2017-18 State of Good Repair Approved Project List Recipient Sub-Recipient Project Title Project Description 2017-18 Estimated total SGR Award Amount Metropolitan Transportation Commission Alameda-Contra Costa Transit District East Bay Bus Rapid Transit (BRT) Funding will support ongoing construction on the East Bay Bus Rapid Transit project. EBBRT will operate along a 9.5 mile corridor from downtown Oakland to the San Leandro BART Station, primarily along International Blvd and E. 14th Street. $ 3,149,541 Metropolitan Transportation Commission San Francisco Bay Area Rapid Transit District Railcar Procurement Project Procurement of 775 railcars to replace BART’s existing fleet of 669 railcars that have reached the end of their useful life and expand capacity by 106 additional railcars. $ 10,247,507 Metropolitan Transportation Commission San Francisco Bay Area Rapid Transit District STA SGR Preventative Maintenance Preventative Maintenance Activities on : Elevator & Escalator, Train Control, Electrical, Mechanical & Traction Power, Track, Automatic Fare Collection, Facilities, Rolling Stock & Shops on AC Traction Motors, Rail Cars, Battery, Axle and Gearbox $ 6,102,066 Metropolitan Transportation Commission City of San Francisco Fire and Life Safety Improvements Upgrade fire alarm systems at the Metro Green Shops, Metro Green Annex, Flynn Division, Scott Division, Kirkland Division and Potrero Division. $ 4,026,493

Upload: phungdang

Post on 29-Jun-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Metropolitan Transportation Commission

Alameda-Contra Costa Transit District

East Bay Bus Rapid Transit (BRT)

Funding will support ongoing construction on the East Bay Bus Rapid Transit project. EBBRT will operate along a 9.5 mile corridor from downtown Oakland to the San Leandro BART Station, primarily along International Blvd and E. 14th Street. $ 3,149,541

Metropolitan Transportation Commission

San Francisco Bay Area Rapid Transit District Railcar Procurement Project

Procurement of 775 railcars to replace BART’s existing fleet of 669 railcars that have reached the end of their useful life and expand capacity by 106 additional railcars. $ 10,247,507

Metropolitan Transportation Commission

San Francisco Bay Area Rapid Transit District

STA SGR Preventative Maintenance

Preventative Maintenance Activities on : Elevator & Escalator, Train Control, Electrical, Mechanical & Traction Power, Track, Automatic Fare Collection, Facilities, Rolling Stock & Shops on AC Traction Motors, Rail Cars, Battery, Axle and Gearbox $ 6,102,066

Metropolitan Transportation Commission City of San Francisco

Fire and Life Safety Improvements

Upgrade fire alarm systems at the Metro Green Shops, Metro Green Annex, Flynn Division, Scott Division, Kirkland Division and Potrero Division. $ 4,026,493

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Metropolitan Transportation Commission City of San Francisco

Flynn Lifts and Maintenance Facility Improvements

Replace four vehicle lifts to ensure the safety of employees, continue proper maintenance of vehicles and keep equipment in good operating condition. $ 2,562,863

Metropolitan Transportation Commission City of San Francisco

Woods Bus Facility Boiler Replacement

Phase I of the project includes the replacement of existing boiler, performing HVAC and other improvements needed to improve the efficiency of the facility. $ 2,909,836

Metropolitan Transportation Commission

Central Contra Costa Transit Authority

Intelligent Transportation System Security Maint

Provide ongoing maintenance to a capital system that is directly related to security, including our radio, onboard computer, CAD/AVL, and BusTime systems. $ 119,162

Metropolitan Transportation Commission

Eastern Contra Costa Transit Authority

Replacement of Damaged or Missing Bus Shelters

We have had many bus shelters damaged out in the field mostly from automobile accidents. And, we are aware of some missing shelters. We want to use these funds to acquire four or five shelters to install. $ 55,157

Metropolitan Transportation Commission City of Fairfield Local Bus Fleet Replacement

The City of Fairfield plans to use FY 2017-2018 SB1 State of Good Repair funds to help fund the purchase of up to 3 zero-emission electric buses. $ 26,276

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Metropolitan Transportation Commission

Golden Gate Bridge Highway and Transportation District

MS Marin Ferry Boat Repower and Dry Dock

The MS Marin (MSM) Ferry boat is a 750/125 passenger/bicycle capacity Spaulding Class vessel and is a vital component in the seven ferry Golden Gate Ferry fleet. The proposed project includes improvements to the superstructure and hull and the purchase and installation of two main engines. Work is necessary to remain in compliance with federal and state regulatory bodies. $ 578,261

Metropolitan Transportation Commission

Livermore-Amador Valley Transit Authority

Bus Shelter and Stop Maintenance

Rehabilitation and maintenance of various bus stop locations, including relocation of bus shelters and amenities affected by the COA route realignments. $ 55,640

Metropolitan Transportation Commission Marin County Transit District Purchase One Shuttle Vehicle

Purchase a cutaway vehicle needed to meet existing service levels (currently operated with a retired active vehicle) $ 130,000

Metropolitan Transportation Commission Marin County Transit District

MCTD: Replace Four (4) Rural cutaway vehicles

Replace four (4) cut-away 7-year cutaway vehicles used on rural service with 30ft narrow diesel vehicles (10 -12 year life) $ 75,113

Metropolitan Transportation Commission

Napa County Transportation and Planning Agency (submitted as Napa Valley Transportation Authority)

Vine Transit Bus Maintenance Facility

For the construction of a new bus operations and maintenance facility. $ 13,449

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Metropolitan Transportation Commission

Peninsula Corridor Joint Powers Board MP36 Mid Life Overhaul

Mid-life overhaul of MP36 locomotives to keep them in a state of good repair $ 1,100,000

Metropolitan Transportation Commission

Peninsula Corridor Joint Powers Board Grade Crossing Improvements

Improvements to eight grade crossings to enhance safety $ 145,276

Metropolitan Transportation Commission City of Petaluma Preventative Maintenance

Capital expenses related to preventative maintenance on Fixed Route buses. $ 6,558

Metropolitan Transportation Commission

San Francisco Bay Area Water Emergency Transportation Authority (WETA) Vessel Replacement - Vallejo

