FACILITIES MANAGEMENT Facilities Planning & Construction Department
Date: May 3, 2018 Report No. 3
CONSTRUCTION PROJECT STATUS REPORT Brandon Avenue Upper Class Housing
General Contractor: KBE Building Corporation, Farmington, CT Architect: Goody Clancy, Boston, MA
Current Status:
Current Activities: •Caisson installation complete•Nearing completion of grade beam excavation, rebar and concrete placement•Building wall forming and pouring continuing along the west line•Column forming and pouring•Utility installation of the site storm water line at the sediment pond area•Electrical ductbank excavation and installation at building access road•Site retaining wall at building access road complete•Construction progress live stream video: www.fm.virginia.edu/depts/fpc/projects/active/brandonavenue.html
Future Activities: •Exterior finish selections for the start of the exterior mock-up•Interior finish selections
Contact Information: Steve Ratliff, Senior Project Manager at [email protected] / (434) 982.4654 Charlie Durrer, Senior Construction Administration Manager at [email protected] / (434) 982.5393 Amanda Farmer, Construction Administration Manager at [email protected] / (434) 566.2736 Raleigh Roussos, Project Coordinator at [email protected] / (434) 924.9600
Contract Award NTP December 8, 2017 Start December 8, 2017 Complete June 15, 2019 % complete 18%