army construction manual fm5 430 vol1 entire

491
Field Manual No. 5-430-00-1 Air Force Joint Pamphlet No. 32-8013. Vol I ·FM 5-430-00-1 ·AFJPAM 32-8013. Vol I Headquarters Department of the .. Department of the Air Force WashIngton. DC. 26 August 1994 ..... A .......... " A ........... ... "" ....... "" A .... "" A ................. "" A .... _ •• _ ..... __ ... "" r'L"'I'tI'tIl'tU "'1'tU vr "'NU nCLIt'Un I IN THE THEATER OF OPERATIONS-ROAD DESIGN TABLE OF CONTENTS Volume I Page PREFACE .................................................................... v CHAPTER 1. GENERAL INFORMATION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1-1 General Information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1-1 Basic Planning Considerations In the Theater of Operations. . . . . . . . . . . . . . . . . . . . . .. 1-1 Airfield Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1-2 Road Construction ....................................................... , 1-2 Engineering Study ........................................................ 1-3 CHAPTER 2. SITE SELECTION AND RECONNAISSANCE ............................ 2-1 Location Factors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1 Reconnaissa.'t')ce ..... , ..................................................... 2-5 Route and Road Reconnaissance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-11 Engineer Reconnaissance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14 Airfield Reconnaissance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14 CHAPTER 3. SURVEYS AND EARTHWORK OPERATIONS ........................... 3-1 Construction Surveys ...................................................... 3-1 Construction Stakes ....................................................... 3-3 The Mass Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-19 DISTRIBUTION RESTRICTION: Approved for public release; distribution Is unlimited. "'This pubiication together with FM 5-430-00-2iAFJpAM 32-8013, Voi Il, 29 September 1994 supersedes FM 5-165/AFR 86-13,29 August 1975, FM 5-335,2 December 1985 and TM 5-330/AFM 83-6, Voll, 8 September 1968. /

Upload: johnbullas

Post on 22-Feb-2015

248 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Army Construction Manual FM5 430 Vol1 Entire

Field Manual No. 5-430-00-1 Air Force Joint Pamphlet No. 32-8013. Vol I

·FM 5-430-00-1 ·AFJPAM 32-8013. Vol I

Headquarters Department of the .. A~1'1nY

Department of the Air Force WashIngton. DC. 26 August 1994

..... A .......... " A ........... r"~." ... "" ....... "" A .... "" A ................. "" A .... _ •• _ ..... __ ... "" r'L"'I'tI'tIl'tU "'1'tU UC~IUN vr nv"'u~, "'lnrICLU~, "'NU nCLIt'Un I ~

IN THE THEATER OF OPERATIONS-ROAD DESIGN

TABLE OF CONTENTS

Volume I

Page

PREFACE .................................................................... v

CHAPTER 1. GENERAL INFORMATION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1-1

General Information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1-1 Basic Planning Considerations In the Theater of Operations. . . . . . . . . . . . . . . . . . . . . .. 1-1 Airfield Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1-2 Road Construction ....................................................... , 1-2 Engineering Study ........................................................ 1-3

CHAPTER 2. SITE SELECTION AND RECONNAISSANCE ............................ 2-1

Location Factors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1 Reconnaissa.'t')ce ..... , ..................................................... 2-5 Route and Road Reconnaissance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-11 Engineer Reconnaissance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14 Airfield Reconnaissance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14

CHAPTER 3. SURVEYS AND EARTHWORK OPERATIONS ........................... 3-1

Construction Surveys ...................................................... 3-1 Construction Stakes ....................................................... 3-3 The Mass Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-19

DISTRIBUTION RESTRICTION: Approved for public release; distribution Is unlimited.

"'This pubiication together with FM 5-430-00-2iAFJpAM 32-8013, Voi Il, 29 September 1994 supersedes FM 5-165/AFR 86-13,29 August 1975, FM 5-335,2 December 1985 and TM 5-330/AFM 83-6, Voll, 8 September 1968.

/

Page 2: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-lIAFJPAM 32-8013, Vol I

CHAPTER 4. CLEARING. GRUBBING. AND STRIPPING ............................. 4-1

Forest Types and Environmental Conditions ................................... 4-1 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2 Clearing Considerations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4 Performance Techniques ................................................... 4-6

CHAPTER 5. SUBGRADES AND BASE COURSES ................................. 5-1

Design Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5- 1 Subgrades ............................................................... 5-4 Select Materials and Subbase Courses ........................................ 5-8 Base Course . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 5-10

CHAPTER 6. DRAINAGE ...................................................... 6-1

SECTION I. Construction Drainage .......................................... 6-1

Preliminary Measures ...................................................... 6-1 Drainage Hydrology ....................................................... 6-4 The Hydrograph .......................................................... 6-9 Drainage-System Design .................................................. 6-11 Design Proced ures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6- 11 Estimating Runoff Using the Rational Method ................................. 6-22

SECTION Il. Open-Channel Design ......................................... 6-38

Design Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-38 Design Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-45 Design Techniques ....................................................... 6-46

SECTION Ill. Culverts .................................................... 6-59

Culvert Types and Designs ................................................ 6-59 Ponding Areas ........................................................... 6-84 Drop Inlets and Gratings .................................................. 6-89 Subsurface Drainage ..................................................... 6-92

SECTION IV. Surface Drainage Design in Arctic and Subarctic Regions ........... 6-102

Fords. Dips. Causeways. and Bridges. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-107 Erosion Control ........................................................ 6-114 Nonuse Areas and Open Channels ......................................... 6-115 Culvert Outlets ......................................................... 6-124

CHAPTER 7. SOILS TRAFFICABILITY ........................................... 7-1

Basic Trafficability Factors ................................................. 7-2 Critical Layer ............................................................ 7-3 Instruments and Tests for Trafficability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-3 Measuring Trafficabil1ty .................................................... 7-5 Application of Trafficability Procedures in Fine-Grained

Soils and Remoldable Sands .............................................. 7-11

Page 3: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFJPAM 32-8013, Vol I

Self-Propelled. Tracked Vehicles and AIl-Wheel-Drive Vehicles Negotiating Slopes ............................................... 7-11

Operation In Coarse-Grained Soils .......................................... 7~26 Trafflcab1l1ty Data ........................................................ ·/~"L I Soil~ Traffic ab ili ty Classification ............................................. 7 ~36

CHAPTER 8. MAINTENANCE. REPAIR. AND REHABILITATION OF ROADS. AIRFIELDS. AND HELIPORTS ........................................ 8-1

Maintenance and Repair Considerations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-1 Maintenance and Repair Operations ............................. , ........ , , , . 8-2 Road Maintenance ........................................................ 8-9 Airfield and Heliport Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-17

CHAPTER 9. ROAD DESIGN. " .............. " ., ............................. 9-1

Geometric Design ......................................................... 9-1 Vertical Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9~ 18 Structurai Design ........................................................ 9~27 Spray Applications and Expedient-Surfaced Roads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-30 Use of Polymer Cells (Sand Grid) to Build

Roads in Sandy Soils .................................................. . Surface Treatments .................................................... . Construction Methods .................................................. . General Road Structural Design .......................................... .

Volume 11

9-36 9-41 9~49

9-58

CP~ER 10. PRELlrv1It~ARY PLA..L'Ji~ING ........................ t •••••••••••••• • 10-1

Mission Assignment ...................................................... 10-1 Classification ............................................................ 10-5 Construction ............................................................ 10-8

CHAPTER 11. AIRCRAFT CHARACTERISTICS AND AIRFIELD DESIGN ................ 11-1

Aircraft Characteristics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 11-1 Correlation of Army and Air Force Terminology .............................. " 11-1 Airfield Design ........................................................ " 11-6 Aids to Navigation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 11-31 Special Airfields ........................................................ 11-50

CHAPTER 12. AIRFIELD PAVEMENT DESIGN .................................... 12-1

Airfield Structure 1'ype .................................................... 12-1 Expedient-Surfaced Airfields ....................... , , , , , , .... , . . . . . . . . . . . .. 12-8 Aggregate-Surfaced Airfields .............................................. 12-22 Flexible-Pavement Airfields . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 12-35 Special Design Considerations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12-43 Evaluation of Airfield Pavements ........................................... 12-50 Pavement and Airfield Classification Numbers ................................ 12-61

III

Page 4: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFJPAM 32-8013, Vol I

CHAPTER 13. DESIGN AND CONSTRUCTION OF HELIPORTS A .... l\lD HEL!pft.nS ......... 13-1

'fypes of Helicopters. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 13-1 Heliport Types, DesIgn Criteria, and Layout. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 13-1 DesIgn of Heliport and Helipad Surfaces .................................... 13-15 Design of Unsurfaced Heliports ............................................ 13-15 Mat- and Membrane-Surfaced HeUports and Helipads .......................... 13-21 Thickness Design Procedure ............................................. , 13-23 Special Design Considerations ............................................. 13-27 Marking and Lighting of Heliports and Hel1pads .............................. 13-27 Hellpads in Heaviiy Forested Areas ......................................... 13-32

CHAPTER 14. FORTIFICATIONS FOR PARKED ARMY AIRCRAFT .................... 14-1

Aircraft FortifIcations ..................................................... 14-1 Maintenance, Repairs, and Improvements .................................. , 14-48

APPENDIX A. r-.. 1ETPJC COl\TVERSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. A-I

APPENDIX B. GEOTEXTILE FORMULAS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. B-1

APPENDIX C. HYDROLOGIC AND HYDRAULIC TABLES AND CURVES . . . . . . . . . . . . . .. C-l

APPENDIX D. CONE INDEX REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. D-l

APPENDIX E. SOIL-TRAFFICABILITY TEST SET. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. E-l

APPENDIX F. CURVE TABLES ..... , .............. " . ... ... . ...... .. .. .. . ..... F-l

APPENDIX G. FROST DESIGN FOR ROADS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. G-l

APPENDIX H. GEOTEXTILE DESIGN .... , ...................................... H-l

APPENDIX 1. AIRFIELD CONE PENETROMETER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. I-I

APPENDIX J. DESCRIPTION AND APPLICATION OF DUAL-MASS DYNAMIC CONE PENETROMETER ......................................................... J-l

APPENDIX K. FLEXIBLE PAVEMENT EVALUATION CURVES .................... " ... K-l

APPENDIX L. MAT REQUIREMENT TABLES FOR AIRFIELDS ........................ L-l

APPENDIX M. MAT REQUIREMENT TABLES FOR HELIPADS AND HELIPORTS ........ M-I

APPENDIX N. MEMBRANES AND MATS ......................................... N-I

APPENDIX O. PAVEMENT CLASSIFICATION NUMBER GRAPHS ...................... 0-1

APPENDIX P. BALLISTIC DATA ................................................ P-l

GLOSSARY ........................................................... Glossary-I

REFERENCES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. References-l

Iv

Page 5: Army Construction Manual FM5 430 Vol1 Entire

PREFACE

Field Manual (FM) 5-430 is intended for useas a training guide and reference text for en-gineer personnel responsible for planning,designing, and constructing roads, airfields,and heliports in the theater of operations(TO).

FM 5-430 is divided into two separate vol-umes to make it more user-friendly. FM 5-430-00-1/AFPAM 32-8013, Vol 1, Road De-sign, encompasses Chapters 1 through 9and Appendices A through H. FM 5-430-00-2/AFJPAM 32-8013, Vol II, Airfield and Heli-port Design, encompasses Chapters 10through 14 and Appendices I through P.

FM 5-430-00-l/AFPAM 32-8013, Vol 1 is astand-alone volume for the design of TOroads. This volume also serves as a de-tailed description of information common toboth roads and airfields, such as site selec-tion, survey and earthwork, clearing andgrubbing, base and subbase courses, anddrainage.

FM 5-430-00-2 /AFJPAM 32-8013, Vol IIserves as the basis for airfield and heliportdesign. It discusses the complete processof airfield and heliport construction fromthe preliminary investigations, through de-sign criteria, to the final project layout andconstruction techniques. It is not a stand-alone volume. FM 5-430-00-1/AFPAM 32-8013, Vol 1 contains much of the informa-tion required to design the substructure ofan airfield or a heliport.

The material in this manual applies to alllevels of engineer involvement in the TO.The manual is intended to be used byUnited States (US) Army Corps of Engineerspersonnel.

The provisions of this publication are thesubject of the following international agree-ments:

• Quadripartite Standardization Agree-ment [QSTAG) 306, American-British-Canadian-Australian Armies Stan-

FM 5-430-00-1/AFJPAM 32-8013, Vol I

dardization Program, Fortification forParked Aircraft.

• North Atlantic Treaty Organization(NATO) Standardization Agreement(STANAG) 3158 Airfield Marking andLighting (AML) (Edition 4), Day Markingof Airfield Runways and Taxiways.

Ž STANAG 2929, Airfield Damage Repair.

• STANAG 3346 AML (Edition 4), Markingand Lighting of Airfield Obstructions.

Ž STANAG 3601 Air Transport (TN) (Edi-tion 3), Criteria for Selection and Mark-ing of Landing Zones for Fixed WingTransport Aircraft.

Ž STANAG 3619 AML (Edition 2) (Amend-ment 2), Helipad Marking.

• STANAG 3652 AML (Amendment 3), Heli-pad Lighting, Visual Meteorological Con-ditions (VMC).

• STANAG 3685 AML, Airfield PortableMarking.

This publication applies to the Air NationalGuard (ANG) when published in the Na-tional Guard Regulation (NGR) (AF) 0-2.

This publication, together with FM 5-430-00-2/AFJPAM 32-8013, Vol H: Airfield and Heli-port Design (to be published), will super-sede TM 5-330/AFM 86-3, Volume II, 8 Sep-tember 1968 and FM 5-165/AFP 86-13, 29August 1975.

The proponent for this publication is theUS Army Engineer School (USAES). Sendcomments and recommendations on Depart-ment of the Army (DA) Form 2028 (Recom-mended Changes to Publications and BlankForms) directly to—

CommandantUS Army Engineer SchoolATSE-TDMFort Leonard Wood, MO 65473-5000.

Unless this publication states otherwise,masculine nouns and pronouns do not referexclusively to men.

v

Page 6: Army Construction Manual FM5 430 Vol1 Entire

1General Information

Basic Planning Considerations in the Theater of Operations

Airfield Construction

Road Construction

Engineering Study

FM 5-430-00-1/AFPAM 32-8013, Vol 1

GENERAL INFORMATION

Army engineers plan, design, and construct airfields, heliports,and roads in the TO. To ensure these facilities meet proposedrequirements, the responsible engineer officer must coordinateclosely with all appropriate ground and air commanders. Theengineer depends on the appropriate commanders for informa-tion on the weight and traffic frequency of using aircraft, facilitylife, geographic boundaries governing site selection, and thetime available for construction as dictated by the operation plan.

Detailed planning, reconnaissance, and site investigations areoften limited by lack of time and by the tactical situation. How-even when time and security permit, the engineer should conductnormal ground reconnaissance and on-site investigations. Ifthis is not possible, the engineer should obtain photographs ofthe area.

BASIC PLANNING CONSIDERATIONS IN THE THEATER OFOPERATIONS

Army engineers should use the followingguides in the TO:

• Keep designs simple. Simple designs re-quire minimum skilled labor and spe-cialized materials.

• Use local materials whenever possible.This helps eliminate construction delaysassociated with a long communicationsand logistics line.

• Use existing facilities whenever pos-sible. This helps avoid unnecessary con-struction.

• Remember that safety factors in designare drastically reduced in the TO be-cause of time constraints and the in-herent risks of war.

• Build one of two types of structures inthe TO: initial or temporary. Initialdesign life is up to six months; tem-porary design life is up to two years.

Ž Whenever possible, phase constructionto permit the early usc of the facilitywhile further construction and improve-ments continue.

Ž Generally avoid sites with dense brush,timberland, and rolling terrain that re-quire heavy clearing or grading.

Ž Take care to prevent destruction ofnatural drainage channels, culverts,and roads. Repairs require time andlabor far exceeding that needed toprevent damage.

General Information 7-1

Page 7: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

AIRFIELD CONSTRUCTION

The planning and construction of Air Forcebases in the TO is a joint responsibility ofArmy and Air Force personnel as outlined inArmy Regulation (AR) 415-30/Air ForceRegulation (AFR) 93-10. A summary of eachservice’s responsibilities follows:

AIR FORCE RESPONSIBILITIES

The Air Force provides the following support:

• Emergency repair of war-damaged airbases.

• Force bed down of Air Force units andweapon systems, excluding Army base-development responsibilities.

• Construction management of emergencyrepair of war damage and force bed-down.

• Operation and maintenance of Air Forcefacilities and installations.

• Crash rescue and fire suppression.

• Supply of material and equipment toperform Air Force engineering missions.

ARMY RESPONSIBILITIES

The Army will provide the following troopconstruction support to the Air Force:

Ž Development of engineering designs,standard plans, and material to meetAir Force requirements.

• Reconnaissance, survey, design, con-struction, or improvement of airfields,roads, utilities, and structures.

Ž Rehabilitation of Air Force bases and fa-cilities beyond the immediate emer-gency recovery requirements of the AirForce.

Ž Supply of materials and equipment toperform Army engineering missions.

Ž Construction of temporary standard airbase facilities.

Ž Repair management of war damage andbase development, including supervi-sion of Army personnel. The Air Forcebase commander will set the work priori-ties.

• Road and airfield construction.

ROAD CONSTRUCTION

Engineer construction units, under the • Construct and install signs and otherappropriate Army command, have the following route-marking materials.responsibilities:

Ž Regulate traffic at locations where engi-

• Reconnoiter roads and bridges. neer work is being performed.

Ž Assist vehicles to keep traffic moving on

• Recommend traffic-control procedures. main supply routes regardless ofweather, enemy activity, or other diffi-culties.

1-2 General Information

Page 8: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

ENGINEERING STUDY

After the specific requirements for roads, using certain airfields and roads. To obtainair fields. and heliports have been these facilities quickly, an adequatedetermined engineers should prepare the investigation of each site and a carefulfacilities for use as soon as possible. In study of the design details are essential.most cases, the he need is critical because the This is explained in greater detail inaccomplishment of a mission depends on Chapter 2 of this manual.

General Information 1-3

Page 9: Army Construction Manual FM5 430 Vol1 Entire

2

CHAPTER

Site Selection and Reconnaissance

Location Factors

Reconnaissance

Route and Road Reconnaissance

Engineer Reconnaissance

Airfield Reconnaissance

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SITE SELECTION ANDRECONNAISSANCE

This chapter outlines the location, layout, and design of militaryroads and airfields. The first steps in constructing a road orairfield are determining the best location for the facility andformulating the essential areas and construction features.Throughout the preconstruction phase, problems can be avoidedby a well-planned site selection.

LOCATION

Construction of a road or airfield initiallyconsists of providing a prepared subgradeand base course according to designcriteria. Airfield runways require moretransverse areas than roads. Although thegoverning criteria and dimensions for roadsand airfields differ, the basic approach totheir location and layout is the same. En-gineers should use the factors listed belowto locate and lay out all constructionprojects.

MISSION

The most important factor in selecting asite is to ensure it will fulfill mission re-quirements. Lines of communication (LOC)must be build to accomplish a specific mis-sion in the most direct and efficient mannerpossible. All location factors must beevaluated to support the mission.

EXISTING FACILITIES

Use all existing facilities. The wartime mis-sions of engineer troops arc so extensiveand the demand for their services so greatthat new construction should be avoided.Extensive roadnets of varying quality andcapacity already exist in most areas of the

FACTORS

world, Where possible, use these roadnetsto the fullest extent. In many cases, expan-sion and rehabilitation of existing facilitiesis adequate for mission accomplishment.

Except in highly developed areas, existingairfields are seldom adequate to handlemodern, high-performance aircraft. How-ever, with minimum rehabilitation these air-fields can usually be made adequate to ac-commodate them. They may serve as thenucleus for larger fields that meet the re-quirements of high-performance aircraft.Helicopters and light planes can oftenoperate from existing roads, pastures,athletic fields.

LOCATION AND DESIGN

or

To the greatest extent possible, the locationand design for a facility must provide thebest response to all requirements. Alterna-tive road and airfield plans can beevaluated, from the standpoint of totalearthwork and drainage structure require-ments, to reduce construction effort.

Try to construct airfields in an area thatwill serve existing and future requirements.Consider the future needs of military units

Site Selection and Reconnaissance 2-1

Page 10: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

and facilities, such as depots and hospitals,when locating roads. Soil type andincumbent pavement structurerequirements, rock formations, andvegetation should also be considered inlocating roads. A given road segment to beconstructed or improved should beconsidered in view of its contribution to theoverall network. Similarly, an airfieldshould be evaluated for its ability toenhance an arifield network.

SOIL CHARACTERISTICS

Locate all roads and airfields on terrainhaving the best possible subgrade soilconditions. This will decrease constructioneffort and result in a better facility. Thesubgrade should be compacted underconditions allowing it to support the designloads. Conduct a basic soils investigationprior to construction to provide data neededto ensure good construction decisions.Refer to FM 5-410 for soils information andFM 5-530 for soil survey procedures.

DRAINAGE

Locate roads in areas that are easily drain-ed and where drainage structures areminimized. Drainage is a more criticalfactor in locating airfields than roads.Because of the wide areas involved inairfield installations, water must be divertedcompletely around the field or long drainagestructures that are difficult to maintainmust be constructed. This topic is furtherdiscussed in Chapter 6 of this manual.

Avoid the low points of valleys or otherdepressed areas because they are focalpoints for water collection. Many airfieldsare constructed across long, gentle slopesbecause of the relative ease of divertingwater around the finished installation.Avoid construction on unprotected flood-plains and alluvial fans, if possible, due tothe flood hazard. Alluvial terraces are oftenideal locations for air fields. They offer flatexpanses that are above the river floodplainand are normally protected from flooding.

Avoid constructing facilities in areas of highwater tables. Although it is possible to con-struct subsurface structures that willremove part of this moisture, maintainingroutes through these areas presents acontinual problem. If it is impossible toavoid constructing a road or airfield in thistype of terrain, the water tables must belowered during construction to reduce theadverse effect of water on the strength ofthe supporting subgrade and base course.

GEOLOGY

Before locating any lines of communication,carefully analyze the geology of the area.Sizeable quantities of rock anywhere alonga construction project will cause a largeremoval problem, slow construction, andincrease the construction effort. Engineertroop units require special equipment andtraining to excavate rock.

Rock outcropping are more common inhilly terrain than in flat or rolling country.In areas where the preliminary designindicates that cutting is required to reachfinal grade, take enough borings todetermine the location of the rock.

identify the type of rock material forevaluation as a suitable constructionaggregate. Determine the structuralorientation of the rock mass to properlydesign road cuts and ensure rock-slopestability. In sedimentary rocks it is best toalign road cuts perpendicular to the strike.If this is not possible, use the safe-sloperatios shown in Figure 2-1.

TOPOGRAPHY

Construct all roads and airfields withinmaximum grade specifications. Thespecifications depend upon the facility’sconstruction standard. Thus, avoidexcessive grades and steep hills whenlocating these routes. If steep hills must benegotiated, the route should run along theside of the hill rather than going directlyover it. This may result in a longer route,but it is generally more economical andavoids excessive grades.

2-2 Site Selection and Reconnaissance

Page 11: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-1.

EARTHWORK

The largest single work item during con-struction of LOC is earthwork operations.Any step that simplifies earthwork opera-tions will decrease required work and in-crease job efficiency. Generally, when cut-ting and filling on a project, earth handlingis reduced by using the material excavatedto construct required embankments. Thisbalancing must be within the haulcapabilities of the available equipment.Even though earthwork should be balancedthroughout a project, if the haul distancebecomes excessive, it may be more practicalto open a nearby borrow pit or establishspoil areas. Balancing cannot be donewhere the excavated material is not accept-able for usc in an embankment.

ALIGNMENT

Keep the number of curves and grades at aminimum for efficient traffic flow overroads. All vehiceles have difficulty innegotiating sharp curves; even gentle curvesdecrease traffic capacity. Lay all routeswith minimum curves by making the tan-gent lines as long as possible. Locatinglong tangents is influenced primarily by theterrain and limited by the following prin-ciples of efficient location: minimizingearthwork, avoiding excessive grades, and

Safe-slope ratio

obtaining suitable fill material. Align run-ways in the direction of the prevailing windbecause aircraft usually land and take offinto the wind.

OBSTACLE CROSSINGS

Whenever a route crosses a major obstacle,such as a river, a ravine, or a canal,bridges or other structures arc required.Construction is time-consuming and re-quires materials that may be in short supp-ly. Avoid these obstacles whenever pos-sible. It will be advantageous to foregomany of the other location principles todecrease the number of obstacle crossings.Use existing structures to decrease totalwork requirements, This may require onlythe strengthening of an existing bridge orno bridging work at all. When possible, theroad should not cross a particular obstaclemore than once.

BRIDGE APPROACHES

When locating rou tes, carefully evaluate con-struction requirements for approaches toobstacles. Construction of approaches overmarshes or floodplain areas can causegreater requirements than the obstaclecrossing itself. Approach conditions may bethe prime factor in obstacle crossing and

Site Selection and Reconnaissance 2-3

Page 12: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

may dictate route location. Consider the ap-proach with the obstacle when establishingthe optimum route.

GROUND COVER

All routes should avoid heavily woodedareas that require extensive clearing, lfthis is not possible, the route should passthrough areas having the least vegetation.Precede all earthwork by stripping un-suitable material.

REQUIRED AREAS

Airfields need large areas of relatively flatland to efficiently accomplish their mission.This usually restricts the number of sitesthat can be considered for airfield construc-tion. Advance location and layout willavoid cramping necessary facilities. Fre-quently, the airfield must be spread over alarge section to obtain the required area.This results in the construction of a com-plex network of taxiways and service roads.When this is the case, keep in mind theability to construct this connecting networkto appropriate specifications.

Roads built on rolling or flat terrain seldomrequire large, lateral areas. Roads con-structed in deep cuts or fills require propor-tionately greater lateral areas to account forslopes.

ACCESSIBILITY TO MATERIALS ANDUTILITIES

The efficient operation of airfields requiresthe use of electricity, water, gas, and sewersystems. Locating new airfields near exist-ing utility systems can avoid the construc-tion of new facilities or long transmissionlines. A nearby railhead will help the con-struction effort.

Consider the quality and availability of con-struction materials when locating a facility.Obtain suitable base-course materials fromexisting pits and quarries whenever possiblebecause much planning and effort are re-quired to open a new quarry. The quality

and available quantity of materials mustmeet the construction requirements. Theproximity of a suitable base-course-materialsource is a critical planning factor.

MARGINAL MATERIAL

When planning the location of a project,consider using marginal materials nearby.Using marginal materials for subbase andbase construction and, as an aggregate inpavements is sometimes possible by usinggeotextiles, mechanical stabilization, or ad-mixtures. Often the use of marginalmaterial is unavoidable. Where possible,poor -quality material should be excavatedand replaced with more suitable material,or the project should be relocated.

FLIGHT-WAY OBSTRUCTIONS

The safe operation of fixed- or rotary-wingaircraft requires the removal of all obstaclesabove lines specified by design criteria.These criteria depend upon the operatingcharacteristics of the aircraft to be serviced.For example, most heliports require an ap-proach zone with a 10:1 glide angle (8:1 forshort-duration operations), whereas heavy-cargo aircraft in the rear area require aglide angle as flat as 50:1. To achieve thisglide angle, it is often necessary to removevegetation and hills and perform extensiveearthwork operations far from the airfieldproper. Thus, avoid locations that requireextensive work to achieve the necessaryglide angle.

A similar clearance is required on the sidesof runways. An area of specified widthmust be cleared of all obstacles and gradedaccording to specifications.

SUNLIT SLOPES

lf tactical concealment is not required, lo-cate roads on the sunny, exposed sides ofvalleys or hills, particularly in wet or coldareas. This permits the road surface andsubgrade to dry rapidly, minimizes icy con-ditions, and makes maintenance easier.Prevailing winds should also be considered

2-4 Site Selection and Reconnaissance

Page 13: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

when locating roads. Prevailing winds willcarry snow, rain, and sand onto the road -way, if the orientation of the road is un-desirable. Protective snow or sand fencesshould be oriented to take into account theprevailing winds.

TACTICAL CONSIDERATIONS

Frequently, it is necessary to construct tem-porary roads or heliports or to improve land-ing strips to move personnel and materials.When this is the case, consider the follow-ing tactical factors:

Defilade. Locate all roads in a defiladeposition on the reverse side of a hill orravine to avoid enemy observation and toprovide cover from direct artillery or mortarfire.

Camouflage. When constructing a road orairfield in an exposed area, take advantageof all natural camouflage and concealment.

Defense. Air fields in forward areas areprime targets for enemy air and ground at-tacks. When designing the airfield, dis-

perse the facilities to minimize the effects ofbombing or strafing attacks. It may benecessary to use ground troops in defensivepositions against enemy ground action.

FUTURE EXPANSION

Due to the unpredictability of military opera-tions, engineer troops are often required tomodify and expand previously completedconstruction. The road that is adequate fortoday’s maneuvers may be inadequate fortomorrow’s operations. Airfields built forsmall aircraft with a limited evacuation mis-sion may have to be modified to meet morestringent design criteria for accommodationof high-performance aircraft, Improvementand expansion are a continuing job on allmilitary construction.

Try not to construct a road or airfield in arestricted area where there is no possibilityof expansion. Design basic facilities so thatthey can be used as part of the expandedfacilities. The ability to expand an existingroute or facility will conserve personnel andmaterial and permit rapid completion of fu-ture projects.

