Page 0 of 26
Wisconsin Department of Transportation
Published for Comment 8/27/20
Submitted to FHWA 10/3/19
ADA TRANSITION PLAN 2020 UPDATE
Page 1 of 26
ADA TRANSITION PLAN 2020 UPDATE
THIS PAGE LEFT INTENTIONALLY BLANK
Page 2 of 26
ADA TRANSITION PLAN 2020 UPDATE
TABLE OF CONTENTS
INTRODUCTION ...................................................................................................................................................... 3
CURB RAMP AND SIDEWALK ADA INVENTORY ........................................................................................................ 4
INVENTORY ................................................................................................................................................................... 4
INVENTORY SUMMARY ..................................................................................................................................................... 4
INVENTORY DATA VALIDATION ........................................................................................................................................... 4
DATABASE ..................................................................................................................................................................... 4
ROADSIDE FACILITIES ....................................................................................................................................................... 5
TRANSITION PLAN .................................................................................................................................................. 6
SIX-YEAR PROGRAM ........................................................................................................................................................ 6
STAND-ALONE PROGRAM ................................................................................................................................................. 6
TECHNICALLY INFEASIBLE LOCATIONS .................................................................................................................................. 7
TRAINING ...................................................................................................................................................................... 7
PUBLIC INVOLVEMENT ........................................................................................................................................... 9
OUTREACH ACTIVITIES ...................................................................................................................................................... 9
APPENDIX ............................................................................................................................................................. 10
NOTICE TO THE PUBLIC .....................................................................................................................................................A
ADA WEBSITE ................................................................................................................................................................. B
TITLE VI AND ADA COMPLAINT FORM................................................................................................................................... C
ADA FACILITY COMPLAINT FORM ....................................................................................................................................... D
CURB RAMP AND SIDEWALK ADA INVENTORY DATABASE GIS MAP .............................................................................................. E
SIX-YEAR PROGRAM PROJECTS COMPLETED IN 2019 .............................................................................................................. F
SIX-YEAR PROGRAM PROJECTS SCHEDULED FOR COMPLETION IN 2020 ..................................................................................... G
SIX-YEAR PROGRAM PROJECTS SCHEDULED FOR 2021-27 ...................................................................................................... H
STAND-ALONE PROGRAM LOCATIONS ................................................................................................................................... I
Page 3 of 26
ADA TRANSITION PLAN 2020 UPDATE
I. INTRODUCTION
It is the policy of the Wisconsin Department of Transportation (WisDOT) to ensure that its programs,
services, activities, and facilities are accessible to and usable by individuals with disabilities in
accordance with Section 504 of the Rehabilitation Act of 1973 (Section 504) and Title II of the Americans
with Disabilities Act of 1990 (ADA). The ADA Transition Plan provides information about WisDOT’s
efforts to ensure accessibility on the “Path to Zero” barriers in its public right-of-way. WisDOT’s ADA
Transition Plan was accepted as substantially meeting the regulatory minimum requirements of the ADA
by the Federal Highway Administration (FHWA) on February 25, 2020.
WisDOT’s ADA Transition Plan is a “living document” and is updated annually.1 The Secretary-designee
of WisDOT, Craig Thompson, is the official responsible for the implementation of WisDOT’s ADA
Transition Plan. WisDOT’s ADA Program is administered by the Office of Business Opportunity and
Equity Compliance (OBOEC) in the Division of Transportation System Development. OBOEC coordinates
a multi-disciplinary approach to implement and manage WisDOT’s compliance efforts. These efforts
include curb ramps, roadside facilities (i.e. rest areas) and buildings. The ADA Program Coordinator
addresses complaints, investigates formal grievances, and tracks the overall progress of the
implementation of the ADA Transition Plan. The ADA Program Coordinator also acts as the primary
contact for all public outreach pertaining to discrimination against people with disabilities. Comments
or inquiries and requests for this update in an alternate format should be directed to the ADA Program
Coordinator.
The WisDOT ADA Program Coordinator contact information is:
Taqwanya Smith, Senior Title VI and ADA Coordinator Office of Business Opportunity and Equity Compliance Wisconsin Department of Transportation 4822 Madison Yards Way, 5th Floor South Madison, Wisconsin 53705 Phone: (608) 266-8129 Fax: (608) 267-3641 Email: [email protected]
1 28 CFR §35.150(d)(3)(iii).
Page 4 of 26
ADA TRANSITION PLAN 2020 UPDATE
II. CURB RAMP AND SIDEWALK ADA INVENTORY
A. Inventory
A desktop inventory was conducted in 2014-15 to identify existing curb ramps and sidewalks
along state highways including connecting highways or within the state highway right-of-way.
The inventory was based on visual inspection using WisDOT Photolog, Google Street View, and
satellite imagery. The inventory information was captured as Geographic Information System
(GIS) data.
B. Inventory Summary
The data acquired through the inventory includes approximately 46,000 curb ramp locations.
This data was validated and is noted in the Inventory Data Validation section. For data regarding
sidewalks and shared-use paths along state highways including connecting highways or within
state highway right-of-way, there is a total of 1,483 linear miles with 1,323 linear miles as
sidewalk.
The inventory also provides a snapshot of information as progress is made through the
implementation of the Transition Plan. As projects are completed and field survey data is
provided, inventory data is updated.
C. Inventory Data Validation
A cluster sampling method was used to obtain a level of confidence for validating the desktop
inventory data. Cluster sampling is a statistical methodology designed to address problems of a
widespread geographical population. Rather than taking inventory of all the curb ramps located
on the state highway system, an inventory of clusters provided insight and confidence on
estimating the number of ramps that will likely need to be upgraded.
Three WisDOT urbanized regions – SW, SE and NE – where higher pedestrian traffic exists, were
selected for the cluster sampling areas. These areas contain eight urban corridors which served
as the sampling areas. To verify the sample size as being adequate, a sample size was calculated
based on approximately 50,000 curb ramp locations, with a confidence level of 95%, and a
confidence interval of +/‐5%. This produced a sample size of 384 curb ramp locations to
inventory. A consultant firm, DAAR Corporation, inventoried 524 curb ramps and identified 147
missing curb ramps for a total of 671 possible curb ramp locations in the sample. The statistical
analysis indicated that the number of existing curb ramp locations is 8.3% greater than
expected.
D. Database
The resulting data from the inventory was recorded in the Curb Ramp and Sidewalk ADA
Inventory Database. The Curb Ramp and Sidewalk ADA Inventory Database is an interactive
Geographic Information Systems (GIS) map available for viewing on the ADA website. See
Appendix E – Curb Ramp and Sidewalk ADA Inventory Database GIS map example.
Page 5 of 26
ADA TRANSITION PLAN 2020 UPDATE
The desktop data collected includes:
1. Curb Ramps: Presence or absence of a curb ramp, detectable warning field
presence or absence at street edge of ramp, presence of pattern in curb ramps (i.e.
wire mesh imprint2).
2. Sidewalks/Shared-Use Paths: Presence of sidewalks or shared-use paths along the
state highway including connecting highways or within state highway right-of-way.
3. Sidewalk or Curb Ramp Defects: Some sort of cracking, damage, or tripping hazard
significant enough to be visible in photo imagery.
WisDOT will use field survey data collected as part of the project design and construction
process to update the Curb Ramp and Sidewalk ADA Inventory Database on an ongoing basis.
E. Roadside Facilities
WisDOT’s Roadside Facilities Unit continuously monitors ADA-related issues and updates the
facilities as opportunities arise. This includes curb ramps and sidewalks. In addition,
improvement projects also evaluate conversion to electric-operated ADA doors from air-assisted
ADA doors. The conversion improves reliability of the system. In 2020, ADA doors at Rest Area
13 (Lake Mills) and Rest Area 14 (Johnson Creek) were converted to electric-operated.
The last ADA assessment of roadside facilities was over 20 years ago. The Roadside Facilities
Unit is exploring retaining a consultant to pilot a comprehensive assessment of four locations -
Janesville rest area, Beloit rest area, Beloit SWEF (Safety and Weight Enforcement Facility), and
Madison SWEF. Janesville and Beloit rest areas are two of the most frequently used rest areas
in the state. Beloit SWEF is a Mega SWEF, which includes a large indoor truck inspection area
and 24/7 trucker rest stop facilities. In addition to curb ramps and sidewalks, buildings and
parking lots will also be evaluated. The pilot is expected to be completed in 2021 or 2022.
2 WisDOT standard had been wire mesh imprint which WisDOT believed was acceptable at the time. In 2004, WisDOT standards
were modified following 2002 and 2004 FHWA memos describing ADAAG Detectable Warning requirements.
