4-1 mcgraw-hill/irwin operations strategy copyright © 2008 the mcgraw-hill companies, inc. all...
TRANSCRIPT
4-1McGraw-Hill/IrwinOperations Strategy Copyright © 2008 The McGraw-Hill Companies, Inc. All rights reserved.
Capacity Strategy
Chapter 4
4-2
Some issues from Biotech industry
Strategic impact of long lead times and (often) high financial impact
Models for timing and size Effects of variability Competitive factors
4-3
The Capacity Strategy Decision How much capacity should the company
have to cover expected demand in the short, intermediate and long term?
In what increments and when, or at what intervals, should the company add capacity?
What type of capacity should the company add?
Where in the value chain, internal or external to the company, should capacity be added?
4-4
Some Capacity Definitions Capacity: volume of output per period of
time Maximum or design capacity: the highest
rate of output that a process or activity can theoretically achieve
Effective or planned capacity: the output rate expected for a given activity or process
Demonstrated capacity: the actual level of output for a process or activity over time
Capacity utilization: the percentage of a facility’s maximum or effective capacity used by actual production
4-5
Means of Adding Capacity
Human resources Process technology Information technology Facilities Suppliers or subcontractors Extracting additional output from
existing resources:Quality improvementProcess optimization
4-6
Capacity Management Time Horizons
4-7
Capacity Expansion Alternatives Using Different Time Increments
4-8
Capacity models: The Lead, Lag, Stay-Even Model
Volu
me
Time
Lead Policy
Predicted demand
Lag Policy
Stay Even Policy
4-9
The Lead, Lag, Stay-Even Model: Choosing Among Them
4-10
Economies and Diseconomies of Scale in Facilities
4-11
Sizing Capacity Increments when Demand is Known or Certain: Optimum Expansion Intervals
4-12
Sizing Capacity Increments when Demand is Known or Certain: Guidelines
As discount rates rise, add capacity in smaller incrementsFuture expenditures on capacity are
relatively less expensiveThus, delaying expenditures is more
economical As scale factors rise, add capacity in
smaller incrementsCost per increment of capacity goes downMaking larger investments in capacity up
front isn’t worth it
4-13
Choosing Between Capacity Expansion Internally and at a Contractor
4-14
Lead time impact
4-15
Hedging for uncertainty – For specific time in future
Inventory problem ofCapacity during a time period (e.g.. kg. per
year) or, equivalentlyPhysical size of equipment (liters)
Set service level or use costs of not meeting capacity or falling short
Can use the newsvendor approach
4-16
Capacity expansion in Biotech Costs of not meeting demand are extremely large! Costs of extra capacity are large, but two orders of
magnitude lower Use newsvendor approach of costs of underage and
overage Co = Cost of overage, or cost of having one too many units
of capacity Cu = Cost of underage, or cost of having one too few units of
capacity Find z such that P(d<z) = Cu/(Co+Cu) For Genentech, this is 99.05%
4-17
Concept: Find percentile corresponding to cost balance point (critical fractile or
percentile)
Demand correspondingTo critical percentile
Area equal to percentile
4-18
Concept: Find percentile corresponding to cost balance point (critical fractile or percentile)
Demand correspondingTo critical percentile
Area equal to percentile
4-19
Normal distribution is an easy way to determine the appropriate demand levels
84% of area CSL ZUnder curve 84% 1(Z=1) 90%
1.28 95%
1.64 99%.
2.33
Calculate required capacity as:Average demand + z * standard deviation of demand
4-20
Note that high services greatly increase capacity!
Exhibit 4-24: Capacity Required as Service Level Increases
2500
3000
3500
4000
4500
5000
0.5 0.55 0.6 0.65 0.7 0.75 0.8 0.85 0.9 0.95 1
Service Level
Cap
acit
y (U
nit
s)
4-21
How do we generalize for any lead time and also when the time is uncertain?
Required capacity increase = Expected demand growth over the lead time + z * σgL
σgL2 = E(L) * σg
2 + (E(g)) 2 * σL2
σgL = SQRT (E(L) * σg2 + (E(g)) 2 * σL
2)
Where E(L) = expected lead time σL = standard deviation of lead time E(g) = expected growth σg = standard deviation of growth
Example: 2% growth, 5 year lead, 5% uncertainty in five years, 98% service
Increase = 5x2% + 1.96x5% = 19.8% increase
4-22
Capacity Expansion under Uncertainty: Decision Analysis Models
4-23
Capacity Expansion under Uncertainty: Multistage Decision Analysis Models
4-24
Example for Genentech
BuildCCP3
Both approved
Lungapproved
Neitherapproved
Lung,Breast
approved
Option?
Lung,Breast
approved
.
.
.
Largeexpansion
.
.
.
4-25
Capacity Management and Flexibility
Capacity that can be used for multiple uses is more efficient in terms of hedging (safety capacity)
This can be in terms of flexible capacity or through postponement (stock components not finished goods)
Example: Suit one: sigma = 680 Suit two: sigma = 646
2.33 x sum = 3085 (99% service)Sigma for total demand is 938 (law of
large numbersPooled capacity yields 2.33x938 = 2186
4-26
Competition and Gaming with Capacity
4-27
Developing a Capacity Strategy
Understand the business strategy and competitive environment
Develop a demand forecast Identify capacity expansion (or
contraction) alternatives Apply relevant models to develop
capacity strategy Assess implications for flexibility and
balance Develop an implementation plan Implement, assess and measure results