![Page 1: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/1.jpg)
6MSD Weekly Scheduling Meeting
Wednesday @ 1:30, MCC Conference Room
October 12, 2011
1) Glance Back and 2-Week Look Ahead (F. Pilat) ................................................... 10 mins
2) PMI Report (P. Collins) ........................................................................................... 5 mins
3) Critical Path Service Provider Reports .................................................................. 25 mins (a) Alignment (Curtis) (b) SRF (Hogan) (c) EESIC (Garza) (d) Software (P. Kjeldsen)
4) Hall C Special Report: Qweak (G. Smith) ............................................................. 20 mins
5) Safety Report: M. Logue ......................................................................................... 5 mins
6) Meeting Recap and Action Items (All) ..................................................................... 5 mins
![Page 2: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/2.jpg)
6MSD: Glance back & look ahead
Fulvia Pilat
6MSD MeetingOctober 12, 2011
![Page 3: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/3.jpg)
Progress Wed Oct 5 – Wed Oct 12Weeks: 22 down, 5 to go (30 days to Physics? November 11)Highlights:• NE Stub: backfilling in progress• NE Stub: utilities work progressed very fast• NE Gate: installation started this morning!• Work with beam started at the gun.• PSS pre‐checks & certifications in progress• C100‐2 : cavity gradient > 20 MV/m in 7 out of 8• C100‐1 : LLRF work, micro‐phonic measurements• Hall C HKS Removal continues, Qweak “mid‐term” survey done• Re‐aligned Primavera and SAD calendar, moved out some FEL and Hall A scope of workAreas of attention:• Halls work appear to be late in the progress schedule…real or reporting ‘hiccups’?• No crisis at this moment in time, but monitor Ops start‐up, C100 and civil work
schedules
![Page 4: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/4.jpg)
2 weeks look ahead• Civil construction work continues:
– NE Stub work (ramp) & Back fill to Grade– Ongoing Hall D Buildings (Counting House, Tagger Area & Service Bldg)
• Finish temporary gate at NE stub tunnel start of injector operations• RECO process officially started, daily meeting • Injector PSS certifications & Injector Hot Checkout• PSS Pre‐Checks & Certifications: NL and SL/BSY/End Stations• Various Systems HCO• C100‐1 & 2 commissioning/testing in tunnel • Restore 5.6 GeV machine (no C100)• RF installation continues in the Linacs• Hall‐A: G2P Beamline work & Target Repair• Hall‐B: HDIce work• Hall‐C: Qweak preps, removal HKS, final survey
![Page 5: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/5.jpg)
6MSD Organization• NO CRs & NTFs have been submitted, reviewed, and approved this week
• Transition 6MSD to operations– PD rotation starts Monday October 17, 0745 and 0800 am meeting revert
to the operations format– Wednesday Progress/Resource Meeting will continue. Hall Physicists to
tell us about preparation for beam (will start today with Hall C, then following with Hall B and Hall A)
– Weekly Thursday 6MSD Planning Team Meetings will be scheduled regularly for coordination and early discussions of lesson learned
– 6MSD team and organization in place until physics running and for lessons learned and 6MSD post‐mortem input to 12MSD organization
![Page 6: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/6.jpg)
PM&IP
6MSD 10/12/11 Weekly Progress Meeting(10/07/11 Data)
Report #22
![Page 7: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/7.jpg)
PM&IP• Schedule Issues: Hall D Phase 3 Tunnel Extension is ~23
Days behind schedule. (Nov. 10th completion date)• Hall A Septum and Target: 18 days behind scheduled
completion of 01 Dec• Hall C: Moller Polarimeter 1 day of float
– Compton Polarimeter 0 float• LCW System Restoration – Acid Flush ?• Ops Start Up Schedule in flux.• FEL – Activities have been removed from the schedule.
• Resource issues: Alignment Week of Oct 17th
![Page 8: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/8.jpg)
PM&IP• Other Schedule Information at
https://www.jlab.org/6MSD_Integrated_Schedule/SCHEDULES/– Two Week Look Ahead - Shows all activities that have started
that are not complete and any activities due to start in the next two weeks
– Critical Path – Shows all MUST activities that have 2 days or less float.
– Schedule Variance - Shows all MUST activities that are not 100% complete and that the Start/Finish dates have slipped by at least 5 days.
![Page 9: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/9.jpg)
6MSD weekly mtg ‐ Align Oct‐12 Page 1 of 3
Shutdown Work Summary Organization: Alignment
Name: Chris Curtis
Date: 12th Oct, 2011
Last Week
Work That Went Better Than / As Expected:
• Hall A dump penetration survey completed.
• PEPPo solenoid aligned.
