3 Oct 2006 [email protected] 1
Cost and Schedule UpdateCraig Ogilvie, Iowa State University Analysis of system risks Update schedule
Critical path Quantitative milestones
Project completion requirements Manpower summary
MoUs Budget summary
3 Oct 2006 [email protected] 2
System Risks Action item: “Complete a more comprehensive risk analysis and
update the cost and schedule contingency analysis as appropriate, prior to project initiation.”
“The overall understanding of the risks may be actually missing. It is also interesting to think about the project as a whole, and try to identify the risks [..snip..] and the consequences of these risks happening. Contingency plans can then be envisioned to control and mitigate the impact of these risks.
System managers were asked: “what keeps you awake at night” (about the VTX:)
10 areas identified Mitigation
Explicit planning, resources, milestones when passed
3 Oct 2006 [email protected] 3
Identified system risks (I to V) Pixel/Strip performance in close proximity Two rounds combined pixel+strip ladders tests, winter 06, summer 07
Thermal stress of pixel and strip ladder assemblies Perform thermal cycle tests winter06/7
Mechanical design firm (HYTEC) Weekly with VTX mech. Engineer + monthly meetings with VTX office
VTX/PHENIX integration: slow control, monitoring, calibration, integration into DAQ
Develop/review operating plan with PHENIX managers, winter 06/07, winter 07/08
Ground loops Develop/review grounding plan with all stakeholders, winter 06/07,
winter 07/08
3 Oct 2006 [email protected] 4
Identified system risks (VI to X ) Pixel bump-bonding
Increase contingency in schedule by approx 50% Pixel bus performance
Test using prototype ladder pixel bus + SPIRO + FEM + stave April 07 RCC and ROC development
Apply more R&D $ in FY06 to design/prototype of RCC ASIC Design/fabrication pre-production RCC, July 06 to winter 06/07
Decision to start item’s production Formal review process before any item’s production
VTX/FVTX integration Cross-meeting attendance esp. by engineers, updates at quarterly
3 Oct 2006 [email protected] 5
Critical Path
Explicit float44 weeks(re-analysis =>increase from 20 weeks at time of review)
WBS Task Name
1.1.1.1.2 ROC Pre-production
1.1.1.1.2.1 ROC Design Pre-production
1.1.1.1.2.2 ROC Design Review
1.1.1.1.2.5 ROC Fab Pre-production
1.1.1.1.2.7 Test pre-production ROC/RCC
contingency
1.1.3 Strip System test
1.1.3.2 Strip system tests: Electronics ROC & Sensor
1.1.3.2.1 strip system test with 2nd round roc
1.1.3.2.1.1 strip system telescope tests
contingency
1.1.3.3 Strip Ladder system test (roc, sensor, bus, pilot, stave)
1.1.3.3.7 strip system test: assemble pre-production test ladder (using pre-production ROC)
1.1.3.3.8 strip system test: test of pre-production ladder
contingency
Milestone - Pre-production strip ladder performs to spec
1.1.4 Assembly and Testing of Strip ladders
1.1.4.2 ROC & sensor+pilot+ladder
1.1.4.2.4 Mount sensor modules on stave and wire bonds between the ROC
1.1.4.2.5 test assembled strip ladders
contingency
Milestone: 44 strip ladders + spare performs to spec, sufficient for full-VTX
1.4 Electronics System Integration
1.4.4 Tests before VTX is installed
1.4.4.1 Testing of fully assembled barrel detector
contingency
1.5 Auxiliary Systems & Integration
1.5.2 Mechanical Structure
1.5.2.2 barrel staves
1.5.2.2.2 procure strip staves
1.5.2.2.2.2 Tooling strip staves
1.5.2.2.2.3 fabrication strip staves
contingency
1.5.3 Assembly of VTX
1.5.3.3 mount strip Ladders on barrel mounts
1.5.3.3.1 align + fix strip ladders onto barrel mounts
1.5.3.3.2 test strip ladders on barrel
contingency
1.5.3.4 mount barrel onto space frame
contingency
Milestone - all ladders on VTX
Milestone: project complete
12/17
9/17
11/11
1/27
Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr2006 2007 2008 2009 2010
3 Oct 2006 [email protected] 6
Quantitative+Risk Milestones (FY07) Milestone: pre-production ROC/RCC perform to spec FY07 3Q
Milestone: 123 strip sensor modules Q/A'd, sufficient for half-vtx FY07 3Q
Milestone: 246 + spare strip sensor modules Q/A'd FY07 4Q
Milestone: 60 pixel sensor modules performs to spec, sufficient for half vtx FY07 1Q
Milestone: 1st prototype pixel ladder performs to electrical, thermal spec FY07 3Q
Milestone: 120 + spare pixel sensor modules performs to spec FY07 3Q
Milestone: 60 pixel buses + spares fabricated FY07 4Q
Milestone: 60 pixel spiro modules + spare performs to spec FY07 4Q
Milestone: Design completed for DCMs FY07 4Q
Milestone : Completion of Mechanical Specifications FY07 1Q