This project will design and construct a replacement vessel for the M/V Vallejo, currently utilized in the ferry service between the City of Vallejo and San Francisco. Dakota Creek was awarded the vessel construction contract in September 2016. Vessel construction is underway and vessel delivery is expected in December 2018. $ 277,255

Metropolitan Transportation Commission San Mateo County Transit District

Replacement of 10 Gillig buses w/ electric buses

Replacement of 10 end of life 40-foot Gillig buses $ 568,328

Metropolitan Transportation Commission San Mateo County Transit District

Linda Mar Park-n-Ride Repaving Repaving of existing park and ride lot $ 657,921

Metropolitan Transportation Commission

Santa Clara Valley Transportation Authority

Kinkisharyo Light Rail Vehicle Mid-life Overhaul

Rehab of light rail vehicles at the mid-point in their useful life benchmark. $ 4,330,471

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Metropolitan Transportation Commission City of Santa Rosa

Preventive Maintenance of Fixed-Route fleet

Assist in the preventive maintenance of the fixed-route fleet which consists of 32 buses. Performing preventive maintenance on the buses in a timely manner enables Santa Rosa CityBus to provide reliable service to our customers. $ 28,791

Metropolitan Transportation Commission Solano County Transit (SolTrans)

Replacement Engines for Diesel Hybrid Buses

Diesel hybrid buses used in local service need engine replacements mandated by the California Air Resources Board upon attaining 185,000 miles. The funds will be used to perform the replacements on four (4) diesel hybrid buses. $ 64,599

Metropolitan Transportation Commission County of Sonoma

Operations Facility Roof Rehabilitation

This project will rehabilitate the roof at Sonoma County Transit's Operations Facility. $ 33,956

Metropolitan Transportation Commission

Sonoma-Marin Area Rail Transit District (SMART) SMART Capital Spare Parts

Additional capital spare parts to support maintenance schedules recently established with the startup of SMART services to accommodate more trips and longer trains than planned. Request is for up to $499,395 with a minimum of $153,741. $ 153,741

Metropolitan Transportation Commission City of Union City

Replace six (6) Paratransit Vans

Replace six (6) cutaway vehicles used in ADA Paratransit service $ 17,115

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Metropolitan Transportation Commission

Western Contra Costa Transit Authority

Local Match for Purchase of Vehicle Replacement

These funds will be used to support the local match requirement of the replacement of Revenue Vehicles using Federal Funds $ 71,403

Metropolitan Transportation Commission

Alameda County Congestion Management Agency - to Altamont Corridor Express (ACE) Preventative Maintenance

San Joaquin Regional Rail Commission houses an inventory of spare parts to maintain ACE rolling stock, ensuring equipment is service-ready at all times. May include brake shoes, wheels, and reconditioning of brake valves on railcars and locomotives. $ 60,000

Metropolitan Transportation Commission

Santa Clara Valley Transportation Authority - to Altamont Corridor Express (ACE)

Facility Upgrades and Improvements

ACE’s transit facilities will receive maintenance to ensure facilities are kept in a state of good repair. Examples of station improvements include fixing pavement at parking lots and platforms. $ 58,960

Sacramento Area Council of Governments

Sacramento Area Council of Governments

Connect Card Equipment Maintenance

Connect Card Equipment Maintenance $ 151,681

Sacramento Area Council of Governments City of Davis (Unitrans)

Bus Stop Improvements Project

Improve access, amenities, and passenger security at bus stops in the Davis Urbanized Area and on the UC Davis campus. $ 32,086

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Sacramento Area Council of Governments City of Elk Grove

Purchase of Two Cutaway Buses for E-van Service

The City of Elk Grove is purchasing two cutaway buses for replacement of two existing 2012 cutaway buses. The buses are needed in order to maintain the City's paratransit bus service. $ 242,824

Sacramento Area Council of Governments City of Folsom Preventative Maintenance

The City of Folsom preventative maintenance expense for light rail operations within City limits. $ 110,324

Sacramento Area Council of Governments County of Sacramento 2018 bus replacement Replacement of 3 Starcraft buses $ 53,787

Sacramento Area Council of Governments Sacramento Regional Transit System Preventative Maintenance

These funds will be used for preventative maintenance for bus and rail. $ 2,306,188

Sacramento Area Council of Governments Yolo County Transportation District

40 Foot CNG Transit Bus Replacement

Replace 7 vehicles - 40 Foot CNG Transit Buses $ 329,879

Sacramento Area Council of Governments Yuba-Sutter Transit Authority

Replace Demand Response/Rural Route Buses

Purchase 10 paratransit replacement vehicles $ 246,218

San Diego Association of Governments North County Transit District

Locomotive Replacement Project

This project will replace five Tier 0 and two Tier 2 COASTER locomotives with cleaner, more efficient Tier 4 locomotives. Project benefits include more efficient operations, decreased emissions and fuel savings. $ 1,743,219

San Diego Metropolitan Transit System

San Diego Metropolitan Transit System

Substation DC Feeder Breaker Replacement

This project is a continuation of an existing project that includes upgrading 9 traction power substations with new DC circuit breakers. $ 3,280,000

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

San Diego Metropolitan Transit System

San Diego Metropolitan Transit System

Orange/Blue Line Tie Replacement

This investment includes the replacement of up to 5800 timber crossties; surfacing and placement of top ballast; and destressing of 28,207 feet of track from Massachusetts Ave. to Spring St. on the Orange Line. $ 1,271,892

Tahoe Regional Planning Agency Tahoe Transportation District Preventive Maintenance Preventive Maintenance $ 105,525

Tahoe Regional Planning Agency Placer County-Tahoe Area Regional Transit TART Transit Bus Replacement 40' Gillig Low Floor CNG Transit Bus $ 44,836

Alpine County Transportation Commission County of Alpine

Security Cameras for Dial-A-Ride Minivan

New security cameras for Dial-A-Ride Vehicle $ 1,621

Amador County Transportation Commission Amador Regional Transit System Bus Shelter Rehab

Replace damaged plastic bus shelter roofs with metal-solar lighted roofs $ 35,700

