    BAPL RELOCATION OF EXISTING OVERHEAD HT LINE ACROSS AIRPORT AT ANDAL

    MONTHLY PROGRESS REPORT

    SEPTEMBER 2013

  • 2 | P a g e

    Table of CONTENTS

    Page No.

    1. Executive Summary 3

    2. Package-wise status 4-9

    3. Major Highlights 10-11

    4. Areas of concern with Mitigation Plan 13

    5. Engineering Status 14-16

  • 3 | P a g e

    1.0 EXECUTIVE SUMMARY

    This report for the month ending 30TH September 2013 records the progress of activities

    during the month and provides early warnings for possible delays to the major project

    milestones. Critical activities and areas of concern have been identified and highlighted

    along with mitigation measures to be taken.

    The major scope of work for the project is mentioned below

    M/s. L & T had been engaged for diversion of 400 KV & 220 KV WBSETCL lines

    and 220 KV DVC line

    Relocation of existing OH HT line across Airport at Andal is in progress for

    WBSETCL 400 KV D/C line

    Diversion work for WBSETCLs 220 KV line has already started from 31-08-2013

    onwards within BAPL area.

    Areas of Concern:

    i. Obtaining approval from DVC for diversion of existing 220 KV DVC line

    ii. Right of Way (ROW) issues for all the three lines

  • 4 | P a g e

    2.0 PACKAGE WISE STATUS The following Table-1 represents the details of Summary Progress Status with

    reference to various Packages as identified for this project.

    Table-1

    S N Package Scope Ordered on E D C Status

    1

    33 KV S/C

    BULK

    POWER

    SUPPLY

    FOR

    AIRPORT

    Incoming power

    from Ukhra S/s

    and energisation

    of Airport S/s.

    Overhead

    route

    length14.60

    KM

    UG cable

    laying 1.050

    KM

    The National

    Electrical

    Works

    31.12.13

    93 PCC poles

    out of 261 have

    been erected.

    4 rail poles out

    of 36 erected.

    GTP Approval

    received on

    08.03.2013 for

    completion of

    erection in

    balance

    locations by

    12.8 M rail

    poles at

    Amlouka &

    Sorpi areas

    Further erection

    of rail poles in

    Amlouka &

    Sorpi areas

    could not be

    carried out due

    to stiff

    resistance from

    land owners

  • 5 | P a g e

    Alternate route

    alignment

    survey under

    progress from

    last pole

    erected to edge

    of airport and

    thereafter along

    ADDA road

    before passing

    under airport

    and runway.

    The drawal/

    construction of

    33 KV S/C Bulk

    Power Supply

    line from

    existing local

    power supply

    grid of West

    Bengal State

    Electricity

    Distribution

    Company

    Ltd.(WBSEDCL

    ) to upcoming

    airport under

    construction by

    BAPL at Andal,

    Durgapur have

    been completed

    and the system

    have been

  • 6 | P a g e

    energized

    successfully at

    08:15 PM on

    21st. August

    2013

    Note: An alternate

    proposal is being

    discussed &

    worked out

    keeping in view

    the budget and

    cost saving aspect

    and formulation of

    the same will be

    effected in

    consultation with

    WBSEDCL after

    confirmation of

    the load growth

    plan from airport

    operations team.

    This load growth

    data will also be

    the decisive factor

    whether this line

    is required to be

    constructed or

    not.

  • 7 | P a g e

    2

    WBSEDCL

    33 KV D/C

    HT LINE

    DIVERSION

    Diversion of 33

    KV D/C

    WBSEDCL

    power line

    running across

    the Airport area.

    Total diversion

    route length of

    6.8 KM - OH 6.3

    KM & UG Cable

    0.5 KM

    STERLING &

    WILSON

    30.09.13

    100 Rail poles

    erected over 3.3

    K.M stretch

    Insulator &

    Structure erected

    on completed.

    Further erection

    of rail poles in

    Amlouka & Sorpi

    areas could not be

    carried out due to

    stiff resistance

    from land owners

    Alternate proposal

    for diverting from

    intermediate pole

    erected up to

    edge of airport

    and thereafter by

    UG Cable through

    airport periphery

    submitted to

    WBSEDCL for

    approval.

    Note: Approval of

    proposal obtained.

    WO issued by

    WBSEDCL.

    Negotiation with

    S&W in progress.

  • 8 | P a g e

    3

    400KV

    WBSETCL

    line

    diversion

    Relocation of

    lines along with

    supply & fixing

    of conductor,

    insulator,

    hardware, earth

    wire etc.

    Larsen &

    Toubro Ltd

    31.12.13

    Check survey

    completed

    Stub and

    Template

    supplied at site for

    SA - 28 sets, SB -

    5 sets,

    SD+NT,+3&6-12

    Sets, SD - 14

    sets, SD+9 -4

    sets, DD - 4 sets

    G.I Earthing pipe-

    102 Sets

    400KV Tower

    parts-450 MT

    ROW under

    progress by L&T

    in consultation

    with BAPL

    Foundation

    completed for

    location no.

