NATIONAL HIGHWAYS AUTHORITY OF INDIA(Ministry of Road Transport and Highways)
GOVERNMENT OF INDIA
DESIGN, CONSTRUCTION, DEVELOPMENT, FINANCE, OPERATION ANDMAINTENANCE OF 6-LANING OF VADAKANCHERY-THRISSUR SECTION
OF NH-47 (KM 240.000 TO 270.000) IN THE STATE OF KERALA ON DESIGN,BUILD, FINANCE, OPERATE AND TRANSFER (DBFOT) BASIS
CONTRACT PACKAGE NO.NS2/BOT/KL-3.
Independent Engineer[Intercontinental Consultants and Technocrats Pvt. Ltd.]
MONTHLY PROGRESS REPORT NO. 64
FOR THE MONTH OF: DECEMBER 2016
2
1.1 Summary of Current Month’s Progress
Physical Progress Summary:-
Physical and financial progress as on the month of December 2016 is as follows:-Monthly progress report (MPR) from October- 2012 to December 2016 had not been submitted by the Concessionaire. Concessionaire hasreported only physical and financial progress for the month of December 2016. The physical progress as assessed by IE is as follows:
Physical Progress:- (%)Description Upto previous
monthThis month Cumulative
Target as perConcessionaire’sProgramme based on EPCcost
80.67 6.82 87.49
Achieved as reported bythe Concessionaire basedon EPC cost
45.88 8.66 54.54
Achieved as assessed byIE.
40.90 5.77 46.67
Project Financial Data as of December 2016:Means of Finance Amount in crores Source of found as per Statutory
Auditor Certificate in croresRemarks
Equity 161.17 240.32Includes unsecured termloan & current liabilities
Term loan 505.11 398.54 -Grant 243.99 79.28 ReleasedTotal 910.28 667.74 -
3
Application of funds as per statutory Auditor Certificate dated 24.10.2016Sl.No
Particulars Amount in crores
1 EPC-Work done 425.352 Advance to – EPC Contractor 120.923 Current Assets & Loans & Advances 1.394 Fixed Assets 0.095 Financial and Administrative Expenses 32.926 Interest 93.91Total 674.67
Concessionaire’s work program is not satisfactory despite 100% obstruction free land are available in both structure and road work. Betterprogress can be achieved by good planning and expeditious deployment of adequate resources. Construction activities came to standstill in allthe fronts since last July 2012 and as a result, Project Milestone – I, ll & lII based on revised Appointed date as 15th September 2012 had notbeen achieved by Concessionaire apart from breach of Maintenance requirements of the ECW resulting issue of an “Intention to issue aTermination Notice” vide Authority letter no: NHAI/HQ/Tech/KL/2011/98 dated 30.04.2014.
After restructuring the term loan, Concessionaire had resumed the project activities w.e.f 7th Oct 2014 with commencing the nominal activities atroad and structure work apart from entering upon the tunnel from entry and exit approaches.
Though the Project work was resumed from Oct 2014, the pace of progress was not upto the mark and project activities have been haltedintermittently resulting conducting a meeting with the Concessionaire and IE at NHAI HQ on 20th May 2015, 30th Nov 2015 and 1st Feb 2016emphasizing the Concessionaire to mobilize adequate resources and to demonstrate their capability to establish that Concessionaire couldcomplete the Project by 31.03.2017.
Therefore, due to the concurrent delay by both parties for the reasons broadly brought out by IE in its recommendation for 1st interim EOT, EOTin Construction period without damages and without extension in the Concession Period has been approved by Executive committee of NHAI inits 283rd meeting held on 25.05.2016 by duly rescheduling the milestones and SPCD from 17.03.2015 to 31.03.2017 for which Concessionaireshall not claim any cost overrun or any time overrun (Concession Period) due to restructuring of milestones. With respect to the restructuredmilestones, Concessionaire has achieved the milestones I & II within the cure period. Concessionaire has not achieved the 3rd milestone falls on11.11.2016. However, there is a cure period available for 90 days.
On approval EOT, Concessionaire had raised 1st and 2nd tranche Grant proposal after infusing their equity and debt disbursal as per debtequity ratio and as certified by the Statutory Auditor. The same was released by the Authority. Further, Concessionaire has raised 2nd & 3rd
Tranche grant in the month of Oct 2016. In view of approval of EOT on construction period, notice regarding an “Intention to issue aTermination Notice” vide Authority letter no: NHAI/HQ/Tech/KL/2011/98 dated 30.04.2014 stands invalid.
4
Summary of Progress – [DECEMBER, 2016]:
Highway Work StatusClearing and grubbingClearing and grubbing is carried out for 48.40Km as bushes and shrubs have grown up in the area where C&G Completed earlier.Earth workEarth work is carried out at for 37.64 Km stretch and further work in progress.SubgradeSubgrade is carried out at for 25 Km stretch and further work in progress.GSBGSB work is carried out for 23.50 Km stretch and further work in progress.WMMWMM work is carried out for 22 Km stretch and further work in progress.Rock ExcavationRock excavation is being carried out at Ch. 243 & Ch. 251 and still around 30000m3 works to be carried out.DBMDBM work is carried out for 16 Km stretch and further work in progress
SurveyConcessionaire has commenced control points checking and center line markings and concessionaire has re-established center line chainagemarkings, Control points and TBMS shifted in regular intervals which are disturbed due to scarifying and maintenance of Existing carriageway.
Tunnel worksDrilling and blasting through left tube tunnel in D shape profile is in progress and achieved for about 1300 m. Following to this, Concessionaireshall require to undertake rock supporting work as proposed in the drawings. Similarly, treatment of vertical face of tunnel entry approach shallrequire to be done by the Concessionaire as proposed in the drawings to ensure stability of the cutting face.
Structure Work ProgressStructure work includes new construction of one major bridge, 2 flyovers, 10 underpasses, Up-gradation of one minor bridge and 87 culverts tobe widened or reconstructed as per site condition.
i) Cd Structures: 21 nos Box Culvert and 16nos Pipe Culvert completed and work in progress at 28 nos and 13 nos in Box and Pipe culvertsrespectively.
ii) Underpasses: Deck slab completed for underpass at Ch. 258+920 on LHS side, and Ch 261+830 on both sides. Wall lifts are in progress atCh 238+120 on LHS side, Ch 258+920 on RHS and Ch 262+240 on LHS.
5
iii) Flyover: Confirmatory boring for working piles are carried out for Flyover at Ch.262+707 and report has been submitted. All workingpiles for Mannuthy Flyover on both sides have been completed. Substructure, Girder casting & stressing works are in progress.Confirmatory bore hole work have been completed for flyover at Km. 237+035 and foundation , substructure Girder casting works are inprogress for few piers.
iv) Major Bridge: At Major Bridge Km. 247+170, 18 Nos. of foundations have been completed and substructure work, Girder casting,stressing & grouting works are in progress. 2 nos of deck slab completed.
v) Initial pile load test at one location has been done against the requirement of 2 nos. at Mannuthy flyover Km. 262+707 and test report afterconducting lateral load test is still awaited from Concessionaire.
vi) Minor Bridge: Excavation work is standstill on RHS side.
Contractor’s Work Programme:-After revising the Appointed Date as 15th September 2012, Concessionaire has again submitted the revised work program with SPCD as
March 2017.