• Cryomodule spaceframe QC check completed.
• Hall D control survey completed
• Q‐Weak‐HKS mid‐stage teardown survey completed.
• North‐east accelerator quick check completed.
Work That Went Slower Than Expected, Delays, and Issues:
• West arc stack 15 re‐checked and re‐aligned.
Ongoing Shutdown Work
Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns
12 GeV Arcs X Oct 21 Final alignment of NE arc magnets
Started today
G2p X TBD Harp & Dump fiducialization When availableHall C – Q‐Weak X TBD Target alignment Scheduled for next weekPEPPo X Oct 21 Alignment of PEPPo components Scheduled for next week
![Page 10: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/10.jpg)
6MSD weekly mtg ‐ Align Oct‐12 Page 2 of 3
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns
Hall D X October Solenoid alignment Second phase of solenoid alignmentG2p X TBD Alignment of all downstream
components and target Additional alignment for target repair
Hall B X TBD Complete target /beamline alignment
October
Q‐Weak X TBD HKS monitoring; final alignment of detectors etc.
End of October
New Work Requests Requiring Schedule Changes: • None
Permits Not Already in Hand (hot work, lifting, blind penetrations): • None
Significant Problems Pending (delays, technical issues, resource issues, scheduling): • Beginning to see light at the end of the accelerator tunnel.
Staffing Outlook: • OK
![Page 11: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/11.jpg)
6MSD weekly mtg ‐ Align Oct‐12 Page 3 of 3
Hall C Elevations
![Page 12: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/12.jpg)
Shutdown Work Summary_12OCT2011_JH Page 1 of 2
Shutdown Work Summary Organization: SRF
Name: John Hogan
Date: 12‐OCT‐2011
Last Week
Work That Went Better Than Expected: • N/A
Work That Went Slower Than Expected, Delays, and Issues: • N/A
Ongoing Shutdown Work
Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns
C100‐01 Checkout X LLrf control; Microphonics damping investigation
Making good progress.
C100‐02 Checkout X SRF commissioning. Making good progress.
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns
C100‐01 Checkout X LLrf control ongoing. Added HOM waveguide filters in preparation of beam tests.
C100‐02 Checkout Standard SRF performance commissioning activities. LLrf will confirm performance.
Checkout on schedule for completion prior to hot checkout, 24‐OCT‐2011.
![Page 13: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/13.jpg)
Shutdown Work Summary_12OCT2011_JH Page 2 of 2
Project & Customer Status Completion Tasks Comments/Concerns
New Work Requests Requiring Schedule Changes: • N/A
Permits Not Already in Hand (hot work, lifting, blind penetrations): • N/A
Significant Problems Pending (delays, technical issues, resource issues, scheduling): • The time to install and checkout C100‐02 is very tight; there is no float for ‘unknown’ problems.
Staffing Outlook: • Ok.
![Page 14: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/14.jpg)
Shutdown Work Summary10‐12‐11 Page 1 of 2
Shutdown Work Summary Organization: EESIC
Name: Omar Garza
Date: 10‐12‐11
Last Week
Work That Went Better Than Expected:
Work That Went Slower Than Expected, Delays, and Issues:
Ongoing Shutdown Work
Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/ConcernsHall C Qweak Cavity Electronics
X Ongoing Digital Section Testing Order DAC Brd. / Parts Building Chassis
Near Completion DAC Brds and Components on‐hold due to acct. freeze $$
Hall A G2P Low Current BPM Electronics
X Ongoing Complete PC Brds. <2wks Assemble Brds. In‐house Brd. Changes at 90% completion
Hall A G2P Diagnostics
X Ongoing Cables completed Harp 1 installed, Harp 2 assembled, YAG assembled & tested
Awaiting Driver Chassis
Hall A G2P Motor Driver Chassis
X Ongoing Testing Unit delivered to Software
12Gev SRF Vacuum Instrumentation
X Ongoing SL23, 24, 25 Going Well
![Page 15: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/15.jpg)
Shutdown Work Summary10‐12‐11 Page 2 of 2
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/ConcernsInjector PePPo
X Ongoing Beam Scrappers wiring
Faraday Cup wiring
Viewer wiring completed
BPMs
Waiting for beamline component installation
Ops AIPBSY (I to V) Module
X On‐hold Brd Procurement, Assembly, Testing Software
Software Procure Brds – Onhold ‐ $$
Accelerator Network Firewall Configuration