Amador County Transportation Commission Amador Regional Transit System

I-Stop Solar Battery Replacement

Replace damaged I-Stop Solar Batteries $ 2,715

Amador County Transportation Commission Amador Regional Transit System

Admin bldg Interior Lighting upgrade

Replace inefficient and defective can lights in Admin Bldg $ -

Amador County Transportation Commission Amador Regional Transit System

Admin Bldg Parking Lot Light Rehab

Replace old Sodium Halide lights with energy efficient LED $ 1,500

Amador County Transportation Commission Amador Regional Transit System

Transit Center Parking Lot light Rehab

Replace old Sodium Halide lights with energy efficient LED $ 10,000

Amador County Transportation Commission Amador Regional Transit System

Maintenance Shop exterior lighting replacement

Old Metal Halide lights replace with energy efficient LED $ 3,784

Butte County Association of Governments Butte Regional Transit Vehicle replacement One 35 ft. low floor diesel Gillig $ 319,011 Butte County Association of Governments City of Gridley- Specialized Service Preventative maintenance

Repairs on bus scheduled preventative maintenance $ 191

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Calaveras County Local Transportation Commission

County of Calaveras - Calaveras Transit Preventative Maintenance

SB1 State of Good Repair project funding will be used in FY2017-18 for the maintenance and repair of our rolling stock $ 61,029

Colusa County Local Transportation Commission

County of Colusa - Colusa Co Transit Agency Shop Equipment

These funds will be used for update/replacement of outdated equipment in our shop used to keep the transit system operational and in good repair. $ 30,347

Del Norte County Local Transportation Commission Redwood Coast Transit Authority Bus Stop Improvements

Purchase and Install shelters, benches, and information at existing bus stops $ 38,115

El Dorado County Transportation Commission El Dorado County Transit Authority Preventative Maintenance Preventative maintenance for Fleet $ 235,684 El Dorado County Transportation Commission El Dorado County Transit Authority Vehicle Replacement Local Fixed Route Bus Replacement $ -

Fresno County Council of Governments City of Clovis

Maintenance Facility Boiler Replacement

Replacement of obsolete RITE boiler with an efficient Cleaver Brooks 2-boiler system in the bus fleet shop. The boiler is used to heat the floor in the bus maintenance facility. $ 75,120

Fresno County Council of Governments City of Clovis

Maintenance Facility Vehicle Lifts Replacement

Replacement of two obsolete vehicle lifts with new, greater-weight bearing lifts in bus fleet shop. The lifts are used by the mechanics to perform repairs and period maintenance on the buses. $ 94,265

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Fresno County Council of Governments City of Fresno (FAX) Purchase Electric Bus

Purchase replacement 40-foot low floor fixed route battery electric bus. $ 1,060,828

Fresno County Council of Governments

Fresno County Rural Transit Agency (FCRTA)

2017/18 Budget-Bus Maintenance Facility

FCRTA will build or renovate a Bus Maintenance and Fuel Yard Facility for its bus fleet at a site to be determined in Fresno County. FCRTA will acquire land large enough for the site of this Facility and all of its activities which will include bus storage, repair and maintenance, and CNG fueling and/or Electric Charging. All site improvements, infrastructure improvements, and any equipment and amenities necessary for the functioning of this Facility will be included in this grant project. $ 287,482

Glenn County Local Transportation Commission

County of Glenn- Glenn Transit Service

Transit Vehicle Preventative Maintenance/Repower

Perform preventative maintenance on transit vehicles, including replacement of major components such as engine, transmission, or fare boxes. $ 39,392

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Humboldt County Association of Governments City of Arcata

Arcata Transit Center Improvements

Install new PA system, make ADA improvements to existing public and driver restrooms, improvements for records storage onsite. Replace aged main ADA access door to Intermodal Transit Facility (ITF), ITF break room and meeting room improvements $ 33,549

Humboldt County Association of Governments City of Arcata

Giuntoli Bus Stop Improvements

Install a solar powered enhanced pedestrian crossing warnings device at an existing uncontrolled roadway/mid-block crossings including ADA improvements, stripping and signage located adjacent to two bus stops. $ 43,000

Humboldt County Association of Governments City of Eureka Maintenance and Repair Maintenance and repair of vehicles $ 7,133 Humboldt County Association of Governments City of Fortuna - Specialed Service HTA Bus Shelter Solar Lighting

Solar lighting inside the HTA shelter to improve security $ 137

Humboldt County Association of Governments Humboldt Transit Authority (HTA) Bus Shelter Solar Lighting

Solar lighting inside the shelter to improve security $ 19,638

Humboldt County Association of Governments Humboldt Transit Authority (HTA) Passenger Counters

Automated passengers counters that track boarding and alighting on the bus $ 51,705

Humboldt County Association of Governments Humboldt Transit Authority (HTA)

Passenger Counter Software & Data Station

A base station that transmits the counts from the bus to a server. $ 23,200

Humboldt County Association of Governments Humboldt Transit Authority (HTA)

CTSA Fleet Maintenance and Repair

Rehabilitation of existing consolidated transportation services agency (CTSA) vehicles $ 33,082

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Inyo County Local Transportation Commission Eastern Sierra Transit Authority Preventative Maintenance

Preventive maintenance of Eastern Serra Transit Authority's revenue vehicles in Inyo County.The PM services will repair/replace systems and components including: brakes, cooling, transmission, engine tune-up, A/C, auto-chains, and electrical. $ 24,732

Kern Council of Governments City of ArvinVehicle replacements and facility improvements Electric vehicle infrastructure $ 69,699

Kern Council of Governments City of California City Vehicle replacements and facility improvements Electric vehicle infrastructure $ 238

Kern Council of Governments City of Delano Construction of bus shelters Bus stop shelters $ 72,778

Kern Council of Governments Golden Empire Transit DistrictMaintenance facility and vehicle replacements

Maintenance garage and vehicle replacements $ 712,974

Kern Council of Governments County of Kern - Kern Transit Bus Replacement Purchase two cutaway buses $ 274,889

Kern Council of Governments City of McFarlandConstruction of a transit facility

Construction of a new transit facility, that will provide enhanced operation and maintenance services to sustain the current Dial-a-Ride bus fleet; and improve operational efficiency and quality of services for its residents. $ 19,853

