220 kv em substaion
TRANSCRIPT
Page 1 of 5
EVACUATION OF BBGS 250 MW UNIT #3
CESC COMMISSIONS FIRST 220 kV SUBSTATION
The 220 kV Eastern Metropolitan Substation of CESC is now ready to receive power from its 250
MW 3rd Unit of Budge-Budge Generating station. The first three 160 MVA, 220/132/33 kV
Transformers at the above substation have been commissioned. The project for evacuating power
from BBGS Unit #3 which is one of the major and critical part of the CESC’s integrated
transmission plan conceived in the year 2006 comprise of about 85 km long one 220 kV Double
Circuit Overhead line from BBGS and terminating at 220/132 kV Eastern Metropolitan Sub-station
at mouza Nonadanga adjacent to existing WBSETCL’s 220 kV Kasba sub-station.
The 220 kV EM Substation will ultimately have 4 nos. 160 MVA 220/132/33 kV transformers. The
above transformers will, on one hand, step down the power to 132 kV level for onward
transmission to various Load Centres and, on the other hand, will meet the local area load at 33 kV
through the 33 kV tertiary winding of these transformers. This will reduce the need for stepping
down from 132 kV to 33 kV level through another set of transformers but will also render the
existing 3 nos. 75 MVA 132/33 kV transformers at Kasba Receiving Station spare for utilisation
elsewhere in the network to meet load growth. The 220 kV Outdoor Yard will also have outlets for
two 220 kV underground cable circuits to NCGS to meet the area demand following closure of the
Station in future. Till now the Generating Stations, Power exchange and Load centre Substations
are interconnected at 132 kV, which is the highest Transmission Voltage in CESC system .With the
commissioning of EM Substation CESC takes first step towards upgrading its Transmission
Voltage to 220 kV.
View of the 220kV Outdoor Yard
Page 2 of 5
Following are the some salient features of the Eastern Metropolitan S/S.
• One & Half breaker scheme designed 220 kV switchyard comprising 5 nos. Diameters.
• State & Central grid interconnectivity with WBSETCL & PGCIL (through 220 kV Double
Circuit OH line in future) for better operational flexibility, reliability and maintaining stability
of supply.
• Installation of internationally reputed make latest state of the art :-
1. SF6 filled 220 kV CTs and Gapless 220 & 132 kV Lightning Arrestors with Composite
Insulator casings.
2. 17 Bay, 132 kV Gas Insulated Switchboard (GIS) with duplicate bus-bar arrangement for
integration with the existing132 kV transmission network.
3. Dry silicone bushing plug-in type 132 kV Outdoor Cable Sealing End Termination, 50%
lighter in weight, without fire hazard oil and first time used in India.
4. Numerical Technology based relays for 220 and 132 kV network including Bus-bar Zone
protections for faster clearance of faults to enhance system stability & reliability and
recording of disturbances.
5. OF & OPGW based SDH communication system to provide reliable SCADA, line
differential & tele-transfer trip protection for 220 kV O/H & 132 kV UG lines and voice
communication.
160MVA 220/132/33kV Auto Transformer 132kV Gas Insulated Switchgear
A view of Control Room 220kV SF6 gas filled CTs with
Composite Insulators
Page 3 of 5
For an urban utility like CESC, availability of suitable land for such a large infrastructural
requirement is often a dominant issue. Seventy percent of the land at EM S/S was of hazardous and
poor soil quality. The area therefore required extensive land treatment with soil consolidation.
Considering the constraints and difficulties, commissioning of EM sub-station, a major milestone is
achieved in record time of about 18 months for the BBGS evacuation project.
Unless a glimpse of the hurdles encountered is given, it would be difficult to conceive the
enormous task that has to be dealt with 220 kV Double Circuit BBGS – EMSS Over Head line
execution.
The various ROW issues that had to be addressed while executing the OH line are as under.