RECONNAISSANCE

Reconnaissance operations vary with theoperational environment; the assigned mis-sion: and the size, type, and composition ofthe reconnaissance element. An aerial,map, or ground reconnaissance is necessaryto determine the best existing or best pos-sible location for a future road or airfield.

MISSION

The primary mission of a reconnaissanceparty is to find a site meeting most require-ments, to recommend a general layout andconstruction plan, to estimate the work re-quired to construct the facility, and to ob-tain the data needed to determine a comple-tion date and detailed construction sched -ules. When the reconnaissance mission iscomplete, the reconnaissance report servesas the basis for tactical plans and construc-tion schedules.

The final construction plans and schedulesare made with regard to the tactical andlogistical situation and the constructiontime available. The reconnaissance report,submitted by personnel conducting the in-vestigation, must be complete, comprehen-sive, and sufficiently detailed to permit care-ful analysis,

RECONNAISSANCE-PARTYCAPABILITIES

Thorough reconnaissance requires qualified,trained, and experienced personnel. Thequality of the reconnaissance is directly re-lated to the abilities of the party accomplish-ing it. This is especially true in airfieldreconnaissance, which requires broader en-gineering judgment than any other engineerreconnaissance, Even a qualified civil

Site Selection and Reconnaissance 2-5

Page 14: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

engineer with civilian or military experiencerequires special training for this activity. Itis unusual for one person to be proficientin all the items a thorough reconnaissancemust include. Therefore, the assignment ofpersonnel to the party must provide for itsoverall efficiency as a unit. The party mustbe selected with regard to the conditions itmay confront.

Factors to be considered include the road -net, the general nature of the terrain, theweather, the prevalence of land mines, theattitude of the civilian population, and theamount of enemy resistance the party mayexpect. These factors also influence theequipment assigned to the party. The equip-ment should include all items necessary forsoil and topographic surveys, mobility,security, and good communication. The suc-cess of the mission depends on proper per-sonnel and equipment. One without theother will not accomplish the neededresults, If available, a soils or terrainanalyst is a valuable member of the recon-naissance party, If an analyst is not avail-able, obtain soil samples for later analysis.

Ž

STEPS IN RECONNAISSANCE

Reconnaissance involves the steps that fol-low. Ž

Planning

Planning is concerned with the formation ofa reconnaissance mission. It involves thecoordination of reconnaissance efforts by ap-propriate headquarters, the estimation ofneeds, and the assignment of a reconnais-sance mission. Both ground and aerialmethods should be integrated. This is aresponsibility of the engineer brigade, thegroup, or the battalion, not the individualreconnaissance party. Reconnaissance mis-sions are based on user requirements asgoverned by ground forces. Maintain closeliaison with all headquarters to achieveproper coordination, Improper coordinationresults in duplication of effort in someareas and inadequate reconnaissance inother areas.

Briefing

The briefing tells the reconnaissance partyexactly which site or area is to be recon-noitered, what is already known about thearea or site, and what information the partyis expected to obtain, Details concerningthe time or methods of reporting the infor-mation will be included in the briefing. Theparty must also know the type of facility forwhich it is reconnoitering. If a site hasbeen tentatively selected or if some informa-tion has already been determined from apreliminary study, the party must be in-formed. Otherwise, time and effort will bewasted. A soils or terrain analyst shouldbrief the reconnaissance party, if such anexpert is not able to accompany the party,If available, aerial photos should be used inthe briefing.

The following information is necessary for afull understanding of a particular reconnais-sance mission and should be covered in thebriefing:

The general area to be covered, if anarea reconnaissance is to be conducted;or the exact location of the site orfacility to be investigated, if a specificreconnaissance is to be done.

The nature of the proposed facility; thetypes of vehicles or aircraft scheduled touse it; the length of time such use is an-ticipated; and the minimum require-ments concerning dimensions, grades,and clearances. (These items arecovered by reference to the applicablestandard layout and specifications pub-lished by the joint force commander inthe theater. They are usually familiarto the reconnaissance officer but shouldbe kept for reference.)

The anticipated vehicle traffic and num-ber of aircraft and personnel to be ini-tially accommodated at the proposedfacility. (When dealing with airfields,figures are often given in terms of thenumber and type of aviation units to beassigned to the installation. Strengthand equipment figures should also beavailable for reference.)

Ž

2-6 Site Selection and Reconnaissance

Page 15: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• The minimum amount of aircraft ser-vice, repair facilities, and special re-quirements needed.

• The expected future expansion of thenew facility.

Ž The expected construction time avail-able for building support facilities.

Ž Information previously obtained aboutthe proposed project.

• The essential details concerning thereport and how, when, and to whom thereport should be made,

When the reconnaissance party is to beaway from its parent unit for a lengthy, con-tinued reconnaissance, the following addi-tional instructions must be covered in thebriefing:

• The location where rations, clothing,and equipment replacements can bedrawn.

Ž The source from which petroleum, oils,and lubricants (POL) supplies can bedrawn.

Ž The service facility where vehicle main-tenance can be obtained.

• The form of communications to be ar-ranged; for example, radio, messenger,or telephone.

When ground reconnaissance is orderedahead of forward ground-force elements, thefollowing additional instructions are neces-sary:

Ž Friendly-force situation.

• Known enemy-force situation,

• Location of adjacent friendly units.

The following instructions are applicableonly to parties engaged in air reconnais-sance:

• Alternative and emergency-landing in-structions.

• Location of available aviation petroleumsupplies.

• Location of the forward flying line.

Preliminary Study

The preliminary study consists of studyingthe information obtained during the brief-ing, conducting a map reconnaissance ofthe area involved, studying aerial photos,delineating soil boundaries, assemblingother available preliminary information, andplanning and preparing for the actual recon-naissance.

Sources of information that may be usefulin the preliminary planning of reconnais-sance missions and in the preliminarystudy of a specific mission are discussedbelow. Such information must be verifiedby ground reconnaissance.

• Intelligence dossiers that provide plan-ning data and other information on aparticular airfield site or route that mayalready exist. These dossiers are theresult of previous reconnaissance orreconnaissance plans and can usuallybe obtained if adequate coordination ismaintained with higher headquartersand other units engaged in reconnais-sance. Similarly, reports of aerial recon-naissance that were conducted in an-ticipation of later ground reconnais-sance may be available from adjacent orhigher units.

• Strategic and technical reports, studies,and summaries on specific areas of ac-tual or potential military importance areprepared by the Office of the Chief of En-gineers and subordinate agencies.These reports provide the best dataavailable at the time they were printed.Topographic, geologic, and soil maps, aswell as data on the climate andgroundwater tables, are usually in-cluded. These reports may contain in-formation on water supply, construction

Site Selection and Reconnaissance 2-7

Page 16: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

materials, vegetation, and special physi-cal phenomena.

Ž Army and Air Force periodic intelligencereports are important, reliable sourcesof information. Intelligence reports areusually prepared in the interior zone,but periodic intelligence reports arefield-prepared reports of all-aroundforce elements. They include factslearned by prisoner-of-war interroga-tions, tactical data, reports, records,and interrogation of local inhabitants.Intelligence reports are used to preparestrategic and technical reports.

• Road, topographic, soil, vegetation, andgeologic maps published by friendly orenemy govern ments and agencies aresources of information. Maps showingthe suitability of terrain for variousmilitary purposes may be of consider-able value in planning roads and air-fields.

Ž Aerial photographs show the ap-proximate amount of grading and ex-cavation required, the total area and ex-tent of promising sites, the extent ofnecessary clearing, the presence offlying hazards (for airfields), and thearea and local drainage conditions.

Ž If time and facilities are available,topographic maps should be preparedfrom aerial photographs.

Ž Weather reports published bygovernmental agencies and the AirForce Air Weather Service are used todetermine critical factors for runoffdetermination, prevailing winds, andcloud cover which will affect construc-tion and future operations.

Ž Aeronautical reports and charts providean overview to help plan aerial recon-naissance.

Ž Indigenous governmental agencies mayprovide valuable information on a greatdiversity of subjects.

Air Reconnaissance

Air reconnaissance involves a general studyof the topography, drainage, and vegetationof the area. The construction problems,camouflage possibilities, and access routesshould be visualized. Usually the specificground-reconnaissance procedure isplanned by selecting, from the air, areasthat need investigating and by determiningwhat questions need answering. Air recon-naissance can provide valuable negative in-formation by eliminating unsuitable sites,but it cannot be solely relied on for positiveinformation.

Ground Reconnaissance

While air reconnaissance can effectivelyreduce the amount of ground reconnais-sance, it cannot replace ground reconnais-sance. It is on the ground that most ques-tions are answered or that questions tenta-tively answered from the air are verified.Often ground and air reconnaissance arenot separate missions, A continuing airreconnaissance may be interspersed withspecific ground reconnaissance.

REPORTING

The reconnaissance party must always sub-mit its report on time. Reports are sub-mitted for all sites investigated, even if thereconnaissance party considers the site un-suitable.

Full details on the method, place, and timeof submitting reconnaissance reportsshould be included in the instructions givento the reconnaissance party. Reconnais-sance reports can be submitted in writingor by radio. A radio report should be fol-lowed by a detailed written report. Stand-ard reconnaissance reports are preferred.They ensure full coverage of needed informa-tion and allow a comparative evaluation oftwo or more sites. Standard formats arehelpful in comparing sites which have beenreconnoitered by different parties. Theysimplify each party's work in preparingreports.

2-8 Site Selection and Reconnaissance

Page 17: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Military roads and road networks aredefined according to location and use.They are classified according to width, sur-face, and obstructions. Terms and for-mulas approved by the member nations ofthe NATO, the Southeast Asia Treaty Or-ganization (SEATO), the United States, theUnited Kingdom, the Canadian andAustralian Armies Nonmaterial Stand-ardization Program, and other treaty na-tions are covered in FM 5-36.

Abbreviations, symbols, and notations usedin route reconnaissance (described in FM 5-36) may also be used in airfield reconnais-sance. Information given in road reconnais-sance reports is useful in reporting on ac-cess roads to airfield and heliport sites.

AIR RECONNAISSANCE

An air-reconnaissance team generally con-sists of only two members: the pilot andthe engineer observer. Having the officer incharge of the ground-reconnaissance partyact as the engineer observer is ad-vantageous and should be arranged whenpossible. Time is saved and errors of omis-sion are minimized when a report from theengineer observer to the officer in charge ofthe ground-reconnaissance party is notnecessary except as a matter of record,The pilot can also assess the site and makethe appropriate recommendations.

Two -place, fixed -wing aircraft or two-placehelicopters are suitable for most air-recon-naissance missions, Reconnaissance ofenemy-occupied airfields is best ac-complished with modified tactical aircraft.

Effective air reconnaissance should providethe following information:

• Determination of terrain features.

Ž Description of obstacles.

• Evaluation of LOC.

Ž Assessment of suitability of the area forvarious types of construction.

• Identification of available sources ofwater.

• Supply evaluation of constructionmaterials in the area of operations.

• Discussion of cover and concealment.

GROUND RECONNAISSANCE

The composition of the ground-reconnais-sance party depends on the scope and ex-tent of the mission and the nature of theterrain it must traverse. The compositiondepends upon the probability of contactwith the enemy, the attitude of the civilianpopulation, and the prevalence of mines inthe area to be reconnoitered. Table 2-1,page 2-10, provides a list of personnelsuitable for an airfield reconnaissance. Thelist can be modified to meet the particularneeds of the situation.

All personnel involved should be trained inground reconnaissance. It is importantthat the person in charge and the assistantbe well versed in all aspects of reconnais-sance.

All equipment needed to carry out the as-signed tasks should be taken. The equip-ment varies as the composition of the partyvaries. A typical list of equipment suitablefor the party is listed in Table 2-2, page2-10.

Map and air studies are not substitutes forground reconnaissance; they only reducethe amount of ground effort required.Ground reconnaissance should determinethe following information:

• Estimated grades to be encountered.

• Estimated amount of clearing involved.This includes trees, tree stumps, andboulders. Sometimes objects such asbuildings and concrete foundations areincluded.

Ž Consideration of debris generatedduring clearing operations. In some

Site Selection and Reconnaissance 2-9

Page 18: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 2-1. Typical airfield ground-reconnaissance party

Table 2-2. Suggested equipment list for airfield ground-reconnaissance party

2-10 Site Selection and Reconnaissance

Page 19: Army Construction Manual FM5 430 Vol1 Entire

cases, the trees removed may be used inthe construction operation. Details ofclearing operations are discussed inChapter 4 of this manual.

• Nature of soil encountered, field deter-mination of gradation, percentage offine-gradient materials, and plasticitycharacteristics.

• Conditions of streams at crossing sites;width, depth, and velocity of the stream;condition of the banks and streambed;and indications of high water levels.

• Presence or absence of local construc-tion materials, including possible sour-ces of sand, gravel, cement, tar, asphaltculvert pipe, and lumber, Local con -struction capabilities and labor condi-tions are included.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• Estimated amount of earthwork neces-sary, the approximate balance betweencut and fill, and the necessity for longhauls of earth material.

• Errors or discrepancies on the mapsfrom which the site was tentativelyselected and the effects of such errorson the selection.

Ž Local rainfall data and other pertinentinformation about seasons and weatherobtained through local inhabitants orother sources,

• Information or observations which affectthe final facility location.

• Relationship with the local population.

ROUTE AND ROAD RECONNAISSANCE

Thorough reconnaissance is essential in theselection of roads. It starts with a study ofavailable maps and aerial photographs.Aerial reconnaissance provides valuable in-formation. Detailed information, however,can be obtained only by ground reconnais-sance. Reconnaissance performed in con-nection with military LOC is route recon-naissance. Reconnaissance to check exist-ing roads is road reconnaissance. Recon-naissance to determine the location for anew road is location reconnaissance.

ROUTE RECONNAISSANCE

Route reconnaissance includes gathering in-formation about roads, bridges, tunnels,fords, waterways, and natural terrain fea-tures that may affect the movement oftroops, equipment, and supplies in militaryoperations. Route reconnaissance may behasty or deliberate. A hasty route recon -naissance is conducted to determine the im-mediate trafficability of a specified routeand is limited to critical terrain data. Itmay be adequately recorded on a map over-lay or sketch and be supplemented byreports about various aspects of the terrain,

A deliberate route reconnaissance isdetailed. It provides the data necessary fora thorough analysis and classification of sig-nificant features along a route, includingrepair or demolition procedures, if required,An overlay is used to point out exact maplocations, and enclosures are attached tothe overlay. The enclosures are DA Recon-naissance Report forms that provide a per-manent record and ensure enough detail isrecorded, The use of these forms is ex-plained in FM 5-36.

ROAD RECONNAISSANCE

Road reconnaissance is conducted to deter-mine the traffic capabilities of existingroads and to provide more detailed informa-tion than is needed for route classification.It may include enough information todevelop work estimates for improving theroad to certain standards of trafficabilityDA Form 1248, shown in Figure 2-2, pages2-12 and 2-13, is used to record this infor-mation. Maps, overlays, and sketches areused as necessary.

Site Selection and Reconnaissance 2-11

Page 20: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-2. Sample Road Reconnaissance Report, DA Form 1248

2-12 Site Selection and Reconnaissance

ROAD RECONNAISSANCE REPORT I OAT29 AU~ 86 For un or Ih1t form , .. FIoA ~<u~ tor .... ponlllf')l ltq .... n !, TP_OOr:

"fO IH •• ouat'", OI'Ht"fIiO r.eo"n.~u'flc.i ::'ROM : ..,.",. qrtH ,f1d ut't.ti 01 Offlt.f or NCO m.lw,,, '~om'J.I"*I'I'e.'

COR. ArT",: S -2 . 21:Jr EtlC,R . BN. ~_M{)ONEY, s,c:-c, ca.4, 2/s?: £NGI? aN.

I' I • COUNTRY e SCALE SHEET NUMSER OF -..AP'; 2 DAfEIT!Me GAOUP

I':r. LEtlI'fAIU> WtJob 4fV1:5 V733 '01 ""n.ruf.l U.p!'!: ;/: SCl,OOO i SHE'€ r ,5.5(0 I El 1~9 1430Au4 84-I SPEC.IAL I

SECTION I - GENERAL ROAD INFORMATION

3 ROAD GA'D REFER£NCE j .. ROAO .... ARKING (CIIfI;I." Of .."III.ty l'Iumo., 01 fOW) , lENGTH OF "OAO (Alii .. (N .,10""'""

I UT 09'19P9

I_If FROM

ffovrl! ilJr 12"864 VIRGiINIAt ~/7 I' /fM. "WIDTH OF .. OAOWAY(F_or_ ._'/)'1 I. WEATHER OU'UNG RECONNAISSANCE (1.01_ /ai, _loll. It __ I

'-.7," "" 9.3", FAIr<. • rt:MP 79° 7 RECONNAISSANCE

O"TE I TIME LA5r RAIN .&;4u.. - IS Al..IG, 88 '29 Ao4 88 0"15

SECTION 11 - DETAILED ROAD INFORM" nON /W_ 0"".""1",, ... _mIt """" _."od "'10""''''''' riI". ._" In an _or .... ,"" __ .,.." .... ',,", _ _ ot __ .S_.,.-_o._1 I. ALl_1Nl /c __ ONl.Y) 10. ORA'NAGI!I~ _ONLYI

11, !'\.AT GRADIENTS ANO EASV CUIIIVlI 11, AOEQUATE DITCHII. CIIOWI'IICAMIIER WITH "DEQUATE

12, nup GRADlI!NlS rr._ ot 1 lit fOO) CULVE"'TS IN GOOD CONDITION

(3) SHAAPCUIIVUI __ ._ '0011,_) (2) INADEOu,oTl OITCHI!S. CIIOWMiCAMHfI 011 CULl/PTa,

V V ITS CU~I/ERTS 0fI OITCHII .... IIILOCkED 0111 OTHEfI-(4) STEEP' GR"DIENTS AND SHA"p CU"'VU WISIIN PQO'" CONDIT.ON

" FOUNDATION (C_ ..... ONI."

V l (\, STAIIILIZEOCOWAcr ..... TEAIAl Of 0000 OUAlITY 121 UNIT ...... LOOU OIIIEASILV OIIJll'l.AC«l) MATEA'''L

It _'''01 EIUCIIll'TIOItt~ ,_ 'h _ 01

L THt! SUl!f'AClIIlI(C_ ..... ONty!

v' 111 fila Of POTHOI.I!II. _. OfIIlU'tS UKI\. Y TO (:I) !lUMPY. ~~ /I'OTMOI.ED TO All !XTl!NT UKEI. Y

RIDUCE CONI/OY_O TO lllOU OY SNEO

b. TYf'I! OF SUIIFllCE IC __ ONlYI "-'" ';'/) (\) COHCRETI! (I) \'iIITEIlIIOUH ~OAAI (2) llTUMlNOUS 1'-111 /)''''' ...... kno .... )· llIIoGlIa'-e. / --

f\'il AlLIO V A SP}/AL 1" ~

~ ~TAIILllEO SOt~. SANOClAV. SHl!LL. ~ IIlNTI!GIlATIO GRANITE. 0lIl OTHER

I3IM'CKr_, TER' .....

/_1 '-~ ~) OTH8!I_""~

Cl, C_HEO ROCK 011 COMl. " SECTION III OeSTRUCTlONS /LioIltt'IIO ____ - _ .... ""_wIIWt.".." .... " __ oI._. If/rtw,,, .. loItol_' __

---~,-~ ~ '/~ /.,O __ ' __ '_f4_or4.n __ .. ~~. __ -"-""I>uIId""" /0/ __ "' __ ... __ , .. ,, __ .__ '" , __ .-bul/dittfll.

to, En...,...~ fAbOft 1 Ht '00' (II/C __ ...... 'oo_I·_I .. _

/0/-

SIIIIAL NU .... !! .. PART'CULAR, GAIO REfERINCE "EMARKI . 0 0 rI

.1TE t:P GaA PE - 8% ur l/(fg1~ :200,"" ~

SHARP C!~Ii.VE ur 11'2..1377 [,f"Plu5 '/-1""" J

le ()NSr'~JC.TION UT 11'2 a'1g 1t..7Mf fU'"e 3oo111t1 Ltwt;,. !r!()/J 51"R.,allcul rr fQ5"f/9lD 1'1. . "JJb" If)" _ ~AJ<:'

DA FORM 1248, 1 JUL 80 PREVIOUS EDITION IS OBSOLETE

Page 21: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-2. Sample Road Reconnaissance Report, DA Form 1248 (continued)

Site Selection and Reconnaissance 2-13

IlCTlOtt IV , IIIL UGI CM"'"

t--________ ---"=T:..:L. _________ -tlCa". 'ts 11>,.,. •

... - UT 122864 1 ~:' = 29Aug sa

(oa) Con.strlctiOn.

(os) ConstrIction

S~l!p Curve

Steep GN!de

REVERSE OF DA FORM 1248, 1 JUL 80

--~~~----'b.O~-----------~

ad T.3/9.31"11 kb (oe)

-----11.0

A 7.0/9.01"11 Kb (oe)

------6.0

8CC;O (-Fp) .,Ye. 7m J<b (OS)

Page 22: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The most important factor in planningmilitary roads is making maximum use ofthe existing roadnet. Subject to the require-ments of the tactical plan, the existing road-net must be adapted to military use beforeundertaking new construction. Existingroads should be surveyed at the earliest op-portunity to determine their condition andcapacity. Time is saved by improving an ex-isting road rather than constructing a newone.

Periodic road reconnaissance is conductedto obtain information about the road situa-tion in a specific area. A situation map isprepared and kept current to show the con-dition of roads, the density of traffic, theneed for maintenance work, and the resultsof maintenance. Periodic reconnaissanceimportant during wet or unusually dry

ENGINEER

weather to determine the effects of theseconditions. Maintenance requirementsbased on periodic reconnaissance must becoordinated with the agencies using theroads to ensure proper standards of main-tenance and to avoid work on roads nolonger needed.

LOCATION RECONNAISSANCE

When a new road is necessary, the firststep is the location reconnaissance. This re-quires reconnaissance of all possible routesto ensure selection of the best route. Themain objective of a location reconnaissanceis to locate a new road that will withstandanticipated traffic and provide the best pos-sible operating conditions.

is

Engineer reconnaissance is often conductedin conjunction with deliberate route recon-naissance to determine route conditions (in-cluding work estimates) and to locate con-struction materials to improve or maintainthe route. It is either a general or specialreconnaissance. General engineering recon-naissance gathers engineering informationof a broad nature within the operationalarea to locate and evaluate construction

RECONNAISSANCE

materials, resources, terrain features, andfacilities that have engineer implications.Special engineer reconnaissance obtainsdetailed information regarding an investiga-tion of a specific site or evaluates the poten-tial use of an undeveloped facility such asan airport or heliport. DA Form 1711-R isa required enclosure to the route reconnais-sance, as specified in FM 5-36.

AIRFIELD RECONNAISSANCE

Airfield reconnaissance differs from road-location reconnaissance, described in FM5-36, in the scope of information. An air-field project involves more personnel,machine-hours, and material than a roadproject. Air traffic imposes more severelimitations on its traffic facilities thanvehicular traffic. Consequently, the siteseIected must be the best site available.

PLANNING AIRFIELD RECONNAISSANCE

Tentative airfield sites are selected withinenemy territory using map and aerial

photograph reconnaissance, supplementingdata from reports of aerial observers or in-telligence sources. These sites may be un-developed potential sites or operating enemyinstallations. Reconnaissance should beginas soon as possible.

For an undeveloped potential site, the ob-ject of the reconnaissance is to verify oramend tentative selections and layouts andto estimate the material, equipment, andtroop requirements for the constructionplanned. If it is a captured enemy airfield,

2-14 Site Selection and Reconnaissance

Page 23: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFP 93-4. Vol 1 FM 5-430-00-1/AFP 93-4, Vol I

a decision is needed on whether to use thecaptured field or develop a completely newsite. Estimates of the engineeringessary to restore the airfield mayquired.

New airfields added to an area inaircraft are already operating canoped in the following manner:

effort nec-also be re-

which ourbe devel-

• Select the best available map of the areain which the new airfields are to be lo-cated. Draw a 5-mile-diameter circlearound existing airfields and shadethem. Note all high-tension, electrictransmission lines and shade a 2-mile-wide strip centered on these lines. Lo-cate and shade all similar obstructionson the map. Assault or hasty airfield se-lection is discussed in Chapter 10 of FM5-430-00-2/Air Force Pamphlet(AFPAM) 32-8013, Vol 2.

• Confine the study for potential airfieldsto the unshaded parts of the map. Lookfor sites of sufficient area, preferablyflat with good natural drainage, unob-structed air approaches, and accessibil-ity to routes of communication. Assignthe most likely sites to reconnaissanceparties for appropriate air and groundinvestigation.

SELECTING RUNWAY LOCATION

A convenient way of selecting a runway loca-tion at a site that meets glide-angle require-ments is to prepare and use the ah-field-sit-ing template illustrated in Figure 2-3, page2-16. This template can be drawn on ace-tate or heavy cellophane for use on anymap to meet specifications for flight way,horizontal approach, and glide angle. Whenplaced on the map, the template shows landforms and natural or manufactured obsta-cles that are in or above the plane of theglide angle.

In Figure 2-3, any hill within the approachzone at a distance of 8,000 feet from theend of the overrun and having an elevationof more than 160 feet above that of the endof the proposed runway, is in a 50:1 glide

angle. This runway location is unsuitableaccording to the specifications. The tem-plate is useful to the reconnaissance officerand to the preliminary planning group. Pre-pared templates can measure distances infeet, yards, miles, and kilometers by placinggradations along their edges.

PROCEDURES FOR AIRFIELD AIRRECONNAISSANCE

The general procedure for an air reconnais-sance follows:

En route to a particular site or a generalarea, the engineer notes open borrow pits,large stockpiles of construction material,rail and road accesses to the site, and er-rors on maps that have been studied. Thepilot plays an important role on the recon-naissance team. Besides chauffeuring theengineer officer, the pilot considers ap-proaches, mental hazards, and physical ob-structions related to tactical aircraft thatmay use the proposed installation. A pilotwho is familiar with operational require-ments and the performance characteristicsof tactical aircraft is more valuable thanone who is not.

The engineer observer assesses possible con-struction problems at a potential site. Theengineer selects tentative sites and directsquestions to the ground reconnaissanceparty. The engineer receives the pilot’s sug-gestions concerning the flying-related charac-teristics of the sites investigated and modi-fies estimates according to these recommen-dations.

To be effective as an engineer observer theofficer should possess the following qualifica-tions:

• Knowledge of road and airfield require-ments and construction procedures andexperience in airfield work.

• Immunity to airsickness. An airsick offi-cer cannot effectively accomplish air re-connaissance. Any tendency of the engi-neer observer to become airsick isgreatly enhanced by the continual con-centration on a particular site and by

Site Selection and Reconnaissance 2-15

Page 24: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-3. Sample airfield-siting template

the steep turns and maneuvers essen-tial to continued observation.

• Proficiency in map reading. Upon ap-proaching a designated or tentativelyselected site for reconnaissance, the nor-mal altitude for the first circuit is ap-proximately 300 feet. Nothing morethan orientation can be accomplished inthis circuit. Sometimes a site tentative-ly selected during an area search can beeliminated during this circuit or thenext few passes.

Similar second and third passes are flown.During these circuits, obstructions, mainslopes, and general features are noted. Thepilot begins to formulate an estimate of theflying-related characteristics of the field.Pinpoints for the ends of the runway are

made on the map, but additional tripsshould be flown across the area, if neces-sary.

After the runway has been selected, an ini-tial low pass is made at about 50 yards toone side of the proposed centerline. Asecond pass in the opposite direction isflown on the other side of the centerline.Both of these flights should be made at aconstant air speed so the runway lengthcan be estimated by multiplying the airspeed by the average flight time.

NOTE: The length usually is overes-timated when flying at low air speeds if astrong wind is blowing along the center-line. This can be decreased if the distan-ces obtained by two passes in opposite

2-16 Site Selection and Reconnaissance

Page 25: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

directions along the centerline areaveraged (assuming the wind is constant).

A final circuit is then flown at approximate-ly 200 feet. During this trip, the ends andcenterline of the runway are given a finalcheck, and the pilot completes the appraisalof the field’s flying suitability.

In departing, the observer reviews dispersalareas and again checks access roads. Addi-tional passes over the site are made if ques-tions arise as a result of this last check.An air reconnaissance report similar to Fig-ure 2-4, page 2-18, may be used.

An area reconnaissance then proceeds bysimilar inspection of other possible sites,Complete notes must be kept to avoidreviewing sites already checked however, areinvestigation of the final site selected andany selected alternative sites may some-times be necessary.

PROCEDURES FOR AIRFIELD GROUNDRECONNAISSANCE

The general procedure for ground reconnais-sance follows:

The ground-reconnaissance phase ispreceded by map and air reconnaissance todiscover what specific sites and questionswarrant ground investigation.

En route to the site or sites to be inves-tigated on the ground, the reconnaissanceparty should properly record the generalcondition of roads and bridges, the locationof usable or repairable railheads, the locallyavailable materials and equipment, and thepotential water points. When reconnais-sance of a definite site is involved, a moredetailed observation of the access routeshould be made. A check must be made ofbridge capacities, overhead clearances, andfeatures that might hinder the movement ofconstruction equipment to the site, as wellas the suitability of railheads and sidingsfor use in construction. A detailed reportof the quantity and quality of materialsavailable at quarries, pits, and stockpilesmust be prepared.

