Facilities Project Management Monthly Report
Friday, May 29, 2020 216Approved Projects
9BOIE, GREGG J
Rudman Hall ‐ Clean Steam Generator Replacement1.1‐ PLAN/EST RR
5/28/20 Project Suspended due to the COVID‐19 3/23/20
Petersen Engineering is scheduled for site visit the 2nd week of March.
Design Firm: Contractor:
2019‐0067
Year Approved
Funding: DMA PROJECT SUSPENDED
Nesmith Hall ‐ Air Sourced Heat Pump suite 1071.1‐ PLAN/EST FCR
5/28/20 Project Suspended due to the COVID‐19 3/23/20
Design Firm: Contractor:
2019‐0227
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Nesmith Hall ‐ Door Automation and Directional Signage1.1‐ PLAN/EST FCR
5/28/20 Project Suspended due to the COVID‐19 3/23/20Yates has PO for electrical will postpone
Design Firm: Contractor: Yates And Portsmouth sign
2020‐0008
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
2 Leavitt Lane ‐ new natural gas boiler1.1‐ PLAN/EST FCR
4/30/20 Project Suspended due to the COVID‐19 3/23/20
Design Firm: Contractor:
2020‐0054
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Dimond Library ‐ Guidance on furniture & design1.1‐ PLAN/EST FCR
5/28/20 Project Suspended due to the COVID‐19 3/23/20
Design Firm: Contractor:
2020‐0061
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Kingsbury Hall ‐ RM S311 Laboratory Ventilation1.1‐ PLAN/EST FCR
5/28/20 Project Suspended due to the COVID‐19 3/23/20
Design Firm: Contractor:
2020‐0210
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
McConnell Hall ‐ Roof Leak Investigation and Repair1.1‐ PLAN/EST RR
5/28/20 Project Suspended due to the COVID‐19 3/23/20 Careno and Building Envelope Specialists will
review the Atrium..at a later date to be determined
Design Firm: Contractor:
2020‐0212
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Friday, May 29, 2020 Page 1 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Taylor Hall ‐ Communications and Marketing Relocation2‐ IN DESIGN SI
4/30/20 Project Suspended due to the COVID‐19 3/23/20Placework gave proposal and I filled out the PO just
missing the fund number when the work from home started and will be on hold
Design Firm: Placework Contractor:
2019‐0146
Year Approved
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Parsons Hall ‐ Rm S128 Ammonia Gas Control System3‐ IN CONSTRUCTION FCR
5/28/20 Project Suspended due to the COVID‐19 3/23/20On hold until we return to the Campus .
Design Firm: Norris Contractor: Norris
2017‐0431
Year Approved2018
Funding: COLLEGE /
DEPT ALLOC
7BRICKETT, ALEXANDER J
Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative3‐ IN CONSTRUCTION CP
CAPITAL PROJECT 5/28/2020 GMP 3‐ Phase I contract executed. Steel erection completed. Dtailing in progress. Exterior utility
work in progress. Mechanical, electrical and plumbing work in Spaulding basement, Rudman basement, and
Parsons basement underway.
Design Firm: Ellenzweig Contractor: Skanska USA Building
2016‐0278
Year Approved2016
Funding: SARRC
ALLOC
Spaulding Hall ‐ Utility and Infrastructure3‐ IN CONSTRUCTION FCR
5/28/2020 ‐ Please see Project #2016‐0278 for updates.
Design Firm: Contractor:
2020‐0246
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Campus Wayfinding ‐ Phase 33.1‐ SUBSTANTIAL COMPLETION SI
5/28/2020 ‐ . Additional items to be added to scope pending funding availability. 101 Sign Repair Design in
progress.
Design Firm: Contractor:
2016‐0156
Year Approved2019
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Morse Hall ‐ Third Floor Tepid Water Loop3.1‐ SUBSTANTIAL COMPLETION RR
5/28/2020 ‐ Final inspection to be completed with installation of connected eyewash station.
Design Firm: Contractor: GSPH
2017‐0004
Year Approved2017
Funding: DMA
Whittemore Center ‐ Arena ‐ Dehumidification System3.1‐ SUBSTANTIAL COMPLETION FCR
5/28/2020 ‐ New unit has been installed. Commissioning to wrap up fall 2020.
Design Firm: Harriman Contractor: Careno Construction
2017‐0308
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Parsons Hall ‐ Processed Chilled Water System Replacement3.1‐ SUBSTANTIAL COMPLETION RR
5/28/2020 ‐ Water berm installed. Controls programming for auto‐refill in progress.
Design Firm: Harriman Contractor: Northern Peabody
2018‐0048
Year Approved2019
Funding: DMA
Friday, May 29, 2020 Page 2 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Stoke Hall ‐ First Floor Renovation/Paul College Program3.1‐ SUBSTANTIAL COMPLETION FCR
5/28/2020 ‐ Main Door Replaced. Punchlist in progress.
Design Firm: Office Interiors Contractor: Milestone
2018‐0225
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
19GEUTHER, MARK E
Field House ‐ Women’s Team and General Locker Rooms – Design‐Only1.1‐ PLAN/EST SI
05‐28‐2020: Project suspended effective 3‐23‐2020 due to COVID‐19
Design Firm: Harriman Contractor: TBD
2019‐0163
Year Approved
Funding: SARRC
ALLOC
PROJECT SUSPENDED
10 West Edge Drive ‐ Roof and HVAC Replacement1.1‐ PLAN/EST RR
05‐28‐2020: Project suspended on 03‐23‐2020 due to COVID‐19.
Design Firm: Petersen Eng./Hoyle‐Tanner Contractor: TBD
2019‐0260
Year Approved
Funding: DMA PROJECT SUSPENDED
Whittemore Center ‐ Arena ‐ Ice and Arena Renovations1.1‐ PLAN/EST FCR
05‐28‐2020: Effective 3‐23‐2020 Project on hold due to Financial consideration related to the COVID‐19
pandemic. It is anticipated that the project will move forward in April of 2021.
Design Firm: RFS Engineering Contractor: PC Construction
2020‐0001
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Field House ‐ Replacing office doors1.1‐ PLAN/EST FCR
05‐28‐2020: Project suspended on 3‐23‐2020 due to COVID‐19
Design Firm: N/A Contractor: Charters Brothers
2020‐0052
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Utility Distribution ‐ Thermal Energy Storage Tank Feasibility Study1.1‐ PLAN/EST FCR
05‐28‐2020: Consultant close to publishing study report.
Design Firm: H.F. Lenz Company Contractor: TBD
2020‐0159
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Field House ‐ Volleyball Locker Room Renovation1.1‐ PLAN/EST FCR
05‐28‐2020: Project suspended effective 3‐23‐2020 due to COVID‐19
Design Firm: Contractor: TBD
2020‐0236
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Child Study & Development Center ‐ Decks1.1‐ PLAN/EST FCR
05‐28‐2020: Will follow up with client
Design Firm: Contractor: TBD
2020‐0250
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 3 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Field House ‐ Glass Wall, Outdoor Deck/Roof and Door Replacement Design Only2‐ IN DESIGN RR
05‐28‐2020: Meet with Design team on site. Design underway.
Design Firm: LaVallee Brensinger Contractor: TBD
2013‐1044
Year Approved2021
Funding: DMA
Child Study & Development Center ‐ Playground Repairs2‐ IN DESIGN FCR
05‐28‐2020: Pricing is over budget. Working thru prioritizing playground features
Design Firm: Ironwood Contractor: T&S Construction
2020‐0173
Year Approved2020
Funding:
Field House ‐ Pool Chemical Storage ‐ Design Only2‐ IN DESIGN RR
05‐28‐2020: Design is continuing.
Design Firm: Weston & Sampson Contractor: TBD
2020‐0181
Year Approved2020
Funding: INST RR
Water Treatment Plant ‐ New Construction3‐ IN CONSTRUCTION SI
05‐28‐2020: FFE Installation complete. Site work and C of O corrections on going.
Design Firm: Woodard & Curran Contractor: Waterline Industries
2008‐0038
Year Approved2014
Funding: SARRC
ALLOC
Field House ‐ 1st Floor AC Installation3‐ IN CONSTRUCTION SI
05‐28‐2020: Project will start back up mid‐June. Athletic flooring on order.
Design Firm: Harriman Contractor: Charters Brothers
2011‐0653
Year Approved2019
Funding: SARRC
ALLOC
Kendall Hall ‐ 3rd Floor Repurposing3‐ IN CONSTRUCTION SI
05‐28‐2020: Finishes, balancing, and final inspections on going. Anticipate the project to be substantially
complete mid‐June. FFE on order, early August installation anticipated.