Page 6 of 26
ADA TRANSITION PLAN 2020 UPDATE
III. TRANSITION PLAN
A. Six-year Program
1. Scope
As a general practice, WisDOT installation or updates of curb ramps is part of its Six-year
Program projects that meet the definition of an alteration per ADA3. WisDOT will continue to
address curb ramps on improvement projects and has a policy to acquire the necessary right-of-
way to allow curb ramps to be constructed or updated on roadway improvement projects that
are defined as an alteration per ADA4. If sufficient right-of-way is not owned and additional real
estate is needed to install an ADA compliant curb ramp or to upgrade an existing curb ramp to
full ADA compliance or to the maximum extent if technically infeasible, the needed real estate
will be acquired to allow the curb ramp work to be constructed. (See FDM 11-46-1.1.5 ADA Curb
Ramp Compliance and Right-of-Way Requirements)
2. Budget
For curb ramp improvements that are to be addressed as part of the Six-year Program, it is
estimated that expenditures will be roughly $15 million for construction costs not including
acquiring right-of-way.
3. Schedule5
It was estimated as part of the 2018-2023 Six-year Program, that approximately 994/year curb
ramp locations would be addressed in 2019 and 2020. In the 2019 construction season, WisDOT
completed 48 improvement projects which installed/updated approximately 1,050 curb ramps
on the state trunk network. See Appendix F – Six-year Program projects completed in 2019 and
Appendix G – Six-year Program projects scheduled for completion in 2020.
It is estimated that 1,000 to 1,500/year curb ramp locations will be addressed beginning in 2021.
These estimates are based on the number of projects in the 2021-2027 Six-year Program that
meet the definition of an ADA alteration. See Appendix H – Six-year Program projects scheduled
for 2021-2027.
B. Stand-alone Program
1. Scope
WisDOT will address curb ramp locations that are not within the Six-year Program in a Stand-
alone Program. These locations will be prioritized based on safety, existing conditions,
complaints, and pedestrian generators (e.g. employment centers, government services,
3Department of Justice/Department of Transportation Joint Technical Assistance on the Title II of the Americans with
Disabilities Act Requirements to Provide Curb Ramps when Streets, Roads, or Highways are Altered through Resurfacing.
4 WisDOT evaluated its improvement concept codes to determine concepts that meet the definition of an alteration per ADA
per USDOJ and USDOT joint technical assistance definitions which require curb ramps to be installed or updated as part of the highway improvement.
5 28 CFR §35.150(d)(3)(iii) requires that if the time period of the transition plan is longer than one year, identify steps that will be taken during each year of the transition period[.]
Page 7 of 26
ADA TRANSITION PLAN 2020 UPDATE
recreational/trail facilities, etc.). A pilot program was initiated in 2019, see item 4 below for
details.
2. Budget
It is estimated that expenditures will be roughly $1-5 million per year for design and
construction costs not including acquiring right-of-way. Yearly allocations to the Stand-alone
Program will be made through the State Highway Rehabilitation (SHR) subprogram.
3. Schedule6
The schedule for the Stand-alone Program is to address all non, Six-year Program curb ramps
within 3 six-year program cycles (18 years). This is separate from the Six-year Program
described in part A. above. It is estimated that approximately 1,000/year curb ramp locations
will be addressed over a six-year period. See Appendix G – Stand-alone Program.
4. Pilot Program
The pilot for the Stand-alone Program began in 2019. The design phase of the pilot will run from
2019 to 2020. The construction phase of the pilot will run from 2020 to 2021. The statewide
program is expected to begin in 2022.
C. Technically Infeasible Locations
Any WisDOT pedestrian facility or features being altered shall be made accessible to full
compliance or the maximum extent feasible, if technically infeasible conditions apply within the
scope of the alteration. WisDOT recognizes that there are locations where it is “technically
infeasible” to bring the facilities or features into compliance due to existing physical site
constraints. Alterations to features, spaces or facilities within public right-of-way are considered
technically infeasible when existing physical site constraints such as underlying terrain, right-of-
way availability, underground structures, adjacent developed facilities, drainage or the presence
of a notable natural or historic feature, make it impracticable to bring the altered elements into
compliance with the U. S. Access Board’s Public Rights-of-Way Accessibility Guidelines
(PROWAG). For these locations where technical infeasibility applies, WisDOT will address
deficiencies, to ensure that the maximum compliance is achieved and shall be documented and
identified as a future project in the work program to be addressed as soon as possible.
D. Training
1. Designing Pedestrian Facilities for Accessibility
This two-day training was designed to ensure that pedestrian facilities and access routes are
properly constructed and maintained for individuals of all abilities. This training also focuses on
proper design and maintenance of pedestrian access routes in new construction or when
existing facilities are altered. Participants are engaged through a power point presentation,
discussion, video demonstrations, small group problem identification, and features a hands-on
outdoor wheelchair, low-vision goggles, white cane exercise. This training was developed to
6 28 CFR §35.150(d)(3)(iii) requires that if the time period of the transition plan is longer than one year, identify steps that will be taken during each year of the transition period[.]
Page 8 of 26
ADA TRANSITION PLAN 2020 UPDATE
provide information for those involved in the design and maintenance of pedestrian facilities,
and for those individuals that ensure the proper adherence to all applicable laws and guidelines.
a. Dates: September 16-17, 2019
b. Attendees: 33
2. 2019 Construction Standards
This training focused on the importance of achieving compliance for curb ramps and upcoming
changes to curb ramps. This training also provided a preview of the new Curb Ramp Compliance
Post Construction Report.
a. Dates: Multiple dates in 2019
b. Attendees: 740
Page 9 of 26
ADA TRANSITION PLAN 2020 UPDATE
IV. PUBLIC INVOLVEMENT
A. Website
WisDOT’s website, wisconsindot.gov/ADA, is where the public can inspect and submit
comments on the 2020 update. The website also includes a link to the Curb Ramp and Sidewalk
ADA Inventory Database GIS map. See Appendix B - ADA Website.
B. Social Media
WisDOT will use social media sites: Facebook, Twitter, and YouTube to drive traffic to the 2020
update with a call to action to submit comments.
C. DMV Electronic Message Board
WisDOT will post brief messages on electronic message boards in DMV Customer Service
Centers statewide saying that the 2020 update is online for public comment.
D. News Releases and Newsletters
WisDOT will provide brief news releases prior to the comment period specifying that the 2020
update is online and available for public comment, see Appendix J - Public Comments and
Results. WisDOT will also provide an article in the department’s weekly Bulletin (internal-facing)
driving WisDOT staff to the 2020 update with a call to submit comments.
E. Public Libraries
WisDOT will provide a notice with a link to the 2020 update for posting on library bulletin boards
to the state’s 16 federated public library systems covering 382 public libraries.
F. Disability Advocacy Organizations
WisDOT will email 43 organizations representing individuals with disabilities and invite them to
inspect and submit comments on the 2020 update.
G. Wisconsin Network of ADA Coordinators Listserv
WisDOT will email 100 municipal ADA Coordinators through the Wisconsin Network of ADA
Coordinators listserv and invite them to inspect and submit comments on the 2020 update.
H. University ADA Coordinators
WisDOT will email 15 University of Wisconsin System ADA Coordinators and invite them to
inspect and submit comments on the 2020 update.
I. Virtual Public Involvement
WisDOT recorded a brief overview presentation using PowerPoint for the web to provide a
broader explanation of the 2020 update and public comment process.
