageAgreement No./

    Date DHS DFCProgress up to

    30.09.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KARLA

    PALEM/001

    R/f Ganapavaram R&BRoad to Kesavapuri ST colony 7/2011-2012

    27.04.2011 27.04.11 26.01.2012 Work not started

    NCRMP/B-W/AP/PRED/07/Nagaram/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-201227.04.2011 27.04.11 26.4.2012

    Earth work inprogress

    R/f R&B Road to Katurivaripalem. Earth work inprogress

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

    Reconstructuion of Highlevel Bridge@Km5/2 of Bapatla-Suryalaka Road acrossperli drain in Guntur 79/2010-20111.12.2010 01.12.10 31.5.2012

    Abutments andpiers completed

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

    Reconstructuion of Highlevel Bridge@Km2/4 of Bapatla-Pandurangapuram

    Road across perli drain in Guntur 78/2010-20111.12.2010 01.12.10 31.5.2012

    Abutments andpiers completed,

    one deck slabcompleted

  • 7/31/2019 1.September MPR 2011

    14/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with13

    Status of works in Prakasam District up to 30.09.2011

    Category Packages allotted underPhase - 1Names of works under each

    package Agreement No. / Date DHS DFCProgress up to

    15.09.2011

    BRIDGES NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012

    Construction of High levelBridge at Km 16/10 of

    Naguluppalapadu Kanaparthiroad in Prakasam District

    76/2010-11 Dated 1/12/2010 01.12.10 31.5.12 Piers raised up tobed block

    RHB

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/

    001

    Road from Pakala ZP Road to Aulavaripalem Cyclone shelter

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Dated 10/02/201110.02.11 9.2.12 GSB to bed one

    Road from R&B Road toSomarajupalli

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Dated 10/02/201110.02.11 9.2.12 GSB to bed one

    Road from R&B road toNarravaripalem

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Dated 10/02/201110.02.11 9.2.12 Work not Resumed

    NCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/002

    Road from NH5 toMulaguntapadu

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    dated 10/02/201110.02.11 10.02.12 Not Started

    Road from R&B road toChalivendradibba

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    dated -10/02/201110.02.11 10.02.12 GSB to bed one

    Road from Pakala R&B road toMosanaladinne

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002dated 10/02/2011

    10.02.11 10.02.12 GSB to bed one

    Road from R&B road toBinginapalli Harijanawada

    Cyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    dated 10/02/201110.02.11 10.02.12 Work not Resumed

  • 7/31/2019 1.September MPR 2011

    15/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with14

    Status of works in Prakasam District up to 30.09.2011

    Category Packages allotted under Phase -1Names of works under

    each package Agreement No. / Date DHS DFCProgress up to

    30.09.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatna

    m/003

    Road from R&B Road Allur to M T Raju colony NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/

    003 Dated 27/04/201127.04.11 27.04.12

    CC road layingcompleted and GSB in

    progress

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatna

    m/004

    Road from KEM R&BRoad to Sankuvarigunta

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/

    004 Dated 27/04/201127.04.11 27.04.12

    CC road layingcompleted and GSB

    progress

    Road from KEM R & BRoad to

    Pullareddypalem

    NCRMP/B-

    W/AP/RHB/PRED/08/Kothapatnam/004 Dated 27/04/2011 27.04.11 27.04.12

    CC road laying

    completed and GSBprogress

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/0

    7

    Road from MC Road toSubbarayudu Satram

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

    dated 27/04/201127.04.11 27.04.12 GSB in progress

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/0

    8

    Road from R&B roadTettu to Ramayapatnam

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

    dated 27/04/201127.04.11 27.04.12

    CC road and BTlaying completed

    Shoulders progress

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

    Road from R&B roadPellur to Vasepallipadu

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

    dated 16/03/201116.03.11 16.03.12 CC road completed &GSB in progress

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10

    Road from R&B road toKesupalem

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10

    dated 16/03/201116.03.11 16.03.12 Culvert EncasementWork is in Progress

  • 7/31/2019 1.September MPR 2011

    16/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with15

    Status of works in Nellore District up to 30.09.2011

    CategoryPackages allotted under Phase

    - 1 Names of works under each packageAgreementNo. / Date DHS DFC

    Progress up to30.09.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/001

    Road from NH 5 to Sambasivapuram34/2010-11, Dt.19.01.2011 19.01.11 19.4.12

    WBM Gr-II CompletedRoad from 9/6 of Zuvvaladinne R&B Road to 11/0 of Zuvvaladinne R&B viaVenkideshpalem(Venkateshpalem) WBM Gr-III is in Progress

