2013-06-20 modul pengajaran instruktur-heru pms101
DESCRIPTION
Primavera 101;Learn about Project Planning And Controlling;OBS (Organizational Breakdown Structure),EPS (Enterprise Project Structure)OBS, EPS, Project, WBS InterrelationshipsTRANSCRIPT
-
PMS101 Planning and Controlling
By Heru Winarto
-
Agenda Hari 1
08:30 09:00 Pre Test Planning and Controlling
Registration B0 Profile
09:00 - 10:15 Training in the Classroom
10:15 10:30 Break 1
10:30 12:00 Training in the Classroom
12:00 13:00 Lunch Break
13:00 15:00 Training in the Classroom
15:00 15:15 Break 2
15:15 17:00 Training in the Classroom
PMS101 Planning and Controlling
-
Agenda Hari 2
08:30 - 10:15 Training in the Classroom
10:15 10:30 Break 1 and Foto Group
10:30 12:00 Training in the Classroom
12:00 13:00 Lunch Break
13:00 15:00 Training in the Classroom
15:00 15:15 Break 2
15:15 16:30 Training in the Classroom
16:30 17:00 Evaluation (Post Test) & Questioner
PMS101 Planning and Controlling
-
PRIMAVERA Project Planning ( Primavera P6 R8.3 )
Project Portfolio ManagementPPM : - Client Base (Desktop / Client Server)
Enterprise Project Portfolio ManagementEPPM : - Client Base (Client Server)
- Web Base (Intranet / Internet)
Lain-lain :
- PRIMAVERA Risk Management v.8.7
- ABC ( Activity Base Cost Estimate ) API P6 R?- Naviswork (Autodesk) Primavera (Planning)
Produk PRIMAVERA
-
PRIMAVERA P6 R8.? :
I. Microsoft Database
MS SQL SERVER 2008 > (Server)
II. Oracle Database
ORACLE 10g Express Edition (Standalone)- PPM (Include Database)- Max Space 2 GByte
ORACLE 10g Database Server > (Server)- EPPM (Not Include Database)
Media Penyimpanan Data
-
Flowchart Project Planning
-
Flowchart Project Control
-
OBS (Organizational Breakdown Structure)
-
EPS ( Enterprise Project Structure )
-
Legend
OBS Elements"Program"Managers
ProjectA
ProjectB
ProjectC
TeamLeader
EPS
WBSA.1
WBSA.1
WBSA.2
WBSA.2
WBSA.3
WBSA.3
OBS Elements"Project"
Managers
OBS
EPSNode
EPSNode
EPSNode
TeamLeader
TeamLeader
Enterprise Project Structure (EPS)
Project
WBS
Organization Breakdown Structure (OBS)
OBS, EPS, Project, WBS Interrelationships
-
Format :
Setting User Preference
-
Format :
Setting User Preference
-
Format :
Setting User Preference
-
Format :
Setting User Preference
-
Format :
Setting User Preference
-
Project Definition :
EPS : RamaProject Id : Rama EastProject Name : Rama Office Building EastPlanned Start : 12 Feb 2013 9:00 AMProject Finish : ?