    13/2,14/0,15/0 -

    Circuit 1 & 2

    outside BAPL

    area

    Foundation

    completed for

    location no.

    3A/0,3A/1,4/0,5/1,

    5/2,6/0,Circuit 1 &

    2 inside BAPL

    area and 5/0 ,AP-

    7A for circuit 2

  • 9 | P a g e

    Conductor

    inspection

    complete.

    4

    220 KV

    WBSETCL

    line

    diversion

    Relocation of

    lines along with

    supply & fixing

    of conductor,

    insulator,

    hardware, earth

    wire etc.

    Larsen &

    Tubro Ltd.

    31.12.13

    Stub and

    Template

    supplied at site for

    LT2-(+9&12 M)-2

    Set, LT2-

    (NT,+3&6 M)-8

    Sets,ST2-2 Sets,

    T2-1 Set,

    ST2(NT,+3&6 M)-

    2 Sets,

    T2(NT,+3&6 M)-1

    Set,

    MT2(NT,+3&6 M)-

    1 Set, 220 KV

    Tower parts-270

    MT

    Foundation work

    completed for

    location no. AP 7,

    AP-6, AP-5.

    Foundation work

    outside BAPL area

    to commence

    subsequently after

    resolving ROW

    issues

    5

    220 KV DVC

    line

    diversion

    Relocation of

    lines along with

    supply & fixing

    of conductor,

    insulator,

    Larsen &

    Tubro Ltd.

    31.12.13

    Site work to

    commence after

    receipt of approval

    of diversion

    proposal from

  • 10 | P a g e

    hardware, earth

    wire etc.

    DVC followed by

    resolution of ROW

    issues.

    Note: DVC

    proposal still not

    firmed up due to

    lack of survey

    work which is

    pending for

    reasons of ROW.

    Until the proposal

    is firmed up with

    all other

    necessary

    documents no

    progress can be

    made in this

    regard

  • 11 | P a g e

    3.0 Major highlights

    Sl No. Activity Description Status

    1

    Follow up with WBSEDCL for approval of

    revised 33kV Line Diversion route.

    The fresh revised proposal has been

    approved by WBSEDCL. The existing WO

    on S & W will have to be amended as per

    new scope of work and site work to be

    commenced.

    2 Work front available with L & T for

    WBSETCLs 400kV Tower foundation

    work.

    Tower location nos. 7/0 for both

    circuits inside BAPL Aerotropolis

    area is held up due to land dispute.

    Tower location no. 8/0 for Circuit I

    inside BAPL Aerotropolis area held

    up due to overlapping of realigned

    Tamra Nala passing through the

    area of two legs of proposed tower.

    The excavated Nala alignment has

    to be realigned further away to

    make area for the leg foundations.

    The said area is flooded with Tamra

    Nala water and the diversion

    followed by foundation work can

    only be carried out after monsoon

    and after drying up of the area

  • 12 | P a g e

    3 33 KV S/C Temporary Bulk Power

    Supply

    The drawal/ construction of 33

    KV S/C Bulk Power Supply line

    from existing local power supply

    grid of West Bengal State

    Electricity Distribution Company

    Ltd. (WBSEDCL) to upcoming

    airport under construction by

    BAPL at Andal, Durgapur have

    been completed and the system

    have been energized

    successfully at 08:15 PM on

    21st. August 2013.

    The DC Power Supply and

    associated Incoming/Outgoing

    Control Panels have been

    installed and commissioned.

    4 Foundation work for 220kV WBSETCL

    Towers

    Foundation work completed at location

    no. AP 7, AP-6, AP-5 .

  • 13 | P a g e

    4.0 Areas of concern with mitigation plan

    Sl

    No.

    Areas Critical issues Mitigation

    Plan

    Actio

    n By

    Remarks

    1

    220KV AP-1 TO

    AP-6 SURVEY

    REPORT

    Survey submission to Bankura

    for accord of approval. Then

    onwards after approving it from

    Bankura it has to be submitted to

    WBSETCL kolkata office for

    accord of approval after which

    L&T can be given Go Ahead

    clearance to start foundation

    work at site.

    The entire

    activity is

    planned to be

    completed by 06-

    09-2013

    BAPL/T

    CE

    Approval

    obtained

    with certain

    comments

    for

    incorporation

    . L&T to

    revise

    accordingly.

    2 DVC AND

    WBSETCL

    SHUT DOWN

    PROGRAM

    We have to Initiate Strategy for

    the Shut down Program and start

    discussion with competent

    authorities of WBSETCL & DVC

    for accord of Approval from their

    end. A No. of "Hold" Points is

    dependent on this activity.

    Scheduled to be

    completed by 05-

    09-2013

    TCE Discussion initiated. Further progress can be made after receiving survey data from L&T.

    3 GANTRY

    DESIGN

    APPROVAL

    Submission of 400kV gantry

    design drawings to WBSETCL

    for accord of approval.

    Submission and

    follow up with

    WBSETCL for

    approval before

    10-09-2013

    BAPL/T

    CE

    Follow up in

    progress.