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/002

    Road from 1/6 of Zuvvaladinne R&B road toTellagunta

    / 2010 - 11, Dt.07.02.2011 07.02.11 06.11.11 WBM Gr-II Completed

    NCRMP/B-W/AP/RHB/PRED/09/Chittamur/003

    Road from R&B road to Muttembake Via Pittuvanipalli 2010-11Dt18.01.2011 18.01.11 18.4.12

    GSB Completed

    Road from R&B Chittamur to Soma Samudram GSB Completed

    NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

    Road from K.T R&B Road to Alliguntapalem

    32/2010-11, Dt.17.01.2011 17.01.11 27.4.12

    BT is in progressRoad from Km 5/8 of Chennayapalem Road

    toGummadi Bandala BT CompletedRoad from Pedapattapupalem R&B road toChennayapalem H. Wada Side Earth in progress

    NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005

    Road from R&B Road Alagani padu to Vavilla/ 2011 - 12, Dt.27.04.2011 27.04.11 27.7.12

    CC Road completedRoad from R&B road Kancharapalem HW to

    Alaganipadu Side Earth is in Progress

    RHBNCRMP/B-W/AP/RHB/PRED/09/Muthukur/006 Road from R&B Road to PatuvariKandriga

    /2010-11Dt.25.04.2011 25.04.11 25.1.2012 BT Completed

    NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/007

    Survepalli Pudiparthi Road to Srikanth Colony / 2011 - 12, Dt.27.04.2011 27.04.11 27.4.2012

    WBM Gr_III CompletedRoad from R & B Road to Edagali Kandriga WBM Gr_III Completed

    NCRMP/B-W/AP/RHB/PRED/09/Allur/009

    Road from R&B Road Allur to Galidibbalu (via)Chukavani dibba

    /2010-11 Dt.24.01.2011 24.01.11 24.4.2012 GSB is Completed

    RCS

    NCRMP/B-W/AP/RCS/PRED/09/Kota/001

    Road from R&B Road to A.S. Puram 2010-11Dt10.05.2011 10.05.11 10.2.2012

    Earth work in embankmentRoad from GD road to Vavillapalem Earth work in embankment

    NCRMP/B-W/AP/RCS/PRED/09/Muthukur/002

    Road from R&B road Kappaladoruvu to BandlapalemH.Wada

    /2010-11 Dt.21.04.2011 21.04.11 21.1.2012 WBM-Gr-III

    NCRMP/B-W/AP/RCS/PRED/09/Chillakur/004 Road from Kakuvaripalem R&B Road to Vellapalm

    /2010-11Dt23.05.2011 23.05.2011 23.2.2012

    Jungle clearence is inprogress

    NCRMP/B-W/AP/RCS/PRED/09/T.P.Gudur/005

    Road from 7/2 M.C road to VenkannapalemPattapupalem

    2011-10 Dt17.05.2011 17.05.2011 17.2.2012 GSB is in progress

    NCRMP/B-W/AP/RCS/PRED/09/DV.Satram/008

    Road from R&B road to Sullurpeta Mallam toBerjengalapalli cyclone shelter

    /2010-11 Dated9.05.2011 09.05.2011 9.2.2012

    Construction of culvert isin progress

  • 7/31/2019 1.September MPR 2011

    17/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    6.0 District wise status of tests conducted by TPQA:

    Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

    stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests

    are carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The

    details of tests conducted in the field till end of September 2011 are presented.

    Summary of QC Tests - Up to 30.09.2011

    S.No. District Total No. TestsDoneTotal no. of Tests

    Passed Failed

    1 Srikakulam 100 85 15

    2 Vizianagaram 122 119 3

    3 Visakhapatnam 155 154 1

    4 East Godavari 39 39 0

    5 West Godavari 0 0 0

    6 Krishna 0 0 0

    7 Guntur 53 53 0

    8 Prakasham 95 91 4

    9 Nellore 154 154 0

    140

    160

  • 7/31/2019 1.September MPR 2011

    18/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    7.0 Details of Audit Reports Submitted During this Month:

    S.NO District Package Number Name of work

    1 Srikakulam NCRMP/BW/AP/RHD/PRED/01/Santhabommali/003

    Road from Borubadra,Malagam toKollipadu in Santhabommali mandal.

