accelerated ridge construction · spmt units –abc construction self propelled modular transit...

34
ACCELERATED BRIDGE CONSTRUCTION THE CLAYTON STREET BRIDGE REPLACEMENT Malek Al-Khatib, P.E., Vice President , Project Manager | Louis Berger ASCE & SEAM January 15, 2015

Upload: others

Post on 20-Jun-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

ACCELERATED BRIDGE

CONSTRUCTION

THE CLAYTON STREET BRIDGE

REPLACEMENT

Malek Al-Khatib, P.E.,Vice President , Project Manager | Louis Berger

ASCE & SEAM January 15, 2015

Page 2: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Background

History of the Clayton Street Bridge

• First Massachusetts Bay Transportation Authority (MBTA) transit bridge built using Accelerated Bridge Construction (ABC) methods

• Built in 1911 and modified in 1926

• Deteriorated three-span steel structure with steel bents

• Replaced in 2013 with a single-span steel structure, thus opening up the street and the sidewalks below

• Design completed September 2012

• New structure erected November 2013

Page 3: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

• Located in the Dorchester

neighborhood of Boston,

Massachusetts

• Mix of residential industrial

neighborhoods

• Part of the MBTA Ashmont

Red Line

• Frequent truck route

Location MapDorchester, Massachusetts

Clayton St. Bridge

Quick Facts

Field

Corner

Station

Braintree

Branch

Page 4: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

• Steel elements showed

signs of deterioration

• Original 13’-10”

clearance was not

sufficient for current

truck traffic

• Steel bents blocking the

roadway caused hazards

for motorists and

obstructed sidewalks for

pedestrians

Old StructureCondition

steel bents

Through Girder Deck

Structure

obstructed sidewalks

13’-10” clearance

Page 5: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

Structure

• Low Clearance

• Truck collision damage

proved that low clearance

was an ongoing issue that

had to be fixed

Page 6: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Community and MBTA Red Line Operation

• Residential abutters cross the street from the bridge

• MBTA Red Line trains could not be shut down on

weekdays

• Limited number of possible Red Line weekend

shutdowns

• Coordination with other MBTA construction projects

Notice for public information meeting

Challenges

Page 7: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

Structure

500 ft. radius track curve

Page 8: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

Structure

50 degree bridge skew angle

Page 9: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

Structure

• Converting 3 span

structure to a single span

• Existing abutments

couldn’t sustain the load

increase

Page 10: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

Structure

• Framing Configuration

Page 11: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

MBTA System

• Traction power lines run

through the bridge

• Third rail and heater cables

run through the bridge and

were in poor condition

• Signal and communication

system was outdated and

not well plotted

• Rail sprinkler system runs

through the bridge and was

in poor condition

Page 12: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Challenges

MBTA System

• Conduct testing and tagging of signal and communication cable.

• Replace antiquated signal system and reducing the number of conductor cables from 500 to around 80

• Replace several manholes and junction boxes.

• Cannot combine power and signal cable conduits

• Maintain MBTA System operational.

Rendering for temporary bridge

Page 13: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Construction Site Constraints

• Limited ROW

• Heavy traffic on Clayton Street during rush hours

• City ordinance regarding noise and work hours

• Limited number of possible streets shutdowns

• Coordination with the utility companies

Challenges

Page 14: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

• Clayton Street Bridge

clearance is the highest in

the area.

• Narrow residential one way

streets

• Main streets are congested

weekdays.

ChallengesTraffic Management Plan

(Clayton Closed & Dickens Closed

Page 15: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Weekend Hourly Schedule

Page 16: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Temporary BridgeUsed to re-route MBTA

systems off bridge during

construction

• Temporary bridge built in

Spring 2013 to re-route

cables off existing

structure

• Minimized interference

with train service during

construction

• (Left) temporary bridge

completed with utility

ducts re-routing utilities

Page 17: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

System Work

System work without

interrupting service

• Systems were

replaced, re-routed

and/or upgraded

• New manholes were

installed

• New cables and

junction boxes

improved service

Page 18: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Strengthening Existing Abutments

40ft deep minipiles

85ft long tieback soil

anchors

Installation of tiebacks and mini piles

Page 19: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Strengthening Existing Abutments

40ft deep minipiles

85ft long tieback soil

anchors

Installation of tiebacks and mini piles

Page 20: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Strengthening Existing Abutments