When the site to be surveyed is reached,the most likely locations for a runway mustbe investigated. If the terrain is openenough to permit good observation, theselocations may be quickly determined. Loca-tions for runways are traversed by vehicleor on foot. A rough survey of each selectedrunway is carried out immediately. Lengthsare paced, critical slopes are measured witha clinometer, and directions are determinedwith a magnetic compass. The type of soilis noted and observations of a few samplesare made. A preliminary check of a pos-sible runway can be made in 15 minutes, ifthe country is reasonably clear and open.

If the country is rough and is not sufficient-ly open to permit a quick selection of run-way locations, a detailed search must bemade on foot. The reconnaissance officer,accompanied by necessary personnel, fol-lows the centerline of the area for the run-way and dispersal areas. The reconnais-sance officer notes on a large-scale map orsketch all obstacles that cannot readily beeliminated, such as gullies, rock outcrops,and swampy areas. Examination of theresults discloses the possible runway loca-tions.

The best runway location is selected by con-sidering these centerline investigations withprevailing wind direction, air approaches,glide angles, groundwater conditions, dis-charge areas for collected runoff, clearing,grubbing, and earthwork. If a suitable run-way does not exist, a negative report on thesite is submitted.

Once the selection of a potential runway ismade, a careful and detailed walk of thecenterline of each runway is made torecheck its suitability. Stakes are driven ateach end of the runway and prominent fea-tures are properly referenced to later ex-pedite the location of the selected runwayby construction unit surveyors.

The survey sergeant of the reconnaissanceparty stakes out the centerline of the run-way and runs a ground profile of it at thecenterline and at each shoulder line.Levels are taken at 500-foot intervals

Site Selection and Reconnaissance

and

2-17

Page 26: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-4. Air Reconnaissance Report

at intermediate breaks or slope changes. In eluded in the report. A suggested report for-flat country, this interval may be increasedto as much as 1,000 feet. If an alternativerunway is selected, a similar survey is con-ducted for that runway, if time permits.The soils analyst conducts a field investiga-tion of the soil conditions at the site, Referto Chapter 7 of this manual for more infor-mation about soil conditions.

Previously acquired information is checkedat the site for accuracy. Errors, includingdiscrepancies on maps and mistakes inaeriaI photograph interpretations, are in-

mat is shown in Figure 2-5:

When possible, local inhabitants are inter-viewed to check information already ob-tained and to obtain more information.Several opinions should be obtained. Ques-tions should be phrased to provide the bestcomparison of answers. Information mustbe weighed carefully with regard for thecredibility of each person questioned.

The reconnaissance of a designated siteshould be accomplished in one day, unless

2-18 Site Selection and Reconnaissance

Page 27: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-5. Ground Reconnaissance Report - Undeveloped Airfield Site

Site Selection and Reconnaissance 2-19

RlCOfllfllA,S\.A"'Cl RlPOHI

ufIIDEVELOPEO A,Rflllll SIIE

10 Comm.nCltnQ QUlc.r :5:1.7 rN'~R QN FROM CO C CP _____ _

Note - Th. 'econnil,h,llnl..t' ,hutV mUll bi:' fu,nl~ht'tJ .,.,.!h UIt" '0111,,,,,, "\I,nlurm ... on

1

2

3

4

locillon 'uf .II,t't!'ld g~nt:, .. 1 Uf ilJt'l.IItL

b TvPt!' of • .,t.:rlllh Ihdl Will occuP'r' "'t' IIIlfI'I'hl

c f\.Iumbt'f 01 ,,'uuj):» .ea"t'Cle:d 11..1 uCCu~y 11,,: ,urlt ... I"

DESIGNATIO'" "'don" C'It'Ef. ""-EtY #,4"" Nu,,,,,,·, I AlleF/EL.D

LOCATION IJ"vs v'J.,..,~r 0" .,A"",.ANP /I1IP DFP~ • M.~ ,.I",."cw""'l1!t4i.4! "'I'''''£i'4I<''u l'~ •. " .. ,,, __ -.....:.2~:L:..::j!....---'F::...!.;-=----------­

S('4.61:..I .. ' ,fIIAME .nd SCALEI

Ldllh . .lClt! & lon .... ludco ·:, ... ~·r"';,;:, 7';;-",," Md~ ~ vullhll,II .. :» t( U8p(A. E 8'&(1<:' 'l d Ntt~,by lown~ (tr'I"LTEN.y4.tf(fue <gal (£1rfJ Dye L,sr ,rhn ;flU

,S,/e: dlSlanclI!' .. nu ctUt:"LI1U'( hUIII :o.IIt', t;~If~D ~At/£J. A'cAO ,.tr""" .' re ROADS ~S:lOI tI-r cdc,rlNt(41(( .... cF"c«r,llrrlLitf W"~I'" "-ol.tJe.1L 12."1-2 NEr

""~ ..:unc.hllun bl,dVt!i 'oHho ,:,_ • AAILROAP$ J"e{..t'N.JU Vd,.,.,,,,, If" s(Q(.nl dT %"9'*"1" 42 m" #1 £de r pr SI rC·

IGdYt' cundlllon c.)I'!t 1.1 Ill..t" I'ulll ::'111' itrllJ.nw c.;dj).JL.lly lunnt'l,

GENERAL DESCR,PTlO'" Of LAfIIOlfllG AREA AfIIO <;UHHUUfIIO,,,,u COUNTRY '';CCAY' '-#,(' vI h'tft'l'L fi'd.DIO sr41'relt/ 51""'£ Nql!( pCCLyrtQN ((OMC Fel PC'tNdvfiyr ,Dqys

6 GLIDE A~IH.iLES Mt";U", UNe/MIUP IN MqSr D,u(r«l6'1 scE IrE.., '7

ID"~'1ton s.lu,",t' dl'!tldll~t"1 ANr£lvAlA, FilA-NI Ar hi N. S IS IS-n" tV o,r Sire;' 1 fLIGHT OE.STRUC110fll5 A"'O MEflllAL HAlARO~ CL£vl'T"EP w.orlfit -r"ow{lt AT 11 v'" C or SirE.

,RdVlflt'5. 1..1"" muufll •• ,n'!t .. ,ull"" ::.tlt'~JJIe:!I t.::tHnlnlt'y::. to"-'t!.!t powt'r Ilnt'!t to". I

8 MEIEOROI...OliollAl CONDITIONS ttvEfrChY ..... <A('N- «rruc",tI·a.'tad, ",,0 PIEC,ecr4Tm('l4.«oJ!4,'v.

'P't"\I,III,tI/lW W'V1.llh '!tlut"':. l,u:»1 IJf~ll,"ldllon Irml)t:'tdhJlt'! v,sllI,hl"

9 HYOROlOCilCAL CONDITIONS SrPEdf-S G6I eACH .'flOC o,.c:= SIrE "UN Ta erSC,T4lfjay Rp/Ca

10 ORA'fIIAul <,iaQQ

ISI't:".I"'~ \.I'UIIIHI.....,.IIt" 1I ••• "II..UIII'II,un::. IIUd! v,I",lllon::.,

<VA w?AL pRAINAGe

11

12

13

14

16

1 J

18

19

Ifl.11 '!tltlj)ln~ cJll~l'I'Un IIUlllll~1 ul • ul",,~'1 pi ... ,.

SOIL TYPb A"'O uEOlO(';'CAL OA 1 A _-'C:"'~A!.:Y",-.J!.A2..y,","a2.._q!::U.r~AiU<V::'E~L'--_____________ _ ISdn(1 W'd"".:1 Cld~ !tdl U' (Un.II,'l.IIIt)II'!t ,,, ... o\lI""u6» t.:ordl lutf .... llId'cl

CLEARINli..(lQ AUN'S,,.£" CLC&«",s eFe(' "'O,4UD rT,es-f'''IIA«M«&,o ,r#4..,' lu,LpcKl_ ,A'~d it I It:" diU' Ut'n!tll'r uf Ilmh~t IUI."::.I w."4D "".,1 74 .£ IlE""I~$A

PROPOSED LAYOUT N' C .. SW «NWV' U1F EltJ.1r,@ If.lDQ S .S"<',r,l 81lNk/4v$ 't.(tUD+L' 'cL

Ilo~ dllun "nU U.';:;llun ut , I,In~d" .. tiel tll::.", ... '::'dl ,yslem , .. Udl.1I .1I.~lch)l C·,~,,· ,,~("-,.AS· RECOMME"'OlD SURf AlIfllu h4< 'If ;ScMILA~ ""pua' C SUPCBC WG

,PSP SMl PR,S llIe-dldn" .. d' ::.1"UII./.IlIon cor.' luftl

CAMOUFL~GE i<crr,,: CIA TWA4 CQI1ICFtl4M1fNc AfEgfPJ)£Q, d.p,."uAU Otlp;rt,Mb IGsS/.£. ICU""tH c.;unc.;cdlmt!nl IJISVt'r!tlun tJt!(;t:f,lIIOnl

BIVOUACAREIAS VJ~ ~.f(3T<41<i Pa''1,z:qtCtE5 - ..... ILL ACC.Qw""qPAzE ~rQ MEN

ILocallon SIlt!' cuvcr p,e:vlou!illy UCl.up,,:!tJl .MA" STI.A/IIfS A',"OIJ)

WA.TER SUPPLY &Me~ €,€VAr€f) rAttltt "ao DISr«"au Z7"IY 1 ysriH 1ft( Opa.fTIO'Y #DP€QF~" ;~ .. moN. ISUUfC~ h,u .. dllun QUdnt,I'r Qu •• I'hIJ£-.lA~t" rll~ArllllMr "'.'IIS 1I~AMf..P.tVll '~"ltIy O"C~AIJ'£;'

EXISTING rAClUrlES ('''CrC'e w'C,ty6 ,5wtAQeC tU««"lO'1 t'7+<1T Blr INsr44'£P lBudu,nys 'IIU'''We: PO""&!' ""dl~1 k'hll!'fIllWt!" C,6A ... ,1. p,r +'~,. f:flf&'J~~{: ':,~""L PIT.

MATERIALS AVAILA.BLE "0 ..... ,11 p+A,vt w"C'dEEl!£ ,PArL ur 1l/4L4G£:

.~qulpm~nt bulluVv P'I!!. W'IIIlf'tI!l o.nk~ qUd".e, mine dump, 11mb."

20 WORI( ESTlMAIE OUAfIITIT'ES CI •• 'ln" _-"r{:La~i..I'iIlUr",",I ... Q,",I:Ja.l..t:"..ir,-__________________________ _

tAI.,cI ~IJII!' ul IlmulI!" ue:ns"YI

b O'llln.wll!' GUt( Plr&€"f 4CalMl.a URIM€rFti 9' '''AlwAy ,earl r;. s-rUdM

IL.ntl4r Ict!'1 01 UIJt'n lMl.:hlnw I\umll~' ut lulv~fb ... mount 0' IJlpe .nd .pproa,m.te dl.m~lerJ

E.,.II n'O""lnW ,..q"g"r "(0"" C'<a((;. YP$ NO I1e"""" '&a(L pR LqNe:. tjAUL

IEsIIIIl.It:' tu, R W T W H 5,

d Surt4c.;Inw rAy -9 Qcur lfl~ POg id' ET ,t,rz&

.Oudnlll-w- tur R W 1 W H S 't:'commt:'nUt'tJ I'¥'l).'

RUdd' "llt:'~nd :.t:"V~CII! :/ CL" ~ T'5 £,.sI's r SqME "tvICE - KELp ('lPe4 EMEAVT!Kf.J IMdt:'5 cundlllonl

Bu'I(.lin",~ &E;'fEN r tlJ.PQs. ;5'1< r-,l'4' E 1/ulL a ("f(N're.:z.<. 7P WC£1f . l~u",lIe" .. nu Illlt' lull.lIdll'¥' to. ope'8110n, ql,l.nlll'lng.

;; i i'ME ES T,MA YE fOR COMPL[ T 10fll _____ ....:;;=I<--... Cl"l:2..:.....-_ .. P,,'dz...z:V-"S'-____________ _

22

23

24

Ill' IBn (JAl~ 0' Co d''r'11 AOOITIOfllAL IfIIfORMAT,Ofll 1- ojIo'r_ tI~APWIf: ,.,A'I ", .. 41"41J"£ r.r_,." ""D D~prt>" Pu~/t:

'4tI"",,,'EM#AI"Y':Y, ClvnhlN Pe,f'S~AlAlLL ut' IIII'£A (10" .. 0 IIC Mr&.J' F_~ /'00<' ~IJC""-" ",,"riVer ~"PEA~ r.rI~A<p,y. ""pr "r I"Rr>P"'SCP A-....... A"y #,/NNJr c.",r~CT>_ D<lc,y NIIIP <1",&1 ., .... _t'~,S/,"", 1'."",,. If' KII"."

"fIIfIIEXES $"cE Arrtf('h'ED ItUP "'1'2 o rEA! • 1y

SIG"'ATUR( IM""~:=51~11o,.mlJlrlo'

Page 28: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-3/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

hostile forces delay the work. A specificreconnaissance of a captured enemy airfieldis somewhat different from that outlinedabove. Detailed information about the exist-ing facilities and their condition is desired.The specific information needed is indicatedon the suggested form for reconnaissancereports of captured enemy airfields shownin Figure 2-6.

When the reconnaissance parties are operat-ing at a considerable distance from theheadquarters directing the reconnaissance,it is imperative that an initial report reachheadquarters without delay. Use organicradio equipment and the suggested message

format in Figure 2-7, page 2-22. The tacti-cal situation may dictate the amount of in-formation transmitted. Unit standingoperating procedures (SOPS) should indicatewhat information is critical for radioreports. A complete, written report shouldfollow the radio report.

The formats illustrated in Figure 2-4, page2-18; Figure 2-5, page 2-19; and Figure 2-6, are suggested for written reports. Thereports should include the same items of in-formation shown on these forms. Suitablesketches should be attached to all writtenreconnaissance reports. Figure 2-8, page 2-23, is a typical sketch.

2-20 Site Selection and Reconnaissance

Page 29: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-6. Ground Reconnaissance Report - Captured Enemy Airfield

Site Selection and Reconnaissance 2-21

FROM

RECONNAlss"'''ce REPORT

CAPTUREO ENEMY AlIFlFIELO

3.2 7 EN(7R ,8#

_-,=C~o~..!=c,--___ Cl' _______ OAlE

DESJGNATlON N .. m .. .2ikNsLO ,eNtia ,4d'T/EI.l) I\j"m"." _-!/~ _____________ _ lOCATION P&Nt",PAJ.1 r}l (Ill'" 2Jt:IHQa

Ma" , .. I~f~nc., Milp.tr [(,41. c I r-t: E, ..... """ ___ .!...-'::...:=~:....!.... __________ _

,Na"'" .. nil s,.'''' ,MSL, L.I"Ul;t!' .NI longtl",d. 'ri2 S'sltl, 3'7 :13' e M ... ~ cuo,d,,, .. tt"!a

d N,,,,,t,, ,u",,, • .3bt:!:;'" q_t;e ,$ rill ""'It.'! 1'1 E 01'" Se,-§' POeG;,L~-rI"N A!k?u-r ¥CI?O

3 RUNWAYS

8

I, '2

No 1 EwPv..vWA)' "'7~ eo No 2 N S Pv ........ ",Y ;J 7<'0

Nu 3 /loA/£"

HAROSTANOS lliumC"" ~ h .....

CONDiTiO'" OF AIRFlhD FACILITIES

; ....... a. "')"0 ;;,. ;; 6)' »tA, ... U»"""'" l e.»t'ri f.) t. tqq T r I W"C C q" +u<+ htr'cu lv(Q1?«'C'« r,,;'

RUf\lN'dVS, rEt"qt"'PA'y "''''.N' ....... y Que !Iv r «<£p:r M/Alp g "C PAI<r Mel r (41tHI'''' ff£€-PJ

b Tfu.WdVll "Q9D 7Y'6t.HID.fNq

HarQS1"n/lS "t!hqr ..-Atl'" vr €ACt' (/lc;dU,I:-. AOTdC€""'T Weeri!' "'e"', €N'" ",I(IIJ!tr (i RUdt,l!. IClass1tv us~ng symool~1 ~DJt "",Q,.., r rA!AF"""

d. "',L"" I"",t><Mf £4['- A~W9;::-r <6, ':='0." N<JR,# A.il.ty'3o,.,.r K6

"

.2. S~'V!,~ " /1/17 K'b G'$Ul!r"Ii::' stot4V~-EMaAN.rllf£Nr- PeR r£C""s'l2 pey""' , T""IJIA4£ A~E-"''' /'Is. "1"'AI'tIK~ t!)N

iNumD¥'t u, tdO"'~ I..dUdlt,)l\' U S VdIS' PIPE" kiN'£:.

8Qtflb >ifiU dfflmU"ltlon Lh"nlU\ $IAlfI • ..f~ re; i r/ill"'f E

St!!t.ot.tMlii.: l;dnlJ,(ff~ N9"':: rc?' '$E~)(" <:;,:-1"[4£ O,e ~€ PAI/2AlJ~ If Cqa'Qt rice( ISI"~ "IJI" LU('IthltOlH :/16,/£h'£,o BUT r:AN~ pc

Oth\.t" >'-ldL~ rlv,tddul~ eN" r ,rptC'y llRICK 8J.Ptir Ilc"r<SO~r - 4'4$14. V e€, r9..('1!!.a

ON6 ,,~~ INumbll!'( ul bun\J.ny" lI:Q "'/f/::u,'IO .-IIA'IA 3.,.l""tI ~';a,.r &.I/w __ L:1 ".t.4~K Sf'loi,i '3l)dt.it,r,,~(,~ Jlt'tI~'.r .. y J~E!2 4S ..$1/0# "'~.A .4LHDS"""'" r~tJfPMI"'''''' "'€"''''(N'~tt,

lt4ulT'"b~' ut th.lHQ,nV$ IQ tJl

StQld\lit ~i,)dt..c:' CU\l ... t~fJ A;~1.:"~ f:1':-~ OCtrn --:::i.I;A.;==77""lnI"":::==-"=::-::="""-'::-="""'-6,....11_ s .. ::W $V¥r,AIf Jtri.'.""'I..'tI .p-""Aal1J~I'If"J)3 1fItIIh",.2 »"AIA ~.,.. ,,, .. 4.-

O, ... n.Vt" 'h~tt:"m 9' 'Y'U· , Y" Ooef'l "'''''"'' ·n "'K" '1"9",,4 J.tlr" ',9< e' ; T VUI!:' ~.rtU''It .nu IVCoHi" 01 {J4I"'4Wt:"S: 10(:"'101\ 0' ourt,.JI I ,JIIP' "."", .. A "'1'" '4fJA"

Ul"'!,n Pu--II"J ,fNP "",P£~ ""#""&;""1"1£ 11, Wdltof SYUUh -CtrtL /' ~,¥,«C Ne 1:Jt,<",(',tl"f"/fM' sr; r€Nf~ "c ,.,IJ{ Peg rc, tlgN

I21 S~Wfl!.'(.,,~ S\t!ttt'm vyr.pgg4!! _dr#;,.,t:' 'Yl ~€C! %'€pr CL {'.I«"'''' t 't'<,,9 9< f(JI'ff4,.ph~" 131 Erffclfl('!h "(14«<<1 cfeC."" r£. 4"H"ure< IV' aM ",fMtfg'P 8C)l'wYP :fi!!PAJR 14. "'r.'rttln~ 'vSlt,om5 it"1Ptff -::..:N.:..:<:~N'-l<""-,«"I{,,",<Wli:p:,,#",",a,,-_________________ _

Ot·\e-t 1dt.d'ttfl!.'~ f'Wr""<64 "'"bM'«« 'P€«K'r<~:lO """",...,.. ,<It c !tUGC ,s(1 "'(4'1 <!'

._~, ~~;~J'(J~J..,iRo~'lII!HII' ,J';P0W'Jj,,'8(Jou}j!~ "'i,.;,'PJJ,I'ji'l£' p, :lll. ",,,,. 'Ii . R •• tfl,;ttus.:z:!IWt«b {""'=!4C£ ... p, .... , .htY49 re ea'T

tf,r:c"" At,,, fllw'1" os .., .. IU:P At:IES

Page 30: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-7. Air Landing Area Report

2-22 Site Selection and Reconnaissance

I ~, undinl SillS Ltttll desipation

A

B

C

0

E

F

G

H

I

J

Airstnps (Runw,ysl letter dlSllII.IICItI

A

8

C

D

E

F

G

H

AIR lANDING AREA REPORT

EaplalllliCltl

Map sheel(S1

Dall .nCl time of cdeclioll 0' infarmation

Location Will r.'erllltesl

Runw.y

III 81111nl

12) lInatf\lIId widlh

III Gradients IItlldinl slandards

141 ROUlh .ptII'aisII 01 earttl work

15) FusIbility of runw.y ext.nsion

Dru." Major oOstKIIs to llyinl

111 Wilhm tll •• pproach ZOll.

12) Outsld. the allPlOIth zone but .. iII 5 1IIi11s

Type of sod

Wbetller sUltabl • • 11. lor diJpersiIs till be lound

lataIlISOUItlS

APIlfO.clI roads

uplan.tlon

M.p slleetlsl

D.le .nd tlm. of collection 0' Inform.tiCltl

Loc:alJOn (11Id relerencesl

DimenSions

Type .nd condlllon 0' IlIe .lIstnp

Access by road

FelSlblllty 0' runw., utension

Any otfIer l"formallGn such IS work required, in m.ft· hours. 10 m.ke tile •• rstnp servic:e.bie lor sustained or hmlted openllofts

Report air landing areas by serial number. The appropriate letter designation must precede each category of Information reported.

Page 31: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 2-8. Typical sketch to accompany airfield reconnaissance report

Site Selection and Reconnaissance 2-23

o o

I--~-~I ~

..............

............ ----"'--... -----

.~ -~ ------

.~-

s;fe ske fch 1:.1.'" 000

I I --

Page 32: Army Construction Manual FM5 430 Vol1 Entire

3

Surveys and Earthwork Operations

Construction Surveys

Construction Stakes

The Mass Diagram

SURVEYS ANDOPERATIONS

FM 5-430-00-1/AFPAM 32-8013, Vol 1

EARTHWORK

Construction surveys are initiated when new construction isnecessary. These surveys reveal the kinds of stakes to be used:provide data for earthwork estimation, including which methodof estimation to use; and provide information for use on themass diagram. The finished survey books should be filed withthe construction project records of the Operations and TrainingOfficer (US Army) (S3).

Earthwork operations are one of the most important constructionaspects in road and airfield construction. Earthwork reqiresthe greatest amount of engineering effort from the standpoint ofpersonnel and equipment. Therefore, the planning, scheduling,and supervision of earthwork operations are important in ob-taining an efficiently operated construction project.

CONSTRUCTION SURVEYS

Construction surveying is the orderlyprocess of obtaining data for various phasesof construction activity. It includes the fol-lowing surveys: reconnaissance, prelimi-nary, final location, and construction lay-out. The reconnaissance and preliminarysurveys are used to determine the best loca-tion. The remaining surveys are conductedafter a location has been established.

The purpose of construction surveys is tocontrol construction activities. The numberand extent of surveys conducted isgoverned by the time available, the stand-ard of construction desired, and the

il bilit f l d t i l I

ducted for a deliberate project in the com-munications zone. The quality and efficien-cy of construction is directly proportional tothe number and extent of surveys and otherpreplanning activities. The principles andtechniques of field surveying are discussedin detail in technical manual (TM) 5-232and FM 5-233.

After completing a thorough constructionsurvey, transfer the design information frompaper to the field by construction stakes.These stakes are the guides and referencemarkers for earthwork operations.

M k th t k th t th t ti

Page 33: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

RECONNAISSANCE SURVEY

The reconnaissance survey provides thebasis for selecting acceptable sites androutes and furnishes information for use onsubsequent surveys. If the location cannotbe selected on the basis of this work, itmust be determined by the preliminary sur-vey.

PRELIMINARY SURVEY

The preliminary survey is a detailed studyof a location tentatively selected on thebasis of reconnaissance, survey informa-tion, and recommendations. It consists ofrunning a traverse along a proposed route,recording topography, and plotting results.For roads, it may be necessary to conductseveral preliminary surveys if the reconnais-sance party has investigated more than onesuitable route. Establish, station, andprofile the route centerline with horizontaland vertical control points set. Take cross-section readings to allow rough calculationsof the earthwork involved. (Sometimescross sections may be taken during thereconnaissance survey if the conditions war-rant.) If the best available route has notbeen chosen, select it at this time.

The airfield survey consists of establishingcontrols, noting terrain features, measuringglide-angle clearance, making soil profiles,and investigating drainage patterns and ap-proaches. Accurately establish the finalcenterline during the survey.

FINAL LOCATION SURVEY

When time permits, conduct a final locationsurvey. Establish permanent bench marksfor vertical control and well-marked pointsfor horizon tal control. These points arccalled hubs because of the short, squarestake used. On most surveys, the hub isdriven flush with the ground, and a tack inits top marks the exact point for angularand linear measurements. The hub loca-tion is indicated by a flat guard stake ex-tended above the ground and driven at aslope so its top is over the hub. Hubs are

2 inches by 2 inches and the guards areflat stakes, about 3/4 inch by 3 inches.

Horizontal Control

The purpose of horizontal control is to ac-curately determine points for the variousfacilities of an engineering project. Estab-lish permanent, well-marked points forhorizontal control and reference them at thesite before construction begins. On a largefacility, establish a grid network and use itfor this control. Tie the network into themilitary grid system in the particular area,if such a system has been established. Onan airfield, place control points beyond theclear zone. These points define the center-line of the runway and other important sec-tions of the airfield.

As the taxiways and other facilities are laidout, establish and reference new controlpoints. In laying out the centerline, placetarget boards at each end of the runway sothe instrument person can make frequentchecks on alignment while the line is beingstaked out. Target boards may be set upon any line that requires precision align-ment. Reference control stakes to ensurereplacement, if they are disturbed or lost.Locate the target board just beyond the out-ermost control-point stake.

Vertical Control

Vertical control methods determine the dif-ference in elevation between points. If avail-able, establish a level reference surface ordatum from a known bench mark. Differen-ces in elevation, with corrections, are sub-tracted from or added to this assignedvalue, resulting in the elevation of thepoints. Take the datum of the bench marksystem from a known elevation orbarometer reading or make an arbitrary as-sumption.

CONSTRUCTION LAYOUT SURVEY

The construction layout survey is the finalpreconstruction operation. It provides align-ments, grades, and locations that guide con -struction operations. The survey includesdetermining exact placement of the

3-2 Surveys and Earthwork Operations

Page 34: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM

centerline; laying out curves; setting all culvert sites; and performingremaining stakes, grades, and shoulders; quired to begin construction.

32-8013, Vol 1

other work re-Continue this

staking out necessary structures; laying out survey until construction is completed.

CONSTRUCTION STAKESUse construction stakes for centerline,slope, offset, shoulder, grade, reference,ditch, culvert, and intermediate slakes andfor temporary bench marks. The stakesshould be approximately 1 inch by 3 inchesby 2 feet. Use finished lumber when pos-sible. If it is not possible to usc finishedlumber, usc small trees or branches blazedon both sides and cut to length. Finishedgrade stakes and temporary bench marksare 2 inches by 2 inches by 12 inches.Place stakes using a three- to five-personcrew equipped wtth transit, level, rod, tape,ax, sledgehammer, and machete.

The primary functions of constructionstakes are to indicate facility alignment con-trol elevations, guide equipment operators,and eliminate unnecessary work. They alsodetermine the width of clearing required byindicating the limits of the cut and fill atright angles to the centerline of a road.

Mark and place construction stakes to con-form to the planned line and grade of theproposed facility. Use colored markingcrayons to mark the stakes. Use a uniformsystem so the information on the stakescan be properly interpreted by the construc-tion crew.

Construction stakes indicate-

Ž The stationing or location of any part ofthe facility in relation to its startingpoint. If the stake is located at a criti-cal point such as a point of curvature(PC), point of intersection (PI), or pointof tangency (PT) of a curve, note this onthe stake.

Ž The height of cut or fill from the existingground surface to the top of the sub-grade for centerline stakes or to theshoulder grade for shoulder or slopestakes.

• The horizontal distance from the center-line to the stake location.

Ž The side-slope ratio used on slopestakes.

The number and location of stakes used dif-fer between roads and airfields. A typicalset of construction stakes consists of acenterline stake and two slope stakes andis referred to as a three-point system.Point one is the centerline of the facility.Points two and three are the constructionlimits of the cut and fill at right angles tothe centerline.

CENTERLINE OR ALIGNMENT STAKES

The centerline or alignment (hub) stakes,shown in Figure 3-1, are placed on thecenterline of a road or air field and indicateits alignment, location, and direction. Theyare the first stakes placed and must be lo-cated accurately. These stakes are used asreference points in locating the remainingstakes. Centerline stakes are placed at 100-foot (or 30-meter) intervals. On roughground or sharp horizontal and vertical

Figure 3-1. Centerline stakes

Surveys and Earthwork Operations 3-3

Page 35: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

curves, place the stakes closer together.On horizontal curves, also stake the PC, PI,and PT. On vertical curves, also stake thepoint of vertical curvature (PVC), the pointof vertical intersection (PVI), the point of ver-tical tangency (PVT), and the low point (LP)or high point (HP) of the curve.

