appendix 1 - allerdale 1 … · 49 piccadilly manchester m1 2ap . allerdale borough council interim...
TRANSCRIPT
Appendix 1
Issue 1.4
Date: 31 October 2014
GATEWAY 4 REPORT
New Swimming Pool and Leisure
Centre
for
Allerdale Borough Council
Pick Everard Piccadilly House 49 Piccadilly Manchester M1 2AP
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
IN19-8 Rev A
PI CK EV ER A R D
Document History
Issue Date Comment Author Checked
1.4 31.10.14 Gateway 4 Report PD/AL AD
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
IN19-8 Rev A
PI CK EV ER A R D
CONTENTS
1.0 EXECUTIVE SUMMARY .................................................................................................................. 1
2.0 PURPOSE OF REPORT ..................................................................................................................... 2
3.0 PROJECT BRIEF .............................................................................................................................. 2
4.0 SCAPE GATEWAY APPROVAL PROCESS ..................................................................................... 2
5.0 DESIGN .......................................................................................................................................... 4
6.0 PROGRAMME ................................................................................................................................ 6
7.0 RISK AND COMPENSATION EVENTS ............................................................................................ 7
8.0 COMMERCIAL AND TECHNICAL ASSURANCE PROCESS ........................................................... 9
9.0 COST AND PROCUREMENT........................................................................................................... 9
10.0 VALUE ENGINEERING ................................................................................................................. 10
11.0 LOCAL SPEND .............................................................................................................................. 11
12.0 VALUE FOR MONEY .................................................................................................................... 12
13.0 COMPLIANCE WITH THE SCAPE FRAMEWORK .......................................................................... 12
14.0 HEALTH AND SAFETY ................................................................................................................... 12
15.0 NEXT STEPS ................................................................................................................................... 12
16.0 RECOMMENDATION ................................................................................................................... 13
APPENDIX A: RCE/WD GATEWAY 4 REPORT 14
APPENDIX B: RISK REGISTER 15
APPENDIX C: LOCAL SPEND 16
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
1
IN19-8 Rev A
PI CK EV ER AR D
1.0 EXECUTIVE SUMMARY
This report provides an overview on the Scape process undertaken in collaboration with
Robertson Construction England (RCE) and Willmott Dixon (WD), in support of the
approval required from the Council Executive on 12 November 2014 to proceed with
signature of the Delivery Agreement to allow RCE/WD to commence building works to
deliver the Workington Leisure Centre.
The current detailed design submitted at Scape Gateway 4 is generally compliant or
exceeds the scope of facilities approved by the Council Executive on 13 November
2013. The key non-compliance items are noted as follows:
No Jacuzzi is provided within the Health Suite; (following discussion with the
Operator at Gateway 2);
The Fitness Suite includes 90no. station’s not 100;
Three 3G 5 aside pens have been provided in place of an artificial full size 3G
pitch, due to the commitment given by Lakes College;
Vending is provided in the Café area, rather than a Café.
The Building Regulations approval stage is sufficient to allow works to commence on to
site.
Planning consent was approved on 22 July 2014 with 39 conditions associated with the
project. Once Planning Department approval is obtained to the pre-commencement
conditions, works can commence on site from a planning perspective.
The programme identifies a commencement date on 8 December 2014, with
Completion on 21 March 2016. The overall construction period is 67 weeks.
The Council risks are considered minimal and within control to determine and mitigate
prior to contract award.
The Local Spend percentages achieved are only based on progress so far. RCE/WD
have developed a strategy to continue to improve local spend throughout the
construction works, that will be measured as a KPI during the contract and at
Completion.
The proposed Contract Price of £10,369,946 plus the additional sum for Fixtures, Fittings
and Equipment at £60,297 (total Contract Price of £10,430,243) is considered to be
value for money for the Council.
Construction works can now proceed from a Health and safety perspective onto site in
compliance with Construction (Design and Management) Regulations 2007.
Pick Everard can conclude that the RCE/WD bid submitted on 15 October 2014
represents value for money and is compliant with the Scape Framework The Next
Steps, Pick Everard recommend that the Council can proceed to Scape Gateway 5;
Mobilisation / Construction.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
2
IN19-8 Rev A
PI CK EV ER AR D
2.0 PURPOSE OF REPORT
The purpose of this report is to set out the progress made since approval was obtained
from the Council Executive on 13 November 2013 to proceed with the New Swimming
Pool and Sports Centre.
This report provides an overview on the Scape process undertaken in collaboration with
RCE/WD, and seeks approval from the Council Executive on 12 November 2014 to
proceed with signature of the Delivery Agreement to allow RCE/WD to commence
building works to deliver the Workington Leisure Centre. (Scape Gateway 5; Mobilisation
/ Construction).
3.0 PROJECT BRIEF
At the Council Executive on 13 November 2013, members’ approval was obtained to
move forward with the procurement of a final design with costs to deliver a new leisure
centre in Workington, located on land adjacent to Brow Top Car Park and the car park
itself as the preferred site. Approval was also obtained to use the Scape Framework.
The proposed facility mix included in item 5.10 of the Council Executive minutes for the
new centre was confirmed as follows:
A 25m x 8 lane pool with small pool for teaching / alternative uses and spectator
seating (this would be a regional facility not currently available in Cumbria)
A spa suite (sauna/ steam room/ Jacuzzi)
Wet and dry changing facilities
4 court sports hall (including soft play area if practical)
Climbing wall
Fitness suite (100 stations) and 2 activity studios (flexible use)
Spinning studio
Artificial full size 3G pitch(es)
2 squash courts
Café
Administration / office provision
At the Council Executive meeting, the proposed facility mix was approved,
supplemented by a Scape Gateway 2 Report (RIBA Stage 1 – Preparation and Brief)
prepared by RCE/WD, dated 25 October 2013.
4.0 SCAPE GATEWAY APPROVAL PROCESS
A Project Order was executed on 6 December 2013 between Willmott Dixon and the
Council for a cost for £582,667.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
3
IN19-8 Rev A
PI CK EV ER AR D
The Project Order enabled RCE/WD to develop a client brief working with GT Architects
and other design consultants to progress the design through the Scape Gateway
Process.
Brief
A Client Brief was prepared by RCE/WD that was signed off by the Corporate Director
on 08.01.14.
Background Survey Information
The Project Order also enabled RCE/WD to procure specialist surveys to inform both the
detailed design and later supplement the planning application for the site. This
included but is not limited to the following examples:
Ground Investigation Report;
Bridge Site Investigation Report;
Flood Risk Assessment;
Topographical Survey;
Ecology reports;
Arboricultural Impact Assessment;
Heritage Statement; and
Traffic Impact Assessment.
Scape Gateway Design process
The Scape Framework has a process that needs to be followed for the design
development of projects. From approval of the Brief, the design is progressively
developed in collaboration with the Council, seeking Scape Gateway design stage
approvals as follows:
13.11.13: Council Executive approval to progress the centre;
08.01.14: Scape Gateway 2 approval obtained to proceed to the next stage;
At the recommendation of Pick Everard an additional Scape gateway stage was
introduced to enable the Project Board to approve the Concept Design (RIBA Stage 2 –
Concept Design). The reason for introducing this additional stage was to ensure that
the design was being developed in accordance with the approved Client Brief within
the overall affordability envelope.
17.02.14: Scape Gateway 3.1 approval obtained for additional interim Gateway
(RIBA Stage 2 – Concept Design) by the Corporate Director to proceed to the
formal Scape Gateway 3.
01.05.14: Project Board approval obtained for the formal Scape Gateway 3 –
Pre-Construction Develop Design. (RIBA Stage 3 – Developed Design) to
proceed to the formal Scape Gateway 4.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
4
IN19-8 Rev A
PI CK EV ER AR D
The Council also considered and approved planning permission on 22 July 2014 that
was subsequently issued on 17 September 2014.
Council Executive approval is now being sought for Scape Gateway 4 – Pre-
Construction Detailed Design (RIBA Stage 4 – Technical Design) to proceed to Scape
Gateway 5.
Scape Gateway 5 is Construction / Mobilisation (RIBA Stage – Construction).
5.0 DESIGN
The design for the new Workington Leisure Centre at the completion of Scape Gateway
4 closely resembles the Project Brief and complies with Sport England and ASA
guidance, subject to limited derogation that has been applied with consideration to
efficiency and affordability.
The design delivers a modern leisure centre that will contribute to the improved health
of the local and regional community, located in a prime position to benefit the town
centre economy.
The design has also been considered in the context of the site location, with scale and
massing appropriate to the centre’s location.
A fundamental consideration of the design has been the focus around accessibility of
the whole facility, both internally and externally. A high priority has been given to
making the building as accessible as possible to all taking into account the special
needs of people with disabilities, children, ethnic/cultural diversity, women and men as
well as the varying levels of sporting ability.
Following extensive consideration and case study visits, the Council approved the
utilisation of Myrtha stainless steel pool tanks to both the main competition pool and
learner pool as the most suitable and cost efficient pool tank solutions based on
numerous factors. The learner pool also has a moveable floor down to 1.6m to maximise
programme opportunity and use.
The new leisure centre will be sustainable and responsible to environmental issues in
terms of the use of energy and sustainable resources together with considerations to
the control of pollution.
Use of environmentally friendly, sustainable building services and building materials has
been maximised and are also recyclable where possible.
Workington Leisure Centre will be required to achieve a BREEAM ‘Very Good’ rating.
External elevations are to utilise high quality, low maintenance finishes and be
sympathetic to the surrounding environment. Finishes are robust and suitable for
location and use.
The detailed design includes the following leisure centre provision to comply with the
Project Brief as follows:
Site preparation, including earth movement and remediation works.
Raising the site levels to the centre and three 3G 5 aside pens to 7.2m in
accordance with the Flood Risk Assessment.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
5
IN19-8 Rev A
PI CK EV ER AR D
8 lane competition swimming pool 25010mm (+10/0) x 17005mm finished with an
allowance for future installation of competition touch pads to a depth falling
from 1000mm to 2000mm and rising back up to 1800mm including a set of easy
access steps and a raised end to the deep end.
186 no. spectator seating gallery to first floor pool hall balcony including fixed
seats plus 4no. disabled viewing positions.
Learner pool 15100mm x 10000mm with moveable floor down to a 1600mm
depth with moveable easy access steps.
Heath suite with sauna and steam room.
Changing village with 2no. Group Change rooms and a separate Dry Change
including toilets and shower facilities.
2no. passenger lifts.
2no. squash courts with spectator seating for 32no. squash spectators plus 2no.
disabled bays
Flexible ‘four court badminton’ sports hall and equipment store and mat store,
for a variety of sports uses.
Climbing wall.
Changing Places room.
Entrance lobby with waiting area / vending area including reception desk.
Fitness suite for 90no. Individual workstations, free weights and stretching and
core work.
Two Dance Studio’s with shared storage.
One Spinning Studio with shared storage.
Dry Male and Dry Female changing rooms, including toilets and showers.
Male and female toilets including accessible toilets, with changing facilities and
a shower for users with disabilities.
Filtration plant room, plant rooms and a sunken external plant deck on the roof.
Ancillary space including store rooms, circulation, stair cores and means of
escape.
8no. new disabled car parking spaces, with 7no. in the existing top car park
Service access road, coach lay-by, drop-off area, service yard, paths and
access bridge.
Three 3G 5 aside football pens inclusive of perimeter fencing, access / egress,
and external lighting.
External works, landscaping and external lighting.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
6
IN19-8 Rev A
PI CK EV ER AR D
Protection and enhancement of the existing ecology including to Soapery Beck,
complying with the requirements of Natural England.
Design compliance with Project Brief
The current detailed design submitted at Scape Gateway 4 is generally compliant or
exceeds the scope of facilities approved by the Council Executive on 13 November
2013. The key non-compliance items are noted as follows:
No Jacuzzi is provided within the Health Suite; (following discussion with the
Operator at Gateway 2);
The Fitness Suite includes 90no. station’s not 100;
Three 3G 5 aside pens have been provided in place of an artificial full size 3G
pitch, due to the commitment given by Lakes College;
Vending is provided in the Café area, rather than a Café.