Milestone: sign mechanical contract FY07 1Q
Milestone: prototype pixel staves delivered FY07 2Q
Milestone: prototype strip staves delivered FY07 4Q
3 Oct 2006 [email protected] 7
Quantitative+Risk Milestones (FY08) Milestone - Pre-production strip ladder performs to spec FY08 1Q
Milestone: RCCs delivered and perform to spec FY08 3Q
Milestone: 123 ROCs performs to spec, sufficient ROCs for half-VTX FY08 3Q
Milestone: 246 + spare ROC performs to spec FY08 4Q
Milestone: 30 pixel FEMs + spare performs to spec FY08 1Q
Milestone: Pixel trigger modules performs to spec FY08 2Q
Milestone: 60 pixel bus extenders + spares fabricated FY08 3Q
Milestone: 77 DCMs + spare completed FY08 3Q
Milestone: grounding plan finalized FY08 2Q
Milestone: pixel/strip test ladders perform to spec when in realistic proximity FY08 2Q
Milestone: VTX operations plan finalized FY08 2Q
Milestone: Environment Safety & compliance granted FY08 3Q
Milestone: electrical services completed FY08 4Q
Milestone: 30 + spare pixel staves delivered FY08 3Q
3 Oct 2006 [email protected] 8
Quantitative+Risk Milestones (FY09)
Milestone: 30 pixel ladders assembled + spare FY09 1Q
Milestone: 44 + spare FEMs + PM performs to spec FY09 1Q
Milestone: infrastructure ready for installation FY09 2Q
Milestone: 22 strip ladders performs to spec, sufficient for half-VTX FY09 4Q
Milestone: 44 strip ladders + spare performs to spec FY09 4Q
Milestone: 12 barrel mounts delivered FY09 1Q
Milestone: 44 + spare strip staves delivered FY09 1Q
Milestone: assembly fixtures delivered FY09 2Q
Milestone: cooling system delivered FY09 3Q
Milestone: dry gas system delivered FY10 1Q
Milestone: space frame delivered FY10 1Q
Milestone: mechanical isolation system mounts delivered FY10 1Q
Milestone - all ladders on VTX FY10 1Q
Milestone: project complete FY10 2Q
3 Oct 2006 [email protected] 9
Project Completion Requirement VTX barrel assembled, ready to install in PHENIX IR.
Infrastructure in the PHENIX IR is installed and ready to accept the VTX barrel.
cooling system, LV/HV power supplies, slow control systems, safety systems, cables, and data fibers.
FEMs and DCMs for the VTX system are ready VTX satisfies the following functional requirements:
Average live area of the ladders within the PHENIX central arm acceptance is more than 90%
The fully assembled detector can be cooled down to 0 degree C. Noise hit rate <0.1% of the pixels in the pixel detector after hot channels
are masked. Clear separation of measured MIP peak from pedestal for strip detector. DCA resolution better than 100 m in r.m.s.
3 Oct 2006 [email protected] 10
Manpower Summary (need to check)
WBS TaskFY07 Total
FY08 Total
FY09 Total
1.1.1 Strip FEE 4.1 4.45 3.9
1.1.2 to 1.1.4 Strip sensors, test, assembly 4.85 4.85 4.95
1.2 Pixel 12.2 11.8 10.2
1.3 + 1.4 DAQ + Electronic Systems 2.6 2.5 1.5
1.5.2 Mechanical Structure 2.3 2.65 0.25
1.5.3 + 1.5.4 Infrastructure+Assembly ladders onto barrel 1 2.5 3
1.6 Management 0.55 0.55 0.55
software 2.25 3.25 4.25
Total DOE 17.65 20.75 18.4
Total Project 29.85 32.55 28.6
3 Oct 2006 [email protected] 11
MoUs
MoU’s being drafted between BNL and institutions In place Fall 06
3 Oct 2006 [email protected] 12
Overall Cost (DOE)
WBS Name TPC k$ FY07
1 VTX project 4,463
1.1 Strip 1,576
1.3 DAQ 190
1.4 Electronics System Integration 664
1.5 Auxiliary Systems & Integration 1,888
1.6 Management 79
1.7 Installation & preops 67
3 Oct 2006 [email protected] 13
Breakdown of costs (FY07 k$)
WBS NameMaterial
k$Personnel
k$
BNLtransfer k$
Conting.%
Conting. k$
TEC k$
Preopsk$
TPCk$
1 VTX project 1,390 1,920 204 25.4 893 4,406 57 4,463
1.1 Strip 634 607 2 27.0 334 1,576 1,576
1.2 DAQ 99 30 23 25.0 38 190 190
1.4Electronics System
Integration141 348 59 21.2 116 664 664
1.5Auxiliary Systems
& Integration515 870 110 26.2 391 1,888 1,888
1.6 Management 0 57 10 17.6 12 79 79
1.7 Installation 0 0 0 0 0 67 57
3 Oct 2006 [email protected] 14
At Year Dollars2% material, 4% personnel
WBS NameTPCFY07 k$
FY07 AY k$
FY08 AY k$
FY09 AY k$
TPC AY k$
1 VTX project 4,463 1,464 2,052 1,085 4,600
1.1 Strip 1,576 693 639 178 1,611
1.3 DAQ 190 0 195 0 195
1.4Electronics System
Integration664 145 375 166 687
1.5Auxiliary Systems &
Integration1,888 500 813 643 1957
1.6 Management 79 26 29 27 82
1.7 Installation 67 0 0 71 71
3 Oct 2006 [email protected] 15
Summary Re-analysis and mitigation of system risks Re-analysis of risk on+near critical path items
increase of schedule contingency Project complete
Ready for installation early 2010 TPC $4.6M AY