Page 10 of 26
ADA TRANSITION PLAN 2020 UPDATE
V. APPENDIX
A. Notice under the ADA
http://wisconsindot.gov/Pages/doing-bus/civil-rights/titlevi-ada/default.aspx
Page 11 of 26
ADA TRANSITION PLAN 2020 UPDATE
B. ADA Website
https://wisconsindot.gov/Pages/doing-bus/civil-rights/titlevi-ada/ADAcompliance.aspx
Page 12 of 26
ADA TRANSITION PLAN 2020 UPDATE
C. Title VI and ADA Complaint Form
https://wisconsindot.gov/Pages/doing-bus/civil-rights/titlevi-ada/filingcomplaint.aspx
Page 13 of 26
ADA TRANSITION PLAN 2020 UPDATE
D. ADA Facility Complaint Form
https://wisconsindot.gov/Pages/doing-bus/civil-rights/titlevi-ada/ADAcompliance.aspx
Page 14 of 26
ADA TRANSITION PLAN 2020 UPDATE
E. Curb Ramp and Sidewalk ADA Inventory Database GIS map
https://wisdot.maps.arcgis.com/apps/webappviewer/index.html?id=98f74e8262e348b28ab862
2e10532d90 (click here to go to the interactive map)
Page 15 of 26
ADA TRANSITION PLAN 2020 UPDATE
F. Six-year Program projects completed in 2019
Project ID Highway Project Limits Improvement Concept Year Project Status
1005-10-77 IH 039* ILLINOIS STATE LINE - MADISON RECSTE 2019 Removed**
1060-40-97 STH 059 ZOO IC GREENFIELD AVE STH 59 PSRS40 2019 Completed
1100-35-70 IH 894* ZOO FREEWAY BRRHB 2019 Completed
1100-36-70 USH 041 MILWAUKEE - FOND DU LAC RSRF30 2019
Completed
1146-75-71/72 STH 015 STH 76-NEW LONDON RECSTE 2019 Moved to 2021
1146-75-72 STH 015 STH 76-NEW LONDON RECSTE 2019 Combined w/previous project
1170-19-60 USH 051 MINOCQUA - MANITOWISH PSRS20 2019 Completed
1204-04-77 USH 151 PLATTEVILLE - MADISON PVRPLA 2019
Completed
1206-08-77 USH 018 MOUNT HOREB - MADISON RECSTE 2019 Completed
1206-07-75 USH 018 MOUNT HOREB – MADISON RECSTE 2019 Completed
1411-01-79 STH 033 HORICON - WEST BEND RCND20 2019
Completed
1430-00-77 STH 023 CITY OF MONTELLO, UNDERWOOD AVENUE RECST 2019 Completed
1430-00-79 STH 023 CITY OF MONTELLO, UNDERWOOD AVENUE RECST 2019 Completed
1430-00-87/89 STH 023 CITY OF MONTELLO, UNDERWOOD AVENUE RECST 2019 Completed
1430-00-89 STH 023 CITY OF MONTELLO, UNDERWOOD AVENUE RECST 2019 Combined w/previous project
1500-37-71/72 USH 010 WALDO BLVD., CITY OF MANITOWOC RECST 2019 Combined w/project below
1500-37-74 USH 010 WALDO BLVD., CITY OF MANITOWOC RECST 2019 Completed
1500-47-71 USH 010 WALDO BLVD., CITY OF MANITOWOC RSRF30 2019 Moved to 2020
1500-72-60 USH 010 MENASHA-REEDSVILLE PSRS40 2019 Advanced to 2018, Completed
1500-73-60 USH 010 MENASHA-REEDSVILLE PSRS40 2019 Removed**
1517-75-73/77 USH 010 USH 10 - USH 10/STH 441 RECSTE 2019 Completed
1560-02-70 USH 063 HAYWARD - DRUMMOND PVRPLA 2019 Removed**
1601-14-73 USH 045 MONICO - EAGLE RIVER RSRF10 2019 Completed
1650-07-71/81 USH 061 MADISON STREET, C LANCASTER RCND20 2019 Completed
1650-07-81 USH 061 MADISON STREET, C LANCASTER RCND20 2019 Combined w/previous project
2025-19-70 STH 190 CAPITOL DRIVE, CITY OF MILWAUKEE BRRPL 2019
Completed
2040-11-70 USH 045 108TH STREET (HALES CORNERS) RECSTE 2019
Completed
2060-00-76 STH 038 S CHASE AVENUE, CITY OF MILWAUKEE RECST 2019 Completed
2060-10-70 STH 038 HOWELL AVE - CITY MILWAUKEE RECST 2019 Advanced to 2018 Completed
2120-16-70 STH 024 STH 24 MISC 2019
Completed
2240-14-61 STH 036 LOOMIS ROAD PSRS40 2019 Completed
2250-12-70 STH 020 MAIN ST/1ST ST VIL WATERFORD RECSTE 2019 Completed
2310-17-70 STH 060 STH 60 RCND20 2019 Moved to 2020
3110-02-71 STH 059 ELKHORN ROAD, CITY OF WHITEWATER RECST 2019 Completed
2709-03-70 STH 164 LOVERS LANE RCND20 2019 Completed
3110-06-70/71 STH 059 MILWAUKEE ST, CITY OF WHITEWATER RECST 2019 Completed
3110-06-71 STH 059 MILWAUKEE ST, CITY OF WHITEWATER RECST 2019 Combined w/previous project
3300-01-73 STH 089 C LAKE MILLS, MAIN STREET RECST 2019 Completed
4080-04-71 USH 045 MAIN & FOND DU LAC STS., V. OF EDEN RECST 2019 Completed
4140-19-72/73 STH 042 GIBRALTAR - SISTER BAY RSRF30 2019 Completed
4430-10-71 STH 042 ALGOMA-STURGEON BAY RSRF20 2019 Completed
4516-07-71 STH 029 V BELLEVUE, STH 29-WILLOW RD RECST 2019 Completed
4570-12-71/72 STH 042 WALDO BLVD., CITY OF MANITOWOC RECST 2019 Completed
4570-12-72 STH 042 WALDO BLVD., CITY OF MANITOWOC RECST 2019 Combined w/previous project
4580-11-60 STH 114 SHERWOOD-HILBERT PSRS40 2019 Removed**
4987-02-65 STH 054 C GREEN BAY, WEBSTER AVE RECST 2019 Completed
4992-00-57/58 USH 010 C MENASHA, CTH LP RECST 2019 Completed
5350-01-73 USH 051 BELOIT – JANESVILLE RSRF30 2019 Completed
5573-05-60 STH 136 REEDSBURG - BARABOO RSRF20 2019 Removed**
5992-09-14 STH 113 N BALDWIN STREET TO FIRST STREET RECST 2019 Completed
6085-02-74 STH 019 WAUNAKEE - SUN PRAIRIE RECSTE 2019 Completed
6176-00-70 STH 033
MILL STREET TO SPRING ST (STH 33) RCND10 2019 Completed
6190-21-60 STH 116 WAUKAU-OMRO PSRS40 2019 Completed
6380-06-75 STH 097 C MARSHFIELD, CENTRAL AVENUE RSRF30 2019 Completed
6999-03-70 STH 054 GAYNOR AVENUE TO STH 13 RCND10 2019 Completed
6999-18-71 STH 051 GRAND AVENUE - EASTHILL DRIVE RECST 2019 Completed
7120-02-73 STH 085 DURAND - EAU CLAIRE RSRF20 2019 Completed
8140-00-70/73 STH 027 C HAYWARD, SOUTH DAKOTA AVENUE PVRPLA 2019 Completed
8140-00-73 STH 027 C HAYWARD, SOUTH DAKOTA AVENUE PVRP_O 2019 Combined w/previous project
9150-29-60 STH 032 MOUNTAIN-TOWNSEND PSRS40 2019 Completed
8727-00-70 STH 112 MARENGO – ASHLAND COLD10 2019 Completed
9180-23-71 STH 022 C SHAWANO, S MAIN & E GREEN BAY STR RSRF10 2019 Completed
Page 16 of 26
ADA TRANSITION PLAN 2020 UPDATE
9180-23-72 STH 022 C SHAWANO, GREEN BAY STREET RSRF10 2019 Combined w/previous project
9266-11-01 STH 032 V ASHWAUBENON, COARMIER RD RECST 2019 Completed
Total Projects for 2019 36 Adjusted Total Projects 48
Page 17 of 26
ADA TRANSITION PLAN 2020 UPDATE
