campus master plan update 2013 · 1/15/2013  · 1. presentation of build-out progression...

30
CAMPUS MASTER PLAN UPDATE 2013 Progress Presentation to the Master Plan Committee January 15, 2013

Upload: others

Post on 27-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

CAMPUS MASTER PLAN UPDATE 2013

Progress Presentation to the Master Plan Committee January 15, 2013

Page 2: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

1. Presentation of Build-out Progression (2013-2032) as refined 2. Campus Landscape Design Standards 3. Chilled Water Distribution System Planning 4. Campus Vehicular Circulation Planning

Agenda

Page 3: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

TAMU-Commerce Campus 2017

Page 4: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

TAMU-Commerce Campus 2022

Page 5: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

TAMU-Commerce Campus 2027

Page 6: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

TAMU-Commerce Campus 2032

Page 7: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

TAMU-Commerce Campus 2032

Page 8: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Typical Fire Lane

Page 9: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Performance Lawn

Page 10: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Site Lighting

4 ½’

12’

Page 11: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Bench, Trash Receptacle & Ash Pan

Page 12: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Tables

Page 13: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Wayfinding & Signage

Page 14: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Bike Racks

Page 15: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Planters

Page 16: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Pedestrian Way Configuration

Existing Pedestrian Way Proposed Pedestrian Way

Page 17: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Retaining Walls

Complement the adjacent architectural elements

Page 18: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Tree Grates

Page 19: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Fencing

Page 20: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Existing Campus Chilled Water Distribution

1

1 Central Plant No. 1 East of Journalism Building (1000 ton + 725 ton)

Central Plant No. 2 In Basement (925 ton) Building shown in Red are served from Chilled Water Loop

2

Purdy-McGuire

2

Page 21: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Existing Campus Chilled Water Distribution

2013 960,000 SF Served by Chilled Water Loop

Peak Tonage: 1,700 tons Total Installed Tonnage: 2675 tons

Purdy-McGuire

Page 22: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

New Campus Chilled Water Distribution

2017 Net Add to Loop: 210,000 SF

New Dining Hall Expansion: 32,000 SF New Library: 120,000 SF

New Gen Academic A': 100,000 SF Deduct Journalism: (43,000) SF

Purdy-McGuire

Page 23: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

New Campus Chilled Water Distribution

2022: Net Adds to Loop: 123,000 SF New Arena: 140,000 SF

New Arts Building: 125,000 SF Deduct Field House: (89,000) SF Deduct Whitley Gym: (30,000 SF Deduct Wathena Temple: (23,000) SF

(Nursing Building and Science Wing would be on Science chillers)

Purdy-McGuire

Page 24: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

New Campus Chilled Water Distribution

2027 Net Adds to Loop: 75,000 SF New One Stop/Mtg/Cinema: 75,000 SF

(New Stadium West Side would not be connected) (New Rec Center exp would be served from Rec chillers)

Purdy-McGuire

Page 25: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

New Campus Chilled Water Distribution

2032 Net Adds to Loop: 117,000 SF

General Academic Building 'B': 100,000 SF Alumni Center: 17,000 SF

Purdy-McGuire

Page 26: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Campus Shuttle Plan

The goal of the Campus Shuttle is to improve pedestrian safety by eliminating the need to cross high-volume/high-speed roadways and to increase the utilization of perimeter parking facilities by reducing the required walking distance. Shuttle System Characteristics - Core route is 2.6 miles & has 12 stops (about 16 min @15 mph) - South Residence Hall Loop increases route length to 3 miles & # stops to 14 (about 19 min

@ 15 mph) - West Residence Hall Loop increases route length to 3.3 miles & 14 stops (about 20 min @

15 mph).

Page 27: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Campus Shuttle System

Page 28: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Goods & Services

The goal is to provide adequate access for goods & services vehicles attempting to make deliveries to each/any building. Goods & Services Plan Characteristics - All buildings are accessible for deliveries - All service access points will accept single unit (SU) vehicles w/ a wheelbase of 20’ and an

overall vehicles length of 30’ - Large vehicle deliveries (vehicles with a wheelbase of 40’ or more and/or an overall

vehicle length in excess of 40’) may need to utilize street right-of-way for loading/unloading purposes.

Page 29: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

Goods & Services

Page 30: CAMPUS MASTER PLAN UPDATE 2013 · 1/15/2013  · 1. Presentation of Build-out Progression (2013-2032) as refined . 2. Campus Landscape Design Standards . 3. Chilled Water Distribution

CAMPUS MASTER PLAN UPDATE 2013

Progress Presentation to the Master Plan Committee January 15, 2013