Design Firm: Manypenny Murphy Contractor: Charters Brothers
2019‐0158
Year Approved2019
Funding: SARRC
ALLOC
Kendall Hall ‐ 4th Floor Repurposing3‐ IN CONSTRUCTION SI
05‐28‐2020: See 2019‐0158
Design Firm: Manypenny Murphy Contractor: Charters Brothers
2019‐0161
Year Approved2019
Funding: SARRC
ALLOC
Telecommunications Center ‐ Addition and Renovation3‐ IN CONSTRUCTION FCR
05‐28‐2020: Siding panels and roofing substantially complete. Topping slab scheduled for 5‐29‐2020. curtain
wall installation scheduled for late June.
Design Firm: Oak Point Contractor: Charters Brothers
2019‐0292
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 4 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Outdoor Facility ‐ New Soccer ‐ Lacrosse Field3.1‐ SUBSTANTIAL COMPLETION FCR
05‐28‐2020: Project is substantially complete. Waiting on close out documents
Design Firm: Tighe & Bond Contractor: R.A.D. Sports
2017‐0285
Year Approved2018
Funding: COLLEGE /
DEPT ALLOC
Campus ‐ South Drive ‐ Temporary Connection to Colovos Road3.1‐ SUBSTANTIAL COMPLETION SI
05‐28‐2020: Substantially Complete. Need loops cut in for gate
Design Firm: Tighe & Bond Contractor: R.A.D. Sports
2018‐0267
Year Approved2019
Funding: SARRC
ALLOC
Field House ‐ Football Locker Room Renovation – Phase II3.1‐ SUBSTANTIAL COMPLETION FCR
05‐28‐2020: Waiting on close out documents
Design Firm: Manypenny Murphy Contractor: Vantage Builders
2019‐0102
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Field House ‐ UV Filter Replacement3.1‐ SUBSTANTIAL COMPLETION RR
05‐28‐2020: Waiting on close out documents.
Design Firm: Weston & Sampson Contractor: Charters Brothers
2019‐0306
Year Approved2019
Funding: DMA
16HEISNER, MICHELE
Nesmith Hall ‐ Life Safety Review1.1‐ PLAN/EST RR
05/27/20 ‐ Report received on 04/15/20. Next steps to be determined.
Design Firm: Contractor:
2019‐0251
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Chase Ocean Engineering ‐ High Bay Lighting Replacement1.1‐ PLAN/EST FCR
05/27/20 ‐ Project suspended 3/23/20 due to Covid‐19. Schedule TBD.
Design Firm: Contractor:
2020‐0077
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Parsons Hall ‐ Convert room to 70‐seat TEAL Classroom1.1‐ PLAN/EST FCR
05/27/20‐ Project suspended 3/23/20 due to Covid‐19. Schedule TBD.
Design Firm: Contractor:
2020‐0171
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Putnam Hall ‐ Spaulding Hall Swing Space1.1‐ PLAN/EST SI
05/27/20 ‐ Space in Putnam Hall temporarily utilized for ʹbunk spaceʹ to support potential use of Hamel Rec
as Covid 19 related overflow. Planning continues for move logistics of collections.
Design Firm: Contractor:
2020‐0204
Year Approved
Funding:
Friday, May 29, 2020 Page 5 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
HSI CHHS Modular Building1.1‐ PLAN/EST FCR
05/27/20‐ RFQ anticipated to be issued first week of June. RFP for design/build services to follow. Continued
discussion on modular construction logistics.
Design Firm: Contractor:
2020‐0231
Year Approved2020
Funding:
Hewitt Hall ‐ Rm G02 Sound Proof1.1‐ PLAN/EST FCR
05/27/20 ‐ Project suspended on 3/23 due to Covid‐19. Schedule TBD.
Design Firm: Contractor:
2020‐0243
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Spaulding Hall ‐ Move Coordination and Support1.1‐ PLAN/EST FCR
05/27/20 ‐Project is part of Spaulding and in support of swing space and move coordination. In planning
Design Firm: Contractor:
2020‐0249
Year Approved
Funding:
James Hall ‐ Suite 364 Fire Alarm Strobes1.1‐ PLAN/EST FCR
05/27/20 ‐ Fire Alarm strobes required in auxiliary cleanroom lab. Work to be performed along with 2020‐
0252 project.
Design Firm: Contractor:
2020‐0251
Year Approved
Funding: COLLEGE /
DEPT ALLOC
James Hall ‐ Suite 364 Lab Repairs1.1‐ PLAN/EST FCR
05/27/20‐ Details discussed with Kevan Carpenter. More information gathered from Lab users re: sink and
eyewash location.
Design Firm: Contractor:
2020‐0252
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Campus ‐ USNH Zoom Capable Classrooms1.1‐ PLAN/EST FCR
05/27/20 ‐ First two phases of rooms identified. Walked through with Academic Technology; permitting
process underway. Yates Electrical performing work.
Design Firm: Contractor: Yates Electrical
2020‐0274
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Hubbard Hall ‐ Bedroom Doors1.1‐ PLAN/EST FCR
05/27/20 ‐ Cost estimates finalized as of 05/27; to be forwarded to Housing for review and consideration.
Design Firm: Contractor:
2020‐0278
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Woodside Apts Community Building ‐ Air Handler Replacement2‐ IN DESIGN FCR
05/27/20 Project Suspended due to the COVID‐19
Design Firm: Petersen Engineering Contractor:
2019‐0307
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Friday, May 29, 2020 Page 6 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Morse Hall ‐ Rm 419 Adding New Equipment2‐ IN DESIGN FCR
05/27/20 ‐ 100% construction drawings to be issued on 05/29.
Design Firm: SMRT Contractor:
2020‐0190
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Congreve Hall ‐ Bathroom Retrofit2.5‐ IN PROCUREMENT FCR
05/27/20 Project Suspended due to the COVID‐19
Design Firm: SMRT Contractor:
2020‐0167
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
McLaughlin Hall ‐ Abatement and Carpeting2.5‐ IN PROCUREMENT FCR
05/27/20 ‐ suspended 3/23/20 Bids were received on 4/3/20. Procurement notified bidders that award
determination was postponed due to Covid‐19. Project suspended due to Covid‐19. Schedule TBD.
Design Firm: Placework Contractor:
2020‐0179
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
James Hall ‐ Rm 185 Autoclave Replacement3‐ IN CONSTRUCTION RR
05/27/20 ‐ Testing of autoclave to occur in next two weeks.
Design Firm: Contractor:
2017‐0315
Year Approved2018
Funding: DMA
29HENRY, PAUL A
Health & Wellness ‐ COVID‐19 Testing Instrumentation1‐ ASSIGNED FCR
Design Firm: Contractor:
2020‐0281
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Huddleston Hall ‐ Creation of Offices within Carsey School1.1‐ PLAN/EST FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
briniging entire project up to DD level to include MEP, deliverables are scheduled for August 2020
Design Firm: Harriman Contractor:
2017‐0402
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Stoke Hall ‐ Gas Code Violations1.1‐ PLAN/EST FCR
5‐28‐20 Laundry room fairly straight forward with a combinded tempered MUA system, lookeing further at
the generator room, trying to verify date of installaiong to apply the correct year code.
Design Firm: Contractor:
2020‐0012
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 7 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Paul Creative Arts Center ‐ Johnson Theatre Renewal ‐ Design Only1.1‐ PLAN/EST RR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Working with Harriman for a design Proposal
Design Firm: Contractor:
2020‐0165
Year Approved2021
Funding: DMA PROJECT SUSPENDED
Huddleston Hall ‐ Fire Code Assessment and Life Safety Plan2‐ IN DESIGN RR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
bringing entire project up to DD level to include MEP, deliverables are scheduled for August 2020
Harriman has provided the Ballroom Occupancy Calcs to the SFMO this task is closed.
Design Firm: SFC Engineering Partnership Contractor:
2012‐0841
Year Approved2019
Funding: DMA PROJECT SUSPENDED
South Drive ‐ Design Advancement2‐ IN DESIGN SI
5‐28‐20 looking at moving the road to the existging Water Works Road location. Working on concept designs
with Campus Plannign and Tighe & Bond
Design Firm: Tighe & Bond Contractor:
2013‐1115
Year Approved2013
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Huddleston Hall ‐ Design of Egress Modifications2‐ IN DESIGN RR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Bringing design up to DD, to included Roof, and Mechanical Systems. DD to be complete by end of summer
tbd
work on CDʹs to include selecting a CM for estimating and preconstruction pre site investigation of system
routes and obstructions. Construction tentative schedule starting phases 2022‐2023.