Handing over of site:-NHAI has handed over 100% of ROW to Concessionaire including 86.86 Ha. of existing ROW and 13.95 Ha. of forest land during the
month of May 2013.Please refer NHAI letter No. – NHAI/PD/Palakkad/NH47/BOT/KL-3/HOL/784A dt. 31st May 2013. Details of land handedover to Concessionaire are given below:-Total land required for the Project – 181.122 Ha.Total land acquired by NHAI – 181.122 Ha. (100%)Total land free from Occupation – 181.122 Ha.(100%).Forest land acquired – 13.95 Ha.Existing ROW – 86.86 Ha.
Even though the joint inspection has been made regarding land availability as per Clause 10.3 of CA, the Memorandum and Appendix hasnot been signed by Concessionaire since May 2011.
6
Shifting of utilities
Even site clearance and dismantling of the structures within the acquired ROW had been completed by NHAI about 3 years before forentire stretch, still electric poles for 2 km length to be shifted. Revised estimate under Palakkad district have already been approved. Revisedestimate for Electric line shifting for Pattikkad division under Thrissur District has been approved. Concessionaire is still to initiate action forshifting the water supply lines at Thrissur and Palakkad District.
Forest clearance and removal of trees:-
MOEF stage 2 clearance (Final clearance) has been received on 14thMay 2013. Trees other than forest area from existing ROW havebeen almost felled down.
Design Review:-
Highway:GFC drawing of Plan and Profile for the entire stretch i.e. from Ch.236+135 to Ch. 264+410 has been issued except Ch.247+000 to
Ch.249+900 & Ch. 250+750 – Ch. 251+200. GFC drawing forService Road Plan & Profile has also been issuedexcept Ch. 236+135 – Ch.237+000, Ch. 249+450 – Ch. 250+200(LHS) and Ch. 249+450 – Ch. 254+000(RHS) and balance Plan and Profile of Service Road andDrainage Plan comments has been issued.
Structure:
The designs for Flyover at Ch. 262+707 and at Ch. 237+035 are reviewed. The design for Major Bridge at Ch. 247+170 is reviewed. Pilefoundation design calculations has been reviewed by IE and concessionaire was advised to go ahead with casting of 2no’s of initial pile forinitial pile load test at each flyover location in order to ascertain the pile capacity. The design for Minor Bridge at Ch. 241+166 for newconstruction on RHS is reviewed and for widening on LHS is reviewed and comments issued. The design for Underpass at Ch. 236+320, Ch.238+120, Ch. 258+920, Ch. 261+830 and 262+240 are reviewed. GFC for foundation, substructure and superstructure issued for Flyover at Ch.237+035 & Ch. 262+707. GFC for new construction of Minor Bridge at Ch. 241+166 issued and for Major Bridge at Ch. 247+170 are issued.GFC for 75 Nos. of Culverts issued. GFC for underpasses at Ch. 236+320,Ch. 238+120, Ch. 258+920, Ch. 261+830 and Ch. 262+240 areissued. Concessionaire has proposed for revision in design of flyover Ch. 237+035 with open foundation and revising the span arrangement ofalready reviewed drawings. Subsequently, the revised design/ drawing submission and review is in final stage.
7
Quality and Material Status
As on date 5 No’s of borrow areas have been reviewed for using in road embankment construction and out of which schedule - E permit for 3Nos of Borrow Area were not yet obtained.
i) As on date, 4 Nos. of Brand of cement viz Chettinad, Penna, Ultra Tech, Dalmia have been approved for use in the Project Highway.ii) Source for Fine and Coarse Aggregate from km.291+000 (RHS) at Perambra had been approved.
iii) Concrete Trial mix design on M15, M25, using Chettinad, Penna, and Ultra Tech cement had been approved.iv) Concrete Trial mix design on M15, M20, M20(Kerb), M25, M35 (RCC),M35(REB), M35 (Pile) & M45 for PSC girders using Dalmia
cement have been carried out.v) Concrete mix design for all grades of concrete for the change in source of aggregate is in progress
vi) GSB Mix Design carried out from the source Perambra Quarry km.291+000 (RHS)had been approved by IE.vii) WMM Mix Design carried out from the source Perambra Quarry km.291+000 (RHS)had been approved by IE.
viii) SAIL, RINL Vizag, TISCO have been approved as source for sourcing steel reinforcement for Project Highway.ix) Source approval for NP4 class RCC Hume Pipe also given for sourcing the pipe for pipe culvert work.x) This is required for socketing the pile/resting the raft foundation in the required strata strength. Concessionaire was also instructed to
perform bore hole investigation in the approaches of structure as the same was not done earlier.xi) Subsoil investigation at 27 Nos. of box culvert locations has been Completed and SBC reports have not yet submitted by the
concessionaire.xii) QAP of the project approved by IE for those items of work submitted.
Current Issues & Recommended Actions by IE:
DEFECTS / DEFICIENCIES IN WORK:
Existing Carriageway (ECW) of Project Highway has not been maintained for traffic worthy condition at certain stretches and the ridingquality is poor.
Even though Concessionaire has taken up road formation work at several stretches as well as structures, adequate work zone safetymeasures has not been provided till date which is posing threat to the road users and the same was brought out in the Audit Report of NHAI’sRoad Safety Consultant.
As per the final reviewed drawings of RCC Box culverts, the SBC at the founding level shall be confirmed prior to execution. But,Concessionaire has proceeded with the works of culverts even where strata at founding level is clayey, without confirming SBC and complyingwith the NCR raised by IE.
8
Concessionaire has executed all working piles in arbitrary manner even without completing the Initial pile load tests at the balance 1 nos of Testpile and without submitting the report where test done to confirm the design capacity of pile. Concessionaire is continuing with the casting ofpilecap and raising the super structure at mannuthy flyover Km 262+707 without conducting routine pile load test on working pile to confirm thesafe load carrying capacity of piles. Similarly, Concessionaire has cast all piles (16 nos) at Major bridge (P1 LHS) without submitting therevised drawing and confirming the pile capacity through initial pile load test on test pile. This is not acceptable to IE as this does not conform toGood Industry practices.
Concessionaire has carried out embankment widening at certain stretches of water logged areas without submitting a methodology and adoptingthe proper foundation improvement as per Mo RT&H specs despite issuing a NCR. This is liable for pavement failure in future.
Concessionaire continues to execute the RE wall foundation at Mannuthy stretch without adhering to the system provider recommendations andwithout checking available SBC at site.
Concessionaire is continuing with the construction of lined drain without providing weep holes at the GSB bottom despite issuing NCR. Thiswould pose pavement failure in future due to lack of pavement sub- surface drainage.
Concessionaire continues to carry out the backfilling with filter media behind box & pipe culverts in a stroke without compacting in layers evenafter NCR issued, which is liable for pavement settlement and posing threat to the safety of road users.
9
1.2 Critical Issues & Action Log
1.2.1 Pending Issues & Action Log
SNoIssue
DescriptionType
Ongoing/New
Issue/Resolved
ConcernedAuthority
Chainage(s)affected dueto the issue
Lengthaffected
(km)Action(s) taken till now Action(s) suggested by the IE
Expected date/Actual Date forresolving issue
NIL
10
1.2.2 Obligations as perContract
Expected Contents & Structure
Please write a summary of non-compliances of contractual obligations highlighting reasonsfor delay, stating pending actions and their potential risk to the project’s progress andrecommended actions by the IE.
