Project Update

January 9th, 2012

Roadway Projects

• Temporary lanes have been installed on the east side and all traffic has been shifted towards the east

• The bridge over clear creek has been partially demolished to allow work to begin on the new bridge

• Work has begun on the installation of the storm trunk along the west right of way beginning at the creek

Cullen Parkway – Phase II

Phase II – Mary’s Creek Bypass to SH35 • Remaining punchlist items re-

communicated to TxDOT • Streetlight installation underway

Dixie Farm Road

• Completed installation of the irrigation system and landscaping

• Quantity overruns on existing storm sewer removal • The subcontractor completed the asphalt overlay

segments • Quantity overruns on base repairs • Full opening of SH35 intersection is dependent upon

TxDOT completion of the new signal

Walnut Reconstruction

• Traffic signal at Mykawa installation is complete. The signal was operational on December 9th

• Traffic switch completed last week • Potentially will extend beyond mid-February

completion date

Orange Street

• Cable and phone companies relocating • Waiting on a proposal from WSA for

modifications to the plans to address TxDOT comments at FM 1128 intersection

Bailey Road (Veterans to FM1128)

• 90% plans have been reviewed and returned to engineer

• Continued coordination with developer, County staff and CR59 designers

• 100% plans will be submitted in January

Business Center Drive

• Work to demo existing paving in the center lane and medians began and drainage laterals will be extended to the existing northbound lanes

• Contractor is preparing to begin lime stabilization at the north end

• TxDOT working with TCEQ on intersection with FM 518

• Mitigation Ponds bid opening on December 8th

SH35 – BW8 to FM518

• All signal poles installed • Project is on schedule for completion in

January 2012

FM 2234 Widening

• System has been running in full automated control since late November

• Tactics system required some debugging and went through several weeks of adjustments

• The system was determined to be Substantially Complete on Dec. 15th and a punch list was developed and transmitted to Siemens

Adaptive Traffic Signal Improvements

Drainage Projects

Diversion Ditch • DD4 continued excavation of diversion ditch west

of CR 143 Pump Station • Awarded the final design and construction phase

services contract to Montgomery & Barnes. Issued NTP

Re-grading of Roadside Ditches • Awaiting County response regarding exceptions to

the standard design criteria for the maintenance portion of the project

Cowart Creek Diversion

Facility Projects

• Punchlist near completion • Addressing warranty issues as necessary • Fuel island is functioning • Working on closeout documents

Hillhouse Road Service Center

• January is the latest completion date • Working on interior finishes

Fire Station #6

• Foundation piers were drilled the week of Dec. 12th

• Structural inspections complete • Monument base formed and poured • Architect reviewing stone and decorative

steel submittals

Pearland Gateway – Project Stars

Parks

• Trail areas around Park and along McLean

to Magnolia are cut and ready for forms • All concrete should be completed by the end

of January • Site furnishings received

Trail Connectivity

• Transmitted Interlocal Agreement and MOU to BDD4; approval scheduled for tomorrow

• Property acquisition ongoing • Developer Agreement scheduled for next CC

meeting • USACE responded requesting more information

and clarification on PCN for outfalls and weir to USACE for review

Sports Complex at Max Road

Utility Projects

30” Waterline Interconnect

• CoH flushed and disinfected the 72” line but did not pass BTs

• Re-flushed line and new tests scheduled for today • HMI should begin flushing & disinfection the 30”

water line system this week if 72” line passed

City of Houston Interconnect

City of Houston Interconnect

Alice Street Water Plant • Awaiting CoH water for startup of plant

• Staff reviewed 60% submittal and returned comments

• Held follow-up meeting to discuss plan review comments for clarification

Longwood WWTP Rehabilitation

• Design completed • Technical review meeting was held • Staff is loading bid information into the E-

Bid system • Advertise for bids by the end of January

Barry Rose WWTP Rehabilitation

• PER is under review

Hatfield Basin Trunk Sewer

• 90% review underway

Twin Creek Regional Lift Station

Far Northwest Wastewater Treatment Plant Improvements

• Design contract will be on the January 23rd agenda

Old Alvin 20” Waterline

• Received PER; currently in review process with staff

• Phase II ESA field work performed; contaminated soils issues identified near FM518 and Old Alvin

BellaVita Waterline Interconnect

• Requesting USACE to review wetland findings and environmental reports for Dixie Farm Rd Park property

• Survey work ongoing • Bella Vita HOA for right of entry obtained • Public Works began work at Bella Vita in mid

December

Project Update

Questions/Comments

January 9th, 2012