2013-12-31 - @preliminary report - kawasan industri akr - improvement menthod
TRANSCRIPT
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
1/15
AKR INDUSTRIAL ESTATE - GRESIK
EAST JAVA, INDONESIA
INITIAL REPORT
FOR
AKR INDUSTRIAL ESTATE
AT
GRESIK, EAST JAVA
GROUND IMPROVEMENT SCHEME
Document No : ILSIWJKT24001/001
REV DATE PREPARED BY REVIEWED BY APPROVED BY
NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE
00 LY 29/12 MD 29/12 LR 29/12
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
2/15
TABLE OF CONTENT
I. INTRODUCTION .......................................................................................................... - 3 -II. SITE AND SOIL CONDITION .................................................................................... - 4 -III. GROUND IMPROVEMENT METHODS................................................................... - 8 -IV. GROUND IMPROVEMENT RESUME .................................................................... - 15 -
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
3/15
I. INTRODUCTIONThis document describes various method of ground improvement may apply for roadconstruction at AKR Industrial Estate, Gresik, East Java.
Key Plan
The detail calculation will perform by PT. Geotekindo after more discussion with owner
about their need and technical requirement of the area.
This report is produced based on the following documents :
Block Plan. Soil properties. Boreholes. Oral explanation about the requirement.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
4/15
II. SITE AND SOIL CONDITIONBLOCK PLAN
Area is dividing in 4 section named M-1, M-2, M-3 and M-4. Map below shows the block
plan.
Block Plan
Base on oral information from consultant, it state area M-1 already backfill use limestone
with 1 m thickness but quite bouncy. Area M-2, M-3 and M-4 not prepared yet (swamp or
fish pond) and later will backfill use limestone as in M-1.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
5/15
SOIL DATA
Typical boreholes for M-1
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
6/15
Typical boreholes for M-2 and M-3
Here we can see the soft clay depth about 1012 m from surface. The soft clay has CPT
between 0 to 2 means it has a very low bearing capacity.
Base on lab test, Compression Index (Cc) value around 0.8 to 1.1 means its a highly
compressible layer.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
7/15
LOAD PLAN, ASSUMPTION, CROSS SECTION AND PROPOSE METHOD
Base on drawing, ROW is 80 m : road, drainage, infrastructure space and open area. In
our opinion the ground improvement should only focus on road area because its the only
area bearing a high traffic load.
The assumption below is use in proposal :
ROW : 80 m. Road section : 15 m x 2 = 30 m. Road length : 6.000 m Road area : 180.000 m2. Traffic load : 3.5 t/m2. Road structure : 27 cm concrete + 0.15 m base + 0.60 limestones.
Total permanent load is (0.27*2.4 + 0.15*1.8+0.60*1.8)= 2.0 t/m2.
Total load : 3.5 + 2.0 = 5.5 t/m2. Total preload : at least 7.0 t/m2. Soft soil depth : average 10 m. Soft soil type : Clay. Base material : limestone is preferred by owner. Working hours : 2 shift. Construction : finish at 9 September 2014. Ground level : +0.00 (treatment final level)
Above +0.00 is the layer of Road Structure construction
Here we propose several methods as mention below. In each section it will describe
advantage and disadvantage of each method and estimated cost and schedule.
Propose method are :
1. Soil Preloading2. Vacuum Preloading3. Stone Column4. Dynamic Replacement
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
8/15
III. GROUND IMPROVEMENT METHODSSOIL PRELOADING
Soil preload method is a well-known conventional ground improvement. Here we only
shows the work sequence, construction cost and duration. The calculation is based on
10.000 m2 area.
Schedule :
Area : total 18.000 m2 divide by 6 sub-zones with 3 Ha each.
Work group : 3 groups.
PVD installation : 8.000 m / unit / day.
PHD installation : finish 2 weeks after PVD installed.
Soil backfill : max 1 m thickness / week to avoid sliding.
Consolidation : 6 months.