Critical obligations and constraints of concessionaire as per contract - NIL
Critical obligations of authority as per contract - NIL
Critical pending obligations of IE as per contract - NIL
NOTE: Please include important issues requiring intervention of various parties,giving details and background wherever necessary
11
1.3 Project Overview
1.3.1 Salient Features of Project
Project Name Design, Construction, Development, Finance, Operationand Maintenance of 6 lane of Vadakkancherry – Thrissursection of NH-47 (Km.240.000 - Km.270.000) in the stateof Kerala on Design, Build, Finance, Operation andTransfer (DBFOT) pattern under NHDP phase-II
NH No. (New/ Old) NH-544 (Old 47)
Scheme/ Phase Phase-II
Mode of the Execution (BOT Toll/ BOT Annuity/EPC/ HAM/ Item Rate/ Others)
BOT (Toll)
No. of Lanes/ Configuration 6 Lane
Length of the Project (in Km) 28.355 Km (As per design)
Total Project Cost (in Cr) Rs.617 crore as per RFP and Rs.910.28 crores as per MRA
No. of Bypasses (Name of Town, Length) Nil
No. of Major Bridges (Number and Location) 1 No. (Km. 247.170)
No. of Toll Plazas (Number and Location) 1 No. (Km. 239.020)
No. of Fly Overs (Number and Location) 2 Nos. (Km. 237.035 & Km. 262.707)
DPR Consultant Name M/s. Sowil Consultant
Lead & Consortium Members of Banks AXIS Bank
Concessionaire Name (SPV & Parent Company) M/s. Thrissur Expressways Ltd.
Date of Award (LOA Date) 24.08.2009
Appointed Date 15.09.2012
Concession Period 20 Years
Construction Period (in Days) 913 Days
O&M Period (in Days) -
Scheduled Date of Completion 31.03.2017 (Rescheduled SPCD)
Independent Engineer M/s. Intercontinental Consultants and Technocrats Pvt. Ltd.
IE Agreement Date 11th March 2010
IE Mobilization Date 04th April 2010
12
1.3.2 Project Milestones
Sl.No. State of Milestone
Time/Date of RescheduledMilestone as per EOT approval Target %
Progress oftotal capital
cost*
RemarksTime in days Date
1 Project Milestone – I 253 10.06.2015 10 Achieved
2 Project Milestone – II 513 25.02.2016 35 Achieved
3 Project Milestone – III 773 11.11.2016 70 In progress
4 Scheduled 6 Laning date 913 31.03.2017 100
15
1.4 Physical Progress
Component % WeightagePhysical Progress
(During Current Month)
Physical Progress
(Cumulative, Upto CurrentMonth)
Road Works 38% 1.81% 18.07%
Major Bridge works and ROB / RUB 22% 1.46% 11.5%
Structures 19% 0.26% 8.1%
Other Works 21% 1.19% 8.51%
Physical Progress 4.72% 46.18%
16
1.4.1 Detailed Scope of Work & Physical Progress by Component
S.No Description Unit BOQ QTY Proposedweightage
% Calculation: (BOQ /Total
BOQ)% ofweightage
ExecutedQTY
weightage%
TotalExecuted
weightage%
Remark
I EARTH WORK1 Clearing and Grubbing Ha 98 0.00071% 90 0.00%2 Roadway Excavation Cum 429496 3.09% 330270 2.38%3 Excavation in Rock Cum 265549 1.91% 213914 1.54%4 Excavation in Structure Cum 48076 0.35% 24000 0.17%5 Embankment Cum 1306814 9.41% 823949 5.93%6 Sub grade and Shoulder Cum 502821 3.62% 272167 1.96%7 Median filling Cum 72809 0.52% 3402 0.02%8 RE wall Filling Cum 429754 3.09% 0 0.00%
3055417 22% 12.01% 12.01%II GRANULAR COURSE1 GSB Cum 176165 3.79% 86972 1.87%2 WMM Cum 195291 4.21% 92929 2.00%
371456 8% 3.87% 3.87%III BITUMINOUS COURSE
1 Profile Corrective Coursewith BM Cum 2306 0.13% 583 0.03%
2 Dense Bituminous Macadam Cum 96333 5.45% 38162 2.16%3 Bituminous Concrete Cum 42765 2.42%
141404 8% 2.19% 2.19%
IV CROSS DRAINAGE(CULVERTS)
1 Box culvert 58 No's No's 58 6.19% 28.36 3.03%2 Pipe culvert 29 No's No's 29 1.81% 20.59 1.29%
87 8% 48.95 4.31% 4.31%v UNDERPASSES
As per CA LHS No's 7 2.00% 3.10 0.62%As per CA RHS No's 7 2.00% 1.56 0.00%
14 4% 0.62% 0.62%
17
VI BRIDGESScope as per CA LHS No's 1 3.60% 0.00098 2.71%Scope as per CA RHS No's 1 3.60% 0.00063 1.76%Minor Bridge LHS 1 0.27% 0.00000 0.00%Minor Bridge RHS 1 0.53% 0.000005 0.09%
1 8% 4.56% 4.56%VII FLYOVER
Scope as per CA LHS No's 2 5.00% 1.38 3.44%Scope as per CA RHS No's 2 5.00% 1.15 2.88%
4 10% 6.32% 6.32%VIII RE WALL
Sqm 52202 5.00% 8222 0.79% 0.79%52202 5%
IX DRAINConstruction of RCC Drain LM 30419 6% 6.00% 15200 3.00% 3.00%
X Miscellaneous & RoadSafety
1 Traffic Diversion LM 3000 0.96% 1800 0.58%2 Highway Lighting No's 487 0.90% 0.00%3 Toll plaza No's 1 0.60% 0.00%4 Signage's No's 596 0.20% 0.00%5 Bus shelter No's 21 0.15% 0.00%6 Kerb Laying LM 84765 0.73% 10121 0.09%7 Pavement Marking Sqm 37200 0.79% 0.00%8 Metal Beam crash barrier LM 20000 1.18% 0.00%9 Pitching with filter media Cum 23220 0.49% 0.00%
6% 0.66% 0.66%XI Tunnel with Approach
Approach LM 860 2.70% 2.70% 458.00 1.44% 1.44%Tunnel LM 900 12.30% 12.30% 469 6.41% 6.41%
100% 46.18%
24
1.5.2 Strip Plan (Summary)
1. Workfront Unavailable & Reason fory
2. Length Completed by Layer (MCW)Unavailability
3. Length Completed by Layer(Service Road)
1.6 Land Acquisition andClearances
1.6.1 LA Summary
Description Total Required (ha)Total in possession at start
(ha) Total to be acquired (ha)
Existing ROW 60 m 60 m 0
Pvt. Land To be Acquired 181.122 Ha 181.122 Ha 0
Forest Land To be Transferred 13.95 Ha 13.95 Ha 0
Length(km)
TotalPendingLength
Total Length 56.71 51
Total WorkfrontUnavailable
0 0
PendingAcq.
