advanced distribution automation application with...
TRANSCRIPT
Advanced distribution automation application with miscoordination correction algorithm based on neural network Alexandr Stinskiy, Ph.D – SiemensChristopher Huff, P.E. - Southern California Edison
• 15 million residents in a 50,000 square mile area
• 46% energy from carbon-free sources• Joined open letter to support Paris Climate
Accord• Utility Dive “2017 Utility of the Year” for our
2017 Clean Power and Electrification Vision Plan
• Procured close to 500 MW of storageSupporting California’s 2030 greenhouse gas reduction goals
2
Southern California Edison
Remote Integrated Switch (RIS)
– Decentralized DA Application;– Advanced Automation for fault detection and
auto circuit reconfiguration;– Incorporate greater levels of telemetry to
support DERMS & GM;– Support multiple communication technology
standards;– Support various circuit topologies;– Drop-into-place solution
RIS Project Concept
TS
TS
TS
1.5 Circuit 2.5 Circuit 3.5 Circuit
RIS Extended Schemes
CB
MS1
TS3
MS2
Substation A
CB
MS5
MS4
Substation B
TS9
MS6
MS7
TS8
Substation C
TS10
CB
MS11
Substation D
MS12
TS13
Operation Examples
CB
MS1
TS3
MS2
Substation A
CB
MS5
MS4
Substation B
TS9
MS6
MS7
TS8
Substation C
TS10
CB
MS11
Substation D
MS12
TS13
RIS CommunicationLegacy NetCom Radio System– DNP Protocol– Contains ~50,000 radio nodes– Unlicensed operation
in 902-928 MHz band– 9600 bps data rate – 0.1 Watt output– Packet contains 207 byte of data– Average 20 sec. one-way latency– DNP Router Concept was introduced
Data exchange
RIS1SUB A SUB BRIS2 RIS3 RIS4 RIS5MS A1 MS A2 TS AB MS B2 MS B1
RIS Status
DNP Router
Information from every RIS is broadcasted to the rest of the system via DNP commands
Z1 Z2 Z3 Z4 Z5 Z6
900MhzNetCom System
DNP Router Concept
• Router can skip unnecessary steps in the data processing
• Flexibility by autonomously self-adjusting to system conditions
• Improves operating speed
RIS1Broad-
cast
RIS2Broad-
cast
RIS3Broad-
cast
RIS4Broad-
cast
RIS5Broad-
cast
Mode Broad-
cast
Grid Fault
P1 CommFault
P2CommFault
P4 CommFault
P5CommFault
P3 CommFault
RIS1Poll
RIS2Poll
RIS3Poll
RIS4Poll
RIS5Poll
DNP Router Concept
RIS TOC Coordination
1000
100
10
1
0.1
0.011000 10000
Time, S
Current, A
CB
SMU Fuse
1900 A Trip Release for Mid Switches
- CB settings cannot be changed;
- Narrow gap between CB curve and fuse;
- Three additional curves are required for the RIS;
- Trip release logic is introduced;
- Possible mis-coordination with CB if current is <1900A;
Miscoordination correction
CB1
MS1
TS3
MS2
CB2
MS5
MS4
Substation A Substation B
Z1
Z2
Z3 Z4
Z5
Z6
1. Remote Fault in Zone 4 with fault magnitude <1900A;
2. CB trips faster than MS2;3. CB autoreclose attempt;4. CB trip;5. MS1 operation on loss of S1;
7. MS2 operation from miscoordination logic;
6. CB autoreclose;
8. MS1 operation from miscoordination logic.
System configuration with combination based logicBenefits:- Classic approach employs multiple AND Gates verifying
system conditions;- If certain defined set of conditions is true, AND Gate issues
the operation command to open or close the primary switchgear;
Challenges:- Number of AND Gates per device exponentially grows with
number of automation points in the system;- Hard to account for all abnormal scenarios or multiple near-
simultaneous fault scenarios in the system;- All conditions and their combinations are unique for each
device which requires considerable engineering effort
System logic based on Neural Network
CB1
MS1
TS3
MS2
CB2
Substation A Substation B
MS4
MS5
System Topology
Zone 1
Zone 2
Zone 3 Zone 4
Zone 5
Zone 6
A01
A02
A03
A05
A04
Neural Network A (Forward)
B01
B02
B03
B05
B04
MS1 Control
MS2 Control
TS3 Control
MS4 Control
MS5 Control
MS1 DML MS2 DML TS3 DML MS4 DML MS5 DML
Neural Network B (Reverse)
7SC80
Automation Controllers
System logic based on Neural Network Extended Scheme
CB2
MS3
TS3
MS4
CB3
MS6
MS5
CB1
MS1
MS2
CB4
MS7
MS8
TS1
TS2
TS4
TS5
Substation A Substation B Substation C Substation DA01
A02
A03
A04
A05
A06
A07
A08
A09
A10
A11
A12
A13
B01
B02
B03
B04
B05
B06
B07
B08
B09
B10
B11
B12
B13
Testing and Validation- 1.5 Circuit Logic
156 Tests
- 2.5 Circuit Logic304 Tests
- 2.5 Ext Circuit Logic664 Tests
- 3.5 and 3.5 ExtendedUnder development
Conclusion- Performed >500 hours of RTDS testing- Pilot Deployment
- December 2016- Five locations between 2 circuits- Performed 2 operation
- Spring 2018- Added one operational group with two
circuits- Total of eight locations between 4 circuits
- Winter 2019- Adding addition circuit to group 1- 11 locations between 5 circuits
- Next demonstration phase will focus on variant with high-speed communications
Christopher Huff, P.E.
Southern California [email protected]
Thank You!
Alexandr Stinskiy, Ph.D.
Siemens Industry [email protected]