    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    1

    NATIONAL HIGHWAY AUTHORITYSecretariat Section

    CONFIRMED MINUTES

    Subject:- 219th

    Meeting of the NHA Executive Board Held onJuly 24, 2012 at Islamabad

    1.  Introduction

    1.1. The 219th meeting of the Executive Board of the National

    Highway Authority was held at 1030 hours on Jul 24, 2012 at the

    NHA Head Office Auditorium, Islamabad. The Chairman NHA Syed

    Muhammad Ali Gardezi presided.

    1.2. All Members attended. List of participants is at Annex-A.

    1.3. The meeting commenced with recitation of verses from the

    Holy Quran and Urdu translation.

    2. Opening Remarks - Chairman NHA

    2.1. The Chairman extended warm welcome to the participants

    and thanked them for sparing time for NHA. The last meeting was

    held on Jun 11, 2012.

    2.2. The Chairman greeted Mr Zafar Abbas Lak, IG (NH&MP)

    on joining the Executive Board as its Member. The Board would

    definitely benefit from immense experience and knowledge that he

    brings with him.

    2.3. The Chairman intimated that the Member (Construction),

    Mr Aurangzeb Khan superannuated wef Jul 6, 2012 and in his place

    Mr Yousaf Ali Khan has been appointed. Previously, two Members

    (Construction) were positioned for the projects in North & South buthenceforth there would be only one Member (Construction).

    2.4. The Chairman also provided an update on the status of

    BOT concession for upgradation of 4-lane Karachi - Hyderabad Super-

    highway into 6-lane Motorway (M-9). The Concessionaire viz M/s Bina

    Puri Pakistan (Pvt) Ltd was to achieve financial close within 6 months

    ie by Jul 16, 2012 with a grace period of 45 days. The Concessionaire,

    having failed to achieve this target within the given date, has sought

    six months extension. The Concessionaire has, however, submittedproject design and attended to some other requirements.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    2/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    2

    2.5. M/s Bina Puri has been informed that the arguments put

    forward by them for grant of extension such as global financial

    situation, law & order status in Pakistan, traffic disruption on M-9and delay in RoW acquisition are not convincing enough. The global

    financial situation and law & order in Pakistan remain more or less

    the same as was the case prior to processing and signing of the BOT

    concession. Moreover, M-9 has not encountered any traffic disruption.

    Mutation of land in NHA’s favor is also more than 90% complete and

    the minor remaining land acquisition pertained to interchanges only

    and this is also in final stage. None of these issues could have

    hindered achievement of financial close, as contended.

    2.6. The request of M/s Bina Puri for extension of date for

    financial close has, therefore, been regretted. Alongside, they have

    been asked to furnish details of the efforts made by them for achieving

    the financial close, as NHA expected at least approval from the banks

    for committing finances for construction of M-9, whereas, actual funds

    could be released at a later stage.

    2.7. The JS (MoC) remarked in case M/s Bina Puri ultimately

    fail to achieve the financial close and NHA is compelled to terminate

    the concession agreement, it should be ensured that the matter is very

    wisely handled & that no claims accrue against NHA. The Chairman

    appreciated the suggestion and stated that NHA is fully alive to the

    situation. To ensure that NHA’s response is legally defensible, the

    Authority’s legal counsel and the Head IPDF (Infrastructure Development

    Facility) were also consulted before sending the same to M/s Bina Puri.

    2.8. The Chairman, dilating upon funding status, remarked

    that NHA was expecting release of additional funds / supplementary

    grant for its projects prior to close of FY 2011-12 but neither funds

    were made available by the GoP nor the loans expected from the

    Governments of Khyber Pakhtunkhwa and Balochistan materialized.

    However, NHA’s PSDP allocation of Rs 50.727 billion (Rs 26.124 billion

    FCC and Rs 24.602 billion LCC) for 2012-13 is quite sufficient and the first

    tranche for this year is expected to be released soon.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    3/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    3

    2.9. The Chairman, however, observed that project-wise

    allocation might be problematic. If certain projects were not moving at

    the desired pace but funds are released, NHA would not be able to

    divert funds for projects showing fair progress. Therefore, NHA istrying to convince the Planning Commission to review the decision

    regarding project-wise release of funds; however, NHA would ensure

    that each province gets funds equal to its allocation for FY 2012-13.

    2.10. The Chairman stated that in a recent Board meeting, the

    worthy Additional Finance Secretary had pointed out that it was of no

    use if the Annual Maintenance Plan is presented at the end of the

    financial year. In deference to the Board’s desire, the AMP 2012-13

    has been prepared at priority and will be presented in today’s meeting.With implementation of this plan and simultaneous commencement of

    Flood Emergency Rehabilitation Projects (FERP), the overall situation

    of NHA network in various regions would be considerably improved.

    2.11. The Chairman added that since the condition of NHA

    roads in Sindh is worst, NHA would be according special attention to

    that province. The fact that work on JICA assisted Sehwan - Ratodero

    ACW Project (N-55) and the ADB assisted Sukkur - Jacobabad ACW

    Project (N-65) is moving at quite a brisk pace will also help improve

    overall situation of NHA network in Sindh.

    2.12. The Chairman also talked about GMs Coord Conference;

    which was also witnessed by the Minister and Secretary MoC, held on

     Jul 12, 2012. The aim was to emphasize upon all Regional GMs that

    the roads need to be maintained at an optimum level to bolster NHA’s

    image as a developer & custodian of national highway network and

    that any compromise on quality and output would not be tolerated.

    2.13. The Chairman added that Monitoring Teams headed by

    reputed officers of caliber were constituted for overseeing operation &

    maintenance activities of each region and based on their feedback

    various corrective actions have been taken. One key decision taken

    during GMs Coord Conference was that tenders for all procurements

    will be issued on the 1st Thursday of each month and opened on the

    last Thursday of the month. On both occasions, the Head or a Member

    of the Monitoring Teams would be essentially present.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    4/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    4

    FORMAL BOARD PROCEEDINGS

    3. Agenda Items 

    3.1. The Secretary NHA stated that 16 x working papers were

    distributed in two volumes on Jul 10 & 20, 2012 respectively. Subject-

    wise distribution is as follows:-

    Matter No

    a. Minutes 2

    b. Award of Works 4

    c. Policy Issue 1

    d. Revised PC-I 2

    e. AMP 1

    f.  Toll Issues 2

    g. Financial Issue 1

    h. Admin Issues 3

    Total 16

    3.2. The Secretary NHA added that working papers on thefollowing subjects would be tabled as additional agenda items, if

    permitted by the Board:-

    A1.NHA’s Composite Schedule of Rates (CSR)-2011

    (Presentation by GM-Design)

    A2.Issuance of Tender Documents to National Logistic Cell (NLC)

    for NHA Projects

    A3.

    Bahawalpur Toll Plaza : Relief in payment of monthly

    installments due to financial losses

    3.3 The Chief (T&C) remarked that it is desirable if instead of

    a presentation, a formal working paper is circulated with the agenda

    for the next Board meeting on Item “A1”.

    3.4. At the end of meeting, working paper for only Item “A2”

    was presented and discussed because of paucity of time.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    5/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    5

    4. Agenda Item 1

    Confirmation of Minutes - 217th  Meeting of the

    Executive Board Held on Jun 4, 2012

    4.1. The Secretary NHA solicited confirmation of minutes of

    the 217th  Executive Board meeting held on Jun 4, 2012 conveying

    that the same were circulated on Jul 10, 2012 and no written

    comments / observations have been received from any Member.

    4.2. Minutes were confirmed with some amendments

    suggested by the Chief (T&C).

    Decision 

    4.3. The Executive Board confirmed minutes of 217th meeting

    held on Jun 4, 2012 with following amendments:-

    a.  In opening remarks, Para-2.6, line 6:-

    For: It was jointly decided by the Dy Chairman

    Planning Commission & the Minister for

    Finance that only

    Read: It was decided by the Annual Planning

    Coordination Committee that only

    b.  In opening remarks, Para-2.7, line 5:-

    For: NHA will have the authorization to re-

    appropriate funds from

    Read: NHA will now be required to re-

    appropriate development funds as per laid

    down procedure from

    c.  In Agenda Item 2 titled “Amicable Settlement of

    Dispute: Termination of Contract of Lowari Tunnel

    Project (LTP),” Para 5.26 (b):-

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    6/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    6

    For: Basis and detail of escalation predicted for

    next 5 years and average past projection

    of escalation.

    Read: Basis and cost of escalation required for

    balance work over the proposed future

    time frame and average trend of past

    escalation paid so far.

    Action By : Secretary NHA

    5. Agenda Item 2

    Confirmation of Minutes - 218th  (Special) Meeting of

    the Executive Board Held on Jun 11, 2012

    5.1. The Secretary NHA solicited confirmation of minutes of

    the 218th  (Special) Executive Board meeting held on Jun 11, 2012

    conveying that the same were circulated on Jul 10, 2012 and no

    written comments/observations have been received from any Member.

