adequacy assessment for the 2017 pacific northwest power supply

43
Adequacy Assessment for the 2017 Pacific Northwest Power Supply Steering Committee Meeting October 26, 2012 Portland, Oregon 1

Upload: ivan

Post on 08-Feb-2016

65 views

Category:

Documents


0 download

DESCRIPTION

Adequacy Assessment for the 2017 Pacific Northwest Power Supply. Steering Committee Meeting October 26, 2012 Portland, Oregon. Outline. Final 2017 Resource Adequacy Assessment Changes since August Draft Additional Slides (if needed). NW Adequacy Standard. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

1

Adequacy Assessment for the2017 Pacific Northwest Power

Supply

Steering Committee MeetingOctober 26, 2012Portland, Oregon

Page 2: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

2

Outline Final 2017 Resource Adequacy

Assessment

Changes since August Draft

Additional Slides (if needed)

Page 3: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

3

NW Adequacy Standard Metric: Loss-of-load probability

(LOLP) Threshold: Maximum of 5 percent

LOLP is the probability that extraordinary actions would have to be taken in a future year to avoid curtailment of electricity service

Calculated assuming existing resources only and expected efficiency savings

Page 4: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

4

2017 Assessment The expected LOLP is 6.6% January, February and August most

critical months

Interpretation: Relying only on existing resources and expected efficiency savings yields a power supply in 2017 whose likelihood of curtailment exceeds our agreed upon threshold

Page 5: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

5

2017 Monthly LOLP

Page 6: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

6

Actions to Alleviate Inadequacy 350 MW of new generating resource

capacity drops the expected LOLP to 5% Equivalently, 300 MWa of additional energy

efficiency does the same– Equals 50 MWa per year above the target– Which was accomplished in 2010-11

Demand response measures could also help

This is consistent with utility plans and the Council’s resource strategy

Page 7: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

7

Major Assumptions Existing resources (sited and

licensed) 6th Power Plan conservation Market supplies

– NW: 3,450 MW winter, 1,000 MW summer

– SW on-peak: 1,700 MW winter, none summer

– SW off-peak: 3,000 MW year round Council’s medium load forecast

Page 8: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

8

Sixth Plan Target Efficiency LevelsYear Incremental Savings

(MWa)Cumulative Savings

(MWa) 2010 200 200

2011 220 420

2012 240 660

2013 260 920

2014 280 1,200*

2015 300 1,500

2016 320 1,820

2017 340 2,160

*Council’s target for 2014 is 1,200 MWa with a high-end range of 1,400 MWa. Extrapolating this data yields a high-end value of 2,400 MWa for 2017 (or 240 MWa more than the target).

Page 9: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

9

Major Uncertainties Explicitly modeled

– Water supply– Temperature load variation– Wind– Forced outages

Not modeled explicitly– Economic load growth– Uncertainty in SW market

Page 10: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

10

Effects of Uncertainties

Load SW Winter Market LOLP

Low High 2.8%

Low None 8.4%

High High 7.8%

High None 16.8%

Expected Expected 6.6%

Page 11: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

11

Variation in LOLP due to Load and MarketLoad change in percent from medium >>>>

Market -2.50 -2.25 -2.00 -1.75 -1.50 -1.25 -1.00 -0.75 -0.50 -0.25 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.25 2.500 8.4 11.8 16.8

100 13.2200 13.3300 13.2400 13.2500600700800900 6.3 10.4

1000 5.11100 4.812001300 5.41400150016001700 3.7 4.5 6.6 9.818001900200021002200230024002500 3.8 7.22600270028002900300031003200 2.8 5.0 7.8

Page 12: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

12

Illustration of LOLP Probability

Page 13: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

13

Effects of Adding Resources 350 MW of new resource moved the

reference case LOLP of 6.6% down to 5.0%

2,850 MW of new resource moved a high LOLP of 13.3% down to 5.0%

Sum of utility planned* resources exceeds 3,000 MW

*In this context “planned” means request for proposals or RFPs.