Design Firm: Harriman Contractor: Harriman
2013‐1155
Year Approved2017
Funding: DMA PROJECT SUSPENDED
Paul Creative Arts Center ‐ Sprinkler Installation ‐ Design Only2‐ IN DESIGN RR
5‐28‐20 Issuing PO to Harriman to start desiign
Design Firm: Contractor:
2016‐0032
Year Approved2021
Funding: DMA
Huddleston Hall ‐ Roof Replacement Design Only2‐ IN DESIGN RR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Bringing roof design up to DD by August 2020
Design Firm: ARM Contractor: Harriman
2016‐0165
Year Approved2017
Funding: DMA PROJECT SUSPENDED
Friday, May 29, 2020 Page 8 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Philbrook Hall ‐ Steam Study and Investigation2‐ IN DESIGN RR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Waiting for final Report, working with RFS & EF to install the boiler.
RFS provided three (3) options for steam study. UNH has decided to proceed with using the steam boiler at
Philbrook for hot water make up, this will allow the local steam boiler to operate between August ‐ May with
continuation operation. During Summer when Philbrook is not open the boiler will be put in dry layup with
service assistance from Blake Engineering. Intend to have local boiler online January 2019.
Design Firm: RFS Contractor: Eckhardt Johnson
2018‐0162
Year Approved2019
Funding: DMA
Utility Distribution ‐ Lee Circle Water Line Extension2‐ IN DESIGN FCR
5‐28‐20 Project to continue‐ did not appear on original list‐ Town Money
Design is at DD, Project is +‐ 3 million over budget, working on Easements, Construction summer tbd
Design Firm: Underwood Eng Contractor: TBD
2018‐0256
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Paul Creative Arts Center ‐ Fire Alarm Design Only2‐ IN DESIGN RR
5‐28‐20 Issuing PO to Harriman for Design
Design Firm: TBD Contractor: TBD
2019‐0055
Year Approved2020
Funding: DMA
Paul Creative Arts Center ‐ Building Life Safety Report Update2‐ IN DESIGN RR
5‐28‐20 Have funding for design FY 2020
Addendum to Life Safety plan to be reviewed and approved with the SFMO.
Design Firm: Contractor:
2019‐0241
Year Approved2019
Funding: DMA
Concord ‐ UNH School of Law ‐ Student Services Consolidation2‐ IN DESIGN FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
UNH Law& HL Turner wrapping up design, DBB, construction summer tbd
Design Firm: CP Contractor:
2019‐0277
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Thompson Hall ‐ UNH Testing Center ‐ Phase 22‐ IN DESIGN SI
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Working on design, just had new input from Ted K. Placework are working on changes.
Design Firm: TBD Contractor: TBT
2019‐0322
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Elliott Alumni Center ‐ New Patio Stair Design Services2‐ IN DESIGN FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Funding Design PO Processed, presented budget information, waiting for direction.
Design Firm: MPM Contractor: TBD
2019‐0394
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Friday, May 29, 2020 Page 9 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Morse Hall ‐ Former Clean Rm Renovation2‐ IN DESIGN SI
5‐28‐20 Space to support Spaulding swing, final program has not been identified, First steps is to clean out
the rooms, move existing freezer, and add door to corridor A375A. EOS will be primary occupant when
finished. Have fundign for Design 2021 and Construction FY2022
Design Firm: Harriman Contractor: tbd
2020‐0189
Year Approved2020
Funding: SARRC
ALLOC
Whittemore Center ‐ Arena ‐ Fire Alarm and Sound System Control Panel Repairs2‐ IN DESIGN FCR
5‐28‐20 Working with SFC to come up with a code complyant solution
Design Firm: SFC Eng. Contractor: Norris ‐ Scarponi
2020‐0229
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements2.5‐ IN PROCUREMENT FCR
5‐28‐20 Contract in signature circulation, working on budget issue with team. May have to remove scope of
work to put back in the budget box.
Design Firm: Evan Mullen Contractor: Careno Const.
2017‐0447
Year Approved2018
Funding: GRANT
Holloway Commons ‐ Conference Area Carpeting Replacement2.5‐ IN PROCUREMENT FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Charter Brothers Low Bidder, construction tbd
Design Firm: Harriman Contractor: TBD
2018‐0195
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Paul Creative Arts Center – ADA Improvements – Music Wing Elevator2.5‐ IN PROCUREMENT SI
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
2016 DD design to 2020 CD design. Selected Charter Brothers as CMAR. Construction tbd
Design Firm: Harriman Contractor: tbd
2018‐0273
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Campus ‐ Tennis Court Renovation2.5‐ IN PROCUREMENT FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20‐
Bids in, Low bidder JTI, Processing FCR for PO & Project Costs, Contract pulled until further notice.
Design Firm: Tighe & Bond Contractor: TBD
2019‐0139
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Elliott Alumni Center ‐ 1925 Room2.5‐ IN PROCUREMENT FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Structuretone low bidder.
Design Firm: Manny Penny Murphy Contractor: TBD
2019‐0191
Year Approved2019
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Friday, May 29, 2020 Page 10 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Philbrook Hall ‐ Bathroom and Locker Room Renovation2.5‐ IN PROCUREMENT FCR
5‐28‐20 Project Suspended due to the COVID‐19 3/23/20
Selected Charter Brothers as CMAR, Looking to start Pre‐Construction services.
Design Firm: Harriman Contractor: Charter Brothers
2020‐0162
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Hood House ‐ Minor Renovation for Career and Professional Success Center3‐ IN CONSTRUCTION SI
5‐28‐20 Starting planting today, Yates running exterior receptical for LV lights.
Design Firm: Woodburn Landscaping Contractor: Belko Landscaping
2016‐0409
Year Approved2016
Funding: SARRC
ALLOC
Elliott Alumni Center ‐ Building HVAC Modifications and Improvements3‐ IN CONSTRUCTION RR
5‐28‐20 Structuretone starting today to work on punch list and code compliant issues.
Design Firm: HARRIMAN Contractor: StructureTone
2019‐0048
Year Approved2020
Funding: DMA
Horton Social Science Center ‐ G04 Auditorium – Air Conditioning3.1‐ SUBSTANTIAL COMPLETION SI
5‐28‐20 Chasing down some balancing issues ‐waiting to return to campus
Design Firm: Harriman Contractor: Structuretone
2010‐0411
Year Approved2019
Funding: SARRC
ALLOC
New England Center ‐ Boiler Replacement and BAS Controls3.1‐ SUBSTANTIAL COMPLETION RR
5‐28‐20 Boilers sequencing seems to be working after Factory rep spent the day on site, working on sump
pumps, illicit discharge into sanitaryre‐piping to exterior catch basin on the North side of building in the
process of scheduling
System is currently heating the building
Design Firm: Harriman Contractor:
2016‐0403
Year Approved2020
Funding: DMA
Philbrook Hall ‐ Boiler Replacement3.1‐ SUBSTANTIAL COMPLETION FCR
5‐28‐20 Still having issues with condensate pumps, Installed new float switch, have had mfg. rep on site
trying to figure out the issues.
Design Firm: RFS Contractor: Eckardt & Johnson
2019‐0304
Year Approved
Funding: COLLEGE /
DEPT ALLOC
34HOUDE, DONALD A
Service Building ‐ Durham Fire Department Improvements1.1‐ PLAN/EST FCR
5‐28‐20 Project approved to move forward DFD has funding email sent to Don Houde 5/5/20 from Mike
Mason/Chief Emanuel 5‐27‐20 I have notified B.W. that project2016‐0123 must be funded before I can
proceed with this work.
Design Firm: McHenry Architecture Contractor:
2019‐0279
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 11 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Utility Distribution ‐ Morse Circle ‐ Circuit 111.1‐ PLAN/EST RR
5‐24‐20 No work here until at least after the Dual temp line installation.
Design Firm: Contractor: ICR
2020‐0019
Year Approved2021
Funding: DMA
1 Leavitt Lane ‐ Convert boiler to natural gas1.1‐ PLAN/EST FCR
5‐30‐20 Project Suspended on 3‐23‐20 ‐ Gas line is in place.
Design Firm: OPA Contractor:
2020‐0055
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
6 Leavitt Lane ‐ New Gas Line and Boiler1.1‐ PLAN/EST FCR
5‐28‐20 Conversion Project Suspended 3‐23‐20 But, N.U. has had NEUCCO co install all underground gas
lines at the LL sites.
Design Firm: OPA Contractor:
2020‐0056
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
10 West Edge Drive ‐ Gas Piping1.1‐ PLAN/EST FCR
5‐28‐20 Project Suspended 3‐23‐20. Gas line is in place.