    Approval

    expected by

    end Oct.

    5 ROW Follow up with L&T for the

    cleared locations.

    Action from 03-

    09-2013

    onwards

    BAPL/T

    CE

    Discussions

    in progress

    with local

    leaders,

    administratio

    n and others.

  • 14 | P a g e

    5.0 Engineering status

    A) Vendors drawing approval status- SEPT-13

    Sl

    No Drawing Number

    Drawing

    Description

    Date of

    Receipt

    Planned

    Date of

    Issue to

    WBSETCL

    Remarks

    a) -

    SUBMISSION OF

    GA DRAWINGS OF

    400KV SB, SD

    TYPE AND DD

    TYPE TOWERS

    Directly

    submitted

    by L&T to

    WBSETCL

    22-08-2013

    CAT-B

    approved

    b) -

    GTP OF

    EARTHWIRE 19-08-2013 29-08-2013

    Commented

    c) BIL/LNTECC/EW01-02, Rev R0

    DRUM DRAWING

    OF EARTHWIRE 19-08-2013 29-08-2013

    Commented

    d) -

    GTP OF

    EARTHWIRE 30-08-2013

    Not Issued

    till date

    Commented

    e) BIL/LNTECC/EW01-02, Rev R1

    DRUM DRAWING

    OF EARTHWIRE 30-08-2013

    Not Issued

    till date

    Commented

    f) O13070-T-TL-8S-GA-0103 SHEET 1 OF 8, REV R1

    GA OF +0M BASE (TF)FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    g) O13070-T-TL-8S-GA-0103 SHEET 2 OF 8, REV R1

    GA OF +0M BASE (LF)FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    h) O13070-T-TL-8S-GA-0103 SHEET 3 OF 8, REV R1

    GA OF BASIC BODY FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    i) O13070-T-TL-8S-GA-0103 SHEET 4 OF 8, REV R1

    GA OF K-FRAME FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    j) O13070-T-TL-8S-GA-0103 SHEET 5 OF 8, REV R1

    GA OF K-FRAME VIEW A-10 FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    k) O13070-T-TL-8S-GA-0103 SHEET 6 OF 8, REV R1

    GA OF GIRDER FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    l) O13070-T-TL-8S-GA-0103 SHEET 7 OF 8, REV R1

    GA OF C.A. FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    m) O13070-T-TL-8S-GA-0103 SHEET 8 OF 8, REV R1

    GA OF PEAK FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

  • 15 | P a g e

    n) O13070-T-TL-8S-GA-0104 SHEET 1 OF 1, REV R1

    GA OF +3M B.E. FOR TOWER TYPE A

    08-08-2013

    29-08-2013

    CAT-B approved

    o) O13070-T-TL-8S-GA-0105 SHEET 1 OF 1, REV R1

    GA OF +6M B.E. & VIEW E4 FOR TOWER TYPE A

    08-08-2013 29-08-2013

    CAT-B approved

    p) O13070-T-TL-8S-AS-0002 SHEET 1 OF 1, REV R0

    DETAILS OF 22MM DIA DSHACKLE

    08-08-2013 29-08-2013

    CAT-B approved

    q) O13070-T-TL-8S-AS-0003 SHEET 1 OF 1, REV R0

    DETAILS OF 20MM DIA HANGER ROD

    08-08-2013 29-08-2013

    CAT-B approved

    r) BOM/LE130242/A/006, REV R0

    BOM OF +3M EXTN A TYPE TOWER (400KV S/C)

    08-08-2013 29-08-2013

    CAT-B approved

    s) BOM/LE130242/A/003, REV R1

    BOM OF NORMAL TOWER FOR A TYPE TOWER (400KV S/C)

    08-08-2013

    29-08-2013

    CAT-B approved

    t) - AVIATION LIGHTS -

    NIGHT MARKERS

    16-08-2013 Not Issued

    till date

    Not approved

    u) 013149-T-TL-8D-DC-001

    DESIGN BASIS

    REPORT FOR

    GANTRY

    23-08-2013

    29-08-2013

    Not approved

    v) 013149-T-TL-8D-DC-002 DESIGN OF 400KV

    GANTRY (G22) 23-08-2013 29-08-2013

    Not approved

    w) 013149-T-TL-8D-DC-003

    DESIGN OF 400KV

    GANTRY (G14-

    WITHOUT PEAK)

    23-08-2013

    29-08-2013

    Not approved

    x)

    -

    400kV HARDWARE

    DRAWINGS

    05-09-2013 Not approved

    y)

    -

    AVIATION

    OBSTRUCTION

    LIGHTS (AIRCRAFT

    WARNING LIGHT)

    OF M/S INSTA

    POWER LIMITED.

    30-08-2013 Not approved

    z) - STRING TEST

    REPORT

    01-09-2013 In process

  • 16 | P a g e

    B) summary status of vendor drawing approval

    Estimated No of Drawings for

    Approval Drawings Approved Balance Drawings to be

    Approved

    125 nos 59 nos 66 nos