Secured by Design
GT Architects have held discussions with the local Police Architectural Liaison Officer,
who attended a presentation by WD/RCW/WD with the design team on 2 October
2014. The design has been progressed with aspiration to the principles of Secured by
Design, rather than seeking formal certification.
Building Regulations
Meetings have been held with the Council’s Building Control Department during the
design development process. A staged building regulation application was approved
on 28 February 2014. The approval stage is sufficient to allow works to commence on to
site.
Planning Consent
Planning consent was approved on 22 July 2014 with 39 conditions associated with the
project. Information has been submitted by RCE/WD to discharge 8 pre-
commencement conditions for which RCE/WD is awaiting approval from the planning
department that the pre-commencement conditions have been satisfied. Once this
approval is obtained, works can commence on site from a planning perspective.
6.0 PROGRAMME
A Construction Programme has been submitted by RCE/WD as part of the Contractors
Proposals.
The programme identifies mobilisation on 26 November 2014 with commencement of
construction works on 8 December 2014, Completion is on 21 March 2016, based on an
overall construction programme duration of 62 weeks, plus 5 weeks included for
Christmas 2014, Christmas 2015 and statutory holidays during the construction period.
The overall construction period is 67 weeks.
There will also be an additional 2 to 4 week fit out and familiarisation period by Carlisle
Leisure Limited prior to opening the pool and centre to the public.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
7
IN19-8 Rev A
PI CK EV ER AR D
The Construction Programme has been interrogated as part of a technical query
review process by Pick Everard. The overall construction period is acceptable, although
enhancement has been suggested to include activities such as the detailed testing
and commissioning regime to Myrtha pool tanks, with additional milestones to monitor
progress and extend the commissioning period.
It has also been suggested that the External Works, 3G Pitch Works and Electric Sub-
station activities are brought forward.
It has been agreed that whilst a significant number of activities are on the critical path
that RCE/WD develop the programme to remove the pool off the critical path due to
the incorporation of the Myrtha pool tanks.
RCE/WD has accepted the comments made by Pick Everard and has committed to
review and develop the programme for consideration of ‘Acceptance’ by Pick Everard
as the Project Manager representing the Council.
Pick Everard would advise that the Construction Programme is realistic, fair but
challenging, given the requirement to raise site levels and that it was not viable to
progress an enabling works package, given the additional financial commitment
required by the Council, prior to receiving a fixed price, lump sum offer at completion
of Scape Gateway 4.
The key milestones that need to be achieved are as follows:
Activity
Date
Commencement of mobilisation works 26.11.14
Commencement of construction Works 08.12.14
Milestone: Structural Frame complete 16.07.15
Milestone: Full Weather tightness achieved 16.10.15
Milestone: Mains water supply on achieved 04.12.15
Milestone: Main Gas supply on 04.12.15
Milestone: Power on achieved 07.12.15
Milestone: Lifts Operational achieved 11.12.15
Completion 21.03.16
In collaboration with RCE, Willmott Dixon have also undertaken a review of the
programme and advised that they generally consider the programme acceptable.
The commencement date has been aligned with the Council Executive Meeting on 12
November 2014, allowing a 10 day Standstill period prior to contract signature, subject
to approval to proceed to Scape Gateway 5.
7.0 RISK AND COMPENSATION EVENTS
A risk register has been developed in collaboration with the Council, RCE/WD and Pick
Everard and an updated risk register has been submitted as part of the Contractors
Proposals.
RCE have provided a commentary on the top five (5) risks as Section 3.0 of the Scape
Gateway 4 Report. Refer Appendix A.
These risks have now been further reviewed and developed at a risk workshop as part
of the commercial and technical review process undertaken by Pick Everard from the 2
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
8
IN19-8 Rev A
PI CK EV ER AR D
October 2014, and the results of the workshop are recorded in the latest risk register
dated 13 October 2014, Refer to Appendix B.
The risks attributed to the council are:
Risk ID
Risk Cost £
PR7 Sport England legal charge 3,000
SPR07 Building Insurance 16,000
These risks are considered minimal and within the Councils control to determine and
mitigate prior to contract award.
The NEC Engineering and Construction Contract is recommended for use on the Scape
Framework and Option A: Priced contract with activity schedule is to be used. RCE/WD
has submitted a fixed cost, lump sum that will be subject to the conditions of the
Contract.
Risks will continue to be raised, managed or mitigated during construction works at
Scape Gateway 5 in accordance with the Contract. Under Clause 16, the Contractor
and the Project Manager give an early warning by notifying the other as soon as either
becomes aware of any matter which could:
Increase the total of the Prices (post contract changes to the lump sum fixed
price);
Delay Completion;
Delay meeting a Key Date; or
Impair the performance of the works in use.
The Early Warning process will be followed and the process will be Project Managed by
Pick Everard at Risk Reduction Meetings.
There are 19no. compensation events that can be notified by either the Project
Manager or Contractor under Clause 61 of the NEC3 Contract. There is a defined
process to deal with compensation events with each having a prescribed period.
Under Clause 65, once compensation events are implemented, there will be a change
to either or the Prices, the Completion Date and or the Key Dates.
The following are compensation events:
Clause 60.1
Compensation Events (summarised)
(1) Instruction changing the Works Information.
(2) The Employer does not allow access to the Site.
(3) The Employer does not provide something as the programme.
(4) Instruction to start or stop the works.
(5) The Employer or Others do not work within times shown, conditions
stated, work on the site not stated in the Works Information.
(6) The Project Manager or Supervisor does not reply in the period required.
(7) The Project Manager gives an instruction for dealing with an object of
value or historical interest.
(8) The Project Manager or Supervisor changes a decision.
(9) The Project Manager withholds acceptance.
(10) The Supervisor instructs the Contractor to search for a Defect
(11) A test or inspection causes unnecessary delay.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
9
IN19-8 Rev A
PI CK EV ER AR D
(12) The Contractor encounters physical conditions.
(13) A weather measurement is recorded less frequently than 10 years.
(14) An event which is an Employer’s risk stated in this contract.
(15) The Project Manager takes over part of the works.
(16) The Employer does not provide materials, facilities and samples for tests.
(17) The Project Manager notifies the correction to an assumption.
(18) A breach of contract by the Employer.
(19) A event which stops the Contractor completing the works.
Pick Everard utilise an online Project Management tool that is web based to assist
administration and compliance by the parties to the Contract.
8.0 COMMERCIAL AND TECHNICAL ASSURANCE PROCESS
Following the RCE/WD Gateway 4 submission, Pick Everard undertook a commercial
and technical assurance review.
The commercial review has been undertaken to ensure that the submission represents
value for money and is compliant.
The technical review has been undertaken to ensure that all the Councils requirements
have been incorporated into the design and programme.
9.0 COST AND PROCUREMENT
For the background to the submissions noted below please refer to section 5.0, Target
Cost, of the RCE/WD Gateway 4 Report attached as Appendix A.
Current Financial Position
RCE/WD has submitted two financial proposals at the end of the Gateway 4 period as
detailed in table 1 below:
Table 1
Item Total £ Duration (weeks)
Budget - 4 Court Sports England
Compliant
10,362,702 N/A
Financial Proposal - 2 September
2014
10,536,801 67
Financial Proposal - 15 October
2014
10,369,946 67
The revised financial submission on the 15 October 2014 was the result of the
commercial and technical queries raised during the review of the 2 September 20104
submission and agreements made at the commercial meeting held on the 2 October
2014, where RCE/WD committed to better their package returns with the aim for a
minimum 3 (three) returns to comply with Scape (refer below).
During the period from the 15 October 2014 all commercial and technical queries were
closed with RCE/WD and as a result of this process an additional sum for Fixtures, Fittings
and Equipment was agreed at £60,297 giving a revised total and Contract Price of
£10,430,243.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
10
IN19-8 Rev A
PI CK EV ER AR D
Trade Package Returns
The revised submission of the 15 October 14 demonstrated the trade packages returns
as summarised in table 2 below. The full details of these packages are held by the
Council and PE and have not been published due to commercial sensitivity.
Table 2
Packages Value (£) Number Percentage
by Package
Percentage
by Value
Three or more
Trade packages
returned
7,783,171 27 43 88
Less than three
trade packages
returned
1,059,488. 36 57 12
Total
8,842,659 63 100 100
Pick Everard have undertaken a complete review and full audit of all the packages
returned and have issued and closed in excess of two hundred and sixty commercial
queries.
The framework agreement commits to market testing 100% of the packages with at
least 3 quotations on every trade package. RCE/WD has obtained 88% by trade
package by value and Scape has acknowledged that 3 quotations are not always
practical. We would therefore confirm the packages with less than 3 returns, with the
majority bar one package value of less than one hundred thousand pounds, contain
rates and sums which are considered competitive and current market rates.
RCE/WD have in recognition of the above short fall in the package returns offered an
adjustment item of £192,893 described as “Target subcontract buying/pricing to meet
clients budget” this adjustment include offered 2.5% Main Contractors Discounts and
accounts for a percentage betterment to the trade packages of 2.2%.
We would therefore conclude the trade package quotation exercise to be Framework
compliant.
Schedule of Cost Components People and Plant
With respect to the Schedule of Cost Components People and Plant RCE/WD have
followed the typical Project C templates, however the extended Assistant Building
Manager to the full project duration was considered by the Project Team to be to the
benefit of the project and to be within the parameters of the Framework.
10.0 VALUE ENGINEERING
During the Gateway process a number of value engineering proposals have been
evaluated by the team and agreed as appropriate for the project without
compromising the design intent
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
11
IN19-8 Rev A
PI CK EV ER AR D
11.0 LOCAL SPEND
Local Spend is a key issue and extremely important to the Council to ensure the actual
construction works benefits the local economy and also the regional Cumbrian
economy.
The revised submission of the 15 October 14 demonstrated a local spend in table 3
below based on location only as detailed in Appendix D:
Table 3
Description
Framework %
Required at
Completion
Currently
Achieved %
by Package
Value
Assessed %
Package,
People &
Betterment
Total value in 20 mile radius 40 28 50
Total value in 40 mile radius 75 29 51
The local spend commitment in the Framework Agreement commits to a local spend of
40% within a 20 mile radius and a 75% local spend within 40 mile radius of the project.
However Scape has confirmed these targets are over the framework nationally and
therefore RCE/WD will be challenged to improve under the Local Spend KPI
requirements of the project.
The Local Spend percentages achieved are only based on progress so far. RCE/WD
have developed a strategy to continue to improve local spend throughout the
construction works.
The assessment by PE to forecast the local spend (last column of table 3 above) takes
into account the packages as the 15 October 2014 offer, expected site staff based in
Workington, forecast seven more packages been let to local contractors within the 40
mile radius and a forecast of other packages using local merchants and labour.
RCE/WD proposes to better the above figures with the following approach:
RCE/WD will target more of the local Cumbrian contractors who returned a
tender and try and negotiate them to a more competitive level;
Use skilled and unskilled local labour as a priority;
RCE/WD will re-target local Cumbrian contractors who declined to tender;
Promote the use of local contractors and material suppliers with all
subcontractors
RCE/WD have also employed a local Community Engagement Officer.
It is important to note that the local spend percentage is measured and confirmed at
the end of the project. Also the inclusion of the pool tank which is manufactured in
Europe distorts the figures above and could improve the assessed percentages to 56%
(20 mile radius) and 57% (40 mile radius) respectively.
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
12
IN19-8 Rev A
PI CK EV ER AR D
12.0 VALUE FOR MONEY
Historic cost data/bench marking data for leisure centres are held primarily on the BCIS
(Building Cost Information Service) cost data base and the published data held by
Sports England on affordable sports centre and pool models.
Reviewing the Sports England affordable sports centre data and comparing like for like
elements the elemental cost totals in the revised financial submission on the 15 October
2014 generally compare favourably. This has been further verified by Sports England’s
independent cost consultant (Abacus Cost Management) during the Sport England
funding proposal taking into account variances for site abnormal, higher end envelope
treatments and the mechanical and electrical works.
