5 pdw (selection of app tech)
TRANSCRIPT
-
7/28/2019 5 Pdw (Selection of App Tech)
1/10
SELECTION OF APPROPRIATE
TECHNOLOGY/DESIGN
-
7/28/2019 5 Pdw (Selection of App Tech)
2/10
1. Selection of Appropriate Technology /
Appropriate design
Determined by the following factors:
a. Type of User - the planners have to consider thetype of users (e.g. women, children, persons withdisability) to be more socially responsive.
b. Available Local Resources - selection of anappropriate design could be awkward in the sensethat there are available standard designs for someselected structure or interventions.
-
7/28/2019 5 Pdw (Selection of App Tech)
3/10
- In the selection process, it is important toconsider whether these standard designscan be applied to local conditions.
- For some, standards could mean technicalspecifications of materials to be used forsuch intervention.
- Technical specifications may not be
applicable in some communities but thestandard functional design, or the purposefor which it is applied, can be the same.
-
7/28/2019 5 Pdw (Selection of App Tech)
4/10
c. Geographical Location of the Community- thisinvolves identifying a wide range of applicable
options based on the geographical location and thesocio-cultural orientation of the community.
d. Cost Effectiveness during SPI and O & M
-
7/28/2019 5 Pdw (Selection of App Tech)
5/10
FOR BUILDINGS:
- STANDARD DESIGN
- ALTERNATIVE DESIGN
-
7/28/2019 5 Pdw (Selection of App Tech)
6/10
FOR WATER SYSTEMS:
-LEVEL1
-LEVEL 2
Any level will generally depend on
the capacity of the community to
pay monthly bill, and on the
communitys lifestyle
-
7/28/2019 5 Pdw (Selection of App Tech)
7/10
FOR ROADS:
- ROAD WIDTH SELECTION
Selection of Road Width willdepend on the following:
1. Traffic Volume
2. Mode of Transportation3. Geographical Location and
Condition
-
7/28/2019 5 Pdw (Selection of App Tech)
8/10
Continuation of ROADS:
- APPLICATION OF DESIGN LIMITSa. 1 layer of gravelling for road
improvement
b. 2 layers of gravelling for earth road and
road construction
c. If possible, road profile should
generally follow the existing slope of
the area/old roadd. PCCP should only be along critical
slopes or should not exceed a volume
of 180 m3 whichever is smaller
-
7/28/2019 5 Pdw (Selection of App Tech)
9/10
Social and Environmental Safeguards
In adherence to the provisions of the Loan
Agreement (LA) and existing laws of thecountry, the Project observes the social and
environmental safeguards policies set forth
during project implementation
-
7/28/2019 5 Pdw (Selection of App Tech)
10/10
Social and Environmental Safeguards
Aspects of Project safeguards:
1. Social Safeguards e.g proponent barangay to observeactivities during the selection and implementation phase of sub-
project to include the ff: land acquisition, resettlement and
rehabilitation of project affected persons; safety; IndigenousPeoples concern; the respect of cultural practices in IP areas;
establishment of property ownership used for the sub-project;
and the practice of just compensation for people affected by the
proposed sub-project.
2. Environmental Safeguards
covers compliance toexisting laws required by the Environmental Impact
Assessment (EIA) such as; Environmental Compliance
Certificate (ECC), Certificate of Non-Coverage (CNC), and
Environmental Management Plan (EMP)