X Ongoing Phase I – Segment config. Phase II – Failover config. Phase III – Rules configuration Phase IV – Network Implementation
Phase I completed Going Well
Accelerator Maintenance
X Ongoing Diagnostics – EA, SL Vacuum ‐ pumps
Controls complete BPMs complete Diagnostics – NL complete
New Work Requests Requiring Schedule Changes:
Permits Not Already in Hand (hot work, lifting, blind penetrations):
Significant Problems Pending (delays, technical issues, resource issues, scheduling):
Staffing Outlook:
![Page 16: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/16.jpg)
6MSD Page 1 of 2
Shutdown Work Summary Organization: Controls Software
Name: Pam Kjeldsen
Date: October 12, 2011
Last Week
Work That Went Better Than/As Expected: •
Work That Went Slower Than Expected, Delays, and Issues: •
Ongoing Shutdown Work
Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns
PEPPo X 17‐Oct‐11 Viewers Ready to test with hardware PEPPo X 17‐Oct‐11 Dipole power supply controls Test stand operational; Software
development underway PEPPo X 17‐Oct‐11 Discriminator/scaler for data
acquisition Software installed in field; Waiting for hardware in order to test
12 GeV X 1‐Oct‐11 Low‐level RF Some progress; “RF on” sequence work continuing
12 GeV X 14‐Oct‐11 RF screens Some progress; Work continues G2P X 14‐Nov‐11 New harp controls Chassis received; Software
Development progressing G2P X 15‐Nov‐11 New BPM controls Position and calibration algorithm to
be developed; chassis in 2 weeks G2P X 21‐Sep‐11 Viewers Ready to test with hardware
![Page 17: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/17.jpg)
6MSD Page 2 of 2
Project & Customer Status Completion Tasks Comments/Concerns
G2P X 3‐Oct‐11 Septum magnet controls Waiting for information for last 5%; PSS/MPS X 15‐Nov‐11 CAEN power supply Good progress; Communications
with power supply through Ethernet established
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns
12 GeV X 14‐Nov‐11 IOC boot management CASA X 1‐Nov‐11 MO monitorHall A X 1‐Nov‐11 IOCs moved to accelerator
network Implementation and 80% of testing done; testing remains for 20%
Operations X LCW monitoring Acquisition plans ongoingOperations X 1‐Nov‐11 Control system write logging Wider installation Operations X 14‐Nov‐11 Digital image management Camera and network ready;
computer to be installed Operations X 1‐Nov‐11 Confirm network changes do not
impact accelerator or endstation operation
Testing under way
New Work Requests Requiring Schedule Changes: • None
Permits Not Already in Hand (hot work, lifting, blind penetrations): • None
Significant Problems Pending (delays, technical issues, resource issues, scheduling): • LCW monitoring requires a new server; Plant Engineering is pursuing its acquisition
Staffing Outlook: • OK
![Page 18: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/18.jpg)
Qweak Status & Plans for Beam (10’)
• Status (Greg Smith)– Qweak Run II not a new setup. A continuation…– Run I major down times predominantly:
• QTOR PS, DS beamline vacuum, Target pump– 6MSD used to harden these systems
• And perform maintenance, make improvements to other systems
• Plans for Beam (Roger Carlini)– Plans for 1st week (11/11/11)– Plans for remaining time
![Page 19: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/19.jpg)
• Compton: plan to finish work this week– Doubled gain with new mirrors to ~1.6 kW– Improved e-det effi (4th plane, better cables, etc.)– PbW photon detector gain stabilized
• Moller: unexpected large quad problem– Q3 boneyard, Q2 Q3. Beamline reassembled. – Pull vacuum & stack Pb after Moller tgt swap. – Survey & alignment next week.
• Pivot halo target:– Being re-designed for hor. offset beam
• Improved cavity BCMs:– New electronics on track (Musson, Allison)– 2 new cavities added to beamline– 4 new cables pulled
Upstream Status
![Page 20: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/20.jpg)
Target Status• Pump: replaced scored stator, replaced worn bearings• Loop: replaced broken thermometry• Heater: Installed higher power (3 4 kW) heater PS• Cell: replaced both entrance & exit windows• Coolant: replaced lossy 15K xfer line• Solid tgts: improved heat xfer ( more Ibeam), installed
spare bkg tgts, replaced broken thermometry• Replaced non-SS piping with SS• Added more filters (magnetic & gas)• Painting ballast/storage tanks, new inventory of H2
• Performed 20K He cooldown test last week– Test was successful: target is ready!