Kern Council of Governments City of RidgecrestReplacement of transit maintenance equipment

Fuel pump replacement and emergency generator $ 41,244

Kern Council of Governments City of ShafterReplacement of electric transit vehicles Electric vehicle replacements $ 24,825

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Kern Council of Governments City of Taft Replacement of Rolling StockCity is planning on replacing 2 buses that have exceeded their useful life, 78,882$

Kern Council of Governments City of Taft Replacement security equipment and systems

Our old security cameras monitoring the transit office and yard are in failing condition and need replacing 5,105$

Kern Council of Governments City of Tehachapi Park & Ride and Transit Facility

Construct a park and ride with 120 parking spaces. Bus turnouts, bicycle parking, bus shelters, minor landscaping, lighting and security. $ 16,457

Kern Council of Governments City of Wasco Replace two transit vehicles

Replace existing bus with new 24 passenger bus. The exiting bus has over 104,000 miles and is out of service. Replace existing bus with a new 14-Passenger bus. Rebuild motors on four CNG compressors. $ 35,770

Kings County Association of Governments City of Corcoran

Bus Transmission and Driver Seats

Replace one Corcoran Area Transit bus transmission and two driver seats $ 29,947

Kings County Association of Governments

Kings County Area Public Transit Agency (KCAPTA) Bus Security Camera System

Upgrade or Replace King Area Rapid Transit bus security camera system $ 180,079

Lake County City Council of Governments Lake Transit Authority Replace Dial-A-Ride Vehicle

Purchase replacement Class B cutaway paratransit vehicle with gasoline fuel, wheelchair lift, farebox, etc. $ 63,448

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Lake County City Council of Governments Lake Transit Authority

New 4-post vehicle lift for maintenance shop

Purchase and install one new 4-post vehicle lift for maintenance shop to improve capacity for maintaining vehicles. $ 28,000

Lassen County Local Transportation Commission Lassen Transit Service Agency

Preventative Maintenance for Lassen Rural Bus

The Preventative Maintenance for Lassen Rural Bus project will use SGR funds to pay the part of our maintenance and operation contract with Paratransit which is used to pay for repair of revenue vehicles. $ 34,195

Lassen County Local Transportation Commission Lassen Transit Service Agency

Lassen Senior Services Preventative Maintenance

The Preventative Maintenance for Lassen Senior Services (LSS) project will use SGR funds to pay for repair costs of our subcontractor Lassen Senior Services. $ 2,875

Lassen County Local Transportation Commission Lassen Transit Service Agency

Preventative Maintenance for Big Valley

The Preventative Maintenance for Big Valley project will use SGR funds to pay for repair costs of our subcontractor Big Valley 50 Plus. $ 3,999

Lassen County Local Transportation Commission Lassen Transit Service Agency

Contributions to Vehicle Replacement Fund

Funds to be used to match other local, state, and federal grants for replacing vehicle #17 and #18 of the Lassen Rural Bus fleet $ 2,153

Los Angeles County Metropolitan Transportation Authority

Los Angeles County Metropolitan Transportation Authority

Metro Bus Vehicle Preventive Maintenance

Preventive maintenance expenses at all Metro Bus Operating Divisions from 1/1/18 to 6/30/18 $ 14,305,337

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Fresno County Council of Governments

Los Angeles County Metropolitan Transportation Authority

Metro Rail Vehicle Preventive Maintenance

Preventive maintenance expenses at all Metro Rail Operating Divisions from 1/1/18 to 6/30/18 $ 13,603,692

Los Angeles County Metropolitan Transportation Authority Antelope Valley Transit Authority Server Room Upgrade

Update antiquated computer servers and related equipment $ 183,220

Los Angeles County Metropolitan Transportation Authority City of Commerce Preventive Maintenance

The funds shall be used towards preventive maintenance expenses. $ 44,580

Los Angeles County Metropolitan Transportation Authority City of Culver City

Culver CityBus FY18 Preventive Maintenance

Preventive Maintenance on the Culver CityBus fleet of 56 CNG Transit Buses in fixed route revenue service during FY17-18. $ 140,677

Los Angeles County Metropolitan Transportation Authority Foothill Transit Zone Farebox Rehabilitation

Replace obsolete parts with parts supported by the manufacturer. Replace existing smart card reader with improved security features, real-time communication ready, improved wireless communication with central servers. $ 533,771

Los Angeles County Metropolitan Transportation Authority Foothill Transit Zone

Bus Heavy & Preventive Maintenance

Activities, supplies, materials, labor, services, and associated costs required to preserve or extend the functionality and serviceability of buses. $ -

Los Angeles County Metropolitan Transportation Authority Foothill Transit Zone CNG Bus Replacement

Replace 25 CNG buses that have reached the end of useful life with 25 new CNG buses $ -

Los Angeles County Metropolitan Transportation Authority Foothill Transit Zone

CNG to Electric Bus Replacement

Replace 20 CNG buses that have reached the end of useful life with 20 new all electric buses $ -

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Los Angeles County Metropolitan Transportation Authority City of Gardena Preventative Maintenance

The preventative maintenance undertaken under this grant include repairs and maintenance of SGR funded assets including its facility, equipment, and vehicles. $ 113,263

Los Angeles County Metropolitan Transportation Authority

Long Beach Public Transportation Company Bus Replacement

Replace buses that have met their useful life. Request funding to support the purchase of up to (10) 40ft. Battery Electric Buses that are fully ADA compliant with a passenger count of up to 38 passengers. $ 504,501

Los Angeles County Metropolitan Transportation Authority City of Los Angeles

Electrification of 20 bus shuttles

Funds will replace twenty 22' CNG bus shuttles which have reached their end of useful lives of 12 years. The funds will cover the cost difference between the value of a CNG fueled shuttle and a battery-electric bus shuttle for the CityRide program. $ 815,830

Los Angeles County Metropolitan Transportation Authority County of Los Angeles

South Whittier Bus Shelters Replacement

Replace 16 advertising bus stop shelters located in the unincorporated South Whittier area. Each bus stop shelter will consists of a bench, a trash receptacle and illumination from dusk to dawn. $ 238,071