Land0 0
PendingClearances
0 0
Encumbrances 0 0
Length(km)
% TotalLength
Total Length 51.35 100%Total LengthCompleted(Till DBM)
17 33.10%
BC 0 0%
DBM 17 33.10%
WMM 22.48 43.77%%GSB 23.52 45.80%%Sub-Grade 25.5 49.65%%C&G 48.9 95.22%
Length(km)
% TotalLength
Total Length 32 100%Total LengthCompleted(Till DBM)
17.225 53.8%
BC 0 0%
DBM 17.225 53.8%
WMM 17.78 55.56%%GSB 17.78 55.56%
Sub-Grade 20 62.5%C&G 31 96.87%
25
1.6.2 LA Detail byCALA
CALA
TotalLandleft to
beAcqui
red(Ha)
3HPending(ha)
3HDone(ha)
3GPending(ha)
3GDone(ha)
3DPending
(ha)
3DDone(ha)
3APending
(Ha)
3ADone(ha)
AmountAwarded(Crore
Rs.)
AmountDeposited
(CroreRs.)
AmountDisbursedby CALA
PendingAmount
(CroreRs.)
(CroreRs.)
Spl. Dy.Collector& SLAO,LANH,Palakkad
0 Nil
Spl. Dy.Collector& SLAO,LANH,Thrissur
0 Nil
1.6.3 Clearances Summary
Environment
Proposal Description StatusLength
ImpactedCurrent Stage Issues/ Comments
Approval of construction in coastal zone Nil Nil Nil Nil
Forest Land
Proposal Description Status LengthImpacted
Current Stage Issues/ Comments
Diversion of 6.345 Ha forest land (247.900 to249.150)
obtained 1.25 Km. Tunnel work is inprogress
Final approval received from MoEFon 14.05.2013
26
Wildlife
Proposal Description StatusLength
Impacted Current Stage Issues/ Comments
Diversion of 7.605 Ha. of forest land Obtained 1.50 Km.Tunnel workis in progress
Final approval obtained fromMoEF on 14.05.2013
Tree Cutting
Proposal Description Status LengthImpacted
Current Stage Issues/ Comments
Work completed
Railways (ROBs/ RUBs)
GAD Number StatusLocation/Chainage
Current Stage Issues/ Comments
Nil Nil Nil Nil Nil
27
1.6.4 Status of utilities shifting
UtilityCategory
Name StatusLengthaffected
DepartmentDate of request
by Authority forestimate
Date whenEstimate was
Received fromconcerned dept.
Date ofApproval by
AuthorityRO/ HQ
Date ofDeposit of
super-visioncharge
Progressof Physical
Shifting
Date ofCertificationfrom Agency
forCompletion
EstimateAmount (Rs inlakhs)
Issue/Commen ts
Water-
EstimateApproved
-
KWA 25.11.2009 01.03.2010 14.05.2010 02.06.2010 In progress- 182.44
NHAIHQ hasgrantedEOT upto March2017.Accordingly utilityrevisedestimatehave beenreceivedfromKSEB &KWAwhich hasbeen sentto RO forapprovalon17.09.16&21.09.16
Water-
EstimateApproved
-
Local Self Govt. 25.11.2009 28.01.2010 14.05.2010 NA In progress - 48.51
Electricity-
EstimateApproved
- KSEB
08.10.2009/24.06.2010
18.02.2010/21.07.2010 27.09.2010 29.10.2010
80%completed
-121.23
Electricity -EstimateApproved
- KSEB
04.05.2011/22.09.2014/26.02.2016
31.10.2015/11.03.2016 18.05.2016 29.10.2010
80%completed
- 75.12
28
1.7 Change of Scope
S No. Proposal DetailsDate of first
submission to IECurrent Status
COSAmount
Expected/ Actual Date ofApproval
1Construction of VUP at Km.254.355
- Approved in principle by Authority on
31.10.2009. Detailed quantities in proper order
yet to be submitted
- -
29
1.8 Mobilization of Resources
Sl.No.
Plant/ Equipment/ MachineryDeployed
AvailableUnder
Erection/mobilization
1. Motor Grader 120 H 4 -
2. Wheel Loader 3 -
3. Excavator 15 -
4. Dozer D50 + Tractor dozer 2 -
5. Soil Compacter 3 -
6. Crane 15 Ton 3 -
7. Tipper (Volvo) 30 T 9 -
8. Taurus Tipper 20 T 35 -
9. Tipper 12 T 20 -
10. Conventional boring rig 1 -
11. Water Tanker 2 -
12. Concrete boom placer 1 -
13. S/Stetter Transit Mixture 7 -
14. Concrete Batching Plant 3 -
15. WMM Plant 1 -
16. CAT DG Sets 500 KVA 4 -
17. CAT DG Set 250 KVA 1 -
18. Sudhir 63 KVA DG set 6 -
19. Sudhir 125 KVA DG set 3 -
20. Crusher 250 & 200 TPH 2 -
21. HMP 200TPH 2 -
22. Mobile crusher for GSB – 120 TPH 1
30
18
1.9 Financial Progress Details
1.9.1 Pen Picture - Escrow
TPC (Cr)
Cumulativeinflow to Escrow
till previousmonth (Cr)
Cumulativeoutflow fromEscrow till
previous month
(Cr)
Inflow to Escrowduring the month
(Cr)
Outflow fromEscrow during
the month
(Cr)
910.28 646.50 626.80 77.20 57.90
Are the Escrow withdrawals in accordance with the order of withdrawal as specified in the Concession Agreement?
Tick as applicable Yes No
31
1.9.2 Escrow details
TPC (Cr)Cumulative exp.
till date (Cr)
Escrow Plan tilldate- Debt (BOT)
(Cr)
Escrow Plan tilldate- Equity(BOT) (Cr)
Escrow Plan tilldate- VGF (BOT)
(Cr)
Escrow Actualtill date- Debt(BOT) (Cr)
Escrow Actual tilldate- Equity (BOT)
(Cr)
EscrowActual tilldate- VGF(BOT) (Cr)
910.28 584.31 389.50 161.17 108.15 389.50 161.17 108.15
32
1.10 Monitoring of Operations & Maintenance Obligations
1.10.1 Maintenance Status during Construction Phase
Maintenance of existing road:-Concessionaire shall require to take up immediately the cleaning of all Existing Row chocked drain and
CD structures to prevent entry of rain water over carriageway in the forthcoming monsoon. Concessionaireshall also ensure for smooth natural drainage of surface and subsurface water during the monsoon at thosestretches where widening work taken up. Concessionaire shall require to immediately repair the potholesand patches those have been developed at several stretches in the project highway for traffic worthiness toavoid accident and inconvenience to the road users apart from inviting criticism from the representatives ofpublic and local body.
Safety Measures:-Concessionaire shall require to provide Cautionary Sign Boards at all Curve locations of Existing
Carriageway and due to lack of installation of such sign boards, accidents are occurring at curve locations inthe Project Highway which need to be prevented.
There are frequent instructions from District Administration/Commissioner of Police to enhance thesafety measures at Kuthiran hill by widening the road at paved shoulder area along with provision ofadequate sign boards in view of occurrence of accidents very often. Concessionaire shall require to resumesafety measures on priority basis to avoid further accidents.
Issues of serious concern:-
The Project activities are quite affected for want of adequate resources and deployment of staff underHighway, Bridge and Material section from Concessionaire as well as EPC side. Virtually, adequatenumbers of staff at High, middle level management and supervisory level are not available at Project sitefrom Concessionaire and EPC side to initiate, plan and co-ordinate the Project activities on day-to-day basisfor implementation of the Project.