• Tgt survey & alignment scheduled for Oct. 18th & 19th
![Page 21: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/21.jpg)
2 mm
15 mm Φ, 0.127 mm thick
exit window vacuum side
exit window vacuum sideentrance window 0.097 mm thick
gapsscoring
![Page 22: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/22.jpg)
Solid Targets
Looking Downstream
Looking Upstream
2 axis motion system
![Page 23: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/23.jpg)
• R1 GEMs: – Replacing with pin diodes. Install lead “flapper”
• RII HDC’s: – Resolved an interference– Replace 1 of 4 chambers with working spare (next week)
• Main Detectors: – Compressed poor glue joint on 1 detector– Installed new rail system to move bkg detector around– Re-covering detector shield hut this week
• Downstream beamline at end of hall:– New SS bellows (2’ φ) leak tight– New welded Al spool piece with viewer leak tight– Waiting on quartz window & Ti bolts– Install these parts this week or early next week, with new
vacuum window, & pump out DS beamline• Dump Tunnel:
– Leak in He dump line found & fixed– Diffuser removed– New ion chambers & rad hard cabling– Repair dump tunnel dehumidifier
Downstream Status
![Page 24: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/24.jpg)
Upgrade to DS “Viewer” RegionProblematic - Run 1 Design All Al (at small radius) - Run 2 Design
~10” Φ SS Aluminum Stainless Steel Aluminum
24”
H2O Cooled Window
H2O Cooled Window
~2 cm
![Page 25: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/25.jpg)
Watching carefully…:
• Dumpline dehumidifier– Parts arrive only 10/31. Punt?
• Ballast tank painting– Work order: by Friday…
• DS beamline reassembly– Within a week, to have time to deal with
potential problems • 4K flow re-certification
![Page 26: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/26.jpg)
• Hall C/Qweak appear on track to be ready for beam well before the end of this month, thanks to the hard work and dedication of many people, including: – Dave Hamlette & the radcon group, Neil Wilson &
company, Rick Taylor & installation group, Greg Marble, Rick Gonzales & the vacuum group, survey & alignment group, Dave Meekins & the target group, Omar Garza, John Musson & Trent Allison, the magnet test group, Kelly Mahoney & Rich Wright, Joe Beaufait, and many others.
– And of course Andy Kenyon & our Hall C techs!• Thanks to all of you who have helped & continue
to help us be ready on time! THANK YOU!
Thanks!
![Page 27: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/27.jpg)
Plan for Nov. 11th – 19th• Qweak indeed wants to take 1-pass beam between Nov. 11-19 if
possible.
• The request is to receive (after initial tune-up beam) approximately 2 days of low intensity (200pA-10nA) running for our tracking measurements. We need to do this first before activation of the drift chamber region causes higher than ideal leakage currents in our wire chambers.
• We would then like a couple of days of transverse running with high current beam ~150uA's - using both horizontal and vertical transverse setups - say 1 day of each + mini-spin dance.
• After which we would like to go into a mode as close as possible to "production" - high current with 100% long. polarization. Some of this period would be used to allow Jay to briefly study the front end position corrector feedback system and the experiment to characterize how close we are setup to a "parity quality beam" condition.
![Page 28: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/28.jpg)
Goals for Nov. 20th ‐….
• Production Running– >50% of time at 150µA to 180µA on LH2
– >25% time:• 2 shifts/week on Moller running (@ a few µA’s)• 1µA to 100µA on on Al• 200pA to 100nA for tracking (~once a month)• Some specialty configurations – transverse, spin
dance, …– <25% Exp + Acc down time
![Page 29: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/29.jpg)
0%
5%
10%
15%
20%
25%
0 28 56 84 112 140 168 196 224 252 280
ΔA/A (%
)
Calendar day of scheduled beam
Run 1 Run 2: 70% Goal Run 2: 50% Run 2: 30%
ΔA/A Projections (assumes 235 ppmMD, 87% pol)
summerdown
2.0%
2.5%
3.0%
3.5%
4.0%
4.5%
5.0%
100 128 156 184 212 240 268 296
ΔA/A (%
)Calendar day of scheduled beam
30% efficient
50%70%
Statistical goal = 2.1%
![Page 30: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/30.jpg)
![Page 31: 6MSD Weekly Scheduling Meeting - Jefferson Lab We… · 6) Meeting Recap and Action Items (All) ..... 5 mins . 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12,](https://reader034.vdocument.in/reader034/viewer/2022042208/5eaaf2e4d996f248163fdeb4/html5/thumbnails/31.jpg)
Silica is an OSHA National Emphasis Program due to its hazards of long term lung diseases. Jack-hammering is known to release silica dust.
The jack-hammering job was begun with some water on the operation but no respiratory protection (not ID’d in AHA) & had some visible dust. Blowers supplied some air to the area. After the lack of a respirator was presented to the contractor, they assigned respirator qualified workers.
Air samples the next day ultimately indicated potential over-exposure due to inadequate level of respiratory protection. Contractor reassessed respirator used to better type for future work.
This potential exposure became a reportable event.