Movement forUnderground MetroA Citizen’s Initiative

9/11/2010

Our Basis• The IIT Report – Comparative

Evaluation between Elevated & Underground Metro

• Our practical experience of living with the VAG Elevated Metro

9/11/2010

Does Mumbai need a

Metrorail ?

Question asked to Suburban Respondents in IIT’s Social Perception Survey

Yes, yes, yes (90%)

– but ……..9/11/2010

9/11/2010

Why does Mumbai need a Metro?

To DECONGEST the city

9/11/2010

Will Elevated Metro DECONGEST the city

?Consider …

9/11/2010

Santacruz to Andheri (approx 3 kms)takes about 45 minutes !

9/11/2010

How long will it take?

With Elevated

Metro6-lane will become 4-lane &

4-lane will be

2-lane

9/11/2010

Impact of Elevated Metro

9/11/2010

Each station proposes 45000 sq.ft. commercial space

27 such stations have been planned on Elevated Route9/11/2010

9/11/2010

Actual photograph of Andheri -Chakala Station touching existing building.9/11/2010

VAG traffic scene to be replicated across from CBM Route9/11/2010

MMRDA has scrapped9 flyovers en route

No scope forfuture traffic decongestion

9/11/2010

Elevated Metro flouts legal norms:

• Built under Tramways Act 1886

• Fire Brigade refuses NOC for stations

• CRZ violations • No AAI approval

9/11/2010

9/11/2010

7000 sq mts of footpaths will be occupied by stairs, lifts and escalators !Do we have the pavements ?9/11/2010

12.5 lakh additional pedestrians will spill on to streets with 30-50% less

space9/11/2010

32 km of sewer lines, 12.5 km of water lines and 11 km of gas lines will have to

be relaid9/11/2010

MMRDA needs about 1045 acres of lands forElevated Metro / mono rail projects

9/11/2010

• Will greatly reduce speed• Increase the length of the line• Make it accident-prone

54% of the alignment is on curves

9/11/2010

Potential fire hazard, no

access to fire tenders

9/11/2010

948 of the existing 1950 trees will be destroyed en route

9/11/2010

41.3 hectares of mangroves to be destroyed 9/11/2010

Expected sound level of Metrorail – 85 to 90 db

Limits set by High Court Day/Night – 55/45 db

9/11/2010

What are the advantagesof an Underground Metro?

9/11/2010

• Expansion Potential• Singapore began in 1988 and they are

still expanding the network underground

9/11/2010

Creation of Additional Urban Space- Delhi Metro Mall

9/11/2010

Lower Maintenance Costs

Year 20 km City Underground

32 km Elevated

2021 ` 80.89 cr(`4.04 cr/km)

`188.00 cr(`5.875 cr/km)

2031 `131.76 cr(`6.60 cr/km)

`307.00 cr(`9.60 cr/km)

9/11/2010

Why does MMRDAwant Elevated Metro?

9/11/2010

MMRDA Argument 1:

All over the worlddensely populated city areas have underground metro andsuburbs have elevated metro

9/11/2010

Andheri-Bandra is one of the most congested land masses in the

world !!http://www.citymayors.com/statistics*9/11/2010

MMRDA Argument 2: Underground (`531 cr/km) costs more than Elevated (`260 cr/km)

1.Why underground in city, when suburbs is more densely populated?

2.What about costs of land acquisition, re-laying utilities, increased length, project delay, environmental costs, social costs etc?

3.Cost of relocation of Andheri Pumping Station, Santacruz Police Station and rehabilitating project affected persons?

9/11/2010

IIT Mumbai Report

Govt. must invest in undergroundReasons:• Existing urban fabric not disturbed• Arterial roads not choked• No violation of civil laws• Vast saving in marginal cost• Scope for future expansion underground• Scope for integration with buses, taxi

etc• Creation of additional urban space• Total Decongestion of city• Minimal environmental impact

9/11/2010

The Cost Factor

9/11/2010

Hyderabad Metro (71 km) Cost`12,132 Cr = `171 Cr/km

Mumbai Metro (32.5 km) Cost`11,500 Cr = `354 Cr/km

Our BIG QuestionWhere has `5950 Cr Gone ?!!!

9/11/2010

Metro Rail Cost Comparison

City Stations Kms Cost Elevated per km

Cost Underground per km

Total Cost Diff with Mumbai

Chennai 32 45.1 `100 cr* `300 cr** `14600 cr `7440 crBangalore 32 42.3 `80 cr* `250 cr** `8100 cr `8090 crHyderabad 39 71 `171 cr*** - `12132 cr `5950 cr

* Estimated cost of construction of elevated station `30 cr.** Estimated cost of construction of underground station `100 cr.*** Includes construction cost of stations