Physical progress of 46.67%only achieved as of December 2016 and thus it is unlikely thatConcessionaire could achieve SPCD by March 2017 unless Concessionaire initiate an action plan onwar footing basis with mobilization of all resources for parallel activities in all fronts. As per revisedwork program of the Concessionaire, the financial progress of `659.48 crores should have beenachieved as against the EPC cost ` 753.80 crores whereas, it was only 351.77 crores has beenachieved.
Adequate safety measures should be provided immediately in construction zone. Concessionaire to initiate appropriate action on priority basis to maintain the ECW for traffic
worthiness including constant cleaning of side drains as the condition of road at certain stretches hasbecome very bad due to development of patches/pot holes.
Temporary Handrail provided in the Irumbubalam Bridge is found unsafe which needs to be rectifiedon priority basis for safe traffic over the Bridge.
Drainage proposal should be finalized at the earliest. Applicable permits as per Schedule E are yet to be obtained for KL-3 Project. There is acute shortage of necessary resources like manpower, machinery and material for the
execution of Project even though full work fronts (100%) are available for structure and road work. Concessionaire has still to comply the outstanding 76 No’s of NCR and the same has been enclosed
as Annexure-1
33
Still balance one number initial pile load test on test pile at Mannuthy flyover at Ch. 262+707 is duefor testing since last 4½ years for which Concessionaire needs to expedite the arrangement fortesting, which is a matter of concern.
Concessionaire had started raising the sub structure at Mannuthy flyover Km. 262+707 withoutconducting the routine pile load test for confirming the safe axial/lateral load carrying capacity ofpile, which is a matter of serious concern.
Concessionaire shall require to conduct subsoil investigation at all RE Wall approach locations andHigh embankment forming approach to bridge followed by performing stability analysis andsubmitting to IE with ground improvement, if any for review in advance of commencement of work.This is very important Technical Parameters required to be complied prior to execution of work.Still, this is not complied by the concessionaire.
The Concessionaire has not submitted any proposal for reconstruction of the aqueduct under positivechange of scope for obtaining approval of competent authority.
Concessionaire shall acquire the small piece of land at the exit approach at their risk and cost asagreed in the CGM(T)& RO meeting in order to avoid shifting the alignment at exit approach.
1.10.2 Maintenance Status during Operations & Maintenance Phase : NIL
34
1.11 Pen Picture on safety features
Details to be provided after assessment of the site requirement vis-à-vis provisions in the Concession Agreement:
Location of Black SpotsSuggested Remedial Measures
within provisions of ConcessionAgreement
Additional Remedial Measures
(if any)
Financial implications of additionalRemedial Measures for Authority
(Cr.)
NIL NIL NIL NIL
35
1.12 Annex 1: Detailed List of Physical Components as per Schedule G
Component Physical Item
Road worksincluding culverts,
minor bridges,underpasses,overpasses,
approaches toROB/RUB/Major
Bridges/ Structures(but excludingservice roads)
A- Widening and strengthening of existing road
(1) Earthwork up to top of the sub-grade
(2) Granular work (sub- base, base, shoulders)
(a) GSB
(b) WMM
(3) Shoulders
(4) Bituminous work
(a) DBM
(b) BC
(5) Rigid Pavement
Concrete work
(6) Widening and repair of culverts
(7) Widening and repair of minor bridges
B- New realignment/bypass
(1) Earthwork up to top of the sub-grade
(2) Granular work (sub- base, base, shoulders)
(a) GSB
(b) WMM
(3) Shoulders
(4) Bituminous work
(a) DBM
(b) BC
(5) Rigid Pavement
Concrete work
C- New culverts, minor bridges, underpasses, overpasseson existing road, realignments, bypasses:
(1) Culverts
36
Component Physical Item
(2) Minor bridges
(a) Foundation
(b) Sub-structure
(c) Super-structure (including crash barriers etc. complete)
(3) Cattle/Pedestrian underpasses
(a) Foundation
(b) Sub-structure
(c) Super-structure (including crash barriers etc. complete)
(4) Pedestrian overpasses
(a) Foundation
(b) Sub-structure
(c) Super-structure (including crash barriers etc. complete)
(5) Grade separated structures
(a) Underpasses
(i) Foundation
(ii) Sub-structure
(iii) Super-structure (including crash barriers etc.complete)
(b) Overpass
(i) Foundation
(ii) Sub-structure
(iii) Super-structure (including crash barriers etc.complete)
(c) Flyover
(i) Foundation
(ii) Sub-structure
(iii) Super-structure (including crash barriers etc.complete)
(d) Foot over Bridge
Major Bridge A- Widening and repairs of Major Bridges
37
Component Physical Item
works andROB/RUB
(1) Foundation
(a) Open Foundation
(b) Pile Foundation/Well Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
B- Widening and repair of
(a) ROB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
(b) RUB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
C- New Major Bridges
(1) Foundation
(a) Open Foundation
(b) Pile Foundation/Well Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
D- New rail-road bridges
(a) ROB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
(b) RUB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
38
Component Physical Item
Structures(elevated sections,reinforced earth)
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
(4) Reinforced Earth Wall (includes Approaches of ROB,Underpasses, Overpasses, Flyover etc.
Other Works (i) Service roads/ Slip Roads
(ii) Toll Plaza
(iii) Road side drains
(iv) Road signs, markings, km stones, safety devices, ….(a)Road signs, markings, km stones, ….
(b) Concrete Crash Barrier/ W-Beam Crash Barrier inRoad work
(v) Project facilities
(a) Bus bays
(b) Truck lay-byes
(c) Rest areas
(vi) Repairs to bridges/structures
(vii) Road side plantation
(viii) Protection works
(a) Boulder Pitching on slopes
(b) Toe/Retaining wall
(ix) Tunnel
(a) Excavation
(b) Construction of support system including rock bolting,lining etc.
(c) On complete completion of tunnel
(x) Miscellaneous
* The above list is illustrative and may require modification as per the actual scope ofthe work.
39
Annexure I
S.No. Letter No. Date Work DescriptionCompliancereport with
DateStatus
IE’sLetter
No: withDate
Remarks
1. 1ICT: 468: TL:
KL-3: TEL: 53424.11.2011
Not maintaining thecement register and storingthe unapproved cementwith approved cement atthe Batching plant feedhopper store at Km 274(LHS) Marathakara.
Pending
2. 2ICT: 468: TL:
KL-3: TEL: 56112.12.2011
Casting 1st lift Wall ofunderpass chainage at258+920 (LHS) M35grade on Thrissur sidewithout raising RFI.
Pending
3. 3ICT: 468: TL:
KL-3: TEL: 62724.01.2012
Embankment layer fillingover uncompacted andunapproved OGL bed fromCh. 245.400 to 245.500(RHS).
Pending
4. 9ICT: 468: TL:
KL-3: TEL: 64802.02.2012
Using the unapprovedconcrete admixture andwithout approval of trialmix with changed sourceof admixture in M35 gradeconcrete for underpassdeck slab at km 258+920LHS.
pending
5. 10
ICT: 468: TL:KL-3: TEL: 662
15.02.2012
Laying PCC for boxculvert at ch:263+905 LHSwithout conforming SBCand without raising RFI.