    5.2. Minutes were confirmed with one amendment.

    Decision 

    5.3. The Executive Board confirmed minutes of 218th  (Special)

    meeting held on Jun 11, 2012 with following amendment in Agenda

    Item 2 titled “Amicable Settlement of Dispute: Termination of Contract

    of Lowari Tunnel Project (LTP),” Para 3.13 (b):-

    For: Basis and detail of escalation predicted for next 5

     years and average past projection of escalation.

    Read: Basis and cost of escalation required for balance

    work over the proposed future time frame and

    average trend of past escalation paid so far.

    Action By : Secretary NHA

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    7/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    7

    6. Agenda Item 3

    Award of Works: Improvement / Rehabilitation of OldGT Road in Renala Khurd (Km 0+000 to 3+787.95)

    Introduction - Working Paper

    6.1. Directive / Deposit Work.

    a.  Subject project is based on Prime Minister’s Directive

    No 2624-A sent by the PM’s Sectt on Mar 9, 2011.

    b.  Project entrusted to NHA for implementation as

    “deposit work” vide PM’s Sectt (Public) UO No PMDIR

    /2141/DS(Imp)/PAW/10 dated Nov 2, 2011,

    6.2. Scope of Work (3.788 km).

    a.   Typical x-section (in fill):-

    Width Meter

    i. Carriageway : 7.3

    ii. Shoulders (both sides)  : 2.5

    b.  Following layers have been recommended to be laid

    over existing pavement layers:-

    Pavement Layer cm

    i. Asphalt Wearing Course : 5

    ii. Asphalt Base Course : 8

    iii. Water Bound Macadam (WBM) : 25

    c. 

    In sections (urban area)  where pavement has beenwashed away or is deteriorated at least 15 cm thick

    sub-base will be provided prior to lying of WBM.

    6.3. Source of Funding/PC-I/Engineer’s Estimate.

    a.   The Prime Minister has approved provision of Rs

    99.982 million as per cost estimates prepared by Pak

    PWD. As the project is a deposit work, the Cabinet

    Division will release this amount to NHA from PWP-II

    of PSDP.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    8/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    8

    b.   The Executive Engineer, Project Civil Division, Pak

    PWD, Sahiwal is responsible to provide the approved

    PC-I, which is awaited.

    c. 

    Estimated cost is Rs 98,735,315/- (CSR 2009 + 9.1%)excluding Bill No 7.

    6.4. Pre-qualification/Tendering Process.

    a.  PQ notice was published in press and uploaded on

    NHA & PPRA websites on Feb 16, 2012. Twenty two

    (22) firms applied and twelve (12) fulfilling the given

    criteria qualified.

    b. 

    Invitations for bid were issued to the pre-qualified

    firms. Eleven (11) firms purchased the bidding

    documents but only five (5) submitted technical and

    financial bids on scheduled date viz Apr 12, 2012.

    6.5. Summarized Status.

    Messers’ QualifiedDocumentsPurchased

    BidSubmitted

    a. CALSONS      

    b. Chaudhry     --

    c. FWO     --

    d. Luqman      

    e. NKC     --

    f. RMCC      

    g. SKB      

    h. Sachal   -- --

    i. SARCO-SIAC (JV)      

     j. SCC     --

    k. SMC     --

    l. Usmani     --

    Messers’ Legend  

    a. Ch Abdul Latif & Sons CALSONS

    b. Chaudhry Construction Chaudhry

    c. Frontier Works Organization FWO

    d. Luqman Brothers Construction Co Luqman

    e. Nisar Khan & Co NKC

    f. RMC Construction Co RMCC

    g. Saadullah Khan & Brothers SKB

    h. Sachal Engineering Works Sachal

    i. SARCO – SIAC (JV) SARCO-SIAC (JV)

     j. Standard Construction Co SCC

    k. Sultan Mahmood & Co SMC

    l. Usmani Associates Usmani

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    9/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    9

    6.6. Bid Opening. Bids were opened on Apr 12, 2012 by the

    Bid Opening & Evaluation (BO&E) Committee constituted in

    accordance with NHA Code in the presence of the bidders’ Reps.

    6.7. Financial Bids. Financial bids of qualified bidders wereopened in the presence of BO&E Committee on the same day.

    Following comparative position emerged vis-à-vis   the Engineer’s

    Estimate of Rs 98,735,315 (CSR-2009 + 9.1%) on all Bills except Bill No 7:-

    Lowest

    RankingContractor (M/s)

    Announced

    Bid (Rs)

    Corrected

    Bid (Rs)Variation

    1st RMCC 123,231,715 123,231,715 +24.81%

    2nd CALSON 133,880,764 134,029,264 +35.75%

    3rd SARCO-SIAC (JV) 144,522,958* 144,522,958 +46.38%

    4th  SKB 158,778,523 158,778,523 +60.81%

    5th  Luqman 169,324,562 169,324,562 +71.49%

    * Note. After 2 % rebate. Original bid was Rs 147,431,590.

    6.8. Recommendation. The Tender Acceptance Committee has

    recommended award of works to the lowest bidder M/s RMCC.

    6.9. Deliberations Concerning Financial Constraints.

    a.  Allocation of funds for this deposit work is Rs 99.982

    million but the lowest bid is Rs 123.231 million.

     Therefore, Letter of Acceptance shall be issued to the

    lowest bidder as per available funds only.

    b.  A Letter of Intent was issued to M/s RMCC about the

    funds constraint and consequent reduction in scope

    of work up to Rs 90 million. Balance Rs 9.982

    million to be kept for establishment and supervision.

    c.  M/s RMCC submitted an undertaking not to make

    any cost claim on NHA against the reduced scope of

    work and cost.

    6.10. Proposal. NHA Executive Board is requested to approve:-

    a.  Award of work for “Improvement / Rehab of old GT

    Road in Renala Khurd (Km 0+000 to 3+787.95)” to thelowest bidder M/s RMCC for Rs 123,231,715/-.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    10/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    10

    b.   The Letter of Acceptance for reduced scope of work

    limiting the contract price upto Rs 90 million will be

    issued initially and scope will be enhanced to

    original level on availability of balance funds.

    Board’s Deliberations

    6.11. The Member (Planning) presented details.

    6.12. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Planning Wing

    in respect of each observation is at Annex-B.

    6.13. The AS (Finance) observed that instead of piecemealimplementation, it is desirable if the total funds are arranged now and

    the project constructed in toto so that no escalation / litigation issues

    are encountered. Moreover, it also needs to be explained as to how the

    scope of work will be reduced.

    6.14. The Chief (T&C) made the following observations:-

    a.  Piecemeal implementation implies that the PM’s

    directive has not been properly followed and fullyobeyed. The scope be reduced only if the PM’s

    Secretariat is informed and consent obtained.

    b.  Why the single stage two envelopes system, which

    had proved quite successful in securing competitive

    bids, was not followed in this case? NHA should not

    be influenced by the contractors who pursue their

    own motives / benefits.

    c.  Since the PC-I is still awaited from Pak PWD, it

    should be ensured that the road is constructed

    according to NHA specifications and not the PWD

    specifications, which are less.

    6.15. The Member (Planning) clarified that an undertaking has

    been obtained from the contractor regarding reduction in scope of

    work due to non-availability of full funds and that no complications in

    this regard are envisaged. The scope has been reduced by decreasingthe project length proportionate to the availability of funds.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    11/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    11

    6.16. The Chairman stated that project scope will be enhanced

    as soon as balance funds are received. He clarified that NHA is

    receiving numerous instructions regarding execution of projects

    initiated by different MNAs / Senators and in each case the political

    dignitary is requested to arrange funds otherwise NHA would not beable to implement their scheme.

    6.17. The Chairman added that in this case too, the MNA

    concerned has been taken on board and advised to pursue the case

    for provision of balance funds with the relevant quarters and he is

    already working on this issue. He also quoted the example of Okara

    Bypass Interchange Project where the scope has been reduced from Rs

    297 million to Rs 21 million for an already awarded project because of

    non provision of requisite funds.

    6.18. The Chairman also stated that the observation that NHA

    should not be influenced by the contractors during the procurement

    process is very valid and all possible measures are being taken to

    ensure transparency, fair-play and maximizing competition.

    6.19. The Chief (NTRC) enquired as to who will approve the PC-I

    once it is finalized by Pak PWD. The Member (Planning) clarified that

    the tendered price will be communicated to Pak PWD Sahiwal forprocessing of the PC-I through their prescribed channels as is done for

    all deposit works.

    6.20. Matter was discussed and cleared.

    Decision

    6.21. The Executive Board approved award of work for

    “improvement / rehabilitation of old GT Road in Renala Khurd (Km

    0+000 to 3+787.95)” to the lowest bidder M/s RMC Construction

    Company at their quoted price of Rs 123,231,715/- (Rupees one hundred

    & twenty three million, two hundred & thirty one thousand, seven hundred &

    fifteen)  only; which is +24.81% the estimated cost of Rs 98,735,315/-

    (CSR-2009 + 9.1%) on all Bills except Bill No 7.

    6.22. In the initial phase, the scope of work would be limited to

    the contract price upto Rs 90 million and will be enhanced to original

    level at a later stage on availability of balance funds.

