2013-12-31 - @preliminary report - kawasan industri akr - improvement menthod

Upload: dedy-kristianto

Post on 03-Jun-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    1/15

    AKR INDUSTRIAL ESTATE - GRESIK

    EAST JAVA, INDONESIA

    INITIAL REPORT

    FOR

    AKR INDUSTRIAL ESTATE

    AT

    GRESIK, EAST JAVA

    GROUND IMPROVEMENT SCHEME

    Document No : ILSIWJKT24001/001

    REV DATE PREPARED BY REVIEWED BY APPROVED BY

    NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE

    00 LY 29/12 MD 29/12 LR 29/12

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    2/15

    TABLE OF CONTENT

    I. INTRODUCTION .......................................................................................................... - 3 -II. SITE AND SOIL CONDITION .................................................................................... - 4 -III. GROUND IMPROVEMENT METHODS................................................................... - 8 -IV. GROUND IMPROVEMENT RESUME .................................................................... - 15 -

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    3/15

    I. INTRODUCTIONThis document describes various method of ground improvement may apply for roadconstruction at AKR Industrial Estate, Gresik, East Java.

    Key Plan

    The detail calculation will perform by PT. Geotekindo after more discussion with owner

    about their need and technical requirement of the area.

    This report is produced based on the following documents :

    Block Plan. Soil properties. Boreholes. Oral explanation about the requirement.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    4/15

    II. SITE AND SOIL CONDITIONBLOCK PLAN

    Area is dividing in 4 section named M-1, M-2, M-3 and M-4. Map below shows the block

    plan.

    Block Plan

    Base on oral information from consultant, it state area M-1 already backfill use limestone

    with 1 m thickness but quite bouncy. Area M-2, M-3 and M-4 not prepared yet (swamp or

    fish pond) and later will backfill use limestone as in M-1.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    5/15

    SOIL DATA

    Typical boreholes for M-1

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    6/15

    Typical boreholes for M-2 and M-3

    Here we can see the soft clay depth about 1012 m from surface. The soft clay has CPT

    between 0 to 2 means it has a very low bearing capacity.

    Base on lab test, Compression Index (Cc) value around 0.8 to 1.1 means its a highly

    compressible layer.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    7/15

    LOAD PLAN, ASSUMPTION, CROSS SECTION AND PROPOSE METHOD

    Base on drawing, ROW is 80 m : road, drainage, infrastructure space and open area. In

    our opinion the ground improvement should only focus on road area because its the only

    area bearing a high traffic load.

    The assumption below is use in proposal :

    ROW : 80 m. Road section : 15 m x 2 = 30 m. Road length : 6.000 m Road area : 180.000 m2. Traffic load : 3.5 t/m2. Road structure : 27 cm concrete + 0.15 m base + 0.60 limestones.

    Total permanent load is (0.27*2.4 + 0.15*1.8+0.60*1.8)= 2.0 t/m2.

    Total load : 3.5 + 2.0 = 5.5 t/m2. Total preload : at least 7.0 t/m2. Soft soil depth : average 10 m. Soft soil type : Clay. Base material : limestone is preferred by owner. Working hours : 2 shift. Construction : finish at 9 September 2014. Ground level : +0.00 (treatment final level)

    Above +0.00 is the layer of Road Structure construction

    Here we propose several methods as mention below. In each section it will describe

    advantage and disadvantage of each method and estimated cost and schedule.

    Propose method are :

    1. Soil Preloading2. Vacuum Preloading3. Stone Column4. Dynamic Replacement

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    8/15

    III. GROUND IMPROVEMENT METHODSSOIL PRELOADING

    Soil preload method is a well-known conventional ground improvement. Here we only

    shows the work sequence, construction cost and duration. The calculation is based on

    10.000 m2 area.

    Schedule :

    Area : total 18.000 m2 divide by 6 sub-zones with 3 Ha each.

    Work group : 3 groups.

    PVD installation : 8.000 m / unit / day.

    PHD installation : finish 2 weeks after PVD installed.

    Soil backfill : max 1 m thickness / week to avoid sliding.

    Consolidation : 6 months.

    Start to finish : 11 months.

