5709e september
DESCRIPTION
proj scheduleTRANSCRIPT
-
1 | P a g e
BAPL RELOCATION OF EXISTING OVERHEAD HT LINE ACROSS AIRPORT AT ANDAL
MONTHLY PROGRESS REPORT
SEPTEMBER 2013
-
2 | P a g e
Table of CONTENTS
Page No.
1. Executive Summary 3
2. Package-wise status 4-9
3. Major Highlights 10-11
4. Areas of concern with Mitigation Plan 13
5. Engineering Status 14-16
-
3 | P a g e
1.0 EXECUTIVE SUMMARY
This report for the month ending 30TH September 2013 records the progress of activities
during the month and provides early warnings for possible delays to the major project
milestones. Critical activities and areas of concern have been identified and highlighted
along with mitigation measures to be taken.
The major scope of work for the project is mentioned below
M/s. L & T had been engaged for diversion of 400 KV & 220 KV WBSETCL lines
and 220 KV DVC line
Relocation of existing OH HT line across Airport at Andal is in progress for
WBSETCL 400 KV D/C line
Diversion work for WBSETCLs 220 KV line has already started from 31-08-2013
onwards within BAPL area.
Areas of Concern:
i. Obtaining approval from DVC for diversion of existing 220 KV DVC line
ii. Right of Way (ROW) issues for all the three lines
-
4 | P a g e
2.0 PACKAGE WISE STATUS The following Table-1 represents the details of Summary Progress Status with
reference to various Packages as identified for this project.
Table-1
S N Package Scope Ordered on E D C Status
1
33 KV S/C
BULK
POWER
SUPPLY
FOR
AIRPORT
Incoming power
from Ukhra S/s
and energisation
of Airport S/s.
Overhead
route
length14.60
KM
UG cable
laying 1.050
KM
The National
Electrical
Works
31.12.13
93 PCC poles
out of 261 have
been erected.
4 rail poles out
of 36 erected.
GTP Approval
received on
08.03.2013 for
completion of
erection in
balance
locations by
12.8 M rail
poles at
Amlouka &
Sorpi areas
Further erection
of rail poles in
Amlouka &
Sorpi areas
could not be
carried out due
to stiff
resistance from
land owners
-
5 | P a g e
Alternate route
alignment
survey under
progress from
last pole
erected to edge
of airport and
thereafter along
ADDA road
before passing
under airport
and runway.
The drawal/
construction of
33 KV S/C Bulk
Power Supply
line from
existing local
power supply
grid of West
Bengal State
Electricity
Distribution
Company
Ltd.(WBSEDCL
) to upcoming
airport under
construction by
BAPL at Andal,
Durgapur have
been completed
and the system
have been
-
6 | P a g e
energized
successfully at
08:15 PM on
21st. August
2013
Note: An alternate
proposal is being
discussed &
worked out
keeping in view
the budget and
cost saving aspect
and formulation of
the same will be
effected in
consultation with
WBSEDCL after
confirmation of
the load growth
plan from airport
operations team.
This load growth
data will also be
the decisive factor
whether this line
is required to be
constructed or
not.
-
7 | P a g e
2
WBSEDCL
33 KV D/C
HT LINE
DIVERSION
Diversion of 33
KV D/C
WBSEDCL
power line
running across
the Airport area.
Total diversion
route length of
6.8 KM - OH 6.3
KM & UG Cable
0.5 KM
STERLING &
WILSON
30.09.13
100 Rail poles
erected over 3.3
K.M stretch
Insulator &
Structure erected
on completed.
Further erection
of rail poles in
Amlouka & Sorpi
areas could not be
carried out due to
stiff resistance
from land owners
Alternate proposal
for diverting from
intermediate pole
erected up to
edge of airport
and thereafter by
UG Cable through
airport periphery
submitted to
WBSEDCL for
approval.
Note: Approval of
proposal obtained.
WO issued by
WBSEDCL.
Negotiation with
S&W in progress.
-
8 | P a g e
3
400KV
WBSETCL
line
diversion
Relocation of
lines along with
supply & fixing
of conductor,
insulator,
hardware, earth
wire etc.
Larsen &
Toubro Ltd
31.12.13
Check survey
completed
Stub and
Template
supplied at site for
SA - 28 sets, SB -
5 sets,
SD+NT,+3&6-12
Sets, SD - 14
sets, SD+9 -4
sets, DD - 4 sets
G.I Earthing pipe-
102 Sets
400KV Tower
parts-450 MT
ROW under
progress by L&T
in consultation
with BAPL
Foundation
completed for
location no.
