CAMPUS MASTER PLAN UPDATE 2013

Progress Presentation to the Master Plan Committee January 15, 2013

1. Presentation of Build-out Progression (2013-2032) as refined 2. Campus Landscape Design Standards 3. Chilled Water Distribution System Planning 4. Campus Vehicular Circulation Planning

Agenda

TAMU-Commerce Campus 2017

TAMU-Commerce Campus 2022

TAMU-Commerce Campus 2027

TAMU-Commerce Campus 2032

TAMU-Commerce Campus 2032

Typical Fire Lane

Performance Lawn

Site Lighting

4 ½’

12’

Bench, Trash Receptacle & Ash Pan

Tables

Wayfinding & Signage

Bike Racks

Planters

Pedestrian Way Configuration

Existing Pedestrian Way Proposed Pedestrian Way

Retaining Walls

Complement the adjacent architectural elements

Tree Grates

Fencing

Existing Campus Chilled Water Distribution

1

1 Central Plant No. 1 East of Journalism Building (1000 ton + 725 ton)

Central Plant No. 2 In Basement (925 ton) Building shown in Red are served from Chilled Water Loop

2

Purdy-McGuire

2

Existing Campus Chilled Water Distribution

2013 960,000 SF Served by Chilled Water Loop

Peak Tonage: 1,700 tons Total Installed Tonnage: 2675 tons

Purdy-McGuire

New Campus Chilled Water Distribution

2017 Net Add to Loop: 210,000 SF

New Dining Hall Expansion: 32,000 SF New Library: 120,000 SF

New Gen Academic A': 100,000 SF Deduct Journalism: (43,000) SF

Purdy-McGuire

New Campus Chilled Water Distribution

2022: Net Adds to Loop: 123,000 SF New Arena: 140,000 SF

New Arts Building: 125,000 SF Deduct Field House: (89,000) SF Deduct Whitley Gym: (30,000 SF Deduct Wathena Temple: (23,000) SF

(Nursing Building and Science Wing would be on Science chillers)

Purdy-McGuire

New Campus Chilled Water Distribution

2027 Net Adds to Loop: 75,000 SF New One Stop/Mtg/Cinema: 75,000 SF

(New Stadium West Side would not be connected) (New Rec Center exp would be served from Rec chillers)

Purdy-McGuire

New Campus Chilled Water Distribution

2032 Net Adds to Loop: 117,000 SF

General Academic Building 'B': 100,000 SF Alumni Center: 17,000 SF

Purdy-McGuire

Campus Shuttle Plan

The goal of the Campus Shuttle is to improve pedestrian safety by eliminating the need to cross high-volume/high-speed roadways and to increase the utilization of perimeter parking facilities by reducing the required walking distance. Shuttle System Characteristics - Core route is 2.6 miles & has 12 stops (about 16 min @15 mph) - South Residence Hall Loop increases route length to 3 miles & # stops to 14 (about 19 min

@ 15 mph) - West Residence Hall Loop increases route length to 3.3 miles & 14 stops (about 20 min @

15 mph).

Campus Shuttle System

Goods & Services

The goal is to provide adequate access for goods & services vehicles attempting to make deliveries to each/any building. Goods & Services Plan Characteristics - All buildings are accessible for deliveries - All service access points will accept single unit (SU) vehicles w/ a wheelbase of 20’ and an

overall vehicles length of 30’ - Large vehicle deliveries (vehicles with a wheelbase of 40’ or more and/or an overall

vehicle length in excess of 40’) may need to utilize street right-of-way for loading/unloading purposes.

Goods & Services

CAMPUS MASTER PLAN UPDATE 2013

Progress Presentation to the Master Plan Committee January 15, 2013