G. Six-year Program projects scheduled for completion in 2020
Project ID Highway Project Limits Improvement Concept Code
Year Project Status
1198-03-74 USH 002 C SUPERIOR, EAST SECOND STREET RSRF20 2020 Under Construction
1206-04-67
USH 012 SOUTH TOWN DRIVE BRIDGE BRPVTV 2020 Under Construction
1228-09-74 IH 094* MARQUETTE I/C
RSRF10
2020 Under Construction
1320-17-70
STH 011 USH 14/STH 89 TO TURTLE CREEK DRIVE
RCND20
2020 Under Construction
1330-32-70 STH 083 STH 59 TO PERKINS ROAD
RSRF30 2020 Under Construction 1500-37-76/77
USH 010 FLEETWOOD DR - 14TH STREET
RECST
2020 Under Construction
1500-47-71
USH 010 CTH R - FLEETWOOD DRIVE
RSRF30
2020 Under Construction
1650-07-72
USH 061 PITZEN LANE TO HICKORY LANE
RSRF30
2020 Under Construction
2030-13-70 STH 100 I43 TO HANK AARON STATE TRAIL RSRF 2020 Under Construction
2060-00-76 STH 038 OHIO ST TO LINCOLN AVE
RECST 2020 Under Construction
2080-00-72
STH 190 W GROELING AVE TO W CAPITOL DR
RECST
2020 Under Construction 2225-14-70 STH 032 VARIOUS LOCATIONS ALONG STH 32 MISC 2020 Under Construction
2250-12-70
STH 020 BUENA PARK RD TO MILW AVE (STH 36)
RECST 2020 Under Construction
2260-00-71
STH 011 STH 31 TO KENTUCKY ST
RECST 2020 Under Construction
2260-07-70
STH 011 KENTUCKY ST TO KEARNEY AVE
RECST 2020 Under Construction
2310-17-70
STH 060 EAGLE DRIVE TO STH 181
RCND10
2020 Under Construction
2595-03-73
STH 190 W CAPITOL DR TO W HAMPTON AVE
RECST
2020 Under Construction 2703-00-74
STH 032 STH 32 TO MAIN STREET
RECST
2020 Under Construction
2718-15-70
STH 164 CTH ES TO LES PAUL PARKWAY
RCND10
2020 Under Construction
2782-13-70 STH 175 INT WITH PILGIRM RD & MENOMONEE AVE
MISC 2020 Under Construction
2788-00-71 USH 018 GENESSE RD TO FIDDLERS CREEK RECST 2020 Under Construction
2990-14-70 STH 038 INTERSECTION WITH N MEMORIAL DRIVE MISC 2020 Under Construction
3180-00-74 STH 011 RACINE CO LINE TO STH 83 PVRPLA 2020 Under Construction
3190-08-70 STH 120 N SIDE OF COMO CRK BRIDGE TO STH 36 RCND10 2020 Under Construction
3200-01-72 USH 045 STH 50 TO STH 11 RCND20 2020 Under Construction
3300-01-73 STH 089 TOPEL ST TO MADISON ST RECST 2020 Under Construction
3700-20-80 VAR HWY VARIOUS SIGNALIZED INTERSECTIONS MISC 2020 Under Construction
3700-20-91 VAR HWY VARIOUS SIGNALIZED INTERSECTIONS MISC 2020 Under Construction
4075-33-71 STH 096 LAWE STREET – CLARIBEL STREET RECST 2020 Under Construction
5155-02-62 USH 014 CTH M TO USH 51 B-53-0906 RSRF20 2020 Under Construction
5163-09-72/73 STH 035 SOUTH V LIMIT TO NORTH V LIMIT RCND10 2020 Under Construction
5290-00-72 STH 019 RIVER ROAD TO IH94 RECST 2020 Under Construction
5530-02-71 STH 080 LIBERTY STREET TO STH 82 RCND20 2020 Under Construction
5540-00-60 STH 027 SAINT LO DRIVE TO CIPRA RD RSRF20 2020 Under Construction
5540-00-70 USH 027 OHIO ST TO SAINT LO DRIVE RSRF20 2020 Under Construction
5637-02-70 STH 136 STAND ALONE CURB RAMP PILOT PROJECT MISC 2020 Under Construction
5845-04-72 USH 051 HOEL AVENUE TO PAGE STREET RCND10 2020 Under Construction
6050-00-71 STH 022 STH 16 TO NCL/B-11-0171 RCND10 2020 Under Construction
6075-00-74 STH 060 BULLEN ROAD TO US 51 PVRPLA 2020 Under Construction
6243-08-70 STH 047 SHAWANO CREEK TO MENOMINEE CO LINE RSRF30 2020 Under Construction
6300-00-73 STH 022 PORTAGE COUNTY LINE TO USH 10 RAMPS RSRF10 2020 Under Construction
6430-12-71 STH 076 76 DIVIDED ENDS – CTH JJ RECST 2020 Under Construction
6600-00-61 STH 153 OLD 51 ROAD TO EAST VIEW DRIVE PSRS40 2020 Under Construction
6600-00-62 STH 153 I-39 SB RAMP TO NB RAMP PSRS40 2020 Under Construction
6934-06-70/71 STH 54 STH 54 TO SOUTH BIRON DRIVE RECST 2020 Under Construction
6995-09-72 STH 49 SOUTH CHURCH STREET TO CITY LIMITS PVRPLA 2020 Under Construction
7130-00-71 STH 093 SWENSON LN TO BLASCHKO AVE RSRF20 2020 Under Construction
7130-08-73 STH 093 BUFFALO RIVER TO NORTH COUNTY LINE RSRF30 2020 Under Construction
8010-00-70 STH 035 69TH STREET TO 64TH STREET RSRF20 2020 Under Construction
9080-14-74 STH 070 USH 51 TO STH 155 RSRF10 2020 Under Construction
9560-02-74 USH 141 PINE STREET – 4TH STREET RECST 2020 Under Construction
9560-02-75 USH 141 BETTERS COURT – PINE STREET RSRF20 2020 Under Construction
9650-17-70 STH 047 DUQUAINE RD TO N JCT OF CTH VV RCND10 2020 Under Construction
Total Projects for 2020 53
*Projects will need to be evaluated on a project basis to determine if curb ramp work is needed. **Final project limits did not include curb ramp work.
Page 18 of 26
ADA TRANSITION PLAN 2020 UPDATE
H. Six-year Program projects scheduled for 2021-2027
Project ID Highway Project Limits Improvement Concept Code Year
1146-75-71 STH 015 WI CENTRAL RR-CTH JJ RECSTE 2021
1180-00-75 USH 002 CTH A TO CTH E RSRF20 2021
1198-03-78 USH 002 29TH AVENUE EAST - 53RD AVENUE EAST RSRF20 2021
1206-06-79 USH 012 WHITNEY WAY TO IH 39/90 RSRF10 2021
1310-10-70 STH 050 IH 94 TO 74TH AVE RECSTE 2021
1310-10-71 STH 050 74TH AVE TO 43RD AVE RECSTE 2021
1310-18-70 STH 050 CTH O-STH 75, 236TH AVE-125TH AVE PSRS30 2021
1530-03-76 USH 010 STH 65 TO NORTH BEULAH STREET RSRF20 2021
1540-01-72 STH 065 USH 10 TO MIDWAY AVENUE RSRF20 2021
1580-31-71 USH 008 STH 27 TO RIVER AVENUE RSRF20 2021
1610-11-70 STH 013 MORSE ROAD TO JEFFERSON AVENUE COLD10 2021
1641-03-75 USH 014 MORMON COULEE RD/BROADVIEW PL INTER RCND10 2021
2030-13-70 STH 100 I43 TO HANK AARON STATE TRAIL RSRF30 2021
2040-15-60 STH 100 60TH ST TO LOOMIS RD PSRS40 2021
2220-02-70 USH 045 USH41/45 SPLIT TO ONE MI N OF CTH D PSRS30 2021
2240-00-77 STH 036 STH 20 TO CTH Y RSRF30 2021
2440-09-70 STH 020 ROOSEVELT AVE TO WEST BLVD RECST 2021
2783-05-70 STH 190 CTH M TO STH 190 RECSTE 2021
3070-04-61 STH 073 NORTH STREET TO SCHOOL STREET RSRF30 2021