Pending
6. 11
ICT: 468: TL:KL-3: TEL: 686
05.03.2012
Non Compliance onProduct Notification forlaying PCC at Box Culvertat Km. 250+664 (LHS)Without Confirming SBC.
Pending
7. 12
ICT: 468: TL:KL-3: TEL: 695
13.03.2012
Non Compliance onProduct Notification forDumping and Spreading ofUnsuitable Material forEmbankment ConstructionWithout Compacting OGLBed Between Km.259+000 to 259+100(RHS).
Pending
8. 13
ICT: 468: TL:KL-3: TEL: 700
14.03.2012
Non Compliance onProduct Notification forlaying PCC for BoxCulvert at Ch. 255+032(LHS) WithoutConfirming SBC.
Pending
40
9. 17
ICT: 468: TL:KL-3: TEL: 710
20.03.2012
Non Compliance onProduct Notification forTaking Up EmbankmentIInd Layer WithoutApproval of EmbankmentIst Layer at Km. 257+880to Km. 257+930 (RHS).
Pending
10. 18
ICT: 468: TL:KL-3: TEL: 711
21.03.2012
Non Compliance onProduct Notification forlaying PCC at Box Culvertat Ch. 252+966 (LHS)having Clayey Strata atFounding Level WithoutConfirming SBC andWithout Raising RFI.
Pending
11. 19
ICT: 468: TL:KL-3: TEL: 715
22.03.2012
Non Compliance onProduct Notification forDumping and Spreading ofEmbankment 1stLayerOver Unapproved OGLBed with Bumping at Km.251+280 to Km. 251+420(RHS).
Pending
12. 20
ICT: 468: TL:KL-3: TEL: 717
23.03.2012
Non Compliance onProduct Notification forUsing the EmbankmentMaterial from Untestedand Unapproved BorrowArea at Km. 251+900(LHS).
Pending
13. 21
ICT: 468: TL:KL-3: TEL: 745
11.04.2012
Non Compliance onProduct Notification forStarting of Piling Works inMannuthy Flyover at Ch.262+707 WithoutCompleting the DesignProcedures.
Pending
14. 24ICT: 468: TL:KL-3: TEL: 760
21.04.2012
Non Compliance onProduct Notification forProceeding With FurtherWorks for Box Culverts atCh. 251+961 (RHS), Ch.257+866 (RHS) and Ch.262+942 (LHS) WithoutConfirming SBC andSubmission of Reports
Pending
15. 26ICT: 468: TL:KL-3: TEL: 773
02.05.2012
Non Compliance onProduct Notification forLaying PCC at BoxCulvert at Ch. 252+288(RHS) having ClayeyStrata at Founding Levelwithout Confirming SBC
Pending
16. 28ICT: 468: TL:KL-3: TEL: 802
29.05.2012
Non Compliance onProduct Notification forLaying PCC andProceeding with the Workat Box Culvert at Ch.
Pending
41
251+620 RHS, Ch.254+125 RHS and Ch.253+084 LHS havingClayey Strata at FoundingLevel Without ConfirmingSBC
17. 30ICT: 468: TL:KL-3: TEL: 819
13.06.2012
Non Compliance onProduct Notification forLaying PCC for BoxCulvert at Ch. 253+353(LHS) having ClayeyStrata at Founding Levelwithout Confirming SBC
Pending
18. 31ICT: 468: TL:KL-3: TEL: 826
15.06.2012
Non Compliance onProduct Notification forLaying of WMM TopLayer Without using aSensor Paver at Km.263+200 to Km. 263+400(RHS)
Pending
19. 32ICT: 600: TL:KL-3: TEL: 1329
03.06.2015
NCR No: 32 NonCompliance on ProductNotification for LayingPCC for Box Culvert atCh. 243+447 (LHS)having Sandy ClayeyStrata at Founding Levelwithout Confirming SBC
Pending
20. 33ICT: 600: TL:KL-3: TEL: 1357
15.07.2015
Non Compliance onProduct Notification forconcreting the workingpile in Mannuthy flyoverat Ch. 262+707 withoutcompleting the designprocedures/ confirming thedesign strength of rockprofile (UCS) forsocketing the pile in thehard rock
Pending
21. 34ICT: 600: TL:KL-3: TEL: 1451
30.10.2015
Non Compliance onProduct Notification forconcreting for PSC girderwith M45 grade concreteat flyover Km 262+707between P4 and P5 outergirder no. 2 (RHS) withoutinstalling Electronicprinter for qualityassurance
Pending
22. 35ICT: 600: TL:KL-3: TEL: 1484
04.01.2016
Non Compliance onProduct Notification fornot submitting theManufactured TestCertificate (MTC) onvarious batches of the year2015 pertaining to DalmiaOPC 43 grade cement and
Pending
42
not maintaining the cementindent record
23. 36ICT: 600: TL:KL-3: TEL: 1485
05.01.2016
Non Compliance onProduct Notification forusing the HYSD TMT barsin the major structureworks from the LOT No. 4to 8 without QualityControl tests and withoutconducting tests fromNABL accreditedlaboratory on the first LOTof steel from M/s JSW Ltd.for selection and approvalof source
Pending
24. 38ICT: 600: TL:KL-3: TEL: 1506
22.01.2016
Non Compliance onProduct Notification forlaying the GSB layer onthe Project highwaywithout Quality Assurance
Pending
25. 39ICT: 600: TL:KL-3: TEL: 1509
23.01.2016
Non Compliance onProduct Notification forlaying PCC at Box Culverton LHS of Km.236+601,Km. 236+765, Km.237+193, Km. 237+609and Km. 239+950 withoutverifying SBC at foundinglevel as per therequirement of GFCdrawing – Leading tounsafe work
Pending
26. 40ICT: 600: TL:KL-3: TEL: 1519
04.02.2016
Non Compliance onProduct Notification fortaking up of GSB layerover subgrade in cutformation from Km.257+520 to Km. 257+860MCW (LHS) withoutcompacting the subgradein layer wise to therequired degree ofcompaction to ensuredesign CBR for qualityassurance
Pending
27. 41ICT: 600: TL:KL-3: TEL: 1520
04.02.2016
Non Compliance onProduct Notification forlaying PCC over clayeystrata at Box culvert km245+606, 245+807 &245+932 (RHS) withoutverifying SBC at foundinglevel as per GFC drawing
Pending
28. 42ICT: 600: TL:KL-3: TEL: 1532
10.02.2016
Non Compliance onProduct Notification forlaying the GSB layer oversubgrade on service road
Pending
43
without compacting thesubgrade for 300mmportion from bottom to therequired degreecompaction in thefollowing stretches
29. 43ICT: 600: TL:KL-3: TEL: 1533
12.02.2016
Non Compliance onProduct Notification forDumping of Earth oversoft and unstable bedconsists of over moisturewithout getting review ofalternative methodologyand material for groundimprovement and remedialmeasures adopting thematerial and methodologyas per MoRT&Hspecification at km254+360 to 254+520, Km254+660 to 254+700 &Km. 254+740 to 254+760
Pending
30. 44ICT: 600: TL:KL-3: TEL: 1549
24.02.2016
Non Compliance onProduct Notification forDumping and spreadingthe material over soft andunstable Embankmentfoundation in water loggedcondition at Km. 237+850to Km 237+900 and Km254+620 to Km 254+650with substandard material& methodology leading topavement failure
Pending
31. 45ICT: 600: TL:KL-3: TEL: 1565
04.03.2016
Non-compliance onproduct notification forconstructing Pipe culvertinstead of Box culvert asper GFC drawing at Km260+250
Pending
32. 46ICT: 600: TL:KL-3: TEL: 1566
05.03.2016
Non-compliance onproduct notification for notconstructing subgrade inlayers and that too evenwithout preparing andcompacting the OGL bedwhere subgrade rest onground at km 258+380 to258+700 and 261+080 to261+150 on LHS
Pending
33. 47ICT: 600: TL:KL-3: TEL: 1585
16.03.2016
Non Compliance onProduct Notification forlaying PCC over clayeystrata at Box culvert km.252+156 (RHS) of size6X3.2 m without verifyingSBC at founding level asper GFC drawing
Pending
44
34. 49ICT: 600: TL:KL-3: TEL: 1595
26.03.2016
Non compliance onproduct notification for notproviding 100mm diaweep holes in the RCClined drain in urban stretchfor pavement sub surfacedrainage
Pending
35. 50ICT: 600: TL:KL-3: TEL: 1597
26.03.2016
