adv. no. 2015-020 r1 file: 1613.9 - bc hydro · adv. no. 2015-020 r1 supersedes: r0 issue date: aug...
TRANSCRIPT
Equipment Advisory
Adv. No. 2015-020 R1 Supersedes: R0
Issue Date: Aug 19, 2015 File: 1613.9.1
Information Bulletin: Duct Spacers and Warning Boards for PVC Duct
Revision Note Revised text in this advisory since the previous revision is shown with a vertical bar in the margin: changed or added text is underlined, and deleted text is crossed-out. Revisions in the drawings are encircled with a cloud-shape, and a number in a small triangle indicates the revision edition.
1.0 Items Covered ES54 H1-01 URD AND UD INSTALLATIONS
H1-07 INSTALLATION AT REDUCED DEPTH OF COVER H2-03 CONCRETE ENCASEMENT 5" DUCT H4-01 DUCT CLEARANCES TO OTHER UTILITIES
2.0 Overview Distribution Standards are implementing a new construction practice for the assembly and installation of underground PVC duct for distribution infrastructure. This new construction practice will become mandatory when the revised ES54 Construction Standards are published. In the interim, all new projects shall follow this Advisory and the attached draft ES54 standards, effective August 3, 2015.
Duct Spacers – BC Hydro Catalogue ID 96022508: In accordance with the Class of Work Specifications, the assembly of the duct bank is left up to the BC Hydro contractor. They have the discretion to implement the most suitable and economical method of assembly. In some cases, contractors have installed manufactured duct spacers, resulting in superior assembly and better quality. More frequently, contractors will use 2"x4" or other pieces of lumber, or cut 3"dia PVC duct pieces to use as vertical spacers, which are then covered in concrete. For horizontal spacing, contractors place “rakes” and then remove them following the pour of the concrete layer.
Warning Boards – BC Hydro Catalogue ID 97000676: For mechanical protection and warning of direct buried feeder duct banks, or reduced depth of burial, the BC Hydro standard practice has been to install preservative-treated lumber boards and PVC warning tape above the duct bank. However, a lumber board’s life expectancy is short, mechanical strength deteriorates quickly and a thin yellow warning tape is difficult to see when excavating.
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution. Page 1 of 4
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-020 R1
The new construction practice described herein is based on installing industry standard, impact-resistant polyethylene warning boards. New boards have been developed to perform both functions: mechanical protection for feeder direct buried duct banks, or reduced depth of burial, as well as a visible warning for a cable duct installation presenting an electrical hazard.
For further reference on product evaluation and field trials, refer to ETR051 (http://edmbchwiki1/dist/standards/images/3/31/ETR051_Duct_Spacers_Final.pdf).
3.0 Action BC Hydro stores now carry PVC duct spacers and marker boards as standard stock items 96022508 and 97000676 respectively.
Duct Spacers: For concrete-encased duct banks, BC Hydro designers shall follow the draft ES54 Section H standards and include new PVC type duct spacers. For customer installed concrete-encased duct banks, with customer supplied 5" PVC duct, the customer design shall show and the customer shall install the same IPEX PVC type duct spacer 5W20-2.
Warning Boards: For direct-buried feeder duct banks or reduced depth of burial, BC Hydro designers shall follow the draft ES54 Section H standards, which show a warning board. For direct-buried URD and UD duct banks, warning boards may be installed as selected by the BC Hydro Designer at locations where a high safety hazard is identified by a risk assessment. For customer projects, warning boards can be obtained from LineStar Supply Inc. (www.linestar.ca) located at 4-8125 130th St., Surrey, BC, V3W 7X4 or contact Tony Kuhlman Ph. 604.594.2701 F. 604.594.2751 C. 604.374.3413
Class of Work Specifications 1322 and 1323 will be revised shortly to include duct spacers and warning boards for new construction projects.
Projects currently in progress may proceed with a duct installation per the approved project design.
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution Page 2 of 4
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-020 R1
4.0 Figures
Figure 1 – IPEX 5W20-2 Duct Spacer for 5" dia. PVC Duct
Figure 2 – Warning board Figure 3 – Direct burial
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution Page 3 of 4
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-020 R1
Figure 4 - Duct spacer locking tabs Figure 3 - 5" Duct spacers
5.0 Distribution Standards Contact
Name: Mark Kelvin email : [email protected]
Phone #: 778-452-6844 Cell # : 604-220-3905
6.0
Date: 2015-08-18 Date: 2015-08-18
This Advisory is for the information of personnel working on BC Hydro's distribution equipment, and is not for public distribution
Page 4 of 4
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:DEC 2000ORIGINALLYISSUED: JUN1980
PAGEOF
R
1 3ES54 H1-01
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
GENERAL TRENCHING DETAILSURD AND UD INSTALLATIONS
Notes1. Spacers shall not be used for direct buried ducts.2. For direct-buried duct bank installation, place warning tape or polyethylene marker boards,
catalogue ID 97000676, may be placed instead of treated lumber boards and marking tapeat locations with high safety hazard as determined by the BCH Designer.