Los Angeles County Metropolitan Transportation Authority City of Montebello Preventive Maintenance

Preventive maintenance on hybrid bus fleet $ 182,221

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Los Angeles County Metropolitan Transportation Authority City of Norwalk

On-Road Heavy Duty Engines (4)

Purchase of 4 V10 remanufactured engines to comply with CA Air Resources Board's Executive Order A 359-006. $ 15,158

Los Angeles County Metropolitan Transportation Authority City of Norwalk AC inverters (5)

Purchase 5 AC Inverters to ensure proper temperature onboard buses during the summer months. $ 16,925

Los Angeles County Metropolitan Transportation Authority City of Norwalk Engine Silicone Couplings (3)

Purchase replacement couplings in order to prevent engine failure. $ 6,457

Los Angeles County Metropolitan Transportation Authority City of Norwalk

Miscellaneous maintenance expenses

Cost of services or repairs in order to maintain or repair the existing transit vehicle fleet, such as those described above. $ 38,540

Los Angeles County Metropolitan Transportation Authority City of Redondo Beach

Transit Operations Facility Improvements

Transit Operations facility improvements that may include offices, maintenance rooms, driver operator's room, bathroom facilities and storage. $ 26,490

Los Angeles County Metropolitan Transportation Authority City of Santa Clarita

Transit Maintenance Facility (TMF) Improvements

Transit Maintenance Facility (TMF) Bus Wash Replacement and Upgrade $ 236,585

Los Angeles County Metropolitan Transportation Authority City of Santa Monica Big Blue Bus Bus Replacement

Funds may be used to purchase one 40-ft Near Zero bus for replacement. $ 469,210

Los Angeles County Metropolitan Transportation Authority City of Santa Monica

Big Blue Bus Preventive Maintenance

Preventive Maintenance on fixed route revenue vehicles $ -

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Los Angeles County Metropolitan Transportation Authority City of Torrance TTS Preventive Maintenance

Torrance Transit System will use the State of Good Repair funds to supplement the preventive maintenance of our revenue bus fleet. $ 188,209

Madera County Local Transportation Commission City of Chowchilla

Improvements to Operation Facilities Bus Shelter and Amenities $ 17,939

Madera County Local Transportation Commission City of Madera

Transit Enhancements - Shelters

The most recent on-board survey identified 55% of passengers rode transit to do shopping. This project will update and modernize transit stop(s) in major shopping locations $ 20,000

Madera County Local Transportation Commission City of Madera

Transit Enhancement - Fare Collection Systems

The current fare collection system is cumbersome, outdated, and hard to reconcile. Drivers complain of passenger fare evasion and misuse. This systemwide project will acquire and install a modern fare system based on a solid technology plan. $ 49,075

Madera County Local Transportation Commission City of Madera Transit Enhancement - Signage

This project will address passengers complaints for identified max bus stops and routes by replacement old signage that include stop numbers, routes, and are more visable $ 20,000

Madera County Local Transportation Commission County of Madera Park-and-Ride Lot

Development of New Park-and-Ride Lot $ 103,545

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Mariposa County Local Transportation Commission

County of Mariposa - Mariposa County Transit Preventative Maintenance Maintenance For Buses $ 24,175

Mendocino Council of Governments Mendocino Transit Authority Ukiah Transit Center

Development and construction of a multi-modal transit center in the City of Ukiah, Mendocino County collaborating transportation services for Mendocino Transit, Lake Transit, Greyhound, Amtrak and Walk-Bike Mendocino. $ 128,995

Merced County Association of Governments

Merced County Association of Governments

Acquisition & Remodel of Transit Admin Facility

Local Match on federal project 5339 - Acquisition & Remodel of Transit Administration Facility $ 66,073

Merced County Association of Governments

Merced County Association of Governments

Remodel of Transit Admin Facility

Local Match on federal project 5339 - Remodel of Transit Administration Facility $ 60,929

Merced County Association of Governments

Transit Joint Powers Authority of Merced County Vehicle Lifts

Purchase four vehicle lifts for Maintenance facility $ 252,230

Merced County Association of Governments

Yosemite Area Regional Transportation System

Purchase new camera equipment for YARTS fleet

Use SGR funds as match funds for a capitol grant to purchase new camera equipment for the YARTS fleet $ 11,595

Modoc County Local Transportation Commission

Modoc Transportation Agency - Specialized Service

Capital Grant Match Vehicle Replacement

(1) Ford T350 Type B (Vehicle Replacement) 7 Pass + 1 W/C Gas $ 9,900

Modoc County Local Transportation Commission

Modoc Transportation Agency - Specialized Service Modoc Transportation Agency IT Security Equipment and Systems $ 4,257

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Mono County Local Transportation Commission Eastern Sierra Transit Authority Preventative Maintenance

Preventive maintenance of Eastern Serra Transit Authority's revenue vehicles in Inyo County.The PM services will repair/replace systems and components including: brakes, cooling, transmission, engine tune-up, A/C, auto-chains, and electrical. $ 46,894

Transportation Agency for Monterey County Monterey-Salinas Transit (MST) MST Bus Procurement

Procurement of two 35 ft. suburban transit buses $ 772,263

Nevada County Local Transportation Commission City of Truckee Transit Shelter Replacement

Replace a transit shelter that is not ADA compliant $ 137,780

Orange County Transportation Authority

Orange County Transportation Authority

Ten Zero-Emission Hydrogen Fuel Cell Buses

Purchase 10 zero-emission hydrogen fuel cell buses $ 5,606,362

Orange County Transportation Authority

Orange County Transportation Authority

Heating Ventilation Unit Replacements

Replace 30 year old heating-ventilation units at the Anaheim Bus Base Maintenance Building $ 66,681

Placer County Transportation Planning Agency City of Auburn Preventive Bus Maintenance

Perform regularly scheduled maintenance of 5 fixed route buses to prevent breakdowns and carry out necessary repairs to maintain vehicle safety and performance. $ 15,430