Non compliance onproduct notification for notproviding 'L' Section Kerbas per ConcessionAgreement and IE's finalcomments at the stretchKm. 262+000 to263+280(LHS) betweenMCW and Service road
Pending
36. 51ICT: 600: TL:KL-3: TEL: 1603
30.03.2016
Non compliance onproduct notification forlaying the pavement layersin the approaches of BoxCulvert at Km. 262+016,Km 262+295, Km262+636 and 262+942without the provision ofapproach slab
Pending
37. 52
ICT: 600: TL:KL-3: TEL: 1614
07.04.2016
Noncompliance on productnotification forconstructing theembankment in layers ofmore than 1 m thicknessfrom Km 246+500 to Km246+700(LHS)
Pending
38. 53
ICT: 600: TL:KL-3: TEL: 1615
07.04.2016
Noncompliance on productnotification for taking upof High Embankment fromKm 246+630 to Km247+000 forming approachto Major bridge at Km247+170 over Peechireservoir area havingclayey silty sub soil stratawithout conducting subsoil investigation andstability Analysis onFoundation andEmbankment.
Pending
39. 54
ICT: 600: TL:KL-3: TEL: 1619
19.04.2016
Non Compliance onproduct notification forconstructing the roadpavement withoutproviding the box culvertat Km242+961(RHS) asper the reviewed plan andprofile and GFC drawing
Pending
40. 55
ICT: 600: TL:KL-3: TEL: 1631
19.04.2016
Non-compliance onproduct notification fordumping of waste andunsuitable material over
Pending
45
waterlogged area fallingunder widening of maincarriageway from Km.255+800 to 256+060(RHS) without followingthe appropriate materialand methodology/groundimprovement measures asper MoRT&H Clause305.4.6 and withoutremoving the vegetationand top organic soil –posing pavement failure
41. 56
ICT: 600: TL:KL-3: TEL: 1632
20.04.2016
Non-compliance onproduct notification forconstruction ofembankment layers oversoft and unstable OGL bedin over moisture conditionhaving cohesive soil stratawithout adopting properground improvementtechnique between Km.252+900 to Km 253+160
Pending
42. 57
ICT: 600: TL:KL-3: TEL: 1643
30.04.2016
Non-compliance onproduct notification forproducing and laying theWMM mix on the projecthighway
a. From the materialof unapprovedsource
b. Withoutperforming mixdesign from thechanged source(Tunnel)
c. Withoutproducing thematerial fromWMM plant.
d. Without using thesensor paver forquality assurance.
Pending
43. 58
ICT: 600: TL:KL-3: TEL: 1648
07.05.2016
Non-compliance onproduct notification for notcarrying out backfilling inthe excavated trenches ofPipe culvert in layers withcompaction as perMORT&H clause 2907and QAP of the project atKm 245+656 - posingthreat to settlement ofpavement
Pending
46
44. 59
ICT: 600: TL:KL-3: TEL: 1662
11.05.2016
Non-compliance onproduct notification forcontinuing with theconstruction of pile cap/sub structure withoutconducting the routine PileLoad Tests on workingpile and balance one initialpile load Test on Test pileat Mannuthy Flyover Km262+707
Pending
45. 60
ICT: 600: TL:KL-3: TEL: 1667
12.05.2016
Non-compliance onproduct notification forcontinuing the use ofBitumen emulsion SS1 andRS1 for prime and Tackcoat in the ProjectHighway without sourceapproval and frequencyTest as per QAP of theproject
Pending
46. 61
ICT: 600: TL:KL-3: TEL: 1668
12.05.2016
Non Compliance onProduct Notification forusing the HYSD TMT barsin Major structure worksfrom the LOT No. 9 & 12without Quality Controltests as per QAP of theproject for Qualityassurance
Pending
47. 62
ICT: 600: TL:KL-3: TEL: 1669
12.05.2016
Non Compliance onProduct Notification fornot submitting theManufactured TestCertificate (MTC) onvarious batches of Dalmiaand Chettinad OPC 43grade cement used from01.01.2016 to 30.04.2016and not conducting ThirdTest for every 500 MT asper QAP of the Project forQuality assurance and notmaintaining the cementindent record
Pending
48. 63
ICT: 600: TL:KL-3: TEL: 1670
12.05.2016
Non Compliance onProduct Notification forproducing and using theconcrete in Majorstructures withoutinstalling Electronicprinter at the batchingplant @ Km 237+580(LHS) for qualityassurance
Pending
49. 64
ICT: 600: TL:KL-3: TEL: 1671
12.05.2016Non Compliance onProduct Notification fornot Submitting MTC and
Pending
47
Uniformity Test Reportfrom Third Party forQuality Assurance ofAdmixture Supplied UnderLOT No: 4 to 9
50. 65
ICT: 600: TL:KL-3: TEL: 1678
14.05.2016
Non Compliance onproduct notification forlaying the PCC for REwall foundation from Km261+580 to Km 261+715on LHS for PUP @261+830 without checkingfor SBC at founding levelas per the requirement ofsystem provider designdrawing
Pending
51. 66
ICT: 600: TL:KL-3: TEL: 1680
19.05.2016
Non-compliance onproduct notification fordumping and spreading ofsoil in one stroke for about1.50 m height forconstruction ofembankment over soft andunstable OGL bed in waterlogged condition havingcohesive soil strata withoutadopting proper materialand methodology betweenKm. 250+000 to Km250+100 (LHS)
Pending
52. 67
ICT: 600: TL:KL-3: TEL: 1686
24.05.2016
N Non compliance on ProductNotification for producingand laying the DBM Mixon the Project Highwaywithouta) Obtaining source
approval for thechanged source ofaggregate
b) Performing Mix designc) Submitting the
calibration report ofHMP (200 TPH) andrectifying the defectiveprinter
d) Conducting frequencytests on mix andmaterial-reg
Pending
48
53. 68
ICT: 600: TL:KL-3: TEL: 1687
24.05.2016
Non compliance onproduct notification for notmaintaining the inspectiondocuments / FrequencyTest reports conforming toMoRT&H and IRC SP 11for having executed thework with qualityassurance as per QAP ofthe project – reg
Pending
54. 69
ICT: 600: TL:KL-3: TEL: 1689
25.05.2016
Noncompliance on productnotification for failure ofconcrete cube strengthrepresenting the PSCgirders of MannuthyFlyover Km 262+707 andMajor Bridge Km247+170 - Need tovalidate/ prove thecompressive strength ofconcrete by Core Test asper IS 516
Pending
55. 70
ICT: 600: TL:KL-3: TEL: 1745
20.07.2016
Non compliance onproduct notification forlaying Raft concrete atBox culvert Km. 243+922LHS without Provision ofshear key and withoutraising RFI despite ourreminder for rectifying thedeficiency
Pending
56. 71
ICT: 600: TL:KL-3: TEL: 1823
27.08.2016
Non compliance onproduct notification for notconstructing the Head wallof pipe culvert below bedlevel @ Km 261+181 onRHS side as per GFCdrawing
Pending
57. 72
ICT: 600: TL:KL-3: TEL: 1839
31.08.2016
Non compliance onproduct notification for notconstructing the Retainingwall of Box Culvert belowbed level @ Km 259+733on LHS side as per GFCdrawing
Pending
58. 73
ICT: 600: TL:KL-3: TEL: 1844
1.09.2016
Non-compliance onproduct notification for notConstructing the top slabof Box Culvert withhaunch at Km. 249+992(RHS) – reg
Pending
49
59. 74
ICT: 600: TL:KL-3: TEL: 1872
09.09.2016
Noncompliance on productnotification for laying Raftconcrete at Box culvertKm. 249+892 (LHS)without Provision of shearkey to preventundermining of the raft infuture and bottom haunchdespite our reminder forrectifying the deficiency –reg.