Reference Standards
ES54 H0-02 Duct General NotesES54 H1-06 Duct Entry DetailsES54 H2-01 75 mm (3") Duct ES54 H2-02 100 mm (4") DuctES54 H2-03 125 mm (5") DuctES54 H2-04 ReinforcingES54 H3-01 Window Opening In Underground ChambersES54 H4-01 Clearances to Other UtilitiesES54 W1-01 Base Preparation, Backfill Material
Installation Location Min. Depth of Cover (mm)Railway 1680
MOTI Roadway 1200Other Areas 900
Direct Buried Concrete Encased
Concrete
Backfill
300
Cov
er
Warningtape or board
Finished grade
Backfill
Ducts
300
Cov
er
Warning TapeFinished grade
Base
Ducts
BaseTemporary trench shoring if required by contractor, remove before backfill
1
DRAFT
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:APR 2003ORIGINALLYISSUED:APR 2003
PAGEOF
R
4 0ES54 H1-07
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
GENERAL TRENCHING DETAILSINSTALLATION AT REDUCED
COVER DEPTH
1 .01
Elevation
Ducts
ManholeWarning platesB
Chy
dro
Sidewalk or road
Plan
BC
hydr
o
BC
hydr
o
BC
hydr
o
A_
Manhole
3000MAX
Warning platesBCH Cat ID: 96017849
Min
imum
sta
ndar
d co
ver
< M
inim
um s
tand
ard
cove
r
Min
imum
sta
ndar
d se
para
tion
Other utilities orany otherobstructions
6000 MAX
300
Alternativewarningboards
Warning tape
Finished grade
Rebar: 10M, L=900 mm
Ducts concreteencased
Warning plate
70C
over
Section A_ 2
Detail 1
Detail 1_
_DRAFT
Aug 17
, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:APR 2003ORIGINALLYISSUED:APR 2003
PAGEOF
R
4 0ES54 H1-07
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
GENERAL TRENCHING DETAILSINSTALLATION AT REDUCED
COVER DEPTH
2 .02
Elevation
Bridge
Ducts ManholeWarning plates
Bridge
BC
hydr
o
Sidewalk
Plan
BC
hydr
o
BC
hydr
o
BC
hydr
o
A1
Manhole
6000MAX
Bridgeabutment
Warning platesBCH Cat ID: 96017849
Installation in Bridge Deck
DRAFT
Aug 17
, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:APR 2003ORIGINALLYISSUED:APR 2003
PAGEOF
R
4 0ES54 H1-07
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
GENERAL TRENCHING DETAILSINSTALLATION AT REDUCED
COVER DEPTH
Notes1. The minimum burial depth may be reduced when the minimum burial depth is impractical to avoid obstructions.2. The reduced burial depth for PVC pipe shall be limited to 400 mm from the top surface of the duct bank to the finished grade.3. The duct bank shall be concrete-encased along the entire length and reduced burial depth.4. The maximum continuous length of the reduced burial depth shall not exceed 6 metres, and5. Cast iron warning plates (BC Hydro Catalogue ID 96017849) shall be installed within a finished grade at 3000 mm distance along the duct bank alignment at reduced burial depth, or 6. When installation of cast iron warning plates is impracticable, warning tape shall be replaced with warning boards (Cat ID 91002902).Cast Iron Warning Plates InstallationThe warning plates are designed primarily to be installed within a concrete sidewalk. For installation within a roadway traffic surface, its replacement should be scheduled to follow the road maintenance and resurfacing program.Installation in ConcreteThe plates shall be cast in the concrete during the sidewalk construction as follows: 1. Install a rebar loop through each hole at the bottom side of the plate;2. Tie the loops to other rebar in the concrete and secure plate in the proper position;3. Ensure that the top surface of the plate is flush with or below the roadway surface; 4. Pour the concrete, and ensure minimum concrete cover below the rebar, and5. Ensure that concrete does not cover the plate’s top surface.Installation in AsphaltThe asphalt surface of the roadway is cut for plates during pavement construction, and plates are epoxy cemented in the cut outs as follows:1. Construct roadway surface with a minimum 75 mm asphalt pavement thickness at the warning plate’s location.2. Mark the locations of warning plates at the roadway surface along the centre line of the duct bank.
a) Select locations with no deficiencies in the pavement. b) Avoid joints or cracks.c) Avoid pavement marking and line stripping.
3. Cut and grind the asphalt pavement surface at the marked locations, to a depth necessary to fully recess the warning plates in the roadway surface.
a) Cut outs shall be completely dry and free of oil and foreign materials. b) Ensure that cut is within the pavement depth.c) Abandon overcut and select other location.
3 .03
DRAFT
Aug 17
, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:APR 2003ORIGINALLYISSUED:APR 2003
PAGEOF
R
4 0ES54 H1-07
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
GENERAL TRENCHING DETAILSINSTALLATION AT REDUCED
COVER DEPTH
4. Test the plate fitting into the cut outs, and extend cut depth if necessary. a) Allow 3 mm clearance between pavement cut and plate for epoxy to bond properly.