Place centerline stakes with the broad sidesperpendicular to the centerline. The side ofthe stake that faces the starting point isthe front. Mark the front of the stake witha for centerline and, if applicable, PC, PI,or PT. Also mark on the front the distancefrom zero or the starting point in 1 00-footstations and the fractional part of a station,if used, For example, marked ona stake indicates it is 654.22 feet from theorigin of the facility and is known as thestation of this point. Stations are used inlocating sections of construction and inpreparing reports.

PIace the amount of cut or fill required atthe station on the reverse side of the stake.A cut is marked C; a fill, F. A centerlinestake, placed at station 78 + 00 and requir-ing a fill of 6.0 feet to bring this station upto the final grade line, would be placed andshown as indicated in Figure 3-1, page 3-3.

The amount of cut or fill indicates the dif-ference between the final grade line and theground line where the stake is emplaced. Apoint on the stake is seldom used as theline of reference to the final grade.

To prevent misinterpretation of the amountof cut or fill, mark decimal parts of a foot,as shown in Figure 3-1. The decimal partis written smaller, raised, and underlined.Facing the direction of increasing stations,the centerline forms the dividing line be-tween the right and left sides of the area tobe graded. When facing either side of thecenterline, it is customary to refer to theareas as the right or left side.

SLOPE STAKES

Slope stakes, shown in Figure 3-2, definethe limits of grading work. When used inread work, they can be used as guides in

Figure 3-2. Marking and placement of slopestakes

determining the width of clearing necessary.The area to be cleared usually extends 6feet beyond the slope stakes. Set slopestakes on lines perpendicular to the center-line (one on each side), at points where thecut and fill slopes intersect the naturalground surface. Stakes at points of zerocut or fill are placed sloping outward fromthe centerline.

Sloping the stakes outward allows the equip-ment to work to the stake without removingit. The slope indicates the direction of thecenterline of the road and enables the equip-ment operators to read the stakes more easi-ly. Place slope stakes at 100-foot intervalson tangents and at 50-foot intervals onhorizontal or vertical curves, Whenever asharp break in the original ground profileoccurs, it should be staked.

The front of a slope stake is the side facingthe centerline. On this side of the stake,mark the difference in elevation betweenthe natural ground elevation at this pointand the finished grade at the edge of the

3-4 Surveys and Earthwork Operations

Page 36: Army Construction Manual FM5 430 Vol1 Entire

shoulders. Under this figure, place anotherfigure that indicates the horizontal distancefrom the centerline of the road to the slopestake. Place the station number on theother side of this stake. Below the stationnumber, indicate the appropriate sloperatio. Figure 3-2 shows the proper mark-ings for a slope stake in a typical situation.

OFFSET STAKES

Equipment used on a cut or fill section maydestroy or remove many of the grade (center-line, shoulder, or slope) stakes. To preventloss of man-hours and repetition of surveywork, caution construction crews to protectgrade stakes whenever possible. Place off-set stakes beyond construction limits toavoid resurveying portions of the road torelocate these stakes. Figure 3-3 shows off-set stakes used to relocate the originalstakes.

Place offset stakes on a line at right anglesto the centerline of the facility. Fromthese, the slope stakes can easily be lo-cated. After relocating a slope stake, relo-cate the centerline stake by measuringtoward the centerline of the road thehorizontal distance indicated on the slopestake and placing the new centerline stakethere.

An offset stake contains all the informationgiven on the original slope stake plus thedifference in elevation and horizontal dis-tance from the original slope stake to theoffset stake. Mark the offset distance onthe front of the stake and circle it to indi-cate it is an offset reference. If the offsetstake is at a different elevation from theslope stake, the cut or fill value must be in-creased or decreased by the difference inelevation. An offset stake placed a horizon-tal distance of 10 feet from and 1 footabove the right slope stake would be placedand marked as shown in Figure 3-3. Coor-dination between the surveyor and grade su-pervisor concerning the meaning of themarkings is most important regardless ofthe type of marking used.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 3-3. Marking and placement of offsetstakes

FINISH-GRADE STAKES

Use wooden stakes, 2 inches by 2 inches,with tops colored red or blue, for finish-grade stakes. Blue or red tops, as they arecalled, indicate the actual finished elevationof the final grade to which the completedfacility is to be constructed. They are usedwhen the grade is within a short distanceof the final elevation. Do not use thesestakes in combat road construction exceptin areas with steep slopes. This type ofstake normally requires a guard stake toprotect it and indicate its location. Onlarge projects, it may be impractical to useguards with each stake.

There are no markings on finish-gradestakes other than the color on the top.These stakes may be set for use with thetop of the stake exactly at the finishedgrade or with the top of the stake above thefinished grade, as decided upon by the sur-veyor and construction foreman.

Surveys and Earth work Operations 3-5

Page 37: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

With the stakes set and marked at apredetermined distance above the finishedgrade, stretch a string between two stakesacross the work and use a graduated ruleror stick to check the elevation. On an air-field layout, place these stakes along thecenterline, edge of pavement, intermediatelines, shoulder lines, and ditch slopes. Forroad work, place stakes along the centerlineand the edge of the shoulder; they may ormay not be placed on the slopes.

REFERENCE STAKES

Many hubs marking the location of high-ways and airfields are uprooted or coveredduring construction. They must bereplaced, often more than once, before con-struction is completed. AS an aid in relocat-ing a point which may become hidden byvegetation, or as a means of replacingpoints which may have been destroyed,measurements are made to nearby per-manent or semipermanent objects. Thisprocess is known as referenceing or witness-ing a point. On many surveys, permanentobjects may not be available as witnesses.In such cases, additional stakes may bedriven. These stakes usually are ap-proximately 2 inches by 2 inches by 18 in-ches.

There are no markings on a reference stake.A point can be referenced by a known dis-tance and a known angle or by two knowndistances. A transit must be used in thefirst case and may be used to advantage inthe second, The method of using twoknown distances can be used, however,when a transit is not available. Place twopoints at measured distances from the pointto be referenced. Use two tapes to relocatethe original point or stake. Hold the zeroend of one tape on one reference point andthe zero end of the other tape on the otherreference point. The point of intersection ofthe two tapes at the respective distancesgives the location of the point in question.

To be of most value in replacing a missingstation or point, the reference stakes or wit-nesses will be less than 100 feet from thepoint and, if possible, the arcs should inter-

sect at approximately right angles. Placethem outside the construction limits, and in-dicate their location by blazing trees or addi-tional stakes. Normally, the location of thereference stakes can be obtained from thesurveyor’s notebook.

CULVERT STAKES

Culvert stakes are located on a line parallelto and offset a few feet from the centerline.The information required on the culvertstakes includes the distance from the staketo the centerline, the vertical distance to theinvert, and the station number. Once thesurvey crew has finished staking out the cul-vert, the construction supervisor can placethe pipe accurately by using batter boards.

BENCH MARKS

Vertical control of a road or airfield must bemaintained during construction. To do this,points of known elevation must be estab-lished. Obtain elevations from permanentmonuments, known as bench marks, estab-lished by geodetic surveys. From thesebench marks, run a line of levels and settemporary bench marks (TBMs). On smallprojects the TBMs frequently are set by run-ning the levels from a point of assumedelevation. This is especially true of construc-tion in combat areas.

Usually, TBMs are placed at 500- to 1,000-foot (or 150- to 300-meter) intervals and areplaced off the limits of construction. Stakes2 inches by 2 inches, solidly emplaced inthe ground, may be used for this purpose.However, a nail driven into a tree, a man-hole cover, or a pipe driven into the groundmay also be used. Frequently, referencepoints serve as TBMs. The TBMs are setbefore setting the centerline stakes becausevertical control must be established beforeconstruction begins.

EARTHWORK ESTIMATION

Earthwork computations involve the calcula-tion of earthwork volumes, the determina-tion of final grades, the balancing of cuts

3-6 Surveys and Earthwork Operations

Page 38: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

and fills, and the planning of the mosteconomical haul of material. The exactnesswith which earthwork computations aremade depends upon the extent and ac-curacy of field measurements, which inturn arc controlled by the time availableand the type of construction involved. Toplan a schedule, the quantity of earthworkand the soil and haul conditions must beknown so the most eficient type and quan-tity of earthmoving equipment can bechosen and the appropriate time allotted.

When time is critical, the earthwork quan-tities are estimated either very roughly ornot at all. When time is not critical, higherconstruction standards are possible andearthwork quantities are estimated and controlled by more precise methods.

FUNDAMENTAL VOLUMEDETERMINATION

The volume of a rectangular object may bedetermined by multiplying the area of oneend by the length of the object, Thisrelationship can be applied to the deter-mination of earthwork by considering roadcross sections at the stations along theroad as the end areas and the horizontaldistance between cross sections as thelengths. The end areas of the cross sec-tions must be computed before volumes canbe calculated.

METHODS OF END-AREADETERMINATION

When the centerline of the construction hasbeen located, measurements are taken inthe field from which the required quantitiesof cut or fill can be computed. A cross-sectional view of the land is plotted fromthese measurements. The cross sectionsare taken on vertical planes at right anglesto the centerline. Where the ground sur-face is regular, cross sections are taken atevery full station (100 feet), Where theground is irregular, they must be taken atintermediate points as determined by thesurveyor. A typical cross section is shownin Figure 3-4.

Figure 3-4. Typical fill cross section

Plot ground elevations from the surveyor’snotes. Make a sectional template of thesubgrade that shows the finished subgradeand slopes plotted to the same scale as thecross sections. Superimpose the templateon the cross section and adjust it to the cor-rect centerline elevation. Trace the tem-plate and extend the side slopes to intersectthe original ground. If the section involvesboth cut and fill, draw only the appropriatelines of each template. When the sectionsare completed, begin the end-area measure-ments, then determine the volume. Of theseveral satisfactory methods of measuringthe end areas, only the trapezoidal, strip-per, double-meridian (triangular), andplanimeter methods will be described inthis manual. The method chosen willdepend upon the time available, the ac-curacy desired, the aids at hand, and theengineer’s preference.

Trapezoidal Method

The trapezoidal method is widely used todetermine end areas. The computations aretedious, but the results are accurate. Inusing the trapezoidal method, the area ofany cross section is obtained by dividingthe cross section into triangles andtrapezoids, computing the area of each partseparately, and taking the total area of theverticals to the ground line (Figure 3-5,page 3-8) in order to divide the cross sec-tion into two triangles and two trapezoids.Make the assumption that the ground isperfectly straight between these selectedpoints on the ground line. While this isnot usually correct, the assumption iswithin the accuracy normally required.

Surveys and Earth work Operations 3-7

Page 39: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 3-5. Cross section in cut withverticals drawn at critical points

Basic Formulas. Before the area of thecross section can be computed, the basicformulas for the computation of the areasof triangles and trapezoids must be under-stood. If a line is drawn, as shown in Fig-ure 3-6, from one of the vertices of a tri-angle perpendicular to the side or base (b)opposite this vertex, the line formed repre-sents the altitude (h) of the triangle. Thearea of any triangle can be expressed asthe product of one-half the base multipliedby the altitude. This relationship is ex-pressed by the formula:

Figure 3-6. Triangle base and heightdimension locations

A trapezoid is a four-sided figure havingtwo sides parallel but not equal in length,as shown in Figure 3-7. If the two parallel

sides of the bases are crossedby a line perpendicular to each, the dis-tance between the two bases along this per-pendicular line is the altitude of thetrapezoid. The area of any trapezoid can beexpressed as the average length of thebases multiplied by the altitude. Thisrelationship can be expressed by the for-mula:

Figure 3-7. Trapezoid base and heightdimension locations

Computation of Areas. The first step in com-puting areas by the trapezoidal method isto break the cross-sectional area into tri-angles and trapezoids by drawing verticals,as shown in Figure 3-5. Then determinethe area of these small figures by the ap-propriate formula.

To determine the appropriate dimensions,the notes taken by the surveyors must beknown. The cross-section notes taken inthe field are in fractional form. The figurebelow the line indicates the horizontal dis-tance from the centerline to that point onthe ground. The figure above the line indi-cates the ground elevation of that point.Points on the grade line of the proposedroad are written in a similar manner andare obtained by computations from the finalgrade line to be established, as shown inFigure 3-8. Thus, the note 32.0/21 indi-cates a point that is at elevation 32.0 and21 feet from the centerline of the road. If

3-8 Surveys and Earthwork Operations

Page 40: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

the cross section is divided into triangles Stripper Methodand trapezoids by erecting verticals, obtain The stripper method is a variation of thenotes for the centerline, shoulders, and end trapezoidal method. To use this method,of slopes to solve for the area. consider a section such as that shown in

Figure 3-9.

Figure 3-8. Cross-section cut showingdistances and elevations

To solve the triangles and trapezoidsformed, consider the bases of these figuresto be vertical and the altitudes to behorizontal. All vertical bases are found bysubtracting elevations, and all horizontal al-titudes are found by subtracting horizontaldistances from the closest vertical in thedirection of the centerline.

Examples:

Referring to Figure 3-8, area a], and sub-stituting in the formula for the area of a tri-angle:

Referring to Figure 3-8, area and sub-stituting in the formula for the area of atrapezoid:

Find the areas of the remaining trapezoidand triangle in the same way.

Figure 3-9. Fill cross section arranged toshow the stripper method

Example:

If vertical lines are drawn at equal distan-ces apart, then by the trapezoidal formula,the end area, A, will be given by the follow-ing computation:

Factor in and combine terms:

First, measure (graphically) each length (b)and multiply the sum by the width (w) (con-stant). The distance between vertical lines,w, may be any value, but it must be con-stant throughout the cross-section area. Inrough terrain the vertical lines should becloser together to ensure greater accuracy.

One of the easiest and most convenientways to measure the vertical lines (b) iswith a strip of paper or plastic. Lay thestrip along each vertical line in such a man-ner as to add each in turn to the total.The strip will show the sum of all verticallines in the same scale that the cross sec-tion is plotted. This figure, multiplied bythe value of w, will give the area of thecross section.

Surveys and Earthwork Operations 3-9

Page 41: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Inaccuracies result when either a triangleor trapezoid falls within the limits of w orwhen the area is curved. However, themethod is rapid, and the accuracy is ade-quate under urgent conditions. Figure 3-10shows a typical cross section with a strip-per marked to show the total length of allvertical lines and the value of w. The strip-per indicates that the sum of all verticallines is 21.7 feet: w is given as 10 feet. Ap-plying these figures to the formula, then-

Figure 3-10. Cross section with the sum of allvertical lines added on the stripper

Double-Meridian Triangle Method

The double-meridian method explained inChapter 13 of TM 5-232 gives a moreprecise value for a cross-section area thanthe stripper method. However, it involvesmore time.

With this method, shown in Figure 3-11,the area is subdivided into two series oftrapezoids using the elevations of adjacentpoints and their projections on the center-line (the distances). These trapezoids havebases equal to the horizontal distance ofthe respective points from the centerline,and heights equal to their differences inelevation. Where the difference in elevationis plus, the area of the trapezoid is plus;where the difference is minus, the area ofthe trapezoid is minus. The componentareas are added algebraically. Because thisprocedure uses the sum of the bases of thetrapezoid, the area obtained is double thetrue area and must be divided by 2. Thecomputation is simple arithmetic: subtractadjoining elevations, multiply by the dis-tance from the centerline, add the multi-plied results and list plus and minus quan-tities, add these quantities, and divide by 2.

Figure 3-11. Cross-section area by the double-meridian method

3-10 Surveys and Earthwork Operations

Page 42: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

The steps for completing the procedure forthe double-meridian triangle method follow(refer to Figure 3-11).

1. Start at the centerline ground or gradeelevation, whichever is lower (A). Workfrom the centerline in a clockwise directionto the left (A), (B), (C), (D), (E), (F); andcounterclockwise to the right (A), (G), (H),(I), (F), to the centerline ground or gradeelevation, whichever is higher (F).

2. Working from point to point, multiplythe difference in elevation between each ad-jacent pair of points by the sum of their dis-

tance from the centerline. Point (F) topoint (A) is not considered because the sumof their distances from the centerline iszero. Going from a lower to a higher eleva-tion gives a plus quantity, while going froma higher to a lower elevation gives a minusquantity. Place plus quantities in onecolumn and minus quantities in another.

3. Divide the algebraic sum of the plusand minus quantities by 2 to obtain thearea of the cross section in square feet (sqft). In sections having both cut and fill,treat each part as a separate section.

Surveys and Earthwork Operations 3-11

Page 43: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Planimeter Method

A polar planimeter is an instrument used tomeasure the area of a plotted figure by trac-ing its perimeter. The planimeter, shown inFigure 3-12, touches the paper at threepoints: the anchor point, P; the tracingpoint, T; and the roller, R. The adjustablearm, A, is graduated to permit adjustmentto the scale of the plot. This adjustmentprovides a direct ratio between the areatraced by the tracing point and the revolu-tions of the roller. As the tracing point ismoved over the paper, the drum, D, and thedisk, F, revolve. The disk records therevolutions of the roller in units of tenths;the drum, in hundredths; and the vernier,V, in thousandths.

NOTE: Always measure cut and fill areasseparately.

Check the accuracy of the planimeter as ameasuring device to avoid errors fromtemperature changes and other noncompen-sating factors. A simple method of testingits consistency is to trace an area of 1square inch with the arm set for a 1:1ratio. The disk, drum, and vernier com-bined should read 1.000 for this area.

Before measuring a specific area, determinethe scale of the plot and set the adjustablearm of the planimeter according to thechart in the planimeter case. Check the set-ting by carefully tracing a known area,such as five large squares on the cross-section paper, and verifying the reading onthe disk, drum, and vernier. If the readingis inconsistent with the known area, read-just the arm settings until a satisfactoryreading is obtained.

To measure an area, set the anchor point ofthe adjusted planimeter at a convenientposition outside the plotted area. Place thetracing point on a selected point on theperimeter of the cross section. Take an ini-tial reading from the disk, drum, and ver-nier. Continue by tracing the perimeterclockwise, keeping the tracing point careful-ly on the lines being followed. When thetracing point closes on the initial point,take a reading again from the disk, drum,and vernier. The difference between the ini-tial reading and the final reading gives avalue proportional to the area beingmeasured.

Figure 3-12. Polar planimeter in use

3-12 Surveys and Earthwork Operations

Page 44: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Make two independent measurements to en-sure accurate results. The first is per-formed as discussed above. The secondmeasurement is made with the anchorpoint again placed outside the area beingmeasured but on the opposite side of thearea from its position in the first measure-ment. This procedure gives two compensat-ing readings the mean of which is more ac-curate than either.

To measure plotted areas larger than thecapacity of the planimeter, divide the areainto sections and measure each sectionseparately, as outlined above.

Computer-Aided Design (CAD)

Very accurate measurements can be made ifcross sections arc digitized using CAD.Cross sections can be placed on a digitizingpad, points plotted into the computer and,with one command, the area calculated,

METHODS OF VOLUME DETERMINATION

An engineer can accomplish the necessaryearthwork computations by using the follow-ing methods: average- end-area, prismoidalformula, average-depth -of-cut-or-fill, grid,or contour.

where—

Average-End-Area Method

The average-cnd-area method is most com-monly used to determine the volume bound-ing two cross sections or end areas. usethe formula:

where—

V is the volume, in cubic yards (cy) (1 cy =27 cubic feet (cf)), of the prismoid betweencross sections having areas in square feetof A1 and A2, separated by a distance of Lfeet .

If cross sections are taken at full 100-footstations, the volume in cubic yards betweensuccessive cross sections in squarefeet, may be found by the formula:

In either form, the formula is only accuratewhen A1 and A2 are approximately thesame shape. The greater the difference inshape between the two end sections, thegreater the possibility of error. However,the method is consistent with field methodsin general. In most cases, the time re-quired for a more accurate method is notjustified.

Prismoidal-Formula Method

The prismoidal method is used where eitherthe end areas differ widely in shape or amore exact method of computing volume isneeded. Its use is very limited because itrequires more time than the average-end-area method and gives greater accuracythan is required for most road and airfieldconstruction.

The prismoidal formula is—

Determine by averaging the correspond-ing linear dimensions of andthen determining its area, rather thanaveraging the areas of

Average-Depth-of-Cut-or-Fill Method

With only the centerline profile and finalgrade established, earthwork can be es-timated with the average-depth-of-cut-or-fillmethod. Estimate the average depth of cutor fill between 100-foot stations and obtainthe volume of material from Table 3-1, page3-14, The accuracy of this method dependson the care given to establishing thecenterline profile, the instruments used,and the accuracy of field reconnaissance.

Surveys and Earth work Operations 3-13

Page 45: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 3-1. Earthwork average cut or fill

This table shows the number of cubic yards of earthwork that are in a 100-foot-long section of cut or fill havinga known average depth. To use this table you must know the following:

1. Width.

a. Cut section - the width of the base of the cut, including ditches.

b. Fill section - the width of the top of the fill.

2. Average amount of cut or fill.

3. Slope ratio. Column 2 gives the correct amount of earthwork when the side slopes are 1:1. When theslope ratio is other than 1:1, an adjustment must be made (see column 4).

NOTE: The final answer obtained from the table is for a section 100 feet long. If the actual length ofthe cut or fill is not 100 feet, an adjustment must be made. (For an 85-foot section, multiply by 0.85;for a 50-foot section, multiply by 0.50, and so on.)

However, the volumes obtained by thismethod are generally adequate for mostmilitary construction.

The centerline profile of a road is typical ofthe entire transverse section because of thenarrow widths. Because of the greaterwidth required on an airfield runway, thecen terline profile may be misleading as tothe typical conditions across the entiretransverse width at that point. Therefore,

earthwork quantities for airfields should beestimated mainly from cross sections. How-ever, in the absence of sufficient time, theaverage-cut-or -fill method is better thannone at all.

Determine the following before using Table3-1:

• Average amount of cut or fill.

3-14 Surveys and Earthwork Operations

Page 46: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• Width of the base of the cut or the topof the fill in 2-foot increments between26 feet and 44 feet.

• Quantity to be added to the figure incolumn 2, if the width of the base or topof the fill is an odd number of feet.

Ž Quantity to be added if the slope ratioon both sides is 1.5:1 or 2:1.

NOTE: The table is based upon a lengthof 100 feet between cross sections and aslope ratio of 1:1.

Follow these steps to use the table:

1. Enter column 1 and read down to theaverage amount of cut or fill for the lengthconcerned.

2. Read horizontally to the right and ob-tain the figure under the appropriate baseof the cut or top of the fill in column 2.

3. Make corrections to this figure fromcolumns 3 and 4, if they apply.

4. If the length is not 100 feet between thepoints considered, adjust the answer propor-tionately,

Grid Method

When the quantity of material within thelimits of the cut sections is not enough tobalance the fill sections, material must beborrowed. The most convenient method isto widen the cuts adjacent to the fills wherethe material is needed. Compute thevolume by extending the cross sections.However, where this is not possible, locateborrow pits at some other area. The gridmethod is a convenient method of comput-ing the borrow material available in a givenborrow pit.

In this method, first stake out over the areaa system of squares referenced to pointsoutside the limits of work. The dimensionsof these squares depend on the roughnessof the original terrain, the anticipated rough-ness of the final surface, and the accuracydesired. Rougher terrain requires smallerdimensions to get accurate results. The

squares must be of such size that no sig-nificant breaks, either in the originalground surface or in the pit floor, exist be-tween the corners of the square or betweenthe edges of the excavation and the nearestinterior corner.

By taking elevation readings at the stakesbefore and after excavation, data is ob-tained to compute the volume of borrowtaken from the pit. Figure 3-13 shows aborrow pit over which 25 squares werestaked, To identify the various intersectingpoints, label lines in one direction by num-bers and in ‘the other direction by letters.Thus the intersection of lines C and 3would be labeled C3.

Outline squares falling completely withinthe excavation with a heavy line, Withinthat line, determine the volume of excava-tion for each square in the following man-ner:

1. Label the points on one square, asshown in Figure 3-14, page 3-16,

Figure 3-13. Computation grid system for aborrow pit

2. Points a, b, c, and d are on the originalground line, while and are onthe final ground line. The volume of the

Surveys and Earthwork Operations 3-15

Page 47: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

an hq. (Refer to Figure 3-13, page 3-15and Figure 3-14.) The total borrow-pitquantity also includes the wedge-shapedvolumes lying between the complete solidsand the limits of excavation. For thesevolumes, use proportional surface areas,Use the formula:

A grid is illustrated in Figure 3-15. Thelength of the sides of each square is 50feet. Therefore, given—

Figure 3-14. Excavation volume for one square

resulting form is the product of the rightcross-sectional area A and the average ofthe four corner heights and in cubic yards.

3. The volume represented by each squaremight be computed by the precedingmethod and all volumes added. However,when a number of such volumes adjoin oneanother, it is quicker to use the followingrelation which gives the total volume, repre-sented by all complete squares:

This could be approximated by adding allcorner cuts and multiplying by A, or

In the preceding formula, A is the rightcross-sectional area of one rectangularsolid, is a corner height found in onesolid, is a corner height common to twosolids, is a corner height common tothree solids, and is a corner height com-mon to four solids. As an example, is

An alternative method is to compute thetotal of all cuts at each corner (123 feet),compute the average cut across all squares(123/25 = 4.92), and then multiply by thelength of the sides of the figure.

Figure 3-15. Sample grid-system work sheet

3-16 Surveys and Earthwork Operations

Page 48: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

FACTORS INFLUENCING EARTHWORKCALCULATIONS

On many projects, one objective of thepaper location study is to design the gradeline so the total cut within the limits of thework equals the total fill. The uncertainchange of volume of the material make thisdifficult. It is usually more economical tohaul excavated material to the embankmentsections, thereby eliminating borrow andwaste.

Shrinkage

Shrinkage has occurred when 1 cubic yardof earth, as measured in place before ex-cavation, occupies less than 1 cubic yard ofspace when excavated, hauled to an em-bankment, and compacted. This differenceis due to the combined effects of the loss ofmaterial during hauling and compaction toa greater-than-original density by the heavyequipment used in making the embankment.

Shrinkage is small in granular materialssuch as sand and gravel, and is large in or-dinary earth containing appreciable percent-ages of silt, loam, or clay.

Shrinkage is very high (possibly 70 percent)for shallow cuts containing humus, whichis discarded as unsuitable for embankments.These shallow cuts (usually 4 to 8 inchesdeep) arc called stripping.

Loose and swell refer to a condition whichis the reverse of shrinkage. The earth as-sumes a larger volume than its naturalstate when stockpiled or loaded into atruck. This factor ranges from 10 to 40 per-cent swell and is usually uniform for agiven material.

Shrinkage, however, varies with changes inthe soil constituents and with changes inmoisture content and the type of equipmentused. Consequently, a percentage al-lowance assumed in design may eventuallyprove to be 5 percent or more in error. Acommon shrinkage allowance is 10 to 30percent for ordinary earth.

Settlement refers to subsidence of the com-pleted embankment. It is due to slow addi-tional compaction under traffic and togradual plastic flow of the foundationmaterial beneath the embankment.

Net Volume Calculation

Compute the volume of cut and fill and thenet volume between any two points on theconstruction project. The net volume is thedifference between the volume of cut andthe volume of fill between any two specifiedstations. The net volume may apply to theentire project or to a few stations. Netvolume may be described in a compacted,place, or loose state. Table 3-2 providesconversion factors used to find the netvolume. All calculations are recorded on

Table 3-2. Soil conversion factors

in-

Page 49: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

the earthwork volume sheet shown in Table3-3.

Earthwork Volume Sheet

The earthwork volume sheets allow you tosystematically record this information andmake the neccessary calculations. They pro-vide a means of tabulating earthwork quan-tities for use in the mass diagram dis-cussed later in this chapter. The earthworkvolume calculation sheet, shown in Table3-3, is divided into columns for recordingand calculating information.

Stations (column 1). List in column 1 allstations at which cross-sectional areas havebeen plotted. Normally, these areas aretaken at all full stations and at inter-mediate stations that are required to fullyrepresent the actual ground conditions andearthwork involved.

Area of Cut (column 2). Record in column 2the computed cross-sectional areas of cutat each station. These areas may be com-puted by one of the commonly usedmethods, depending on the degree of ac-curacy required.

Area of Fill (column 3), Complete column 3in the same manner as column 2, exceptshow cross-sectional areas of fill.

Volume of Cut (column 4). Complete thevolume of cut material between adjacent sta-tions and record it in column 4. The mostcommon method for computing volumes isthe average-end-area method (or theearthwork table based on this method).

This volume represents only the volume ofcut between the stations and the volumesreflected as in-place yardage.

Volume of Fill (column 5). Complete column5 in the same manner as column 4, exceptshow fill volumes. Fill volumes reflect com-

This layer varies in depth but is usually 4to 6 inches deep. This material must bewasted because it is not satisfactory toplace in an embankment, Indicate incolumn 6 the volume between stations ofthis humus material over sections of cut.

Stripping Volume in Fill (column 7). Beforean embankment can be constructed, thesame layer of humus must be removed andthe volume replaced with satisfactorymaterial. Indicate in column 7 the volumeof this material between stations over sec-tions of fill.

Net Volume of Cut (column 8). Indicate incolumn 8 the volume of cut material be-tween stations that is available for embank-ment. Column 8 is column 4 minuscolumn 6, because the total cut must bedecreased by the amount of material wastedin stripping, including the organic material.

