GreenPowerOps
Implementation Plan
ECM Case Study 3
Implementation Plan
Assumption1) Phase 1 to 4 are completed (example: stakeholders analysis,
communication strategy, risk plan, blue print, roadmap & design)
2) Implementation plan is made based on 1 business unitin 1 country
Implementation planActivity Resources Duration• Kick off • Functional consultant
• Technical consultant• Trainer• Testers• System /Apps
administrators• Procurement (if
contracts involved)
3 days
• Develop• Working modules• Define testing
(technical & functional end to end)
• User / Administrator manual
8 weeks
• Deploy• Build IT environments• Implement servers and
clients• Integration of line of
business apps• Perform any
customization and conf. reqs
• Operations procedures• Go-Live / Launch
4 weeks
Operate• Monitor & fine tune• Performace SLA’s
2 weeks for handoverActive monitoring for 12 weeksYearly review
Closeout• Sign-off deliverables &
project closure
1 day
Timeframe – Phase I implementation
Develop – 8 weeks
Deploy – 4 weeks
Operate – 2
weeks
Closeout1 day
Phase II is shorter as it is a replication model of this 1st implementation phase