1transformer construction ,testing & maintenance
TRANSCRIPT
-
8/10/2019 1transformer Construction ,Testing & Maintenance
1/52
TRANSFORMER CONSTRUCTION ,
TESTING AND M&R
-
8/10/2019 1transformer Construction ,Testing & Maintenance
2/52
Need of transformer
Transformer Transformer
consumer
low voltage high low
high voltage voltage voltage
Power Station
Generation voltage 11 KV
Transmission Voltage 66 KV/132KV
Distribution Voltage 11 KV & below
Transformer - To step-up or step-down the voltage
and transfer power from one a.c. voltage to
another a.c. voltage at the same frequency.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
3/52
Power transformer
-
8/10/2019 1transformer Construction ,Testing & Maintenance
4/52
Transformer :
A transformer is a static apparatus used for the
transferring power from one circuit to the other
without change in frequency.
It can raise or lower the voltage with a
corresponding decrease or increase in current.
The purpose of transformers is to transfer electricalenergy from systems of one voltage V1 to systems
of another voltage V2.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
5/52
Basic requirements of Transformer
Voltage Ratio
MVA Rating & cooling
Vector group
OLTC
Percentage Impedance
No load loss
Load loss
-
8/10/2019 1transformer Construction ,Testing & Maintenance
6/52
Parts of transformer
Main tank
Radiators
Conservator
Tap changer
Silica breathers
Buchholz relay
MOG
PRD
OTI
WTI
-
8/10/2019 1transformer Construction ,Testing & Maintenance
7/52
Tests on Transformer:
1. Oil Test
2. Voltage Ratio Test
3. Current Ratio Test
4. Vector Group Test
5. Magnetic Balance Test
6. Magnetizing current Test
7. IR Test
-
8/10/2019 1transformer Construction ,Testing & Maintenance
8/52
Successful Electrical
Maintenance
PREVENTION is BETTER than CURE
MAINTENANCE is notthe REPAIR work
PREVENTIVE MAINTENANCE
REPAIR or BREAKDOWN MAINTENANCE.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
9/52
Maintenance Consists of..
Routine Inspection
Testing
Cleaning & Adjustments
-
8/10/2019 1transformer Construction ,Testing & Maintenance
10/52
Key to SUCCESS is. DETECT INCIPIENT TROUBLE by-
- ROUTINE TESTS
- VISUAL
- AURAL
- TOUCH
- SMELL
- INSTRUMENTS
-
8/10/2019 1transformer Construction ,Testing & Maintenance
11/52
Distribution Transformer Maintenance
Transformer Body
Inspect For Rust & Leakage
RustClean & Repaint
LeakageInvestigate
- Leaking Joint to beRectified
-Replace Gaskets
-
8/10/2019 1transformer Construction ,Testing & Maintenance
12/52
Distribution Transformer Maintenance
BREATHER
Silica-gel Dehydrating Breather
- Colour of Crystals
- Saturated CrystalsPink
Need ReactivationBlueOil seal .
-
8/10/2019 1transformer Construction ,Testing & Maintenance
13/52
Distribution Transformer Maintenance
Explosion Vent
Inspect DiaphragmAir tight joint withGaskets.
Gaskets
Shrink During Service
Check tightness of Bolts
Replace Leaking Gasket.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
14/52
Distribution Transformer Maintenance
Transformer Insulation is the Root of the Problem
-
Oil & Cellulose Paper Interact.
- By products decompose Insulation System
- By-products : Increase Moisture Level
: Create EnvironmentOverheat
-Fails
-
8/10/2019 1transformer Construction ,Testing & Maintenance
15/52
Transformer Oil Functions. First : Serves as INSULATION to withstand the high
voltages present inside the transformer.
Second : It functions as the Heat Transfer medium todissipate Heat Generated within the transformerwinding.
Oil must maintain Good Electrical properties whileResisting Thermal Degradation & oxidation.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
16/52
Transformer - Oil
Just Like a car Transformer needsREGULAR
Oil Conditioning
to rid it of Harmful Contaminants
That could SHORTEN its life.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
17/52
Transformer Oil
Deterioration of Oil
1. Oxidation
2. In grace of Moisture
3. Solid Impurities4. Contamination
-
8/10/2019 1transformer Construction ,Testing & Maintenance
18/52
Transformer Oil Even with Best Maintenance Procedures
Chemical Reaction continues.