    2 Srikakulam NCRMP/BW/AP/RHD/PRED/01/Santhabommali/003 Road from DPN R&B Road toUddandapalem in Santhabommali mandal.

    3 Srikakulam NCRMP/BW/AP/RHD/PRED/01/Santhabommali/003

    Road from K.Umilada jn to Koduru (linkroad) in Santhabommali mandal.

    4 Guntur NCRMP/BW/AP/PRED/07/Nagaram/002.

    Road from R&B Road to Katuivaripalem inNagaram Mandal.

    5 Guntur NCRMP/BW/AP/PRED/07/Nagaram/002. Road from Ganapavaram R&B Road toMohammedalipalem.

    6 Guntur NCRMP/B-W/AP/Br/R&B/07/Bapatla/011/

    2010

    Reconstruction of HLB @ Km 2/4 of Bapatla Pandurangapuram road across

    Perli Drain in Guntur

    7 Guntur NCRMP/B-W/AP/Br/R&B/07/Bapatla/010/

    2010

    Reconstruction of HLB @ Km 2/4 of Bapatla Suryalanka road across Perli

    Drain in Guntur 8 Nellore NCRMP/B -

    W/AP/RCS/PRED/09/Muthukur/002

    Road from R&B Road kappaladoruvu tobandla palem H.wada

    9 Nellore NCRMP/BW/AP/RHB/PRED/0 Providing BT Surface to theRroad from

  • 7/31/2019 1.September MPR 2011

    19/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    3 The width of shoulder formation is verified from 0/0 to 2/250 Km., Shoulders portion in some areashave slipped and the same may be rectified.

    4 Formation width is less than 7.50 mts from Km: 1/600 to 1/900, & from Km:2/350 to 2/530.

    5 From Km:1/600 to 1/900 the road level is lower than the surrounding fields level, and in this stretchsand may occur in monsoon period, this aspect needs examination.

    6 The tank bund portion from Km 2.350 to 2.530 , the height difference between road top level and fieldlevel is more than 3.0mts. But no slope protection work is provided.

    7 Safety measures like providing caution boards and providing helmets is to be done.

    8 White wash shall be done to parapet walls of the existing culverts for the clear visibility of vechicular traffic.

    9 Some of the KM & HM Stones are missing in this working road stretch. The field officers are requestedto erect them immediately.

    10 Compliance shall be submitted para wise earlier after attending to the above remarks.

    Name of Work :Road from DPN R&B Road to Uddandapalem in Santhabommali mandal.

    1 13.00 % value of the work is completed. Earth work for Shoulders upto existing road level iscompleted.All the four CD works are completed. 2 layers of WBM+OGPC+SC is to be done from Km 0.0to 1/850.

    2 Combined milestones for 3 works in this packageMilestone 1 : Earthwork, CD Works, GSB - 4 months.Milestone 2 : WBM Gr-II, Gr-III and Shoulders - 8 months.Milestone 3 : BT and Road funiture - 12 months.

  • 7/31/2019 1.September MPR 2011

    20/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    Name of Work :Road from K.Umilada jn to Koduru (link road) in Santhabommali mandal.

    1 25.00 % value of the work is completed. All the 3 culverts completed. Earthwire for wideningembankment is completed. GSB work is in progress

    2 Combined Milestones for three works in this Package : Milestone 1 : Earthwork, CD Works, GSB - 4 months.Milestone 2 : WBM Gr-II, Gr-III and Shoulders - 8 months.Milestone 3 : BT and Road funiture - 12 months.

    3 The width of shoulder formation is verified from 0/0 Km to 1/265Km. At some location shoulders haveslipped and gullies formed which shall be rectified.