Start to finish : 11 months.
Overlapping with road construction : No.
Notes :
The width of road need to improve is 30 m width only. However it need to backfill more
than 30 m for the berm area. Here we assume slope is 1: 2.
At M-1 there is limestone backfill. This limestone should remove before proceed PVDinstallation.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
9/15
VACUUM PRELOADING
The vacuum preloading method or vacuum consolidation method was firstly proposed by
Kjellman in 1952 for treatment of the soft soil strata. Now the vacuum consolidation
method has become a popular technology in the soft soil improvement work in East Asia.
The principle of the method is that when vacuum pressure is induced into the soil, it will
not only drain water but also atmosphere out of the improving site. Thus, it accelerates the
soil consolidation process, reduces the construction time and increases the soil stability.
The design and the construction work of the method of the must follow standards.
Execution Process of Vacuum Preloading Method is show clearly in picture below.
1. PVD installation 2.
Geomembrane
installation
3. Monitoring
equipments
installation
4. Vacuum +
surcharge
preloading
Construction process of vacuum consolidation method
Here we shows the work sequence and improvement cost.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
10/15
Schedule :
Area : total 18.000 m2 divide by 6 sub-zones with 3 Ha each.
Work group : 3 groups.PVD installation : 8.000 m / unit / day.PHD installation : finish 2 weeks after PVD installed.
Soil backfill : can backfill fast as possible.
Consolidation : 3 - 4 months.
Start to finish : 6 months.
Overlapping with road construction : No.
Notes :
The width of vacuum area same with road width of 30 m.
At M-1 there is limestone backfill. This limestone should remove before proceed PVD
installation.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
11/15
STONE COLUMN
Stone column construction aims to provide a high bearing capacity and reduce post
settlement by reinforce method. Here we propose stone column construct by vibro-
displacement. Picture below shows the work sequence.
Assumption :
Stone column diameter : 1 m Stone column distance : 2 m, square. Stone column depth : 5 m and 10 m. Installed alternating. Stone size : 37 cm. Clean stone. Top surface :0.5 m of limestone (not include limestone for
road structure).
Here we shows the work sequence and improvement cost.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
12/15
Schedule :
Area : total 18.000 m2 divide by 9 sub-zones with 2 Ha each.
Work group : 9 groups.
Install capacity : 240 m / unit / day.
Start to finish : 5 months.Overlapping with road construction : Yes.
Notes :
Minimum Su of original soil is 25 kPa.
Bearing capacity of each stone column is 15 t of each stone column with 0.80 m2 surface
area.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
13/15
DYNAMIC REPLACEMENT
Dynamic Replacement construct use special crane for dynamic compaction. The aim is to
make a dense top layer with a short column which construct by hit the limestone material
use special hammer and let it penetrate the soft soil.Typical depth of penetration is 3.0 m (below the stone layer) with diameter about 2.5 3.0 m.
Picture below shows the work sequence.
Assumption :
Column diameter : 2.53.0 m. Use 2.75 m as average. Column distance : 3.5 m, square. Column depth : 3 m under the limestone layer. Stone type : Limestone. Top surface :0.5 m of limestone (not include limestone for
road structure).
Number of hit : 2025 hit / point.Here we shows the work sequence and improvement cost.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
14/15
Schedule :
Area : total 18.000 m2 divide by 8 sub-zones with 2.25 Ha each.
Work group : 8 groups.
Work cap : 4050 minutes / column / unit.
Productivity : 147 m2 of area / unit / day.Start to finish : 5 months.Overlapping with road construction : Yes.
Notes :
Bearing capacity of each column about 80 t of each column with 7.56 m2 surface area.
There is 45 m soft soil layer under the column which may still contribute for long term
settlement. However this soft soil already improved due to replacement effort.
Long term settlement is estimated about 20 cm.
-
8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod
15/15
IV. GROUND IMPROVEMENT RESUMETable below shows the comparison between methods.