1transformer construction ,testing & maintenance

Upload: swatantrakumar66

Post on 02-Jun-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    1/52

    TRANSFORMER CONSTRUCTION ,

    TESTING AND M&R

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    2/52

    Need of transformer

    Transformer Transformer

    consumer

    low voltage high low

    high voltage voltage voltage

    Power Station

    Generation voltage 11 KV

    Transmission Voltage 66 KV/132KV

    Distribution Voltage 11 KV & below

    Transformer - To step-up or step-down the voltage

    and transfer power from one a.c. voltage to

    another a.c. voltage at the same frequency.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    3/52

    Power transformer

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    4/52

    Transformer :

    A transformer is a static apparatus used for the

    transferring power from one circuit to the other

    without change in frequency.

    It can raise or lower the voltage with a

    corresponding decrease or increase in current.

    The purpose of transformers is to transfer electricalenergy from systems of one voltage V1 to systems

    of another voltage V2.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    5/52

    Basic requirements of Transformer

    Voltage Ratio

    MVA Rating & cooling

    Vector group

    OLTC

    Percentage Impedance

    No load loss

    Load loss

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    6/52

    Parts of transformer

    Main tank

    Radiators

    Conservator

    Tap changer

    Silica breathers

    Buchholz relay

    MOG

    PRD

    OTI

    WTI

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    7/52

    Tests on Transformer:

    1. Oil Test

    2. Voltage Ratio Test

    3. Current Ratio Test

    4. Vector Group Test

    5. Magnetic Balance Test

    6. Magnetizing current Test

    7. IR Test

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    8/52

    Successful Electrical

    Maintenance

    PREVENTION is BETTER than CURE

    MAINTENANCE is notthe REPAIR work

    PREVENTIVE MAINTENANCE

    REPAIR or BREAKDOWN MAINTENANCE.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    9/52

    Maintenance Consists of..

    Routine Inspection

    Testing

    Cleaning & Adjustments

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    10/52

    Key to SUCCESS is. DETECT INCIPIENT TROUBLE by-

    - ROUTINE TESTS

    - VISUAL

    - AURAL

    - TOUCH

    - SMELL

    - INSTRUMENTS

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    11/52

    Distribution Transformer Maintenance

    Transformer Body

    Inspect For Rust & Leakage

    RustClean & Repaint

    LeakageInvestigate

    - Leaking Joint to beRectified

    -Replace Gaskets

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    12/52

    Distribution Transformer Maintenance

    BREATHER

    Silica-gel Dehydrating Breather

    - Colour of Crystals

    - Saturated CrystalsPink

    Need ReactivationBlueOil seal .

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    13/52

    Distribution Transformer Maintenance

    Explosion Vent

    Inspect DiaphragmAir tight joint withGaskets.

    Gaskets

    Shrink During Service

    Check tightness of Bolts

    Replace Leaking Gasket.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    14/52

    Distribution Transformer Maintenance

    Transformer Insulation is the Root of the Problem

    -

    Oil & Cellulose Paper Interact.

    - By products decompose Insulation System

    - By-products : Increase Moisture Level

    : Create EnvironmentOverheat

    -Fails

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    15/52

    Transformer Oil Functions. First : Serves as INSULATION to withstand the high

    voltages present inside the transformer.

    Second : It functions as the Heat Transfer medium todissipate Heat Generated within the transformerwinding.

    Oil must maintain Good Electrical properties whileResisting Thermal Degradation & oxidation.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    16/52

    Transformer - Oil

    Just Like a car Transformer needsREGULAR

    Oil Conditioning

    to rid it of Harmful Contaminants

    That could SHORTEN its life.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    17/52

    Transformer Oil

    Deterioration of Oil

    1. Oxidation

    2. In grace of Moisture

    3. Solid Impurities4. Contamination

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    18/52

    Transformer Oil Even with Best Maintenance Procedures

    Chemical Reaction continues.