Page 14: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

14

Adding 350 MW of CCCTLoad change in percent from medium >>>>

Market -2.50 -2.25 -2.00 -1.75 -1.50 -1.25 -1.00 -0.75 -0.50 -0.25 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.25 2.500

100200300400500600700800900 4.5

10001100120013001400150016001700 5.0180019002000210022002300240025002600270028002900300031003200 5.3 6.1

Page 15: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

15

Adding 2,850 MW of CCCTLoad change in percent from medium >>>>

Market -2.50 -2.25 -2.00 -1.75 -1.50 -1.25 -1.00 -0.75 -0.50 -0.25 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.25 2.500 4.9 5.4

100200 5.0300400500600700800900 5.0

10001100120013001400150016001700 2.5180019002000210022002300240025002600270028002900300031003200

Page 16: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

16

Changes Since the last Draft

Many changes were made based on comments from the technical committee

Expected LOLP changed from 6.9 to 6.6%

Page 17: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

17

Revisions since August Draft Code fix (related to Canadian operations,

eliminated anomalous June curtailments) 80 year hydro record and updated

Canadian reservoir operations LLH Summer purchase-ahead changed to

3000 MW (previous value was 1000 MW) Net regional wind dedicated to serving

regional load changed to 4266 MW due to removals, additions and adjustments (previous value was 4421 MW)

Page 18: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

18

Revisions since August Draft Thermal resource changes

– IPP now 3451 MW (was 3586 MW) Centralia 1 (670 MW IPP changed to 290 MW IPP

and 380 MW firm) Tenaska (245 MW firm changed to 245 MW IPP)

– Firm 12746 MW changed to 12881 MW– Mill Creek/Dave Gates Generating Station

changed to 47 MW (33% of 143 MW, previous value was 49.5 MW – 33% of 150 MW)

– Highwood Generating Station removed (previously supplied 13 MW)

Page 19: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

19

Summer Thermal Derates

Page 20: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

20

Illustration of Summer Derate

Page 21: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

21

Revisions since August Draft Wind capacity factor set

– Studied 20 sets of temperature-correlated wind capacity factors, LOLP differed by 1 to 2% depending upon which set was used

– Selected a set that tested at the middle of the LOLP range

Number of games– 6160 games ( = 80 hydro x 77 load), all

unique combinations of water and load (wind is locked to load)

Page 22: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

22

LOLP Surface Map from AugustReference CaseLoad change in percent from medium >>>>

Market -2.5 -2.25 -2 -1.75 -1.5 -1.25 -1 -0.75 -0.5 -0.25 0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.50 7.1 11.6 18.0

100200300400500600700800900 6.7 9.9

10001100120013001400150016001700 3.0 6.9 10.618001900200021002200230024002500 4.0 6.92600270028002900300031003200 2.6 5.9 9.1

Page 23: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

23

Current LOLP Surface MapLoad change in percent from medium >>>>

Market -2.50 -2.25 -2.00 -1.75 -1.50 -1.25 -1.00 -0.75 -0.50 -0.25 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.25 2.500 8.4 11.8 16.8

100 13.2200 13.3300 13.2400 13.2500600700800900 6.3 10.4

1000 5.11100 4.812001300 5.41400150016001700 3.7 4.5 6.6 9.818001900200021002200230024002500 3.8 7.22600270028002900300031003200 2.8 5.0 7.8

