FACILITIES MANAGEMENT Facilities Planning & Construction Department

Date: May 3, 2018 Report No. 3

CONSTRUCTION PROJECT STATUS REPORT Brandon Avenue Upper Class Housing

General Contractor: KBE Building Corporation, Farmington, CT Architect: Goody Clancy, Boston, MA

Current Status:

Current Activities: •Caisson installation complete•Nearing completion of grade beam excavation, rebar and concrete placement•Building wall forming and pouring continuing along the west line•Column forming and pouring•Utility installation of the site storm water line at the sediment pond area•Electrical ductbank excavation and installation at building access road•Site retaining wall at building access road complete•Construction progress live stream video: www.fm.virginia.edu/depts/fpc/projects/active/brandonavenue.html

Future Activities: •Exterior finish selections for the start of the exterior mock-up•Interior finish selections

Contact Information: Steve Ratliff, Senior Project Manager at spr@virginia.edu / (434) 982.4654 Charlie Durrer, Senior Construction Administration Manager at ced5q@virginia.edu / (434) 982.5393 Amanda Farmer, Construction Administration Manager at af5qc@virginia.edu / (434) 566.2736 Raleigh Roussos, Project Coordinator at rnd2u@virginia.edu / (434) 924.9600

Contract Award NTP December 8, 2017 Start December 8, 2017 Complete June 15, 2019 % complete 18%

First placement of wall concrete

Southwest forming of walls / Utility work

Drystack ‘Redi-Rock’ wall complete / Utility work Preparing to drill the elevator jack hole