Adjusted Volume of Cut (column 9). Onecubic yard of material in its natural, undis-turbed state occupies approximately 1.25cubic yards when removed and placed in atruck or stockpile. The same 1 cubic yard,when placed in an embankment section andcompacted, occupies a volume of ap-proximately 0.9 cubic yards. In planningoperations, convert these various volumesto the same state so the comparisons canbe made, Changes in volume of earthworkare discussed in this chapter, and Table3-1, page 3-14, provides the necessary con-version factors. Column 9 is column 8 mul-tiplied by the appropriate conversion factor(in this case, 0.9) to convert it from in-place yardage to compacted yardage.

Total Volume of Fill (column 10). Indicate incolumn 10 the amount of compactedmaterial required between stations to com-plete needed embankments, Column 10 iscolumn 5 plus column 7, plus the amountnecessary to replace the quantity removedby stripping. This figure represents the fill

Page 50: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 3-3. Earthwork volume calculation sheet

material that is available (plus) or required tion 0 + 00. While passing through a(negative) within the station increment after stretch where cutting predominates, thisthe intrastation balancing has been done. column increases in value. While passing

Mass Ordinate (column 12). Column 12 indi-through a stretch where embankment is re-quired, this column decreases.

cates the total of column 11 starting at sta-

THE MASS DIAGRAMThe first step in planning earthmoving plans for economical and efficient comple-operations is the estimation of earthwork tion of the earthmoving mission.quantities involved in a project. This canbe done accurately by one of several The mass diagram is one method of analyz-methods, depending upon the standard of ing earthmoving operations. This diagramconstruction preferred. With these es- can tell the engineer where to use certaintimates, the engineer can prepare detailed types of equipment, the quantities of

materials needed, the average haul

Surveys and Earthwork Operations 3-19

Page 51: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

distanccs and, when combined with aground profile, the average slope for eachoperation. This permits the preparation ofdetailed management plans for the entireproject. The mass diagram is not the com-plete answer to job planning, and it haslimitations that restrict its effectiveness forcertain typres of projects. However, it is oneof the most effective engineer tools and iseasily and rapidly prepared.

CONSTRUCTION OF THE MASSDIAGRAM

Using column 1 (station) and column 12(mass ordinate, cumulative total) of a com-pleted earthwork volume sheet, a massdiagram can be plotted as shown in Figure3-16.

Plot the mass diagram on scaled graphpaper with the stations indicated horizontal-ly and the mass indices (column 12)denoted vertically. Connect all plottedpoints to complete the mass diagram asshown in Figure 3-16. Positive numbersarc plotted above the zero datum line, nega-tive numbers below.

PROPERTIES OF THE MASS DIAGRAM

Figure 3-17 shows a typical mass diagramwith the actual ground profile and finalgrade line of the project plotted. Note thatboth usc the same horizontal axis (sta-tions). The ground profile is placed abovethe mass diagram to facilitate the calcula-tion of the average grade over which equip-ment will work. The horizontal axis is theonly thing these graphs have in common.

The mass diagram is a running total of thequantity of earth that is in surplus or defi-cient along the construction profile. If atone station more material is being cut thanfilled, you have a cut operation at that sta-tion. The quantity or volume of surplusmaterial will be increasing as cutting opera-tions continue through the station, produc-ing an ascending mass diagram curve line.Cutting is occurring from stations A to Band stations D to E in Figure 3-17. The

total volume for the cut at station A to B isobtained by projecting the points on thecurve line at stations A and B to the verti-cal axis and reading the volume

Conversely, if at one station more materialis being filled than cut, you have a filloperation at that station. The quantity orvolume of deficient material will be increas-ing as filling operations continue throughthe station, producing a descending mass-diagram curve line. Filling is occurringfrom stations B to D in Figure 3-17. Thetotal volume for the fill at stations B to D isobtained by projecting the points on thecurve line at stations B and C to the verti-cal axis and reading and adding thevolumes above and below the zero datumline.

The maximum or minimum point on themass diagram, where the curve changesfrom rising to falling or vice versa, indicatesa change from cut to fill or vice versa. Thispoint is referred to as a transition point(TP). On the ground profile, the grade linecrosses the ground line at the TP, as il-lustrated at stations B and D.

When the mass diagram crosses the datumline or zero volume, as at station C, thereis exactly as much material filled as thereis material cut, or zero volume excess ordeficit at that point. The section of themass diagram, from the start of the projectat station A to a point of crossing the zerovolume line, is known as a node. Eachcrossing point on the zero volume line indi-cates another node. The last node may ormay not return to the zero datum line.Nodes are numbered from left to right.

The final position of the mass diagram line,above or below the datum line, indicateswhether the project was predominately cutor fill. In Figure 3-17, where the massdiagram ends at station E, the operationwas cutting; that is, surplus material wasgenerated by cutting and must be hauledaway (waste operation). Borrow operationsoccur when the final position of the massdiagram is below the zero volume line.

3-20 Surveys and Earthwork Operations

Page 52: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 3-16. Plotting the mass diagram

Figure 3-17. Properties of a mass diagram

Surveys and Earthwork Operations 3-21

Earthwork volume sheet

s:-o 2-

c: Cl

0 1ii .~ I/)c:

1/).-- 111'0 Cl) ::Eo (1) (12)

0+00 0 0+75 675 1+50 975 s:-o 2+25 960 2-3+00 850 Cl

E 3+75 575

:J

~ "1+50 0 5+25 -300 6+00 -"lOO

6+75 -380

7+50 -200

.~

Mass diagram

1000

500

0

-500

0+00 11-50 3+00 4+50 6tOO 1+50

Profile

jJ-------------------------~~--------------------~~------~--------~ w

A

Station B

a

--------------

Mass diagram

TP

I I lE

E

Page 53: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

PROJECT ANALYSIS

Once the basic properties of the massdiagram arc understood, the engineer canconduct a detailed analysis 10 determinewhere dozers, scrapers, and clump truckswill operate This is accomplished by usingbalance lines. A balance line is a line ofspecific length drawn horizontally, intersect-ing the mass diagram in two places. Thespecific length of the balance line is therecommended working or maximum hauldistance for different pieces of equipment.The term maximum haul distance is usedbecause opera ting the equipment beyondthis point would not be efficient. The maxi-mum haul distances (balance-line lengths)are—

MaximumEquipment Haul Distance

Dozer Up to 300 feet

Scraper 301 to 5,000 feet

Dump Truck 5,001 feet to severalmiles

These lengths are measured using thehorizontal scale (stations measured inhundreds of feet). Always use the maxi-mum haul distance (length) of each piece ofequipment, provided the project or node isat least that length. Start excavating eachnode with the dozer followed by the scraperand dump truck.

Figure 3-18 shows a balance line drawn ona portion of a mass diagram. If this was adozer balance line, the distance between sta-tions A and C would be 300 feet.

Cut equals fill between the ends of abalance line. The mass line returns to ex-actly the same level, indicating that theinput and the expenditures of earth havebeen equal. In Figure 3-18, this occurs be-tween stations A and C. There has been anexact balance of earthwork.

In Figure 3-18, the amount of materialmade available by cutting between stationsA and B is measured by the vertical linemarked Q. This is also the amount of em-bankment material required between sta-

Figure 3-18. Mass diagram with a balance line

3-22 Surveys and Earthwork Operations

Page 54: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

tions B and C. This is described as thebalanced quantity of earthwork.

If equipment was used to do the balancedearthwork between stations A and C, themaximum distance that earth would have tobe moved would be the length of thebalance line AC.

In accomplishing balanced earthwork opera-tion between stations A and C, some of thehaul distance would be short, while somewould approach the maximum haul dis-tance. The average haul distance (AHD) isthe length of the horizontal line placed mid-way between the balance line and the topor bottom point (transition point) of thecurve (Figure 3-18) and is found by dividingthe vertical distance of Q in half.

If the curve is above a balance line, thedirection of haul is from left to right. Theconverse is true when the curve is below abalance line.

Figure 3-19 shows a part of a massdiagram on which two balance lines have

been drawn. The same principles apply forthe area between the lines as with only onebalance line. The quantity balanced is thevertical distance between the balance line,while the horizontal bisector is the averagehaul distance. The longer balance line isthe maximum haul distance, and theshorter balance line is the minimum hauldistance. The haul distance depends uponthe position of the curve with respect to thebalance lines.

The mass diagram is a useful indicator ofthe amount of work expended on a project.By definition, work is the energy expendedin moving a specified weight a given dis-tance. It is the product of weight times dis-tance. Because the ordinate of the massdiagram is in cubic yards (which representsweight) and the abscissa is in stations ordistance, an area on the mass diagram rep-resents work. In Figure 3-20, page 3-24, ifequipment is used to do the balancedearthwork between the ends of the balancelines as drawn, the work expended is equalto the area between the mass line and thebalance line.

Figure 3-19. Mass diagram with two balance lines

Surveys and Earthwork Operations 3-23

Page 55: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 3-20. “Work” in earthmoving operations

Another item calculated from the massdiagram is average grade. This value isused when computing equipment schedul-ing and utilization. Figure 3-21 and Figure3-22, page 3-26, illustrate a portion of themass diagram on which the average gradehas been determined.

USE OF THE MASS DIAGRAM

The mass diagram is used to find the costof a project in terms of haul distance andyardage, to locate the areas for operationfor various types of equipment, to establishthe requirements for borrow pits and wasteareas, and to provide an overall control ofrequired earthmoving operations. However,the means used to analyze the massdiagram will follow the same principlesregardless of the end result desired. Theanalysis of the mass diagram is based uponthe proper location of balance lines.

Because the lengths of balance lines on amass diagram are equal to the maximum orminimum haul distances for the balancedearthmoving operation between their endpoints, they should be drawn to conform tothe capabilities of the available equipment.Equipment planned accordingly will operate

at haul distances that are within its bestrange of efficiency. Figure 3-21 illustratesa portion of a mass diagram on which twobalance lines have been drawn: 300 feet toconform to dozer capabilities and 5,000 feetfor the scraper.

The following job analysis can be madefrom the diagram in Figure 3-21:

Use dozers between stations C and E. Themaximum haul distance is 300 feet; theaverage haul distance is the horizontalbisector shown. The amount that will becut between stations C and D and filledbetween stations D and E is the length ofthe indicated vertical lines.

Use scrapers for cutting from stations A toC and filling from stations E to G. Theminimum and maximum haul distances are301 and 5,000 feet, respectively. Theaverage haul distance is the horizontal linemidway between the balance lines. Theamount of earthwork is indicated by thevertical line.

To determine the average grade for eitherthe scraper or dozer work area, use the fol-lowing procedure:

3-24 Surveys and Earthwork Operations

Page 56: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 3-21. Balance lines for equipment efficiency

1. Draw on the profile a horizontal linethrough the work area that roughly dividesthe area in half. This is a rough estima-tion. (See Figure 3-22, page 3-26.)

2. Extend a vertical line from the endpoints of the previously determined averagehaul line up through the project profile.These lines are referred to as the averagehaul vertical. (See Figure 3-23, page 3-26.)

3. Draw a final line connecting the inter-secting points of the lines drawn in steps 1and 2. This line represents the averagegrade.

4. Determine the average change in eleva-tion (the vertical distance between the cutand fill).

5. Calculate the average grade as follows:

Average Grade % =

Average change in elevation x 100Average haul distance

In the example shown in Figure 3-23, theaverage grade for the dozer would be—

Average Grade % =

18’x 100 = -8.87%

203’

Since this is an operation which movesearth downhill, the grade would be negative,or -8.87% An uphill cut would have a posi-tive grade.

Surveys and Earth work Operations 3-25

Page 57: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 3-22. Determining average grade, step 1

Figure 3-23. Determining average grade, step 2

3-26 Surveys and Earthwork Operations

Horizontal line divides area approximately in half. ----~

I I

AI----------~~~~

Balance line

Average grade line

Average haul

Vertical---........

Balance line

a

Average haul

Maximum haul distance

B

a Average haul = 203'

Maximum haul distance

.......... : ..... :: ::-/:::::-: ... :::: .. :::;.":.:-•....

Grade line c

Mass Diagram

Page 58: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Placement of Balance Lines to MinimizeWork

Because the area between the apex of themass diagram and the balance line is ameasure of the work involved in the balanc-ing operation, the size of these areasshould be decreased whenever possible,However, the method used to minimize thearea depends upon the shape of the massdiagram and the number of adjacent nodesthat can be used.

If two nodes are adjacent, work is mini-mized when two balance lines are drawn asone continuous line, with the balance linesequal in length. Each balance line must bewithin the maximum efficient haul distan-ces for the equipment. The best placementof balance lines on the portion of a massdiagram shown in Figure 3-24 would belines AE and EF, with AE = EF.

Only one balance line, CH, may be neededif it is within efficient haul distancespecifications. The quantity involved wouldbe Q yards and the work involved would bethe area above CH.

If this one balance line was replaced by twobalance lines, BD and DG, with BD lessthan DG. the quantity of earthworkbalanced would remain the same. Thework would be decreased by the size of thearea between CH and DG and increased bythe size of the area between BD and C.This would result in a savings because theincrease is less than the decrease for thesame amount of earthwork balanced. Thisdecreasing process will continue by raisingthe lines to the point where one equals theother, or until AE = EF is reached.

If there is an even number of adjacentnodes, as shown in Figure 3-25, work isreduced when the balance lines are one con-tinuous line and AB + CD + EF = BC + DE+ FG. The length of each balance line mustbe within equipment maximum haulcapabilities as defined earlier.

Figure 3-25. Minimizing work with an evennumber of nodes

If there is an odd number of adjacentnodes, as shown in Figure 3-26, work isdecreased when the balance lines are onecontinuous line and AB + CD + EF - (BC +DE) equals the limit of efficient haul, or ap-proximately 1,000 feet. All balance linesmust be within equipment limits.

Figure 3-26. Minimizing work with an oddnumber of nodes

Calculation of Earthwork not WithinBalance Lines

It is usually impossible to place balancelines so that the entire amount ofearthwork on a project can be balanced.Some part of the mass line will be outsidethe balance lines. This material must bewasted or borrowed. If the portion notwithin balance lines is ascending (cutting),there is waste; if it is descending (filling),there is borrow, This is shown in Figure3-27, page 3-28. Concentrate all necessaryborrow and waste operations in one generalarea.

Figure 3-24. Minimizing work with two nodes

Surveys and Earthwork Operations 3-27

Page 59: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

LIMITATIONS OF THE MASS DIAGRAM

Figure 3-27. Waste and borrow on a massdiagram

Format for Analysis

The simplest and most practical method ofTabulating the results of a mass diagram isto write all quantities and distances on thediagram, as shown in Figure 3-28. It isalso possible to extract information fromthe mass diagram and put it in a formatthat effectively controls the operation. Onemethod is to prepare a mass diagramanalysis sheet as shown in Figure 3-29.

The mass diagram has many limitationsthat preclude its use in all earthmovingoperations. At best, it is merely a guide in-dicating the general manner in which theoperations should be controlled. Any at-tempt to get exact quantities and distancesfrom it may be misleading. However, it is agood starting point.

The mass diagram is most effective whenused to plan operations along an elongatedproject similar to a road, an airfieldrunway, or a taxiway. The haul distancesare along the centerline or parallel to it.However, if the project becomes relativelywide compared to its length, movement ofearth may be transverse as longitudinal,resulting in longer, transverse haul distan-ces and invalidating the mass diagramanalysis.

The mass diagram is used to analyze onlythe potentiality of balancing within one

Figure 3-28. Mass diagram showing analysis results

3-28 Surveys and Earthwork Operations

Page 60: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

phase of a project. For instance, the massdiagram may indicate that the best balanc-ing of a certain portion of a runway will re-quire a haul distance of 2,200 feet alongthe site. However, it may be better tobalance yardage with an adjacent taxiwayin which the haul distance will be only1,200 feet. The mass diagram can dealonly with the runway or the taxiway, notwith both simultaneously.

The mass diagram assumes that allmaterial excavated in the cut sections is ac-ceptable for use in the embankment sec-

tions. This is not necessarily true. How-ever, all unacceptable quantities can beeliminated from the earthwork table.

The mass diagram is applicable to projectsneeding balanced earthwork. Balancingeliminates the double handling of quan-tities. If there is a short distance betweenan acceptable borrow pit and an embank-ment section, it may be more economical touse the borrow pit instead of a long balanc-ing operation, This can be determined by awork or economy. study.

Figure 3-29. Mass-diagram analysis sheet

Surveys and Earthwork Operations 3-29

Page 61: Army Construction Manual FM5 430 Vol1 Entire

4

Clearing, Grubbing, and Stripping Forest Types and Environmental Conditions Preparation Clearing Considerations Performance Techniques

FM 5-430-00-1/AFPAM 32-8013, Vol 1

CLEARING, GRUBBING,AND STRIPPING

Land clearing is the removal and disposal of all vegetation,rubbish, and surface boulders embedded in the ground. In theTO, land clearing also includes the removal and disposal ofmines, booby traps, and unexploded bombs. Grubbing is theuprooting and removal of roots and stumps. Stripping is theremoval and disposal of unwanted topsoil and sod.

Clearing, grubbing, and stripping are accomplished by usingheavy engineering equipment. Hand- or power-felling equip-ment, explosives, and fire are also used. Factors that determinewhich method to use are: the acreage to be cleared the typeand density of vegetation, the terrain’s effect on the operationof equipment, the availability of equipment and personnel, andthe time available for completion. For best results, a combina-tion of methods is used in a sequence of operations.

Clearing, grubbing, and stripping are the same in road andairfield construction. In airfield construction, the areas to becleared are usually larger than for road construction; the numberof personnel and amount of equipment used are correspondinglygreater; and the disposal of unsuitable materials requires moredetailed planning and longer hauls.

FOREST TYPES AND ENVIRONMENTAL CONDITIONSClearing, grubbing, and stripping operationsdiffer in every climatic zone because eachzone has different forest and vegetativetypes. Forests are not uniform in type,growth, and density within climatic zones.Soils, altitudes, water tables, and other fac-tors vary widely within each zone.

The general nature of a forest is determinedfrom records of the principal climatic fac-tors, precipitation, humidity, temperature,sunlight, and the direction of the prevailingwinds. The nature and action of climaticfactors during the growing season determinethe amount and types of forests. Fromthese records, a general interpretation of

the forests in an area can guide detailed re-connaissance.

The climate classifications of forests are tem-perate, rain, monsoon, and dry, The follow-ing paragraphs describe these classifications.

TEMPERATE FORESTS

Temperate forests contain both softwoodand hardwood trees. Hardwoods are domin-ant where the soils are old, deep, and fer-tile. Softwoods are dominant where thesoils are young, shallow, and less fertile.The density of growth in these forestsvaries with topography and local climate

Clearing, Grubbing, and Stripping 4-1

Page 62: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

conditions. Bogs are common in coldregion, softwood forests. Bogs present ahazard to construction equipment duringthe clearing operations. Root systems varyaccording to geologic conditions andspecies. The types of root systems typicalof various species are listed in Table 4-1.

RAIN FORESTS

Rain forests occur in tropical climateswhere rainfall is heavy throughout the year.They consist of tall, broad-leaved trees thatgrow as high as 175 feet. The trees havean umbrella-like foliage that permits littlesunlight to penetrate. The undergrowth con-sists of thick vines that cling to the treesfor support and grow to great heights.Where sunlight reaches the forest floor, theundergrowth is dense and varied. Becauseof continual precipitation, the root systemsare on or near the ground surface andspread in a lateral pattern around the baseof the trees,

MONSOON FORESTS

Monsoon forests occur in climates of heavyseasonal rains with strong, warm winds.The forests are dense, with varied species ofhardwoods which are moderate-sized, broad -leaved, and have shallow root systems. Theundergrowth is very dense with shrubs,vines, and plants.

DRY FORESTS

Dry forests occur in arid and tropicalregions where there is little precipitation.The forests are either scrub or savanna.Scrub forests usually consist of broad-leaved hardwoods with dense thickets alongwatercourses. In open areas there are scat-

tered growths of low, thorny, stuntedshrubs and stunted trees that usually havelong, tough taproots that are difficult toremove. Savanna forests are in morehumid, dry-forest regions. These forestsare park-like, with large trees widely anduniformly spaced. Savannas usually havecontinuous coverings of small grasses.

GEOLOGIC AND PERMAFROSTCONDITIONS

An investigation of the geologic conditionsof a forest can help when estimating thedensity and depth of the root systems ofthe trees. The investigation should be con-cerned with hardpan, marshy, and per-mafrost conditions.

Hardpan or Rock

Where a forest is closely underlaid byhardpan or rock, the tree roots branch andremain near the surface. This growth iseasy to uproot. Where the soil is firm andthe hardpan or rock is deep, the trees tendto form large, deep taproots that makeuprooting difficult.

Inundated, Marshy, and Boggy Areas

In these areas, trees have thick, wide-spreading. and shallow root systems nearthe surface of the ground.

Permafrost

In northern regions where permafrost oc-curs, the root systems of trees are similarto those in hardpan or rock. Where the per-mafrost is near the surface, roots branchout and lie close to the surface. Where per-mafrost is far belowdevelop taproots.

PREPARATION

RECONNAISSANCE AND PLANNING intelligence reports,

the surface, trees

and aerial and groundreconnaissance. (Refer to Chapter 2 of this

The types of trees, vegetation, soil, and ter- manual for more detailed in formation.)rain encountered while clearing the land After such information has been verified, es-must be determined as accurately as pos- timate the quantity of work, select the avail-sible from climatic and geological maps, able equipment, determine the number of

4-2 Clearing, Grubbing, and Stripping

Page 63: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 4-1. Species of trees and their normal root systems

Clearing, Grubbing, and Stripping 4-3

Species Alder . Ash .... Aspen Basswood Birches:

.' ... : ...... .

Black, cherry, sweet Paper, white Yellow

Cedars Cherry . Chestnut Cypress Elm ... Firs:

Balsam Douglas Lowland white Noble White ....

Gums Red, sweet

Hackberry Hemlock Hickory Juniper Larch . Laurel Locust Magnolia Mahogany Maple Oak Pine:

Eastern white Jack ... Loblolly Lodgepole Longleaf Nut ... . Pitch .. . Ponderosa Red, Norway Shortleaf .. . Slash .... . Stone (Foxtall) Sugar Western white

Poplar . Yellow .

Quassia . Redwoods

Spruce .. Sycamore Tamarack Willows

Normal Root System · Shallow, wide-spreading laterals · Deep in porous soils, shallow and spreading in rocky soils · Shallow laterals · Deep, wide-spreading laterals

· Deep, wide-spreading laterals · Shallow laterals · Shallow, wide-spreading laterals · Shallow, wide-spreading laterals · Moderately deep, wide-spreading laterals · Taproot · Several descending roots and many shallow, wide-spreading laterals · Shallow, wide-spreading laterals; occasionally a taproot

· Shallow, wide-spreading laterals · Wide-spreading laterals · Deep, wide-spreading laterals · Moderately deep, wide-spreading laterals · Shallow laterals · Deep, wide-spreading laterals · Shallow, wide-spreading laterals · Shallow, wide-spreading laterals · Shallow, wide-spreading laterals · Deep taproot · Deep laterals · Deep, wide-spreading laterals · Deep, wide-spreading laterals · Deep, wide-spisading latsials · Deep, wide-spreading laterals · Shallow, wide-spreading laterals · Shallow, wide-spreading laterals · Deep taproot

· Moderately deep; no taproot · Moderately deep, wide-spreading laterals · Short taproot (young), laterals · Deep, wide-spreading laterals; always with taproot · Deep taproot; well-developed laterals · Shallow to moderately deep laterals · Taproot (young); later laterals · Moderately deep, wide-spreading laterals · Strong taproot and laterals · Very deep taproot · Deep, strong taproot with laterals · Taproot supplemented by laterals · Taproot (seedlings), deep laterals · Taproot (seedlings); deep, wide-spreading laterals · Shallow laterals · Deep, wide-spreading laterals · Shallow, wide-spreading laterals · Several descending and many shallow. wide-spreading

laterals · Shallow, wide-spreading laterals · Shallow laterals · Shallow. wide-spreading laterals · Wide-spreading laterals

Page 64: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-80137 Vol 1

personnel needed, and plan a sequence ofoperations to complete the clearing rapidlyand efficiently. In all clearing operations,the decisive factors controlling the methodof clearing are the type and amount ofequipment and the time available for com-pletion.

TIMBER CRUISING

Timber cruising is performed to estimatethe size, the height, and the number ofeach tree species in a given area. It isused either to determine the quantity ofusable timber or to estimate the amount of

work required in clearing. A sample, usual-ly 10 percent of the area, is studied andthe result is applied to the entire area. Thesample may be increased or decreased. Insmall areas, a 100-percent cruise is usuallymade.

In timber cruising for land clearing only,record the diameters of the trees at breastheight (DBH) taken at 4 1/2 feet above theground, and record the species and numberof trees. This information is used to planthe clearing operation and select the type ofequipment most efficient for the diametersand species.

CLEARING CONSIDERATIONS

PERMAFROST

Clearing of ground cover over permafrostwhich is near the freezing point may resultin thawing of material, causing considerableground-surface subsidence.

SAFETY

Careful consideration must be given to thesafety of personnel and equipment duringclearing operations. Protective, tractor-mounted cabs should be used when exten-sive clearing operations are anticipated.Protective cabs permit greater flexibility inclearing operations and increase operator ef-ficiency. With this protection, damage tothe dozer is reduced and continuous produc-tion results.

Proper supervision and planning can helpprevent accidents caused by falling trees,uprooted stumps, stump holes, and roughor broken terrain during the clearing opera-tion. All equipment used in clearingshould, if practicable, be equipped withheavy steel platingdercarriages. Thislogs, and bouldersnerable equipment

for protection of the un-will prevent stumps,from damaging vul-parts.

CAMOUFLAGE

To provide cover and concealment(camouflage) for the construction site, donot remove standing trees and brush out-side the designated cleared area unlessnecessary. When uprooting trees withbulldozers, take care to control their falland avoid breaking surrounding trees.

TIMBER SALVAGE

Trim all timber useful for logs, piles, andlumber, and stockpile it for future use inbridge, culvert, and other construction ap-plications. Push or skid this timber into asalvage area where it can be moved to asawmill with little difficulty.

TEMPORARY DRAINAGE

Phased development of the drainage systemin the early stages of clearing, grubbing,and stripping is essential to ensure uninter-rupted construction. Delays caused byflooding, subgrade failures, heavy mud con-ditions, and the subsequent immobilizationof construction equipment can beeliminated by careful development of thedrainage system before, or concurrent with,other construction. Use the originaldrainage features as much as possible

4-4 Clearing, Grubbing, and Stripping

Page 65: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

without disturbing natural grades. Gradedrainage ditches downhill.

Fill holes left by uprooted trees and stumpswith acceptable soil, and compact theground to prevent the accumulation of sur-face water. Use dozers and graders for thiswork. Slope the ground toward drainageditches to prevent pending on the surface.Backfill existing ditches at the latest pos-sible time to permit the best use of theoriginal drainage.

DISPOSAL

Use waste areas or burning to dispose ofcleared materials. The choice of methoddepends on the type of construction, en-vironmental concerns, the location, thethreat, and the time available. Generally,the material is pushed and skidded off theconstruction site and into the surroundingtimber to speed disposal and keep the areacleared for equipment operation. To dis-pose of material as rapidly as possible, as-sign specific units of equipment to ac-complish this concurrently with the clearingand grubbing. The disposal method shouldbe consistent with the methods ofcamouflage, salvage, and drainageclearing.

used for

WASTE AREAS

In airfield construction, consideration mustbe given to the areas used for disposal ofconstruction waste.

Dumps Adjacent to Work Areas

In forward combat areas where saving timeis essential, the quickest and most con-venient method of material disposal is topile the materials adjacent to the workarea. Study the construction plans to deter-mine where theinterfering withareas.

Off-Site Areas

In constructing

debris can be piled withoutdrainage or potential work

the main project, it may benecessary to clear some adjacent land to dis-pose of the cleared material. Locate thisclearing as close to the main project as

possible to shorten the hauling distance,Use the same methods to clear disposalareas that arc used in clearing work areas.

Revetments

Cleared material can be disposed of byusing it as fill material in revetmentsaround hardstands when protectivemeasures are needed.

Burning

Do not use fire for clearing land unlesssuitable equipment and sufficient personnelare not available for other methods of clear-ing. When burning is required, closely fol-low recommended procedures.

Under favorable tactical conditions, brushand timber debris may be burned. To limitthe likelihood of detection because ofsmoke, keep fires burning as hot as pos-sible and do not push new material into thefire rapidly. Do not permit fires to burn atnight unless tactical conditions are extreme-ly favorable and approval has been obtainedfrom headquarters.

Fire Control. Strip the area around anydebris to be burned before fires are startedto provide a firebreak. If large areas are tobe burned, establish firebreaks on all sidesas a precaution against shifting winds.Maintain a fire guard over the fires as anadditional safety measure. In dry weather,hand shovels, water buckets, and other ex-pedient fire-fighting equipment should beavailable to extinguish fires caused byflying sparks.

Burning Pits. The most satisfactory methodfor burning large quantities of brush andtimber is to burn them in a pit or trenchdug by a bulldozer or scraper. The sides ofthe pit will reflect the heat back into thefire, producing a very hot fire, Burning willbe rapid and complete. Push the materialinto the pit with a bulldozer. Start the firewith limbs and small brush to get a goodbed of coals. Gradually increase the size ofthe material as the intensity of the fire in-creases. Get as little dirt as possible in thepit because it tends to smother the fire andfill the pit. A soldier should be detailed to

Clearing, Grubbing, and Stripping 4-5

Page 66: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

tend the fire and ensure that the pile iskept compact, This method cannot be usedin swampy areas where groundwater willseep into the trench.