    RemedyAnnual Oil Testing

    Oil Testing uncovers several Potential Problems

    Sample Contains Evidence ofSoluble contaminants

    - Dielectric contaminant- Acid Materials

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    19/52

    Testing of Oil Benefits Tests indicate the Interior-Condition of

    oil.

    Prevents Un-scheduled outages.

    Determines Trends, if any.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    20/52

    Tests on Oils

    1. Physical AppearanceColour

    - Clarity

    - Odour2. Electric Strength Test

    3. Crackle Test

    4. Acidity Test5. Insulation Resistance Test

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    21/52

    OEM Recommendations..1. Hourly

    2. Daily

    3. Monthly

    4. Six Monthly5. Yearly

    6. Five Yearly

    LoadAmps

    Temperature

    Voltage Breather

    Oil Level

    Gen. Observations Oil Testing

    Overall Inspection

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    22/52

    BSES Practices. Load readings taken once in 6 months.

    Silica gel replaced before/after

    mansoon.

    Oil Testing once in 12 months.

    Oil Filtered if B.D.V. is low.

    Oil Replaced if acidity beyond 1 mgkOH/gm.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    23/52

    ISO Norms. Transformer Load Readings and

    Inspection = Every Six Months.

    Transformer Oil sampling for B.D.V.Measurement = Every Year.

    Transformer Oil Filteration & Oil Testing

    = Every 4 Years.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    24/52

    DISTRIBUTION TRANSFORMERS FAILURE RATE IN BSES

    Year Total in Units % FailureSystem Failed

    1996-97 3056 70 2.29

    1997-98 3229 65 2.01

    1998-99 3405 40 1.17

    1999-2000 3583 35 0.98

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    25/52

    Failuare Analysis Certain Makes have performed Badly.

    Failuares more in recent make & specific

    Batches.

    75% of failuares at 9 years or less.

    Faliare rate goes down as size increases.

    Causes : Faults on L.T. side on U/G cables.

    Higher Temperature.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    26/52

    THANK YOU

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    27/52

    P.R.V. (Pressure Relief Valve)

    When oil pressure in the tank rises above pre-

    determine safe limit this valves operates.

    This equipment is of spring loaded type. When It

    operates the part of @ 150mm dia of PRV up lifts and

    allow in side tank pressure to drop.

    Saves transformer to buckle or damage further.

    Gives indication of valve operation by rising the flag.

    Operates a micro switch that disconnect the

    transformer from live circuit.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    28/52

    M.O.G. (Magnetic Oil Gauge).

    This is used with conservator

    It's purpose is to indicate the oil level in theconservator vessel and to give alarm when the

    oil level falls below a threshold limit.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    29/52

    SILICA GEL BREATHERS

    Moisture is an enemy of transformer insulationsystem

    Whenever oil contracts transformer breaths inthrough breathers.

    With air lot of moisture which is present in the airalso go inside.

    The silica gel present in the breathers absorbmoisture and only dry air goes inside.

    After a certain level of absorption the color ofsilica gel crystals change from blue to pink whenthese particles should be recharged or replaced.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    30/52

    OTI (Oil Temperature Indicator)

    This consists of a bulb dipped in a oil cup on thecover of the transformer tank cover. This bulb isconnected to the meter placed in the marshalling

    box meant for housing the equipment electricalcontrols by means of a capillary.

    This indicates the temperature of the top part of

    the transformer oil which is the hottest part.

    It gives alarms/trip contacts when temperatureexceeds than set values.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    31/52

    WTI (Winding temperature indicator) Similar in construction to the OTI.

    A current transformer injects current into theheating coil of the equipment giving the extra

    temperature gradient over the top oil temp. whichnormally a winding is expected to have.

    It gives alarms/trip contacts when temperatureexceeds than set values.

    It also gives start/stop contacts for fans & pumpsto start and stop when temperature exceeds.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    32/52

    Oil test:

    Collect samples of oil from main tank bottom,

    Conservator, radiator and tap changer.

    Oil breakdown test should withstand 60KV for 1min. with 2.5mm gap. If the value is lower,

    advice further dry out till this value is achieved,

    before proceeding further.