Placer County Transportation Planning Agency County of Placer

Placer County Transit Preventive Bus Maintenance

Perform regularly scheduled maintenance of 16 fixed route buses and 13 dial a ride buses to prevent breakdowns and carry out necessary repairs to maintain vehicle safety and performance. $ 130,495

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Placer County Transportation Planning Agency County of Placer TART Transit Bus Replacement

Tahoe Truckee Area Regional Transit (TART) 40' Gillig Low Floor CNG Transit Bus $ 153,285

Placer County Transportation Planning Agency City of Roseville

Local Fixed Route Fleet Preventive Maintenance

Perform regularly scheduled maintenance of 14 fixed route buses to prevent breakdowns and carry out necessary repairs to maintain vehicle safety and performance. $ 159,901

Plumas County Local Transportation Commission County of Plumas Preventative Bus Maintenance

Maintenance through a 3rd Party Operator $ 27,599

Riverside County Transportation Commission City of Banning

Preventative Maintenance & Fleet Rehab

Extend service life of some older units in the city's fleet. This project would enhance State of Good Repair much more expeditiously than vehicle replacement, which is not financially possible in the next two fiscal years. $ 38,307

Riverside County Transportation Commission City of Beaumont

Modernization of Maintenance Facility

Mechanics at vehicle maintenance facility currently conduct inspections, service and repairs out in the elements unprotected from weather. A metal structure is proposed to be installed after removing existing unreinforced masonry carports. $ 66,478

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Riverside County Transportation Commission City of Corona

Vehicle Maintenance Oversight Project

Maintenance oversight inspection services for current fleet. Entails monitoring and verifying buses are properly and timely maintained to maximize vehicle service life, minimize mechanical breakdowns and reduce costly and prolonged major repairs. $ 50,000

Riverside County Transportation Commission City of Corona Purchase ADA Accessible Van

ADA accessible van to transport passengers/wheelchair to support the current Dial-A-Ride Program. Transporting few passengers or one wheelchair is more efficient using smaller van rather than a larger vehicle such as a cutaway. $ 48,039

Riverside County Transportation Commission Palo Verde Valley Transit Agency

Facility Shade Structure Project

Procure a 30'x40'x20' shade structure designed securely for parking and for mechanics doing repair work on vehicles. $ 35,510

Riverside County Transportation Commission City of Riverside - Specialized Service

Surveillance System Replacement

Replace camera systems in each of our 35 minibuses. The current DVR systems in buses have been repurposed several times as new replacement buses have been ordered and put into service. The video surveillance systems have been regularly repaired and have become unreliable. $ 96,794

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Riverside County Transportation Commission Riverside Transit Agency

Facility & Fuel Station Enhancements & Upgrades

Existing Facility & Fuel Station Enhancements & Upgrades including but not limited to: ADA upgrades, Fuel station upgrades, security enhancements and enhanced maintenance facilities and equipment as needed. Facility has exceeded useful life. $ 1,856,095

Riverside County Transportation Commission SunLine Transit Agency

Preventative Maintenance Revenue Vehicles

Preventative maintenance to keep revenue vehicles in good state of repair and prolong their useful service life. $ 503,261

Riverside County Transportation Commission SunLine Transit Agency

Division 1 Maintenance Roof Repair

Repair aged interior and exterior roof of the Thousand Palms, CA maintenance bay. $ 75,000

Riverside County Transportation Commission

SunLine Transit Agency Division 2 Maintenance Roof Repair

Repair aged roof of the Indio, CA maintenance bay. $ 50,000

Riverside County Transportation Commission SunLine Transit Agency Maintenance Equipment

Purchase maintenance equipment, shop and small tools. $ 50,000

Riverside County Transportation Commission SunLine Transit Agency

Install Electric Charging for Division 2 Buses

Install electrical charging stations for electric buses to operate in the East Valley. $ 75,362

Riverside County Transportation Commission

RCTC - Corresponding to Southern California Regional Rail Authority Metrolink Capital Maintenance

Rehabilitation, reconstruction or replacement of Metrolink structures, track, trackbed, signals, communication systems, facilities, stations, platforms, signage, equipment, systems and rolling stock to ensure state of good repair. $ 752,084

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Council of San Benito County Governments

San Benito County Local Transportation Authority

Rolling Stock, Replacement, Two Vehicles

Procure Rolling Stock, Replacement, Two Vehicles medium-sized gas cutaways. $ 77,185

San Bernardino County Transportation Authority

San Bernardino County Transportation Authority (formerly SANBAG)

Santa Fe Depot Structural Rehab & Repair

SBCTA will utilize SGR funds to perform various structural repairs in the east and west wingbasements of the San Bernardino Santa Fe Depot and the Masonry Arch of the Harvey House. $ 687,300

San Bernardino County Transportation Authority Morongo Basin Transit Authority Facility Lighting Upgrades

MBTA will perform upgrades to the facility lighting system at the MBTA Operations Center located in Joshua Tree. The Facility Lighting Upgrade Project will consist of replacing the current lighting system to a more efficient LED lighting system. $ 10,100

San Bernardino County Transportation Authority Morongo Basin Transit Authority Bus Stop Upgrades

MBTA will upgrade the bus stop located at State Route 62 and Elk Trail in Yucca Valley to improve accessibility and safety. The upgraded bus stop will include an ADA accessible ramp, sidewalk, concrete bus shelter pad, and a bus shelter. $ 67,436

San Bernardino County Transportation Authority Morongo Basin Transit Authority Security Surveillance Upgrades

MBTA will utilize SGR funds to upgrade various security cameras and related equipment in or around the MBTA facilities located in Joshua Tree, Yucca Valley, and Twentynine Palms. $ 3,030

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

San Bernardino County Transportation Authority Morongo Basin Transit Authority Vehicle Rehabilitation

MBTA will use SGR funds to fund vehicle rehabilitations which may include engine or transmission replacements. $ 23,706

San Bernardino County Transportation Authority

Mountain Area Regional Transit Authority Bus Stop Improvements

Mountain Transit will improve bus stops in the Mountain Transit service area. The bus stop improvements will include design plans, construction of the bus pad and shelter, solar lighting, and ADA improvements as necessary. $ 73,623

San Bernardino County Transportation Authority City of Needles Preventative Maintenance