The project expressed per metre square of GIFA (gross internal floor area) based on the
RCE/WD 15 October 2014 submission is £ 2,312/m2 of GIFA. This compared with the
Sports England affordable sports centre model uplifted to current day value and
reflecting the schemes GIFA (4,512m2) gives a cost of £2,245/m2 of GIFA.
BCIS cost data also supports the RCE/WD figure of £ 2,312/m2 to be competitive and
correct and therefore we can conclude the proposed contract value of £10,430,243 to
be value for money for the Council.
13.0 COMPLIANCE WITH THE SCAPE FRAMEWORK
Pick Everard can confirm that the RCE submission of the 15 October 2014 is compliant
with the Scape Framework,
14.0 HEALTH AND SAFETY
Pick Everard’s were appointed by the council as CDM co-ordinator (CDM-C) to monitor
compliance of duties in respect to the Client, Principal Contractor (RCE/WD) and
Designers to in accordance with the Construction (Design and Management)
Regulations 2007.
The CDM-C has and reviewed Designer Risk Assessments and coordinated required
notifications to the Health and Safety Executive.
The CDM-C has attended design meetings and tracked queries via a Pre-Construction
Information Tracker that enabled the CDM-C to prepare a required Pre-Construction
Information required under the regulations.
The Construction Phase Plan was subsequently approved by the CDM-C on 6 August
2014 to allow construction works to commence onto site.
15.0 NEXT STEPS
To close the Scape Gateway 4 stage the following actions need to be addressed by
the project team in order to sign a Delivery Agreement and proceed to Scape
Gateway 5, Construction Mobilisation:
Table 6
No. Item Action
1 Close out all technical queries RCE/WD
2 Close out all commercial Queries RCE/WD
Allerdale Borough Council Interim Gateway 4 Report
Workington Leisure Centre
13
IN19-8 Rev A
PI CK EV ER AR D
3 Formalise Appointments RCE/WD
4 Finalise Works Information Team
5 Ongoing Value Engineering Team
6 Continue liaison with Planning – concluded, subject to
Council approval on Pre-commencement Conditions
Council
7 Finalise Risk Register Team
8 Finalise Programme Team
9 KPI Review At Scape Gateway 4 Team
10 Finalise Contract Data Part 1 and part 2 ABC/RCE/
WD
11 Finalise the Professional Service Contract ABC/RCE/
WD
12 Sign Memorandum of Agreement – Work in Progress
ABC/RCE/
WD
The proposal is that the documents noted above would need to be agreed and
amended by 7 November 2014. The full set of proposed Contract Documents would
then have to be reissued to Pick Everard to double check actions have been
addressed satisfactorily during the proposed standstill period to allow signature of the
Delivery Agreement on or around 26 November 2014.
16.0 RECOMMENDATION
Pick Everard can conclude that the RCE/WD bid submitted on 15 October 2014
represents value for money and is compliant with the Scape Framework for the Next
Steps, Pick Everard recommend that the Council can proceed to Scape Gateway 5;
Mobilisation / Construction.
Appendix A
17.1 Scape Gateway 4 Report
SCAPE FRAMEWORK 3
Workington Leisure Centre
Workington Leisure Centre Page 1 of 19 Contractors Proposals
Scape Framework 3
Workington Leisure Centre
Gateway 4 Report
Detailed Design & Construction Mobilisation
(RIBA Stage 4 )
September 2014
Workington Leisure Centre Page 2 of 19 Contractors Proposals
Revision History
Rev 00 – 30/07/14 – Initial Draft
Rev 01 – 14/08/14 – Updated to incorporate comment and feedback from project team
Rev 02 – 18/08/14 – Updated to reflect Interim Cost Report
Rev 03 – 20/08/14 – Updated to reflect revised Risk Register
Rev 04 – 26/08/14 – Final Version
Author Position Approved Position Date
Chris Price Contracts
Manager
Andy Mcleod Managing
Director
27/08/14
Workington Leisure Centre Page 3 of 19 Contractors Proposals
Executive Summary
The Workington Leisure Centre scheme is being procured through the SCAPE 3 Framework with Robertson CE
Ltd being the contractor allocated by Allerdale Borough Council.
As noted within the Gateway 3 report dated April 2014, the Framework is a partnership agreement between
Allerdale Borough Council and Robertson CE Ltd. The partnership is working very well and yielding good
results for the project.
The following report summaries progress up to Gateway 4, Pre Construction Detailed Design & Construction
Mobilisation (RIBA Stage 4). This stage develops the design from the Gateway 3 report, Planning submission
and Building Control application. During the Gateway 4 period tender information and tender packages have
been developed to allow market testing to be undertaken and a target cost developed.
The principal design team consultants have been appointed for the project. The Architect being GT Architects,
with WYG providing Multi Discipline Engineering design services. Both parties were chosen through a design
competition and have integrated well into the project team.
In addition to the primary design team members, specialist consultants have been appointed to the project, in
particular SKM Jacobs (Transport Consultant), WYG (Planning Consultant), Sub Surface (Site Investigation and
Flood Risk) and Devin Consulting (Aquatic Consultants). All parties have integrated into the project team and
have performed well.
The layouts developed during Gateway 3 have been further developed into the detailed Contractors Proposals
contained within this report. Throughout this gateway a number of consultations and design reviews have
been undertaken with Allerdale Borough Council, Carlisle Leisure, Sport England, other statutory consultees
and the general public. Where practicable the comments received have been incorporated into the design
proposals.
Furthermore during this gateway and in consultation with all members of the project team, Allerdale Borough
Council have advised that they wish to utilise a stainless steel pool tank (Myrtha System). The Contractors
Proposals contained within this report reflect this requirement.
Throughout the Gateway 4 period, the project team have been continually reviewing the layout to maximise
the usable area and reduce wasted space, for example the incorporation of the climbing wall within the main
reception area saves on additional floor space but also provides a USP for the Leisure Centre.
Build ability has also been considered throughout this process and as part of the costing exercise with
enquires sent out to the market place for all packages and key supply chain partners engaged to provide
costing, programme and technical advice.
Furthermore, Building Control have been consulted on a continuous basis to ensure that all design proposals
meet the requirements of the Building Regulations and that all necessary pre commencement conditions have
been met.
Planning permission for the project was granted on 22nd
July 2014, with 39 conditions associated with the
project, 8 number conditions are required to be discharged prior to the commencement of Gateway 5.
During the design development period a number of risk reduction workshops have been undertaken with
Allerdale Borough Council and the project team to review the risk register and to implement a number of
strategies for mitigating the risks associated with the project.
In addition to the aforementioned risk reduction workshops, specific client workshops have been undertaken.
These workshops assessed the clients and end users principles, requirements and the ethos for the project to
ensure they are being included in the design. These workshops also covered the social and environmental
principles for the project.
Key performance Indicators have been set and will be assessed following sign off of this gateway.
The project is progressing to budget and to the agreed timescales and is presented at Gateway 4 (RIBA Stage
4) for approval and sign off.
Workington Leisure Centre Page 4 of 19 Contractors Proposals
Contents
1.0 Statutory Consents
1.1 Planning Permission
1.2 Building Control
1.3 Utilities
2.0 Design
2.1 Contractors Proposals
3.0 Risk Register
3.1 Commentary & Top 5 Risks
4.0 KPI Review
5.0 Target Cost
5.1 Tender Report
5.1.1 Budget
5.1.2 Proposed Tender Lists
5.1.3 Procurement Strategy
5.1.4 Tender Evaluation Process
5.1.5 Cost saving Exercise
5.1.6 Final Agreed Target Costs
5.1.7 Option A Proposal
6.0 Contract Data
6.1 Summary of Status
7.0 Programme
7.1 Construction Programme
7.2 Schedule of Key Dates
Workington Leisure Centre Page 5 of 19 Contractors Proposals
1.0 Statutory Consents
1.1 Planning Permission
Allerdale Borough Council confirmed acceptance of the Gateway 3 proposals in March 2014, with design
freeze achieved on 27th
March 2014. The planning application was submitted on 14th
April 2014.
Following the initial planning submission a letter of non support was received from the Environmental Agency.
The Environment Agency raised concerns relating to the flood risk associated with the site. Further flood risk
assessment work and modelling was undertaken and a revised planning application was submitted on 11th
June 2014.
Planning approval for the project was obtained on 22nd
July 2014, and the current planning status is as follows;
Planning Reference – 2 / 2014 / 0271
Planning Officer – Claire Chambers
Date of Approval – 22nd
July 2014
Conditions – 39 conditions are associated with the planning permission for the project, 8 number of which are
pre commencement conditions.
A copy of the Planning Permission notice, associated conditions and discharge matrix is contained within
section 17.10 of the Contract Data.
1.2 Building Control
Throughout the Gateway 4 period regular meetings have been undertaken with Allerdale Borough Council,
Building Control. The purpose of these meetings was to review the design proposals and ensure compliance
with the Building Regulations. Where comments have been received from Building Control they have been
incorporated into the design proposals and re submitted for approval.
The current Building Control status is as follows;
Building Control Reference – FPAP / 2014 / 0154
Building Control Officer – Robert Doran
Compliance Achieved – Stage Approval Obtained (B1 – B5 & G1)
Ongoing submissions will be made to Building Control prior to works commencing onsite and as works
progress to ensure compliance with the Building Regulations.
A copy of the Building Control notices are contained within section 18.1 of the Contract Data.
Workington Leisure Centre Page 6 of 19 Contractors Proposals
1.3 Utilities
Applications for all permanent supplies have been made to the relevant utility provider during the Gateway 4
period. All costs associated with the permanent site supplies have been identified on the cost plan for
inclusion within the final project cost.
It can be noted that the expiry dates on the main utility quotes will be reached prior to works commencing
onsite, Robertson confirm that discussions have been ongoing with the relevant utility provider and that
revised quotations have been obtained.
Quotations have also been obtained for the temporary site supplies. These works will be progressed prior to
commencing onsite upon signing of the Delivery Agreement.
A utility matrix has been established and is shown below.
Workington Leisure Centre Page 7 of 19 Contractors Proposals
2.0 Design
As noted within the executive summary of this report the design has been developed throughout the Gateway
4 period to enable full market testing to be undertaken and planning permission obtained.
Design team meetings and design review with project stakeholders have been held on a 2 weekly basis during
the period, with all comments fed back into the finalised design proposals.
2.1 Contractors Proposals
The finalised design proposals for the project are contained within the Works Specification and Drawings,
which is contained within section 17 of the Contract Data. The Works Specification and Drawings have been
subdivided into the following elements;
• 17.1 Gateway 4 Report
• 17.2 Schedule of Accommodation
• 17.3 Architectural Drawings and Specifications
• 17.4 Civil and Structural Engineering Drawings and Specifications
• 17.5 Building Services Engineering Drawings and Specifications
• 17.6 Aquatic Consultant – Filtration Plant Drawings and Specification
• 17.7 Aquatic Consultant – Moveable Floor Drawings and Specification
• 17.8 External Works / Landscaping Drawings and Specification
• 17.9 3G Five a Side Pitches, Fencing and Floodlighting
• 17.10 Planning Information – Planning Consent and Planning Condition Matrix
• 17.11 Building Control – Approval Notices
• 17.12 Acoustic Design Strategy Report
• 17.13 BREEAM Status / Credit Report
• 17.14 Room Data Sheets
• 17.15 FF&E Schedule
• 17.16 Design and Access Statement
• 17.17 Secured by Design
• 17.18 Design Life Strategy
• 17.19 Crime Prevention Plan
• 17.20 Disabled Access Statement
• 17.21 Acoustic Survey
• 17.22 Pool Timing System
Any subsequent changes to the aforementioned design proposals will be governed by the change control
process contained within the Project Execution Plan (PEP).
Workington Leisure Centre Page 8 of 19 Contractors Proposals
3.0 Risk Register
3.1 Commentary and Top 5 risks
A project Risk Register has been developed for the project and actions are being taken to minimise risk as the
design progresses.
The risk register is subject to continual review by the project team.
A number of risk review workshops have been held during the Gateway 4 process and the Risk Register has
been updated to reflect the outcome of each workshop.
During the market testing process the Risk Register was reviewed and specific package risks have been
incorporated that account for deficiencies or exclusions in the tenders received.