Design Firm: OPA Contractor:
2020‐0060
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Christensen Hall ‐ Relocate Electric panels1.1‐ PLAN/EST FCR
5‐28‐20 Project Suspended on 3‐23‐20.
Design Firm: Harriman Contractor:
2020‐0168
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Morse Hall ‐ Stand By Generator and Distribution ‐ Design ONLY1.1‐ PLAN/EST SI
5‐24‐2020 We are looking into all issues.I started by making contact with David Divins. I will be providing
an encumbrance for logging of the generator loads.
Design Firm: Contractor:
2020‐0214
Year Approved2020
Funding: SARRC
ALLOC
Demeritt Hall ‐ Research Lab Stand By Power Design1.1‐ PLAN/EST SI
5‐28‐20 Project Suspended on 3‐23‐20.
Design Firm: Contractor:
2020‐0215
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Utility Distribution ‐ Conant Hall Transformer Upgrade1.1‐ PLAN/EST FCR
5‐28‐2020 Excavation and start of Utility conduit installation, this week.
Design Firm: Contractor: ICR‐Yates
2020‐0225
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 12 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Morse Hall ‐ Card Access for Lenharth Data Center1.1‐ PLAN/EST FCR
5‐30‐20 Project Suspended 3‐23‐20.
Design Firm: Contractor:
2020‐0240
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Field House ‐ Indoor Pool Electrical Service Replacement2‐ IN DESIGN RR
5‐28‐20 Project Suspended on 3‐23‐20.
Design Firm: Harriman Contractor:
2012‐0824
Year Approved2021
Funding: DMA PROJECT SUSPENDED
Paul Creative Arts Center ‐ High Voltage Electrical Service Replacement2‐ IN DESIGN RR
5‐26‐20 This project to bring Electrical power to the rear of PCAC to create a newMain Electrical Service
room for the whole building. Our main objective is to be prepared to supply power to the new Elevator
project this summer.. The HV contractor has a PO.
5‐26‐20 I am prepairing to have the underground HV ductbank only installed from the Spaulding
sector cabinet to the new PCAC transformer location.
Design Firm: Harriman Contractor: ICR
2017‐0106
Year Approved2021
Funding: DMA
Combined Heat & Power Plant ‐ Steam to HW Heat Exchanger Replacements Phase
Design Only2‐ IN DESIGN RR
5‐28‐20 Project suspended on 3‐23‐20.
Design Firm: Harriman Contractor:
2019‐0063
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Combined Heat & Power Plant ‐ Generator Replacement2‐ IN DESIGN RR
5‐30‐20 Project Susprnded on 3‐23‐20.
Design Firm: Harriman Contractor:
2020‐0034
Year Approved2021
Funding: DMA PROJECT SUSPENDED
Service Building ‐ Dispatch Center Keltron System2.5‐ IN PROCUREMENT FCR
5‐28‐20 ‐ Contractors have POʹs and incumbrances. Some work has been started. I thought this was on Hold,
I am getting verification. On hold for now.
Design Firm: Contractor: Norris / UNH Telecom
2016‐0123
Year Approved2018
Funding: COLLEGE /
DEPT ALLOC
Combined Heat & Power Plant ‐ Bring the catwalk & mezzanine to code2.5‐ IN PROCUREMENT FCR
5‐30‐20 project Suspended.
Design Firm: Harriman Contractor:
2017‐0188
Year Approved2017
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Utility Distribution ‐ Spaulding Pedestrian Bridge Circuit 11 Conduit Replacement2.5‐ IN PROCUREMENT RR
5‐23‐20 ICR has a PO and are planning this work in conjunction with Spaulding/Rudman shutdown . Start
for this project is now, as soon as we coordinate with the Spaulding project.
Design Firm: Contractor: IC Reed and Sons
2019‐0123
Year Approved2020
Funding: DMA
Friday, May 29, 2020 Page 13 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Dimond Library ‐ Elevator Card Access2.5‐ IN PROCUREMENT FCR
5‐30‐20 Project Suspended.
Design Firm: Housing Contractor: Stanley , Yates, Housing
2019‐0270
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Keener Dairy Research Building ‐ Rm 127A Grinding Room Safety Improvements2.5‐ IN PROCUREMENT FCR
5‐28‐20 Project Suspended on 3‐23‐20.
Design Firm: McHenry Contractor:
2019‐0318
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Christensen Hall ‐ Lighting improvements2.5‐ IN PROCUREMENT FCR
5‐28‐20 Project Suspended on 3‐23‐20.
Design Firm: Contractor: Scarponi
2020‐0039
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Utility Distribution ‐ Circuit 11‐12 Tie Cable Upgrade2.5‐ IN PROCUREMENT FCR
5‐24‐20 . Upgrade the conductors under the RR tracks that connect cirt 12 in A lor to cirt 11 by Woodside
appts. This Summer.Contractor has PO. Waiting on the cable.
Design Firm: Contractor: I C Reed and Sons Inc.
2020‐0185
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Presidentʹs House ‐ Security Cameras2.5‐ IN PROCUREMENT FCR
5‐30‐20 Project Suspended on 3‐23‐20
Design Firm: Contractor: Yates, Burns, Telecom.
2020‐0211
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
MacFarlane Greenhouse ‐ Renovation/Improvements3‐ IN CONSTRUCTION FCR
5‐24‐20 This project is in construction. Project meetings will be on Tuesdays from 8:30AM to 10;AM.
Footings and foundation in place. Vestibule Firewall in construction. .New greenhouse going up.
Design Firm: SMRT Contractor: Careno
2019‐0001
Year Approved2018
Funding: COLLEGE /
DEPT ALLOC
Campus Lot‐F ‐ Pay & Display Unit3‐ IN CONSTRUCTION FCR
5‐24‐20 Working with T&S and Dirk Timmons. Some work is done, Waiting for material.and will finish B‐
lot in June.
Design Firm: Contractor: T&S
2019‐0358
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Ritzman Laboratory ‐ Electrical Work to Circuit 123‐ IN CONSTRUCTION FCR
5‐24‐20 This project is to demo cirt 1 and to tie Ritzman lab to circuit #12., in the Summer. Contractor has PO.
Coordinating.
Design Firm: Contractor: I C Reed & Sons inc.
2020‐0184
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 14 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Utility Distribution ‐ Lot A circuit 8 to circuit Tie3‐ IN CONSTRUCTION FCR
5‐24‐20 . Tap into circuit #8 at A Lot and connect all the way to Woodside and remove the fyying sub.
Summer 2020 work. Pulling new cables in on Monday.
Design Firm: Contractor: I C Reed
2020‐0186
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Utility Distribution ‐ Gables Way to Lot‐A 5KV Underground Extension3‐ IN CONSTRUCTION FCR
5‐28‐20 This work may be completed next week.
Design Firm: Contractor: I C Reed ‐
2020‐0195
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Utility Distribution ‐ Eversource Transmission Line3.1‐ SUBSTANTIAL COMPLETION FCR
5‐25‐20 The installation of undergound ductbanks is complete and the areas disturbed have been restored.
Eversource returning to install underground cable has been installed. . We are working with Eversource on a
planting plan for 3 areas, Gregg, F.H. and Gables to be done next Spring. 2020. Completion of bumper
installation in A‐Lot during Spring break. Eversource has picked up material by Gregg lot.
Design Firm: Contractor:
2016‐0277
Year Approved2019
Funding: SARRC
ALLOC
Utility Distribution ‐ Sub Station 1 ‐ Transformer and Circuit Realignment3.1‐ SUBSTANTIAL COMPLETION FCR
5‐23‐20 This work substantially complete on punchlist.
Design Firm: Contractor: ICR
2019‐0243
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Kingsbury Hall ‐ Installation of Card Access and Wireless Door Openers3.1‐ SUBSTANTIAL COMPLETION FCR
5‐23‐20 This project is substantially complete. Waiting on Housing.
Design Firm: UNH Housing Contractor: Yates & NE door.
2019‐0353
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Combined Heat & Power Plant ‐ UNH CoGen Card Access3.1‐ SUBSTANTIAL COMPLETION FCR
5‐24‐20 New,Scope with the same PN. Installing low voltage lines to bring communication to the control
center from 23 points. Contractor has funding. Contractor intalling pathways complete. And cable
installation was ompleted before the shutdown.
Design Firm: Contractor: Yates Electric.
2019‐0391
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
6 Leavitt Lane ‐ interior Panel board wiring3.1‐ SUBSTANTIAL COMPLETION FCR
5‐28‐20 Project substantially complete. Generator to be installed.