Page 24: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

24

Effects of 70-yr vs. 80-yr hydro

Page 25: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

25

Additional Slides

Page 26: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

26

Final 2017 Assessment ResultsLOLP Pk LOLP E LOLP A EUSR CVaRE CVaRPk EUE LOLH

Study Case Load Dev. Mkt. (%) (%) (%) (%) (MWh) (MW) (MWh) (Hrs/Yr)Reference Case 0.00% 1700 6.6 1.9 6.6 9.7 98813 4000 5038 2.7High Load, High Market 2.50% 3200 7.8 1.4 7.8 13.6 73034 4014 3834 2.4High Load, Low Market 2.50% 0 16.8 6.6 16.8 21.7 382967 5591 23872 12.1Low Load, High Market -2.50% 3200 2.8 0.4 2.8 5.1 22876 1873 1144 0.7Low Load, Low Market -2.50% 0 8.4 2.9 8.4 10.7 156950 3755 8335 4.8Med-High Load, Med-High Mkt 1.50% 2500 7.2 1.6 7.2 11.8 86055 4098 4455 2.5Med-High Load, Med-Low Mkt 1.50% 900 10.4 3.7 10.4 14.2 213705 5021 11595 6.0Med-Low Load, Med-High Mkt -1.50% 2500 3.8 0.9 3.8 6.3 41283 2587 2069 1.2Med-Low Load, Med-Low Mkt -1.50% 900 6.3 2.1 6.3 8.4 112189 3787 5692 3.0Reference Load, High Market 0.00% 3200 5.0 0.8 5.0 8.4 42082 2881 2133 1.3Reference Load, Low Market 0.00% 0 11.8 4.6 11.8 15.1 255612 4637 14503 7.7High Load, Reference Market 2.50% 1700 9.8 2.9 9.8 15.1 173744 5117 9248 5.0Low Load, Reference Market -2.50% 1700 3.7 1.0 3.7 5.8 50679 2618 2536 1.4

Key:LOLP ALOLP PkLOLP EEUSREUE LOLHCVaRECVaRPk

Average of 5% largest total annual curtailmentAverage of 5% largest single hour curtailments

Loss of Load Probability (annual) = Forum Standard MetricLOLP based on peak curtailments onlyLOLP based on energy curtailment onlyExpected Use of Standby ResourcesExpected Unserved EnergyLoss of Load Hours = expected number of hours of curtailment per year

Study Summary

Page 27: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

27

Revisions since August Draft Thermal resource changes

– Summer derate for thermal plants Project capacity is represented by a single

number (winter capacity) Reduced summer capacity is achieved

through adjustment to the maintenance schedule

Reviewed summer and winter capacity figures and specific schedules in the White Book (from PNUCC submittals) to create customized maintenance schedules

Page 28: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

28

Thermal derate schedules

Page 29: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

29

Thermal derate schedules

Page 30: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

30

Thermal derate schedules

Page 31: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

31

Effects of 70-yr vs. 80-yr hydro

Run the reference case with 70-yr hydro and 1000 MW summer purchase-ahead resource. Note that August issues, which are not as apparent with 80-yr hydro, appear when switching back to 70-yr hydro

LOLP Pk LOLP E LOLP A EUSR(%) (%) (%) (%)5.8 1.2 5.8 9.6

CVaRE CVaRPk EUE LOLH(MW-Hrs) (MW) (MW-Hrs) (Hrs/Yr)

62623 3227 3204 2.1

Page 32: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

32

Monthly LOLP Monthly LOLP and EUE for each of the

study cases is shown on the following charts

Page 33: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

33

Monthly LOLP

Page 34: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

34

Monthly LOLP

Page 35: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

35

Monthly LOLP

Page 36: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

36

January LOLP surface mapLOLP Variance due to Load/Conservation Uncertainty and On-Peak Winter Market Uncertainty (This is for January only)

0 5.40% 7.10% 9.60%

900 4.30% 5.90%

1700 2.30% 3.80% 4.90%

2500 2.10% 3.60%

3200 2.30% 2.30% 3.10%-2.50% -2.00% -1.50% -1.00% -0.50% 0.00% 0.50% 1.00% 1.50% 2.00% 2.50%

Load Deviations from Medium Forecast (surrogate for load+conservation uncertainty)

On-

Peak

Win

ter

SW M

arke

t Su

pply

(MW

)

Page 37: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

37

How much CT gets you to 5%

Add a CT resource that will bring study cases with >5.0% LOLP down to 5.0%Study Summary LOLP Pk LOLP E LOLP A EUSR CVaRE CVaRPk EUE LOLH