    Action By : Member (Planning)

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    12/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    12

    7. Agenda Item 4Review/Settlement of Frequent Issues Pertaining to“Form” of Bid Security & Performance SecurityDuring Procurement of Works

    Introduction - Working Paper

    7.1. Bid Security. It is kept to ensure seriousness of bidders

    during the bid validity period and for small period ahead (usually 28

    days) as a mandatory part of all procurements. It can be furnished by

    the bidders in following customary formats:-

    a.  Deposit at call.

    b. 

    Bank guarantee issued by a scheduled bank inPakistan.

    c.  Insurance bond issued by an insurance company at

    least having “AA” rating from PACRA/JCRA.

    Note. Another form known as “Bid Securing Declaration” is alsoused as an option in foreign funded projects.

    7.2. Performance Security. It is also mandatory part of all

    procurements kept to ensure performance of contractors during

    project execution. It can also be provided by the contractors in the

    customary formats described in “a” to “c” above.

    7.3. Executive Board’s Decisions. The issue of “Form” of bid and

    performance securities had been deliberated by the Board on several

    occasions since Sep-2009:-

    a.   The acceptance requirement of bid / performance

    securities was reduced from “AA” rated insurance

    companies to “A” including “A+”, “A-”, “A” & “A1” but

    reinsurance arrangement from “AA” rated companies

    (Ref: Executive Board’s 178th meeting of Sep 5, 2009).

    b.   The decision was reviewed and NHA did not allow

    securities of even “AA” rated insurance companies

    and restricted the bidders for securities/ bonds only

    from scheduled banks of Pakistan on NHA’s panel(Ref: Executive Board’s 201st meeting of Jan 20, 2011).

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    13/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    13

    c.   The CAP (Contractors Association of Pakistan) agitated the

    decision at “b” above pleading that it was against

    PEC (Pakistan Engineering Council)  Guidelines; which

    NHA is bound to follow. APCA (now CAP) also movedthe court-of-law against NHA’s decision (Ref: Executive

    Board’s 202nd meeting of Mar 17 & Apr 4, 2011).

    7.4. Preference of Bidders and NHA.

    a.  Bidders/contractors prefer to submit insurance bond

    mostly issued by insurance companies having “AA”

    rating being less costly.

    b.  NHA & most other employers prefer bank guarantee

    for both bid and performance securities because of

    better encashment mechanism. However, due to

    codal / legal requirements and, at times, to ensure

    competition in bidding process, the employers accept

    insurance bond as well.

    7.5. Points for Consideration.

    a.  NHA may devise a uniform and consistent policy in

    procurement process regarding acceptable “Form” of

    bid and performance securities after getting all

    stakeholders on board. The policy should not be

    fragile and discriminatory and proper legal cover be

    made available once the policy is finalized.

    b.   The Rules of PPRA, PEC & NHA Code be harmonized

    in the light of current bidding trends, bidders’

    attitude, prevailing practices / tactics of bidders,

    procedural shortcomings and the lessons learnt

    while implementing applicable procurement rules.

    c.   The principles of procurement process may be

    revisited while keeping in consideration the best

    interest of biggest stakeholder of procurement ie

    ‘Public.’ PPRA Rules should be deliberated andcommented in a legal manner.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    14/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    14

    d.  If Executive Board agrees to proposed amendments

    in clauses of PEC standard bidding documents

    pertaining to bid & performance securities, matter

    may be taken up with PEC officially for resolution.

    7.6. Rule Position.

    a.  PPRA Rules, 2004 are applicable on NHA for

    procurement of goods, works & services and are also

    part of NHA Code (Ref: Chapter 3, NHA Code 2005, Vol-I).

    b.  NHA Code also specifies that PEC bidding documents

    approved by ECNEC shall be used for procurement ofgoods, works and services.

    c.  ECNEC on Nov 12, 2007 decided that PEC standard

    bidding documents shall be applicable to

    procurement of all engineering goods, works and

    services and that the federal, provincial departments

    / organization and district governments will be

    responsible to implement this decision.

    d.  Implementation of PEC bidding documents has also

    been emphasized by P&D Division, PEC and MoC

    from time-to-time.

    7.7. Current Scenario.

    a.   The CAP in a meeting held with Secretary (MoC) on

    Feb 13, 2012 raised the conflict in bidding

    documents recommended by PEC & those prepared

    by NHA (P&CA Section) with special reference to

    provision of insurance guarantee.

    b.  Follow-up meeting was held between NHA and CAP

    on Mar 1, 2012 and, subsequently, clarifications

    were sought from PEC on Mar 27, 2012 regarding

    “Form” of bid and performance securities for single

    stage two envelope bidding process.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    15/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    15

    c.   The PEC on Apr 9, 2012 clarified as under:-

    i.  Bid security for single stage two envelope bidding

    can be submitted at the option of the bidder

    including at least “AA” rated insurance company.

    ii.  In case of performance security, Clause-10.1 of

    the Particular Conditions of the Contract (CoC)

    allows performance security from insurance

    companies also. Specific provision in particular

    conditions supersedes any similar provision

    either in general conditions or instructions to

    bidders or bid data sheet.

    iii.  If the employer finds any contradiction between

    instructions to bidders or CoC then priority will

    be those of harmonized document and such

    anomalies be brought to the notice of PEC for

    clarification.

    d.  It is mandatory for NHA to comply with the PEC

    Guidelines which now allows insurance bond from

    “AA” rated insurance companies both for bid andperformance securities. The earlier decision of NHA

    Executive Board (201st meeting of Jan 20, 2011) needs to

    be reviewed.

    7.8. Proposal. NHA Executive Board is requested to review the

    matter and revisit its earlier decision (201st meeting of Jan 20, 2011).

    Board’s Deliberations

    7.9. The Member (Planning) presented details.

    7.10. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Planning Wing

    in respect of each observation is at Annex-C.

    7.11. The VP-NESPAK observed that although NHA has to

    follow PEC Guidelines but it should keep on fighting for review of

    these instructions and seek deletion of insurance bond from the list ofadmissible securities.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    16/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    16

    7.12. The Chief (NTRC) remarked that the PEC is allowing

    insurance bonds rendered by 4 to 5 “AA” rated insurance companies

    and NHA may follows these instructions.

    7.13. The AS (Finance) opined that NHA has not made any

    particular recommendation for consideration by the Board in the

    working paper. As to what specific decision NHA is recommending

    and for what reason be elaborated.

    7.14. The Member (Finance) responded that the Board while

    deliberating on this subject (201st meeting of Jan 20, 2011) directed NHA

    not to accept securities of even “AA” rated insurance companies and to

    restrict the bidders for securities/ bonds only from scheduled banksof Pakistan to cover and safeguard risk of NHA’s construction &

    maintenance projects. However, the CAP is agitating the decision

    being against PEC Guidelines.

    7.15. The JS (MoC) remarked that the Reps of CAP visited MoC

    and pleaded that the Board’s decision is in contradiction to the

    provisions of PEC Guidelines; which should be followed. He observed

    that if submission of insurance bond is restricted to 4 or 5 “AA” rated

    insurance companies not much complications are envisaged.

    7.16. The AS (Finance) observed that the aim is to minimize

    financial risk. If NHA feels that sufficient risk is not covered, one odd

    item out of the available options for submitting security can be

    considered for exclusion.

    7.17. The Chairman explained that restricting the bid security

    to bank guarantee would amount to restricting healthy competition as

    the contractors react by creating cartels. However, for mobilization

    advance, security in the shape of bank guarantee only is accepted.

    7.18. The JS (MoC) enquired as to what procedure is followed

    for verification of bid securities.

    7.19. The Member (Finance) responded that guarantees are

    issued by the branches of the banks. Verification is sought from the

    bank’s head office; which have designated and empowered authorizedsignatories to render the required confirmation.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    17/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    17

    7.20. The matter was cleared after detailed discussion.

    Decision

    7.21. The Executive Board revisited its decision taken in the

    201st  meeting of Jan 20, 2011 and authorized NHA to accept

    insurance bonds issued by an insurance company at least having “AA”

    rating from PACRA / JCRA for bid & performance securities.

    7.22. For provision of mobilization advance, NHA will only

    accept bank guarantee issued by a scheduled bank of Pakistan.

    7.23. The Board, however, advised NHA to keep on persuadingthe PEC to disallow acceptance of insurance bonds for bid &

    performance securities for better risk management of NHA’s projects

    and schemes.

    Action By : Member (Planning)

    8. Agenda Item 5

    Revised PC-I of Makran Coastal Highway Project

    (MCHP, N-10)

    Introduction - Working Paper

    8.1. Introduction - Makran Coastal Belt.

    a.  Pakistan has about 1200 km long coastal belt along

    Arabian Sea. Portion from Hub in Balochistan upto

     Jiwani is called “Makran Coastal Belt.”

    b.   The Makran Coastal Highway Project (MCHP) was

    conceived as an all-weather link for Makran Coast.

    c.  MCHP provides an all-weather road to serve the

    population of Makran Coastal Belt and facilitates

    communication & trade by linking Karachi with

    Ormara, Pasni, Gwadar and Jiwani Ports.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    18/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    18

    d.  Aim was to provide basic amenities to the people

    living in far-flung coastal areas; boost up economic

    activity and connect Karachi with Gwadar Port.