The City of Needles will utilize SGR funds for preventative maintenance costs. $ 7,201

San Bernardino County Transportation Authority Omnitrans I Street Facility Upgrades

Omnitrans will use SGR funds to perform various upgrades to the Omnitrans Facility on I Street which will include CNG vehicle maintenance upgrades and a methane detection system for safety purposes. $ 1,558,464

San Bernardino County Transportation Authority Victor Valley Transit Authority Replacement Buses

VVTA will use SGR funds to replace transit vehicles that are part of the active vehicle fleet. $ 681,847

San Bernardino County Transportation Authority

SBCTA - Corresponding to Southern California Regional Rail Authority Metrolink Capital Maintenance

SCRRA will use SGR funds to rehabilitate, reconstruct, or replace various Metrolink structures and equipment vital to Metrolink service. $ 247,826

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

San Joaquin Council of GovernmentsSan Joaquin Council of Governments

Capital Improvements throughout SJ County

Capital improvements across multiple systems. Include, but not limited to: bus replacements, station upgrades, passenger amenities, security upgrades, maintenance facility upgrades, preventative maintenance. $ 992,080

San Joaquin Council of Governments City of Escalon Preventive MaintenanceCover preventative maintenance costs of eTrans vehicles $ 249

San Joaquin Council of Governments City of LodiLight Pole upgrade at Parking Structure

Replace 11 of the existing 400 watt lamp fixtures with upgraded energy efficient LED fixtures for enhanced area lighting in the parking structure at the Transit Station. The new lights are brighter, and cover a larger area for added security. $ 4,449

San Joaquin Council of Governments City of Manteca Preventive MaintenanceCover preventative maintenance costs of Manteca Transit vehicles $ 1,154

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

San Joaquin Council of GovernmentsSan Joaquin Regional Transit District

RTC Maintenance Bay Floor Resurfacing

This project will include resurfacing of the maintenance bay of the Regional Transportation Center (RTC). The project will apply a new surface to the existing maintenance bay that has not been able to withstand current usage and has shown cracks and other damage. The new surface will be if a higher quality, will be more resilient, and rehabilitate the facility to ensure its useful life. $ 112,678

San Joaquin Council of Governments

San Joaquin Regional Rail Commission - to Altamont Corridor Express (ACE) Railcar Midlife Overhaul

Midlife overhauls of the existing ACE fleet will extend the useful life of railcars by over 25 years. $ 80,000

San Luis Obispo Area Council of Governments City of Morro Bay

Morro Bay Transit Replacement Vehicle

Purchase replacement vehicle that is beyond the Useful Life Criteria set by the FTA, which would also include the purchase and installation of exterior graphics and communications equipment. Bus will be Class B medium-size gas bus. $ 540

San Luis Obispo Area Council of Governments City of San Luis Obispo Transit

Fleet Replacement - "Clean" Fuel Vehicle

Purchase one electric replica trolley. Vehicle approaching the end of its FTA defined “useful life.” Available SB SGR funds would be to work now towards clean fuel fixed route transit vehicles. $ 7,358

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

San Luis Obispo Area Council of Governments

San Luis Obispo Regional Transit Authority

New SLO RTA Bus Maintenance Facility

Construction of a new Bus Maintenance Facility on a 6.5-acre site to meet long-term needs. This funding is being recommended for possible inclusion of the final two design and engineering tasks. The new facility will house ops, maintenance, and admin. $ 387,347

San Luis Obispo Area Council of Governments

South County Area Transit - Funds to SLO RTA See SLO RTA Description $ 1,537

Santa Barbara County Association of Governments City of Guadalupe

Transit Bus Replacement Local Match

Replace one bus that has reached the end of it's useful life. $ 869

Santa Barbara County Association of Governments City of Lompoc Replacement Buses for COLT

Purchase of 5 replacement buses for City of Lompoc Transit (COLT) system. The buses will be gas-powered 26 ft. cutaways. $ 397,427

Santa Barbara County Association of Governments

Santa Barbara Metropolitan Transit District (SBMTD)

SBMTD Match for Bus Replacement

A portion of the local match to replace 14 buses that are beyond their useful life. New buses will be 40-ft. 10 will be diesel, 4 will be electric. $ 123,829

Santa Barbara County Association of Governments City of Santa Maria

SMAT Capital Assistance - (2) Replacement Buses

Capital assistance for two bus replacements for Santa Maria Area Transit (SMAT) existing local transit services. The buses have exceeded the useful life benchmark of 12 years. These will be diesel buses. $ 226,004

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Santa Barbara County Association of Governments City of Solvang Rolling Stock

Replacement of two existing transit vehicles in FY 19/20 that have reached the end of their useful life. The buses will be Allstar cutaways gas powered. $ 791

Santa Cruz County Transportation Commission

Santa Cruz Metropolitan Transit District CNG Replacement Buses

Use Santa Cruz County Regional Transportation Commission (SCCRTC) and Santa Cruz METRO SGR apportionments to pay the local match for an FTA grant to buy up to nine CNG replacement buses $ 671,079

Shasta Regional Transportation Agency

Shasta Regional Transportation Agency CTSA Vehicle Replacement

Replace one Coordinated Transportation Services Agency vehicle. $ 51,044

Shasta Regional Transportation Agency Shasta County

Burney Express Vehicle Replacement

Replace two Burney Express vehicles. Vehicles to include ADA lift, bike racks, mobile data terminal, video equipment, and other technology consistent with planned Redding Area Bus Authority technology improvements. $ 200,000

Sierra County Local Transportation Commission

Sierra County Local Transportation Commission Transit Vehicle Replacement

Replace two transit vehicles that have reached their useful life limit $ 4,486

Siskiyou County Local Transportation Commission County of Siskiyou

Replacement of aging transit vehicles

All funds will be used to replace aging transit vehicles that no longer meet the needs of the agency. $ 62,270

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Stanislaus Council of Governments Stanislaus Council of Governments Regional Bus Stop Cleaning/Maintenance Project

Ongoing cleaning, maintenance, and repair of all transit stops and shelters in the region to help attract and retain ridership by maintaining transit stop facilities in a state of good repair. $ 727,995