3240-14-70 STH 032 91ST STREET TO 85TH STREET RSRF30 2021
3706-01-60 STH 067 SALT BOX ROAD TO USH 14 PSRS40 2021
4090-06-71/72 STH 067 BAUMANN STREET-TRIPLE S ROAD RECST 2021
4100-39-60 USH 151 STH 67 - ROOSEVELT STREET PSRS40 2021
4540-27-71 STH 032 IH 43-CTH D RSRF20 2021
4550-03-71 STH 067 SOUTH COUNTY LINE-STH 32/57 RSRF20 2021
4550-04-71 STH 067 SUHRKE ROAD-NCL RSRF20 2021
5120-02-70 STH 033 JACKSON ST/STH 35/WEST AVE INTER RCND10 2021
5120-03-72 STH 033 3RD STREET TO 23RD STREET RSRF20 2021
5245-02-72/75 STH 023 COUNTY SHOP ROAD TO MINERVA STREET RECST 2021
5310-02-76/77 USH 014 WALTER ROAD TO CTH KP RECST 2021
5630-06-72 STH 078 EAGLE VIEW COURT TO WEYNAND ROAD PVRPLA 2021
5991-07-43 STH 035 CALEDONIA ST TO GEORGE ST (STH35) RECST 2021
5996-00-77 STH 080 STALEY AVENUE TO COMMERCIAL DRIVE RCND10 2021
6054-06-73 STH 022 B-39-0062 TO 5TH STREET RSRF10 2021
6070-02-60 STH 068 EDGELAWN DRIVE TO WEST STREET RSRF20 2021
6070-02-70 STH 068 WEST STREET TO STH 49 RSRF20 2021
6090-08-71 STH 049 CTH TC - WCPL PSRS40 2021
6150-00-72 STH 022 MARQUETTE CTY L/CTH JJ TO STH 21W RSRF10 2021
6170-00-61 STH 021 STH 22 S TO STH 73 N PSRS40 2021
6310-00-60 STH 073 STH 22 (N) TO CTH BB PSRS40 2021
6321-00-72 STH 073 CTH BB TO 5TH AVE RSRF10 2021
6425-00-70 STH 073 STH 23 TO OLD SAINT MARIE ROAD RECST 2021
6570-08-73 STH 055 STH 54-LAKE ROAD RSRF30 2021
6918-01-72 USH 051 ONTARIO STREET TO E PLEASANT STREET RECST 2021
6999-10-60/61 STH 029 EVEREST DRIVE TO SCHOFIELD AVE PSRS40 2021
7575-00-71 STH 016 BRAUND ST TO CTH OS RCND10 2021
7575-07-70 STH 016 LA CROSSE ST/STH 35/WEST AVE INTER RCND10 2021
7630-00-72 STH 029 CTH CC SOUTH TO STH 128 RSRF20 2021
7640-00-72 STH 029 SOUTH MAIN STREET TO STH 65 RSRF20 2021
7650-01-75 STH 029 CTH QQ SOUTH JCT TO CEMETERY ROAD PVRPLA 2021
7650-02-73 STH 029 CTH FF & 770TH AVENUE INTERSECTION RCND10 2021
8070-00-74 STH 046 SNOW STREET TO YORK PARK ENTRANCE RSRF10 2021
8080-02-60 STH 035 FRONT STREET TO VINE STREET RSRF10 2021
8080-02-72 STH 035 COULEE RD/BUCKEYE ST INTERSECTION RSRF10 2021
8080-05-70/72 STH 035 LAKE MALLALIEU BRIDGE - SOMMERS ST RECST 2021
8080-07-70/72 STH 035 VINE STREET TO WILLOW RIVER RECST 2021
8600-01-74 STH 178 CTH I INTERSECTION RECST 2021
8630-03-82 STH 170 STH 128 TO STH 79 RSRF20 2021
8630-05-83 STH 170 STH 79 TO STH 25 COLD10 2021
9070-05-73 STH 070 MORGAN ROAD TO USH 51 RSRF10 2021
9190-20-71 STH 032 CTH B - EAST GREEN BAY STREET RSRF30 2021
9190-23-71 STH 032 STH29-VILLAGE OF PULASKI COLD20 2021
Page 19 of 26
ADA TRANSITION PLAN 2020 UPDATE
9220-04-73 STH 117 CTH BE TO STH 22 RSRF10 2021
Total Projects for 2021 65
Project ID Highway Project Limits Improvement Concept Code Year
1016-05-70 STH 082 STH 82 INTERCHNG/B29-36,152-155,157 RECST 2022
1112-06-74 USH 151 STH 49 INTERCHANGE RSRF20 2022
1146-75-72 STH 015 CTH JJ - LILY OF THE VALLEY DR RECSTE 2022
1180-05-75 USH 002 CLEVEDON RD TO SZNAIDER RD RSRF20 2022
1228-09-73 STH 059 MITCHELL I/C TO MARQUETTE I/C RSRF30 2022
1310-04-70 STH 050 256TH AVE TO 236TH AVE RECST 2022
1380-02-70 STH 167 WASHINGTON CO LINE TO BUNTROCK AVE RCND10 2022
1470-34-60 STH 042 DUVALL STREET-NCL PSRS40 2022
1560-00-70/80 USH 063 GREENWOOD AVE TO POPLAR STREET RECST 2022
1570-05-73 USH 008 CTH P TO WYE STREET RSRF30 2022
1590-18-61 USH 008 ONEIDA COUNTY LINE TO BOULEVARD AVE PSRS40 2022
1600-28-61 USH 045 STH 32 TO VILAS COUNTY LINE PSRS40 2022
1610-00-76 STH 013 JEFFERSON AVE TO GOLF COURSE ROAD RSRF20 2022
1610-39-60 STH 013 5TH ST NORTH TO ASHLAND COUNTY LINE PSRS40 2022
1610-44-71 STH 013 CTH D TO CTH F PVRPLA 2022
1610-44-73 STH 013 WALNUT ST-N FK FLAMBEAU RVR BRDGE RSRF10 2022
1641-02-72/82 USH 014 GREEN BAY STREET TO WARD AVENUE RECST 2022
1646-08-72/82 USH 014 HIGH ECHO LANE TO LOCUST STREET RECST 2022
1661-09-72 USH 018 SOUTH TOWN LN/SELCH RD INTERSECTION RCND10 2022
1693-05-72 STH 069 CTH D TO VALLEY ROAD RECST 2022
1693-05-73 STH 069 CTH D TO V BELLEVILLE NORTH LIMIT RECST 2022
1706-01-73 STH 011 STH 104 TO CTH B RSRF30 2022
1706-01-74 STH 011 2ND STREET TO STH 104 RSRF30 2022
2260-08-70 STH 011 KEARNEY AVE TO EAST OF MEMORIAL DR RECST 2022
2270-04-70 STH 057 TEUTONIA AVENUE TO MEQUON ROAD RCND20 2022
2395-05-71 STH 038 S 6TH STREET TO S CLEMENT AVENUE RECST 2022
2703-11-70 STH 032 DOUGLAS AVENUE TO MAIN STREET RECST 2022
2718-04-71 STH 018 MOUNTAIN AVE TO MADISON ST RECST 2022
2722-07-71 STH 018 I-94 TO W BLUEMOUND ROAD PVRPLA 2022
2773-10-70 STH 059 SUNSET DRIVE TO ARCADIAN AVENUE PSRS20 2022
3030-02-72 STH 067 WEST JCT CTH S TO RUEDEBUSCH AVE RSRF30 2022
3670-01-71/72 STH 089 0.32MI S OF AVALON RD TO PARK AVE RECST 2022
5010-06-72 STH 082 STH 80 TO CTH G RSRF30 2022
5163-07-77 STH 035 SUNNYSIDE DR TO GARNER PLACE RECST 2022
5207-00-70 STH 023 ALEXANDER AVE TO ALBERT AVENUE RECST 2022
5400-00-72 USH 151 WILSON/WILLIAMSON ST INTERSECTION RCND10 2022
5400-00-73/74 USH 151 E WILSON ST TO BLOUNT ST PVRPLA 2022
5601-00-60 STH 078 USH 14 TO USH 12 PSRS40 2022
5940-02-60 STH 133 STH 80 TO STH 130 RSRF10 2022
6270-00-63 STH 049 DEPOT STREET TO S JCT STH 161 PSRS40 2022
6280-00-60 STH 066 NORTH CTH J TO STH 49 PSRS40 2022
6370-01-73 STH 153 PINE ST TO WISCONSIN RIVER BRIDGE RSRF10 2022
6370-01-75/76 STH 153 RANGELINE ROAD TO PINE STREET PVRPLA 2022
6380-00-62 STH 097 NORTHRIDGE STREET TO SOUTH STREET RCND10 2022
6530-01-71 STH 073 CTH J TO WHITE RIVER BRIDGE RSRF10 2022
6530-01-72 STH 073 FOX RIVER BRIDGE TO CTH J RSRF10 2022
6570-09-71 STH 055 IH 41-STH 54 RSRF20 2022
6933-00-76 STH 173 CTH G (N) TO STH 73 RSRF10 2022
6999-11-78 STH 013 W RIVERVIEW EXP TO JACKSON ST BRDGE RECST 2022
7575-07-73/83 STH 016 OAKLAND ST TO LOSEY BLVD RCND10 2022
7995-02-61 STH 312 STH 312 TO COUNTY LINE ROAD RECST 2022