    8.2. Introduction - Makran Coastal Highway (N-10).

    a.  MCHP starts from Shaikh Raj, approx 105 km north

    of Karachi on RCD Highway (N-25), and ends at

    Gabd near Pakistan-Iran border.

    b.  MCHP in the long run will also cater for traffic from

    Iran, Gulf and Central Asian Republics & facilitateinternational trade.

    8.3. Project PC-I.

    a.  NHA carried out design & feasibility studies in 1993-

    94 at an estimated cost of Rs 11.442 billion.

    b.  PC-I was updated on CSR-2000, with revised value of

    Rs 15.01 billion (Rs 11.498 billion LCC & Rs 3.511 billion

    FEC). ECNEC approved it on May 3, 2001.

    8.4. Construction Packages. For construction & management

    purposes, MCHP was bifurcated into four sections:-

    Sect 

    Route 

    Km 

    Start 

    Completion 

    I.  Lyari-Ormara  249.75   Jul-2000   Jun-2003 

    II. 

    Ormara-Pasni 

    Sub-section-I 

    50.96 

     Jan-2003 

    Dec-2004 

    Sub-section-II 

    51.12 

     Jan-2003 

    Dec-2004 

    Sub-section-III 50.03 

     Jan-2003 

    Dec-2004 

    III. 

    Pasni-Gwadar 

    137.20 

    Feb-2002 

    Feb-2004 

    IV.  Gwadar - Jiwani - Gabd 

    Gwadar - Pleri - Jiwani  67.80  Apr-2006  Sep-2008 

    Pleri - Gabd  42.39   Jan-2007   Jun-2011 

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    19/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    19

    8.5. Variations.

    Rs in Million

    Section Contract Financial

    Im act

    Revised

    a. Lyari - Ormara 3906.372 981.016 4797.388b. Ormara – Pasni 2146.601 478.774 2625.375

    c. Pasni – Gwadar 2888.761 (-) 247.162 2641.599

    d. Gwadar - Gabd 3508.804 (-) 353.004 3155.800

    Total 12450.538 769.624 13220.162

    8.6. Improvement and Rehabilitation Works.

    Rs in Million

    Section Contract Saving Reviseda. Lyari - Ormara (Pack-I) 374.258 (-)18.708 355.55

    b. Ormara - Pasni (Pack-II) 506.89 (-)305.131 201.759

    c. Two Minor Bridges 81.471 (-)1.247 80.224

    Extension of Phor Nai Bridge

    d. Phase-I 251.001 +9.037 260.038

    e. Phase-II 90 -- 90

    Total 1303.62 (-)316.049 987.571

    8.7. Land Acquisition Provision : Original & Revised PC-I.

    Rs in Million

    Sec Route Original Revised

    I. Lyari-Ormara 20.710 142.00

    II. Ormara-Pasni 15.734 175.00

    III. Pasni-Gwadar17.855

    728.80

    IV. Gwadar - Jiwani - Gabd

    Gwadar - Pleri - Jiwani 120.00

    Pleri - Gabd 70.00

    Total  54.299 1235.80

    8.8. Summarized Comparison of Scope/ Cost.

    Rs in Million

    Section Original PC-I Revised PC-I

    Executed Proposed

    a. Lyari-Ormara 5287.926 6247.436

    b. Ormara-Pasni 3952.544 3377.569 1697.00

    c. Pasni-Gwadar 2791.687 3673.040 1771.468

    d. Gwadar-Gabd 2977.210 4065.279

    Sub Total 17363.325 3468.468

    Gross Total 15009.367 20831.793

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    20/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    20

    8.9. Financing : Year-wise PSDP Allocation.

    Rs in Million

    F/Year  Allocation  Utilization 

    a. 

    2001-01 

    300 

    201,221 

    b.  2001-02  2,000  1,387.421 

    c.  2002-03  3,000  4,993.650 

    d.  2003-04  2,350  4,039.199 

    e.  2004-05  2,500  1,525.882 

    f.  2005-06  1,500  640.511 

    g.  2006-07  1,125  1,078.877 

    h.  2007-08  1,800  1,095.626 

    i.  2008-09  1,000  1,094.130 

     j.  2009-10  500  682.332 

    16,075  14,738.849 

    8.10. Other Costs / Project Life.

    a.  Annual recurring operation/ maintenance cost (pkm):-

    Section  Rs in M 

    i.  Lyari – Ormara  0.214 

    ii.  Ormara – Pasni  0.200 

    iii.  Gwadar – Pak Iran Border (Jiwani)  0.276 

    b.  Periodic maintenance cost is same as above.

    c.  Pavement life is ten years and structures 50 years.

    8.11. Proposal. The Executive Board is requested to recommend

    the revised PC-I of MCHP (N-10) to CDWP/ECNEC for approval by

    endorsing any one of the following options:-

    a. 

    Revised PC-I costing Rs 20.832 billion. It entails+38.79% variation vis-à-vis  the approved PC-I cost of

    Rs 15.009 billion.

    OR

    b.  Revised PC-I costing Rs 17.363 billion by deleting

    additional works of Rs 3.469 billion to be carried out

    at a later stage through a separate PC-I considering

    the paucity of funds and law & order situation along

    the project area. It entails +15.68% variation vis-à-vis  the approved PC-I cost of Rs 15.009 billion.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    21/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    21

    Board’s Deliberations

    8.12. The Secretary NHA introduced the proposal with remarks

    that the Executive Board had decided (201st meeting of Jan 20, 2011) to get

    the revised PC-I of MCHP and related aspects scrutinized through a

    Sub-committee of the Board comprising Senior JS (MoC), Chief (NTRC)

    and VP-NESPAK. However, the Sub-committee could not make any

    headway because two incumbents of the post of Senior JS (MoC) were

    transferred and 2 x Chief (NTRC) retired within a short span of time.

    8.13. Matter is awaiting finalization since Jan-2011. Meanwhile,

    cost of the PC-I has been rationalized from Rs 20.832 billion to Rs

    17.363 billion. Therefore, the JS (MoC) has opined that it is desirable

    if the issue is reviewed afresh by the Executive Board.

    8.14. The JS (MoC) added that due to delay in finalization of the

    revised PC-I, certain Audit Paras of MCHP, likely to be soon debated

    by the PAC, are awaiting disposal.

    8.15. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Construction

    Wing in respect of each observation is at Annex-D.

    8.16. The GM (MCHP) presented details. In response to various

    queries, he stated that the expenditure so far incurred on MCHP is

    less than Rs 15 billion, as explained below:-

    Description Rs in M

    a. Total Work Done 13,424.923

    b. Escalation 933.987

    c. Consultancy Cost 116.495

    d. Land Acquisition 175.025

    e. Utilities Re-location 5.463

    f. Establishment 290.592Total 14,946.485

    8.17. The GM (MCHP) further conveyed that major contributory

    factors for revision in cost are:-

    a.  Increase in land acquisition cost from Rs 67 million

    to Rs 1,236 million (+8.24% of total original PC-I cost).

    b.  Increase in other costs / scope is Rs 1117 million

    (+7.44% of original PC-I cost).

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    22/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    22

    c.   Total increase from original PC-I is Rs 2,353 million

    ie +15.68%.

    8.18. The GM (MCHP) added that the cost of the revised PC-Ihas been rationalized by deleting following additional works, but, he

    would request that the matter may be reconsidered and these works

    also recommended because of their importance:-

    Sec 

    Routes 

    Rs in M 

    I. Ormara-Pasni

    Basol River remedial works 272.800

    Shadi Kaur Bridge works & road realignment 1424.200

    II. Pasni-Gwadar

    36 km re-alignment of MCH required by GDA/Govt of Balochistan

    1771.468

    Total  3468.468 

    8.19. The JS (MoC) remarked that an independent PC-I may be

    processed for the additional works.

    8.20. The Chief (T&C) observed that the additional works of

    Section-I are of important / sensitive nature & can not be overlooked.

    He would, therefore, recommend inclusion of additional works in the

    revised PC-I for the matter to be decided by CDWP / ECNEC.

    8.21. The AS (Finance) observed that constructing MCHP very

    close to coastline in areas prone to flash floods perhaps was not a wise

    decision. Since it is essential that MCHP always remains operational

    at all times, it is desirable if additional works required for the purpose

    are undertaken expeditiously.

    8.22. The Chairman provided details of various ongoing projects

    on Gwadar - Turbat - Hoshab (M-8), Hoshab - Panjgur - Nag - Basima

    - Sorab (N-85) and Khuzdar - Ratodero (M-8) and stated that all these

    projects are lingering on for the past quite some time but completion

    is not in sight. Work on Gwadar - Turbat - Hoshab (M-8) and Hoshab -

    Sorab (N-85) is suspended for the past around 3 years because of

    security challenges and paucity of funds. Prudence demands that no

    additional works be committed on MCHP till completion of ongoing

    linkages for Gwadar Port.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    23/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    23

    8.23. The VP (NESPAK) added that damages on coastal roads do

    occur and since traffic on MCHP is moving and occasional disruptions

    because of abnormal rains, flash floods and cyclones are not for

    lengthy durations, the additional works can be attended to separately.

    8.24. After lengthy deliberations, the PC-I was recommended for

    approval without additional works.