Log Piles. If it is not desirable to constructburning pits, burn piles of logs by looselypiling them so that the heat and flames canpass through, It is always best to start thefire with brush. After a large bed of coalsis formed, add a few logs at a time to ob-tain a good blaze.

To burn piles of green, wet logs, it may benecessary to use fuel oil to furnish enoughheat to dry out the logs and start the burn-ing process. Pile the logs parallel, one ontop of the other. The fuel oil is carried tothe center of the pile by a pipe in whichholes have been drilled or cut. Once thepile is burning well, the fuel can be cut offand the pipe removed. Care must be takento avoid ground contamination.

Fuel oil is also a quick and convenientmeans of starting brush fires, particularly ifthe brush is green and wet. If material isto be pushed onto the pile while the pipe isbeing used, it is best to bury the portion ofthe pipe outside the pile to protect it from

damage from tractor grousers and bulldozerblades.

Clearing and Piling Stumps. In preparingstumps for burning, remove as much dirtas possible from the roots. Dirt on theroots will retard combustion and smotherthe fire. When the stumps are pushed out,leave them with the roots exposed to sunand wind so the dirt till dry quickly.Scrubbing with the side of the bulldozerblade will knock off much of the dry dirt.Pile the stumps as close together as pos-sible with the trunks pointing toward thecenter of the pile. Keep the stumpstogether after they start to burn. This pro-cedure will speed up the burning.

AIRFIELD APPROACH ZONES

Airfield glide angles and approach zones arefurther discussed in Chapter 11 ofFM 5-430-00-2/AFPAM 32-8013, Vol 2. Ob-structions extending above the glide anglemust be removed. Although glide-angle re-quirements may be met by only toppingtrees, it is best to fell or uproot trees thatextend above the glide angle. Disposal isno problem in the approach zone, becauseall demolished material is left in place.

PERFORMANCE TECHNIQUES

CLEARING WITH EQUIPMENT

The use of engineer equipment is the mostrapid and efficient method of clearing. Theuse of such equipment is limited only by unusually large trees, stumps, and terrainthat decrease the maneuverability of theequipment and increase maintenance re-quirements. This type of equipment in-cludes bulldozers; tree-dozer, tractor -mounted units; tractor -mounted clearingunits; winches; power saws; rippers; andmotor graders. In addition, pioneer toolsare used for some clearing operations.Table 4-2 summarizes the limitations andproper applications of engineer equipmentin clearing operations. Use productionrates of equipment under normal operatingconditions for determining the total time re-

quired for the job. Clearing rates are dis-cussed in FM 5-434. Limitations and ap-plications for each type of equipment follow.

Bulldozer

When clearing an area in dry or temperateforests, the bulldozer is the most efficientmechanical equipment for removing smallbrush, trees, and stumps up to 6 inches indiameter. Although more time and effortare required, bulldozers can also removetrees up to 30 inches in diameter when trac-tor-mounted clearing units and power sawsare not available. Because of its ability topush, move, and skid felled trees andbrush, the bulldozer is used extensively asthe primary unit of equipment in all clear-ing operations.

4-6 Clearing, Grubbing, and Stripping

Page 67: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 4-2. Applications and limitations of engineer equipment in land clearing

Clearing, Grubbing, and Stripping 4-7

Equipment

Bulldozer

Tree-dozer, tractor-mounted unit (Rome Plow)

Tractor ·mounted clearing unit

Winches (towing):

Tractor -mounted

Truck-mounted

Felling equipment:

Chain saw

Applications

·Primary equipment for all land clearing. -Excellent for removing brush, trees, and stumps up to 6 inches in diameter. ·Push, pull, or skid cleared material for disposal.

-Medium clearing of brush and trees at ground level rather than uprooting.

·For extensive clearing operations requiring heavy pulling. -Uproot trees and stumps of almost unlimited diameters. ·Skid cleared material for disposal. ·Extrlcate mired equipment. -Excellent for operation in jungles, swamps, and bottom lands with heavy growth.

-For general light and medium pulling. -Uproot trees and stumps up to 24 inches in diameter. ·Skid cleared material for disposal. ·Extricate mired eqUipment.

-Expedient for light pulling of trees up to 6 inches in diameter. -Skid small trees and brush. -Extricate mired eqUipment.

-Controlled felling of trees of almost unlimited diameters. -Saw timber for salvage. -Rapid felling.

Limitations

-Trees over 6 inches in diameter require special and slower methods of removal by dozer. -Maneuverability limited in muddy or swampy terrain and in dense, heavy growth.:

-Skilled personnel required for cutting of trees; other units required for completion of clearing when burning is not permitted.

·Skilled personnel required for rigging. ·Slow in clearing an area; other units required for speedy completion. ·Not TOE.

.Pulling capacity limited by size of tractor. ·Terrain affects maneuverability of tractor.

.Rigging personnel required. -Terrain must be suitable for truck use. .Pulling capacity too limited for most operations.

-Other units required for uprooting stumps and disposing 01 felled timber. -Pneumatic saws are very dangerous to use on steep, rugged ground. Air hoses frequently are fouled and broken by rolling logs and chunks. Gasoline chain saws are far easier to handle than the pneumatic ones because there are no hoses 10 contend with. They can be used in any type of terrain with a reasonable degree of safety if operated by skilled operators.

Page 68: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 4-2. Applications and limitations of engineer equipment in land clearing (continued)

When clearing with bulldozers, the se-quence of operations depends on the type oftrees, the terrain, and planned construc-tion. After establishing the boundaries ofthe clearing, select spoil areas for disposalof all cleared material based on the shortesthaul, a downgrade slope, effectivecamouflage, and general accessibility.

Start clearing at the disposal area andmove in each direction away from it. Useone or two dozers to clear the small treesand brush only. Another pair of dozers willremove the larger trees and stumpsbypassed by the previous units. If neces-sary, add more dozers for a third cycle ofoperation to take care of the heaviestremovals.

Move the cleared material to the spoil areaby skidding, pushing, or pulling. Disposalshould be done with uprooting and remov-ing. It is best to have a separate crew as-signed for disposal.

Multiple operations are possible when othertypes of equipment are available, using

each type where it is most effective. Usepower saws, for example, to fell large trees.Use clearing units to uproot large stumpsand work in areas inaccessible to dozers.Use bulldozers to clear, stockpile, and dis-pose of light material. The operationalmethods used by bulldozers in clearingdepend on the size of the trees. Themethods briefly discussed below are dis-cussed fully in FM 5-434.

Small Trees, 6 Inches or Less in Diameter,and Brush. In clearing small trees andbrush, operate the bulldozer with the bladestraight and digging slightly. It may benecessary to back up occasionally to clearthe blade. The cleared material can eitherbe pushed into windrows for later removalor pushed off to one side of the area to becleared.

Medium Trees, 6 to 12 Inches in Diameter.To push over trees that range from 6 to 12inches in diameter, set the blade of thebulldozer as high as possible to gain addedleverage (Figure 4-1). As the tree falls, the

4-8 Clearing, Grubbing, and Stripping

Page 69: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

bulldozer is backed up quickly to clear theroots. With the blade lowered, the dozertravels forward again and digs the rootsfree by lifting the blade. The felled tree isthen ready for removal to the spoil areas.

Large Trees. Removing large trees (over 12inches in diameter) is much sIower andmore difficult than clearing brush andsmall trees. First, gently and cautiouslyprobe the tree for dead limbs that could falland injure you. Then, position the bladehigh and center it for maximum leverage.Determine the direction of fall before push-ing the tree over; the direction of lean, ifany, is usually the direction of fall, If pos-sible, push the tree over the same as youwould a medium tree.

However, if the tree has a large, deeply em-bedded root system, use the followingmethod (Figure 4-2, page 4-10):

Step 1. Opposite the direction of fall, makea cut deep enough to cut some of the largeroots. Use a V-ditch cut around the tree,tilted downward laterally toward the treeroots.

Step 2. Cut side two.

Step 3. Cut side three.

Step 4. To obtain greater pushing leverage,buld an earth ramp on the same side asthe original cut. Then push the tree over.As the tree starts to fall, reverse the tractorquickly to get away from the rising root

Figure 4-1. Bulldozer removing medium-sized trees, 6 to 12 inches in diameter

Clearing, Grubbing, and Stripping 4-9

Page 70: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 4-2. Four steps for removing large trees with a bulldozer

felling the tree, fill the stump edge shears them off at ground level. Thewater will not collect in it. operator is protected by a steel canopy and

a guide bar that controls the direction ofroots on the fourth side may falling trees.

mass. Afterhole so that

NOTE: Theneed to be cut also.

The tree-dozer is a simple and efficientTree-Dozer, Tractor-Mounted Unit piece of equipment used for military land-

The tree-dozer, or Rome plow, is a tractor clearing operations. It does not appreciably

with a blade that stings and slices large disturb the soil. It provides—

trees. A sharp projection on the left side ofthe blade splits the trees, while the cutting

4-10 Clearing, Grubbing, and Stripping

Page 71: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• Clear fields of fire and security aroundcantonments, airfields, and otherfacilities.

• Right-of-way clearance to desireddepths along roads and railroads, there-by reducing the enemy’s capability ofambush.

Before committing a tractor equipped withthe tree-dozer mounting, investigate the soilcondition in the area of operation to deter-mine if it will support the equipment. Usethe tree-dozer mounting to make cutsthrough any kind of forest except heavyswampland. Shear trees at ground level,sweep them into piles or windrows, and dis-pose of them. One tractor equipped with atree-dozer mounting can clear approximate-ly 1 to 2 acres per hour, depending on thetree density and size. Use one of the follow-ing clearing methods:

Ž When the tractor can move forward al-most continuously, it shears to groundlevel anything in its path, Fast produc-tion can be obtained by laying out long

areas (200 to 400 feet wide) that can becut from the outside toward the centerin a counterclockwise direction. Thecut material then slides off the trailing(right) end of the tree-dozer mountingand leaves the uncut area free of fallendebris. The windrows are placedlengthwise on the borders of the areas.Piling is done by sweeping with the tree-dozer mounting. Sweep a blade widthat a time. Work from the center of eacharea, at a right angle to the border (Fig-ure 4-3).

Ž Another method is shown in Figure 4-4,page 4-12. Again, long areas are laidout in 200- to 400-foot widths, but thecutting is done from the center towardthe sides in a clockwise direction. Thisallows the cut material to fall towardthe center, which becomes the windrowsite. The piling is done with the tree-dozer mounting, following the patternoutlined on the right side of Figure 4-4.When windrowing, the operator keepsthe cutting edge on the ground whilepushing into the windrow and raises it

Figure 4-3. Cutting vegetation to ground level and piling cut materialusing the counterclockwise method

Clearing, Grubbing, and Stripping 4-11

Page 72: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

4 -12

Figure 4-4. Cutting vegetation to ground level and piling cut materialusing the clockwise method

when backing away. This allows ac-cumulated soil to sift away and lessenssoil deposits in the windrow.

• On extreme slopes, rapid production isobtained by working in a semicircularpattern, from left to right, at approxi-mately right angles to the windrow (Fig-ure 4-5). If the terrain is steep, the

Clearing, Grubbing, and Stripping

windrows should be on the contour,and the tractor should work from theuphill side and push downhill to thewindrow.

• Where the vegetation is dense andsmall, the highest production can be ob-tained by cutting and windrowing simul-taneously. Work from left to right at a

Page 73: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 4-5. Clearing on steep slopes covered with large trees

90-degree angle to the windrow, withthe trailing edge of the tree-dozer work-ing against the uncut material. Thisprevents cut material from sliding offthe moldboard and allows the cutmaterial to accumulate on themold board.

When the moldboard is filled, the operatorshould stop the tractor and deposit the cutmaterial. The operator should then reverseto the starting point and repeat the opera-tion to the right (Figure 4-6, page 4-14),reducing the time lost in backing up. Whenthe tractor reaches the previously cutmaterial, the operator should deposit cutmaterial and form another windrow.

The area of vegetation should be laid out asshown in Figure 4-6, with the operatorworking in patches, from inside to outsidein a counterclockwise direction and at rightangles to the windrows. Sweeping andpiling the resulting debris can be accom-plished much faster when tractors are usedin teams traveling abreast.

Winches

Towing winches mounted on tractor-dozerunits or trucks are limited in use for clear-ing operations because of their smallcapacities in comparison with the tree- andstump-pulling units.

Tractor-Mounted Winch. Use tractor-mounted winches for uprooting trees andstumps up to 24 inches in diameter.

Clearing, Grubbing, and Stripping 4-13

Page 74: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 4-6. Cutting and piling dense growths of small-diameter vegetation on level terrain

hoisting and skidding felled trees, and ex-tricating mired equipment. On the tractor-dozer unit, the winch is mounted in therear and is directly geared to the rearpower take-off on the tractor. The line pulldeveloped varies with the size of the tractor,the speed at which the winch is operated,and the number of layers of rope on thedrum. The line pull of a tractor-mountedwinch is only about one-half the pull of astandard tree- and stump-pulling unit.

Truck-Mounted Winch. As an expedient,truck-mounted winches can be used ontrees up to 6 inches in diameter. Their

capacities are too limited for heavy work.Their best use is for skidding felled treesand logs to a disposal area, if the haul roadis sufficiently cleared for trucks to operate.

Felling Equipment

Felling can be done with hand tools orpower equipment. Axes, two-man saws,shovels, pick-mattocks, and machetes areused to chop or saw down standing timber;dig and uproot stumps: and slash grass,vines, and undergrowth. Clearing by handis usually too slow and difficult for militaryrequirements unless explosives or mechani-cal methods are used. When labor is

4-14 Clearing, Grubbing, and Stripping

Page 75: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

plentiful, forests are dense, and terrain isrough, this method of clearing can be usedwith good results. Power equipment andchain and circular saws are the principalways of felling limber.

Ripper

In land clearing, the ripper is used to helpin the removal operations of bulldozers andtree- and stump-pulling units. The rippercuts and breaks tree roots and loosensboulders from the ground. The short depthof shank penetration limits its use to shal-low root systems. Prior to stripping opera-tions, the ripper is used to loosen andbreak up frozen soil or organic material foreasier removal by graders or scrapers.

Grader

The grader is used 10 cut grass and weeds,remove small brush, and clear the area ofdead vegetation. The terrain must be leveland free from boulders and trees. Usedwith rippers and bulldozers, graders canwindrow the cleared material for laterremoval by other equipment. The grader isextremely limited in most clearing opera-tions.

CLEARING WITH EXPLOSIVES

Explosives may bc used to fell standingtrees, uproot entire trees and stumps, andremove and dispose of large boulders. Ex-plosives, however, have several disadvan -tages. The sound of the explosive cantravel farther than the sound of the con-struction equipment. In loose soil, the ini-tial charge may be entirely a expended in com-pacting the soil under a tree or stump, anda second charge may be required to removeit. Deep taproots often are only broken byexplosives and have to be removed by hand.Also, explosives generally take time to placeand they create large craters, which requireborrow excavation and compaction to back-fill. In spite of these disadvantages, it isstill sometimes necessary to use explosivesto clear an area where the terrain precludesor seriously impedes the operation of heavy

equipment. Refer to FM 5-250 for the cor-rect application of explosives and demoli-tions.

Trees and Stumps

Methods of tree and stump blasting varywith the size and condition of the tree, rootstructure, and ground conditions, Figure4-7, page 4-16, shows the methods of plac-ing charges to blast stumps with differentroot structures. Table 4-1, page 4-3, showsthe type of root system for several treespecies in temperate forests.

The size of the charge required depends onthe strength of the explosive available; thesize, variety, and age of the tree or stump;and soil conditions.

Various types of tools (such as pinch bars,earth augers, and spoons) can be usedwhen drilling holes for the charge. Woodaugers can be used for taproots. For load-ing and tamping, any smooth, wooden poleabout 5 feet long and 1 1/2 inches indiameter can be used. The handle from along-handled shovel is excellent because thecrook of the blade end provides a good grip.All holes must be tamped firmly with earthto retain the full force of the explosion.

Boulders

When boulders cannot be used in an em-bankment or fill, they must be removedfrom the construction area. Blasting is aquick and easy method of dislodgingboulders. Mudcapping, blockholing, orsnakeholing (described in Chapter 3 of FM5-250 or Chapter 6 of FM 5-34) may beused. Refer to Chapter 3 of TM 5-332 forquantities and types of explosives to beused and details regarding blasting rock.

REMOVAL OF SURFACE ROCKS

All surface rocks must be removed in cer-tain types of construction. There are threemethods used in this operation: hand,bulldozers, and cranes or scoop loaderswith trucks. The choice of method dependsupon the situation.

Clearing, Grubbing, and Stripping 4-15

Page 76: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 4-7. Stump-blasting methods for different root structures

Hand

When there is sufficient time and person-nel, rocks are picked up and loaded intohauling units by hand. This slow methodis used in military construction only as anexpedient.

Bulldozer

The bulldozer is the most commonly usedengineer equipment for moving rocks to afill or disposal area. The rocks may be

windrowed by dozers for later removal byscrapers or shovels and trucks. If the dis-tance is short, they may be pushed bydozers to the designated disposal area.

Cranes or Scoop Loaders with Trucks

Clearing surface rock by this method aloneis possible, but it is slow. If the rocks arefirst windrowed or moved into piles bybulldozers or graders, the shovel will loadthe trucks quickly and efficiently. The

4-16 Clearing, Grubbing, and Stripping

Page 77: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

rocks can then be hauled long distances fordisposal.

STRIPPING

Stripping consists of removing and dispos-ing of the topsoil and sod that cannot beused as a subgrade, foundation under a fill,or borrow material. Examples of thismaterial are organic soils, humus, peat,and muck, Unsuitable soil must beremoved to a depth at which compactionand thickness requirements are satisfied.Stripping is done concurrently with clearingand grubbing by using bulldozers, graders,scrapers, and sometimes shovels, Good top-soil and sod should be stockpiled for lateruse on bare areas for dust or erosion con-trol or for camouflage.

REMOVAL OF STRUCTURES

An airfield construction site may be accept-able except for obstructions such ashouses, railroads, power lines, and otherstructures on the proposed site or near theoperation of aircraft. The primary selectionof a site always involves compromises, Thesurvey party often selects a site wherelimited clearing of structures will be neces-sary before full-scale operations can takeplace.

Power Lines

Power lines obstructing forward area con-struction or glide angles should be remov-ed. In rare instances, the lines may beneeded intact and a different approach tothe airfield must be used. If the lines crossthe runway, relocate them around thenearest end of the runway. As a lastresort, underground installation may beused if armored underground cable or con-duit is available that will adequately insu-late the lines, In rear areas, power linesthat are not in an approach zone or nothigh enough to extend into the glide anglewhen located in an approach zone may bemarked with suitable warning lights.

Roads and Railroads

In general, roads and railroads present noobstructions when located near airfields, if

the traffic does not interfere with the ap-proach or takeoff of aircraft. Do not des-troy main paved highways and railroadlines because they may be required forground operations. It is desirable to havethe airfield located near a good road or rail-road so supplies may be readily transportedto the site.

Buildings

Buildings may be completely razed with ex-plosives or heavy equipment, leaving no sal-vage. They may be razed in a manner toconserve usable material, or they may berelocated.

REMOVAL OF BURIED EXPLOSIVES

Mines, booby traps, unexploded ordnance(UXO), and other buried explosives must belocated and removed or neutralized beforeany construction operations begin. Checkall reports and data on an area to locateand identify explosives.

Establish the boundaries of the construc-tion area first, then make a visual search ofthe most likely places for explosives. Theyare usually near existing structures,houses, and roads; in disturbed ground hol-lows where the earth has visibly settled;and under stockpiles, pickets, or stakesplaced in unnatural locations. If time al-lows, thoroughly investigate the area withmine detectors or by probing methods.

The safety of personnel and equipment isprimary at all times during the removal ofmines. The speed of clearance is secon -dary, Whenever possible, use trained ex-plosive ordnance disposal (EOD) detach-ments, particularly when the size of bombsprecludes detonation in place.

The method of mine and UXO removal is acommand decision. For minefield withbooby traps or other antihandling devices,it is best to destroy the mines in place byexplosives or mechanical means. UXOsmay be disarmed by ordnance personneland then manually removed from the areaand disposed. If ordnance personnel arenot available, destroy the device in place.

Clearing, Grubbing, and Stripping 4-17

Page 78: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Surface mines or bomblets may be able to be filled and compacted with acceptablebe pushed from an area by using a drag material, using dozers or graders. For addi-chain or dozer. If devices are destroyed in tional information, see FM 5-434.place, all resulting holes and craters must

4-18 Clearing, Grubbing, and Stripping

Page 79: Army Construction Manual FM5 430 Vol1 Entire

5

Subgrades and Base Courses Design Considerations Subgrades Select Materials and Subbase Courses Base Course

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SUBGRADES ANDBASE COURSES

This chapter discusses the functions of the subgrade, subbase,and base courses and covers the selections of materials andconstruction procedures. Chapters 8 and 9 of this manualdiscuss the determination of the base- and surface-course thick-ness for roads. Chapters 11 and 12 of FM 5-430-00-2/AFPAM32-8013, Vol 2, include similar information for all classes ofairfields and heliports as well as all commonly used types OJsurface materials. Additional information on soils, compaction,and California Bearing Ratio (CBR) requirements is containedin Chapters 2, 6, and 10 of FM 5-410 and in Chapter 2 of FM5-530.

DESIGN CONSIDERATIONS

Pavement structures may be rigid orflexible. In rigid pavements, the wearingsurface is made of portland cement con-crete. A rigid pavement made of concretewill have great flexural strength, permittingit to act as a beam and allowing it to bridgeover minor irregularities that may occur inthe base or the subgrade upon which itrests.

All other types of pavements are classifiedas flexible. In a flexible pavement, any dis-tortion or displacement occurring in thesubgrade is reflected in the base courseand continues upward into the surfacecourse. Flexible denotes the tendency of allcourses in ibis type of structure to conformto the same shape under traffic.

Flexible pavements are used almost ex-clusively in the TO for road and rear areaairfield construction. They are adaptable toalmost any situation, and they fall withinthe construction capabilities of the combatheavy engineer battalion and its supportunits. Rigidsuited to TO

pavements are generally notconstruction requirements (un-

less the materials are more readily avail-able) and are not discussed in detail in thischapter.

FLEXIBLE-PAVEMENT STRUCTURE

A typical flexible-pavement structure isshown in Figure 5-1, page 5-2. It il-lustrates the terms used in this manualthat refer to the various layers. All thelayers shown in Figure 5-1 are not presentin every flexible pavement. For example, aflexible-pavement structure may consistonly of an asphaltic-concrete surface, abase course, and the subgrade. The designof flexible pavements must include athorough investigation of the subgrade con-ditions; borrow areas; and sources of select,subbase, and base materials.

TESTS

Engineers should classify soils according toChapter 2 of FM 5-410, and then select rep-resentative samples for detailed tests.Detailed tests determine compaction charac-teristics, CBR values, and other properties

Subgrades and Base Courses 5-1

Page 80: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 5-1. Typical flexible-pavement section

needed for designing the flexible-pavement DISTRIBUTION OF LOADSstructure. Subbase-and base-coursematerials are tested for compliance withspecification requirements for gradation, liq-uid limit (LL), plasticity index (PI). and CBRvalues. When tests arc completed, limitingconditions in the subgrade and subsoilmust be determined. Materials are selectedfor each layer based on their characteristics(gradation, LL, PI. and CBR values).

Flexible-pavement design is based on theprinciple that the magnitude of stress in-duced by a wheel load decreases with depthbelow the surface. Consequently, the stres-ses induced on a given subgrade materialcan be decreased by increasing the thick-ness of the overlying layers (subbase, base,and surface courses). Figure 5-2 shows thedistribution of a single-wheel load on two

5-2 Subgrades and Base Courses

Page 81: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 5-2. Distribution of pressures under single-wheel loads

sections of flexible pavement. one with athick and one with a thin flexible-pavementstructure. In both cases, the subgrade isthe found ation that eventually carries anyload applied at the surface. Figure 5-2demonstrates that the magnitude of thestresses on the subgrade decreases as theflexible-pavement structure is thickened. Inthe left diagram in Figure 5-2, the flexible-pavement structure is thick, the load at thesubgrade level is spread over a wide area,and the stresses on the subgrade arc low.In the right diagram the structure is thin,the load at the subgrade level is confined toa much smaller area, and the stresses onthe subgrade level are significantly higher.The pattern of decreasing stresses with in-creasing depth is the basis of the conven-tional flexible-pavement design in whichsubgrade materials of low-bearing capacityarc covered with thick flexible-pavementstructures.

The distribution of pressures under a multi-ple-wheel assembly is shown in Figure 5-3,page 5-4. Multiple-wheel assemblies arebeneficial because the stress distributionsproduced by the tires do not overlap to alarge degree at shallow depths. This is il-lustrated at line A-A in Figure 5-3. There-fore, multiple-wheel assemblies are benefi-cial on thin, flexible- pavement structuresconstructed on subgrades with high-bearingcapacity.

The intensity of stress at a given point in aflexible pavement is affected by the tire-con-tact area and tire pressure. The major dif-ference in stress intensities caused by varia-tion in tire pressure occurs near the sur-face. Consequently, the surface course(pavement or a well-graded crushed ag-gregate) and base course arc the mostseriously affected by high tire pressures.

Subgrades and Base Courses 5-3

Page 82: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 5-3. Distribution of pressures produced by muitiple-wheel assemblies

SUBGRADESUsing information from a deliberate soil sur-vey as outlined in Chapter 2 of FM 5-530,consider the following factors when deter-mining the suitability of a subgrade:

• General characteristics of the subgradesoils.

• Depth to bedrock.

• Depth to the water table.

• Compaction that can be attained in thesubgrade.

• CBR values of uncompacted and com-pacted subgrades.

• Presence of weak or soft layers or or-ganics in the subsoil.

• Susceptibility to detrimental frost actionor excessive swell.

GRADE LINE

Classify the subgrade soil in accordancewith the Unified Soil Classification System(USCS) (as described in FM 5-410) and con-sider the previously listed factors to deter-mine the suitability of a subgrade material.When locating the grade line of a road orairfield, consider the suitability of the sub-grade, the depth to the water table, and thedepth to bedrock. Generally, the grade lineshould be established to obtain the bestpossible subgrade material consistent withthe design parameters. However, simplicityof construction must also be considered.

COMPACTION

Compaction normally increases the strengthof subgrade soils, The normal procedure isto specify compaction according to the re-quirements in Figure 5-4. A specificationblock should be used to determine limitsfor density and moisture content.

5-4 Subgrades and Base Courses

Page 83: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 5-4. Recommended compaction requirementsfor rear areas

Compaction is relatively simple in fill sec- Specific requirements for minimum depth oftions because all the layers are subjected to subgrade compaction for both cohesive andconstruction processes and can be com- cohesionless soils for road designs are de-pacted during construction. Compaction is scribed in Chapter 9 of this FM. This samemore difficult in cut sections. Compaction information for airfield designs is describedmust be obtained during construction to a in Chapter 12 of FM 5-430-00-2/AFPAM 32-depth at which the natural density of the 8013, Vol 2.material will resist further consolidation un-der traffic.

Subgrades and Base Courses 5-5

Page 84: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SUBGRADE COMPACTION—NORMALCASES

Cohesionless soils (except silts) can be com-pacted from the surface with heavy rollersor very heavy vibratory compactors. Cohe-sive soils [including silts) cannot be com-pacted in thick layers. In cut areas consist-ing of cohesive soils, it may be necessary toremove the subgrade material and replace itwith sequential lifts capable of being com-pacted to the required density. As a rule ofthumb, initially replace material in 6-inchlifts, then adjust the lift thickness up ordown, as necessary, to determine the mini-mum compactive effort. Compaction of co-hesive soil is best achieved with penetratingrollers such as tamping or sheepsfoot.

Compare the subsoil with compaction re-quirements for the subgrade (as describedin Chapter 9 of this FM and Chapter 12 ofFM 5-430-00-2/AFPAM 32-8013, Vol 2) todetermine if consolidation of the subsoil islikely to occur under the design traffic load.If such consolidation is likely to occur, pro-vide a means for compacting the subsoil ordesign a thicker flexible-pavement structureto prevent subsoil consolidation.

Cohesive materials, including those of rela-tively low plasticity showing little swell,should be compacted at the optimum mois-ture content determined from the density-moisture curves developed for that soil us-ing the 55-blows-per-layer compactive effort(CE 55) test. CE 55 may also be desig-nated for ASTM 1557, the American Societyof Testing and Materials code for density-moisture curves. Cohesionless, free-drain-ing materials should be compacted at mois-ture contents approaching saturation.

SUBGRADE COMPACTION—SPECIALCASES

Although compaction normally increasesthe strength of soils, some soils lose stabil-ity when scarified and rolled. Some soilsshrink excessively during dry periods andexpand excessively when they absorb mois-ture. Special treatment is required whenthese soils are encountered. The following

paragraphs describe the soils in whichthese conditions may occur and suggestedmethods of treatment.

Soils That Lose Strength

The types of soils that decrease in strengthwhen remolded are generally in the USCSCH, MH, and OH groups. They are soilsthat have been consolidated to a very highdegree, either under an overburdened loadby alternate cycles of wetting and drying orby other means, and they have developed adefinite structure. They have attained ahigh strength in the undisturbed state.Scarifying, reworking, and rolling thesesoils in cut areas may reduce the soil’s load-bearing capacity.