Whilst formulating the target cost, the risks identified within the aforementioned Risk Register were assessed
in order to further quantify them in terms of time and cost on a most likely and worst case basis. Upon
completion of this exercise, the sum of the most likely estimates was utilised to ascertain the level of overall
risk.
The project is to be delivered via NEC3 option A and the Risk Register has been developed in accordance with
the requirements of NEC3 form of contract with each risk allocated to either Robertson or Allerdale Borough
Council.
The current Risk Register which will be included within the contract documentation is contained within section
20 of the Contract Data.
A summary of the 5 key risks for the project are identified below:
Workington Leisure Centre
RISK Owner Value Comments
Abortive costs
incurred for bridge
design if FEC is
constructed
Allerdale £30,000 Bridge location identified onsite plan,
awaiting confirmation of Masterplan
proposals – Refer to SPR 8 on Risk Register
Agreement of Mineral
Rights, Restrictive
Covenants and Access
Rights to site
Allerdale £25,000 Legal agreement in place with Lonsdale
Estates, awaiting execution of contracts –
Refer to LEG 5 on Risk Register
Client unable to obtain
Insurance due to flood
risk
Allerdale £20,000 Monies identified are for potential uplift in
premium. Currently awaiting feedback from
Insurance provider – Refer to SPR 7 on Risk
Register
Diversion /
Strengthening of
existing Gas Main
Robertson £20,000 Awaiting feedback from Northern Gas
Network on specific requirements
Protection works to
United Utilities
detention tank
Robertson £20,000 Awaiting feedback from United Utilities on
specific requirements
Workington Leisure Centre Page 9 of 19 Contractors Proposals
4.0 KPI Review
There are a number of KPI’s which are measured throughout the Scape process and they fall into one of the
following 4 categories:
• Time & Cost
• Quality
• Social
• Environmental
At the Gateway 4 stage the main KPI’s that are measured relate to Time & Cost Predictability for the
Preconstruction element of the project. The KPI targets are set at Feasibility stage (Gateway 2) and are
reviewed on a monthly basis throughout the design development stages (Gateways 3 & 4).
Updates are contained in following screenshots from the KPI Reporting System - MiProject:
Workington Leisure Centre Page 10 of 19 Contractors Proposals
Workington Leisure Centre Page 11 of 19 Contractors Proposals
Workington Leisure Centre Page 12 of 19 Contractors Proposals
As the project progresses and enters the construction phase the following KPI’s will be activated and monthly
reporting against these elements will commence;
KPI Category KPI’s
Time & Cost Time Predictability - Construction
Cost Predictability – Construction
Defects
Quality Client Satisfaction - Product
Client Satisfaction - Service
Client Satisfaction – Value for money
Client Satisfaction – Whole life performance
Client Satisfaction – Settlement of final account
Health & Safety
Social Employment & Skills Plan
Fair Payment
Considerate Constructor
Local Labour
Local Spend
SME Engagement
SME Spend
Environmental Energy use – Process
Waste diverted from landfill
Workington Leisure Centre Page 13 of 19 Contractors Proposals
5 .0 Target Cost
5.1 Tender Report
5.1.1 Budget
As identified within the Gateway 3 report, dated 17th
April 2014, the Project Budget was developed as part of
the design development process (RIBA Stages 2 & 3), with a detailed cost plan prepared by Robertson. The
project budget at this stage was set at;
Gateway 3 Report
£9,916,702 based upon a GIFA of
4527m2
Excluding Client Direct Fees and Costs
Full copies of the Gateway 3 Cost Plan Summary the project are contained within the Gateway 3 report, dated
17th
April 2014.
Notwithstanding the above, the targeted budget advised by Allerdale Borough Council is currently set at
£9,916,702.
5.1.2 Proposed Tender Lists
Prior to commencing the market testing exercise, a detailed list of work packages and proposed supply chain
partners for each package was prepared by Robertson.
The proposed list of supply chain partners was subsequently issued to all members of the project team for
comment and review. Upon receipt of comments from all parties the finalised tender list was agreed and
tender documents for each work package was issued in line with the requirements of the Pre Construction
Programme.
A copy of the finalised work package and supply chain list is contained within section 1 of the Contract Data.
5.1.3 Procurement Strategy
Robertson have prepared a full set of Bills of Quantities / Pricing Schedules in house for all of the designed
information.
Tender lists were subsequently prepared with the Scape requirement of a minimum of three enquiries being
met or exceeded in all instances and with additional emphasis being placed on the requirement to satisfy the
further obligations in respect of local spend. A separate commentary in respect of the local spend criteria is
contained within the Employment Skills Plan, a copy of which is contained within section 21 of the Contract
Data.
The following Subcontract Packages have been prepared for pricing purposes:
Air Test Bill
Automatic Doors Bill
Balustrade & Handrailing Bill
Bird Proofing Bill
Blinds Bill
Brick & Blockwork Bill
Ceramic Tiling Bill
Cubicles, Vanity Units, IPS, Lockers Bill
Climbing Wall Bill
Decoration Bill
Excavation/Earthworks Bill
External Doors Bill
Workington Leisure Centre Page 14 of 19 Contractors Proposals
Fencing & Gates Bill
Fire Protection Bill
FF&E Bill
Foundations Bill
General Joinery Bill
Glazed Screens Bill
Ground Floor Slab Bill
Hard Landscaping Bill
Internal Doors Bill
Ironmongery Bill
Lift Bill
Louvres Bill
Mechanical, Electrical, AGD, Sanitaryware Plan & Spec
Metaldecking Bill
Metalwork Bill
Mirrors Bill
Plastered/Rendered coatings Bill
Pool Filtration Plan & Spec
Pool Tank Plan & Spec
Pre-cast lift shaft Bill
Pre-cast stairs Bill
Purpose made joinery Bill
Rainscreen & Composite cladding Bill
Sauna & Steam Room Plan & Spec
Scaffolding Schedule
Screed Bill
Signage Bill
Single Ply Roofing Bill
Soft Floor Finishes Bill
Soft Landscaping Bill
Sports Pitches Plan & Spec
Sto Render Bill
Street Furniture Bill
Structural Steel Frame Plan & Spec
Stud Partitions Bill
Surfacing Bill
Suspended Ceilings Bill
Syphonic Drainage Bill
Timber Floors Bill
Windows & Curtain Walling Bill
Upon receipt of the tender information from GT Architects and WYG, a bill of quantities was prepared and a
tender enquiry was issued to the Supply Chain for tender purposes together with the relevant Design
Drawings, Specifications, Programme, Site Information, Scope of Works Documents and other Subcontract
Information so as to allow the various packages to be competitively priced.
Workington Leisure Centre Page 15 of 19 Contractors Proposals
5.1.4 Tender Evaluation Process
Copies of all the subcontractor tender returns will be issued to Pick Everard on 2nd September 2014, in order
for them to identify any queries and carry out their own checking / auditing process.
In conjunction with Pick Everard, the tender returns were evaluated on a package by package basis during
which the optimum subcontract price was selected in terms of competitiveness and compliance. During the
same process any clarifications and adjustments for errors and / or omissions were also addressed.
Upon completion of the individual Sub-Contract Package Reviews and Assessments, Main Contractor
Preliminaries were addressed and agreed in conjunction with Pick Everard and the Risk Registers were jointly
updated to reflect the known matters / risks.
Consultant Fees and Survey Costs were agreed in with Pick Everard and after the application of the 1.75% On-
Cost for Willmott Dixon / RNE Overheads and Profit and the 0.5% Scape Fee initial Target Cost values were
determined.
5.1.5 Cost Saving Exercise
As identified within the Gateway 3 Report dated 17th
April 2014, the client budget is currently set at
£9,916,702. Throughout the Gateway 4 period and as the design has developed a number of additions have
been requested by both the Client and Sport England, details of which are shown below;
Items requested by Sport England - £471,000
Items requested by the Client - £335,000
Items requested by Carlisle Leisure - £25,600
Value Engineering Proposals not Achieved in Period - £105,000
Following a detailed review by all parties a Value Engineering exercise has been undertaken and a number of
savings identified. Details of the proposed Value Engineering List and associated costs are contained within
Section 1, Priced Activity Schedule.
5.1.6 Final Agreed Target Costs
A final Target costs will be issued to Allerdale Borough Council on 2nd
September 2014 with the final
agreement of the Target Costs to be made with Allerdale Borough Council on or before 8th
October 2014.
The agreed Target Cost figures are contained within the priced activity schedule contained within section 1 of
the Contract Data.
It should be noted that the figures contained within our Target Cost are based upon the Contract being
awarded on the basis of NEC3 Option A.
5.1.7 Option A Proposal
As identified within 3.1 of this report a detailed risk register has been developed for the project with a
number of risks have been identified with associated mitigation measures. Each risk has been allocated to
either Robertson or Allerdale Borough Council, with both a maximum risk cost and factored risk cost
identified.
The adjustment to the overall risk allowance is shown below;
Robertson Allerdale Borough Council Total Risk Allowance
£43,056 (Factored Cost) £59,000 (Factored Cost) £102,056(Factored Cost)
Workington Leisure Centre Page 16 of 19 Contractors Proposals
Taking the above factored risks into account a maximum risk allowance and design contingency has been
taken forward within the cost plan. The total cost of the project based upon an Option A proposal has been
adjusted accordingly as identified within the Option A Cost Summary Page and Priced Activity Schedule is
contained within section of the Contract Data.
Workington Leisure Centre Page 17 of 19 Contractors Proposals
6.0 Contract Data
6.1 Summary of status
Throughout the Gateway 4 period a number meetings have been undertaken with Allerdale Borough Council
and Pick Everard to develop and review the contract data and appendices in line with the requirements of the
Pre Construction Programme.
The contract data has been prepared in line with the NEC3 option A proposal, dated 2nd
September 2014 and
the following documents;
Workington Leisure Centre Page 18 of 19 Contractors Proposals
Workington Leisure Centre Page 19 of 19 Contractors Proposals
7.0 Programme
7.1 Key Dates
As the design has been developed during the Gateway 4 period, Robertson have continually developed the
Construction Programme with the design team and principle supply chain partners.
Presently, the Pre Construction Programme 61097/ Pre Con/ Rev P, dated 23rd
July 2014 identifies that
construction works will commence onsite on 3rd
November 2014, based upon receipt of the Delivery
Agreement on 20th
October 2014.
As identified on the aforementioned Pre Construction Programme a number of key tasks are required to be
completed to allow works to commence, these key tasks are identified below;
• Conclusion of cost savings exercise (Dependent upon results of market testing) *
• Review of outstanding design comments and revision of works information to reflect savings outcome
of cost savings exercise *
• Agreement of contract and signing of Delivery Agreement
• Discharge of all pre commencement planning conditions
• Approval of Gateway 4 report and Contractors Proposals
• Submission of utility applications for site establishment
• Uplifting of design proposals to construction status
• Finalisation of site logistics and site establishment requirements
• Procurement of initial subcontractors and subcontract design packages
*Action to be determined based upon acceptance of Option A cost proposal of 2nd
September 2014.
Upon completion of the aforementioned key tasks, construction works will commence. The following key
dates have been identified on Construction Programme 61097 / CP /GW4 / Final dated 15th
August 2014.
Workington Leisure Centre Commence Complete
Site Establishment 10/11/14 21/11/14
Enabling Works 03/11/14 06/03/15
Substructure Works 15/12/14 02/07/15
Superstructure Works 12/01/15 03/11/15
Weather tight (Full) 11/09/15
Fit Out Works 12/06/15 15/02/16
External Works 10/08/15 15/02/16
Project Complete 15/02/16
7.2 Programme
A copy of the aforementioned Construction Programme 61097 / CP /GW4 / Final dated 15th
August 2014 is
contained within section 21 of the Contract Data.
Appendix B
Project Risk Profile
User Guide & Notes
Introduction.
User Guide
Step 1 Enter the Project Title and Number on the "Report" tab
Step 2Step 2.1Step 2.2Step 2.3Step 2.4Step 2.5Step 2.6
1 (rare) : may only occur in exceptional circumstances.2 (unlikely) : Could occur at some time.3 (possible) : Might occur.4 (likely) : Will probably occur.5 (Almost certain) : Can be expected to occur.
