Primavera and SAP PS Integration in Saudi Aramco
Manal M. Al-Ghamdi
[© Copyright 2012, Saudi Aramco. All rights reserved.
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 2/27
[ Abstract
SAP’s Project System (PS) tool provides comprehensive and fully-integrated
project management functionalities. Key strengths of SAP PS are real-time
integration with SAP application components, such as SAP solutions for
financials, procurement and logistics, and SAP Human Capital Management
(SAP HCM).
In some situations, having another project management tool is unavoidable
Because it is the tool used by users/contractors or,
Real Experience. Real Advantage.
In such cases, the sought-after goal should be
To bring the strengths of both technologies together
Which creates a significant need to integrate the data
So the project stays synchronized
This presentation presents a case study of the SAP Project System tool’s
coexistence and integration with Primavera to manage projects performed
by multiple organizations or contractors in an owner-operator organization.
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 3/27
[ Company
The Saudi Arabian Oil Company (Saudi Aramco), SaudiArabia’s national oil company
A fully-integrated, global petroleum enterprise and a worldleader in exploration, production, refining, distribution,shipping and marketing
Manage the world’s largest proven crude oil reserves of 260.1billion barrels and the world’s fourth-lar est as reserves, with
Real Experience. Real Advantage.
279 trillion cubic feet
Among the world's leading refiners and are moving furtherdownstream into chemicals production
More than 54,000 employees from 70 nations Headquarters in Dhahran, Saudi Arabia, also have offices in
North America, Europe and the Far East
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 4/27
[ Learning Points
WBS Standardization
Primavera Implementation
SAP PS Implementation
Real Experience. Real Advantage. 4
Primavera and SAP PS Integration
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 5/27
[ WBS Standardization - Design Concepts
Work Breakdown Structure (WBS) and Product Breakdown
Structure (PBS)
Common Service Elements
Real Experience. Real Advantage.
Project and Program WBS
Contract WBS
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 6/27
[ Categories of WBS Elements
Real Experience. Real Advantage.
Source: The Work Breakdown Structure in Government Contracting , Gregory T. Haugan
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 7/27
[ Alternate Structure Concepts
• Organizations often operate with a
standard set of process steps• A temptation to structure the WBS by
process steps despite the fact thatthe output is products
• Figure 3-9 illustrates how a WBS iscreated
• When an A&E firm is responsible
Real Experience. Real Advantage.
Source: The Work Breakdown Structure in Government Contracting , Gregory T. Haugan
• However, if a separate firm wasresponsible for Collection lines, Sludgetanks, Vacuum station, and Pumpbuilding
• The four elements would be Level 2items and,
• The appropriate design elementswould be included at Level 3
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 8/27
[ Alternate Structure Concepts
• Level 2 items in Figure 3-10 arecontrol accounts or workpackages.
• The Level 3 elements of eachare identical and are really theprimary output products of theproject
Real Experience. Real Advantage.
• In general, whenever a WBS ispresented with identical elementson the next level,
• The WBS should be reviewedto see if an alternativepresentation would be morerepresentative of the productbreakdown
Source: The Work Breakdown Structure in Government Contracting , Gregory T. Haugan
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 9/27
[
The Product BreakdownStructure shows the
The Work BreakdownStructure shows all
Subsystem A Subsystem B Subsystem C Management Systems
Engineering
Integration,
Test & Verification
Logistics
Support
System
Relationship between Product Breakdown Structure
(PBS) and Work Breakdown Structure (WBS)
PBS WBS
Real Experience. Real Advantage.
components from whichthe system was formed.
The PBS reflects thework to produce
the individualsystem components.
work components necessaryto produce a completesystem.
The WBS reflects the
work to integratethe componentsinto a system.
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 10/27
[ Project/Program WBS
The program/project WBS (PWBS) structure encompassesthe entire program or project
It usually consists of three levels of products/elements withassociated work definitions
The three upper levels of the PWBS are defined as: Level 1 is the entire program/project
Real Experience. Real Advantage.
Level 2 elements are the major product segments or subsections
Level 3 contains definable components, or subsets, of the Level 2elements
Properly structured PWBS will readily allow complete aggregation of cost, schedule and performance data
from lower elements up to the project or program level
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 11/27
[ Contract WBS
If a project involves several organizational participants orcontractors
Guidance for one contractor can be provided in a Contract WBS (CWBS)
The CWBS is the complete WBS for a specific contract
Developed by the contractor in accordance with the contract statementof work (SOW)
CWBS includes
PWBS elements for the products
Real Experience. Real Advantage.