When these soils are encountered, obtainCBR values for the soil in both the undis-turbed and disturbed conditions. Compactthe soil that is removed to the design den-sity at the design moisture content. Othersamples should be compacted to the designdensity across the range of specified mois-ture contents. If the undisturbed value ishigher than the laboratory test results, nocompaction should be attempted and con-struction operations should be conducted toproduce the least possible soil disturbance.Since compaction should be avoided inthese cases, the total thickness designabove the subgrade may be governed by therequired depth of compaction rather thanthe CBR method. (See Chapter 3 of TM 5-825-2.)

Silts

The bearing capacity of silts, very finesands, and rock flour (predominantly USCSML and SC groups) is reasonably good ifproperly compacted within the specifiedmoisture range. Compaction of deposits ofsilt, very fine sand, and rock flour locatedin areas with a high water table can pumpwater to the surface. The material becomesquick or spongy and practically loses allload-bearing capacity. This condition canalso develop when silts and poorly draining,very fine sands are compacted at a highmoisture content. Compaction reduces theair voids so that the available water fills thevoid space. Therefore, it is difficult to

5-6 Subgrades and Base Courses

Page 85: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

obtain the desired compaction in these siltsand very fine sands at moisture contentsgreater than optimum.

Water from a wet, spongy silt subgradeoften enters the subbase and base duringcompaction through capillary action. Thisadditional moisture may have detrimental ef-fects on bearing capacity and frost suscepti-bility. If the source of water can be re-moved, it is usually not difficult to drythese deposits. These soils usually crumbleeasily and scarify readily. If the soils canbe dried, normal compaction effort shouldbe applied. However, removing the sourceof the water is often very difficult and, insome cases, impossible in the allotted con-struction period.

In areas with a high water table, drying isnot possible until the water table is suffi-ciently lowered. Compaction operations willcontinue to cause water to be pumped tothe surface. Areas of this nature are besttreated by replacing the soil with subbaseand base materials or with a dry soil thatis not adversely affected by water.

Do not disturb the subgrade where drain-age is not feasible or a high water table can-not be lowered. Also, do not disturb thesubgrade in cases where soils become satu-rated from sources other than high water ta-bles and cannot be dried (as in construc-tion during wet seasons). Compaction oflifts during wet periods can cause finesfrom the subgrade to contaminate upper lay-ers of the flexible-pavement structure.

The pumping and detrimental actions pre-viously described should be anticipatedwhenever silts or very-fine-sand subgradesare located in areas with a high water ta-ble. Pumping action limits the ability to ob-tain the desired compaction in the immedi-ate overlying material.

Swelling soils

Soils are characterized as swelling if theydisplay a significant increase in volumewith the addition of moisture. These soilscan cause trouble in any region where con-struction is accomplished during a dry sea-

son and the soils absorb moisture during asubsequent wet season. If the moisture con-tent of the compacted soil increases aftercompaction, the soil will swell and producelarge, uplift pressures. This action may re-sult in unacceptable differential heaving offlexible pavements. For military construc-tion, swelling soils are placed at moisturecontents that will not result in more than a3-percent change in volume if soil moistureis later increased.

Preswelling is a common method for treat-ing subgrade soils with expansive charac-teristics. The soil should be compacted ata moisture content at which a 3-percent orgreater swelling has already occurred. Thisreduces the impact of future expansion.Proper control of moisture content is themost important item to remember for swel-ling soils.

SELECTION OF SUBGRADE ANDSUBSOIL DESIGN CBR VALUES

The CBR test described in FM 5-530 in-cludes procedures for conducting tests onsamples compacted in test molds (designdensity and soaked for four days) and fortaking in-place CBR tests on undisturbedsamples. These tests are used to estimatethe CBR that will develop in the prototypestructure. Where the design CBR is above20, the subgrade must also meet the grada-tion and Atterberg limit requirements for asubbase given in Table 5-1.

SUBGRADE STABILIZATION

Subgrades can be stabilized mechanically(by adding granular materials), chemically(by adding chemical admixtures), or with astabilization expedient (sand-grid, matting,or geosythetics). Stabilization with chemi-cal admixtures (lime, port-land cement, flyash, and such) is generally costly but mayprove to be economically feasible, dependingon the availability of the chemical stabiliza-tion agent in comparison with the availabil-ity of granular material. Chemically stabi-lized layers should be designed according tothe criteria presented in Chapter 9 of FM5-410.

Subgrades and Base Courses 5-7

Page 86: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 5-1. Recommended maximum permissible value of gradation and Atterberg limitrequirements in subbases and select materials for roads and airfields

If mechanical stabilization is used and thestabilized material meets the gradation andAtterberg limit requirements in Table 5-1, itcan be assigned a subbase CBR rating. Ifit does not meet the requirements for a sub-base, the material must be considered a se-lect material.

A stabilization expedient may provide signific-ant time and cost savings as a substituteto other means of stabilization or lowstrength fill. The most popular of the man-made stabilizers are sand grid, roll-matting,and various types of geosynthetics, espe-cially geotextiles. Matting and sand gridare expedient methods of stabilizing cohe-sionless soils such as sand for unsurfacedroad construction. Geotextiles and othergeosynthetics are primarily used to reinforceweak subgrades, maintain the separation ofsoil layers, and control drainage throughthe road or airfield design. The

SELECT MATERIALS

When designing flexible pavements, locally

availability of these materials must beweighed with the considerable time savingsfor use of expedients in combatconstruction.

FROST SUSCEPTIBILITY OF SUBGRADE

In areas subjected to seasonal freezing andthawing, subgrade materials may exhibitfrost heave and thaw weakening. Table5-2 lists the frost-susceptibility ratings ofsoils. Those materials with the F3 and F4classifications are extremely frost-suscepti-ble, especially if the water table is less than5 feet below the top of the subgrade. Siltysoils are particularly susceptible and theirCBR value may be less than 1 during thaw-ing periods. The thaw period and resultingdegraded soil strength may last from one tofour weeks. Emphasis must be placed on re-ducing traffic loads during this period tohelp reduce the possibility of damage.

AND SUBBASE COURSES

equal to 20 are called select materials, andavailable or other inexpensive materials may those with CBR values greater than 20 arebe used between the subgrade and base called subbases.course. These layers are designated in thismanual as select materials or subbases. Where the CBR value of the subgrade, with-Those with design CBR values less than or out processing, is in the range of 20 to 50,

5-8 Subgrades and Base Courses

Page 87: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 5-2. Frost-design soil classification

select materials and subbases may not be and CL groups may be used in certainneeded. However, the subgrade cannot beassigned a design CBR value greater than20 unless it meets the gradation and plastic-ity requirements for subbases.

Where subgrade materials meet plasticity re-quirements but are deficient in grading re-quirements, it may be possible to treat anexisting subgrade by blending in stone, limerock, sand, or similar materials to producean acceptable subbase and raise the designCBR value.

MATERIALS

Select Materials

Select materials will normally be locallyavailable, coarse-grained soils (classified Gor S), although fine-grained soils in the ML

cases. Consider lime rock, coral, shell,ashes, cinders, caliche, and disintegratedgranite when evaluating sources of selectmaterial. To qualify as a select material, amaterial must meet the gradation and Atter-berg limit requirements established in Table5-1. A maximum aggregate size of 3inches will aid in meeting aggregate grada-tions.

Subbase Materials

Subbase materials may consist of naturallyoccurring, coarse-grained soils or blendedand processed soils. Lime rock, coral,shell, ashes, cinders, caliche, and disinte-grated granite may be used as subbaseswhen they meet the requirements in Table5-1, page 5-8. The existing subgrade maymeet the requirements for a subbase

Subgrades and Base Courses 5-9

Page 88: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

course, or it may be possible to treat the ex-isting subgrade to produce a subbase. Donot admix native or processed materials un-less the unmixed subgrade meets the LLand PI requirements for subbases.

A suitable subbase may be formed usingmaterial stabilized with commercial admix-tures. Portland cement. hydrated lime, flyash, and bituminous materials are com-monly used for this purpose. The plasticityof some materials can be decreased by add-ing lime or portland cement, enabling themto be used as subbases.

COMPACTION

Select and subbase materials can be proc-essed and compacted using normal compac-tion procedures. Specify compaction accord-ing to the criteria described in Figure5-4, page 5-5.

SELECTION OF DESIGN CBR

CBR tests are usually conducted on re-molded samples. However, where existingsimilar construction is available, conductCBR tests on material in place when it hasattained its maximum expected water con-tent or on undisturbed, soaked samples.The procedures for selecting test values de-scribed in the section on subgrades also ap-plies to select and subbase materials. In or-der to be used as a select or subbase, thematerial must comply with the require-ments indicated in Table 5-1, includingCBR value, gradation, and Atterberg limits.If a material meets the requirements for gra-dation and Atterberg limits for the nexthigher design CBR category, but the mate-rial’s CBR value does not meet the maxi-mum design CBR for that category, assignthe material design a CBR value equal tothe measured CBR results. For example, a

material with a measured CBR value of 37,which meets the gradation and Atterberglimit requirements for a CBR 40 subbase,should be used as a CBR 37 subbase. Con-versely, if the material failed to meet theCBR 40 subbase requirements (gradationand Atterberg limits) but met the CBR 30subbase requirements, it would be used asa CBR 30 subbase rather than a CBR 37.

Some natural materials develop satisfactoryCBR values but do not meet the gradationrequirements in Table 5-1. These materialsmay be used as select or subbase materials,as appropriate, if supported by adequate in-place CBR tests on construction projects us-ing the materials that have been in servicefor several years.

The CBR test is not applicable for use inevaluating materials stabilized with chemi-cal admixtures. These chemically stabilizedsoils must be assigned an equipment CBRvalue based on the type of admixture andmethod of application. (See Chapter 9 ofFM 5-410.) Ratings as high as 100 can beassigned to these materials when properconstruction procedures are followed.

POTENTIAL FOR FROST ACTION

Select and subbase materials which are sub-jected to freezing and thawing may exhibitdetrimental frost effects. Although thesematerials generally are not affected by exces-sive frost heave, they may lose up to 50 per-cent of their strength during thawing condi-tions. This is especially true of materialswhich have more than 20 percent fines (par-ticles passing the Number (No.) 200 sieve).If possible, materials listed in Table 5-2,page 5-9, as NFS, S1, S2, F1, or F2 shouldbe used as subbase and select materials inseasonal frost and permafrost areas.

BASE COURSEThe purpose of a base course is to distrib- shows the distribution of stress throughute the induced stresses from the wheel two base courses. When the subgradeload so that it will not exceed the strength strength is low, the stress must be reducedof the underlying soil layers. Figure 5-5 to a low value and a thick base is needed.

5-10 Subgrades and Base Courses

Page 89: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Fjgure 5-5. Distribution of stress in base courses and affects of subgrade strengthon basecourse thickness

When the subgrade strength is higher, athinner base course will provide adequatestress distribution. Because the stresses inthe base course are always higher than inthe subgrade (Figure 5-5), the base coursemust have higher strength.

The base course is normally the highest-quality structural material used in a flexible-pavement structure, having CBR valuesnear the CBR standard material (crushedlimestone). Base courses are always cohe-sionless materials and are normally proc-essed to obtain the proper gradation.

REQUIREMENTS

Give careful attention to the selection of ma-terials for base courses. The materialsshould be dense and uniformly graded sothat no differential settlement occurs. Forcontinuous stability, base courses mustmeet gradation and plasticity requirements.

Gradation

Normally, a material used as a base coursemust meet the gradation requirements out-lined in Tables 5-3, 5-4 and 5-5, page 5-12(depending on the type of material). Deter-mine gradationing mechanical

of the proposed material us-analysis. If strict adher-

ence to gradation requirements is not feasi-ble, a safe rule of thumb is to avoid usingmaterials which have more than 15 percentfines (particles passing the No. 200 sieve).

Plasticity Index and Liquid Limit

In addition to the gradation requirement, abase-course material must meet the same PIand LL requirements for a subbase materialas indicated in Table 5-1, page 5-8. Mate-rial with a LL greater than 25 or a PIgreater than 5 should not be used as abase course.

Compaction

Base-course material must be capable of be-ing compacted to meet the requirementsgiven in Figure 5-4, page 5-5. When con-structing a base course, lift thickness mustbe based on the ability to attain the re-quired density. Lift thickness is dependenton the type of material, the compactionequipment used, and the method of con-struction.

The CBR of the finished base course mustconform to that used in the design. The to-tal compacted thickness must equal that ob-tained from the flexible-pavement designcurves, Table 5-6, page 5-13 lists ninetypes of materials commonly used as base

Subgrades and Base Courses 5-11

Page 90: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 5-3. Generally suitable base course materials

Table 5-4. Desirable gradation for crushedrock or slag, and uncrushed sand and gravel

aggregates for nonmacadam base coursesTable 5-5. Desirable gradation for crushed

rock, gravel, or slag aggregatesfor macadam base courses

5-12 Subgrades and Base Courses

Page 91: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 5-6. Assigned CBR ratings forbase-course materials

courses for roads and airfields. A typicaldesign CBR is given for each type ofmaterial. Laboratory CBR tests to deter-mine design CBR are not necessary.

MATERIALS

Natural, processed, and other materials areused for base courses. Descriptions ofthese materials follow.

Natural Materials

A wide variety of gravels; sands: gravellyand sandy soils; and other naturalmaterials such as lime rock, coral, shells,and some caliches can be used alone orblended as a suitable base course. Some-times natural materials require crushing orremoval of oversize material to maintaingradation limits. Some natural materialsmay be suitable for use as a base course bymixing or blending them with othermaterials.

Sand and Gravel. Many natural deposits ofsandy and gravelly materials make satisfac-tory base-course materials, Gravel depositsdiffer widely in the relative proportions ofcoarse- and fine-grained material and in thecharacter of the rock fragments. Satisfac-tory base materials can often be produced

by blending materials from two or moredeposits. Uncrushed, clean, washed gravelis normally not suitable for a base coursebecause not enough fines are present.Fines act as a binder and fill the voids be-tween coarser particles.

Sand and Clay. Natural mixtures of sandand clay are often located in alluvialdeposits of varying thicknesses. Oftenthere are great variations in the proportionsof sand and clay from the top to the bottomof the deposit. Depending on the propor-tions of sand and clay, these deposits mayalso provide suitable base-course materials.With proper proportioning and constructionmethods, satisfactory results can be ob-tained with sand-clay soils.

Deposits of partly disintegrated rock thatconsist of fragments of rock, clay, and micaflakes should not be confused with sand-clay soils. The mica flakes make thedeposit unsuitable for use as a base course.Mistaking these deposits for a sand-claysoil may result in base-course failure.

Processed Materials

Processed materials are made by crushingand screening rock, gravel, or slag. Aproperly graded, crushed rock base-coursematerial produced from sound, durable rockmakes the highest-quality base material.Existing quarries; ledge rock; cobbles andgravel: talus deposits; coarse mine tailings;and similar hard, durable rock fragmentsare the sources of processed materials.Table 5-3 shows the common rock typesthat are generally suitable for base-coursematerial. Generally, rock which is hardenough to require blasting during excava-tion makes suitable base-course material.

Base courses made from processedmaterials can be divided into three generaltypes: stabilized, coarse-graded, andmacadam.

Stabilized. In a stabilized base course,material ranging from coarse to fine ismixed to meet the gradation requirementgiven in Table 5-4. The mixing processbe accomplished in advance (at a

Subgrades and Base Courses

can

5-13

Page 92: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

processing plant) or during the placingoperation. Because the aggregatesproduced in crushing operations or ob-tained from deposits are often deficient infines, it may be necessary to blend inselected fines to get a suitable gradation.Screenings, crusher-run fines, or naturalclav-free soil may be added for this purpose.

Coarse-Graded. A coarse-graded type ofbase course is composed of crushed rock,gravel, or slag, When gravel is used.50 percent of the material by weight musthave two or more freshly fractured faces,with the area of each face equal to at least75 percent of the smallest midsectional areaof the piece.

Macadam. The term macadam is usuallyapplied to construction in which a coarse,crushed aggregate is placed in a relativelythin layer and rolled into place. Fine ag-gregate or screenings are placed on the sur-face of the coarse-aggregate layer and rolledand broomed into the coarse rock until it isthoroughly keyed in place. Water may beUsed in the compacting and keying process.When water is used, the base is termed awater-bound macadam. The crushed rockused for macadam base courses should con-sist of clean, angular, durable particles freeof clay, organic matter. and other unwantedmaterial or coating, Any hard, durable,crushed aggregate can be used, providedthe coarse aggregate is one size and thefine aggregate will key into the coarse ag-gregate. Aggregates for macadam-type con -struction should meet the gradation require-ments given in Table 5-5, page 5-12.

Other Materials

In some TO areas, deposits of natural sandand gravel and sources of crushed rock arenot available. This has led to the develop-ment of base courses from materials thatnormally would not be considered. Theseinclude caliche, lime rock, shells, cinders,coral, iron ore, rubble, and other similarmaterials. Some of these materials arcweak rock that crush or degrade under con-struction traffice to produce composite basematerials similar to those described in thepreceding paragraphs. Others develop a

cementing action that results in a satisfac-tory base.

These materials cannot be judged on thebasis of the gradation limits used for othermaterials. Rather, they arc judged on thebasis of service behavior. Strength tests onlaboratory samples arc not satisfactory be-cause the method of preparing the sampleseldom replicates the characteristics of thematerial in place. The PI is a reasonablygood criterion for determining the suita-bility of these materials as base courses.As a general rule, a low PI is a neces-sity. However, observation of these types ofbase materials in existing roads and pave-ments is the most reliable indicator ofwhether or not they will be satisfactory.

Coral. Coral is commonly found along thecoastlines of the Pacific Ocean and theCaribbean Sea. Coral is normally very an-gular and, as such, its greatest assets as aconstruction material are its bonding proper-ties. These properties vary, based on theamount of volcanic impurities, the propor-tion of fine and coarse material, and theage and length of exposure to the elements.Proper moisture control, drainage, and com-paction arc essential to obtain satisfactoryresults. Avoid variations of more than 1percent from optimum moisture content.Uncompacted and poorly drained coral issusceptible to high capillary rise, resultingin too much moisture and loss of stability.Sprinkling with sea water or sodiumchloride in solution promotes bonding whenrollers are used. As a rule of thumb, coralshould cure for a minimum of 72 hoursafter compaction is completed.

Caliche. Caliche is a by-product of chemi-cal weathering processes. It is composed oflimestones, silts, and clays cementedtogether by lime, iron oxide, or salt.Caliche has been used extensively in aridregions as a base material because of itsability to recement when saturated withwater, compacted, and given a settingperiod. Caliche varies in content (lime-stone, silt, and clay) and in degree of cemen -tation. It is important that caliche of good,uniform quality be obtained from deposits

5-14 Subgrades and Base Courses

Page 93: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

and that it be compacted within a specifiedmoisture range.

After caliches have been air-dried for 72hours, the LL of the material passing theNo. 40 sieve should not exceed 35, and thePI should not exceed 10. For base-coursematerial, caliches should be crushed tomeet the following gradations:

Percent passing 2-inch sieve 100Percent passing No. 40 sieve 15-35Percent passing No. 200 sieve 0-20

Stripping should be used to remove unde-sirable material from surface deposits ofcaliche.

Tuff. Tuff and other cement-like materialsof volcanic origin may be used for basecourses. Tuff bases are constructed in thesame manner as other base courses exceptthat the oversize pieces are broken and thebase is compacted with sheepsfoot rollers af-ter the tuff is dumped and spread. The sur-face is then graded and final compactionand finishing are accomplished.

Rubble. The debris or rubble of destroyedbuildings may be used in constructing basecourses. Jagged pieces of metal and simi-lar objects must be removed: large pieces ofrubble should be broken into 3-inch piecesor smaller. Caution should be exercisedwhen using rubble in a tacticalenvironment to avoid mines or booby traps.

Bituminous Base. In general, a bituminousbase course may be considered equal, onan inch-for-inch basis, to other types ofhigh-quality base courses. Bituminous mix-tures are frequently used as base coursesbeneath high-use bituminous pavements,particularly for rear-area airfields carryingheavy traffic, Bituminous bases may be ad-vantageous when locally available aggre-gates are relatively weak and of poor qual-ity, when mixing-plant and bituminous ma-terials are readily available, or when a rela-tively thick structure is required for the traf-f ic .

When a bituminous base course is used, itis placed in lifts no more than 3 1/2 inches

thick. If a bituminous base is used, thebinder and leveling courses may be omittedand the surface course may be laid directlyon the base course.

SELECTION OF BASE COURSE

Selection of the type of base-course con-struction depends on the materials andequipment available and the anticipatedweather conditions during construction. Acomplete investigation should be made todetermine the location and characteristicsof all natural materials suitable for base-course construction. Base courses of un-treated natural materials are less affectedby adverse weather and normally requireless technical control. Untreated bases arerelatively easy and fast to build and arepreferable to bituminous or cement-stabi-lized types. This is true even where suit-able admixture materials for such construc-tion are readily available, which is not truein many areas of the world.

SPECIAL CONSIDERATIONS FORSEASONAL FROST AND PERMAFROST

CONDITIONS

Since base-course materials are near thesurface of the road or airfield, the amountof strength loss during thawing periods willhave a strong influence on the life of the fa-cility. If possible, materials listed in Table5-2, page 5-9, as nonfrost susceptible(NFS), or possibly frost susceptible (S1 orS2) should be used as base courses in sea-sonal frost and permafrost areas.

CONSTRUCTION OPERATIONS

Construction operations for roads and air-fields include the following tasks which areorganized according to the constructionschedule and quality control plan for theproject.

Fine Grading

The subgrade is fine graded to achieve thedesired cross section established by finalgrade stakes. Before placing selectmaterial, subbase, and base course, the

Subgrades and Base Courses 5-15

Page 94: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

subgrade should be compacted to attain therequired density, and ruts and other softspots should be corrected.

Hauling, Placing, and Spreading

Placing and spreading material on theprepared subgrade may begin at the pointnearest the borrow source or at the pointfarthest from the source. The advantage ofworking from the point nearest the sourceis that the haul vehicles can be routed overthe spread material, which compacts thebase and avoids damage to the subgrade.An advantage of working from the point far-thest from the source is that hauling equip-ment will further compact the subgrade.Also, this practice will not overwork thebase course, which can cause unwantedsegregation. This method also reveals anyweak spots in the subgrade so that theycan be corrected prior to placement of thebase courses, and interferes less withspreading and compaction equipment.

The self-propelled aggregate spreader is thepreferred piece of equipment for placing abase course. If a self-propelled spreader isnot available, base-course material can bespread using towed spreaders, scrapers, ordump trucks. If equipment capable ofspreading the aggregate in even lifts is notavailable, the material can be initiallydumped in long windrows and subsequentlyspread with graders, dozers, or front-endloaders.

Lift thickness should be based on theability to compact the material to the re-quired density. A good rule of thumb is toinitially place the base course in 6-inchlifts. After testing the compacted density,increase or decrease the lift thickness asnecessary to meet the project requirements.

Blending and Mixing

Materials to be blended and mixed shouldbe spread on the road, runway, or taxiwayin correct proportions, with the finermaterial on top. Fold the fine material intothe coarser aggregate with the grader blade.If available, dry-mix the material usingblades, disks, harrows, or rototillers, leav-ing the material in windrows. When a

grader is used, thoroughly mix thematerials by blading the windrows ofmaterials from one side of the area to theother, with the blade of the grader set togive a rolling action to the material. Thecoarse and fine aggregates can also bemixed in mechanical plants (mobile or sta-tionary) or on a paved area with gradersand bucket loaders. Proportionally dis-tribute the coarse and fine aggregates byweight or volume in quantities so that thespecified gradation, LL, and PI requirementsare attained after the base has been placedand compacted. Mixing operations shouldproduce uniform blending.

When mechanical mixing is used, place thecoarse and fine aggregates in separate stock-piles or adjacent windrows to permit easyproportioning. When bucket loaders areused, place the fine- and coarse-aggregateportions in adjacent windrows on a pavedarea. Blade the windrows together to meetthe requirements specified for the project.

Watering Base Materials

As in subgrade-compaction operations, ob-taining the specified compacted density re-quires that the material be placed and com-pacted at a moisture content inside thespecification block. The moisture contentof the base material at the site can be ob-tained by a nucIear densometer, a speedymoisture tester, or by expedient methods.Given the on-site moisture content, the en-gineer in charge can calculate exactly howmuch water is to be added or if the baseneeds to be aerated to achieve the specifiedmoisture content range.

Controlled watering can be done with atruck-mounted waler distributor. Asphaltdistributors should not be used because thepump lubrication system is not designed forwater. Any container capable of movementand gravity discharge of water may be usedas an expedient water distributor.

Compacting

Base-course compacting must produce auniformly dense layer that conforms to thespecification block. Compact base-coursematerial with vibratory or heavy.

5-16 Subgrades and Base Courses

Page 95: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

rubber-tired rollers. Maintain moisture con-tent during the compaction procedurewithin the specified moisture-content range.Compact each Iayer through the full depthto the required density. Measure field den-sities on the total sample. Use a test stripto determine which rollers are most effec-tive and how many roller passes are neces-sary to achieve the desired compaction.The care and judgment used when con-structing the base course will directlyreflect on the quality of the finished flexiblepavement. Base-course layers that containgravel and soil-binder material may be com-pacted initially with a sheepsfoot roller andrubber -tired rollers. Rubber-tired rollersare particularly effective in compacting basematerials if a kneading motion is requiredto adjust and pack the particles. Base cour-ses of crushed rock, lime rock, and shellare compacted with vibratory, steel-wheeled,or rubber -tired rollers. Select the equip-ment and methods on each job to suit thecharacteristics of the base material. Whenusing rollers, begin compaction on the out-side edges and work inward, overlappingpasses by one-half of a roller width.

Finishing

Finishing operations must closely followcompaction to furnish a crowned, light,water-shedding surface free of ruts anddepressions that would inhibit runoff. Usethe grader for finishing compacted ag-gregate bases. Blade the material from oneside of the runway, taxiway, or road to themiddle and back to the edge until the re-quired lines and grades are obtained.Before final rolling, the bladed materialmust be within the specified moisture-con-tent range so it will consolidate with the un-derlying material to form a dense, unyield-ing mass. If this is not done, thin layers ofthe material will not be bound to the base,and peeling and scabbing may result. Finalrolling is done with rubber-tired and steel-wheeled rollers.

SPECIAL PROCEDURE FOR MACADAMBASES

Construction of macadam base courses re-quires the procedures that follow.

Preparing Subgrade

If a macadam base course is constructed ona material with high plasticity, there maybe base infiltration. This can be preventedwith a blanket course of fine material suchas crusher screenings or 3 to 4 inches ofsand. The blanket course should be lightlymoistened and rolled to a smooth surfacebefore spreading the coarse macadam ag-gregate. A membrane or a geotextile fabricmay be used in lieu of the blanket course.

Spreading

Macadam aggregate must be placed andspread carefully to ensure that haulingvehicles do not add objectionable materialto the aggregate. Care is particularly neces-sary when placing the aggregate at thepoint nearest to the source and routinghauling vehicles over the spread material.If the compacted thickness of the lift is 4 in-ches or less, spread the loose macadam ag-gregate in a uniform layer of sufficientdepth to meet requirements. For greatercompacted thickness, apply the aggregatesuccessively in two or more layers. Spread-ing should be from dump boards, towed ag-gregate spreaders, or moving vehicles thatdistribute the material in a uniform layer.When more than one layer is required, con-struction procedures are identical for alllayers.

Compacting

Immediately following spreading, compactthe coarse aggregate the full width of thestrip by rolling it with a steel-wheeledroller. Rolling should progress graduallyfrom the sides to the middle of each stripin a crown section, and from the low sideto the high side where there is a transverseslope across the road, runway, or taxiway.Continue rolling until the absence of creepor wave movement of the aggregate aheadof the roller indicates that the aggregate isstable. Do not attempt rolling when thesubgrade is softened by rain.

Applying Screenings

After the coarse aggregate has beenthoroughly stabilized and set by rolling, dis-tribute sufficient screenings (fine

Subgrades and Base Courses 5-17

Page 96: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

aggregates) to fill the voids in the surface.Roll continuously while screenings arebeing spread, so the jarring effect of theroller will cause them to settle into surfacevoids. Spread screenings in thin layers byusing hand shovels, mechanical spreaders,or moving trucks. Do not dump them inpiles on the coarse aggregate. If necessaryuse hand or drag brooms to distributescreenings during rolling.

Do not apply screenings 100 thick becausethey will bridge over the voids and preventthe direct bearing of the roller on thecoarse aggregate. Continue spreading,sweeping, and rolling until no more screen-ings can be forced into the voids. Startsprinkling the surface with water after thescreenings have been spread. The sprin-kling causes the screenings to be flusheddown into the voids of the aggregate. Thesurface is then rolled. Do not saturate andsoften the subgrade.

Continue sprinkling and rolling until a mix-ture of screenings and water forms, fills allvoids, and gathers in a small wave beforeeach roller. When a section of a strip hasbeen grouted thoroughly, allow it to drycompletely before performing additionalwork.

FINISHED SURFACES

The base-course surface determines thesmoothness of the finished pavement. Ifthe finished base dots not conform to thespecified grade when tested with a 12-footstraightedge, the finished pavement alsowill not conform. The base surface shouldbe smooth and conform to specified designrequirements.