    4 The Contractor has not provided Q/C laboratory at site.

    5 From CH:1/100 to 1/265 the road level is lower than the surrounding fields level.

    6 Pipe culverts alignment & headwall line, are not maintained properly.

    7 Old narrow pipe culvert between Ch:1/100 to 1/200 were not replaced and it may be prone to accidents.

    8 Safety measurements are not taken while execution of the work like providing safety helmets andCaution boards..etc.

    9 White wash shall be done to parapet walls of the existing culverts for the clear visibility of vehicular traffic.

    10 Some of the KM & HM Stones are missing in this working road stretch. The field officers are requested

    to erect them immediately.11 Cautionary and mandatory signboards shall be at necessary points like sharp curves and schools.

    12 Compliance shall be submitted para wise earlier after attending to the above remarks

  • 7/31/2019 1.September MPR 2011

    21/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    4 The field officers have not furnished the test results for Embankment soil .The field officers are requestedto furnish the Soil test results to the T.P.Q.A. staff for verification.

    5 The earth work done in the widening portion is not yet compacted. It is to be compacted in layers and thethe field density shall be compared with laboratory density for ensuring the specified relative compaction.

    6Material Registers are not available. The field officers are requested to maintain the material registersand same shall be furnished to the T.P.Q.A. staff for verification.

    7 The field officers have not furnished the Mix designs for various grades of concrete (cc pavemant andculverts).The field officers are requested to furnish the mix designs to the T.P.Q.A. staff for verification.

    8 KM & HM Stones are not available on the working road stretch. The field officers are requested to erectthem after compaction of widened portions.

    9 The project informatory boards with all details were not provided as per agreement. The same may beprovided immediately at site as per the guidelines given by PIU, NCRMP.

    10Cautionary signboards at necessary points and village name boards shall be erected. Guide stones shallbe fixed along the outer edge of all the sharp curves. Extra width fof formation is necessary at sharpcurves

    11The field officers are requested to furnish the test reports of water and ensure its suitability for concretingbefore proceeding with CC pavement work.

    12The quality control tests should be conducted as per IRC SP-11, maintain Q.C. record and the same shallbe produced to Q.A. wing for verification. The Dy. Executive Engineer and Executive Engineer shouldalso conduct the tests as per the guide lines of IRC SP-11

  • 7/31/2019 1.September MPR 2011

    22/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    1 Progress: Earth work is in progress. GSB , CD Works and WBM are not taken up. The progress of workis very poor as per the mile stones stipulated in the Agreement . With this speed it is very difficult tocomplete the work within the Agreement period. The Executive Engineer (PR) Tenali is requested to takenecessary measures to speed up the work so as to achieve the mile stones stipulated in the agreement.

    2 Milestone 1 : Earthwork, GSB , CD Works and WBM - 4 months. (26.08.2011)Milestone 2 : CC Pavement - 8 months (26.12.2011)Milestone 3 : BT Shoulder and Road furniture - 12 months (26.04.2012).

    3 Site order book is not being maintained by the field officers. The field officers are requested to maintaininvariably the site order book and get the instructions from the inspecting officers from time to time.

    4 The field officers have not furnished the test results for Embankment soil .The field officers are requestedto furnish the Soil test results to the T.P.Q.A. staff for verification.

    5 The earth work done in the widening portion is not yet compacted. It is to be compacted in layers and thethe field density shall be compared with laboratory density for ensuring the specified relative compaction.

    6 Material Registers are not available. The field officers are requested to maintain the material registersand same shall be furnished to the T.P.Q.A. staff for verification.

    7 The field officers have not furnished the Mix designs for various grades of concrete (cc pavement andculverts).The field officers are requested to furnish the mix designs to the T.P.Q.A. staff for verification.

    8 KM & HM Stones are not available on the working road stretch.The field officers are requested to erectthem after compaction of widened portions.

    9 The project informatory boards with all details were not provided as per agreement The same may be

  • 7/31/2019 1.September MPR 2011

    23/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    14 Safety measures for workers such as Helmets, Gum shoes, jackets etc., are to be provided by thecontractor.

    15 DCBM, TBM Stones not available at site.The field officers are requested to fix the DCBM & TBM Stonesand carry the levels and same shall be furnished the DCBM & TBM list to the T.P.Q.A. staff for verification.

    16 Pre-levels of earth work are not submitted by the field officer. Hence The field officers are requested tofurnish the pre levels to the T.P.Q.A. staff for verification.