RemedyAnnual Oil Testing
Oil Testing uncovers several Potential Problems
Sample Contains Evidence ofSoluble contaminants
- Dielectric contaminant- Acid Materials
-
8/10/2019 1transformer Construction ,Testing & Maintenance
19/52
Testing of Oil Benefits Tests indicate the Interior-Condition of
oil.
Prevents Un-scheduled outages.
Determines Trends, if any.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
20/52
Tests on Oils
1. Physical AppearanceColour
- Clarity
- Odour2. Electric Strength Test
3. Crackle Test
4. Acidity Test5. Insulation Resistance Test
-
8/10/2019 1transformer Construction ,Testing & Maintenance
21/52
OEM Recommendations..1. Hourly
2. Daily
3. Monthly
4. Six Monthly5. Yearly
6. Five Yearly
LoadAmps
Temperature
Voltage Breather
Oil Level
Gen. Observations Oil Testing
Overall Inspection
-
8/10/2019 1transformer Construction ,Testing & Maintenance
22/52
BSES Practices. Load readings taken once in 6 months.
Silica gel replaced before/after
mansoon.
Oil Testing once in 12 months.
Oil Filtered if B.D.V. is low.
Oil Replaced if acidity beyond 1 mgkOH/gm.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
23/52
ISO Norms. Transformer Load Readings and
Inspection = Every Six Months.
Transformer Oil sampling for B.D.V.Measurement = Every Year.
Transformer Oil Filteration & Oil Testing
= Every 4 Years.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
24/52
DISTRIBUTION TRANSFORMERS FAILURE RATE IN BSES
Year Total in Units % FailureSystem Failed
1996-97 3056 70 2.29
1997-98 3229 65 2.01
1998-99 3405 40 1.17
1999-2000 3583 35 0.98
-
8/10/2019 1transformer Construction ,Testing & Maintenance
25/52
Failuare Analysis Certain Makes have performed Badly.
Failuares more in recent make & specific
Batches.
75% of failuares at 9 years or less.
Faliare rate goes down as size increases.
Causes : Faults on L.T. side on U/G cables.
Higher Temperature.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
26/52
THANK YOU
-
8/10/2019 1transformer Construction ,Testing & Maintenance
27/52
P.R.V. (Pressure Relief Valve)
When oil pressure in the tank rises above pre-
determine safe limit this valves operates.
This equipment is of spring loaded type. When It
operates the part of @ 150mm dia of PRV up lifts and
allow in side tank pressure to drop.
Saves transformer to buckle or damage further.
Gives indication of valve operation by rising the flag.
Operates a micro switch that disconnect the
transformer from live circuit.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
28/52
M.O.G. (Magnetic Oil Gauge).
This is used with conservator
It's purpose is to indicate the oil level in theconservator vessel and to give alarm when the
oil level falls below a threshold limit.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
29/52
SILICA GEL BREATHERS
Moisture is an enemy of transformer insulationsystem
Whenever oil contracts transformer breaths inthrough breathers.
With air lot of moisture which is present in the airalso go inside.
The silica gel present in the breathers absorbmoisture and only dry air goes inside.
After a certain level of absorption the color ofsilica gel crystals change from blue to pink whenthese particles should be recharged or replaced.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
30/52
OTI (Oil Temperature Indicator)
This consists of a bulb dipped in a oil cup on thecover of the transformer tank cover. This bulb isconnected to the meter placed in the marshalling
box meant for housing the equipment electricalcontrols by means of a capillary.
This indicates the temperature of the top part of
the transformer oil which is the hottest part.
It gives alarms/trip contacts when temperatureexceeds than set values.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
31/52
WTI (Winding temperature indicator) Similar in construction to the OTI.
A current transformer injects current into theheating coil of the equipment giving the extra
temperature gradient over the top oil temp. whichnormally a winding is expected to have.
It gives alarms/trip contacts when temperatureexceeds than set values.
It also gives start/stop contacts for fans & pumpsto start and stop when temperature exceeds.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
32/52
Oil test:
Collect samples of oil from main tank bottom,
Conservator, radiator and tap changer.
Oil breakdown test should withstand 60KV for 1min. with 2.5mm gap. If the value is lower,
advice further dry out till this value is achieved,
before proceeding further.