Step 2.71 (None)2 (Low)3 (Moderate)4 (High)5 (Severe)
Step 2.8Step 2.9Step 2.10Step 2.11
Column J = Factored cost. Cost proportioned to Risk Score, with cost expressed in 1000's. Column K = Risk Category, based on Risk Score, High (20 > 25), Med (15 > 20), Low ( 0 > 15) The Risk is defined as High when the Impact is score as 5 irrespective of the Likelihood rating or risk
Column H = Risk Score - Likelihood x Impact
Column D = Describe possible effect.Column E = Describe Mitigation Action
Column I = Potential maximum cost expressed in 1000's
The Bid Manager is responsible for completing and maintaining the Risk Management Register during the Preconstruction Phase.
The residual value owner by Willmott Dixon must be carried forward and entered into the pricing document.
It is recommend that a formal Risk Meeting is arranged immediately after the project launch meeting and at regular intervals thereafter. Every team member, consultants, client and stake holders should contribute to the risk evaluation.
During the Production Phase the Construction Manager shall be responsible for updating the Risk Management Register
Column G = Impact or consequence to programme or cost. - rated between 1(low) and 5 (high)
Enter known risks for each of the Risk categories and complete as example shown belowColumn A = Risk item No : The Grey Button allow the item to be sorted by item number.Column B = Selection of applicable items selecting the "Y" using the dropdown box.Column C = Risk description
Column F = Likelihood - rated between 1(low) and 5 (high) as expected frequency.
Com
plete 11 risk W
orksheets
Enter Project Details
Risk Meeting
Appoint Manager
Step 2.12Step 2.13Step 2.14Step 2.15
Step 3.1Step 3.2
Step 4.1Step 4.2Step 4.3
Step 5
Step 6
General Notes
Column L = Risk Owner (liability of cost)
Risk is defined as High when the Impact is score as 5 irrespective of the Likelihood rating or risk score.
Column M = Organisation/person who is responsible for mitigation action.Column N = Action target close date.Column O = Notes
Select the "Create Summary" button to generate a collection of High Category RisksHigh, High/Med or All risks may be displayed by using the Grey Button.
The Risks may be sorted by "Item" or "Risk Cat" by selecting the button which are available above the appropriate column.
A summary of the risks is created by using the "Summary" worksheet
Risk Tracker worksheet is to be completed at agreed milestones/meeting.
Note. To refresh the Summary, use the "clear " button followed by the "Create Summary" button.
Complete each of the 11 worksheets
Note. Any apparent incorrect formatting may be corrected by selecting the "Format" button
Printing : A "Print All Sheet" function is available below (please do not print until the "Summary" has been created.
Return to the "Report" worksheet. This analyses the risk by Score and Cost allocation.
If a Macro Visual Basic error message appears when creating the summary : select "End", followed by selecting the "Clear Data" and "Create Summary" buttons.
This displays a Risk Management profile.
Progress Tracker
Report
Create Summary
Project Risk Profile
£0.00 £0.00
ItemSelect
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk
Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk CatRisk
Owner
Risk
Manager
Target
Close
Date
Notes
Total All Risks
Project : Workington Leisure Centre
High Risk Summary13-Oct-14
Project No. 61097
Format
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile Date
Project
Project No.
Max Risk Factored WD Client Other
FF 1.FF Financial and Funding 143 £0.0 £0.0 £0.0 £0.0 £0.0 4 2 4
CC 2.CC Contract Conditions 99 £0.0 £0.0 £0.0 £0.0 £0.0 2 3 2
LEG3.LEG Legal - Easements / Party Walls etc 107 £22,000.0 £7,040.0 £7,040.0 £0.0 £0.0 3 1 6
DES4.DES Design (inc CDP) 109 £25,519.0 £1,020.8 £1,020.8 £0.0 £0.0 1 2 13
PL 5.PL Planning 125 £15,000.0 £8,800.0 £8,800.0 £0.0 £0.0 3 1 7
SA 6.SA Statutory Authorities 85 £40,000.0 £25,600.0 £25,600.0 £0.0 £0.0 0 4 2
ENV7.EV Environmental 88 £500.0 £80.0 £80.0 £0.0 £0.0 2 2 2
HS 8.HS Health & Safety 41 £0.0 £0.0 £0.0 £0.0 £0.0 0 1 3
QL 9.QL Quality 69 £0.0 £0.0 £0.0 £0.0 £0.0 0 0 8
PR 10.PR Programme 110 £5,000.0 £3,000.0 £0.0 £3,000.0 £0.0 1 5 1
SPR11.SPR Specific Project Risks 132 £20,000.0 £16,000.0 £0.0 £16,000.0 £0.0 3 4 1
Total > 1,108 £128,019.0 £61,540.8 £42,540.8 £19,000.0 £0.0 19 25 49
Workington Leisure Centre
13 October 2014
HIGH MED
Precon Bid Manager Chris Price
Ian Johnstone
LOW
61097
Data SummaryContents
Risk
ScoreRisk TitleItem
Total Risk Cost (1000's)
Construction Manager
20%
27%53%
HIGH MED LOW
£10,000.0
£15,000.0
£20,000.0
£25,000.0
£30,000.0
£35,000.0
£40,000.0
£45,000.0
Val
ue
Risk Value (1000's) WD Client Other
Risk Proportion
0
20
40
60
80
100
120
140
160
Fin
anci
al a
nd F
undi
ng
Con
trac
t Con
ditio
ns
Lega
l -
Eas
emen
ts /
Par
ty W
alls
etc
Des
ign
(inc
CD
P)
Pla
nnin
g
Sta
tuto
ry A
utho
ritie
s
Env
ironm
enta
l
Hea
lth &
Saf
ety
Qua
lity
Pro
gram
me
Spe
cific
Pro
ject
Ris
ks
Risk Score
£0.0
£5,000.0
£10,000.0
WD Client Other
Risk Owner
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Project
Project No.
Risk
Score
Risk
Score
Risk
Score13/10/2014 30/04/2014 06/03/2014
FF 1 Financial and Funding 143 77 77
CC 2 Contract Conditions 99 61 61
LEG 3 Legal - Easements / Party Walls etc 107 78 78
DES 4 Design (inc CDP) 109 132 132
PL 5 Planning 125 144 144
SA 6 Statutory Authorities 85 101 101
ENV 7 Environmental 88 109 109
HS 8 Health & Safety 41 8 8
QL 9 Quality 69 34 34
61097
Workington Leisure Centre
Risk ItemItem
PR 10 Programme 110 40 40
SPR 11 Specific Project Risks 132 99 99
Total > 1,108 883 883
0
200
400
600
800
1,000
1,200
06/03/2014
09/03/2014
12/03/2014
15/03/2014
18/03/2014
21/03/2014
24/03/2014
27/03/2014
30/03/2014
02/04/2014
05/04/2014
08/04/2014
11/04/2014
14/04/2014
17/04/2014
20/04/2014
23/04/2014
26/04/2014
29/04/2014
02/05/2014
05/05/2014
08/05/2014
11/05/2014
14/05/2014
17/05/2014
20/05/2014
23/05/2014
26/05/2014
29/05/2014
01/06/2014
04/06/2014
07/06/2014
10/06/2014
13/06/2014
16/06/2014
19/06/2014
22/06/2014
25/06/2014
28/06/2014
01/07/2014
04/07/2014
07/07/2014
10/07/2014
13/07/2014
16/07/2014
19/07/2014
22/07/2014
25/07/201428/07/2014
31/07/2014
03/08/2014
06/08/2014
09/08/2014
12/08/2014
15/08/2014
18/08/2014
21/08/2014
24/08/2014
27/08/2014
30/08/2014
02/09/2014
05/09/2014
08/09/2014
11/09/2014
14/09/2014
17/09/2014
20/09/2014
23/09/2014
26/09/2014
29/09/2014
02/10/2014
05/10/2014
08/10/2014
11/10/2014
Series1
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
FF1
Insufficient design fees included
within Project Order / Cost Plan.
Increased costs and failure to
deliver the design to meet the
requirements of the project.
Additional fees incurred to WYG
for bridge design and the
appointment of Devin Consulting.
Determine how overspend on
Project Order will be addressed.
5 4 20 £0.0 £0.0 HIGH WD
Costs to be included within final cost
plan within design fees
FF2
Client budget & brief remain
unfixed in relation to 2 court / 4
court sports hall
Abortive design, increased costs
incurred and delays to
programme
Client decision required no later
than 17th March 20144 4 16 £0.0 £0.0 MED Client
Instruction received 28/03/14
FF3Inflation & Increased material
costs
Increased costs make scheme
unaffordable
Identify monies to offset costs
during development &
construction period
4 4 16 £0.0 £0.0 MED WDAllowance to be made within cost
plan as contract is GMP
FF4
Failure to secure Sport England
funding
4 court Sports Hall becomes
unaffordable plus omission of
fundamental Sport England
items and impact to programme
Early engagement with potential
funders such as Sport England.
Abortive fee costs have been
ascertained for the fundamental
Sport England items. (2nd
drainage channel, 2nd lift and
moveable floor to the learner
pool)
4 5 20 £0.0 £0.0 HIGH Client
Expression of Interest to Sport
England was successful. Stage 2
meeting held with Sport England on
15.07.14. Sport England decision will
not be known until review by Sport
England Board on 15.09.14.
FF5VAT not included within cost plan Scheme becomes unaffordable Allerdale BC have confirmed that
VAT can be reclaimed.2 3 6 £0.0 £0.0 LOW Client
Allerdale BC to reclaim VAT.
FF6Agreement and signing of PSA Delay to payments and potential
impact upon commencement
date
Review wording and resolve
issues with legal team 3 4 12 £0.0 £0.0 LOW ClientScape have advised Pick Everard that
Agreement can not be changed.
FF7
Inclusion of 2nd drainage
channel, 2nd lift and moveable
floor as fundamental Sport
England items.
Omission of fundamental Sport
England items on 15th
September 2014 if Allerdale BC
is not successful.
Abortive fee cost established.
2 2 4 £0.0 £0.0 LOW Client
Costs contained within cost plan as a
measured works item
Council instruct full size 3G pitch Impact on business case / future capable of being sub-divided into Full size 3G pitch omitted from
Project No. 61097
Project : Workington Leisure Centre
Financial and Funding
13-Oct-14
FF8Council instruct full size 3G pitch
in July 14
Impact on business case / future
revenue
capable of being sub-divided into
3G 5 aside pitches. 3 3 9 £0.0 £0.0 LOW ClientFull size 3G pitch omitted from
scheme
FF9
Council instruct full size 3G pitch
in July 14
Increased cost to raise the site
levels of a full size 3G pitch to
7.2m
GT Architects have verified that
full size 3G pitch will fit.
However, it will impact on the
open space in front of the leisure
centre.
5 4 20 £0.0 £0.0 HIGH Client
Full size 3G pitch omitted from
scheme
FF10
Sport England Funding (Lottery
Heritage Fund)
It must be demonstrated that
the formal Council Executive
wish to progress the new leisure
centre on 08.10.14 to enable the
Lottery Funding Agreement to be
put in place. This may delay
actual contract signature by the
council.
Council to consider and advise.
5 4 20 £0.0 £0.0 HIGH Client
FF11 0 £0.0
FF12 0 £0.0
FF13 0 £0.0
FF14 0 £0.0
FF15 0 £0.0
FF16 0 £0.0
FF17 0 £0.0
FF18 0 £0.0
FF19 0 £0.0
FF20 0 £0.0
FF21 0 £0.0
FF22 0 £0.0
FF23 0 £0.0
FF24 0 £0.0
FF25 0 £0.0
FF26 0 £0.0
FF27 0 £0.0
FF28 0 £0.0
FF29 0 £0.0
FF30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
CC1
Provision of Performance Bond Increased costs associated with
provision of performance bond
Identify bond costs and offer
PCG in lieu of bond. Pick Everard
to determine if PCG is
acceptable.