Pending
60. 75
ICT: 600: TL:KL-3: TEL: 1875
10.09.2016
Non Compliance onProduct Notification forDumping and spreadingthe material over soft andunstable ground in waterlogged conditionsupporting subgrade atKm. 254+680 -740 (LHS)of service road withsubstandard material &methodology leading topavement failure– reg
Pending
61. 76ICT: 600: TL:KL-3: TEL: 1902
22.09.2016
NCR No. 76: NonCompliance on ProductNotification for boring ofpiling works in Pile No.5of Pier P1 (LHS) at MajorBridge Km. 247+170.455without completing thedesign Procedures – reg.
Pending
62. 77
ICT: 600: TL:KL-3: TEL: 1904
22.09.2016
Non-compliance onproduct notification forcontinuing withproduction and laying ofWMM mix on the projecthighwayWithout producing thematerial from WMM plant
b. Without using the sensor paver forquality assurancec. Without performing mix
design from thechanged source(Tunnel)-reg
Pending
50
63. 78
ICT: 600: TL:KL-3: TEL: 1910
24.09.2016
Non Compliance on
Product Notification for
laying of bed PCC for Box
culvert of Km. 255+964
without confirming the
design SBC as the soil at
founding level is silty
clayey in nature – reg
Pending
64. 79
ICT: 600: TL:KL-3: TEL: 1925
29.09.2016
Non Compliance on
Product Notification for
Dumping and spreading
the unsuitable material
over soft and unstable
OGL ground in water
logged condition at Km.
250+030 -300 (LHS) of
MCW with improper
methodology leading to
pavement failure – reg
Pending
65. 81
ICT: 600: TL:KL-3: TEL: 1967
17.10.2016
Non Complianceon ProductNotification forlaying the PCCover clayey strata atBox culvert km.255+581 withoutconfirming the SBCat founding level asper GFC drawing –reg.
Pending
66. 82
ICT: 600: TL:KL-3: TEL: 1969
19.10.2016
Non Complianceon ProductNotification forconcreting all theworking piles atPier P1 (LHS) ofMajor Bridge atKm. 247+170without completingthe design processand complying thereview commentsdespite rejecting theRFIs – reg.
Pending
51
67. 83
ICT: 600: TL:KL-3: TEL: 1990
25.10.2016
Non Compliance onProduct Notification forexecuting the pipe culvertat Km.249+466 on LHSside without submittingthe revised drawingincorporating the reviewcomments for approvaland despite rejecting theRFI for laying of PCC.
Pending
68. 84
ICT: 600: TL:KL-3: TEL: 2023
05.11.2016
Non Compliance onProduct Notification fordumping of unsuitablematerial over waterlogged area falling underwidening of maincarriageway from Km.256+060 to 256+230(RHS) without followingthe appropriate materialand methodology/groundimprovement measures asper MoRT&H Clause305.4.6 and withoutremoving the vegetationand top organic soil –posing pavement failure
Pending
69. 85
ICT: 600: TL:KL-3: TEL: 2024
07.11.2016
Non Compliance onProduct Notification forlaying the PCC in REWall foundation withoutcompacting to the desireddensity and ensuring thespecified unit weight offoundation soil propertiesbetween Km. 262+060 toKm. 262+150 (BHS)
Pending
70. 86
ICT: 600: TL:KL-3: TEL: 2055 16.11.2016
Non Compliance onProduct Notification fortaking up RE Wallfoundation work withoutfoundationsimprovement to achievedesign SBCrequirement asrecommended by thesystem provider fromKm. 261+930 to Km.262+060 (RHS)
Pending
52
71. 87
ICT: 600: TL:KL-3: TEL: 2059 18.11.2016
Non Compliance onProduct Notification forcontinue to using theBitumen emulsion forprime coat from theunknown source andwithout qualityassurance requirement
Pending
72. 88
ICT: 600: TL:KL-3: TEL: 2060 18.11.2016
Non Compliance onProduct Notification forconstructing the highembankment bydumping the materialfor more than 3 m in astroke and withoutforming a benching atthe widening of MCWfrom Km 244+100 to300 (LHS)
Pending
73. 89
ICT: 600: TL:KL-3: TEL: 2061 18.11.2016
Non Compliance onProduct Notification forusing the unsuitablematerial and adoptingimproper methodologyin the execution ofembankment work oversoft/ unstable groundfrom Km. 253+460 toKm. 253+540
Pending
74. 90
ICT: 600: TL:KL-3: TEL: 2066 21.11.2016
Noncompliance onproduct notification forcarrying out thebackfilling behind boxculvert wall in a strokefor about 2.50m heightwithout compacting inlayers and that toowithout providing filtermedia at Km. 259+035(LHS) - Posing threat tothe safety of road users
Pending
53
75. 91
ICT: 600: TL:KL-3: TEL: 2076 23.11.2016
Non Compliance onProduct notification forlaying of PCC over theclayey strata for BoxCulvert at Km. 255+458(RHS) withoutconfirming the SBC byjointly witnessing thetest
Pending
76. 92
ICT: 600: TL:KL-3: TEL: 2084 25.11.2016
Non Compliance onProduct notification forrepairing, stressing,grouting and launchingthe distressed PSCgirder pertaining toouter girder 1 of spanP13-A2 (RHS) over thespan P12-P13 (RHS) atMannuthy Flyover Km.262+707 without takinginto the comments of IE
Pending
54
Photo showing launching of girder at Mannuthy flyover
Photo showing Major Bridge Deck Slab reinforcement work