13/2,14/0,15/0 -
Circuit 1 & 2
outside BAPL
area
Foundation
completed for
location no.
3A/0,3A/1,4/0,5/1,
5/2,6/0,Circuit 1 &
2 inside BAPL
area and 5/0 ,AP-
7A for circuit 2
-
9 | P a g e
Conductor
inspection
complete.
4
220 KV
WBSETCL
line
diversion
Relocation of
lines along with
supply & fixing
of conductor,
insulator,
hardware, earth
wire etc.
Larsen &
Tubro Ltd.
31.12.13
Stub and
Template
supplied at site for
LT2-(+9&12 M)-2
Set, LT2-
(NT,+3&6 M)-8
Sets,ST2-2 Sets,
T2-1 Set,
ST2(NT,+3&6 M)-
2 Sets,
T2(NT,+3&6 M)-1
Set,
MT2(NT,+3&6 M)-
1 Set, 220 KV
Tower parts-270
MT
Foundation work
completed for
location no. AP 7,
AP-6, AP-5.
Foundation work
outside BAPL area
to commence
subsequently after
resolving ROW
issues
5
220 KV DVC
line
diversion
Relocation of
lines along with
supply & fixing
of conductor,
insulator,
Larsen &
Tubro Ltd.
31.12.13
Site work to
commence after
receipt of approval
of diversion
proposal from
-
10 | P a g e
hardware, earth
wire etc.
DVC followed by
resolution of ROW
issues.
Note: DVC
proposal still not
firmed up due to
lack of survey
work which is
pending for
reasons of ROW.
Until the proposal
is firmed up with
all other
necessary
documents no
progress can be
made in this
regard
-
11 | P a g e
3.0 Major highlights
Sl No. Activity Description Status
1
Follow up with WBSEDCL for approval of
revised 33kV Line Diversion route.
The fresh revised proposal has been
approved by WBSEDCL. The existing WO
on S & W will have to be amended as per
new scope of work and site work to be
commenced.
2 Work front available with L & T for
WBSETCLs 400kV Tower foundation
work.
Tower location nos. 7/0 for both
circuits inside BAPL Aerotropolis
area is held up due to land dispute.
Tower location no. 8/0 for Circuit I
inside BAPL Aerotropolis area held
up due to overlapping of realigned
Tamra Nala passing through the
area of two legs of proposed tower.
The excavated Nala alignment has
to be realigned further away to
make area for the leg foundations.
The said area is flooded with Tamra
Nala water and the diversion
followed by foundation work can
only be carried out after monsoon
and after drying up of the area
-
12 | P a g e
3 33 KV S/C Temporary Bulk Power
Supply
The drawal/ construction of 33
KV S/C Bulk Power Supply line
from existing local power supply
grid of West Bengal State
Electricity Distribution Company
Ltd. (WBSEDCL) to upcoming
airport under construction by
BAPL at Andal, Durgapur have
been completed and the system
have been energized
successfully at 08:15 PM on
21st. August 2013.
The DC Power Supply and
associated Incoming/Outgoing
Control Panels have been
installed and commissioned.
4 Foundation work for 220kV WBSETCL
Towers
Foundation work completed at location
no. AP 7, AP-6, AP-5 .
-
13 | P a g e
4.0 Areas of concern with mitigation plan
Sl
No.
Areas Critical issues Mitigation
Plan
Actio
n By
Remarks
1
220KV AP-1 TO
AP-6 SURVEY
REPORT
Survey submission to Bankura
for accord of approval. Then
onwards after approving it from
Bankura it has to be submitted to
WBSETCL kolkata office for
accord of approval after which
L&T can be given Go Ahead
clearance to start foundation
work at site.
The entire
activity is
planned to be
completed by 06-
09-2013
BAPL/T
CE
Approval
obtained
with certain
comments
for
incorporation
. L&T to
revise
accordingly.
2 DVC AND
WBSETCL
SHUT DOWN
PROGRAM
We have to Initiate Strategy for
the Shut down Program and start
discussion with competent
authorities of WBSETCL & DVC
for accord of Approval from their
end. A No. of "Hold" Points is
dependent on this activity.
Scheduled to be
completed by 05-
09-2013
TCE Discussion initiated. Further progress can be made after receiving survey data from L&T.
3 GANTRY
DESIGN
APPROVAL
Submission of 400kV gantry
design drawings to WBSETCL
for accord of approval.
Submission and
follow up with
WBSETCL for
approval before
10-09-2013
BAPL/T
CE
Follow up in
progress.
Approval
expected by
end Oct.