� Growth of Urban and semi-urban area on the earlier envisaged line route in the intervening
period and by-passing of the area in Baruipur earmarked for the proposed 24 Paraganas
Head Quarter and Barasat – Raichak Expressway as advised by the Govt. body, resulting
extensive de-touring a necessity.
The revised route alignment also falls under East Kolkata Wetlands area, a Ramsar site under
international guideline which required further adherence as under.
� Maintaining of alignment as fixed by the Institute of Environmental Studies and Wetland
Management (IESWM) / East Kolkata Wetland Management Authority (EKWMA) and
keeping aside the proposed area for Wetland Interpretation Centre (WIP) from alignment of
transmission line.
� Installation of transmission line on the embankment between two canals.
� Number of towers to be one instead of two i.e. only one tower to be installed in between the
two canals.
� A part of the transmission line about 3.5 KM also to be underground to avoid the settlement
and water area.
� Towers to be erected on land only and to be eco-friendly. No tower to be installed in the
water area.
� Arrangements to be made so that the line does not create obstructions to flying migratory
birds.
Page 4 of 5
Consequences vis-à-vis Technical Aspects for O/H line due to above Issues:
1. Requirement of renewed survey.
2. Transmission line needed further deviation. The total length of line as on today thus has
become 88.5 KM comprising 85 KM of O/H section and 3.5 KM of underground cable
section compared to original estimate of 70 KM.
3. Since de-touring resulted intrusion more to eastwards, the encountered soil conditions for
erecting transmission towers have become more and more hazardous and difficult. Most of
the soils are water logged paddy fields, marshy, filled with decomposed vegetation. In other
words the load bearing properties of the soil are so poor that foundation requirement
compared to that on normal soil has become much critical. At several places special narrow
based heavy duty towers are needed to avoid the water body and to accommodate in narrow
tower footing area available at various places.
4. Revised alignment also made the transmission route zigzag at many places to avoid various
obstacles in the semi-urban areas. Crossing over large nos. of EHV O/H line (10 Nos.) and
passing through unavoidable fruit orchards also have to be taken care off. Compared to earlier
estimate all these issues thus resulted in increase in total no. of towers and more nos. of heavy
duty angle towers instead of normal tangent towers, higher towers (50-75 m.) to traverse over
fruit orchards and other transmission lines along with installation of gantries wherever
deemed necessary.
5. The conditions of erecting only one tower compelled to go in for a stretch of about 14 KM of
O/H line with multi-circuit towers in the EKW area to take care also of the future connectivity
of EM S/S with PGCIL along with the present line to BBGS at one go. Since these multi-
A view of 220kV Multi Circuit Tower Conductor Stringing work in Progress
Page 5 of 5
circuit tower will carry 2 nos. D/C line i.e. 4 circuits, hence special design consideration with
respect to strength & reliability have to be taken for such towers. These special type towers
have not only given a considerable impact on steel structure design but also on massive
foundation requirement due to the poor EKW area soil property and availability of limited
tower footing area. In addition to the above, in order to comply with the requirement of the
State’s Irrigation & Waterways Dept., pile foundation designs with minimum number of piles
had to be adopted on the embankment between two canals towards east of Bantala to ensure
no impediment during eventual merger of two canals if takes place in future.
6. Being most part of the transmission line route falls in low lying water catchments & EKW
area, mechanised excavation or transportation of material is extremely difficult . The work of
foundation, erections including stringing for many of such towers required massive head
loading and special arrangement.
7. Since within the multi-circuit tower section, a part of the transmission line of about 3.5 KM
near Bamunghata area required to be underground to avoid the settlement and water area in
the EKW area, additional cable bridges at canal crossings, Gantry structures and Isolators &
Lightning arrestors thus also have become essential to establish UG-OH connectivity at
Bamunghata.
.
The execution of 220 kV Double Circuit OH line in-spite of various hurdles & ROW issues is
presently under execution in full swing and will be ready shortly to integrate the 3rd Unit of BBGS
into the system as scheduled.