    17 Compliance shall be submitted para wise at an early date after attending to the above remarks.

    Name of Work : RECONSTRUCTION OF HLB@Km 2/4 OF BAPATLA-PANDURANGAPURAM ROAD ACROSS PERALI DRAIN IN GUNTUR

    1 Progress of work: Reinforcement fabrication for one deck slab is completed.

    2 Site order book is not being maintained by the field officers. The field officers are instructed to maintaininvariably the site order book and get the instructions from the inspecting officers.

    3 The field officers are requested to get the samples of steel tested from every consignment of steel ,before it is used.

    4 The steel should be protected from rusting till the concrete is placed by applying cement coating properly

    as per clause 1603 of MORT&H standard specification.5 Steel and cement stock register should be maintained with proper incoming and usage recording should

    be maintained.

  • 7/31/2019 1.September MPR 2011

    24/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    12 Extra care shall be taken to check the quality of water used for mixing in concrete and curing concrete.

    13 Samples of cement and steel are collected by TPQA staff and sent for confirmatory testing. The resultswill be furnished in the next QC report.

    Name of Work : RECONSTRUCTION OF HLB@Km 5/2 OF BAPATLA-SURYALANKA ROADACROSS PERALI DRAIN IN GUNTUR

    1 Progress of work: 2 abutments and 7 piers completed upto bed block level. Bed block over one pier iscompleted.

    2 Site order book is not being maintained by the field officers. The field officers are instructed to maintaininvariably the site order book and get the instructions from the inspecting officers.

    3 The dimensions of bed block laid over P5 are measured and found taillling with drawing, but the bedblock offset all around the pier is not seen as it is flushed with the pier. The pier is bluged at the bottom of bed block, because of which the offset is not seen.(Photograph attached.) Proper Shuttering shall be

    used and finishing shall be carried out as per clause 1700 of MORT&H Standard specification for Roadand Bridge works.

    4 The field officers are requested to get the samples of steel tested from every consignment of steel ,before it is used.

    5 The steel should be protected from rusting till the concrete is placed by applying cement coating properly.

    6 The overhead electrical lines passing across the structure should be shifted as it is posing danger toproceed further above the piers.

    7 Safety measures for workers such as Helmets, Gum shoes, jackets etc., are to be provided by thecontractor. Caution boards, sign boards are to be kept.

    8 The field officers have not furnished the copies of the Bills of Cement and Steel utilized on the bridge

  • 7/31/2019 1.September MPR 2011

    25/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    2 It is observed that the shoulder material is not properly mixed (Sand & Gravel Mix). It shall be scarified,uniformly mixed, watered and compacted to the required density.

    3 The measurements like width and thickness of the WBM Gr-III from Km 0/0TO3/088 are verified andfound to be tallying with the required measurements. The details are given in Annexure - 1.

    4 Review of degree of Quality Control exercised:

    The summary QC tests by field officers shown under 3.0 of this QCR are noted from the following:

    1) Test records shown by line departmental officers

    2) Test results like CBR and Plasticity Index etc., obtained from local testing facilities.This aspect requires further improvement and commitment of senior engineers such as SEs and EEs.Setting up of a QC lab for conducting most of the regular tests for each package by the contractor isnecessary. The line departmental officers also require one laboratory for each sub-division or Divisiondepending on the workload for ensuring better quality control. In the present case, no QC lab wasestablished by the contractor so far. Also, no QC lab was available at Sub Division or Division.

    Name of Work :Providing BT Surface to the Road from R&B road to Edagali kandriga

    1 Works to be done as per Milestone:Mile stone 1:- Earth work, pipe culverts, GSB: 4 months. (26.04.2011)Mile stone 2:- WBM Gr-II, Gr-III and Shoulders: 8 months. (26.08.2011)Mile stone 3:- BT and Road funiture: 12 months. (26.04.2012)

    2 51% of value of the work is completed. Gravel shoulders is in progress

    3 The measurements like width and thickness of the GSB Layer from Km 0/0 to 0/570 are verified and foundto be tallying with the required measurements. The details are given in Annexure - 1.

    4 The measurements like width and thickness of the WBM Gr.-2 Layer from Km 0/0 to 0/570 are verified andf d ll i i h h i d Th d il i i A 2

  • 7/31/2019 1.September MPR 2011

    26/31

  • 7/31/2019 1.September MPR 2011

    27/31

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    Temple9. NCRMP/B-

    W/AP/RHB/PRED/05/Kalla/003Road from A-U Road to Satyanarayanapuram.

