5108879 14 01 1000 rev0 transmission protection
TRANSCRIPT
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
1/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
2/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0
Notice
This document and its contents have been prepared and are intended solely for AL GHAIL POWER LLCsinformation and use in relation to protection application of their 33kV transmission system
ATKINS ENERGY assumes no responsibility to any other party in respect of or arising out of or in connectionwith this document and/or its contents.
Document History
Job number: 5108879 Document ref: 5108879/14.01/1000
Revision Purpose description Originated Checked Reviewed Authorised Date
Rev 0 First Version GV VAM KS JS 20/04/12
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
3/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
4/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0 4
1. Introduction
Al Ghail Power LLC operates two power plants in the Emirate of Ras Al Khaimah. With the approval ofGovernment of Ras Al Khaimah, Al Ghail Power LLC intends to interconnect both power plants with 33KVTransmission line from Al Ghail area to Al Hamra area in Ras Al Khaimah. This 33kV transmission system is
hybrid line comprising sections of underground cable and overhead lines. The existing 33kV switchgearpanel houses Main and Backup Protections. This report examines suitability of existing Protections at both AlGhail and Al Hamra ends and suggest suitable Protection requirement for the hybrid transmissionapplication.
1.1. Abbreviations
The abbreviations used in this document are as follows:
OHL - Over Head Line
AAAC - All Aluminium Alloy Conductor
UG Cable - Underground Cable
IED - Intelligent Electronic Device
+Seq Imp - Positive sequence impedance in Ohms/kM
Zero Seq imp - Zero sequence impedance in Ohms/kM
KN - Residual compensation factor
P.U. impedance - Per Unit Impedance
2. Application CheckThis section examines the application check for suitable protection for the 33kV Transmission system. The33kV Transmission system connecting Al Ghail and Al Hamra Power stations is hybrid line comprisingsections of underground cables and over head lines. Details are as below
Al Ghail end Al Hamra end
Al Ghail end: 1Cx500sq.mm, Cu; 1 run; 2 Circuits; Length=1km
33kV OHL AAAC, Single conductor; double circuit; Length=45km
Al Hamra end: 1Cx500sq.mm, Cu; 1 run; 2 Circuits; Length=6.2km
Cables
Over Head Line
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
5/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
6/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
7/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0 7
Z1 P.U. impedance =
=..= 1.62 P.U.
Z0 = Zero Seq Imp of line = (0.623+j0.244) x1+ (0.2234+j1.4203) x45+ (0.623+j0.244) x6.2
Z0 = Zero Seq Imp of line = (14.54+j 65.67) = 67.2677.51
Z0 P.U. impedance =
=..= 6.17 P.U.
Transformer impedance = 12.72% at 31.5 MVA.
On 100MVA Base, transformer impedance =.. 100= 40.38% = 4.038 P.U.
Effective impedance when two transformers are operated in Parallel = 2.109 P.U
Al Ghail end
Zone 1 Settings = 80% of line length = 0.8 x 52.2 = 41.76kM
This corresponds to 1 Km of Underground cable plus 40.76kM of Overhead Line
Z1 = +Seq Imp of line = (0.0521+j0.144)x1+ (0.0754+j0.3616)x40.76 = (3.12+j14.88)
Z1 = +Seq Imp of line = 15.2078.15 =..= 1.39 P.U. ----------------------------------(1)
Z0 = Zero Seq Imp of line = (0.623+j0.244) x1+ (0.2234+j1.4203) x 40.76 = (9.73+j58.135)
Z0 = Zero Seq Imp of line = 58.9480.5 =..= 5.41 P.U.--------------------------------(2)
KN Residual compensation factor =
1= .. 1= 0.96------(3)
Zone 2 Settings = 150% of line length = 1.5 x 52.2 = 78.3kM
Z1 = +Seq Imp of line = 1.5 x (3.77+j 17.31) = (5.655+j25.965) = 26.5777.71
Z1 = +Seq Imp of line = ..= 2.44 P.U.---------------------------------------------------------(4)
Z0 = Zero Seq Imp of line = 1.5 x (14.54+j 65.67) = (21.81+j98.505) = 100.8977.51
Z0 = Zero Seq Imp of line = =.. = 9.264 P.U.------------------------------------------------(5)
KN Residual compensation factor =
1= .. 1= 0.93---(6)
Zone 3 Settings = 200% of line length = 2 x 52.2 = 104.4kM
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
8/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
9/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
10/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
11/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0 11
Table 3. Differential Relay Vendor List
Vendor Type of Protection
ABB RED 670
Alstom P54x series
Siemens 7SD 610
Schweitzer EngineeringLaboratories, Inc.