    Decision

    8.25. The Executive Board recommended the revised PC-I of

    Makran Coastal Highway Project (N-10) costing Rs 17.363 billion to

    the CDWP/ECNEC for approval. It entails +15.68% variation vis-à-vis  the approved PC-I cost of Rs 15.009 billion.

    8.26. The Board decided that the additional works of Rs 3.469

    billion, as detailed in Para-8.18 above, will be carried out at a later

    stage through a separate PC-I considering the paucity of funds and

    law & order situation along the project area or through a second

    revision of this PC-I at an appropriate time.

    Action By : Member (Construction) & Member (Planning)

    9. Agenda Item 6

    Award of Toll Plazas Through Negotiated Tendering

    Introduction - Working Paper

    9.1. Preliminary Facts.

    a.  Under Section-10 of the NHA Act, 1991 (amended 2001)

    NHA is empowered to levy and collect toll tax; which

    is the main sources of revenue generation for

    maintenance of the national highway & motorway

    network. NHA has installed a number of toll plazas

    on various sectors of its network to collect revenue

    from the commuters to provide smooth and hazard

    free traffic flow.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    24/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    24

    b.  Upkeep and maintenance of NHA network require a

    source of continuous funding based on international

    highway safety standards. To coup with continuous

    expanding requirements, it is imperative to improve

    upon this source of revenue generation by bringingun-tolled roads to toll network. This on the one hand

    will meet future funding requirements, and, on other,

    inculcate a tolling culture.

    c.  Although, the masses in general have accepted toll as

    a necessity for using a well maintained road, still in

    certain cases severe public resentment was

    encountered. These included following locations:-

    i.  Pabbi Toll Plaza (N-5), District Nowshera, KP.

    ii.   Jand Toll Plaza (N-80), District Attock, Punjab.

    iii.  Mansehra Toll Plaza (N-35), KP.

    9.2. Pabbi Toll Plaza (N-5), District Nowshera, KP.

    a.  NHA previously attempted to install a toll plaza at

    this point in the year 2000 through NLC, but could

    not succeed due to severe public resentment.

    b.  Local surveys & consultations indicate severe

    resistance from local commuters and inter-regional

    transporters, if any such attempt is made again. It is

    considered advisable to adopt a pragmatic result

    oriented approach for generating toll revenue.

    c.   Tentative reserve price based on 1 day traffic count is

    Rs 161.1 million per annum.

    9.3. Jand Toll Plaza (N-80), District Attock, Punjab.

    a.  Previous two attempts made in 2004 & 2006 to

    install a toll plaza at this point attracted severe

    public agitation.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    25/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    25

    b.  Matter cannot be left unattended and there is a need

    to engage local influential’s who could mange public

    sentiment to avoid / minimize resentment.

    9.4. Mansehra Toll Plaza (N-35), KP.

    a.   This toll plaza established in Mar-2000 was initially

    run by FWO but, subsequently, handed over to the

    District Govt, Mansehra (DGM) on 30% sharing

    basis. In 2004, the DGM, on expiry of term contract,

    sought enhancement of its share to 50% of the net

    income and also proposed withdrawal of

    enhancement in toll rates at this point.

    b.  Negotiations with DGM were not fruitful and NHA

    awarded the toll O&M contract through open

    bidding. However, the law & order situation

    worsened resulting in murder of a Police officer,

    while one other suffered serious injuries.

    c.  NHA agreed to re-fix the DGM share as 50%, but the

    demand to withdraw enhancement in toll rates was

    not endorsed by the Executive Board on Aug 24,

    2008. The Board also directed to relocate the toll

    plaza at a place where such like situation could be

    avoided in future.

    d.   The DGM went into litigation against NHA and toll

    operation could not re-commence. The Civil Court

    Mansehra granted status quo   against establishment

    of toll plaza and the matter remained in lengthy

    litigation. Nevertheless, NHA has recently succeeded

    in getting the stay order vacated at the level of

    Supreme Court of Pakistan.

    e.   Tentative reserve price calculated for original location

    is Rs 75.7 million, while at the newly selected place

    in District Abbottabad Rs 56.3 million per annum. If

    the location is further changed, tentative reserve

    price will further vary.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    26/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    26

    9.5. Exploration of Non-Traditional Approach.

    a.  It is apprehended that if services of operation &

    management (O&M) contractors for above toll plazas

    are procured through competitive bidding, unendinglitigation might jeopardize the procurement process.

    b.  Since establishment of toll plazas at the above

    locations is essential to generate precious revenue for

    maintenance, it was felt prudent to explore non

    traditional ways.

    c.  It is considered advisable to adopt the course of

    negotiations for award of these toll plazas to localinfluential’s, who, on one hand could put a check on

    resistance from the general public and, on the other,

    successfully operate the toll plaza by providing some

    relief to local commuters under own arrangement.

    9.6 Bids Received. Summarized status of bids (net revenue per

    annum) for O&M of the three toll plazas in question filed by certain

    interested parties:-

    Rupees in Million

    Company(M/s)

     Toll Plaza Traffic Count Tentative

    Reserve PriceOfferedPrice

    a.AfridiOperators

    Pabbi(N-5)

    Near AzakhelPark (2011)

    161.1 60

    b.WasimBukhariBuilders

     Jand(N-80)

    Km 80(2010)

    13.9 24.05

    c.

    Sardar

    & Co

    Mansehra

    (N-35)

    Km 63 & 90

    (2008)

    75.7 &

    56.3 26.4

    9.7. Negotiations by the Committee of Officers.

    a.  A Committee of officers headed by GM (Operation)

    and comprising Director (OMU), Director (P&CA),

    Director (RAMS) and DD (P&R) deliberated upon all

    the aspects of negotiated tendering in relaxation of

    normal bidding procedure provided in PPRA Rules viz

    auction through advertisement in the press onprescribed terms & conditions.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    27/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    27

    b.   The Committee opined that in the peculiar

    circumstances encountered on the three locations in

    question, adopting regular procedure will further

    worsen the situation. This is also supported by the

    PPRA Rule-42(d), which provides for negotiatedtendering, when processing through normal

    procedure is not feasible.

    c.   The Committee decided to negotiate to bring the bids

    at a reasonable level as it was considered advisable

    to award the O&M of above toll plazas to local

    influential’s, capable of handling adverse situations,

    and thwarting resistance, on interim basis till toll

    culture is inculcated and masses enlightened of thelong term benefits of paying toll.

    9.8. Revised Bids. Three meetings were held with interested

    parties. First meeting took place in Feb-2012 and the second in Mar-

    2012. However, the bidders could not be convinced to enhance bids.

    Nevertheless, in the final meeting held on May 16, 2012, the bidders

    agreed to enhance their bids as under:-

    Rupees in Million

    Company(M/s)

     TollPlaza

     TentativeReserve Price

    OfferedPrice

    a. Afridi OperatorsPabbi(N-5)

    161.1 100

    b.Wasim BukhariBuilders

     Jand(N-80)

    13.9 26.05

    c. Sardar & CoMansehra

    (N-35)75.7 & 56.3 35

    9.9. Points to Note.

    a.  Award of toll plazas through negotiated bidding will

    not meet the financial expectations, as the bidders

    will have to meet allied expenses apart from

    operational expenditure viz relief to local commuters

    and arrangements with the local administration and

    political elites who will be in a much better position

    to tackle the issue of resistance by local populace/

    commuters.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    28/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    28

    b.   The above mentioned bidders are already working

    with NHA for the past quite some time. They are well

    acquainted with the task and possess the capability

    to operate toll plazas. They are financially sound and

    have so far not defaulted in payment of revenue.

    c.  Presently, NHA is generating zero revenue from the

    above three stations. Award of toll plazas through

    negotiated tendering will start revenue generation

    though less with immediate effect and this will help

    promote toll culture among local masses and prove

    beneficial in the long run. Once toll culture is fully

    ingrained, NHA will be in a better position to award

    toll plazas through open bidding.

    9.10. Proposal. The NHA Executive Board is requested to

    approve award of the O&M of the three toll plazas in question on

    negotiated tendering at the rates and to the bidders mentioned in

    Para-9.8 for the period ending Jun-2013.

    Board’s Deliberations

    9.11. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Operation Wing

    in respect of each observation is at Annex-E.

    9.12. The Member (Operation) presented details.

    9.13. The Chairman added that many key sections of NHA

    network taking significant traffic are yet not covered through toll. NHA

    intends to utilize the influence & authority of local prominent figures

    to inculcate toll culture while also earning some revenue. The

    individuals with political background can mute the hue & cry which israised when NHA attempts to award toll O&M contracts through open

    competition.

    9.14. The Member (Operation) remarked that the toll O&M

    contracts in question are proposed to be assigned till Jun-2013 only

    and, around Mar-2013, these toll plazas would be advertised for

    award on open tendering basis. He added that in a similar nature

    case, the Executive Board had allowed identical dispensation (189th -

    Special Board meeting of Apr 24, 2010)  for award of O&M contracts for anumber of toll plazas in Balochistan through negotiation.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    29/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    29

    9.15. The JS (MoC) observed that NHA should not succumb to

    pressure from the public and road users to circumvent requirements

    of PPRA. He also felt that the traffic counts mentioned in the proposal

    were outdated.