To be furnished by the contractor
The contractor Extends these elements
Defines the lower-level products
The contract reporting requirements will indicate the CWBS levelsor elements for which contract status is to be reported
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 12/27
[ PWBS/CWBS Relationship
PWBS
Project WBS
Real Experience. Real Advantage.
… CWBS 1 CWBS 2
… …
Contract WBS
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 13/27
[ Learning Points
WBS Standardization
Primavera Implementation
SAP PS Implementation
Real Experience. Real Advantage. 13
Primavera and SAP PS Integration
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 14/27
[ Primavera Implementation - Part1
A central database for all projects
Standard Enterprise Project Structure (EPS) that identifies
The company-wide project organization
For project summarization, roll-up, and cross reporting
Standard Organization Breakdown Structure (OBS) for
project organization to manage
Real Experience. Real Advantage.
, ,
And standardized
Project template for different project types
Project codes
Activity codes User define fields
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 15/27
[ Primavera Implementation – Part 2
Integration with SAP ERP Project System (PS)
Primavera Web Access
with configured Dashboards
and Project Workspaces
LDAP authentication
Real Experience. Real Advantage.
rov es common user cre en a s orage across app ca ons
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 16/27
[ Program and Contract WBS Integration Techniques
Technique #1 - Incorporating the CWBS element as a
subproject
Into the PWBS
In the same database
Manage authorizations at WBS level
Technique #2 - Incorporating the CWBS and PWBS as
Real Experience. Real Advantage.
In the same database or,
With Export/Import and Reflection capabilities
Either integration technique provides An automated means to logically connect the schedule
dependencies
Among all project work elements
Using inter-project linking capabilities
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 17/27
[ Technique #1 - CWBS Element as a Subproject
CWBS
Restrict access to OBS\
Contractor A
Primavera
Real Experience. Real Advantage.
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 18/27
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 19/27
[ Learning Points
WBS Standardization
Primavera Implementation
SAP PS Implementation
Real Experience. Real Advantage. 19
Primavera and SAP PS Integration
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 20/27
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 21/27
[ Project Master WBS
PWBS and CWBS
Finance and Controlling
Cost Planning
Budgeting
Easy Cost Planningtem late based calculation
Structural Cost PlanningTop Down / Bottom Up
€ 400 € 600
€ 1.200
€ 200
Real Experience. Real Advantage.
Settlement and Period end closing
Cost Reporting
Material Management and Monitoring
Network CalculationDuration * Work * Rate/HProcurement / Cost Activities
ΣΣ
l l l
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 22/27
[ Standard WBS (Templates)
Standard structures can be usedas a template to standardize
operative projects
Making the processing of projects
more transparent (everyone
create an operative project from
Real Experience. Real Advantage.
a standard project)
Enabling comparison of projects
with similar structures
Facilitates project controlling
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 23/27
[ Learning Points
WBS Standardization
Primavera Implementation
SAP PS Implementation
Real Experience. Real Advantage. 23
Primavera and SAP PS Integration
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 24/27
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 25/27
[ Integration – Scenario #1- One to One
With this scenario, one project in SAP PS will be mapped to
one project in Primavera.
This scenario works with small and tightly integrated
projects.
One to One
Real Experience. Real Advantage.
ummary – etai s rimavera
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 26/27
[ Integration – Scenario #2 One to Many
With this scenario, one project in SAP PS will be mapped to
many projects in Primavera.
Each CWBS element in level two in the Project Master WBS
in SAP PS will be created as separate file/project in
Primavera.
Real Experience. Real Advantage.
ne to ne
Summary (SAP PS) – Details (Primavera)
8/10/2019 2810 Project System and Primavera Integration Success at Saudi Aramco
http://slidepdf.com/reader/full/2810-project-system-and-primavera-integration-success-at-saudi-aramco 27/27
[
] Thank you for participating.
SESSION CODE:
Please remember to complete and return yourevaluation form following this session.
For ongoing education on this area of focus, visit the
Year-Round Community page at www.asug.com/yrc.
Real Experience. Real Advantage. 27