4 4 16 £0.0 £0.0 MED WD
Offer of PCG accepted, no Bond to be
provided
CC2
Design team do not accept terms
& conditions of appointment /
contract
Increased costs and delays to
Pre Construction Programme
Scape have now advised that
Contract terms can not be
changed.4 4 16 £0.0 £0.0 MED WD
Design team have confirmed
acceptance of terms within PSA.
CC3
Interface with Carlisle Leisure
(Operator)
Potential contract amendments
to incorporate interface &
requirements
Carlisle Leisure are being
consulted in Scape Gateway 4. 2 3 6 £0.0 £0.0 LOW Client
Manufacturer list has been developed
& agreed with Carlisle Leisure
CC4
Exclusion of Flood Risk by
Contractor / Design Team
Unable to agree contract terms
and sign Delivery Agreement.
Engagement with EA to ascertain
flood modelling data. Ensure
appropriate due diligence.
Finished floor level now
increased from 7.05m to 7.2m
2 3 6 £0.0 £0.0 LOW Client
Agreed site level contained with
revised FRA and subsquent planning
approval
CC5
Failure to agree drafting of
Delivery Agreement
Increased costs and delays to
Pre Construction Programme
Prepare early draft of the
Delivery Agreement for review
by all parties and ensure early
agreement
5 3 15 £0.0 £0.0 MED WD
Delivery Agreement to be based
upon standard drafting with no
additional Z clauses
CC6
Failure to agree drafting of
Consultant Appointment
documents
Increased costs and delays to
Pre Construction Programme
Prepare early draft of the
Delivery Agreement for review
by all parties and ensure early
agreement
5 4 20 £0.0 £0.0 HIGH WD
PSA in place and replaced with
Delivery Agreement
CC7
Timescale to conclude the
Robertson PSC Contract
Delay signature of the consultant
appointment, warranties and the
Delivery Agreement.
Additional legal support obtained
to Allerdale BC Solicitor.5 4 20 £0.0 £0.0 HIGH Client
Delivery Agrreement will replace PSA
CC8 0 £0.0
CC9 0 £0.0
Project No. 61097
Project : Workington Leisure Centre
Contract Conditions
13-Oct-14
CC9 0 £0.0
CC10 0 £0.0
CC11 0 £0.0
CC12 0 £0.0
CC13 0 £0.0
CC14 0 £0.0
CC15 0 £0.0
CC16 0 £0.0
CC17 0 £0.0
CC18 0 £0.0
CC19 0 £0.0
CC20 0 £0.0
CC21 0 £0.0
CC22 0 £0.0
CC23 0 £0.0
CC24 0 £0.0
CC25 0 £0.0
CC26 0 £0.0
CC27 0 £0.0
CC28 0 £0.0
CC29 0 £0.0
CC30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
LEG1
Change in Building Regulations /
Statutory Compliance
Increased costs and amended
design to meet changes in
legislation (Part L)
Undertake initial discussions with
Building Control & Planning to
ascertain changes.2 1 2 £0.0 £0.0 LOW WD
Application made on 25th Feb 2014.
Building Control have confirmed
acceptance of 2010 regulations.
LEG2
Red Line Boundary & Legal Title
to be confirmed
Increased costs and potential
delays in order to resolve legal
issues
Confirmation of RLB & Title
required by client 2 1 2 £0.0 £0.0 LOW Client
All title information now obtained
LEG3
Construction access via rear
track
Alternative access to be via
Griffin Street
Allerdale BC agreement
established with Lonsdale
Estates to use the rear access
road.
4 2 8 £22,000.0 £7,040.0 LOW WD
LEG4
Building & Contents Insurance Problems obtaining building
insurance due to site being
located within a flood zone
Early discussions required with
Insurance provider, possible anti
flooding measures required4 5 20 £0.0 £0.0 HIGH Client
Closed: moved to Specific Project
Risks (SPR 07)
LEG5
Agreement of Mineral Rights and
restrictive covenants, and access
rights to site
Increased costs and potential
delays in order to resolve legal
issues
Early engagement of legal team
and discussions with rights
holder3 2 6 £0.0 £0.0 LOW Client
Agreement has been reached with
Lonsdale Estates, agreement is still
to be executed
LEG6
Site becomes subject to village
green status
Increased costs and potential
delays in order to resolve legal
issues
Early review by legal team to
ensure no village green status is
applicable3 2 6 £0.0 £0.0 LOW Client
No village green issues identified,
planning permission obtained
LEG7
28th February 1992: Easement
(gas supply pipe)
Robertson need WYG to verify if
the Easement relates to the cast
iron pipe or Yellow pipe
discovered during investigation
works to establish the exact
location of the cast iron pipe.
WYG also need to verify what
the cast iron pipe and Yellow
pipe serves with the utility
WYG need to urgently determine
what the cast iron pipe is and if
it is redundant. WYG need to
urgently verify what the Yellow
pipe is and its location.
Early engagement of legal team
with County Council and Utility
Company to ascertain ownership
4 5 20 £0.0 £0.0 HIGH WD
Trial holes have indicated that the
pipe is outside the site boundary
Project No. 61097
Project : Workington Leisure Centre
Legal - Easements / Party Walls etc
13-Oct-14
pipe serves with the utility
companies.
Company to ascertain ownership
and potential diversion works.
LEG8
Public Right OF Way (PROW) Delays to programme and
increased costs associated with
PROW
SKM have established that the
PROW was not closed and is
incorrectly identified. The PROW
should have been diverted along
the top of the embankment by
Cumbria County Council. SKM
have advised Cumbria County
Council. Robertson to pursue
update.
4 2 8 £0.0 £0.0 LOW Client
No public right of ways issues
identified, planning permission
obtained
LEG9
Establish if what the cast iron
pipe is and whether it is active or
not which runs along the site
boundary.
Delays to programme and
increased costs associated with
PROW
WYG to review the utility plans
4 5 20 £0.0 £0.0 HIGH WD
Further investigation works required
to ascertain ownership of the pipe
LEG10
Legal requirement relating to
security of land through the Land
Registry by Sport England for 25
years if the bid application is
successful
Impose legal charge on the
leisure centre.
Programme delay if this needs to
be in place prior to contract
signature.
Council to consider and advise.
5 3 15 £0.0 £0.0 MED Client
Legal charge to be made, further
information required.
LEG11 0 £0.0
LEG12 0 £0.0
LEG13 0 £0.0
LEG14 0 £0.0
LEG15 0 £0.0
LEG16 0 £0.0
LEG17 0 £0.0
LEG18 0 £0.0
LEG19 0 £0.0
LEG20 0 £0.0
LEG21 0 £0.0
LEG22 0 £0.0
LEG23 0 £0.0
LEG24 0 £0.0
LEG25 0 £0.0
LEG27
LEG28
FM-PC-07 Issue 1 Effective Date 01/01/2012
LEG29
LEG30
FM-PC-07 Issue 1 Effective Date 01/01/2012FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk
Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
DES1
Pool / Filtration Design Failure Increased costs, design issues
and programme delays
Devin consulting have been
appointed to deliver a design,
tender and site monitoring role. 1 1 1 £25,519.0 £1,020.8 LOW WD
Detailed performance specification
prepared by Aquatic Consultation and
full turnkey sub contract package
established
DES2Specialist design interface and
design development
Increased costs, design issues
and programme delays
Dealt with via detailed design
development 2 2 4 £0.0 £0.0 LOW WD
DES3
Design does not meet the clients
brief
Potential political & financial
implications to client and
abortive design costs
Early establishment of
affordability and design brief.
Regular reviews and updates
required with client
1 4 4 £0.0 £0.0 LOW WD
Regular dialogue ongoing with the
client. Frozen design now obtained
DES4
Flood Risk & Establishment of
site datum level
Abortive design and delays to
programme due to additional EA
flood modelling
Detailed discussions held
between the EA and FRA.
Finished floor slab level set at
7.200m.
2 5 10 £0.0 £0.0 HIGH WD
Site datum level established via
revised FRA
DES5Delays in obtaining updated flood
modelling data from EA
Increased costs, abortive design
and programme delays
Engage with EA and request
updated model information 1 4 4 £0.0 £0.0 LOW WDDiscussion held with the EA. Flood
data and approach now received.
DES6
Delays in confirming 2 court / 4
court sports hall option
Increased costs, abortive design
and programme delays
Ongoing discussions with client.
Design freeze required no later
than 17th March 14.
1 3 3 £0.0 £0.0 LOW Client
Instruction received 28/03/14 and
Frozen design agreed
DES7
Access road and embankment
interface
Abortive design and delays to
programme due to additional
design requirements
Relocate access road and
building footprint to avoid
embankment works1 3 3 £0.0 £0.0 LOW WD
Considered by GT Architects in the
design and building location.
DES8
Additional credits to achieve
BREEAM rating
BREEAM Very Good instructed.
Increased cost and design works
to achieve rating
undertake detailed pre
assessment to ascertain
requirement2 3 6 £0.0 £0.0 LOW WD
Initial Pre Assessment indicates
61.8% and achieves Very Good
DES9
Additional seating and design
requirement to meet
Increased costs and delays to
programme
Instruction issued to Robertson
to increase the spectator seating 5 1 5 £0.0 £0.0 LOW WD
Additional seating costed within
measured works items
Project No. 61097
Project : Workington Leisure Centre
Design (inc CDP)
13-Oct-14
DES9requirement to meet
requirements of sport England
and sports clubs
programme to increase the spectator seating
from 135 to 186.5 1 5 £0.0 £0.0 LOW WD
measured works items
DES10Additional surveys required to
inform the design
Increased costs and delays to
programme
Review with planners and
building control 3 3 9 £0.0 £0.0 LOW WDno further survey works required,
Planning Approval obtained
DES11
Removal of Sport England
fundamental items at late stage
if funding bid is not successful on
15.09.14 (2nd drainage channel,
2nd lift and moveable floor to the
learner pool
Late amendment required to the
internal design
Abortive fees established which
increase each month.
2 1 2 £0.0 £0.0 LOW WD
DES12
Council can not afford 4 court
sports hall if Sport England bid
unsuccessful on 15.09.14
Redesign back to 2 courts. Project Board have authorised
Total Overall Cost up to £9.7M.
This decision needs to be
formally endorsed by the formal
Council Executive on 08.10.14.
2 4 8 £0.0 £0.0 LOW Client
4 Court option instructed and
contained within cost plan
DES13
5 aside 3G pitches can not flood Damage to 3G playing surface 5 aside 3G pitches need to be
raised to height of 7.2m in line
with finished slab level.3 3 9 £0.0 £0.0 LOW WD
Monies included within cost plan to
raise level of pitches
DES14
Council decide to instruct full size
3G pitch at the end of July 14 if
Lakes College unsuccessful
Impact on derogated Dry Change
with possible additional external
change facility required.
GT Architects have verified that
full size 3G pitch will fit.
However, it will impact on the
open space in front of the leisure
centre.
3 3 9 £0.0 £0.0 LOW Client
Full size 3G pitch omitted from
scheme
DES15
Pool tank strategy Delay to programme Pool tank strategy report
produced. Case study visit
undertaken to see stainless steel
tank option. Current actions with
Robertson. Potential programme
delay if not concluded by
18.07.14.
4 4 16 £0.0 £0.0 MED WD
Pool tank strategy confirmed,
instruction received from client to
progress with Myrtha system
FM-PC-07 Issue 1 Effective Date 01/01/2012
DES16
Raised end to shallow end of the
main pool
Future injury to user due to
diving into shallow water
Do not provide raised end to
shallow end.
Consider removable option to
reduce turning board set up.
Council instruction required to GT
Architects.
4 4 16 £0.0 £0.0 MED
Monies included within cost plan to
include raised end to one end of main
pool only
FM-PC-07 Issue 1 Effective Date 01/01/2012FM-PC-07 Issue 1 Effective Date 01/01/2012
DES17 0 £0.0
DES18 0 £0.0
DES19 0 £0.0
DES20 0 £0.0
DES22 0 £0.0
DES23 0 £0.0
DES25
DES26 0 £0.0
DES27 0 £0.0
DES28 0 £0.0
DES29 0 £0.0
DES30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
PL1
Results of FRA require anti
flooding measures to be
implemented
Requirement to provide anti
flood measures or lift building
levels, results in increased costs
& programme time
Finished floor slab level raised to
7.2m5 2 10 £0.0 £0.0 LOW WD
Site levels lifted to 7.200 and
included within measured works
PL2
Planning authority refuse
application due to site being
within a flood zone
Political and financial implications
and increased programme time
Post application meeting held
with the EA that resulted in
finished floor level being raised
from 7.050 to 7.200. EA have
informally advised that objection
will be removed.