    9.16. The Chairman responded that NHA needs to follow a

    pragmatic approach to counter opposition faced at selected locations.

    NHA is not facing any such problem at locations where toll culture is

    deep rooted. On the existing toll plazas, normally only locals resist

    toll and NHA compensates them by issuing frequent user passes.

    9.17. The Member (Ops) added that traffic counts do not matter

    much as the guaranteed revenue figures have been agreed to throughnegotiation. The prospective toll operators had offered much lower

    figures but the bids have been got revised after hectic effort.

    9.18. The VP (NESPAK) enquired whether FWO and NLC were

    also consulted. He also apprehended that private toll operators

    assigned the toll O&M responsibility based on their ability to use

    influence might exploit the road users through over-charging.

    9.19. The Member (Ops) responded that FWO and NLC were not

    approached before but can be consulted now. However, it needs to be

    highlighted that FWO were previously operating the Mansehra Toll

    Plaza but backed out after public outcry. Moreover, track record of

    FWO is not so promising as they are holding NHA’s toll revenue

    generated from the Motorways (M-1, M-2 & M-3) sine Jul-2009 and

    are already defaulter of more than Rs 5.75 billion.

    9.20. The Member (Ops) further explained that exploitation of

    road users will not be allowed because approved toll rates would be

    prominently displayed and NHA functionaries would ensure regular

    monitoring of toll operations.

    9.21. The Board discussed the matter and decided that in the

    first instance NHA would invite NLC to check if they would be

    interested in operating the three toll plazas in question at the

    guaranteed revenue rates significantly higher than that agreed with

    private toll operators. In case, NLC refuses to offer higher guaranteedrevenue, the bids discussed in Para-9.8 would be accepted.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    30/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    30

    Decision

    9.22. The Executive Board approved award of toll O&M

    contracts for three toll plazas in question on negotiated tendering atthe rates and to the bidders mentioned in Para-9.8 for the period

    ending Jun-2013.

    9.23. The Board, however, decided that in the first instance

    NHA would offer these toll plazas to NLC to check if they would be

    interested in toll O&M of these toll plazas at the guaranteed revenue

    rates significantly higher than that agreed with private toll operators.

    9.24. In no case the toll O&M contracts will be extended beyond Jun-2013 and, towards this end, NHA would ensure timely action for

    award of these toll plazas through open competitive bidding.

    Action By : Member (Operation)

    10. Agenda Item 7

    Rationalization of Toll Rates on Satra Mile - Lower

    Topa Expressway

    Introduction - Working Paper

    10.1. Introduction. Current schedule of toll rates on national

    highways was implemented in pursuance to the decision of NHA

    Executive Board (206th meeting of Aug 11, 2011) wef Sep 1, 2011:-

    Vehicular Category Toll (Rs)

    a. Car, Jeep, Land Cruiser, Pajero, Tractorwithout Trolley & Equivalent

    25

    b. Wagon upto 24 seats / Coaster / Mini Bus /

    Mazda / Chassis upto 24 seats and Mini Truck

    35

    c. Bus / Coach / More than 24 seats 75

    d. 2 / 3 Axle Truck 90

    e. 4/5/6 Axle Truck (Articulated) 175

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    31/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    31

    10.2. Satra Mile - Lower Topa Expressway.

    a.  NHA has constructed the Satra Mile - Lower Topa

    Expressway at a huge cost. Although this low

    gradient expressway is preferentially used by localand foreigner visitors and tourists, NHA has kept toll

    rates at par with national highways.

    b.   This facility of international standard traverses

    difficult terrain and is exposed to vagaries of nature

    including frequent landslides. Keeping traffic moving

    on this facility at all times requires additional

    resources and continuous effort. Due to heavy traffic

    load, the ratio of general wear & tear increases, andthis requires additional funds for maintenance.

    c.   The aspect of public and highway safety on this road

    is also of prime importance as traffic density

    increases abnormally in peak tourist season and on

    weekends, as the majority of commuters plying on

    this road are visitors/ tourists on recreational trips.

    d. 

    Improved highway safety for ensuring traffic

    discipline requires additional resources to upkeep

    and maintain this expressway as an all whether road

    and thus the need for toll rationalization.

    10.3. Old Murree Road. The old Islamabad - Murree Road is a

    2-lane single carriageway of high gradient and Punjab Govt is

    charging Rs 45 for each light vehicle for upward journey only.

    10.4. Proposal. Toll rates on Satra Mile-Lower Topa Expressway

    may be rationalized by doubling the existing rates for all categories of

    vehicles. The Executive Board’s approval is requested.

    Board’s Deliberations

    10.5. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Operation

    Wing in respect of each observation is at Annex-F.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    32/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    32

    10.6. The Member (Operation) presented details.

    10.7. The Chairman added that the proposed rationalization of

    toll rates is the need of the hour. The Minister (C) and the Secretary

    (C) have also directed necessary action to this effect.

    10.8. The VP-NESPAK remarked that the need for toll

    rationalization is appreciated but the increase should be gradual so

    that it is absorbed by the road users without much ado. Therefore, the

    proposed increase may be actualized in two phases of 50% increase in

    each phase staggered over a considerable length of time (say one year).

    10.9. The Chairman, however, stressed that the proposal may

    be approved as submitted because the road traverses difficult terrainand is very heavy on maintenance and the cost is regularly increasing.

    Matters concerning this road were deliberated with the local MNA, Mr

    Shahid Khaqan Abbasi also in the context of RoW management,

    removal of encroachments and issues concerning villages’ located en-

    route and he also suggested rationalization of toll rates.

    10.10. Matter was discussed and cleared by the Board.

    Decision

    10.11. The Executive Board approved rationalization of toll rates

    on Satra Mile-Lower Topa Expressway (E-75), as follows:-

    Vehicular Category Existing Proposed

    a. Car, Jeep, Land Cruiser, Pajero,

     Tractor without Trolley & Equivalent

    25 50

    b. Wagon upto 24 seats / Coaster /Mini Bus / Mazda / Chassis upto

    24 seats and Mini Truck

    35 70

    c. Bus / Coach / More than 24 seats 75 150

    d. 2 / 3 Axle Truck 90 180

    e. 4/5/6 Axle Truck (Articulated) 175 350

    Action By : Member (Operation)

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    33/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    33

    11. Agenda Item 8Raising of Funds by Floating Rupee DenominatedSukuk in Domestic Capital Market Against Islamabad- Peshawar Motorway (M-1)

    Introduction - Working Paper

    11.1. M-2 (International). The Executive Board (124th Special

    meeting of Jan 6, 2005)  had passed a “Resolution” regarding sale

    transaction of certain portion of land comprised in Lahore - Islamabad

    Motorway (M-2) with Pakistan International Sukuk Coy Limited, a

    public limited company incorporated under the laws of Pakistan and

    wholly owned by GoP to raise funds by floating dollar-denominated

    Sukuk in international capital market. The GoP raised USD 600

    million through this exercise.

    11.2. M-3 (Domestic). Another “Resolution” was passed by the

    Board (179th meeting of Sep 19 & 30, 2009)  for sale transaction of certain

    portion of land comprised in Faisalabad - Pindi Bhattian Motorway

    (M-3) with Pakistan Domestic Sukuk Coy Ltd to raise funds by floating

    rupee-denominated Sukuk. The GoP raised Rs 42 billion.

    11.3. M-2 (Domestic). A third “Resolution” was passed by the

    Board (208 meeting of Oct 19, 2011) for sale transaction of any or certain

    portion of land comprised in Motorway (M-2) with Pakistan Domestic

    Sukuk Coy Ltd to raise funds by floating rupee-denominated Sukuk.

     The GoP had set a target of raising Rs 50 billion.

    11.4. Proposal. The Finance Division vide letter No F4(21)EF

    (C.III)/2009 dated Jun 15, 2012 intimated that the government is

    considering to raise new funds by issuing a Sukuk against the

    underlying assets of Islamabad - Peshawar Motorway (M-1). It has also

    been confirmed that this Sukuk transaction would not involve any

    financial, legal or administrative implication for NHA.

    11.5. Acknowledgment. Earlier, the Finance Division vide UO

    Note No 4(21)EF(C.III)/2009 dated May 28, 2012 had acknowledged

    the cooperation extended by NHA from time-to-time for raising funds

    from the international and domestic capital markets by floating

    Sukuks while also conveying that they are considering adding new

    assets like Motorway (M-1) & Makran Coastal Highway (N-10) to build

    additional capacity for raising funds through Sukuk transactions.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    34/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    34

    11.6. Views NHA. NHA has no objection to the proposal.

    11.7. Proposal. Following Members Executive Board may be

    authorized to enter on behalf of NHA into the process of saletransaction of certain portion of land comprised in M-1 with Pakistan

    Domestic Sukuk Coy Ltd for consideration & approval by the Board:-

    a.  Mr Abdul Khaliq, Add’l Secretary (Finance Division).

    b.  Mr Shoaib Ahmad Khan, Member (Finance) NHA.

    c.  Mr Sabir Hasan, Member (Planning) NHA.

