4d bim the evolution of construction scheduling
TRANSCRIPT
-
8/10/2019 4D BIM the Evolution of Construction Scheduling
1/2
Time has always been an important factor of any construction project since
the dawn of civilization. In 1910 Henry Laurence Gantt developed the first bars
charts commonly referred to as gantt charts in modern construction scheduling
terminology. ( Architectural Evangelist) Critical Path Method or CPM schedul-
ing was introduced to the world in the mid 1950s and the first version of CPM
construction scheduling software called Primavera was developed in 1983. So
what is the next significant innovation in the evolution of construction sched-
uling? 4D BIM (Building Information Modeling) provides a visual 3D CAD design
that is integrated with the CPM construction schedule; the 4th dimension oftime is added to the model. The end result is a virtual construction simulation
that can provide detailed insight that was never before possible.
Sir John Egan released his Rethinking Construction report in 1998 where he at-
t t d th t t t h i d i i l f th i d t i h
4D BIM: The Evolution of Construction SchedulingApril 18, 2011
Knowing how to correct
estimate activity duratiocombined with multipl
reasonability checks, can
create an effective constr
tion oversight tool that c
significantly improve pro
performance.
-
8/10/2019 4D BIM the Evolution of Construction Scheduling
2/2
2www.precisionscheduling.com
2011 Precision Scheduling Consultants. All Rights Reserved.
www.precisionscheduling.com
2011 Precision Scheduling Consultants. All Rights Reserved.
The Building Information Model (BIM) provides a dynamic multi-dimensional view of the construction project
that can contain an almost limitless amount of information of the project and components of the project. As
defined by the National BIM standard, a BIM is the digital representation of the physical and functional charac-
teristics of a facility. As such, it serves as a shared, collaborative information resource for a facility from inception
outward. (Lutton 5) Through the integration of BIM and construction scheduling, we now have the ability to
apply the concept of 4D scheduling and visually communicate the project plan with relation to the timeline to
the project team before the project is constructed.
The Gantt chart has been the visua l display of choice for virtually all construction schedules for over a century.
Gantt charts provide bars along a timeline that represent durations of activities defined in the construction
schedule. ( Architectural Evangelist) The display of Gantt charts provides the basic purpose of constructionschedule; although, visualization of the activities and sequencing could only be done in the minds of the project
team members. Visualization accounts for up to 80% of what people perceive; 4D BIM maximizes the power of
visual communicating the construction schedule. Gant charts alone can be too detailed or complicated to ef-
fectively communicate to the project team in a reasonable amount of time. 4D BIM dramatically enhances the
usefulness of Gantt charts by providing a quick visual picture of what is going to occur and when. (4D BIM)
By linking the CPM construction
schedule to the BIM, the project
controls capabilities are improved
by providing a visual picture of
where the project should be at any
given point in time which is invalu-
able to construction schedule over-sight. The critical path activities
can be flagged and or highlighted
within the model so project manag-
ers know where to focus their re-
sources.
Through the continued develop-
ment and progressive elaboration of
BIM, new uses and applications have
emerged; although, the CPM construction schedule integration has not yet reached its full potential. There are
other components of the construction schedule that have not been added to BIM. Only through consolidated
efforts between designers and scheduling experts, will the full potential of 4D BIM be realized. Compared to
other industries, the construction industry is slower to adapt to technological advancement. The acceptanceand implementation of this relatively new tool combined with expert judgment from various team members will
ensure that the project team has the best project plan conceivable. The construction schedule literally comes to
life and effectively communicates the project plan which will gi ve the project a higher chance o f success.
Resources:
1) 4D BIM Modeling: Improve Cost, Scheduling and Coordination of Building Project. Architectural Evangelist 12 01 2010: n. pag. Web. 11 A
www.architecturalevangelist.com/building-information-modeling/4d-bim-modeling-improve-cost-scheduling-and-coordination-of-b
html>.
2) 4D BIM. Wikipedia. 2010. Web. .
3) Egan, John. Rethinking Construction. synchroltd.com. N.p., 04 Apr 1998. Web. 11 Apr 2011. .
4) Lutton, Nicholas. BIM: Helping the Air Force better design, construct, and manage assets. Center Views . 17.2 (2011): 5. Print.
Figure 2: Synchroltd.com. Web. 9 Apr 2011.
.