5 2 10 £0.0 £0.0 LOW WD
Discussions ongoing with Planning
Authority and EA. Site re-classed as
Flood zone 2 due to 2009 floods.
PL3 Y
Existing road network requires
upgrading to deal with increased
traffic for development
Increased costs and programme
time to upgrade existing road
network
Detailed TIA to be prepared as
part of the planning application2 2 4 £0.0 £0.0 LOW WD
Scoping requirements now
determined by Cumbria County
Council and included within TIA
PL4
Discharging Planning Conditions Additional time and cost to
enable conditions to be
discharged
Early engagement with planning
authority held. Negotiation held
to influence pre-commencement
and pre-start conditions.
3 4 12 £0.0 £0.0 LOW WD
Pre Commencement conditions
identifed and information submitted
to planners for approval
PL5
Additional Ecological Surveys
required
Delay to programme as certain
surveys are time bound
Survey expanded and included in
the planning application
submission.4 2 8 £5,000.0 £1,600.0 LOW WD
Ecologist to advise if any trees
require removing from site
PL6
Planning documents do not
match design proposals
Planning application rejected due
to inaccuracies within documents
/ design proposals
Planning application submitted
on 14.04.14 1 5 5 £0.0 £0.0 HIGH WD
Resolved as application is now
validated
PL7
Planning objections Redesign and abortive costs to
obtain planning approval
Objections received. Meetings
held with the EA and Natural
England. Paper produced to
address cricket club concerns. 5 4 20 £0.0 £0.0 HIGH WD
Planning permission obtained for
development
Project No. 61097
Project : Workington Leisure Centre
Planning
13-Oct-14
PL7 address cricket club concerns.
Continue dialogue with planning
and council officers.
5 4 20 £0.0 £0.0 HIGH WD
PL8
Potential noise & light pollution
due to location of 3G pitch / 5 a
side courts
Increased costs and design in
order to relocate pitch / provide
mitigation measures
Undertake early discussions with
Environmental Health to
ascertain requirements3 4 12 £0.0 £0.0 LOW WD
Planning permission obtained and
information issued to EH to discharge
associated condition
PL9Additional planning & TIA issues
due to proposed Ice Rink
Additional time and cost due to
impact upon pre commissioned
surveys
Carlisle Leisure to confirm
requirements to client 0 £0.0 £0.0 ClientIce rink removed from scheme
PL10Potential S106 agreement for
street lighting to underpass
Additional costs associated with
discharging S106 agreement
Discussions required with
planners & Cumbria CC 2 4 8 £0.0 £0.0 LOW WDNo S106 agreements expected due
to applicant being Allerdale
PL11
Amendments to Griffin Street car
Park
Additional costs associated with
realigning car park
Car park strategy to be
confirmed by the council
including conclusion of speed
bumps / payment options.
5 4 20 £5,000.0 £4,000.0 HIGH WD
Discussions are currently ongoing
with Client & SKM in relation to
revised car parking strategy
PL12
Council decide to instruct full size
3G pitch at the end of July 14 if
Lakes College unsuccessful
Amendment to the planning
consent, subject to approval
being obtained on 22.07.14.
GT Architects have verified that
full size 3G pitch will fit.
However, it will impact on the
open space in front of the leisure
centre.
4 4 16 £5,000.0 £3,200.0 MED WD
Full size 3G pitch omitted from
scheme
PL13 0 £0.0
PL14 0 £0.0
PL15 0 £0.0
PL16 0 £0.0
PL17 0 £0.0
PL18 0 £0.0
PL19 0 £0.0
PL20 0 £0.0
PL21 0 £0.0
PL22 0 £0.0
PL23 0 £0.0
PL24 0 £0.0
PL25 0 £0.0
PL26 0 £0.0
PL27 0 £0.0
PL28 0 £0.0
PL29 0 £0.0
PL30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
SA1
Surveys identify unknown
services
Increased costs to deal with
relocation/ diversion of services
Undertake detailed discussions
with all utility providers to
ascertain existing infrastructure3 3 9 £0.0 £0.0 LOW WD
Allowance to be made for additional
investigations prior to commencing
onsite
SA2EA / United Utilities request
Water Impact Assessment
Increased costs and delay to
programme
Early discussions required with
EA / United Utilities to establish
requirements
3 4 12 £0.0 £0.0 LOW WDUnited Utilities have confirmed that
no water impact Assessment is
required
SA3
Protection / easement required
to existing United Utilities
detention tank
Increased costs & programme
time due to protection works or
alternative design solutions
being required
Early discussions required with
United Utilities to establish
requirements4 4 16 £10,000.0 £6,400.0 MED WD
Currently awaiting confirmation of
requirements from United Utilities
SA4
Late or non response from utility
companies in response to
applications
Increased costs & programme
time due to temporary supplies
being required
Undertake early discussions with
utility providers to ascertain
costs and programme durations4 4 16 £10,000.0 £6,400.0 MED WD
Revised quotes have been requested
from the relevant utility providers,
currently awaiting update
SA5Diversion / Strengthening works
to gas main
Increased costs & programme
time to undertake works
Discussions required with
National Grid / Fulcrum to
ascertain requirements
4 4 16 £20,000.0 £12,800.0 MED WDCurrently awaiting confirmation of
requirements from Northern Gas
Networks
SA6
Reduced / limited discharge
rates from United Utilities for
foul /surface water drainage
additional cost and programme
time to develop attenuation
systems
Engage with United Utility and
agree discharge rates 4 4 16 £0.0 £0.0 MED WD
Discharge rate received from United
Utilties and design developed to
reflect agreed rates
SA7
Provision of additional
infrastructure to facilitate
development
Increased costs & programme
time to undertake works
Early engagement with utility
providers to ascertain as built
information and design proposals0 £0.0 £0.0 WD
As built information and budget
proposals received
SA8 0 £0.0
SA9 0 £0.0
SA10 0 £0.0
SA11 0 £0.0
SA12 0 £0.0
Project No. 61097
Project : Workington Leisure Centre
Statutory Authorities
13-Oct-14
SA12 0 £0.0
SA13 0 £0.0
SA14 0 £0.0
SA15 0 £0.0
SA16 0 £0.0
SA17 0 £0.0
SA18 0 £0.0
SA19 0 £0.0
SA20 0 £0.0
SA21 0 £0.0
SA22 0 £0.0
SA23 0 £0.0
SA24 0 £0.0
SA25 0 £0.0
SA26 0 £0.0
SA27 0 £0.0
SA28 0 £0.0
SA29 0 £0.0
SA30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
EV1
Additional surveys indicate
presence of protected species
Programme impact as surveys
and removal are time bound
Early engagement with Ecologist
held. Himalayan Balsam present. 5 4 20 £0.0 £0.0 HIGH WD
Surveys have indicated no protected
species onsite
EV2Removal of invasive species Removal works are time bound
and may result in increased costs
Identify species and agree
removal methodology with
specialist
4 5 20 £0.0 £0.0 HIGH WDCosts contained with cost plan for
removal of invasive species
EV3
Mine shafts / mine workings
located within site boundary
Additional time and cost due to
geotechnical works required to
stabilise ground
There are records of a coal seam
at between 150m and 160m
depth last being worked in 1900.
It is considered that any ground
movement from these workings
would have stopped by now. Sub
Surface concludes that the
abandoned mine workings are of
such depth and character that
they present little risk to ground
stability beneath the site.
2 3 6 £0.0 £0.0 LOW WD
Draft assessments received from
Coal Authority, no mine works
present onsite.
No notices of subsidence have been
served and there are no recorded
mine entries within 20m of the site
boundary.
EV4
Ground contamination & ground
water
Increased costs and programme
time due to requirement to
undertake remedial works
Sub Surface concluded that there
are no contaminants requiring
remediation and/or precautions
to be taken for the proposed
development.
2 3 6 £0.0 £0.0 LOW WD
EV5
Delays in obtaining permits /
licences from EA and statutory
bodies
Increased programme time Early engagement with EA to
establish requirements 2 2 4 £500.0 £80.0 LOW WD
EV6Delay in obtaining updated flood
modelling data from EA
Delays to programme and
planning application as FRA can
not be finalised
Updated flood modelling data
now received. 4 4 16 £0.0 £0.0 MED WDMonies contained within CC4
Presence of Atlantic Salmon and Delays to enabling / culvert Detailed discussions required Ecology report indicates no Atlantic
Project No. 61097
Project : Workington Leisure Centre
Environmental
13-Oct-14
EV7Presence of Atlantic Salmon and
Lamprey within Soapery Beck
Delays to enabling / culvert
works as the migration season is
time bound
Detailed discussions required
with Ecologist to establish
presence and proposals
4 4 16 £0.0 £0.0 MED WDEcology report indicates no Atlantic
Salmon and Soapery Beck
EV8 0 £0.0
EV9 0 £0.0
EV10 0 £0.0
EV11 0 £0.0
EV12 0 £0.0
EV13 0 £0.0
EV14 0 £0.0
EV15 0 £0.0
EV16 0 £0.0
EV17 0 £0.0
EV18 0 £0.0
EV19 0 £0.0
EV20 0 £0.0
EV21 0 £0.0
EV22 0 £0.0
EV23 0 £0.0
EV24 0 £0.0
EV25 0 £0.0
EV26
EV27
EV28
EV29
EV30
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
HS1Client Understanding of CDM
responsibilities
Increased costs & programme
delays due client amendments
Appointment of CDMC and
understanding of duties4 4 16 £0.0 £0.0 MED Client
CDM-C now appointed and client
duties explained
HS2Design risk assessments Non-compliance with CDM
Regulations
Design risk assessment strategy
agreed and identified on
drawings
2 2 4 £0.0 £0.0 LOW WDDesign Risk Assessments received for
all disciplines
HS3CDM-C presentation To ensure CDM-C updated Presentation to be coordinated at
specific meeting. 4 3 12 £0.0 £0.0 LOW WDPresentation arranged for 04/09/14
HS4Pre-construction information Non-compliance with CDM
Regulations
Produce Pre-construction
Information early for CDM-C
review
3 3 9 £0.0 £0.0 LOW WDPre Construction Info received and
included within CPH&S Plan
HS5 0 £0.0
HS6 0 £0.0
HS7 0 £0.0
HS8 0 £0.0
HS9 0 £0.0
HS10 0 £0.0
HS11 0 £0.0
HS12 0 £0.0
HS13 0 £0.0
HS14 0 £0.0
HS15 0 £0.0
HS16 0 £0.0
HS17 0 £0.0
HS18 0 £0.0
HS19 0 £0.0
HS20 0 £0.0
HS21 0 £0.0
HS22 0 £0.0
HS23 0 £0.0
HS24 0 £0.0
HS25 0 £0.0
Project No. 61097
Project : Workington Leisure Centre
Health & Safety
13-Oct-14
HS25 0 £0.0
HS26 0 £0.0
HS27 0 £0.0
HS28 0 £0.0
HS29 0 £0.0
HS30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
QL1
Sub contractor / supply chain
failure
Increased costs and delays to
programme
Utilise robust, local supply chain
partners. Undertake full financial
health check prior to order2 4 8 £0.0 £0.0 LOW WD
Detailed supply chain list developed
with all parties
QL2
Insufficient tender returns during
market testing
Best value is not achieved Utilise robust, local supply chain
partners. Undertake full financial
health check prior to order3 4 12 £0.0 £0.0 LOW WD
Meet the buyer event undertaken
and adverts placed in local press
QL3
Cost plan does not allow client
aspirations
Political and financial implications
for client
Robust cost checking exercise to
be undertaken as design
develops3 3 9 £0.0 £0.0 LOW Client
Detailed reviews ongoing with Client,
Pick Everard and Design Team.