    Collect 5 liters of oil from the tank send to a

    standard laboratory like ERDA for moisture

    content, resistivity testing.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    33/52

    ERDA detail testing of oil

    No. Test Requirement Obtained

    value

    Remarks

    1 Electric strength Min. 60 KV

    2 Water Content, ppm Max. 15

    3 Neutralization value mg KOH/g of oil Max. 0.03

    4 Sediment & sludge % by wt. Non-detectable

    5 Dielectric dissipation factor Max. 0.015

    6 Specific resistance, Ohm.cm Min. 6x 10

    7 Interfacial tension, mN/m Min. 35

    8 Flash point , deg.C Min. 140 deg.C

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    34/52

    Voltage Ratio Test:Apply 3-Phase 400 Volts on HV side and measure

    respective voltage on LV side.

    Tap no. ry (V) yb (V) br (V) rn (V) yn (V) bn (V)

    1 95.9 95.4 94.5 55.3 54.6 54.4

    9 105.3 104.4 105.5 61.0 60.0 59.9

    17 117.1 116.0 117.2 67.9 66.3 66.5

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    35/52

    Current Ratio Test:

    Apply 3-Phase 400 Volts on HV side keeping R-Y-B

    phases shorted on LV side.

    Measure the current on HV and LV side starting

    from 1sttap to last tap.

    Tap no. R (A) Y (A) B (A) ryb (A)

    1 6.4 6.0 6.5

    9 8.1 7.8 8.2 32.5

    17 10.7 10.4 10.8

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    36/52

    Vector Group Test:

    Short R-ph of HV & r-ph of LV.

    Apply 3 phase, 440 V on HV side

    Measure respective voltage as under:

    rR

    by

    n

    B Y

    Ry: 67 V Bb: 346 V RY: 408 V

    Rb: 68 V By: 347 V YB: 410 V

    Yy: 400V Yb: 415V BR: 415 V

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    37/52

    Magnetic Balance Test:

    Apply 415 Volts on LV side between phase &

    neutral.Measure voltage on respective LV

    terminals as under.

    LVWinding

    rn yn bn

    rn= 407 407 334 78

    yn= 407 205 407 201

    bn =407 79 332 407

    Apply 415 Volts on two terminals of HV andmeasure voltage on HV terminals as under:

    HVWinding

    RY YB BR

    RY=424 424 194 222

    YB=424 392 424 18.9

    BR=424 381 36.2 424

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    38/52

    Magnetizing Current Test:

    Apply 3-Phase 400 volts on HV side with LV

    open.Measure the current on HV side

    Apply 3-Phase 400 volts on LV side with HV open.Measure the current on LV side

    Voltage Applied Current measured

    RY440 V R11.11mA

    YB440 V Y07.62 mA

    BR440 V B10.95 mA

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    39/52

    Insulation Resistance Test:

    15 seconds 60 seconds 60/15seconds (PI)

    HT to Earth 190 x 5 260 X 5 1.4

    LT to Earth 200 X 5 330 X 5 1.6

    HT to Earth 270 X 5 400 X 5 1.5

    CORE to Earth

    Dryness of insulation is determined by

    measuring insulation resistance of winding.

    It should be taken by 2.5 KV motorized Megger.

    IR of 60sec/IR of 15sec (PI) should be greater

    than 1.2 for good insulation.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    40/52

    Differential Stability Test

    Out Zone Testing : Apply 400 volts 3 Phase on HV

    side keeping shorting after CTs for 11 KV Incomer.

    Type of fault R Phase Y Phase B Phase REF Relay

    HV LV OP. HV LV OP. HV LV OP.

    RN

    YN

    BN

    RY

    YB

    BR

    RYB

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    41/52

    Type of fault R Phase Y Phase B Phase REF Relay

    HV LV OP. HV LV OP. HV LV OP.