Design Firm: Contractor: Yates Electric Service
2020‐0031
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Friday, May 29, 2020 Page 15 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Utility Distribution ‐ Install Underground Duct Bank in Lot‐A3.1‐ SUBSTANTIAL COMPLETION FCR
5‐24‐20 This work is substantially complete. On Punchlist.
Design Firm: Contractor: Yates Electric.
2020‐0194
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
1 Leavitt Lane ‐ Electrical Distribution Circuits In Data Center3.1‐ SUBSTANTIAL COMPLETION FCR
5‐30‐20 This work was completed before suspension. The contractor is looking for direct payment from the
department.
Design Firm: Contractor: Yates
2020‐0239
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
20MANCINI, MATTHEW E
Rudman Hall ‐ Vivarium Upgrades ‐ Phase II1.1‐ PLAN/EST SI
5/28/2020: Design to commence soon. Previously, this project was incorrectly associated with Phase I
Vivarium Project.
Design Firm: Contractor:
2019‐0141
Year Approved2019
Funding: SARRC
ALLOC
Barton Hall ‐ 2nd Floor Reno for Diagnostic Labs1.1‐ PLAN/EST SI
5/28/2020: Programming meetings with stakeholders have begun. Design to begin subsequent to progress of
2020‐0092 Cole Hall Structural Space Improvements.
Design Firm: H.L. Turner Group Contractor:
2020‐0091
Year Approved2020
Funding: SARRC
ALLOC
Dimond Library ‐ Interior Heating Distribution ‐ Design Only2‐ IN DESIGN RR
5/28/2020: BIM model in development. Schematic Design Issue expected mid‐June.
Design Firm: Harriman Contractor:
2010‐0281
Year Approved2021
Funding: DMA
Paul College ‐ HVAC and Control Modifications from Original Construction2‐ IN DESIGN FCR
5/28/2020: Project suspended.
Design Firm: Contractor: TBD
2016‐0295
Year Approved2016
Funding: SARRC
ALLOC
Dimond Library ‐ Comprehensive Planning Effort2‐ IN DESIGN SI
5/28/2020: Assisting Campus Planning. To be coordinated with heating hot water system renovation project.
Design Firm: Perry Dean Rogers /
Harriman
Contractor:
2019‐0160
Year Approved2020
Funding: SARRC
ALLOC
Cole Hall ‐ Instructional Space Improvements2‐ IN DESIGN SI
5/28/2020: Final CDs under way. Architectrual portion of wrok is expected to proceed with coompletion by
September ʹ20. HVAC scope will be defered.
Design Firm: John L Turner Contractor:
2020‐0092
Year Approved2020
Funding: SARRC
ALLOC
Friday, May 29, 2020 Page 16 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Rudman Hall ‐ AHU‐3 Replacement2‐ IN DESIGN RR
5/28/2020: Design nearly complete for replacement of supply AHU‐3. Project to continue.
Design Firm: SMRT Contractor:
2020‐0128
Year Approved2021
Funding: DMA
Stoke Hall ‐ Conceptual Design of Lobby & Vending Machine Relocation2‐ IN DESIGN FCR
5/28/2020: Project has beem suspended effective 3/23/20.
Design Firm: Placework Contractor:
2020‐0192
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Elliott Alumni Center ‐ Renovate Restrooms 109 & 1112.5‐ IN PROCUREMENT FCR
5/28/2020: Project has beem suspended effective 3/23/20.
Design Firm: Placeworks Contractor: Milestone
2019‐0386
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Christensen Hall ‐ A Tower Roof Replacement2.5‐ IN PROCUREMENT FCR
5/28/2020: Bid withdrawn. Project to be re‐bid with planned construction for Summer ʹ21.
Design Firm: Manypenny Murphy ‐ ARM Contractor: Viking Roofing
2020‐0036
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Williamson Hall ‐ A Tower Roof Replacement2.5‐ IN PROCUREMENT FCR
5/28/2020: Bid withdrawn. Project to be re‐bid with planned construction for Summer ʹ21.
Design Firm: Placework ‐ ARM Contractor: Viking Roofing
2020‐0037
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Rudman Hall ‐ Laboratory Fume Hood Control System Replacement3‐ IN CONSTRUCTION RR
5/28/2020: Project to continue.
Design Firm: SMRT Contractor: StructureTone
2010‐0479
Year Approved2017
Funding: DMA
Rudman Hall ‐ Conversion to DDC Controls3‐ IN CONSTRUCTION RR
5/28/2020: Reference ID 2010‐0479 for updates. Project to continue.
Design Firm: SMRT Contractor: StructureTone
2015‐2336
Year Approved2018
Funding: DMA
Rudman Hall ‐ Fire Alarm Replacement3‐ IN CONSTRUCTION RR
5/28/2020: Reference ID 2010‐0479 for updates. Project to continue.
Design Firm: SFC / SMRT Contractor: StructureTone
2015‐2352
Year Approved2016
Funding: DMA
Friday, May 29, 2020 Page 17 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Rudman Hall ‐ Retro‐Commissioning of ARO HVAC System3‐ IN CONSTRUCTION FCR
5/28/2020: Reference ID 2010‐0479 for updates. Project to continue.
Design Firm: SMRT Contractor: Structuretone
2019‐0305
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Dimond Library ‐ Rm 421 Minor Renovation3‐ IN CONSTRUCTION FCR
5/28/2020: Phase II of project to resume 6/8/20. Two‐week duration expected for architecural renovations. AV
upgrades to follow.
Design Firm: Contractor: Malthouse Construction
2019‐0357
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Rudman Hall ‐ AHU‐3 ‐ Make Ready Repairs and Modifications3‐ IN CONSTRUCTION RR
Emergency Repair 5/28/2020: Reference ID 2020‐0128 for updates. Work remains to replace isolation valves and chilled water
valve. Project to continue.
Design Firm: SMRT Contractor: Grainte State Plumbing &
Heating
2020‐0015
Year Approved2020
Funding: INST RR
Stoke Hall ‐ Lounge Updates3‐ IN CONSTRUCTION FCR
5/28/2020: Design has been provided. Work to be coordinated with 2020‐0192. Project has beem suspended
effective 3/23/20.
Design Firm: Placework Contractor:
2020‐0191
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Rudman Hall ‐ AHU‐4 Condition Assessment and Repairs3.1‐ SUBSTANTIAL COMPLETION RR
5/28/2020: Project punch list.
Design Firm: SMRT Contractor: Granite State Plumbing &
Heating
2020‐0043
Year Approved2020
Funding: DMA
Thompson Hall ‐ Presidentʹs Office Painting, Furniture and Window Treatments3.1‐ SUBSTANTIAL COMPLETION FCR
5/28/2020: Project to continue.
Design Firm: Contractor: APC Services of New
England
2020‐0080
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
28PETERS, NICK E
Murkland Hall ‐ Slate Roof Repairs1.1‐ PLAN/EST RR
5/27/2020 ‐ Project suspended on 3/25 and resumed 5/1. Reached out to contractor and Asset Management to
being building requirements. Confirmed no building permit required. Contractor has material on hand, and
is working with UNH for scheduling. Project expected to begin mid‐June.
Design Firm: Contractor: Viking Roofing
2013‐1048
Year Approved2021
Funding: DMA
Friday, May 29, 2020 Page 18 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Memorial Union Building ‐ Roof Replacement Design and Planning1.1‐ PLAN/EST BAR
27 May 2020 ‐ Project suspended 1 May. Awaiting information from stakeholders before proceeding.
Design Firm: ARM Contractor:
2018‐0337
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Murkland Hall ‐ Rooftop Mechanical Catwalks1.1‐ PLAN/EST RR
27 May 2020. Project suspended on 23 March. Reaching out to customers and contractors to confirm scope.
Identified engineer consultant to reach out too.
Design Firm: Contractor: Careno
2019‐0099
Year Approved2020
Funding: DMA PROJECT SUSPENDED
FY21 Campus Envelope and Interior Painting1.1‐ PLAN/EST RR
27 May 2020: Received quote from contractor. Soliciting to other contractors for additional quotes. Expect to
receive proposals back week of 25 May.
Design Firm: N/A Contractor: Milestone
2019‐0369
Year Approved2021
Funding: INST RR
Ambulance Corp Building ‐ Envelope and Interior Repairs1.1‐ PLAN/EST RR
Emergency Repair 27 May 2020: Project is to abate mold issues from building, and remove damaged finishes. No restoration
will be accomplished under this project.