Collect 5 liters of oil from the tank send to a
standard laboratory like ERDA for moisture
content, resistivity testing.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
33/52
ERDA detail testing of oil
No. Test Requirement Obtained
value
Remarks
1 Electric strength Min. 60 KV
2 Water Content, ppm Max. 15
3 Neutralization value mg KOH/g of oil Max. 0.03
4 Sediment & sludge % by wt. Non-detectable
5 Dielectric dissipation factor Max. 0.015
6 Specific resistance, Ohm.cm Min. 6x 10
7 Interfacial tension, mN/m Min. 35
8 Flash point , deg.C Min. 140 deg.C
-
8/10/2019 1transformer Construction ,Testing & Maintenance
34/52
Voltage Ratio Test:Apply 3-Phase 400 Volts on HV side and measure
respective voltage on LV side.
Tap no. ry (V) yb (V) br (V) rn (V) yn (V) bn (V)
1 95.9 95.4 94.5 55.3 54.6 54.4
9 105.3 104.4 105.5 61.0 60.0 59.9
17 117.1 116.0 117.2 67.9 66.3 66.5
-
8/10/2019 1transformer Construction ,Testing & Maintenance
35/52
Current Ratio Test:
Apply 3-Phase 400 Volts on HV side keeping R-Y-B
phases shorted on LV side.
Measure the current on HV and LV side starting
from 1sttap to last tap.
Tap no. R (A) Y (A) B (A) ryb (A)
1 6.4 6.0 6.5
9 8.1 7.8 8.2 32.5
17 10.7 10.4 10.8
-
8/10/2019 1transformer Construction ,Testing & Maintenance
36/52
Vector Group Test:
Short R-ph of HV & r-ph of LV.
Apply 3 phase, 440 V on HV side
Measure respective voltage as under:
rR
by
n
B Y
Ry: 67 V Bb: 346 V RY: 408 V
Rb: 68 V By: 347 V YB: 410 V
Yy: 400V Yb: 415V BR: 415 V
-
8/10/2019 1transformer Construction ,Testing & Maintenance
37/52
Magnetic Balance Test:
Apply 415 Volts on LV side between phase &
neutral.Measure voltage on respective LV
terminals as under.
LVWinding
rn yn bn
rn= 407 407 334 78
yn= 407 205 407 201
bn =407 79 332 407
Apply 415 Volts on two terminals of HV andmeasure voltage on HV terminals as under:
HVWinding
RY YB BR
RY=424 424 194 222
YB=424 392 424 18.9
BR=424 381 36.2 424
-
8/10/2019 1transformer Construction ,Testing & Maintenance
38/52
Magnetizing Current Test:
Apply 3-Phase 400 volts on HV side with LV
open.Measure the current on HV side
Apply 3-Phase 400 volts on LV side with HV open.Measure the current on LV side
Voltage Applied Current measured
RY440 V R11.11mA
YB440 V Y07.62 mA
BR440 V B10.95 mA
-
8/10/2019 1transformer Construction ,Testing & Maintenance
39/52
Insulation Resistance Test:
15 seconds 60 seconds 60/15seconds (PI)
HT to Earth 190 x 5 260 X 5 1.4
LT to Earth 200 X 5 330 X 5 1.6
HT to Earth 270 X 5 400 X 5 1.5
CORE to Earth
Dryness of insulation is determined by
measuring insulation resistance of winding.
It should be taken by 2.5 KV motorized Megger.
IR of 60sec/IR of 15sec (PI) should be greater
than 1.2 for good insulation.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
40/52
Differential Stability Test
Out Zone Testing : Apply 400 volts 3 Phase on HV
side keeping shorting after CTs for 11 KV Incomer.
Type of fault R Phase Y Phase B Phase REF Relay
HV LV OP. HV LV OP. HV LV OP.
RN
YN
BN
RY
YB
BR
RYB
-
8/10/2019 1transformer Construction ,Testing & Maintenance
41/52
Type of fault R Phase Y Phase B Phase REF Relay
HV LV OP. HV LV OP. HV LV OP.