    RN

    YN

    BN

    RY

    YB

    BR

    RYB

    Differential Stability Test

    In Zone Testing : Apply 400 volts 3-Phase on HV side

    keeping shorting for 11 KV Incomer before CTs.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    42/52

    Voltage transformation ratio:

    Primary winding & Secondary winding

    E1 = 4.44* f *N1* m

    E2= 4.44* f *N2* m

    E2 / E 1 = N1/ N2

    Where N1 = Primary Turns

    N2 = Secondary Turns

    m = FluxF = frequency

    In our system we have different Voltage ratio

    transformers: 220/132KV, 132/66KV, 132/33KV,

    66/11KV, 33/11KV, 11/0.44KV.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    43/52

    % Impedance Voltage: The Impedance voltage is defined as that voltage

    having the rated frequency which must be

    applied to the primary side of a transformer so

    that the rated current Ir flows when secondaryterminals are shorted.

    The rated impedance voltage is usually stated as

    a percentage of the voltage rating Ur of the

    winding to which the voltage is applied.

    % Impedance = (Applied voltage/Rated

    voltage)x100

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    44/52

    MVA rating & cooling: It defines the total output capacity of the

    transformer in MVA at the given cooling like

    ONAN, ONAF and OFAF.

    Our 12.5MVA and 20MVA, 66/11kv transformersare with ONAN cooling.

    Our 30MVA,132/11kv and 50MVA,132/33KV

    transformers are with ONAN/ONAF Cooling.

    Our 65MVA &100MVA, 132/66kv and

    150MVA,220/132kv transformers are with

    ONAF/ONAF/OFAF Cooling

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    45/52

    Vector group: Yna0 for 220/132kv,132/66kv interconnecting

    transformers. DYn1 for 132/11kv, 66/11kv and 33/11kv

    distribution transformers.Ynyn0 for 132/33kv

    transformers. The vector group denotes the way the windings are

    connected and the phase position of their respective

    voltage vectors.

    To identify the phase angle the vector of High voltage

    winding is taken as a reference. The number multipliedby 30denotes the angle by which the vector of the LV

    winding lags that of the HV winding.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    46/52

    It add or subtract turns from the main coil of HVwinding while RAISE or LOWER command isgiven and maintains constant voltage on LV side.

    Generally housed inside the transformer tank andoperation through local box/remote panel.

    These are the standard products.

    Selection is based on Winding connection,

    current rating,range in terms of % of winding,number of steps, independent operation, paralleloperation.

    OLTC: on load tap changer

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    47/52

    It is basically the core material loss.

    Core is the magnetic circuit through which fluxflows.The material used for core making is called

    CRGO i.e cold rolled grain oriented steel.

    It is the power loss that transformer consumeswhen charged at Normal voltage and at No load.

    It should be minimum as possible to reduce T & D

    loss of the system. We insist manufactures to use prime grade

    imported first quality CRGO material formanufacturing the core of the transformer.

    No load loss

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    48/52

    It is basically the copper loss.

    It is the power consumed by the transformerwhen on load.

    It will change at different load and tap position ofthe transformer.

    load loss

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    49/52

    Transformer tank

    Bell type tank :A tank in

    which the cover is not flat inshape and the tank and cover

    junction is near the bottom of

    the tank .Tank is in two parts

    top tank and bottom tank

    Conventional tank:A tankin which the cover is flat and

    tank to cover junction is at thetop of the tank.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    50/52

    Radiators

    Tank mounted :Directly mounted on the tankwall, if the size and numbers of radiators is small.

    Separately mounted:Mounted separately on A

    OR H frame structure and connected with maintank through oil headers.

    Selection of radiator banks mounting and its

    positioning depends on MVA rating, type of cooling

    like ONAF,ONAF and site space availability.

    Arrangement need to be specified at the time

    tendering for total L X B X H dimensions of

    transformer, tank mounted,separately mounted,

    HV side, LV side, on left side and right side.

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    51/52

    Buchholz relay

    Because of any internal fault heat is generated whichdecomposes oil and insulation material resulting inthe formation of gases.

    These gases rise up and while approaching theconservator passes through the buchholz relay.

    Transformer

    Tank

    Alarm

    Conservator

  • 8/10/2019 1transformer Construction ,Testing & Maintenance

    52/52