8072-00-70 STH 046 STH 64 TO SNOW STREET COLD10 2022
8949-00-71 USH 012 STH 65 NORTH TO USH 63 NORTH RSRF20 2022
8949-00-74 USH 012 USH 63 NORTH TO USH 63 SOUTH RSRF10 2022
8999-00-65 STH 035 6TH STREET NORTH TO 3RD ST NORTH RECST 2022
9050-03-71 STH 047 KILDEER ROAD TO VILAS COUNTY LINE RSRF10 2022
9080-14-72 STH 070 CTH H TO USH 45 NORTH RSRF10 2022
9110-10-72 STH 139 FOREST COUNTY LINE TO FAY LAKE ROAD RSRF10 2022
9170-12-71 STH 032 TRINITY CHURCH RD-CTH AA RSRF20 2022
Total Projects for 2022 59
1146-75-76 STH 015 CTH T-WI CENTRAL RR RECSTE 2023
1146-75-77 STH 015 WI CENTRAL RR-CTH JJ RECSTE 2023
1210-11-71 STH 172 AIRPORT ENTRANCE-IH 41 RSRF10 2023
Page 20 of 26
ADA TRANSITION PLAN 2020 UPDATE
1300-09-70 STH 083 STH 20 TO IH 43 RCND20 2023
1360-15-70 STH 145 GOOD HOPE RD INTERCHANGE TO 68TH ST RSRF30 2023
1491-22-71 USH 141 CTH Z-CTH R RSRF30 2023
1570-06-72 USH 008 CEDAR SWAMP ROAD TO CHIPPEWA RIVER COLD20 2023
1620-00-61 STH 013 SOUTH CTH N TO NORTH STREET PSRS40 2023
1620-01-62 STH 013 STH 98 TO SOUTH JUNCTION CTH N PSRS20 2023
1620-02-78 STH 080 STH 21 TO COUNTY LINE ROAD RSRF30 2023
1620-03-73 STH 013 LINDEN ST TO PINE ST RSRF10 2023
1620-03-74 STH 013 NORTH ST TO LINDEN ST RSRF10 2023
1632-03-70 USH 053 SOUTH COUNTY LINE TO HARRIS ROAD RSRF20 2023
2275-05-70 STH 057 NORTH AVE TO HOPKINS ST RSRF30 2023
3070-04-60 STH 073 SHAUL LANE TO NORTH STREET RCND10 2023
3080-04-70 USH 018 STH 67 TO MORAINE VIEW DR RSRF30 2023
3180-00-76 STH 036 STH 83 TO STH 20 RSRF10 2023
3325-06-71/72 STH 067 GENEVA ST TO GLENWOOD DR RSRF30 2023
3575-02-73 USH 012 MADISON AVENUE TO CTH M RSRF20 2023
3670-00-74 STH 089 CLARKSON ROAD TO AVALON ROAD RSRF10 2023
4085-33-71 STH 032 SOUTH COUNTY LINE-DUESTER STREET RSRF30 2023
4140-34-60 STH 042 RAINBOW RIDGE RD-BLUFF LN PSRS40 2023
4580-10-71 STH 114 USH 10-VILLAGE OF SHERWOOD RCND10 2023
4610-10-60 STH 042 SCANDIA RD-WISCONSIN BAY RD PSRS40 2023
4670-10-71 STH 055 SOUTH JCT STH 114 - CASTLE DRIVE RSRF30 2023
5030-01-72 STH 033 V WONEWOC S LIMITS TO MAIN STREET RSRF20 2023
5030-01-73 STH 033 LA VALLE STREET TO PRESTON AVENUE RSRF30 2023
5030-01-74 STH 033 PRESTON AVENUE TO STH 23 RSRF30 2023
5080-02-74/75 STH 023 USH 14 TO CTH GG RSRF30 2023
5150-02-70 STH 082 STH 35 TO STH 27 RSRF30 2023
5280-03-70 STH 113 SUNSET LANE TO CTH V PVRPLA 2023
5410-00-74 USH 051 USH 151 TO PIERSTORFF STREET PVRPLA 2023
5640-04-70 STH 113 STH 60 TO STH 188 RSRF20 2023
6230-14-72 STH 054 TOWER DRIVE - N BEECH STREET RSRF10 2023
6360-05-70 STH 107 NORTH STREET TO MARATECH AVENUE RSRF10 2023
6370-00-72 STH 153 STH 107 TO RANGELINE RD RSRF10 2023
6517-15-60 STH 076 SOUTH JCT S-STH 54 PSRS40 2023
6590-02-76 STH 022 CTH N (N) TO USH 45 RSRF10 2023
7140-00-70 STH 035 LA CROSSE/TREMP CO LN TO 10TH ST COLD20 2023
7998-00-77/78 USH 012 VETERANS STREET INTERSECTION AREA PVRPLA 2023
8060-00-70 STH 035 CTH C TO LASER DRIVE PVRPLA 2023
8620-00-73 STH 040 13TH AVENUE TO EAST JUNCTION STH 64 COLD20 2023
Total Projects for 2023 42
1150-64-71 USH 041 PESHTIGO BYPASS-CTH T RSRF20 2024
1170-19-72 USH 051 MANITOU PARK TO MINOCQUA LK BRIDGE PVRPLA 2024
1170-20-60 USH 051 CTH M TO CTH W PSRS40 2024
1175-19-62 USH 051 CTH C TO IRON STREET PSRS40 2024
1198-03-73 USH 053 BELKNAP ST TO BLATNIK BRG (NB & SB) RSRF20 2024
1210-17-71 STH 172 STH 54 - AIRPORT ENTRANCE RSRF30 2024
1360-14-70 STH 145 N 19TH ST TO N 12TH ST RSRF30 2024
1470-30-71 STH 042 34TH STREET-NCL RSRF30 2024
1535-07-73 USH 010 NELSON RD TO ROSE LN PVRPLA 2024
1580-04-72 USH 008 RIVER AVENUE TO PRENTICE STREET RSRF20 2024
1580-04-73 USH 008 PRENTICE STREET TO RUSK/PRICE CO LN RSRF20 2024
1610-01-76 STH 013 CTH O TO TAYLOR STREET RSRF20 2024
1610-44-72 STH 013 CTH F TO BALSAM STREET PVRPLA 2024
1620-03-72 STH 013 26TH ROAD TO STH 98 RSRF10 2024
1706-06-71 STH 011 V HAZEL GREEN W LIMIT TO V N LIMIT PVRPLA 2024
2140-14-70 STH 181 FLORIST AVE TO MILL RD (CTH S) RSRF20 2024
2195-04-70 STH 032 N BROADWAY TO N PROSPECT AVE RECST 2024
2200-18-70 USH 018 12TH ST TO OLD WORLD THIRD ST RSRF30 2024
2200-19-70 USH 018 STORY PKWY TO WISCONSIN AVE RECST 2024
2210-12-70 USH 018 STH 83 TO CTH TT RSRF30 2024
2225-15-70 STH 032 NEWBERRY BLVD TO EDGEWOOD AVE RECST 2024
2225-16-70 STH 032 OGDEN AVE TO BRADFORD AVE RSRF30 2024
2250-15-70 STH 020 OAKES RD TO STH 31 RSRF30 2024
2310-13-70 STH 060 CTH P TO EAGLE DR RSRF30 2024
2340-10-70 STH 020 STH 36 TO SB USH 45 RCND10 2024
2350-15-70 STH 032 2000' N 4MI RD TO 800' S E CO LN RD RSRF30 2024
Page 21 of 26
ADA TRANSITION PLAN 2020 UPDATE
2698-03-70 STH 020 THOMAS DRIVE TO HONEY CREEK ROAD RCND20 2024
2729-05-70 STH 181 CTH C - LINCOLN, CHESTNUT - STH 60 RSRF30 2024
3150-07-70 USH 014 IH 43 TO CTH K PVRPLA 2024
3330-07-70 STH 031 STH 50 TO CTH S PSRS20 2024
3694-00-71 STH 120 STH 36 TO O'LEARY LN RSRF20 2024
4070-00-70 USH 045 WB CTH H TO WB STH 28 RSRF30 2024
4085-60-71 STH 032 CTH AA-JORDAN AVENUE RSRF10 2024
4085-67-71 STH 032 ALTONA AVENUE-USH 151 RSRF20 2024
4110-28-71 USH 045 SCOTT STREET-NCL RSRF20 2024
4130-11-71 STH 054 VALLEY ROAD - SUNSET AVENUE RSRF20 2024
5080-09-73 STH 023 ELDER RIDGE ROAD TO CTH K PVRPLA 2024
5090-05-60 STH 033 W MULBERRY ST TO E V LIMITS PVRPLA 2024
5090-05-71 STH 033 W CITY LIMIT TO LINCOLN AVENUE PVRPLA 2024
5180-00-70 STH 060 E JCT OLD HWY 60 TO KICKAPOO RIVER RSRF20 2024
5255-01-73 STH 023 WISCONSIN RIVER BRIDGE TO USH 14 RSRF30 2024
5330-02-73 STH 080 ILLINOIS STATE LINE TO STH 11 PVRPLA 2024
5350-02-70/71 USH 051 NICOLET STREET TO COURT STREET PVRPLA 2024
5540-02-71 STH 027 0.1 MI N NORTH AVENUE TO CTH C RSRF30 2024
5752-00-72 STH 058 LEE LAKE BRIDGE TO STH 33 RSRF30 2024
5939-00-70 STH 080 USH 18 TO KENNEDY STREET RSRF20 2024
