acarp roadway development operator workshops march 2009 modelling of gateroad development

29
1 ACARP Roadway Development Operator Workshops March 2009 Modelling of Gateroad Development Ernest Baafi – UOW Geoff Gray – SMS Ian Porter – UOW Osvaldo Rojas - SMS University of Wollongong

Upload: honey

Post on 07-Jan-2016

28 views

Category:

Documents


0 download

DESCRIPTION

ACARP Roadway Development Operator Workshops March 2009 Modelling of Gateroad Development. Ernest Baafi – UOW Geoff Gray – SMS Ian Porter – UOW Osvaldo Rojas - SMS. University of Wollongong. The Development Challenge. Longwall mining is a cost effective means of extracting coal - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

1

ACARP Roadway Development Operator Workshops March 2009

Modelling ofGateroad Development

Ernest Baafi – UOWGeoff Gray – SMSIan Porter – UOWOsvaldo Rojas - SMS

University of Wollongong

Page 2: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

The Development Challenge

• Longwall mining is a cost effective means of extracting coal

• …..provided roadway development can keep pace…

• ACARP initiated a project to assist improving the roadway development process.

2

Page 3: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Modelling The Process

• ACARP recognised the need for modelling tools

• The concept of using dynamic simulation technology was proposed

• UOW and SMS worked with industry experts• Modelling tools and Models developed.

3

Page 4: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Simulation Technology

• Methodology has numerous alias’s• Monte Carlo Simulation• Discrete Event Simulation• Computer Simulation• Simulation Modelling• Dynamic Simulation

4

Page 5: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Simulation Technology

• But not this…

5

British Army WWI Horse Simulator

Page 6: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Simulation Technology

• In our context:• Models operate over time• Dynamic interactions between components• Allow for randomness/variability in operations• Provide animated displays

• ……provide WHAT IF analysis capability.

6

Page 7: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Scope Of Modelling

• Focus On Gate Road Development• 2 heading development

• Modelling will cover operations from face to boot

7

Page 8: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Modelling System For Roadway Development

• Dynamic modelling system• Allows Roadway Development options to be

explored• Predicts:

• Achievable development rates (days/1000m)• Bottlenecks (including unrecorded delays) eg

• Miner waits on shuttle car• Shuttle car waits on miner• Boot end delays• Traffic delays (car interactions)

8

Page 9: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Development Process

9

Page 10: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

RoadSIM – toolkit + models

10

RoadSIM DEVELOPER RoadSIM USERBuilds a Mine Specific Model. Uses a Model for …

Process Improvement Who ? Mine planning/design

UOWMining Engineer Who ?Modelling Consultants Mining Engineer

Process Improvement StaffRequires… Modelling Consultants

Basic Arena SkillsAccess to RoadSim Tool kit Requires…

Basic Excel SkillsAccess to developed RoadSim Model

ARENA SIMULATION

SYSTEM

ARENA RuntimeSYSTEM

Knowledge of Layout/Equipment EXCEL

Issues to Address ???? REPORTS

RoadSIMTool Kit

RoadSIMMODEL

Page 11: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Model – Users

11

RoadSIM DEVELOPER

Builds a Mine Specific Model. Uses a Model for …Process Improvement

Who ? Mine planning/designUOW

Who ?Modelling Consultants Mining Engineer

Process Improvement StaffRequires… Modelling Consultants

Basic Arena SkillsRequires…

Basic Excel SkillsAccess to developed RoadSim Model

ARENA SIMULATION

SYSTEM

ARENA RuntimeSYSTEM

Knowledge of Layout/Equipment EXCEL

Issues to Address ???? REPORTS

RoadSIMTool Kit

RoadSIMMODEL

Page 12: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Model Setup

• Data Required To Set Up The Model• Configuration (roadway dimensions)• Miner cycle times• Support times• Shuttle Car Performance• Operational Availability

• Planned• Unplanned (randomly imposed on the model)

12

Page 13: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Running The Model

• Each Setup is replicated many times• Each replication of the model has the same setup

– but different possible unplanned events.

• Animation to confirm operations

• Reporting available in Excel for assessment.

Page 14: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Animated Display

14

Page 15: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Animated Display

15

Page 16: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Model Output

• Estimates of :• Time to complete a Pillar

• Scheduled operating time per 1000m• First coal to first coal time

• Exposure rates• Metres/Running Hour

• Utilisation of time.

16

Page 17: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Miner Utilisation Definitions

Output – Utilisation Definitions

Utilisation ….

17

Calculated from random interactions in the model

Page 18: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Output – Exposure Rates

18

Page 19: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Case Study Mine

• Mine was selected to test models ability to reproduce past performance

• Mine 1:• 2 Heading Operation• 1 Bolter-Miner• 1 Shuttle car

19

Page 20: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

20

Case Study Mine – Historical Performance

Mine 1 Stats

Pillar Cycle Time (First coal to first coal) 11 days

Exposure Rate (m/op. hour) 1.8 m/op. hr

Exposure Rate (m/rep. run hour) 4 m/rep. run hr

Delay Categories (% of Simulation Time)

Mine Process Planned 0.3

Mine Process Unplanned 0.1

Outbye Services Unplanned 16.2

Panel Engineering Planned 3.6

Panel Engineering Unplanned 3.9

Panel Process Planned 16.3

Panel Process Unplanned 3.1

Sequence Move Planned 15.5

Unscheduled Planned 14.4

Unrecorded Delay 2.0

Page 21: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

21

Case Study Mine – Model vs Historical

Page 22: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

22

Case Study Mine – Model vs Historical

Page 23: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

23

Case Study Mine – Model vs Historical

Page 24: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

24

Case Study Mine – Model Exposure Rate

0.00

0.50

1.00

1.50

2.00

2.50

3.00

3.50

4.00

4.50

5.00

0 20 40 60 80 100 120

Rate

(m/n

et ru

n ho

ur)

Metres Cut

Advance Rate (m/net run hr)

Page 25: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Exploring Options

• Simulation model can be used to explore alternative options

• These can include:• Pillar length• Shuttle car size• Discharge rates• Support times• Others …

25

Page 26: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Exploring Options

• Impact of Support time

26

Page 27: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Exploring Options

• Impact of Shuttle Car Discharge Times

27

3.2

3.4

3.6

3.8

4.0

4.2

4.4

4.6

0 1 2 3 4

m/o

pera

ting

hour

SC Discharge Time (min)

Advance Rate (m/op. hour)

Page 28: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

In Summary…

• ACARP project has resulted in a modelling tool for Australian industry

• RoadSIM is aimed at assisting in evaluating roadway development options

• Provides a What If tool to assist with process improvement.

28

Page 29: ACARP Roadway Development Operator Workshops  March 2009 Modelling of Gateroad  Development

Thanks for your attention…Questions ??

University of Wollongong