SEL-411L
Toshiba GRL100
2.2.3.1. CT and VT requirements
CT requirement
The performance of a protection function will depend on the quality of the measured current signal.Saturation of the current transformer (CT) will cause distortion of the current signal and can result in a failureto operate or cause unwanted operations of some functions. Consequently CT saturation can have aninfluence on both the dependability and the security of the protection. The protection IED should be designedto permit heavy CT saturation with maintained correct operation.
The current transformer ratio is mainly selected based on power system data for example, maximum load.However, it should be verified that the current to the protection is higher than the minimum operating valuefor all faults that are to be detected with the selected CT ratio. The minimum operating current is different fordifferent functions and normally settable so each function should be checked. The current error of the currenttransformer can limit the possibility to use a very sensitive setting of a sensitive residual overcurrent
protection. If a very sensitivesetting of this function will be used it is recommended that the current transformer should have an accuracy
class which have an current error at rated primary current that is less than 1% (for example, 5P). If current
transformers with less accuracy are used it is advisable to check the actual unwanted residual current duringthe commissioning.
With regard to saturation of the current transformer all current transformers of high remanence and lowremanence type that fulfill the requirements on the rated equivalent secondary e.m.f.VKnee can be used.
Detailed CT requirement calculations will be done after finalizing the following details
1. Type of protection to be used2. Maximum fault level in the system3. CT secondary resistance4. Lead resistance5. CT ratio6. Burden of the IED used
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
12/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0 12
VT requirement
The performance of a protection function will depend on the quality of the measured input signal. Transientscaused by capacitive voltage transformers (CVTs) can affect some protection functions. Magnetic orcapacitive voltage transformers can be used.
The capacitive voltage transformers (CVTs) should fulfill the requirements according to the IEC 600445
standard regarding ferro-resonance and transients. The ferro-resonance requirements of the CVTs are
specified in chapter 7.4 of the standard.The transient responses for three different standard transient response classes, T1,T2 and T3 are specifiedin chapter 15.5 of the standard. CVTs according to all classes can be used.Most of the new generation protection IED has effective filters for these transients, which gives secure andcorrect operation with CVTs.
2.2.3.2. Additional Functions
Broken Conductor detection 46BC
The majority of faults on a power system occur between one phase and ground or two phases and ground.These are known as shunt faults and arise from lightning discharges and other over voltages which initiateflashovers. Alternatively, they may arise from other causes such as birds on overhead lines or mechanicaldamage to cables etc. Such faults result in an appreciable increase in current and hence in the majority ofapplications are easily detectable.Another type of unbalanced fault that can occur on the system is the series or open circuit fault. These canarise from broken conductors, maloperation of single phase switchgear, or single-phasing of fuses. Seriesfaults will not cause an increase in phase current on the system and hence are not readily detectable bystandard protection. However, they will produce an unbalance or asymmetry between currents in the threephases. This can be detected by almost all new generation IEDs. Generally this function is integrated with inthe Main protection IED.
Under Voltage Protection 27
In the majority of applications, under voltage protection function will be available to detect loss of voltageconditions. The threshold value selected should be less than single phase voltage depressions due to earthfaults. The voltage threshold setting for the under voltage protection should be set at some value below thevoltage excursions which may be expected under normal system operating conditions. This threshold isdependent upon the system in question but typical healthy system voltage excursions may be in the order of-10% of nominal value.Time delay shall depend upon the time for which the system is able to withstand a depressed. This can bedetected by almost all new generation IEDs. Generally this function is integrated with in the Main protectionIED.
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
13/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0 13
3. Conclusion
From the foregoing sections, we wish to infer the following
1. Existing Protections Solkor N- 7SG813 and MBCI are not suitable and hence have to be replaced.
2. Distance Protection is not suitable for this application
3. Line differential protection working on digital communication technology will be best suited for thisapplication. Major IED manufacturers in the market Viz ABB, Siemens, Alstom, SEL, etc. have linedifferential protections in their product range.
4. Other monitoring and protection functions Viz. Broken conductor and under voltage functions can beintegrated with the main protection.
5. Existing BACKUP Protection can be retained.
6. New IED can be fitted in the existing switchgear panel and interfaced to existing tripping circuits aftersite confirmation.