5 ROW Follow up with L&T for the
cleared locations.
Action from 03-
09-2013
onwards
BAPL/T
CE
Discussions
in progress
with local
leaders,
administratio
n and others.
-
14 | P a g e
5.0 Engineering status
A) Vendors drawing approval status- SEPT-13
Sl
No Drawing Number
Drawing
Description
Date of
Receipt
Planned
Date of
Issue to
WBSETCL
Remarks
a) -
SUBMISSION OF
GA DRAWINGS OF
400KV SB, SD
TYPE AND DD
TYPE TOWERS
Directly
submitted
by L&T to
WBSETCL
22-08-2013
CAT-B
approved
b) -
GTP OF
EARTHWIRE 19-08-2013 29-08-2013
Commented
c) BIL/LNTECC/EW01-02, Rev R0
DRUM DRAWING
OF EARTHWIRE 19-08-2013 29-08-2013
Commented
d) -
GTP OF
EARTHWIRE 30-08-2013
Not Issued
till date
Commented
e) BIL/LNTECC/EW01-02, Rev R1
DRUM DRAWING
OF EARTHWIRE 30-08-2013
Not Issued
till date
Commented
f) O13070-T-TL-8S-GA-0103 SHEET 1 OF 8, REV R1
GA OF +0M BASE (TF)FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
g) O13070-T-TL-8S-GA-0103 SHEET 2 OF 8, REV R1
GA OF +0M BASE (LF)FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
h) O13070-T-TL-8S-GA-0103 SHEET 3 OF 8, REV R1
GA OF BASIC BODY FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
i) O13070-T-TL-8S-GA-0103 SHEET 4 OF 8, REV R1
GA OF K-FRAME FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
j) O13070-T-TL-8S-GA-0103 SHEET 5 OF 8, REV R1
GA OF K-FRAME VIEW A-10 FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
k) O13070-T-TL-8S-GA-0103 SHEET 6 OF 8, REV R1
GA OF GIRDER FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
l) O13070-T-TL-8S-GA-0103 SHEET 7 OF 8, REV R1
GA OF C.A. FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
m) O13070-T-TL-8S-GA-0103 SHEET 8 OF 8, REV R1
GA OF PEAK FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
-
15 | P a g e
n) O13070-T-TL-8S-GA-0104 SHEET 1 OF 1, REV R1
GA OF +3M B.E. FOR TOWER TYPE A
08-08-2013
29-08-2013
CAT-B approved
o) O13070-T-TL-8S-GA-0105 SHEET 1 OF 1, REV R1
GA OF +6M B.E. & VIEW E4 FOR TOWER TYPE A
08-08-2013 29-08-2013
CAT-B approved
p) O13070-T-TL-8S-AS-0002 SHEET 1 OF 1, REV R0
DETAILS OF 22MM DIA DSHACKLE
08-08-2013 29-08-2013
CAT-B approved
q) O13070-T-TL-8S-AS-0003 SHEET 1 OF 1, REV R0
DETAILS OF 20MM DIA HANGER ROD
08-08-2013 29-08-2013
CAT-B approved
r) BOM/LE130242/A/006, REV R0
BOM OF +3M EXTN A TYPE TOWER (400KV S/C)
08-08-2013 29-08-2013
CAT-B approved
s) BOM/LE130242/A/003, REV R1
BOM OF NORMAL TOWER FOR A TYPE TOWER (400KV S/C)
08-08-2013
29-08-2013
CAT-B approved
t) - AVIATION LIGHTS -
NIGHT MARKERS
16-08-2013 Not Issued
till date
Not approved
u) 013149-T-TL-8D-DC-001
DESIGN BASIS
REPORT FOR
GANTRY
23-08-2013
29-08-2013
Not approved
v) 013149-T-TL-8D-DC-002 DESIGN OF 400KV
GANTRY (G22) 23-08-2013 29-08-2013
Not approved
w) 013149-T-TL-8D-DC-003
DESIGN OF 400KV
GANTRY (G14-
WITHOUT PEAK)
23-08-2013
29-08-2013
Not approved
x)
-
400kV HARDWARE
DRAWINGS
05-09-2013 Not approved
y)
-
AVIATION
OBSTRUCTION
LIGHTS (AIRCRAFT
WARNING LIGHT)
OF M/S INSTA
POWER LIMITED.
30-08-2013 Not approved
z) - STRING TEST
REPORT
01-09-2013 In process
-
16 | P a g e
B) summary status of vendor drawing approval
Estimated No of Drawings for
Approval Drawings Approved Balance Drawings to be
Approved
125 nos 59 nos 66 nos