5952-03-73 STH 039 N LIMITS V LINDEN TO FAIR STREET RSRF30 2024
6020-04-72 USH 051 TOMLINSON ROAD TO ONTARIO STREET RSRF30 2024
6100-08-60 STH 044 WCL-STH 49 PSRS40 2024
6230-20-71 STH 054 FRENCH ROAD-SEMINARY ROAD RSRF30 2024
6240-22-71 STH 047 CTH JJ - CTH B RSRF30 2024
6240-29-71 STH 047 CTH B-BURDICK STREET RSRF10 2024
6250-02-73 STH 022 STH 156 TO LAKE WAGNER ROAD PVRPLA 2024
6320-00-75 STH 073 STH 173 TO STH 54 RSRF20 2024
6518-06-71 STH 076 STH 54 - NCL RSRF30 2024
6950-04-72 STH 054 SWANSON ROAD TO SENECA ROAD RSRF20 2024
7560-05-74 STH 095 TREMPEALEAU/JACKSON CO LN TO IH 94 RSRF20 2024
8120-02-76 STH 048 USH 63 NORTH TO STH 25 COLD10 2024
8160-00-75 STH 013 THOMPSON CREEK TO SUPERIOR AVE PVRPLA 2024
8220-00-76 STH 064 NATIONAL AVE TO STH 13 RSRF20 2024
8550-02-72 STH 077 CTH I TO CTH G COLD20 2024
8610-02-74 STH 124 HIGH STREET TO BRIDGE STREET RSRF20 2024
8610-08-73 STH 124 ELM STREET TO CTH S RSRF20 2024
8650-00-73 STH 128 STH 170 TO STH 64 COLD10 2024
9130-03-72 STH 032 CTH C TO FOREST AVENUE RCND10 2024
9130-03-73 STH 032 FOREST AVENUE TO USH 8 PVRPLA 2024
9215-01-72 STH 086 4TH STREET TO USH 51 PVRPLA 2024
9220-04-72 STH 117 EXPRESS WAY TO CTH BE PVRPLA 2024
Total Projects for 2024 68
1175-19-72 USH 051 CTH J TO WEBER CREEK BRIDGE RSRF20 2025
1330-00-73 STH 083 GOLF RD TO VETTELSON RD RECST 2025
1330-22-70 STH 083 STH 167 TO MONROE AVENUE RSRF30 2025
1470-27-71 STH 042 E MAGNOLIA AVE-12TH STREET RSRF20 2025
1470-37-71 STH 042 WALDO BLVD - E MAGNOLIA AVE RSRF20 2025
1520-00-77 STH 073 INDUSTRIAL STREET TO STH 186 RSRF20 2025
1530-06-80 USH 010 HUNT LANE TO NELSON ROAD COLD20 2025
1550-04-74 USH 063 WEST JUNCTION STH 48 TO CHARRIE LN RSRF20 2025
1590-18-70 USH 008 GLEN STREET TO PIONEER STREET RSRF10 2025
1590-18-71 USH 008 STH 55 SOUTH TO STH 32 SOUTH PVRPLA 2025
1590-18-72 STH 032 BOULEVARD AVENUE TO LAKE AVENUE RSRF10 2025
1600-14-71 USH 045 CTH B TO CTH Q PVRPLA 2025
1602-10-71 USH 045 CLINIC STREET TO OTTER LAKE LANE PVRPLA 2025
1610-00-77 STH 013 BUTTERWORTH RD TO USH 2 RSRF20 2025
1640-03-73 USH 014 BOHMANN DRIVE TO CTH O RSRF20 2025
2015-10-71 STH 119 STH 119 AT HOWELL AVE RCND10 2025
2025-07-73 STH 190 STH 16 TO .3 MI E OF 5 FIELDS RD RSRF30 2025
2040-14-70 USH 045 RAWSON AVE TO COLLEGE AVE RECST 2025
2050-09-70 STH 241 INTERSECTION OF RAWSON AVENUE RECST 2025
2120-18-70 STH 024. USH 45 TO 45TH STREET RSRF30 2025
2200-20-70 USH 018 IH 94 TO EAST COUNTY LINE RSRF30 2025
2225-00-73 STH 032 SCHOOL ROAD TO DEAN ROAD RSRF30 2025
2240-00-78 STH 036 STH 100 TO 51ST STREET RSRF30 2025
Page 22 of 26
ADA TRANSITION PLAN 2020 UPDATE
2290-24-70 STH 038 DUNKELOW RD TO E OAKWOOD RD PSRS40 2025
2420-00-70 STH 075 STH 50 - STH 20 RSRF30 2025
2565-06-70 STH 057 W CAPITOL DR TO W SILVER SPRING DR RESURF 2025
3020-00-70 STH 028 CTH V TO STH 175 RSRF20 2025
3060-03-71 STH 073 STH 19 TO N MARSHALL V LIMIT PVRPLA 2025
3240-16-70 STH 032 ILLINOIS STATE LINE TO 91ST ST RSRF30 2025
3380-06-70 STH 083 IL STATE LINE TO STH 50 RSRF30 2025
4010-21-71 STH 028 SCL-STH 57 RSRF30 2025
4050-15-71 STH 055 STH 114-USH 10 RSRF20 2025
4075-35-71 STH 096 CLARIBEL STREET-CTH JJ RSRF10 2025
4075-35-72 STH 096 CTH JJ - CTH D RSRF30 2025
4085-68-71 STH 057 RANDALL AVE-GRIGNON ST RSRF10 2025
4090-01-74 STH 067 STH 175 TO EAST COUNTY LINE PVRPLA 2025
4110-32-71 USH 045 SCL-SCPL OSHKOSH RSRF20 2025
5060-00-77 STH 023 STH 33 TO IH 90 RAMP PVRPLA 2025
5163-07-72 STH 035 LACROSSE CO LINE TO SUNNYSIDE DR RECST 2025
5510-00-70 STH 071 CTH U TO CTH V RSRF30 2025
5580-04-70 STH 035 W JUNCTION STH 133 TO USH 18 RSRF30 2025
5590-00-72 STH 078 STH 11 TO CTH D RSRF20 2025
5606-03-70 STH 092 EAST AVENUE TO USH 14 RSRF10 2025
5710-00-72 STH 082 KICKAPOO RIVER TO STH 33 RSRF20 2025
5750-06-70 STH 058 0.7MI N OF CTH N TO LEE LAKE BRIDGE RSRF20 2025
5780-03-61 STH 131 STH 60 TO SUNNY RIDGE RD,B12-XXX RSRF10 2025
5780-03-72 STH 131 SUNNY RIDGE ROAD TO PLEASANT STREET RSRF20 2025
6160-00-70 STH 021 SHERIDAN STREET TO EAST COUNTY LINE PVRPLA 2025
6220-01-76 STH 022 USH 10 RAMPS TO WCL RR BRIDGE RSRF10 2025
6230-16-71 STH 054 WCL-PARK AVENUE RSRF30 2025
6420-00-72 STH 049 NORTH STREET TO DEPOT STREET RSRF10 2025
6517-16-71 STH 076 EVERGLADE ROAD - CTH JJ RECST 2025
6991-00-60 STH 054 PORTAGE CO LINE TO FOXFIRE DRIVE PSRS40 2025
7050-00-72 STH 073 HUNT STREET TO STH 29 E PVRPLA 2025
7050-00-73 STH 073 ROCK CREEK BRIDGE TO HUNT STREET RSRF20 2025
7080-01-73 USH 012 INDUSTRIAL DR TO FALL CREEK UNDER RSRF20 2025
7125-00-70 STH 037 STH 88 TO USH 10 PVRPLA 2025
7575-01-76 STH 016 LOSEY BLV TO SOUTH KINNEY COULEE RD RSRF30 2025
8010-01-79 STH 035 BACON STREET TO STH 70 E RSRF20 2025
8520-01-75 STH 077 USH 63 TO CTH K RSRF20 2025
9040-03-71 STH 017 USH 8 TO STEVENS STREET PVRPLA 2025
9070-03-73 STH 070 CTH F TO MORGAN ROAD RESURF 2025
9260-00-71 STH 032 USH 8 TO CRANDON RR OVERHEAD RSRF10 2025
9931-02-72 STH 013 N FORK FLAMBEAU RVR BRDG - 5TH ST N RSRF10 2025
Total Projects for 2025 64
1140-00-78 USH 045 CHURCH ROAD TO REINKE ROAD RSRF20 2026
1170-19-61 USH 051 MINOCQUA BRIDGE TO LAKESHORE DRIVE PSRS20 2026
1175-21-70 USH 051 IRON STREET TO USH 2 PVRPLA 2026
1180-00-60 USH 002 53RD AVE E TO CTH C PSRS20 2026
1190-03-73 USH 053 OLD TOWN HALL RD TO GOLF RD NB & SB RSRF20 2026
1190-06-61 USH 053 GOLF ROAD TO 40TH AVENUE PSRS20 2026
1540-02-76 STH 065 IH 94 TO USH 12 WEST RSRF20 2026
1540-02-78 STH 065 USH 12 EAST TO 1500' N OF 157TH AVE RSRF20 2026
1550-04-77 USH 063 CHARRIE LN TO BARRON/WASHBURN CO LN RSRF20 2026
1620-02-77 STH 080 POPLAR ST TO STH 73 PVRPLA 2026
1640-03-74 STH 014 S JCT STH 162 TO CHURCH STREET RSRF30 2026
1640-03-77 STH 023 RICHLAND CO LINE TO WISCONSIN RIVER RSRF20 2026