Design Firm: Contractor:
2020‐0196
Year Approved2020
Funding: INST RR
Kingsbury Hall ‐ Rms N101, S145 Classroom Repairs1.1‐ PLAN/EST RR
27 May 2020 ‐ Chairs tightened 26 March. Contractor identified arms that need to be replaced, but are in
stock. Looking to perform next install once Covid Restrictions are removed. Room S145 has been put on hold
and will need to be readdressed as a separate project to replace all existing in the room.
Design Firm: N/A Contractor: K.I.
2020‐0222
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Rudman Hall ‐ Move Mass Spectrometer Wiring from 326 to 3211.1‐ PLAN/EST FCR
27 May 2020 ‐ Project suspended on 23 Mar. Awaiting further information from senior leadership.
Awaiting Identified project requirements. Mass Spectrometer must move because research team has
relocated to room 326. Heat load study on new room will need to be performed, and rebalanced to
accommodate Mass Spectrometer. Electrical requirements have been identified. Received proposal and
waiting for coronavirus to settle before continuing.
Design Firm: Contractor:
2020‐0230
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Handler Hall ‐ SERC Tile and Shower Base Repairs1.1‐ PLAN/EST FCR
27 May ‐ Project Suspended on 23 March. Customer removed and investigated behind tile and drafted
suggestions for solution. Proposal received. Discussing options with Housing.
Design Firm: N/A Contractor: Sprague Floor Covering
2020‐0233
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Friday, May 29, 2020 Page 19 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Memorial Union Building ‐ Consolidate Student Service Center1.1‐ PLAN/EST FCR
27 May 2020 ‐ Project suspended on 23 March. Awaiting further direction from senior leadership.
Met with Design team and customers to develop scope of work. Awaiting Design team proposal. Expecting
delay to receive proposal back due to Coronavirus.
Design Firm: Placework Contractor: TBD
2020‐0235
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Hewitt Hall ‐ Rm 144 Install Dutch Door1.1‐ PLAN/EST FCR
27 May 2020 ‐ Project suspended on 23 March. Performed site visit. Received proposal. Will reconnect with
contractor when project resumes.
Design Firm: Contractor:
2020‐0237
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Nesmith Hall ‐ Rm 107 Install Power and Mount for AV1.1‐ PLAN/EST FCR
27 May 2020 ‐ Project suspended on 23 March. Awaiting further direction from senior leadership.
Reached out to customer to schedule site visit. Waiting for good time to have site visit with customer. Will
try to coordinate a meeting when virus settles.
Design Firm: Contractor:
2020‐0238
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Field House ‐ Lundholm Sound System1.1‐ PLAN/EST FCR
27 May 2020 ‐ Project suspended on 23 March. Awaiting further direction from senior leadership.
Met with customer at Gymnasium. Developed project requirements. Customer recommended a person in
Academic Technologies to talk to about the Gymnasium [Andy Bruns]. Awaiting Coronavirus to settle before
proceeding.
Design Firm: Contractor:
2020‐0241
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Holloway Commons / MUB ‐ Verizon Wireless In‐Building Antenna System1.1‐ PLAN/EST FCR
27 May 2020 ‐ Met with design team on 26 May. Project has 100% CD and we are beginning the permit
process while the project is bid for contractor selection.
Design Firm: Verizon Wireless Contractor: Verizon Wireless
2020‐0267
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Wildcat Stadium ‐ Verizon Wireless Distributed Antenna Installation1.1‐ PLAN/EST FCR
27 May 2020 ‐ Met with design team on 26 May. Project has 100% CD and we are beginning the permit
process while the project is bid for contractor selection.
Design Firm: Verizon Wireless Contractor: Verizon Wireless
2020‐0268
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Whittemore Center ‐ Verizon Wireless In‐Building Cellular Antenna System1.1‐ PLAN/EST FCR
27 May 2020 ‐ Met with design team on 26 May. Project has 100% CD and we are beginning the permit
process while the project is bid for contractor selection.
Design Firm: Contractor: Verizon Wireless
2020‐0269
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 20 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Verizon Wireless Head End Building ‐ Construction1.1‐ PLAN/EST FCR
27 May 2020 ‐ Met with design team on 26 May. Project has 100% CD and we are beginning the permit
process while the project is bid for contractor selection.
Design Firm: Verizon Wireless Contractor: Verizon Wireless
2020‐0270
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Campus Wide ‐ COVID Barrier Installatoins1.1‐ PLAN/EST FCR
28 May 2020 ‐ Awaiting plans from departments for requirements.
Design Firm: Contractor:
2020‐0279
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Presidentʹs House ‐ Replace Wood Trim1.1‐ PLAN/EST FCR
28 May 2020 ‐ Site walk at 8am on 1 June.
Design Firm: Contractor:
2020‐0280
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Memorial Union Building ‐ Granite State Room Chiller Replacement2‐ IN DESIGN FCR
27 May 2020 ‐ Project Suspended due to the COVID‐19 on 3/23/20. Awaiting further direction from senior
leadership.
Design Firm: SMRT Contractor:
2016‐0453
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Taylor Hall ‐ Flat and Shingle Roof Replacement2.5‐ IN PROCUREMENT RR
27 May 2020 ‐ NTP issued for 1 June. Building permits, equipment/material staging in place. Building will
be vacant through August.
Design Firm: ARM Contractor: Skyline
2017‐0218
Year Approved2021
Funding: DMA
New Hampshire Hall ‐ Window Replacements and Exterior Painting2.5‐ IN PROCUREMENT RR
21 May 2020 Project Suspended due to the COVID‐19 until 1 November.
Design Firm: McHenry Architecture Contractor: Careno
2018‐0306
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Demeritt Hall ‐ Rm 112 Carpet Replacement and Chair Refurbishing2.5‐ IN PROCUREMENT RR
27 May 2020 ‐ Project Suspended due to the COVID‐19 on 3/23/20.
Design Firm: Harriman Contractor:
2019‐0384
Year Approved
Funding: DMA PROJECT SUSPENDED
Kingsbury Hall ‐ Career Services Design2.5‐ IN PROCUREMENT FCR
27 May 2020 ‐ Project design complete ‐ submitted to procurement to initiate bid process. Completing bid
draft on 22 May. Meeting with stakehold to discuss laydown locations. Awaiting ACM sampling results
before completing Draft 2 of bid documents.
Design Firm: Placework Contractor:
2020‐0216
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 21 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Morse Hall ‐ Emergency Eyewash Installation3‐ IN CONSTRUCTION FCR
27 May 2020 ‐ Construction completed. Final inspection scheduled for 4 June 2020.
Design Firm: N/A Contractor: Milestone Eng & Const, Inc
2020‐0150
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Campus ‐ Facilities Sit‐Stand Desks3.1‐ SUBSTANTIAL COMPLETION FCR
21 May 2020 ‐ Desks installed. Performing closeout documents. Warranty received, and will submit to
records team for completion. Another chair is being procured for Jeff Prince. Awaiting Rhonda for when
chair can be purchased.
Design Firm: N/A Contractor: Summit Ergonomics
2020‐0161
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Morse Hall ‐ Humidification Tank System Replacement3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 27 May 2020 ‐ Project completed. Boiler issues resolved through Operations. Beginning project closeout.
Design Firm: Petersen Engineering Contractor: Granite State Plumbing and
Heating
2020‐0221
Year Approved2020
Funding: INST RR
Christensen Hall ‐ MetroPCS ‐ T‐Mobile Antenna Upgrade3.1‐ SUBSTANTIAL COMPLETION FCR
27 May 2020 ‐ Work complete. Awaiting closeout documents.
Design Firm: NB+C Contractor: NB+C
2020‐0228
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Pettee Hall ‐ Ceiling Light Fixture Repairs3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 27 May 2020 ‐ Construction complete. Beginning closeout process.
Design Firm: N/A Contractor: Scarponi
2021‐0003
Year Approved2020
Funding: INST RR
33RINES, DANIEL M
Service Building ‐ Fire Department Sprinkler Installation1.1‐ PLAN/EST RR
5/26/20 ‐ . Confriming scope changes, budget revisions, with AM, once complete PM will confirm scope with
A/E for design processes to begin. Project anticipated to be constructed in the Fall.
Design Firm: TBD Contractor:
2010‐0356
Year Approved2021
Funding: DMA
Train Station & Dairy Bar ‐ Transit Facility Improvements ‐ UNH ‐ Durham Rail
Station1.1‐ PLAN/EST SI
5‐26‐20: Project suspended 3‐23‐20
Design Firm: Contractor:
2018‐0031
Year Approved
Funding: GRANT PROJECT SUSPENDED
121 Technology Drive ‐ Covid‐19 Construction Estimate1.1‐ PLAN/EST FCR
5‐26‐20: Project is in conceptual design waiting for landlord feedback.
