Considerations and Processes Selecting Construction Materials for Testing and Selecting the Laboratory
to carry out the Testings
Considerations and Processes - Selecting
Construction Materials for Testing and the Laboratory to
carry out the Testing
Objectives of the Presentation
• Explain what is a construction material
• Explain what to consider when selecting construction
materials for testing
• Define construction materials testing laboratory
• Explain what to consider when selecting construction
materials testing laboratory
• Explain Construction materials and testings used in
JICA IV works
2
Considerations and Processes - Selecting
Construction Materials for Testing and the Laboratory to
carry out the testing
Objectives of the Presentation
• Explain the process, criteria and roles/responsibilities
selecting testing laboratory in JICA IV
• Explain the challenges selecting testing laboratory in
JICA IV Nangarhar Project
• Make recommendations for best practices in selecting
testing laboratory for construction works
3
Key Words used in the presentation
Construction - the process of creating and building
infrastructure or a facility.
Material - the substance or substances of which a thing is
made or composed. Example, plastic, stone, cement, etc.
Laboratory - a facility that provides controlled conditions in
which scientific or technological research, experiments, and
measurement may be performed.
Testing – the means by which the presence, quality, or
genuineness of anything is determined
Challenges - the situation of being faced with something
that needs great mental or physical effort in order to be done
successfully and therefore tests a person's ability
4
Key terminology to understand the presentation
Construction Materials – same as building materials. Any
material which is used for construction purposes (natural or
manufactured)
Testing Laboratory - a facility that provides controlled
conditions in which the presence, quality, or genuineness of
anything can be tested.
Construction Materials Testing Laboratory – a facility for
carrying out test on construction material and construction
products to determine if material’s or product’s properties
meet required or allowed structural performance and
deformation permitted.
5
Key terminology to understand the presentation
Quality - the standard of something as measured against
other things of a similar kind; the degree of excellence of
something.
Quality Assurance – the process or activity for providing
confidence that quality requirements will be fulfilled.
Administrative and procedural activities implemented in a
quality system so that requirements and goals for a product,
service or activity will be fulfilled.
Quality Control - The observation techniques and activities
used to fulfill requirements for quality. A part of quality
management focused on fulfilling quality requirements.
QAQC Plan – a plan that details how quality will be
managed (assured & controlled) in a project or activity.6
Construction Materials
Purpose
• For the construction of various types of structures used in
civil engineering or works;
• Serve as binders and aggregates, and structural
components, such as cement, water, prefabricated units
• Serve as elements to be installed in buildings, such as
reinforced-concrete panels, toilet stalls, and door and
window
• To provide technical functionality and building personality
• To contribute to the sustainability on energy efficiency
• To provide compatibility with climatic, cultural, and
appealing conditions
7
Construction Materials
Examples
• Gravel, rock dust, crushed stone, and sand
• Concrete, cement, plaster, gypsum plaster, and lime
• Metals, steel
• Timbers, thatch, plant parts
• Glass, ceramics, asbestos, fiberboard
• Mud and clay, bricks, terracotta,
• Rubber, plastics, sealants, adhesives, bitumen
• Fabrics, papers and membranes, and mineral wool
• Ice and snow
8
Construction Materials
Consideration for selection for testing
• Consider the function of the component;
• Consider the construction method or processes to be
performed, before, during and after construction;
• Consider the technical specifications requirements, such
as, the material or product performance requirements,
and testing performance requirements;
9
Testing to carry out during construction
• Safe working practices, testing processes and methods;
• Structural tests – Load, Impact, Tensile, Exposure site,
Strength, Weatherability, Durability, Settlement, Fatigue,
Cable loading on support systems, Air tightness, Water
tightness, Light reflectance value, Slip resistance,
Chemical, etc.
• Non-structural tests – Permeance, Pressure, Equipment
Operations Performance, etc.
11
How is the type of test selected
• The function of the component;
• Construction method or processes to be performed,
before, during and after construction;
• The technical specifications requirements, such as, the
material or product performance requirements, and
testing performance requirements;
12
Construction Materials Testing Laboratory
Definition
• a facility used to carry out test on construction material
and construction products.