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
14/29
Private and confidentialAtkins 5108879/14.01/1000/Rev 0
Appendices
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
15/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0
Appendix A. Single Line Diagram of33 kV Transmission System
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
16/29
GENERATOR - 1
11kV, 33MW
GENERATOR - 2
11kV, 33MW
TRANSFORMER 1
11kV/33kV
YNd11
TRANSFORMER 2
11kV/33kV
YNd11
VT
VT
VT
VT
TRANSFOR
11kV/33
YNd1
TRANSFOR
11kV/33
YNd1
1km CABLE
1km CABLE
6.2km CABLE
6.2km CABLE
21
ZONE 1
ZON
DISTANCE PROTECTION SOLUTION
OVER HEAD LINE
OVER HEAD LINE
11kV AL GHAIL
SUBSTATION33kV AL GHAIL
SUBSTATION
33kV AL HAMRA
SUBSTATION
TIME
TIME
ZONE 1
ZONE 2
ZONE 3
OUTGOING
11kV FEEDERS
DISTANCE PROTECTION AT
AL HAMRA END MAY ENCROACH
INTO 11kV SYSTEM -
NOT DESIRABLE
ZOM - ZERO SEQUENCE MUTUAL
IMPEDANCE IMPACT ZONE
MEASUREMENTS
21 21
21
8.2km CABLE
33kV A
SUBS
ZOM
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
17/29
UNIT PROTECTION SOLUTION
GENERATOR - 1
11kV, 33MW
GENERATOR - 2
11kV, 33MW
TRANSFORMER 1
11kV/33kV
YNd11
TRANSFORMER 2
11kV/33kV
YNd11
VT
VT
VT
VT
1km CABLE
1km CABLE
6.2km CABLE
6.2km CABLE
87L
OVER HEAD LINE
OVER HEAD LINE
11kV AL
GHAIL
SUBSTATION
33kV AL GHAIL
SUBSTATION
33kV AL HA
SUBSTAT
87L 87L
87L
OUTGOING
11kV FEEDERS
ZOM - ZERO SEQUENCE MUTUAL
IMPEDANCE DO NOT IMPACT ZONE
MEASUREMENT
OPTIONAL
OPTIONAL
OPTIONAL
OPTIONAL
DIGITAL COMMUNICATION INTERFACE
UNIT PROTECTION
ZONE
UNIT PROTECTION
ZONE
DIGITAL COMMUNICATION INTERFACE
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
18/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
19/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
20/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
21/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0
Appendix C. Red/Green Markups
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
22/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
23/29
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
24/29
33 kV Interconnection of Al Ghail and Al Hamra Power Plants33kV Transmission System Protection Application
Private and confidentialAtkins 5108879/14.01/1000/Rev 0
Appendix D. Sample Specification
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
25/29
The IED shall be suitable for protection, control and monitoring of
overhead lines and cables for all voltage levels in solidly or impedance
grounded networks. The IED shall be of phase-segregated design for two and up
to five line ends; it shall also be possible to apply up to two power transformers
in the protected zone. It shall even be possible to apply a small power
transformers connected to a line tap without having a line differential IED
installed at the tap and still get selectivity with overcurrent protections on the
low voltage side of the power transformer. The IED shall be based on advanced
and proven algorithms and an easy and efficient upgrade of the IED
functionality shall be possible. A tool for user-friendly engineering and
disturbance handling shall be available. It shall be possible to integrate
protection and control functionality for several objects in the IED e.g. back-up
protection for power transformers and reactors. The IED shall have complete
functionality for single or multi-breaker arrangements with single or three phase
tripping. At least five independent parameter setting groups shall be included.
The IED shall have extensive self-supervision including analog channels. In
order to achieve cost effective engineering, testing and commissioning shall
preconfigured, ready to use IEDs for different applications be available. If
needed, it shall be easy to modify the configuration. At new installations or at
extensions and replacements in existing installations shall it be possible to
integrate the IED into substation automation or monitoring system or use theIED as a stand-alone multifunction unit.
Sample specification
It shall be possible to equip the IED with a large HMI for local operation
of breakers and disconnectors and visualization of single line diagrams with
positions indications of included breakers and disconnectors. For the line
differential protection shall individual phase currents in 1 breaker and
Multi-breaker arrangements are connected to the IED without external
summation for improved through fault stability. A restrained dual biased
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
26/29
operate characteristic shall be used and the highest phase current in any line
shall be utilized as bias current. Charging current compensation for increased
sensitivity for long lines or cables shall be included. The IED shall be suitable
for multiplexed; route switched or dedicated fibre communication networks.