RN
YN
BN
RY
YB
BR
RYB
Differential Stability Test
In Zone Testing : Apply 400 volts 3-Phase on HV side
keeping shorting for 11 KV Incomer before CTs.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
42/52
Voltage transformation ratio:
Primary winding & Secondary winding
E1 = 4.44* f *N1* m
E2= 4.44* f *N2* m
E2 / E 1 = N1/ N2
Where N1 = Primary Turns
N2 = Secondary Turns
m = FluxF = frequency
In our system we have different Voltage ratio
transformers: 220/132KV, 132/66KV, 132/33KV,
66/11KV, 33/11KV, 11/0.44KV.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
43/52
% Impedance Voltage: The Impedance voltage is defined as that voltage
having the rated frequency which must be
applied to the primary side of a transformer so
that the rated current Ir flows when secondaryterminals are shorted.
The rated impedance voltage is usually stated as
a percentage of the voltage rating Ur of the
winding to which the voltage is applied.
% Impedance = (Applied voltage/Rated
voltage)x100
-
8/10/2019 1transformer Construction ,Testing & Maintenance
44/52
MVA rating & cooling: It defines the total output capacity of the
transformer in MVA at the given cooling like
ONAN, ONAF and OFAF.
Our 12.5MVA and 20MVA, 66/11kv transformersare with ONAN cooling.
Our 30MVA,132/11kv and 50MVA,132/33KV
transformers are with ONAN/ONAF Cooling.
Our 65MVA &100MVA, 132/66kv and
150MVA,220/132kv transformers are with
ONAF/ONAF/OFAF Cooling
-
8/10/2019 1transformer Construction ,Testing & Maintenance
45/52
Vector group: Yna0 for 220/132kv,132/66kv interconnecting
transformers. DYn1 for 132/11kv, 66/11kv and 33/11kv
distribution transformers.Ynyn0 for 132/33kv
transformers. The vector group denotes the way the windings are
connected and the phase position of their respective
voltage vectors.
To identify the phase angle the vector of High voltage
winding is taken as a reference. The number multipliedby 30denotes the angle by which the vector of the LV
winding lags that of the HV winding.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
46/52
It add or subtract turns from the main coil of HVwinding while RAISE or LOWER command isgiven and maintains constant voltage on LV side.
Generally housed inside the transformer tank andoperation through local box/remote panel.
These are the standard products.
Selection is based on Winding connection,
current rating,range in terms of % of winding,number of steps, independent operation, paralleloperation.
OLTC: on load tap changer
-
8/10/2019 1transformer Construction ,Testing & Maintenance
47/52
It is basically the core material loss.
Core is the magnetic circuit through which fluxflows.The material used for core making is called
CRGO i.e cold rolled grain oriented steel.
It is the power loss that transformer consumeswhen charged at Normal voltage and at No load.
It should be minimum as possible to reduce T & D
loss of the system. We insist manufactures to use prime grade
imported first quality CRGO material formanufacturing the core of the transformer.
No load loss
-
8/10/2019 1transformer Construction ,Testing & Maintenance
48/52
It is basically the copper loss.
It is the power consumed by the transformerwhen on load.
It will change at different load and tap position ofthe transformer.
load loss
-
8/10/2019 1transformer Construction ,Testing & Maintenance
49/52
Transformer tank
Bell type tank :A tank in
which the cover is not flat inshape and the tank and cover
junction is near the bottom of
the tank .Tank is in two parts
top tank and bottom tank
Conventional tank:A tankin which the cover is flat and
tank to cover junction is at thetop of the tank.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
50/52
Radiators
Tank mounted :Directly mounted on the tankwall, if the size and numbers of radiators is small.
Separately mounted:Mounted separately on A
OR H frame structure and connected with maintank through oil headers.
Selection of radiator banks mounting and its
positioning depends on MVA rating, type of cooling
like ONAF,ONAF and site space availability.
Arrangement need to be specified at the time
tendering for total L X B X H dimensions of
transformer, tank mounted,separately mounted,
HV side, LV side, on left side and right side.
-
8/10/2019 1transformer Construction ,Testing & Maintenance
51/52
Buchholz relay
Because of any internal fault heat is generated whichdecomposes oil and insulation material resulting inthe formation of gases.
These gases rise up and while approaching theconservator passes through the buchholz relay.
Transformer
Tank
Alarm
Conservator
-
8/10/2019 1transformer Construction ,Testing & Maintenance
52/52