    Board’s Deliberations

    11.8. The Secretary NHA remarked that this proposal was

    initiated at the behest of the Finance Division and since that Division

    wanted expeditious action in the matter; approval of the Executive

    Board was solicited on circulation basis. Whereas, all the Members

    accorded consent, the AS (Finance) and JS (MoC) desired that the

    issue may be debated formally in the Board meeting.

    11.9. The Member (Finance) presented the details.

    11.10. The AS (Finance) remarked that he has no specific

    comment to offer and the reason he did not endorse his signatures

    earlier was that he had not been able to consult the relevant case file

    in the Finance Division. He would appreciate if the Member (Finance)

    NHA could separately provide him relevant details.

    Note. Subsequent to the Board meeting, the Member (Finance) provided relevant

    details to the AS (Finance) and he has accorded his clearance.

    11.11. The Chief (T&C) suggested that nomination of Executive

    Board Members to Pakistan Domestic Sukuk Coy Ltd instead of by

    name may be made by designation so that the Board’s clearance may

    not be required in case of posting transfer of any officer. Moreover, the

    said officers may also perform this function for any future proposals of

    similar nature, if & when initiated by the Finance Division regarding

    sale transaction of NHA land with Sukuk Bonds.

    11.12. Matter was discussed and cleared.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    35/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    35

    Decision

    11.13. The Executive Board approved sale transaction of rupee

    denominated Sukuk in Domestic Capital Market against Islamabad -Peshawar Motorway (M-1) with Pakistan International Sukuk Coy Ltd

    and authorized the following Board Members to enter into the process

    of sale transaction of certain portion of land comprised in M-1:-

    a.  Additional Secretary (Budget, Finance Division).

    b.  Member (Finance) NHA.

    c.  Member (Planning) NHA.

    11.14. The Board also decided that the above officers will alsoperform this function for any future proposals of similar nature, if &

    when initiated by the Finance Division regarding sale transaction of

    NHA land with Sukuk Bonds.

    Action By : Member (Finance)

    12. Agenda Item 9Writing-Off Loss Sustained by NHA : Theft of ToyotaDouble Cabin No KN-2031, Model 2004

    Introduction - Working Paper

    12.1. Vehicle No KN-2031, Toyota Double Cabin, Model 2004

    was detailed with Mr Abdul Qadoos Shaikh, Ex-Project Director (S-R)

    Larkana for performing official duties. It was snatched on Jul 24,

    2009 at about 0830 hours by unknown armed persons from the driver

    while he was waiting in the parking area of the officer’s residence near

    Regional Office, Sukkur. The dacoits kidnapped the driver also and

    took him along with vehicle.

    12.2. The officer rushed to the office of DPO Sukkur who

    passed orders of “Naka Bandi”   at outlets of Sindh Province border

    with Balochistan. FIR was also lodged by the officer in the concerned

    Police Station Sukkur. However, the police have so far not succeeded

    in recovering the vehicle.

    12.3. The vehicle was not comprehensively insured being 2004

    model as only new vehicles are comprehensively insured that too onlyfor 3 years as per NHA Motor Vehicle Use Policy.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    36/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    36

    12.4. An Inquiry Committee headed by Mr Basharat Hussain,

    PD NHA, Larkana was constituted. The inquiry report furnished by

    him was found to be full of flaws and lacuna.

    12.5. A fresh inquiry was assigned to Mr Abdul Rauf Sheikh,

    Director (Monitoring) NHA, Karachi. He concluded that the officer was

    not at fault and declared him innocent as the loss was accidental in

    nature and nothing adverse against the officer was observed. The

    incident occurred due to overall law & order situation in the country.

    12.6. Since no action is required to be taken against any NHA

    official, it is proposed that entire loss ie reserve price of the vehicle of

    Rs 1,674,036/-, as calculated/vetted by Finance Wing, may be writtenoff by NHA Executive Board, being the competent forum as per Table-

    XI to Chapter-10 of NHA Code.

    Board’s Deliberations

    12.7. The Member (Admin) presented details.

    12.8. The JS (MoC) remarked that NHA is seeking approval for

    writing-off loss of vehicles in certain cases and in few other cases

    recoveries are being affected from the officers / officials who lost the

    vehicle. The criteria / SOPs on the subject need to be explained.

    12.9. The Member (Admin) clarified that write-off or recovery

    action depends on the outcome of the formal inquiry. Matter is

    processed in accordance with the conclusion drawn and

    recommendation made by the Inquiry Officer/Committee. If the

    conclusion is that the loss of vehicle is also attributable to negligence

    by the officer or the driver concerned, the Inquiry Officer/Committee

    recommends full or partial recovery and the action is taken

    accordingly. If the loss is not attributable to the officer or the driver

    concerned, write-off of the loss is recommended.

    12.10. The Member (Admin) added that no case of theft of

    vehicles is submitted to MoC. However, if recovery action is ordered,

    the officer or the official concerned do submit appeals to the MoC for

    review of NHA decision.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    37/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    37

    12.11. Matter was discussed and it was opined that the element

    of bias on the part of the Inquiry Officer/Committee cannot be ruled

    out. To ensure that no injustice is done, NHA should bring all cases

    of theft of vehicles to the Executive Board for info in case the loss is

    being recovered from the officer or the driver concerned or for approvalif the loss is proposed to be written-off.

    Decision

    12.12. The Executive Board approved writing of the loss of Rs

    1,674,036/- due to theft of Theft of Toyota Double Cabin No KN-2031,

    Model 2004.

    12.13. Henceforth, NHA will bring all cases of theft of vehicles to

    the Executive Board for info in case the loss is being recovered from

    the officer or the driver concerned or for approval if the loss is

    proposed to be written-off.

    Action By : Member (Admin)

    13. Agenda Item 10Extension in Contract Appointment of Lt Col (Retd)Abid Ali Khan, Director (Engr, BS-19)

    Introduction - Working Paper

    13.1. Lt Col (Retd) Abid Ali Khan was appointed on contract as

    Director (Engr, BS-19) after fulfilling all codal formalities wef May 3,

    2010 against a PC-I post of Lowari Tunnel Project completion date of

    which is Mar-2014. His contract tenure expired on May 2, 2012.

    13.2. The services of Lt Col (Retd) Abid Ali Khan are required on

    continued basis, keeping in view project needs. Therefore, NHA

    recommends extension in his contract wef May 3, 2012 to Mar 31,

    2014. His performance in 2011 & 2012 has been rated as “good.”

    13.3. Approval of the Executive Board is solicited.

    Board’s Deliberations

    13.4. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Admin Wing in

    respect of each observation is at Annex-G.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    38/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    38

    13.5. The Member (Admin) presented details.

    13.6. Matter was discussed & cleared by the Board.

    Decision

    13.7. The Executive Board approved extension in the contract

    appointment of Lt Col (Retd) Abid Ali Khan, Director (Engr, BS-19) wef

    May 3, 2012 to Mar 31, 2014.

    Action By : Member (Admin)

    14. Agenda Item 11

    Fixation of Pay & Allowances in BS-19 & Payment ofArrears from the Date of Deferment to Mr Abdul

    Hameed Qureshi, Retired Director (Accounts, BS-19)

    Introduction - Working Paper

    14.1. The case of Mr Abdul Hameed Qureshi, the then DD

    (Accounts, BS-18) was placed before the DPC for consideration of his

    promotion on Jan 19, 2004 against two promotion quota vacancies of

    Director (Accounts, BS-19). The DPC recommended his super-cession

    due to weak service record/discipline.

    14.2. The NHA Executive Board is the authority competent for

    appointments to posts in BS-18 to 19. Recommendations of the DPC

    were placed before the Board (117th meeting of Mar 13, 2004). The Board

    converted the recommendation for super-cession into deferment.

    Necessary office order was issued on Mar 24, 2004 and its copy was

    endorsed to the officer.

    14.3. Mr Qureshi submitted a departmental representation /

    appeal to MoC against his deferment. The MoC regretted the appeal

    being time barred vide letter No 4(2)97/ Roads dated Aug 17, 2006.

    14.4. After rejection of his departmental appeal, the officer

    should have filed an appeal before the Federal Services Tribunal (FST),

    within the statutory period of 30 days but he did not and thus

    decision about his deferment for promotion to BS-19 attained finality.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    39/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    39

    14.5. Mr Qureshi, however, again submitted a departmental

    appeal on Dec 17, 2006 to the Chairman NHA against his deferment.

    His case was processed and he was provided with a copy of MoC’s

    letter dated Aug 17, 2006 on rejection of his departmental appeal.

    14.6. Mr Qureshi was finally promoted as Director (Accounts,

    BS-19) on the recommendation of the DPC dated Apr 30, 2009 and

    notified vide Office Order dated Aug 5, 2009. On promotion, he

    submitted an application dated Sep 1, 2009 for fixation of his pay &

    allowances in BS-19 with payment of arrears wef the date of

    deferment viz Mar 13, 2004.

    14.7. Case was processed and submitted to the then ChairmanNHA, for rejection being not covered under the rules. Matter remained

    inconclusive as the file remained pending with the then Chairman

    NHA for a considerable length of time. After relinquishment of the

    charge by the then Chairman NHA in Jan-2011, the Secretary NHA

    returned the case on Jan 8, 2011 to the Admn Wing with directions of

    Acting Chairman that the case be resubmitted afresh, if required.