5. Apply epoxy grout into cut-outs, in accordance with the manufacturer’s recommendation.a) Epoxy shall comply with AASHTO M237 Type 4
6. Place warning plates into the epoxy field cut-outs a) Ensure that the top surface of the plate is flush with or below the roadway surface. b) Ensure epoxy overflows around the plate to seal the cut area. Add additional epoxy if
needed.c) Ensure epoxy does not cover the plate.d) Protect plates from traffic during the epoxy curing time.
4 .04
DRAFT
Aug 17
, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:JUL 2002ORIGINALLYISSUED:JUN 1980
PAGEOF
R
2 3ES54 H2-03
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
CONCRETE ENCASEMENT5” DUCT
1 .01
490 680 870
560
750
950
5" Ducts
Cov
er
Cov
er
Cov
er
150 192
146
190
Notes1. All cross-sections shown are for 125 mm (5") UD or feeder PVC duct, or rigid FRE conduit.2. All concrete-encased 5" duct banks shall be assembled using prefabricated duct spacers, cata-logue ID 96022508. For dimensional references and assembly details, refer to H2-03.02 for IPEX 5W20-2 spacers.
DRAFT
Jul 1
0, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:JUL 2002ORIGINALLYISSUED:JUN 1980
PAGEOF
R
2 3ES54 H2-03
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
CONCRETE ENCASEMENT5” DUCT
2 .02
Reference StandardsES54 H2-04 ReinforcingES54 H4-01 Clearances to Other UtilitiesES54 H1-02 General Trenching Details: FeedersES54 H3-01 Window Opening in Underground ChambersES54 H1-01 General Trenching Details: URD and UD InstallationES54 H2-05 Additions to Existing Duct Bank
384
146
190
192
76
Ø127
38 TYP
25TYP
TOP VIEW
FRONT VIEW SIDE VIEW
50
45
5” Duct Spacer Catalogue ID 96022508
DRAFT
Jul 1
0, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:JUL 2002ORIGINALLYISSUED:JUN 1980
PAGEOF
R
3 3ES54 H4-01
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
DUCT CLEARANCES TO OTHER UTILITIES
1 .01
DRAFT
Jul 1
0, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:JUL 2002ORIGINALLYISSUED:JUN 1980
PAGEOF
R
3 3ES54 H4-01
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
DUCT CLEARANCES TO OTHER UTILITIES
Minimum ClearancesA minimum crossing separation is required from other utilities to provide clearance for repairs.
*Concrete encasement shall extend a minimum 3400 1500 mm on each side of crossing.Horizontal clearances shall be maintained regardless of vertical clearances. Additional separation may be required where the cables are laid in the vicinity of other power cables or metal pipes, to maintain the specified heat ratings from these nearby services.
Type of Pipe or Duct Direct-Buried BC Hydro Ducts
Concrete-Encased BC Hydro Ducts*
Clearances (mm) A B A BTelephone, cable TV or street lights 300 150 75 150Gas mains 300 300 300 300Water, oil pipelines, jet fuel lines, storm and sanitary sewers 900 300 300 300
Steam pipe 3400 3400 3400 3400
2 .02
BB
Other utility ductsOther utility ductsOther utilityducts or pipes
A
BackfillFinished grade
Typical Trench Cross SectionDirect Buried Duct
1/2
B
Warning board - extend1.2m each side from utilityduct or pipe
Warning tape board
DRAFT
Jul 1
0, 15
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
DESIGNED RECOMMENDED ACCEPTED
ISSUED:JAN 2013REPLACES:JUL 2002ORIGINALLYISSUED:JUN 1980
PAGEOF
R
3 3ES54 H4-01
RE
VISI
ON
S:
M. KELVIN L. STEVANOVIC F. DENNERT
ENGINEER OF RECORD
DUCT CLEARANCES TO OTHER UTILITIES
.033
Steam PipesThe clearances shown are for steam pipes of less than 225 mm nominal diameter. For larger diame-ter steam pipes, consult the BC Hydro designer.Steam pipes shall be insulated with a minimum of 75 mm thick foam glass pipe insulation, extending a minimum of 1200 mm on each side of the crossing. Where a steam pipe crosses below the BC Hydro duct bank, the backfill material between the steam pipe and BC Hydro duct bank shall have thermal resistivity.
Railway CrossingsAt railway crossings, if the width of the duct bank exceeds 550 mm, additional strengthening may be required, as defined in CSA Standard C22.3 No. 7, Underground Systems. At railway crossings, the minimum concrete cover over ducts shall be 75 mm.
Reduced Depth of Cover The minimum cover over the duct bank may be reduced, where absolutely necessary to overcome unavoidable site obstructions, subject to the following conditions:
1. The duct bank shall be concrete encased.2. The continuous trench length at the reduced depth shall not exceed 6 metres, unless the ductsare installed in a bridge superstructure.3. The design shall be approved by the BC Hydro Distribution Engineer.
Reference DocumentCSA Standard C22.3 No. 7 "Underground Systems"
Reference StandardsES54 H1-02 General Trenching Details - FeedersES54 H1-02 General Trenching Details - URD and UD
DRAFT
Jul 1
0, 15Cast iron warning plate Cat Id 96-7849 or warning boards Cat Id 9700-0676 shall be placed
over the length of reduced duct burial. 4.
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.