Design Firm: Contractor:
2020‐0248
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 22 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Jessie Doe Hall ‐ Caps on Cement Wall1.1‐ PLAN/EST FCR
5‐26‐20: Reached out to term for budget pricing for minor repairs.
Design Firm: Contractor:
2020‐0275
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Field House ‐ West Parking Lot Repaving2‐ IN DESIGN FCR
5‐26‐20: Project suspended 3‐23‐20
Design Firm: Tighe & Bond Contractor:
2018‐0297
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Holloway Commons ‐ Front Stairs2‐ IN DESIGN FCR
5‐26‐20: Project suspended 3‐23‐20
Design Firm: HL Turner Contractor:
2020‐0024
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Service Building ‐ Storm Water / Building Envelope Design and Temporary Repairs2‐ IN DESIGN RR
5‐26‐20: Project suspended 3‐23‐30
Design Firm: Hoyle Tanner Contractor:
2020‐0047
Year Approved2020
Funding: DMA PROJECT SUSPENDED
College Road ‐ Extend Sidewalk2.5‐ IN PROCUREMENT SI
5‐26‐20: project suspended 3‐23‐20
Design Firm: Weston & Sampson Contractor: Gagnon Construction
2015‐2511
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Campus ‐ Main Street South Sidewalk2.5‐ IN PROCUREMENT SI
5‐26‐20: Bids are due 5‐27. Project anticipated to kick off in June.
Design Firm: CMA Engineering Contractor:
2017‐0384
Year Approved2018
Funding: GRANT
Campus ‐ McDaniel Drive Extend Sidewalk2.5‐ IN PROCUREMENT SI
5‐26‐20: Project suspended 3‐23‐20
Design Firm: Weston & Sampson Contractor:
2019‐0074
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Handler Hall ‐ Replacement of PVI Hot Water Tanks2.5‐ IN PROCUREMENT FCR
5/26/20 ‐ project moving forward, Contract is currently routing through USNH for signatures.
Design Firm: HL Turner Contractor: NPI
2019‐0324
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 23 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Utility Distribution ‐ Tunnel Repairs and Utility Line Replacement Leaving Central
Plant ‐ Design Only2.5‐ IN PROCUREMENT RR
5‐26‐20: Design consulatant awarded to RMF. Contract is being reviewed by vendor.
Design Firm: Contractor:
2020‐0004
Year Approved2021
Funding: DMA
Campus ‐ STR0079 Strafford Ave ‐ NEC Stair Reconstruction2.5‐ IN PROCUREMENT RR
5‐26‐20: Project suspended 3‐23‐20
Design Firm: Tighe and Bond Contractor:
2020‐0009
Year Approved
Funding: DMA PROJECT SUSPENDED
McLaughlin Hall ‐ Repair exterior stair2.5‐ IN PROCUREMENT FCR
5‐26‐20: Project suspended 4‐30‐20 by BA
Design Firm: Hoyle Tanner Contractor: JTI Site Development
2020‐0040
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Woodside apts Community Building ‐ Drainage Improvement2.5‐ IN PROCUREMENT FCR
5‐26‐20: project suspended 3‐23‐30
Design Firm: Tighe and Bond Contractor: T&S Construction
2020‐0188
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Memorial Union Building ‐ Install New Hillside Stair on West Side ‐ Design Only3‐ IN CONSTRUCTION SI
5‐26‐20: Project suspended 3‐20‐20
Design Firm: Contractor: Piscataqua Landscaping
2008‐0120
Year Approved2019
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Utility Distribution ‐ Edgewood Water Tank ‐ Decomissioning3‐ IN CONSTRUCTION SI
5/26/20 ‐ Project anticipated to kick off early June. Tank cleaning underway.
Design Firm: Contractor: Charter Brothers
2010‐0729
Year Approved2018
Funding: SARRC
ALLOC
Pettee Hall ‐ Drainage Repairs and Stair Demo3‐ IN CONSTRUCTION RR
5‐26‐20: Project has been procured under the term agreement.
Design Firm: Hoyle Tanner Contractor: JTI Site Development
2017‐0146
Year Approved2021
Funding: DMA
FY21 Sidewalk and Walkway Repairs3‐ IN CONSTRUCTION RR
5‐26‐20: List has been identified, PM ready to move forward with term contractors
Design Firm: N/A Contractor: Top Quality Construction
2017‐0275
Year Approved2021
Funding: INST RR
Friday, May 29, 2020 Page 24 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Utility Distribution ‐ Piping Replacements from Heating Vault HVT086 to Handler
Hall3‐ IN CONSTRUCTION RR
5‐26‐20: Project is underway, significant delays due to engineering and piping delivery. Steam shut down
may need to be extended in order to complete.
Design Firm: Harriman Contractor: Anderson Welding
2018‐0362
Year Approved2021
Funding: DMA
Woodman Horticultural Barn ‐ Foundation Repair3‐ IN CONSTRUCTION FCR
5‐26‐20: . Veneer work is underway.
Design Firm: Hoyle Tanner Contractor: Careno Construction
2019‐0336
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
FY21 Site Stair Repairs3‐ IN CONSTRUCTION RR
5‐26‐20; list is being priced out via term contracts.
Design Firm: N/A Contractor: Top Quality Construction
2019‐0368
Year Approved2021
Funding: INST RR
FY21 Major Road Repairs ‐ Under Town of Durham Contract3‐ IN CONSTRUCTION RR
5‐26‐20: Bids have come back via the Towns resurfacing bid. Work to be reviewed with the town and low
bidder, and scheduled for late summer.
Design Firm: Contractor:
2019‐0371
Year Approved2021
Funding: INST RR
Field House ‐ Indoor Pool Concrete Repairs3‐ IN CONSTRUCTION RR
5‐26‐20: Pre Con Meeting completed. Construction to begin week of 6‐8 with 5‐6 week duration anticipated.
Design Firm: Hoyle Tanner Contractor: Structural Preservation
Systems
2020‐0129
Year Approved2021
Funding: DMA
Putnam Hall ‐ EMS ‐ Covid‐19 Preparations3‐ IN CONSTRUCTION FCR
5‐26‐20: project is substancially complete. PM looking into Air conditioning for occupants, vehicle heat/AC
units have also been requested.
Design Firm: Contractor:
2020‐0244
Year Approved
Funding: COLLEGE /
DEPT ALLOC
Hamel Recreation Center ‐ Covid‐19 Surge Facility3‐ IN CONSTRUCTION FCR
5‐26‐20: Returned the generator, UNH to use in house 230KW generator for the time being. Fence and other
items still on Rent.
Design Firm: Contractor:
2020‐0245
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Haaland Hall – PVI Tank Replacement3‐ IN CONSTRUCTION FCR
5‐26‐20: Project initiated, ETB confirmed, tank is ordered, and term contractor PO is complete.
Design Firm: N/A Contractor: United Mechanical
2020‐0253
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 25 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Campus ‐ Main Street Paving3‐ IN CONSTRUCTION FCR
5‐26‐20: Project is Via the TOD contract with Continental. Working on budget and scope currently.
Design Firm: Contractor:
2020‐0276
Year Approved
Funding:
Utility Distribution ‐ South Drive STSL ‐ CRL Piping Replacements HVT086 to
Handler Hall Design Only3.1‐ SUBSTANTIAL COMPLETION RR
5‐26‐20: This deisgn only project will be tracked with #2018‐0362
Design Firm: Harriman Associates Contractor:
2016‐0177
Year Approved2020
Funding: INST RR
Forest Park ‐ Decommissioning and Demolition3.1‐ SUBSTANTIAL COMPLETION FCR
5‐26‐20:
Project is complete.
Design Firm: Harriman Contractor: AQE
2019‐0053
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Hewitt Hall ‐ Duel Temperature Mechanical Tie‐In3.1‐ SUBSTANTIAL COMPLETION RR
5‐26‐20: Project to be commissioned week of 6‐1‐20. Final inspections pending after punchlist.
Design Firm: Harriman Contractor: Anderson Welding
2019‐0338
Year Approved2020
Funding: DMA
Field House ‐ G00CRB Concrete Spalling Investigation and Repair3.1‐ SUBSTANTIAL COMPLETION RR
5‐26‐20: Project being tracked under the construction id # 2020‐0129
Design Firm: Hoyle Tanner Contractor:
2019‐0355
Year Approved2020
Funding: DMA
Zais Hall ‐ Water Infiltration Design and Investigation3.1‐ SUBSTANTIAL COMPLETION RR
5‐26‐20: Project design is complete. Project was not funded this year. Project will be closed out upon final
invoicing.