Frozen design agreed.
QL4
External appearance, quality and
design life does not meet client
aspirations
Negative impact on project
success
Design Life strategy agreed.
Images produced by GT
Architects2 4 8 £0.0 £0.0 LOW Client
Costs included within cost plan for
external work enhancements
QL5Internal finishes do not meet
client aspirations
Negative impact on project
success
Mood board presentation held on
08.07.14 2 4 8 £0.0 £0.0 LOW ClientInternal finishes identified on mood
board and signed off by all parties
QL6
Building construction does not
achieve required quality
standards expected.
Negative impact on project
success
NEC Supervisor to be appointed
to ensure compliance with the
Works Information.2 4 8 £0.0 £0.0 LOW WD
Quality plan to be established with
ongoing inspections by site team and
Quality Manager
QL7
Building construction does not
achieve required quality
standards for finishes.
Negative impact on project
success
Sample panels to be produced
on site for prior approval. 2 4 8 £0.0 £0.0 LOW WD
Sample requirements identified
within the Quality Plan
QL8
Building construction does not
achieve required quality
standards for finishes.
Negative impact on project
success
Sample room to be targeted for
early completion. 2 4 8 £0.0 £0.0 LOW WD
Sample requirements identified
within the Quality Plan
QL9 0 £0.0
QL10 0 £0.0
Project No. 61097
Project : Workington Leisure Centre
Quality
13-Oct-14
QL10 0 £0.0
QL11 0 £0.0
QL12 0 £0.0
QL13 0 £0.0
QL14 0 £0.0
QL15 0 £0.0
QL16 0 £0.0
QL17 0 £0.0
QL18 0 £0.0
QL19 0 £0.0
QL20 0 £0.0
QL21 0 £0.0
QL22 0 £0.0
QL23 0 £0.0
QL24 0 £0.0
QL25 0 £0.0
QL26 0 £0.0
QL27 0 £0.0
QL28 0 £0.0
QL29 0 £0.0
QL30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
PR1
Failure to complete works by
December 2015
Potential political and financial
implications to client
Develop robust and achievable
programmes and ensure full
stakeholder buy in5 4 20 £0.0 £0.0 HIGH WD
Gateway 4 Programme identifies
completion date of February 2016
PR2
Extended Pre Construction Period Increased Pre Construction Costs
and programme time
Client to provide clear direction
and milestones. Detailed
discussions required with all
parties to mitigate risks
3 4 12 £0.0 £0.0 LOW WD
8.6 week delay currently realised,
costs included within current cost
plan. Agreed baseline programme
now in place and costs included in
cost plan.
PR3
Procurement programme
indicated on revision O not
achieved.
Delay to programme Robertson are to provide weekly
updates to Pick Everard on the
procurement status.4 4 16 £0.0 £0.0 MED WD
Gateway 4 GMP to be submitted on
02/09/14 as identified on Pre
Construction Programme
PR4
Pool tank strategy to be
concluded by 18.07.14
Delay to programme Project team to conclude
required actions and agree way
forward on the pool tank
construction by 18.07.14
4 4 16 £0.0 £0.0 MED WD
Pool tank stratergy now identified,
Myrtha System to be utilised
PR5
Procurement and reporting can
not achieve formal Council
Executive
Delay to programme Programme developed to
consider realistic procurement
timetable, commercial actions,
reporting and align with formal
Council Executive meeting on
08.10.14.
4 4 16 £0.0 £0.0 MED WD
All information to beissued to Client
on 02/09/14 to allow Council
Executive to meet on planned date
PR6
Sport England Funding (Lottery
Heritage Fund)
Programme delay between
approval of scheme by formal
Council Executive and contract
signature.
Council to consider and advise.
5 3 15 £0.0 £0.0 MED Client
PR7Impose legal charge on the
leisure centre.
Programme delay if this needs to
be in place prior to contract
signature.
Council to obtain smaple, review
and and advise.5 3 15 £5,000.0 £3,000.0 MED Client
PR8 0 £0.0
PR9 0 £0.0
Project No. 61097
Project : Workington Leisure Centre
Programme
13-Oct-14
PR9 0 £0.0
PR10 0 £0.0
PR11 0 £0.0
PR12 0 £0.0
PR13 0 £0.0
PR14 0 £0.0
PR15 0 £0.0
PR16 0 £0.0
PR17 0 £0.0
PR18 0 £0.0
PR19 0 £0.0
PR20 0 £0.0
PR21 0 £0.0
PR22 0 £0.0
PR23 0 £0.0
PR24 0 £0.0
PR25 0 £0.0
PR26 0 £0.0
PR27 0 £0.0
PR28 0 £0.0
PR29 0 £0.0
PR30 0 £0.0
FM-PC-07 Issue 1 Effective Date 01/01/2012
Project Risk Profile
Item
Select
Description Possible Effect Mitigation ActionLikelihood(1 Low -5 High)
(a)
Impact(1 Low -5 High)
(b)
Risk Score(a x b)
Potential
Cost(1000's)
Factored
Cost Risk(1000's)
Risk
Cat
Risk
Owner
Risk
Manager
Target
Close
Date
Notes
SPR01
Construction of Culverts &
bridging systems to Soapery
Beck
Increased costs and programme
in order to undertake works.
Culvert works maybe time bound
WYG instructed to design bridge
to impact as least as possible on
Soapery Beck. Permits &
approval required from EA
5 3 15 £0.0 £0.0 MED WD
Bridge design finalised and costs
contained within cost plan
SPR02SI requires additional works to
make construction viable
Increased costs and programme
in order to undertake works
Review SI with Geotechnical
Engineer 4 4 16 £0.0 £0.0 MED WDNo site constraints identified within
the finalised SI Report
SPR03
Requirement to increase site
levels to mitigate flood risk
Increased costs and programme
in order to design works
The finished floor slab level has
been agreed by the EA at
7.200m. The leisure centre
management will sign up to the
EA flood warning service and
emergency procedures put in
place for all staff and visitors.
5 4 20 £0.0 £0.0 HIGH WD
Site levels now set at 7.2m and
incresed material allowance
contained within measured works
SPR04
Undertaking Due Diligence on
FRA
Increased costs and programme
in order to review / amend
works
The finished floor slab level has
been agreed by the EA at
7.200m. 4 4 16 £0.0 £0.0 MED WD
SPR05
Lack of community buy in to
project
Political and PR issues for client Community engagement events
held by the Council in April 2014. 3 3 9 £0.0 £0.0 LOW Client
Ongoing Community Engagement
taking place and CSR Plan developed
SPR06
Development of council Master
plan for the area
Interface with FEC development
and wider redevelopment of
Workington Town Centre
Undertake community
engagement and stakeholder
meetings4 4 16 £0.0 £0.0 MED Client
SPR07
Unable to obtain Building &
Contents Insurance due to the
flood zone designation
Unable to obtain insurance or
obtain insurance at commercially
viable rates
Council meeting held with
insurance provider on 16.07.14. 4 5 20 £20,000.0 £16,000.0 HIGH Client
Monies identified are to cover
increase in Insurance premium
SPR08Abortive costs for bridge if the Abortive fee and construction Consider bridge location as part
5 4 20 £0.0 £0.0 HIGH ClientAwaiting feedback from Client in
Project No. 61097
Project : Workington Leisure Centre
Specific Project Risks
13-Oct-14
SPR08Abortive costs for bridge if the
FEC development goes ahead.
Abortive fee and construction
costs
Consider bridge location as part
of the master plan for
Workington.
5 4 20 £0.0 £0.0 HIGH ClientAwaiting feedback from Client in
relation to Master Plan
SPR09 0 £0.0
SPR10 0 £0.0
SPR11 0 £0.0
SPR12 0 £0.0
SPR13 0 £0.0
SPR14 0 £0.0
SPR15 0 £0.0
SPR16 0 £0.0
SPR17 0 £0.0
SPR18 0 £0.0
SPR19 0 £0.0
SPR20 0 £0.0
SPR21
SPR22
SPR23
SPR24
SPR25
SPR26
SPR27
SPR28
SPR29
SPR30
FM-PC-07 Issue 1 Effective Date 01/01/2012
Appendix C
Allerdale Leisure Centre Rev 3Local Spend Profile - Summary 15.10.1415 October 2015
Value (£) Required (£) Required % Achieved %
8,842,660 - - -
2,455,173 3,537,064£ 40% 28
2,593,290 6,631,995£ 75% 29
Notes:
1) Based on package value (verified costs) as WD/RCE revised submission of 15 October 2014.
2) Distance calculated "as the crow flies".
3) The post codes used were taken from the bids and may vary from RCE submission.
Total Project subcontract package value
Total value in 40 mile radius
Total value in 20 mile radius
Description
Page 1
Allerdale Leisure CentreLocal Spend Profile Rev 315 October 2015 15.10.14
RCE Ref. Title No.of Bids No. Enquiries Lowest Bid (£) Contractor Location Post Code Distance from
Allerdale (Miles)
27 Sports Pitches 3 3 201,698 SIS Maryport CA15 8NT 4.5
31 Decoration 1 8 53,498 Peter Wise Ltd Mary Port CA15 8NF 4.5
2 Brick & Blockwork 2 8 260,215 Ashcroft Dearham CA15 7EH 5.5
32 Earthworks / Groundworks & Hard Landscaping 2 5 1,480,944 Ashcroft Maryport CA15 7EH 5.5
33 Fencing & Gates 3 4 10,541 Contract Fencing Ltd Rowrah CA26 3XS 7.5
N7 Site Hoardings 2 2 35,351 Birketts Fencing Frizington CA26 3XS 7.5
8 Plastered/rendered coatings 2 5 18,928 Design Grid Ltd Whitehaven Whitehaven CA28 9QD 8.3
41 Stud partitions & linings suspended ceilings 2 11 354,025 Design Grid Ltd Whitehaven Whitehaven CA28 9QD 8.3
44 Timber Ceilings 1 3 39,972 David Mingins Joinery Ltd Cleator Moor CA25 5BY 8.7
2,455,173£
3,537,064£
Shortfall 1,081,891£
Actual Percentage 28£ The below map indicates the 20 mile radius
Scape requires that 40% of the contract value is spent within a 20 mile radius of the project.
40% total Value
Total value in 20 mile radius
Page 2
Allerdale Leisure CentreLocal Spend Profile Rev 315 October 2015 15.10.14
RCE Ref. Title No.of Bids No. Enquiries Lowest Bid (£) Contractor Location Post Code Distance from
Allerdale (Miles)
27 Sports Pitches 3 3 201,698 SIS Maryport CA15 8NT 4.5
31 Decoration 1 8 53,498 Peter Wise Ltd Mary Port CA15 8NF 4.5
2 Brick & Blockwork 2 8 260,215 Ashcroft Dearham CA15 7EH 5.5
32 Earthworks / Groundworks & Hard Landscaping 2 5 1,480,944 Ashcroft Maryport CA15 7EH 5.5
33 Fencing & Gates 3 4 10,541 Contract Fencing Ltd Rowrah CA26 3XS 7.5
N7 Site Hoardings 2 2 35,351 Birketts Fencing Frizington CA26 3XS 7.5
8 Plastered/rendered coatings 2 5 18,928 Design Grid Ltd Whitehaven Whitehaven CA28 9QD 8.3
41 Stud partitions & linings suspended ceilings 2 11 354,025 Design Grid Ltd Whitehaven Whitehaven CA28 9QD 8.3
44 Timber Ceilings 1 3 39,972 David Mingins Joinery Ltd Cleator Moor CA25 5BY 8.7
N5 Scaffolding 1 1 42,600 Carlisle Scaffolding Ltd Carlisle CA6 4SN 30.6
21 Render 1 7 95,517 JPL Plastering Contractors Ltd Penrith CA11 9BF 31.4
2,593,290£
6,631,995£
Shortfall 4,038,705£
Actual Percentage 29£ The below map indicates the 40 mile radius
Scape requires that 75% of the contract value is spent within a 40 mile radius of the project.
75% total Value
Total value in 40 mile radius
Page 3