    14.8. Mr Qureshi is now pleading for pay fixation in BS-19 and

    payment of arrears from the date of deferment on the analogy of the

    following cases:-

    a.  Mr Arif Saeed Rana, DD (Accounts). He was also

    deferred for promotion as Director (BS-19) on Jan 19,

    2004 and after this promotion materialized wef Mar

    13, 2006 was allowed pay fixation in BS-19 and

    arrears of pay & allowances with retrospective effect

    ie date of deferment by NHA Executive Board.

    b.  Mr Haroon Rao, AD (Adm). The recommendation of

    DPC for his super-cession on disciplinary grounds

    was endorsed by the Executive Board. However, the

    FST declared this as unjust & unfair and directed

    reconsideration of his promotion. The officer was

    ultimately promoted as DD (Admn, BS-18) wef Aug

    21, 2006 with retrospective benefits.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    40/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    40

    14.9. The case of Mr Qureshi is not identical to that being

    quoted by him as precedent; therefore, his plea is not justifiable. On

    rejection of his departmental appeal / representation by the appellant

    authority in MoC, he should have filed appeal against the said

    decision before FST within stipulated time, but he opted not to.

    14.10. Since Mr Qureshi has already superannuated wef Dec 8,

    2009, the Executive Board is requested to consider his case on

    humanitarian grounds for fixation of his pay in BS-19 and payment of

    arrears with retrospective effect viz Mar 13, 2004 (date of deferment).

    Board’s Deliberations

    14.11. The MoC had conveyed certain written observations on

    this agenda item. Tabulated response rendered by the Admin Wing in

    respect of each observation is at Annex-H.

    14.12. The Member (Admin) presented details.

    14.13. The AS (Finance) observed that the proposal can not be

    supported being not covered under the rules.

    14.14. The Secretary NHA invited attention to the fact that the

    super-cession of the officer was converted by the Executive Board to

    deferment. Since no disciplinary shortcoming on his part ultimately

    materialized, he was eventually promoted. Whereas, Mr Arif Saeed

    Rana, whose case was identical in nature and was deferred in the

    same Board meeting, was granted all back benefits, Mr Qureshi was

    denied the equal opportunity and hence his case deserve similar

    treatment on the basis of equality under FR-17(1) (Annex-J).

    14.15. Proposal was discussed and regretted on plea that it is

    not covered under the rules.

    Decision

    14.16. The Executive Board considered the proposal regarding

    fixation of pay & allowances in BS-19 & payment of arrears from the

    date of deferment to Mr Abdul Hameed Qureshi, retired Director

    (Accounts, BS-19) but regretted on plea that it is not covered under

    the rules.

    Action By : Member (Admin)

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    41/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    41

    15. Agenda Item 12

    Annual Maintenance Plan for FY 2012-13

    Introduction - Working Paper

    15.1. Introduction.

    a.  NHA, under its Act, is tasked to plan, promote,

    organize, and implement programs for construction,

    development, operation, repair and maintenance of

    national highways. It is currently responsible formaintenance and upkeep of 12,131 km of federalized

    national highways.

    b.  Challenges such as decrease in estimated revenue,

    escalation in prices of construction materials,

    increase in fuel & manpower cost, increase in

    maintenance requirement, new federalization of

    roads in poor condition, financial mismanagement of

    RMA, blockade of collected revenues by O&M

    operators of toll plazas and financing of PSDP

    projects through RMA (road maintenance account), etc, 

    are placing extra burden on NHA in achieving RAMS

    (Road Assets Management System) objectives/ targets.

    c.  Despite the paucity of resources, NHA has achieved

    significant success by gradually increasing the

    quality of maintenance through periodic overlays,

    provision of rigid pavements at places of rutting,

    replacement/rehab of dilapidated bridges, geometric

    improvements, urban area development including

    provision of facilities like service lanes, lighting, bus

    bays, parking lots, underpasses, overhead bridges,

    flyovers, fencing, etc, through toll revenue and

    commercialization of its RoW.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    42/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    42

    15.2. Road Condition Surveys & Strategic Analysis.

    a. 

    In order to prepare Annual Maintenance Plan (AMP,2012-13) on scientific lines, pavement condition and

    road roughness surveys, traffic counts, computation

    of residual pavement strength by Falling Weight

    Deflectometer (FWD) non-destructive testing, etc,

    was undertaken.  Thereafter, future road maintenance

    funding needs were determined by using the Strategy

    Analysis Module of the Highway Development and

    Management Tools, HDM-4 Version 2.0.

    b.   The HDM-4 simulates total life cycle conditions and

    costs for different rehab and maintenance activities,

    and provides economic criteria for decision making.

     The model computes total costs composed of road

    agency and road user costs of the alternatives being

    evaluated by estimating road deterioration and road

    user costs over a period of 20 years.

    c. 

     The model also compares the possible project

    alternatives by computing the present value of the

    net benefits (NPV) of the project alternatives

    compared to the without project alternative, and

    selects the ones with highest NPV in “free budget”

    situation. Optimization of multiyear programs of

    expenditure under budgetary constraints is done

    using incremental benefit / cost analysis techniques,

    as provided by the HDM-4 analysis.

    15.3. Future Equipment & Technology Needs.

    a.   Traffic data is used for different types of studies

    carried out both at organizational level as well as for

    formulation of national level strategies. It is being

    collected manually only at selected points across

    Pakistan by RAMS and only for one day duration.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    43/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    43

    b.  Important factors like growth can be achieved by

    using an automatic counting system which is robust

    and easily manageable. RAMS carried out extensive

    study and has recommended automatic infra-red

    portable traffic counters in this budget.

    c.  In-situ pavement strength is important for deciding

    pavement maintenance strategy at any point in time.

     This can be done by state-of-the-art FWD Machine.

     The existing machine with NHA is more than 16

     years of age and has passed its useful life. Now, NHA

    has to procure a latest vehicle mounted High Weight

    Deflectometer (HWD) for improved decision making

    for pavement maintenance alternatives.

    15.4. International Roughness Index. The present average

    network roughness is 5 IRI (9147 km) compared to 10 in 1998-99 for

    a network of 8039 km. This is because NHA shifted its focus from

    rehab to periodic (functional & structural) overlays. Current overall

    network status is as follows:-

    a.  10.42% is in good condition (2 to 3 IRI).

    b. 

    32.98% is in fair condition (3 to 4 IRI).c.  30.55% is in poor condition (4 to 6 IRI).d.  26.05% is in very poor condition (more than 6 IRI).

    15.5. Budget Scenario.

    a.  Detailed analysis with different budget scenarios

    revealed that the level of expenditures required for

    maintaining NHA network comes to the tune of Rs

    26.6 billion. [About Rs 19 billion in first year and Rs 48billion in second year for rehab and periodic maintenance

    (structural & functional overlays) alone and Rs 2.315 billion for

    routine maintenance, Rs 4.75 billion for other maintenances

    and 0.570 billion for admin, sports, other activities and

    functioning of HRTC at unconstrained level in each year]. 

    b.  NHA, however, has a resource envelope of only Rs

    17.314 billion for FY 2012-13. Hence a maintenance

    backlog will be created in 1-2 years time, in case

    additional funding is not injected to boost upmaintenance funding.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    44/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board’s Confirmed Minutes

    44

    15.6. Twenty Year Rollover Maintenance Plan (FY 2010-11 – FY 2030-31).

    a.   The AMP 2012-13 includes a Rollover Program for

    future maintenance needs of Rs 264.11 billion.Analysis reveals that in next 20 years, despite

    numerous rehab projects, including donor assisted,

    NHA would be required to undertake overlays of

    different forms on its network. If this is done, the IRI

    would be brought down to level 3 - 4 indicating

    substantial improvements.

    b.   The afore-stated maintenance spending is only for

    rehab and pavement overlays. Routine maintenanceneeds and other spending which arise on need basis

    on some emergency / unforeseen situations are not

    included in the figure of Rs 264.11 billion.

    15.7. Financial Resources (2012-13).

    Description Rs in M

    a. GoP maintenance grant 2,000.000

    b. GoP grant for maintenance of KKH -

    Skardu (S-1)

    70.000

    c. GoP grant for maintenance of Thakot

    -Khunjerab (KKH)

    240.000

    d. Net revenue available (estimated) 15,003.583

    e. Total Budget 17,313.583

    15.8. Conclusion. To maintain and upkeep its network, NHA

    required Rs 26.6 billion in AMP 2012-13 as per the HDM-4 program

    analysis (unconstrained), however, due to financial constraint, AMP of Rs

    17,313.583 million has been prepared.

    15.9. Technical Clearance. The “RMA Technical Scrutiny Party”

    and “RMA Steering Committee” have scrutinized and recommended

    the AMP 2012-13 for approval.

    15.10. Proposal. NHA Executive Board is requested to approve

    the AMP 2012-13 of Rs 17,313.583 million.

  • 8/9/2019 219 Executive Borad Meeting of NHA1

    45/66

     

    219th  Meeting, July 24, 2012, Islamabad 

    NHA Executive Board