Stanislaus Council of Governments City of ModestoRenovate Amtrak Station Restrooms

This project will repair and remodel the Modesto Amtrak Station restrooms $ 34,942

Stanislaus Council of Governments City of ModestoRenovate and expand the Transit Center

This project will renovate and expand the administrative office space at the Downtown Transit Center for Transit Administrative staff $ -

Stanislaus Council of Governments City of Modesto Renovate bus stops

This project will improve existing bus stops by rehabilitating concrete, replacing or placing bus stop amenities $ -

Stanislaus Council of Governments City of ModestoVideo Surveillance upgrade at the Transit Center

This project will upgrade the video surveillance system at the Transit Center, including replacing cameras and the communication system in addition to increasing the number of cameras on the property $ -

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Stanislaus Council of Governments City of ModestoVideo Surveillance upgrade on the MAX buses

This project will upgrade the video surveillance system on the Modesto Area Express (MAX) buses, including replacing cameras and the communication system to allow live look-in and automated download and archiving $ -

Stanislaus Council of Governments City of ModestoTwo-way radio system upgrade for the MAX system

This project will upgrade the two-way radio system for drivers and dispatchers on the MAX buses. It will be a digital system that will allow increased functionality. $ -

Tehama County Transportation Commission County of Tehama

Walnut Street Rehabilitation and ADA Access

Rehabilitation of the Red Bluff Transit Transfer Center to bring facility to ADA standards. Replace lighting, fixtures for public safety compliance, upgrade sidewalks and curbing. Repair striping in parking area and other facilities upgrade. $ 87,090

Trinity County Transportation Commission County of Trinity Replacement of rolling stock

Purchase (1) 25-passenger diesel bus for Trinty Transit. $ 19,162

Tulare County Association of Government City of Dinuba

Transit Fleet Maintenance & Repair Repair and maintain transit fleet $ 35,948

Tulare County Association of Government City of Porterville

Purchase One (1) Battery-Electric Paratransit Van

Purchase and operate one (1) 25 ft., Class 4, ADA compliant paratransit van. $ 88,652

Tulare County Association of Government City of Tulare

Replacement of One (1) Fixed-Route Bus

Replacement of One (1) Fixed Route Bus $ 94,354

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Tulare County Association of Government County of Tulare

Transit Operations Maintenance Facility

The project is for the construction of the Transit Operations and Maintenance Facility (TOMF) for Tulare County Area Transit (TCaT).The TOMF project will help maintain and repair the existing transit vehicle fleet. $ 205,071

Tulare County Association of Government

County of Tulare on Behalf of the City of Lindsay

Transit Operations Maintenance Facility

The project is for the construction of the Transit Operations and Maintenance Facility (TOMF) for Tulare County Area Transit (TCaT).The TOMF project will help maintain and repair the existing transit vehicle fleet. $ 17,246

Tulare County Association of Government City of Visalia

Purchase of One (1) Fixed-Route Bus Purchase of One (1) Fixed-Route Bus $ 228,578

Tulare County Association of Government

City of Visalia on Behalf of City of Exeter

Purchase of One (1) Fixed-Route Bus Purchase of One (1) Fixed-Route Bus $ 14,677

Tulare County Association of Government

City of Visalia on Behalf of City of Famersville

Purchase of One (1) Fixed-Route Bus Purchase of One (1) Fixed-Route Bus $ 14,941

Tulare County Association of Government City of Woodlake Transit Vehicle Maintenance

Maintenance of Woodlake's three (3) transit vehicles $ 10,465

Tuolumne County Transportation Council

Tuolumne County Transportation Council

Maintenance and rehabilitation of existing fleet

These funds will be used to cover the cost of Maintaining and or rehabilitating our existing transit fleet. $ 76,984

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Ventura County Transportation Commission Gold Coast Transit

Near Zero Engine Replacement (12 of 26 buses)

The “Near Zero Engine Replacement & Life Extension” projects includes engine replacement in (12 of 26) 2007 New Flyer buses w/ ISL G Near Zero NOx Near Zero emission engines & installation of electric fans. $ -

Ventura County Transportation Commission

Gold Coast Transit14 Near Zero Engine Replacement (14 of 26 buses)

Provide CMAQ Match for the “Near Zero Engine Replacement & Life Extension” projects includes engine replacement in (14 of 26) 2007 New Flyer buses w/ ISL G Near Zero NOx Near Zero emission engines & installation of electric fans. $ -

Ventura County Transportation Commission

Gold Coast Transit Preventative Maintenance

Conduct Preventative Maintenance on Gold Coast Transit District's fleet and service vehicles and facilities $ 49,790

Ventura County Transportation Commission Gold Coast Transit Service Vehicles

Replace up to 6 Service / Relief Vehicles. Vehicles will electric or hybrid-electric. $ -

Ventura County Transportation Commission City of Simi Valley Bus Stop Improvements

Purchase of new bus stop signage; purchase/replacement of amenities at existing bus stops; purchase/installation of new bus stops identified in Short Range Transit Plan. Up to 15 bus stops will be improved. $ 7,293

2017-18 State of Good Repair Approved Project List

Recipient Sub-Recipient Project Title Project Description

2017-18 Estimated total

SGR Award Amount

Ventura County Transportation Commission City of Simi Valley

Replacement of Fixed Route Vehicle 2-way Radios

Replacement of 2-way radios in fixed route vehicle fleet (11 vehicles) $ -

Ventura County Transportation Commission City of Simi Valley

Fixed Route Vehicle Wi-Fi Project

Modernization of 12 buses to install and activate Wi-Fi on the fixed-route vehicles for real time feed of video $ -

Ventura County Transportation Commission City of Thousand Oaks

Municipal Service Center(MSC) Fuel Island

Repair and upgrade of fuel island dispensers. $ 7,377

Ventura County Transportation Commission

VCTC - Corresponding to Southern California Regional Rail Authority

Metrolink Generation 1 Rail Car Rebuild/Overhaul

Refurbish and upgrade 14 Metrolink Bombardier Gen1 rail cars, to improve passenger comfort and safety, reliability, appearance, and upgrade to current standards $ 1,256,425

Totals: $ 104,759,536