Purpose
• To determine if material’s or product’s properties meet
required or allowed structural performance and
deformation permitted
13
Construction Materials Testing Laboratory
Activities
• Testings – chemical composition, unknown materials and
contamination, corrosion, strength, curing and density,
fines, plastic limits, particle size distribution, moisture
content, binder content and grading, physical and
mechanical, packaging, etc.
• Analysis – chemical trace, contamination, bearing
capacity, deformation, failure, thermal, elemental,
Inorganic, etc.
• Investigation – structural, forensic, fracture and failure,
etc.14
Selecting the laboratory to carry out testing of
construction materials and products
Consider
• The Technical Specification requirements in accordance
with the contract
• The construction materials specified and nominated for
testing, investigation, and analysis and results
• The experience and qualification of the team to carry out
the selection and the contractor(s)
• Selecting based on trial and error
• Independent evaluation of a laboratory or a laboratory
which has been evaluated by an independent third party
• Laboratory accreditation and qualification
• Selection evaluation criteria17
Construction materials used in JICA IV Project
• Earth/soil, gravel, sand, boulder rock, stone, mud
• Cement, water, Concrete, Brick
• Polyethylene film, polyvinyl chloride, polypropylene and
polyethylene filter cloth
• Steel bars, stainless steel, steel wire
• Timber, Plywood,
• Acrylic emulsion paint, plastic emulsion paint, blackboard
paint, synthetic resin oil paint, dust oil
• Ceramic wall tiles, terrazzo tiles, Straw, timber, Glass,
• Copper core electrical cable
• UPVC high pressure pipes, GI sheet 24 gage pipes
• Asphalt, Bitumen, Asphalt cement
18
Construction testings used in JICA IV Project
• Tensile test
• Trial mix, Slump test, Air volume test, Air-dried unit
volume weight test, Strength test, Unit volume weight test
• Step drawdown test, Constant discharge test, Time
recovery test, discharge test, pumping test .
19
Selecting testing laboratory in JICA IV Project
Process
• Review the Project Technical Specifications to determine
the type of construction materials and Testings to be
implemented
• Prepare list of construction materials and testings to be
implemented (in the Specs and function consideration)
• Visit laboratory and evaluate accreditation, calibration
certificate, performance certificate, facilities, testing
equipment, personnel, record documentation, etc.
• Select based on evaluation criteria and scoring, etc
• Submit selected laboratories for acceptance,
endorsement, and approval
20
Selecting testing laboratory in JICA IV Project
Criteria
• Laboratory must be accredited and certificated to operate
and provide testing services
• Laboratory must be visited and the facilites, testings
equipment, personnel, record documentation, etc. check
and passed for use
• Laboratory must be able to carry out the tests required in
the project technical specifications and other considered
testings
• Laboratory must pass the evaluation criteria and scoring,
• Laboratory must be accepted by FC, endorsed by DPM
and approved by PM
21
Selecting testing laboratory in JICA IV Project
Roles and responsibilities
• QAQC Engineer - determine the type of construction
materials and Testings to be implemented; list of
construction materials and testings to be implemented;
visit laboratory and evaluate and score; submit selected
laboratory for approval
• Field Coordinator - review laboratory evaluation and
score; accept selected laboratory for endorsement;
• Senior Construction Engineer - review laboratory
evaluation and score; endorse selected laboratory for
approval
• Project Manager - review laboratory evaluation and
score; approve selected laboratory
22
Selecting testing laboratory in JICA IV Project
Challenges
• The few numbers of Laboratory available for evaluation
makes it difficult to have many options to select from
within the Project Zone
• With no tools to check laboratory equipment calibration it
is difficult to determine the efficiency, accuracy and overall
performance and score the laboratory
• Laboratory available do not have the appropriate
technical tools for testing, making it difficult to select
several testing methods
• Without a UNOPS test and calibration methods and
method validation it is difficult to develop test and
methods in a short time
23
Recommendations for best practices in selecting
testing laboratory for construction works
• UNOPS has to have a lab in eastern zone.
• Without calibration methods and method validation no
laboratory should be selected
• If the laboratory is not accredited and certificated to
operate, the laboratory must not be selected
• If the laboratory is accredited and certificated to operate,
but does not have experienced and qualified staff, the
laboratory must not be selected
• There should always be a documented Laboratory
Selection Report
• Sake about Main Branch for important tests
24