Period: 3/26/20 - 4/01/20

Community High School District 99

Master Facility Plan Implementation

Wight Construction Services2500 North Frontage RoadDarien, IL 60561

Weekly Construction Progress Report

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase B - Fine Arts Addition

360° Pictures: 1st Floor Alley Art Gallery 1st Floor 2nd Floor Classroom East Entrance

• MEP/Fire Alarm/Fire Sprinkler trades continue to work on rough-in and light fixtures.

• Ductwork insulation in progress.

• Continue framing for Demo Kitchen, in-wall insulation and started drywall on the 1st floor.

• Continue with curtain wall installation; currently working on pressure plates for cw frames.

• Completed steel stair installation.

• Poured the concrete topping on 2nd floor and stair treads and landings.

• Installed scaffold for brick installation.

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase B - Bleachers & Squad Rooms

• Dant Clayton continue working on visitor bleachers ramps and stairs.

• JWI mobilized back to DGS and will be starting the installation of risers/treads for bleachers.

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase C - Auditorium

• Completed removal/salvage of auditorium light fixtures and delivered them to DGN.

• Continued working on gas piping relocation in band hallway through ceramics room.

• Continued abatement of existing areas in preparation for new Phase C work. GBTA has beensupervising and monitoring work onsite.

• Continued working on Fire Alarm & Fire Sprinkler work to retrofit existing areas. Completed thenew Fire Department Connection.

• Started investigation of existing piping in Auditorium in preparation for selective demolition.

• Moved all remaining items in auditorium to storage trailer in preparation for demolition.

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase C - Learning Commons

• Compass continued layout of gridlines for the commons.

• Kane County Excavating mobilized to the site and started excavation for site utilities and newfoundations.

• Werner Nugent currently working on new underground sanitary line in new commons.

Community High School District 99

Master Facility Plan Implementation

Downers Grove North High School

Phase B - Gym, Kitchen, Alley, Multipurpose,and Gymnastics Loft Addition

360° Pictures: Main Gym Kitchen Multi-Purpose Room Gymnastics Room

• Overhead MEP rough in continues throughout the upper & lower levels as well as the gym area.

• Roofing is progressing and scheduled to be complete this week.

• Interior masonry walls continue to progress throughout kitchen/ servery area.

• Cold form metal framing in alley and 2nd floor rooms is near completion. Received drywalldelivery for 2nd floor.

• Re-routed dual temp piping in basement that was in conflict with stair landing leaving the gymarea.

• Continue to make punch throughs for windows in alley as well as 1st floor opening from southcorridor into alley.

• Cooler/ Freezers have been field measured and are slated for install in a few weeks.

Community High School District 99

Master Facility Plan Implementation

Downers Grove North High School

Phase B - Bleachers & Squad Rooms

• Home bleachers - Geo-piers have been completed and passed load test. Began excavating andpouring bleacher structure foundations.

• Visitor Bleacher – Excavating and pouring for bleacher additions.

Community High School District 99

Master Facility Plan Implementation

Downers Grove North High School

Phase C - Cafeteria, Culinary Arts, Commons,and Southeast Addition

• Continuing environmental abatement for spring break work and also completing abatementpreviously scheduled for summer.

• Working on installing duct runs in classrooms on 3rd floor.

• Continue to work on logistics plan with school on potential areas that could be worked on whileschool is closed.

360° Pictures: Servery Commons