Study Case Load Dev. Mkt. Add CT (%) (%) (%) (%) (MWh) (MW) (MWh (Hr/sYr)Reference Case 0.00% 1700 350 5.0 1.5 5.0 7.3 76466 3410 3851 2.1High Load, High Market 2.50% 3200 750 5.0 0.9 5.0 7.9 43510 2913 2197 1.4High Load, Low Market 2.50% 0 4800 5.0 0.8 5.0 6.2 43007 2645 2162 1.4Low Load, High Market -2.50% 3200 NALow Load, Low Market -2.50% 0 1155 5.0 1.5 5.0 6.5 76118 2593 3829 2.4Med-High Load, Med-High Mkt 1.50% 2500 525 5.0 1.1 5.0 8.0 58041 3165 2923 1.7Med-High Load, Med-Low Mkt 1.50% 900 1950 5.0 1.3 5.0 6.8 61092 2866 3071 1.9Med-Low Load, Med-High Mkt -1.50% 2500 NAMed-Low Load, Med-Low Mkt -1.50% 900 450 5.0 1.5 5.0 6.7 80421 3184 4033 2.3Reference Load, High Market 0.00% 3200 NAReference Load, Low Market 0.00% 0 2750 5.0 0.8 5.0 6.3 53995 2443 2717 1.9High Load, Reference Market 2.50% 1700 1200 5.0 1.5 5.0 7.7 75020 3400 3778 2.1Low Load, Reference Market -2.50% 1700 NAHigh Case within likely region 1.25% 200 2850 5.0 1.0 5.0 6.6 56369 2587 2836 1.9

Page 38: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

38

How much CT gets you to 5%Load change in percent from medium >>>>

Market -2.50 -2.25 -2.00 -1.75 -1.50 -1.25 -1.00 -0.75 -0.50 -0.25 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.25 2.500 1155 2750 4800

100200 2850300400500600700800900 450 1950

10001100120013001400150016001700 3.7 350 120018001900200021002200230024002500 3.8 525260027002800 No additional resource is added to study2900 cases already at or below 5.0% LOLP300031003200 2.8 5.0 750

Page 39: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

39

Add Standby Resources Increase Standby Resources to bring

study cases with >5.0% LOLP down to 5.0%Study Summary LOLP Pk LOLP E LOLP A EUSR CVaRE CVaRPk EUE LOLH

Study Case Load Dev. Mkt. Add SR (%) (%) (%) (%) (MWh) (MW) (MWh) (Hrs/Yr)Reference Case 0.00% 1700 500 5.0 1.9 5.0 9.7 98813 4000 5038 2.7High Load, High Market 2.50% 3200 600 5.0 1.4 5.0 13.6 73034 4014 3834 2.4High Load, Low Market 2.50% 0 4800* 2.1 6.6 6.6 21.7 382967 5591 23872 12.1Low Load, High Market -2.50% 3200 NALow Load, Low Market -2.50% 0 1275 5.0 2.9 5.0 10.7 156950 3755 8335 4.8Med-High Load, Med-High Mkt 1.50% 2500 520 5.0 1.6 5.0 11.8 86055 4098 4455 2.5Med-High Load, Med-Low Mkt 1.50% 900 2400 4.9 3.7 5.0 14.2 213705 5021 11595 6.0Med-Low Load, Med-High Mkt -1.50% 2500 NAMed-Low Load, Med-Low Mkt -1.50% 900 850 5.0 2.1 5.0 8.4 112189 3787 5692 3.0Reference Load, High Market 0.00% 3200 NAReference Load, Low Market 0.00% 0 2600 4.1 4.6 5.0 15.1 255612 4637 14503 7.7High Load, Reference Market 2.50% 1700 2050 5.0 2.9 5.0 15.1 173744 5117 9248 5.0Low Load, Reference Market -2.50% 1700 NAHigh Case within likely region 1.25% 200 3500 3.1 4.8 5.0 17.2 302480 5032 17405 9.0

* in the High Load, Low Market case, standby resources reduced LOLP Pk, but LOLP E stayed at 6.6%

Page 40: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

40

Effects of Adding Resources 500 MW of additional standby resources moved

the reference case LOLP of 6.6% down to 5.0% 3,500 MW of additional standby resources moved

a high LOLP of 13.3% down to 5.0% The existing standby resource thresholds are 660

MW Oct-Mar and 720 MW Apr-Sep

Page 41: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

41

Page 42: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

42

Page 43: Adequacy Assessment for the 2017 Pacific Northwest Power Supply

43