    10. NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

    Road from A-U Road to Mekaladibba.

    Krishna District1. NCRMP/B-

    W/AP/RHB/PRED/06/Machilipatnam/001Road Connecting R&B Road throughGantalammapalem.

    2. NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

    Road from R&B Road to B.V.Thota.

    3. NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

    Road from Potalapalem Z.P.Road toChikativanipalem.

    4. NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from R&B Road to Cyclone Shelter atChandala.

    5. NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road to Rangaraopet.

    EAST Godavari District1 NCRMP/B-W/AP/RCS/PRED/04/Karapa/001 Approach road to Cyclone Shelter at Adavipudi

    2 NCRMP/B-W/AP/RHB/PRED/04/Karapa/001 Road from Gurajanapalli to Bandulavaripalem

    3 NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR road to Dasarivanipeta and toCyclone Shelter

  • 7/31/2019 1.September MPR 2011

    28/31

    QUARTERLY SUMMARY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with 26

    10.0 Photographs of site visits & Important Events During this month:

    Inspection of works by Sri T.Radha, I.A.S, Commissioner,Disaster Management in Guntur District on 17-09-2011

    Inspection of works by Sri T.Radha, I.A.S, Commissioner,Disaster Management in Guntur District on 17-09-2011

    Inspection of works by Sri T.Radha, I.A.S, Commissioner,Disaster Management in Guntur District on 17-09-2011

    Inspection of works by Sri T.Radha, I.A.S, Commissioner,Disaster Management in Guntur District on 17-09-2011

  • 7/31/2019 1.September MPR 2011

    29/31

    QUARTERLY SUMMARY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with 27

    NCRMP one day State level Workshop for Contractors on theWorld Bank Procurement Procedures at Sindhoori hotel,

    Guntur for 5 districts on 20-09-2011. Dr Shetty fromAdministrative Staff College of India delivering the lecture.

    NCRMP one day State level Workshop for Contractors on theWorld Bank Procurement Procedures at Sindhoori hotel,Guntur for 5 districts on 20-09-2011. Delegates listen to

    Manohar Raos inaugural address.

    NCRMP one day State level Workshop for Contractors on theWorld Bank Procurement Procedures at Meghalaya hotel,

    Vijag for 4 districts on 22-09-2011. Ravinder, Sectorial officerinviting the guests and delegates.

    NCRMP one day State level Workshop for Contractors on theWorld Bank Procurement Procedures at Meghalaya hotel,

    Vijag for 4 districts on 22-09-2011. PM, PIUSri.R.Venkateswara Rao giving replies to the doubts raised by

    contractors.

  • 7/31/2019 1.September MPR 2011

    30/31

    QUARTERLY SUMMARY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with 28

    TPQA-NCRMP inspection on 21-09-2011. Road Vempudi toPatimeeda. Dip left unattended on Mulaparra road.

    TPQA-NCRMP inspection on 21-09-2011. Road Vempudi toPatimeeda. NCRMP PIU officials and TPQA engineers are

    seen

    TPQA-NCRMP inspection on 21-09-2011. R&B road toVenkayyapalem. CC road in the village limits.

    TPQA-NCRMP inspection on 21-09-2011. Road Vempudi toPatimeeda. R&B road to Venkayyapalem. Necessity for

    protective work being explained by field officers.

  • 7/31/2019 1.September MPR 2011

    31/31

    QUARTERLY SUMMARY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for NationalCyclone Risk Mitigation Project (NCRMP)

    inJoint Venture

    with 29

    NCRMP-TPQA inspection on 08-09-201. Sulluripeta to MallamR&B road to Berijangalapalli Cyclone shelter in Nellore

    District.

    NCRMP-TPQA inspection on 08-09-201. R&B roadMuttembaka via Pittuvanipalli in Chittamur Mandal in NelloreDistrict. GSB done and undulations are noticed. Shoulders

    require thorough compaqction.

    NCRMP-TPQA inspection on 08-09-201. Chittamur to

    Somasamudram in Nellore District. Earthwork in progressneeds systematic OMC layer by layer compaction.

    NCRMP-TPQA inspection on 08-09-201. Chittamur toSomasamudram in Nellore District. Chittamur village where

    CC road is to be done.