Design Firm: Hoyle Tanner Contractor:
2019‐0402
Year Approved2020
Funding: DMA
21ROULEAU, RICHARD A
Thompson Hall ‐ Single Bottom Elevator Cylinder Replacement NHE 11021.1‐ PLAN/EST RR
5/26/2020 ‐ Project remains suspended due to COVID‐19. When suspension is lifted, project bid package will
need to be developed.
Design Firm: Contractor:
2015‐0091
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Thompson Hall ‐ Clock Tower and Envelope Assessment and Planning1.1‐ PLAN/EST RR
5/26/2020 ‐ Project remains suspended due to COVID‐19. When suspension is lifted, this project will require
a forensic RFQ/P to determine the cause and subsequent remedies.
Design Firm: Contractor:
2016‐0363
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Friday, May 29, 2020 Page 26 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Paul College ‐ Roof Membrane and Flashing Investigation ‐ Corrective Plan/Design1.1‐ PLAN/EST RR
5/26/2020 ‐ ARM recommends water testing to determine where/how the water is getting in. Proposal for
testing is in hand. P.O. request will be submitted now that Covid‐19 suspension has been lifted. Depending
on the results, we will pursue a warranty claim and/or involve PC Construction and the roofer. Using
remaining funds from original construction for this effort (ref. 2009‐0980 / 1XT955)
Design Firm: ARM, LLC (roofing
consultant)
Contractor:
2019‐0331
Year Approved2019
Funding: DMA
Holloway Commons ‐ Main Entrance Door Repairs/Investigation1.1‐ PLAN/EST FCR
5/26/2020 ‐ Project remains suspended due to COVID‐19. When suspension is lifted, the intent is to
implement Granite State Glass recommendations with funding from Business Affairs.
Design Firm: Contractor: Granite State Glass
2019‐0337
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Hamilton Smith Hall ‐ Rms G13, G15 Water Infiltration Investigation and Repair2‐ IN DESIGN FCR
5/26/2020 ‐ Pending further investigation as to specifically where/how the water is entering.
Design Firm: BEA Contractor: Skanska?
2020‐0030
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Campus ‐ Academic Way Improvements2‐ IN DESIGN SI
5/26/2020 ‐ Construction documents being prepared under Project #2010‐0297. SARCC funding in the
amount of $1.5M had been approved but may be in jeopardy due to COVID‐19. Work may be incorporated
into Spaulding Hall project (2016‐0278) due to location being mostly within the limits of the Spaulding project.
Design Firm: Tighe & Bond with
Woodburn Assoc.
Contractor: Skanska
2020‐0089
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Chase Ocean ‐ Rm S210 HVAC Recommendations and Repair2‐ IN DESIGN FCR
5/26/2020 Update ‐ Design ongoing. Estimate preparation is ongoing. Working with Energy Office on
temporary solution for this summer making RTU‐1 primary for the server room and RTU‐2 secondary. If the
customer provides funding, intent is to replace RTU‐2 with smaller unit prior to heating season. New RTU
will be 100% recirc, able to stage and will have reheat.
Design Firm: H.L. Turner Group Contractor: TBD
2020‐0149
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Memorial Union Building ‐ Bookstore Water Infiltration Repairs2‐ IN DESIGN BAR
5/26/2020 ‐ Waiting for a proposal for Careno for application of siloxane water repellent. It is being priced in
conjunction with Nick Petersʹ similar projects at Chase, 10 West Edge and Library Storage. Proposal expected
week of 6/1.
Design Firm: SGH Engineering Contractor: Careno
2020‐0169
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
Morse Hall ‐ Interior Main Heating Line Connections2‐ IN DESIGN RR
05/26/2020 Update: In design by Harriman.
Design Firm: Harriman Contractor: tbd
2020‐0271
Year Approved2021
Funding: DMA
Friday, May 29, 2020 Page 27 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Service Building ‐ Interior Heating Main Connections2‐ IN DESIGN RR
05/26/2020 Update: In design by Harriman.
Design Firm: Harriman Contractor: tbd
2020‐0272
Year Approved2021
Funding: DMA
Morse Hall ‐ Elevators NHE 1997 and 1998 Upgrades2.5‐ IN PROCUREMENT RR
5/28/2020 ‐ Project remains suspended due to COVID‐19. Intent is to keep Structure Tone contract in place,
re‐evaluate in November 2020, and hopefully resume spring 2021
Design Firm: Elevator Consulting
Associates
Contractor: Structure Tone with Stanley
as subcontractor
2013‐1225
Year Approved2020
Funding: DMA PROJECT SUSPENDED
Parsons Hall ‐ Classroom Renovation Iddles Lecture Halls2.5‐ IN PROCUREMENT RR
Static Update: See project #2019‐0132 for all information relative to this project.
Design Firm: Contractor:
2014‐1780
Year Approved
Funding: DMA PROJECT SUSPENDED
Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design
Only2.5‐ IN PROCUREMENT RR
5/28/2020 ‐ Project remains suspended due to COVID‐19. Intent is to keep Chapman contract in place, re‐
evaluate in November 2020, and hopefully resume spring 2021. Academic Technology to take lead on AV
specifications, bidding, and implementation.
Design Firm: Harriman Contractor: Chapman
Construction/Design
2018‐0145
Year Approved2019
Funding: DMA
James Hall ‐ HVAC Modifications Investigation and Design2.5‐ IN PROCUREMENT RR
05/28/2020 ‐ Repairs occurred on 5/18/2020; however, additional parts needed to be ordered. Balance of work
scheduled for 6/4/2020.
Design Firm: Contractor:
2018‐0270
Year Approved2018
Funding: DMA
Parsons Hall ‐ Iddles Auditorium Improvements2.5‐ IN PROCUREMENT SI
Static Update: See project #2018‐0145 for all information relative to this project.
Design Firm: Harriman Contractor: Chapman Construction
2019‐0132
Year Approved2020
Funding: SARRC
ALLOC
PROJECT SUSPENDED
Lord Hall ‐ Fire Alarm Replacement2.5‐ IN PROCUREMENT FCR
5/28/2020 ‐ Project remains suspended due to COVID‐19. When suspension is lifted, intent is to seek an
updated proposal from Norris.
Design Firm: SFC Engineering Contractor: Norris (if within term limits)
2020‐0038
Year Approved2020
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Utility Distribution ‐ Dual Temp Interconnection Plan3‐ IN CONSTRUCTION FCR
5/28/2020 ‐ Piping installation is ongoing in the Combined Heat & Power Plant (CHP). In area between
Morse Hall and Rudman Hall, dual‐temperature piping installation has commenced. Excavation for new
service to Morse Hall is complete. Demo and earthwork in Morse Circle will commence week of June 1st.
Pipe installation continues inside the Combined Heat & Power Plant.
Design Firm: Harriman Associates Contractor: Careno Construction
2019‐0022
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Friday, May 29, 2020 Page 28 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
88 Commercial Street ‐ UNH Manchester ‐ Bio‐Manufacturing Innovation Center
Tenant fit‐out3.1‐ SUBSTANTIAL COMPLETION FCR
5/28/2020 ‐ Construction is complete except for punchlist and miscellaneous extras. Furniture is complete
with exception of damage repair on recently delivered reception desk. Lab casework punchlist is almost
complete. Audiovisual installation is complete. Majority of the loose lab equipment has been received. Use
and occupancy of the space has slowed due to COVID‐19.
Design Firm: John Jordan Contractor: by landlord (using
Milestone)
2018‐0210
Year Approved2019
Funding: COLLEGE /
DEPT ALLOC
Coastal Marine Lab ‐ Fire Clean‐Up and Repairs3.1‐ SUBSTANTIAL COMPLETION FCR
5/28/2020 ‐ Project suspension due to COVID‐19 lifted on 4/27. Next steps are to assemble roofing package for
bidding and line up window repairs.
Design Firm: Contractor: Careno Construction
2018‐0336
Year Approved
Funding: COLLEGE /
DEPT ALLOC
PROJECT SUSPENDED
Hamilton Smith Hall ‐ Major Renovation Project3.5‐ WARRANTY REPAIRS SI
5/28/2020 ‐ Some Skanska warranty work remains. There are three water intrusion issues that we need to
move forward. A few furniture warranty items remain open.
Design Firm: DiMella Shaffer Associates Contractor: Skanska USA, Inc.
2012‐1851
Year Approved2013
Funding: SARRC
ALLOC
Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation3.5‐ WARRANTY REPAIRS RR
5/28/2020 ‐ No change. Complete pending equipment list update and O&M upload.
Design Firm: Harriman Associates Contractor: Charters Bros.
2018‐0249
Year Approved2019
Funding: DMA
Friday, May 29, 2020 Page 29 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management