    Overlapping with road construction : No.

    Notes :

    The width of road need to improve is 30 m width only. However it need to backfill more

    than 30 m for the berm area. Here we assume slope is 1: 2.

    At M-1 there is limestone backfill. This limestone should remove before proceed PVDinstallation.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    9/15

    VACUUM PRELOADING

    The vacuum preloading method or vacuum consolidation method was firstly proposed by

    Kjellman in 1952 for treatment of the soft soil strata. Now the vacuum consolidation

    method has become a popular technology in the soft soil improvement work in East Asia.

    The principle of the method is that when vacuum pressure is induced into the soil, it will

    not only drain water but also atmosphere out of the improving site. Thus, it accelerates the

    soil consolidation process, reduces the construction time and increases the soil stability.

    The design and the construction work of the method of the must follow standards.

    Execution Process of Vacuum Preloading Method is show clearly in picture below.

    1. PVD installation 2.

    Geomembrane

    installation

    3. Monitoring

    equipments

    installation

    4. Vacuum +

    surcharge

    preloading

    Construction process of vacuum consolidation method

    Here we shows the work sequence and improvement cost.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    10/15

    Schedule :

    Area : total 18.000 m2 divide by 6 sub-zones with 3 Ha each.

    Work group : 3 groups.PVD installation : 8.000 m / unit / day.PHD installation : finish 2 weeks after PVD installed.

    Soil backfill : can backfill fast as possible.

    Consolidation : 3 - 4 months.

    Start to finish : 6 months.

    Overlapping with road construction : No.

    Notes :

    The width of vacuum area same with road width of 30 m.

    At M-1 there is limestone backfill. This limestone should remove before proceed PVD

    installation.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    11/15

    STONE COLUMN

    Stone column construction aims to provide a high bearing capacity and reduce post

    settlement by reinforce method. Here we propose stone column construct by vibro-

    displacement. Picture below shows the work sequence.

    Assumption :

    Stone column diameter : 1 m Stone column distance : 2 m, square. Stone column depth : 5 m and 10 m. Installed alternating. Stone size : 37 cm. Clean stone. Top surface :0.5 m of limestone (not include limestone for

    road structure).

    Here we shows the work sequence and improvement cost.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    12/15

    Schedule :

    Area : total 18.000 m2 divide by 9 sub-zones with 2 Ha each.

    Work group : 9 groups.

    Install capacity : 240 m / unit / day.

    Start to finish : 5 months.Overlapping with road construction : Yes.

    Notes :

    Minimum Su of original soil is 25 kPa.

    Bearing capacity of each stone column is 15 t of each stone column with 0.80 m2 surface

    area.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    13/15

    DYNAMIC REPLACEMENT

    Dynamic Replacement construct use special crane for dynamic compaction. The aim is to

    make a dense top layer with a short column which construct by hit the limestone material

    use special hammer and let it penetrate the soft soil.Typical depth of penetration is 3.0 m (below the stone layer) with diameter about 2.5 3.0 m.

    Picture below shows the work sequence.

    Assumption :

    Column diameter : 2.53.0 m. Use 2.75 m as average. Column distance : 3.5 m, square. Column depth : 3 m under the limestone layer. Stone type : Limestone. Top surface :0.5 m of limestone (not include limestone for

    road structure).

    Number of hit : 2025 hit / point.Here we shows the work sequence and improvement cost.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    14/15

    Schedule :

    Area : total 18.000 m2 divide by 8 sub-zones with 2.25 Ha each.

    Work group : 8 groups.

    Work cap : 4050 minutes / column / unit.

    Productivity : 147 m2 of area / unit / day.Start to finish : 5 months.Overlapping with road construction : Yes.

    Notes :

    Bearing capacity of each column about 80 t of each column with 7.56 m2 surface area.

    There is 45 m soft soil layer under the column which may still contribute for long term

    settlement. However this soft soil already improved due to replacement effort.

    Long term settlement is estimated about 20 cm.

  • 8/12/2019 2013-12-31 - @Preliminary Report - Kawasan Industri Akr - Improvement Menthod

    15/15

    IV. GROUND IMPROVEMENT RESUMETable below shows the comparison between methods.