Two time synchronization methods shall be available, the echo-method when
channels with stable and equal delays in both directions are used and GPS to be
used in switched networks with unequal channel delays in both directions.
The communication channel shall be continuously monitored and an automatic
switchover to a redundant channel shall be possible. For line differential
communication it shall be possible to select between a master-master system or
a master-slave system depending on the functional or economic requirements.
An automatic switchover to master-slave communication shall take place
if an interruption occurs in one communication channel in a master-master
communication system. It shall be possible to transfer eight binary signals
between the IEDs. Communication modules for dedicated fibre communication
for short and long distances (>60 km) shall be available. Testing of the completeline differential scheme shall be possible to perform from one freely selected
IED included in the protection scheme. A high impedance differential
protection for tee-feeders shall be possible to include in the IED. A back-up
high speed full-scheme distance protection with at least three zones shall
be possible to include in order to get fault clearance in case of communication
failure, it shall be possible to have the distance protection continuously inoperation or only released for operation at communication failure.
The distance protection shall have a characteristic that will give load
encroachment discrimination and load current compensation of the reactance
line in the first zone in order to avoid overreach. It should be possible to set
each distance protection zone in forward, reverse or non-directional mode. Each
zone shall have individual settings of reactive and resistive reach. No trip for
reverse faults is accepted for a forward looking zone as long as the requirements
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
27/29
on the CTs are fulfilled. Separate phase selection and automatic switch into
fault logic shall be included.
For communication with a distance protection at the remote end shall
permissive, blocking and intertrip scheme communication logic be included.
Power swing detection function and current reversal and weak-end infeed logic
shall be available. It shall be possible to include instantaneous overcurrent
functions for phase and earth faults and time delayed directional/non-directional
overcurrent functions with inverse and definite time characteristic with at least
three steps for phase and earth faults. Scheme communication logic and current
reversal and week-end infeed logic for directional residual overcurrent
protection shall be possible to include. Other current functions such as thermal
overload with alarm and trip steps and breaker failure protection with short reset
time shall also be possible to include in the IED. Stub protection for multi-
breaker arrangements and breaker pole discordance protection shall be
available. Over and under-voltage protection with at least two steps, over and
under-frequency functions and rate-of-change frequency functions shall also bepossible to include in the IED.
For secondary system supervision shall fuse failure and current circuit
supervision is available. The IED shall be provided with programmable logic
for tripping and indications as well as a high number of logic blocks and timers
for user adaptation. Apparatus control for control and supervision of breakers,
disconnectors and earthing switches with interlocking modules for differentswitchgear arrangements should be possible to include.
Synchro/energizing check and synchronizing function as well as auto-
reclosing function for high-speed and/or delayed auto-reclosing for single or
multi-breaker arrangements shall be available. Monitoring functions such as
service values for U, I, P, Q, S, f and power factor shall be included and
supervision of mA input signals from transducers shall be possible to include.
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
28/29
Pulse counter logic for counting of externally generated binary pulses from an
energy meter shall be available. A disturbance recorder which can handle at
least 20 analog channels and at least 60 binary signals and that can record the
last 50 disturbances shall be included. It should be possible to record the sum of
selected analog currents. An event recorder that can handle up to 150 time
tagged events per disturbance and that can record the last 50 disturbances shall
also be included. An accurate fault locator with compensation for load current
and mutual zero sequence impedance for double circuit lines shall be available.
The IED shall be provided with a front mounted human machine interface
(HMI) and a front port for connection of a personal computer. The HMI shall
include LEDs for status indication and at least 15 configurable LEDs for alarm
indication. The IED shall be provided with communication interface for
connection to substation automation system and substation monitoring system.
IEC 61850-8-1 and IEC 60870-5-103 communication protocol shall be
available. The IED shall meet the IEC 61850 standard in every respect and
interoperability with other manufactures IEDs and tools should be verified.It shall be possible to select different mounting alternatives such as rack, flush
or wall mounting.
Depending of the required numbers of I/O modules in the IED shall 1/1 x
19, x 19and x 19 cases are available.
Power supply modules from 24 to 250 DC +/- 20 % shall be available.
GPS time synchronization module with GPS receiver used for timesynchronization shall be available.
A test switch for mounting in connection with the IED should be available.
-
8/10/2019 5108879 14 01 1000 Rev0 Transmission Protection
29/29
Contact Name
Atkins India Pvt. Ltd.10
thFloor, Safina Towers
3 Ali Askar RoadBangalore 560096
Telephone: +91 (80) 4019199Fax: +91 (80) 41475822