Proposed Bridge

Existing BridgeInstallation of tiebacks and mini piles

Page 21: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Strengthening Existing

Abutments

Installation of Tiebacks

• 85-foot-long tiebacks

installed at design

angle while avoiding

existing steel bents

• Installed during two

weekend street

shutdowns while trains

were operational over

the bridge

Page 22: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Installation of Mini Piles

• 40-foot-long mini piles

cored through top of

existing abutment

• Installed during three

weekend Red Line

shutdowns while

keeping the streets

open below

Strengthening

Existing Abutments

Page 23: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

New Bridge

Constructed on site

• New superstructure was

pre-assembled in the shop

• New superstructure

arrived in five panels and

was fully assembled onsite

• New superstructure was

assembled in yard

adjacent to existing

structure

• New structure was erected

on scaffolding

Page 24: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

SPMT Units – ABC Construction

Self Propelled Modular Transit Units

• Two SPMT Units were used to transport bridge

• SPMT Units moved simultaneously and were controlled

by one operator

• Tires of SPMT Unit had 360º rotation capabilities for

ease of mobility and precision when placing new

structure on bearings

• Steel plates were placed along the path of the SPMT to

ensure proper load bearing capacity

Page 25: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Veteran’s Day

Weekend

• Friday Nov. 8, 2013:

Demolition; preparation

began after last train

• Saturday Nov. 9, 2013 at

noon: Clayton Street was

cleared of debris

Page 26: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Veteran’s Day Weekend

Preparing the Substructure

• Saturday 10 p.m.: Bearings and backwalls were

installed

• Existing backwalls were sawn off and cleaned along

with the existing bridge seats

• New backwalls were installed

• Lesson learned: Place down new bridge prior to

installing backwalls

• New bearings were installed and locations were

confirmed by surveyor

• Lesson learned: Ensure bearings and bearing

plates are level prior to placing down bridge

Page 27: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Veteran’s Day Weekend

Moving the Superstructure

• Saturday 5:30 p.m.: Bridge started to move

• SPMT Units lifted the bridge off the scaffolding at 5:30 p.m. on November 9th

• Media and residents gathered to watch the 500,000lb structure slowly roll into place

• Saturday 10:30 p.m.: Substructure modifications were completed, and the bridge began moving to its final position, and lowered on the new bearings.

• Bridge was successfully placed on the bearings and the track and ballast were replaced

• Sunday Nov. 10, 2013: bridge was completed.

• Monday 12:05: Track work completed for Monday morning service

• Service resumed for Monday morning commuters on schedule

Page 28: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

ABC Planning/Design/Construction

Basic Elements

• Detailed planning, design, and constructability reviews.

• Proposed means and methods included in the bid documents.

• Attention to all details that affect schedule.

• Risk assessment and minimize unforeseen conditions.

• Detailed construction scheduling during the design phase, including hourly schedules and assignment of responsibilities, were necessary for success of weekend installation

• Detailed scheduling and dry-runs with the contractor to ensure smooth delivery

• Collaboration and open communication between owner, contractor and designer ensured a smooth weekend

Page 29: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

ABC Planning/Design/Construction

Benefits of Accelerated Bridge Construction

• By conventional techniques, the replacement would

have taken an additional 10 months and $2 million to

complete

• Conventional methods would have resulted in several

weeks of Red Line and street closure

• Community engagement drove the project schedule

and ultimate success

• Due to proper preparation, work that was initially

scheduled for a 3-day weekend was successfully

completed in a 2-day weekend with no injuries or

accidents

Page 30: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Replacement Sequence 3D Animation

Page 31: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

• The bridge was painted a light grey color to match surroundings

• Formliner was added to the face of the abutment walls

• New sidewalks were constructed and the roadway was paved and cleared

• New street lighting under the bridge

Finishing Touches

formliner

sidewalks

14’-0” clearance

lightings

Page 32: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Before & After

• Clearance was increased from 13’-10” to 14’-0”

• Sidewalks were widened

• Steel bents were removed

• Bird netting was installed to protect bridge seats

• Formliner was added for esthetics

Page 33: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously
Page 34: ACCELERATED RIDGE CONSTRUCTION · SPMT Units –ABC Construction Self Propelled Modular Transit Units • Two SPMT Units were used to transport bridge • SPMT Units moved simultaneously

Planning, attention to details, and partnering = Success