1706-02-64 STH 011 SHULLSBURG BRANCH BRDG TO WOLF CRK RSRF10 2026
2010-03-72 STH 175 STH 181 TO IH 41 RSRF30 2026
2025-03-73 STH 190 BROOKFIELD RD TO 124TH ST RSRF30 2026
2225-13-70 STH 032 EDGEWOOD AVE TO KENSINGTON BLVD RECST 2026
2265-18-70 STH 241 LAYTON AVE TO COLLEGE AVE RSRF20 2026
2340-00-79 STH 020 HONEY CREEK ROAD TO BUENA PARK ROAD RSRF30 2026
2340-07-71 STH 020 STH 75 INT AND USH 45 TO CTH C RSRF30 2026
2370-00-75 STH 164 SWAN ROAD TO NORTH COUNTY LINE RSRF30 2026
2390-12-70 STH 031 STH 11 TO STH 20 RECST 2026
2410-10-70 STH 059 39TH ST TO 1ST ST RECST 2026
2729-07-70 STH 181 COUNTY LINE ROAD TO MEQUON ROAD PSRS20 2026
3100-00-75 STH 067 USH 12 TO STH 59 RSRF30 2026
Page 23 of 26
ADA TRANSITION PLAN 2020 UPDATE
3110-00-75 STH 059 STH 106 TO EAST COUNTY LINE PVRPLA 2026
3110-08-70 STH 059 W COUNTY LINE TO CTH X RSRF30 2026
3576-01-72/73 STH 106 PARK DRIVE TO ROBERT STREET PVRPLA 2026
3576-01-75 STH 160 FIRST STREET TO STH 59 PSRS40 2026
4010-29-71 STH 028 STH 57-CTH A RSRF30 2026
4015-22-72 STH 057 STH 28-NCL RSRF10 2026
4050-21-71 STH 055 USH 10-RIDGECREST LANE RSRF20 2026
4065-17-71 STH 114 MANITOWOC STREET-MELISSA STREET PVRPLA 2026
4065-18-71 STH 114 MELISSA STREET-USH 10 PVRPLA 2026
4075-40-71 STH 096 CASALOMA DRIVE - N BADGER AVENUE RSRF20 2026
408547-71 STH 032 STH 114-NCL RSRF20 2026
4337-23-71 STH 310 CTH R-COLUMBUS STREET RSRF30 2026
4540-36-71 STH 032 CTH D-STH 28 RSRF10 2026
5032-00-70 STH 033 BARABOO RIVER TO V WONEWOC S LIMIT RSRF20 2026
5040-03-71 STH 080 S FORK BARABOO R BRIDGE TO STH 33 PVRPLA 2026
5100-01-73 STH 033 C HILLSBORO W LIMIT TO CTH HH PVRPLA 2026
5110-06-70 STH 131 STH 82 TO STH 33 RSRF30 2026
5160-07-72 STH 035 CTH E TO OLD HWY 35 RSRF30 2026
5571-00-72 STH 213 BURTON STREET TO STH 11 RSRF30 2026
5770-02-71 STH 130 WISCONSIN RIVER TO USH 14 RSRF20 2026
5880-00-66 STH 012 MONROE COUNTY LINE TO A STREET RSRF10 2026
5939-00-72 STH 080 KENNEDY STREET TO 0.27 MILE N CTH I RSRF20 2026
5944-04-74 STH 081 STH 23 TO WILDCAT ROAD RSRF30 2026
6140-01-66 STH 013 NORTH ST TO MOUND VIEW DR RSRF10 2026
6360-05-75 STH 107 CTH B TO NORTH STREET RSRF10 2026
6590-01-74 STH 022 STH 54 TO S JCT CTH B RSRF30 2026
6590-02-72 STH 110 STH 161 TO CTH S RSRF10 2026
6590-02-73 STH 110 CTH C TO CTH S RSRF10 2026
6707-01-73 STH 146 STH 16 TO STH 33 RSRF30 2026
6999-10-85/86 STH 029 EVEREST DRIVE TO SCHOFIELD AVENUE PVRPLA 2026
6999-10-87 STH 029 E GRAND AVE TO EAU CLAIRE RVR BRDGE PVRPLA 2026
7160-04-76 STH 035 OLD STH 35 TO INDIAN CREEK RD RSRF20 2026
7720-00-71 STH 095 CTH A TO STH 93 RSRF20 2026
8010-00-73 STH 035 64TH STREET TO BELKNAP STREET RSRF20 2026
8010-01-80 STH 035 STH 48 E TO POLK STREET RSRF20 2026
8030-00-70 STH 046 USH 8 TO STH 35 COLD20 2026
8050-00-70 STH 070 BURNETT/WASHBURN CO LN TO USH 53 COLD20 2026
8100-01-72 STH 025 USH 12 W TO CTH D COLD20 2026
8200-00-71 STH 027 STH 29 TO JOHNSON ROAD RSRF20 2026
8520-00-71 STH 077 STH 13 TO EAST COUNTY LINE RSRF20 2026
8650-00-74 STH 128 USH 12 TO STH 170 COLD20 2026
8760-00-71 STH 105 MN/WI STATE LINE TO STH 35 RSRF20 2026
8820-00-70 STH 048 STH 35 TO BASS LAKE LANE COLD20 2026
8840-00-70 STH 087 USH 8 TO 270TH AVENUE COLD20 2026
8949-00-75 USH 012 STH 65 S TO STH 65 N RSRF20 2026
8949-00-76 USH 012 IH 94 TO STH 25 N RSRF20 2026
9120-09-71 USH 002 PEWABIC STREET TO CTH NN RSRF20 2026
9180-35-71 STH 022 S CPL - N CPL RECST 2026
Total Projects for 2026 72
1170-19-73 STH 051 ONEIDA STREET TO MANITOU PARK DRIVE RSRF30 2027
1180-01-71 USH 002 BEASER AVE TO 36TH AVE PVRPLA 2027
1390-01-76 STH 026 CENTER STREET TO STH 33 RSRF30 2027
1500-49-71 USH 010 USH 114-CTH N PSRS30 2027
1500-69-71 USH 010 STH 32/57-CTH HR RSRF30 2027
1510-01-61 USH 010 ANDERSON ROAD TO APPLETREE LANE PSRS30 2027
1530-05-73 USH 010 PIERCE/PEPIN COUNTY LINE TO CTH P RSRF20 2027
2040-21-70 USH 045 STH 36 TO RAWSON AVE (CTH BB) RSRF30 2027
2200-17-70 USH 018 HIGHLAND BLVD-WISC & 35TH-27TH ST RSRF30 2027
3150-06-70 USH 014 CTH K TO ILLINOIS ST LINE RCND20 2027
3364-02-63 STH 175 EAST COUNTY LINE TO CTH DD PSRS40 2027
4015-22-71 STH 075 SCL-STH 28 RSRF10 2027
4085-65-71 STH 032 STH 96-COOK STREET RSRF20 2027
4085-66-71 STH 032 BREED ST-STH 114 RSRF30 2027
4115-14-71 STH 147 CTH VV - CTH B RSRF20 2027
4115-15-71 STH 147 CTH B - IH 43 RSRF20 2027
4322-10-71 STH 067 STH 32 - USH 151 RSRF20 2027
Page 24 of 26
ADA TRANSITION PLAN 2020 UPDATE
4540-35-71 STH 032 STH 23 - STH 42 RSRF20 2027
5250-06-72 STH 053 CASS STREET TO 2ND STREET PVRPLA 2027
5270-01-70 STH 060 RIDDLE ROAD TO CLARK STREET RSRF30 2027
5280-03-71 STH 113 CTH V TO CTH P PVRPLA 2027
5545-00-70 STH 071 CTH V TO STH 80 RSRF30 2027
5790-02-72 STH 171 STH 27 TO USH 61 RSRF20 2027
6070-01-72 STH 033 0.1MI W OF FOREST STREET TO STH 68 RSRF30 2027
6070-02-72 STH 068 STH 33 TO EDGELAWN DRIVE RSRF30 2027
6090-14-71 STH 049 WCPL BRANDON-STH 23 RSRF30 2027
6180-30-71 STH 021 STH 116 - LEONARD POINT ROAD RSRF10 2027
6260-00-72 STH 161 CTH J TO STH 110 RSRF10 2027
6290-05-60 USH 010 IH 39 TO CTH J PSRS30 2027
6290-05-76 USH 010 BADGER AVENUE TO CTH J RCND20 2027
6414-00-82 STH 054 CTH B TO GREEN DRIVE RECST 2027
7030-00-72 USH 010 STH 73 TO EAST COUNTY LINE RSRF20 2027
8220-00-71 STH 064 CTH B TO STH 73 S RSRF20 2027
8620-00-75 STH 040 USH 12 TO CTH M RSRF20 2027
8620-00-76 STH 040 CTH M TO USH 53 RSRF20 2027
8824-00-72 STH 025 USH 8 E TO STH 48 COLD20 2027
Total Projects for 2027 36
Total Projects 406
*Projects will need to be evaluated on a project basis to determine if curb ramp work is needed.
Page 25 of 26
ADA TRANSITION PLAN 2020 UPDATE
I. Stand-alone Program Locations
Page 26 of 26
ADA TRANSITION PLAN 2020 UPDATE
END OF DOCUMENT