Create Project
-
Work Breakdown Structure
-
Calendar Definition :
Hari kerja dimulai Senin sampai Jumat
Satu hari kerja 8 jam
Jam Kerja Dimulai dari Jam 9:00 AM sampai Jam 18:00 PM
Kalender ini mempunyai hari libur sebagai berikut :
Calendar
01 January 2013 12 March 2013 29 March 2013
09 May 2013 06 June 2013 25 Desember 2013
-
UnIts
- % Complete Type = Physical
- Duration Type = Fixed Duration &
- Activity Calendar = Office 5 Day
Calendar
Activity , Steps & Relationships
-
Activity & Relationships - Lag
-
PROJECT
EPS : RamaProject Id : Rama EastProject Name : Rama Office Building EastPlanned Start : 12 Feb 2013 09:00 AMProject Finish : 14 Nov 2013 06:00 PM
Project Scheduling
-
Update Schedule
Please make sure for activity A1110, specify Remaining Duration as 6d
8027-Jun-13 09:00Form/Pour Basement Slab and FloorsA111010026-Jun-13 18:0007-Jun-13 09:00Floor DeckingA110010004-Jun-13 18:0007-May-13 09:00Erect Structural FrameA1090210006-May-13 18:0003-May-13 09:00Backfill and Compact FillsA108010002-May-13 18:0025-Apr-13 09:00Form/Pour Concrete SlabA107010024-Apr-13 18:0011-Apr-13 09:00Form/Pour Concrete WallsA106010010-Apr-13 18:0027-Mar-13 09:00Form/Pour Concrete FootingsA105010026-Mar-13 18:0013-Mar-13 09:00Install Underground Electrical ConduitA104010026-Mar-13 18:0013-Mar-13 09:00Install Underground Water LinesA103010011-Mar-13 18:0026-Feb-13 09:00ExcavationA1020
10025-Feb-13 18:0012-Feb-13 09:00Site PreparationA101010012-Feb-13 09:00Begin ConstructionA10001%FinishesStartedActivity NameAct IDWBS
The Activities Completed and in Progress are as shown
-
Apply Actual
-
Activity Code
-
Assignment Activity Code
-
Tampilkan seluruh data Activity yang terkelompokdalam WBS Structure saja
I. Latihan Group & Sort
-
Tampilkan seluruh data Activity yang terkelompokdalam WBS Exterior dan Interior saja
II. Latihan Group & Sort
-
Buatlah Filter untuk menampilkan data Activity yang mempunyai Activity Code Finishing Work (FW) saja
III. Latihan Filter
-
Buatlah Filter untuk menampilkan data Activity yang mempunyai Activity Code Civil Work (CW) dan
Finishing Work (FW)
IV. Latihan Filter
-
Buatlah Filter untuk menampilkan data Activity yang dimulaidengan Kode Depan Activity A10.. saja
Contoh : A1000A1010A1020
- - -
A1090dst
V. Latihan Filter
-
eMail : [email protected]
Telp : Hp : 081905002979Telp : 021-5805828 - 29
-
Others :
-
Relationship & Lag Time
FS ( Finish to Start )
FF ( Finish to Finish )
SS ( Start to Start )
SF ( Start to Finish )
Lag Time ( Negative ) Lag Time ( Positif )
-
Relationship FS
FS ( Finish to Start )
FS (Finish to Start)Suatu kegiatan baru dapat dikerjakan jika kegiatan sebelumnya telahselesai.Misalnya : kegiatan pondasi baru dapat dimulai setelah galian
selesai
-
Relationship FF
FF (Finish to Finish)Suatu kegiatan harus selesai bersamaan dengan selesainya kegiatanlain.Misalnya : kegiatan taman selesai bersamaan dengan kegiatan pagar
FF ( Finish to Finish )
-
Relationship SS
SS (Start to Start)Suatu kegiatan harus dimulai bersamaan dengan kegiatan lainnya.Misalnya : kegiatan pembersihan lapangan bersamaan dengan
kegiatan direksikeet
SS ( Start to Start )
-
Relationship SF
SF ( Start to Finish )Suatu kegiatan baru dapat diakhiri jika kegiatan lain dumulaiMisalnya : kegiatan start engine
SF ( Start to Finish )
-
Lag Time
Lag Time NegatifUntuk menghemat waktu yang dibutuhkan dalam penyelesaianSuatu kegiatan
Lag Time Negatif
-
Lag Time
Lag Time PositifTenggang waktu antara penyelesaian kegiatan pertama denganpelaksanaan kegiatan berikutnya
Lag Time Positif
-
Indikator Perhitungan
Durasi (D) = waktu yang diperlukan untuk melaksanakan kegiatanEarliest Start (ES) = saat paling cepat kegiatan tersebut dilaksanakanEarliest Finish (EF) = saat paling cepat kegiatan tersebut diselesaikanLatest Start (LS) = saat paling lambat kegiatan tersebut dilaksanakanLatest Finish (LF) = saat paling lambat kegiatan tersebut diselesaikanFree Float (FF) = jumlah waktu tunda atau memperpanjang waktu
kegiatan tanpa mempengaruhi waktu awal kegiatan berikutnyaTotal Float (TF) = jumlah waktu waktu tunda atau memperpanjang waktu
kegiatan tanpa mempengaruhi akhir proyek
Rumus : EF = ES + D FF = ES EFLS = LF D TF = LF - EF