Alaskan Way Viaduct Replacement Program Update Joint Transportation Committee May 14, 2014 Cam Gilmour Deputy Secretary Lynn Peterson Secretary of Transportation Todd Trepanier AWV Program Administrator

Upload: others

Post on 25-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Alaskan Way Viaduct

Replacement Program Update

Joint Transportation Committee

May 14, 2014

Cam Gilmour Deputy Secretary

Lynn Peterson Secretary of Transportation

Todd Trepanier AWV Program Administrator

Page 2: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

• SR 99 Tunnel Project update

– STP’s schedule and repair

plan

– Change order process

– Disadvantaged Business

Enterprise

• Program updates:

– Construction at north and

south end of tunnel

Overview

2

Page 3: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Seattle Tunnel Partners’ Repair Timeline

3

• Late May 2014: Begin building the access pit’s underground walls.

• June 16, 2014: STP / Hitachi Zosen will submit the seal system repair

and bearing replacement plan to WSDOT.

• Late July through September 2014: Excavate the pit.

• October 2014: Remove the machine’s cutterhead and begin repairing

damage to the seal system and main bearing.

• November 2014: STP / Hitachi Zosen will submit a full report of

machine repairs to WSDOT.

• February 2015: Test machine to ensure it is ready to tunnel beneath

downtown.

• Late March 2015: Resume tunneling.

Page 4: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Today, Above Ground

4

Conceptual

Page 5: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan - Today, Below Ground

5

Conceptual

Page 6: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Injecting Grout

Conceptual

6

Page 7: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Relocating Utilities

Conceptual

7

Page 8: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Relocating Utilities

Conceptual

8

Page 9: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Injecting Grout

Conceptual

9

Page 10: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Installing Secant Piles

Conceptual

10

Page 11: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Completing Access Pit

11

Conceptual

Page 12: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Removing Ground Water

12

Conceptual

Page 13: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Tunneling into the Access Pit

13

Conceptual

Page 14: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Installing the Crane

14

Conceptual

Page 15: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Repairing the Machine

15

Conceptual

Page 16: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Change Order Overview

16

• Change orders are the formal mechanism WSDOT uses to make changes

to its construction contracts.

• Requests can be submitted by a contractor to WSDOT or initiated by

WSDOT.

• Contractor-submitted change order process:

– Contractor provides change notice.

– Contractor submits change order request with more details and cost

estimate.

– WSDOT reviews to determine if contractor is entitled to a change

order per the contract.

– If WSDOT determines the contractor is entitled to a change order:

• Pending change order: ongoing discussions about cost, time and

scope.

• Executed change order: after agreement upon the changes is

reached. Once executed, a change order revises the contract to

include the new terms.

Page 17: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Disadvantaged Business Enterprise

17

Finalized Conciliation Agreement with FHWA

• Agreement contains steps both agencies agreed are necessary to improve DBE

participation on AWV Replacement Program.

• Outlines resources that both WSDOT and STP must dedicate to program.

• Stipulates oversight role of WSDOT in enforcing STP activities related to DBE

participation.

• Includes reporting mechanisms that will remain in place through life of project.

Executed Change Order with STP

• Tunnel contractor now contractually required to award $96 million in paid work to

certified DBE firms.

• With executed change order, WSDOT withdrew earlier finding against the firm for

breach of contract.

• Should STP fail to comply with the terms or conditions of the change order, WSDOT

may either reinstate the finding or implement other appropriate contract actions.

AWV DBE Program Administrator

• WSDOT hired Bobby Forch, formerly of SDOT, to oversee program.

Page 18: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

South Portal Operations Building Construction

18

Page 19: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

North Portal Receiving Pit Construction

19

Page 20: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

North Access Construction

20

Page 21: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

For more information on the

Alaskan Way Viaduct Replacement

Program,

please contact:

Todd Trepanier

Program Administrator

206-805-2843 or

[email protected]

www.alaskanwayviaduct.org

Questions?

21