When tested with a 12-foot straightedge ap-plied parallel and perpendicular to the cen-terline of the paved area, the surface of thebase course should not show any deviationin excess of 3/4 inch for roads and airfields[for propeller-type aircraft) or 1/8 inch forjet aircraft. Correct any deviation in excessof these figures, and remove material to thetotal depth of the lift, replacing with newmaterial and compacting as specified above.

SLUSH ROLLING

The purpose of slush rolling (rolling withenough water to produce a slushy surface)is to achieve compaction when conventionalmethods fail. Slush rolling should be per-mitted only on a free-draining, cured basecourse. Slushing requires a considerableamount of water on the surface. The quan-tity varies greatly with the type of material,the temperature, and the humidity. If thesurface is generally satisfactory but hassome large areas requiring slushing, slushonly the rough areas. Slushing brings finesto the top and creates voids. In general,slush rolling should not be used on a high-quality base-course material. It should beused only when required by the specifica-tions or when conventional compactionmethods have failed.

Applying Water

Engineers must calculate a water applica-tion rate in terms of gallons per squareyard in order to allow the water distributoroperator to accurately apply water. Areasonable estimate for applying water to a6-inch lift is 0.5 to 1.0 gallon per squareyard. The rollers must follow immediatelybehind the water truck to achieve thedesired results because the roller shouldcarry a wave of water ahead of it as it pas-ses over the base course.

Rolling Equipment

Use pneumatic-tired, vibratory, or steel-wheeled rollers to obtain a smooth finish onthe base course. Continue rolling until com-paction has been obtained.

Finishing

There are usually small rivulets or ridges offines left on the surface after slushing iscompleted. Where these are excessive orwhen the thickness of the blanket of finesis excessive, sprinkle the surface with waterand hone (dress lightly) with a graderblade. This delicate operation requires agood operator and a sharp, true blade. Fol-low the grader immediately with apneumatic roller to reset the surface.

5-18 Subgrades and Base Courses

Page 97: Army Construction Manual FM5 430 Vol1 Entire

WET ROLLING

All base courses require a final surfacefinish. The final finish should be obtainedimmediately after final compaction or proofrolling. For less critical base courses orwhere deemed necessary by the project en-gineer, wet rolling and slush rolling may beused to obtain the final finish. Bothmethods have strong points and, in somecases, a job may require a combination ofthe two.

Applying Water

Wet rolling does not require the largeamount of water demanded for slush roll-ing, and the base course does not need togo through the curing period required bythe slush-rolling method. Apply enoughwater to the base course to raise the mois-ture content of the upper 1 to 2 inches ofthe base course to approximately 2 percent-age points above the minimum moisturecontent. The percent of moisture will varywith the type of material and is a matter ofjudgement by the project’s quality controlmanager.

Finishing

Finish the surface by having the graderblade lightly cut the final surface. Thelight blading will loosen the fines; the coar-

FM 5-430-00-1/AFPAM 32-8013, Vol 1

ser particles of the base course will be car-ried along by the blade to form a windrowat the edge of the section being finished.This coarse aggregate can be evenly dis-tributed over the area and incorporated intothe surface of the base by a steel-wheeledroller closely following the grader. Addition-al water may be required, and rolling bythe steel-wheeled and pneumatic-tiredrollers must be continued until a smooth,dense surface is obtained. This methodcan also be used for correcting minor sur-face irregularities in the base course.

QUALITY CONTROL

Quality control is essential to any project’ssuccess. Although visual inspection is im-portant, it is not, by itself, sufficient to con-trol the construction of all coursesdescribed in this chapter, particularly thosewhich contain considerable fine material.Depending on the type of base, control testswill include determinations of gradation,mixing proportions, plasticity character-istics, moisture content, field density, liftthickness, and CBR values. These tests aredescribed in detail in FM 5-530. Prior tostarting construction, a detailed quality con-trol plan should be developed which addres-ses testing procedures, frequency, locationand, most importantly, remedial actions.

Subgrades and Base Courses 5-19

Page 98: Army Construction Manual FM5 430 Vol1 Entire

Drainage

Section I. Construction Drainage

Preliminary Measures

Drainage Hydrology

The Hydrograph

Drainage-System Design

Design Procedures

Estimating Runoff Using the Rational Method

Section II. Open-Channel Design

Design Factors

Design Considerations

Design Techniques

Section III. Culverts

Culvert Types and Designs

Ponding Areas

Drop Inlets and Gratings

Subsurface DrainageSection IV. Surface Drainage Design in Arctic and Subarctic RegionsFords, Dips, Causeways, and Bridges Erosion Control Nonuse Areas and Open Channels Culvert Outlets

FM 5-430-00-1/AFPAM 32-8013, Vol 1

DRAINAGE

Inadequate drainage is the most common cause of road andairfield failure. Therefore, drainage is a vital consideration inplanning, designing, and building military roads and airfields.It is important during both construction and use.

SECTION I. CONSTRUCTION DRAINAGE

Commanders and construction supervisors continuously emphasized by the command.must ensure continuous maintenance of the Construction drainage must be completeddrainage system during construction of a before needed; when a storm begins it ismilitary road or airfield. The construction too late to start drainage work. Construc-drainage system is temporarily established tion-drainage measures used during dif-to prevent construction delays and struc- ferent phases of construction are discussedtural failure before completion. Generally, below.long delays will result if drainage is not

PRELIMINARY MEASURES

RECONNAISSANCE

Prior to the start of construction, prelimi-nary reconnaissance of an area should dis-close features that require advance drainageplanning and operations. These features in-clude—

• Springs and seepage on hillsides whichmay indicate perched or high watertables detrimental to cuts.

Ž Trees adjacent to dry or low-flowstreams that could receive their rootwater from a groundwater table flowingnear the surface. Compacted fillsacross such areas could change themovement of the flow.

• Vegetation or cover that, if removedduring the clearing and grubbing phaseof construction, could increase surfacerunoff.

Ž The presence of level areas which havegood vegetation and adjacent slopes.These areas may indicate a shallowgroundwater table with capillary watermovement and may require interceptingsubsurface drainage.

Ž Streams that should be checked for nor-mal high-water and flood indicators.

PROTECTIVE MEASURES

Controlling runoff during construction canbe costly, The following measures can help

Drainage 6-1

Page 99: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

maintain satisfactory drainage during con-struction:

• Make maximum use of existing ditchesand drainage features. Where possible,grade down hill to allow economical grad-ing and to take advantage of naturaldrainage

• Use temporary ditches to help construc-tion drainage. Ensure efforts are madeto drain pavement subgrade excavationsand base courses to prevent detrimentalsaturation. Carefully consider thedrainage of all construction roads,equipment areas, borrow pits, andwaste areas.

Ž Be aware of areas where open excava-tion can lead to excessive erosion. Thedischarge of turbid water to localstreams will require temporary reten-tion structures.

• Hold random excavation to a minimum,and sod or seed finished surfaces imme-diately.

Ž Plan timely installation of final storm-drain facilities and backfilling opera-tions to allow maximum use during con-struction.

AREA CLEARING

The following constraints should be con-sidered:

Existing Drainage

Clear excess vegetation from streams. Thisincreases the velocity and quantity of flow.Widening the stream can also increase theflow. Bends and meanders can be cut tostraighten the stream. Use care in makingmajor alignment changes because they canchange the hydraulic characteristics of thestream. This change could adversely affectother parts of the stream.

Vegetation Removal

Military projects may require the removal ofall vegetation from large areas. Consider

the following factors with regard to construc-tion stripping:

• Select a disposal area that will not inter-fere with or divert the drainage patternof surface runoff. If the drainage pat-tern is disturbed, the stripped materialmay form a barrier resulting in pendingand may otherwise affect adjacent areas.

Ž Be aware that removing the vegetationfrom an area can lead to excessive sur-face runoff and erosion. This couldlead, in turn, to silting of channels andflooding of low areas.

• Consider that serious bank erosion dueto surface runoff may occur if vegeta-tion adjacent to the banks of streams orditches is removed. To avoid this, itmay be necessary to leave the vegeta-tion or to provide a berm with a chute.

Ž In large, cleared areas, control runoffsediments to prevent failure of otherstructures and possible adverse environ-mental effects. This is more of a con-tern in permanent construction than inwartime TO construction.

Clearing, Grubbing, and Stripping

Any clearing, grubbing, and stripping mustinclude filling holes and back dragging orgrading to a slight slope. This will ensureproper runoff and prevent water from col-lecting and saturating the subgrade. If fill-ing and grading is not done, the advent ofrain will make it necessary to strip off anywet soil until dry soil is reached to startthe fill. Some ditching may be required todirect the surface flow to an outlet point.

Fill

When placing fill, exercise firm control overthe project to prevent adverse effects fromimproper drainage procedures. Some of thefactors requiring attention are—

• The fill section must be rolled smooth atthe end of each working day to seal thesurface. No areas should be left thatcan hold standing water.

6-2 Drainage

Page 100: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• The fill surface must be kept free of rutscaused by trucks and other equipment.These depressions collect rain andsaturate the subgrade. Also, the sur-face must be crowned to dischargerunoff quickly.

• When the fill area is large, it may benecessary to create swales (depressedareas) to conduct surface runoff to dis-charge outlets.

• To allow fill to proceed, it may be neces-sary to install temporary culverts in thefill area in places other than finaldesign locations. After the fill area hasreached design depth, the design cul-verts can be properly trenched in place.

Ditching

Use interception ditches during construc-tion to collect and divert surface runoffbefore building the designed system. Priorto construction, conduct a site investigationof the general layout, consistent with thework plan. When interception ditches can-not be made part of the design drainage.

consider removing the ditches by backfillingand compacting.

Locate interceptor ditches on hillsides andat the foot of slopes to intercept and divertrunoff from the construction site. Makethese ditches part of the final drainage sys-tem wherever possible. Roadside ditches, re-quired during all construction stages,should be placed at design locations.

During construction, use deep ditches forsubsurface drainage. They interceptgroundwater flow, as shown in Figure 6-1.If groundwater flow must be intercepted butditching is not possible, modify the ditchinto a subsurface drainpipe system.

Ditching may be required in swamp areasto either continue drainage ditches to anoutlet point or drain the area.

Engineers may use explosives in suchcases, since the soil may not be capable ofsupporting construction equipment.Draglines should also be considered.

Figure 6-1. Deep interceptor ditch

Drainage 6-3

Page 101: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM

Timber or steel mats can

32-8013, Vol 1

be used to providea firm foundation and support equipmentduring the operation.

Culverts

Culverts are required during construction toallow surface runoff. If streams must bediverted to allow the construction of

DRAINAGE HYDROLOGY

The hydrologic cycle is the continuousprocess which carries water from the oceanto the atmosphere, to the land, and back tothe sea. A number of different subcyclescan take place concurrently in the overallcycle and are discussed below.

PRECIPITATION

Rainfall is the moisture-delivery mechanismof primary concern to most militarydrainage designers. Snowmelt may be ofgreater concern in colder climates or in thedesign of reservoirs in milder regions.These concerns are beyond the scope of thismanual, but they are included in TM 5-852-7.The amount of rainfall that evaporatesdepends on the surface temperature ofground features, the air temperature, thewind speed, and the relative humidity.Evaporation occurs while rain is falling tothe ground and after it lands on vegetationand other ground cover.

INTERCEPTION

Rainfall coming to rest on vegetation is saidto have been intercepted. Large quantitiesof water can be trapped in the leaf canopyof trees and plants. Rain does not reachthe soil until the holding capacity of thevegetation canopy is exceeded.

INFILTRATION

A significant portion of the water that ac-tually strikes the soil soaks into theground. This process is call infiltration.The rate of absorption and the quantity of

permanent culverts, use temporary culvertsin the construction area. Never closenatural drainage channels, even if they arecurrently dry. If these channels are closed,surface runoff from sudden storms couldcause a serious problem. These conditionsmust be anticipated. Construction drainagemust keep pace with the constructionproject.

water absorbed depends on the soil type,the vegetation, the terrain slope, and thesoil moistness prior to the rain. Storm-water runoff begins to accumulate onlywhen the rate of rainfall exceeds the rate ofinfiltration.

DETENTION

Before overland water flow can begin itsdownhill motion, it must be deep enough toovercome any obstacles to its movement.Detention is the amount of water requiredto fill depressions of any size in the earth’ssurface. Except by infiltration or evapora-tion, no water can leave a depression untilthe holding capacity of the depression hasbeen exceeded.

TRANSPIRATION

On a long-term basis, vegetation returnswater to the atmosphere through a processcalled transpiration. Because of the time in-volved, transpiration has no immediate ef-fect on water runoff in an area.

RUNOFF

Evaporation, interception, infiltration, deten-tion, and transpiration are all moisture los-ses, Runoff is precipitation minus thesemoisture losses.

STORMS

Storms can deliver a large quantity of waterto the earth in a short period of time. For

6-4 Drainage

Page 102: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol

that reason, the study of storms is an im-portant part of the study of drainage hydrol-ogy. This section discusses storms interms of duration, frequency, and intensity.It describes procedures for determining max-imum storms and introduces the subject ofrunoff.

Duration

Duration is the length of time a stormlasts, After many years of observation,hydrologists have determined that a stormof long duration usually has low intensity.In contrast. a high-intensity storm usuallyhas a short duration. Figure 6-2 showstypical storm hydrography developed by theNational Weather Service. Time, usuallymeasured in hours, is depicted horizontally.The amount of rain for each unit of time ismeasured vertically in inches. The totalamount of precipitation is the area of thegraph. The five main types of storms aredescribed below.

Thunderstorms

Thunderstorms, represented by Figure6-2(a), are local atmospheric disturbancesof short duration and high average rate ofrainfall (intensity). They are characterizedby thunder, lightning, torrential rain, andsometimes hail, Thunderstorms tend togovern the design of drainage for smallareas.

Moderate Storms

Moderate storms, represented by Figure6-2(b), cover larger areas for several hourswith moderate intensity. These storms

Figure 6-2. Typical storm hyetographs

Drainage 6-5

Page 103: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

develop greater total precipitation thanthunderstorms. The moderate storm nor-mally controls the design of drainage struc-tures for medium-sized basins.

Long-Duration Storms

Long-duration storms, represented by Fig-ure 6-2(c), page 6-5, often have severalpeaks of high rainfall. Durations may beup to several days, developing very largeamounts of precipitation at relatively lowaverage rates of rain fall. With a lowaverage rate of rainfall, such storms havelittle or no impact on small- or medium-sized drainage basins, but they normallycontrol the design of drainage structures forlarge basins.

Monsoons

Monsoons arc seasonal winds of the IndianOcean and southern Asia. These windsblow from the south during April to Octoberand from the north during the rest of theyear. Heavy rains usually characterize theApril-to-October season. This rain is notnormally continuous; it rises to a peak andthen subsides in a cyclic fashion.

Tropical Cyclones

Hurricanes and typhoons are storms causedby severe cyclonic disturbances over a widearea. Precipitation is normally heavy andlong.

Design Life Versus Actual Life of a Struc-ture

The design storm is an idealized storm thatis expected 10 be equalled or exceeded atleast once during the design life of adrainage system. For example, if a drain-age system has been designed for an es-timated life of five years, then the designstorm will have a five-year frequency. Thefrequency of a design storm is the averagereturn period of a storm. For example, if atwo-year frequency storm has an intensityof 1.5 inches of rainfall per hour, it can beexpected that a storm of that intensity orgreater will recur an average of once everytwo years. Two years is also called thereturn period. The reciprocal of the return

period is the probability of having a stormof that value or greater in any one year.

For the two-year -frequency storm, the prob-ability of having a storm equalling or ex-ceeding the value in any one year is 0.5(two out of four times).

The design-storm frequency for TO construc-tion is normally two years. If constructionwith a longer estimated life is desired, theappropriate design storm should bespecified in the authorizing directive.

As with any statistical method of describingessentially random, natural events such asweather, there is a degree of uncertainty.The two-year design storm occurs on theaverage every two years; it is not guaran-teed to occur every two years. Statistically,the probability of a storm equal to orgreater than the two-year design storm oc-curring in any two years is 0.75 (three outof four times). Details of the statistics in-volved can be found in hydrology textbooks.

WEATHER DATA

If there are extensive rainfall and rain-raterecords for the location of interest, and ifhydrologists have examined those recordsstatistically to formulate intensity-durationtables, then those tables can be obtainedthrough the Air Force staff weather officer.The staff weather officer is normally locatedat division level.

Within the United States, the data willgenerally come from the National WeatherService, either directly or through the AirForce. Overseas, the staff weather officermay be able to obtain data from localgovernment sources, but it may take consid-erable time to obtain. However, it is unlike-ly that such pinpoint data is available inmany overseas TO locations. When weatherdata is not available, use rainfall isohyetalmaps. Isohyetal maps have contours ofequal rainfall intensity just as topographicmaps have contours of equal elevation. Fig-ure 6-3 is an isohyetal map of the world, inthis case showing the iso-intensity lines fora 60-minute, 2-year storm.

6-6 Drainage

Page 104: Army Construction Manual FM5 430 Vol1 Entire

Figure 6-3. W

orld isohyetal map

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

Dra

ina

ge

6

-7

40 40 ATLANTIC OCEAN

20 PACIFIC OCEAN 20

o o

INDIAN OCEAN

20 20

PACIFIC OCEAN

40 \/ "-', 40

120 100 80 60 40 20 o 20 40 60 80

Figure 6-3. World isohyetal map

Page 105: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

To properly read a value on the isohyetalmap, find the project location and read thevalue of the appropriate isohyet(s).

Do not interpolate. If a project locationfalls—

Ž On an isohyetal line, read the value ofthat isohyet.

• Between two isohyets, read the largervalue.

• Within an encircling isohyetal line, readthe value of the encircling isohyet.

Examples (in inches per hour (in/hr)):

Southern Australia 1.0North Dakota 1.5Florida 2.5Washington, DC 1.5Vietnam 2.5Cuba 2.5New Orleans, Louisiana 2.5

Note that the intensities just found are fora 60-minute storm. This must now be ad-justed to the critical duration of the projectunder construction. Once the critical dura-tion has been determined, make the adjust -ment using the standard rainfall intensity-duration curves in Figure 6-4.

The standard curves are numbered 1.0, 2.0,3.0, and 4.0, with intermediate values readi-ly interpolated. Note that curve number 1passes through 1 inch per hour at 60minutes, curve number 2 passes through 2inches per hour at 60 minutes, and so on.

Where intensity is known for any nonarcticlocation (taken from the isohyetal map, Fig-ure 6-3, page 6-7) and critical duration iscalculated, the intensity (1) can easily bedetermined. (The standard intensity-dura-tion curves are applicable to any frequency,not just a 2-year frequency.)

To use Figure 6-4, enter the graph usingthe Duration in Minutes (Tc). Follow theline vertically until it intersects the curvewhose number corresponds to the 60-minute intensity determined from theisohyetal map (or from pinpoint data, if YOU

choose not to draw your own intensity-dura-tion curve). Read horizontally to the left todetermine the rainfall intensity (I) in inchesper hour. The following is an example:

2-yr CriticalIntensity Duration (in/hr) (min) (in/hr)

1.0 5 0 1.21.5 3 0 2.42.0 10 5.2

RUNOFF

Precipitation supplies water to the surface,but evaporation, interception, and infiltra-tion begin to draw water at the start of thestorm. Eventually, if the storm is strongenough, vegetation and other surface char-acteristics, such as depressions and soil,will become saturated, allowing water toflow freely over the surface. This conditionis called runoff and is usually measured incubic feet per second (cfs). Runoff beginssometime after the beginning of precipita-tion and may continue long after precipita-tion ends.

The total quantity of runoff from a givenarea, after it is collected in channels andstreams, is the flow estimate used to designan area’s drainage structures.

Transpiration and evaporation also drawfrom the water supplied by precipitation.However, these are relatively small lossesand will not usually affect military drainagedesign. Estimating runoff will be discussedlater in this chapter. Once the runoff hasbeen determined, necessary ditches and cul-verts can be designed.

6-8 Drainage

Page 106: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-4. Standard rainfall intensity-duration curves

THE HYDROGRAPH

Stream-water flow may originate from sur-face runoff, groundwater, or both. Runoffreaches the stream as overland flow.Groundwater flow results from side-bankseepage and springs. The hydrographydepicts the fluctuations of flow with regardto time.

The elements of a hydrograph are baseflow, lag time, peak flow, lime of concentra-tion (TOC), and flow volume. Each streamwill have its own characteristic hydrographywith widely varying values for the elements.A typical stream-flow hydrography is shownin Figure 6-5, page 6-10.

BASE FLOW

The base flow of a stream depends uponthe amount of groundwater that seeps into

the stream and its tributaries from theirbanks and the flow from permanent springsand swamps. Depending on the area,climate, and groundwater level, it may flowat a fairly constant rate. Conversely, theflow may fluctuate widely or even cease com-pletely for some periods of time.

LAG TIMES

When precipitation begins over an area,there is an initial period during which theloss factors induced by interception, infiltra-tion, and detention take effect before anysurface runoff takes place. Stream flow willincrease only when these initial losses havebeen satisfied and surface runoff begins.This is known as initial lag time. Thelength of this lag time is influenced by

Drainage 6-9

Page 107: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-5. Typical hydrograph

vegetation and other terrain characteristics. the hydrography peaks at that point. TOCFor example, a grass-covered parking areawill have a longer initial lag period than anasphalt parking lot of the same size.A second lag time occurs between the timethe stern] reaches its peak pecipitationrate and the time the stream reaches itsmaximum flow. The length of this secon-dary lag time is influenced by the size ofthe area drained. In small- and moderately -sized drainage areas, there will be onlyslight differences between storm peak andstream peak.

PEAK FLOW

The peak of the hydrography is the maxi-mum stream flow that will occur during aparticular storm. In general, peak flow isgenerated when the entire drained area isdischarging its runoff. Peak flow is readdirectly from the maximum ordinate of thehydrograph This flow determines the sizeof the drainage structures required at thebasin outlet.

TIME OF CONCENTRATION

is critical to the drainage engineer, since itdetermines the duration of the storm thatwill demand the most from the drainage sys-tem; that is, the storm’s critical duration.

VOLUME OF FLOW

The area under the curve of the hydrographyindicates the total flow, in cubic feet, result-ing from any particular storm. It is used indrainage design for determining pendingtimes when it is practical to use culvertswith submerged inlets.

CONSTRUCTING A HYDROGRAPHY

A hydrograph is constructed by measuringa stream’s rise and fall and the times re-lated to these changes in flow. When con-structing a hydrograph—

• The base flow must be measured at atime when there have been no recentstorms. A field reconnaissance must bemade for this measurement.

• The peak flow can be estimated usingthe hasty runoff estimation presented inthis chapter.

• The general shape of the curve of thehydrograph will be similar to thatshown in Figure 6-5.

The TOC is the time it lakes for an entiredrainage basin to begin contributing runoffto the stream. Assuming uniform rainfall,

6-10 Drainage

Page 108: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

DRAINAGE-SYSTEM DESIGN

DESIGN DATA REQUIREMENTS

Before designing a drainage system, surveythe various types and sources of drainage-related information, The survey should in-clude, as a minimum, information concern-ing the area’s topography, meteorologicalrecords, soil characteristics, and availableconstruction resources.

TOPOGRAPHICAL INFORMATION

Give special attention to the vicinity of theproposed facility as well as the presence ofany topographical features that may con-tribute runoff to the project area. The com-pleted facility often will interfere with thesite’s natural drainage. Therefore, whenanalyzing the effects of the surrounding ter-rain—

• Identify all areas that contribute runoffto the site.

• Determine the general size and shape ofthese contributing areas.

• Determine the natural direction of sur-face-water flow, the slope of the land,and the type and extent of naturalground cover.

• Locate natural channels that can beused to move runoff within the project

area or to divertsite.

it away from the work

METEOROLOGICAL DATA

Gather information on general climatic con-ditions, seasonal variations in rainstorms,and intensity and duration of representativestorms. This data can then be applied tothe location of the proposed facility.

SOIL CHARACTERISTICS

Obtain soil data from soil and geologicalmaps, aerial photographs, or site tests per-formed by soil analysts. Soil data dealswith the horizontal and vertical extent ofsoil types, the elevation of the groundwatertable, and the drainage characteristics ofthe soil. The most important drainage char-acteristic of a soil is its permeability. Per-meability limits the rate at which the rain-fall infiltrates the ground, which greatly in-fluences the presence and movement of sub-surface water.

AVAILABLE RESOURCES

Make an initial investigation of the time,materials, equipment, and labor available tobuild a drainage system. Without a suffi-cient quantity of these essentials, the con-struction of an adequate system is impos-sible.

DESIGN PROCEDURES

Designing a drainage system involves dures in the design of any drainage struc-numerous assumptions and estimates. The ture:degree of protection to be provided is direct-ly related to the importance of the estab- • Determining the area (usually in acres)

lished time-use period. The general loca- contributing runoff to the facility

tion of the facility will be determined by itsfunctional requirements.

The drainage system must be planned anddesigned for the predetermined location ofthe facility. There are three basic proce-

Ž Estimating the quantity of runoff.

• Designing the drainage structure tocarry the maximum expected runoff.

Drainage 6-11

Page 109: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013 Vol 1

DETERMINING THE AREACONTRIBUTING RUNOFF

theWhen developing a tentative layout fordrainage system, identify all locationswithin the site requiring drainage struc-tures because of topographical or manufac-tured features. This is best done from atopographic map of the area or a sketch ofthe project site.

Next, determine the acreage of the areasthat contribute runoff to these requireddrainage structures. An analysis of existingchannels is helpful in establishing locationsfor the required structures. Upon comple-tion, this tentative plan should be fieldchecked at the project site.

Establishing Drainage-Structure Locations

The initial step in developing a drainage-structure layout is to establish the locationof the required drainage structures. Place-ment, in general. will be controlled by thetopography. For example, a fill sectionwhich crosses a valley will require one ormore culverts to permit the flow of stormrunoff down the valley. A depression orenclosed area will require ditches or cul-verts at various points to remove accumu-lated rainfall.

Figure 6-6 shows an airfield with requiredculverts (X) and open channels or ditches(V). Note that at Point A the elevation is 65feet, while at Point B the elevation is 55feet. Culverts and ditches must be laid tocarry water from high to low elevations.The alignment of these culverts and ditches

Figure 6-6. Typical airfield drainage features

6-12 Drainage

Page 110: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

should be assible, Sharp

straight and smooth as pos-bends in ditches or near cul-

verts will cause erosion. Not shown on thissketch arc the standard ditches constructedalong the sides of all military roads and air-fields.

Delineating Watersheds

After initially locating drainage structures,define the boundaries of the areas (or water-sheds) contributing runoff to each of them.This process is known as delineation.Delineation is performed in six simple steps(refer to Figure 6-6):

Step 1. Locate all existing or proposeddrainage structures on the topographic mapor sketch (X and V).

Step 2. Identify and mark all terrain highpoints.

Step 3. Draw arrows representing waterflow away from these high points. (Thesearrows must always be perpendicular tothe contour lines because water flowsdownhill.)

Step 4. Continue drawing the arrows untilthey converge upon the culvert or the endof the ditch. Remember that runoff willflow parallel to a road or airfield when it isintercepted by side (or interceptor) ditches.

Step 5. Draw delineation lines. (Theselines will run from high point to high point,indicating where the flow of surface runoffseparates.) Delineation lines arc located sothey cannot be crossed by any flow arrows.Flow arrows only cross delincation lines atculverts or ditches.

NOTE: Delineation lines are drawn be-tween opposing arrows, (See Figure 6-7.)

Figures 6-7 and 6-8 depict the use of flowarrows and delineation lines for special,manufactured structures such as roads,airfields, and superelevated roads. Whenairfields or straight roadways are properlyconstructed, they arc shaped so that thehighest portion of the cross section (thecrown) is at the centerline, as illustrated inFigure 6-8. In the plan view, the delinea-tion will be at the centerline precisely

Figure 6-7. Delineation of roads and air fields

Figure 6-8. Delineation of superelevated roads

Drainage 6-13

Page 111: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

where the accumulated storm water would will always separate at the outside edge ofseparate and flow in opposing directions.Figure 6-8, page 6-13, shows how super-elevated roadways (roadways that arcbanked to ease the flow of traffic through acurve) arc delineated. In a properly con-structed, superelevated road, storm water

the curve.

Several examples are provided to aid invisualizing special terrain features, includ -ing hills, ridges, valleys, and saddles, asshown in Figures 6-9 and 6-10 and Figure6-11, page 6-16.

Figure 6-9. Delineation of a hill

6-14 Drainage

Page 112: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-2/AFPAM 32-8013, Vol 1

Since each cover or soil type will measured according to its respective covereffect on the basin, if there arc type. (See Figure 6-12, page 6- 17.)types of cover in the basin, eachsoil type must be delineated and

Step 6.have anmultiplecover or

Figure 6-10. Delineation of valleys and draws

Drainage 6-15

DraW

Delineation line

Page 113: Army Construction Manual FM5 430 Vol1 Entire

FM 50430-00-1/AFPAM 32-8013, Vol 1

Figure 6-11. Delineation of ridges, spurs, and saddles

6-16 Drainage

Ridge line

-.1 __ , __ __ Saddle

Page 114: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-12. Area delineation by cover or soil type

Determining Drainage-System Size

After delineating the watershed determineits size in acres. Make this measurementcarefully, since the size directly influencesthe calculation of runoff from the watershedat peak flow. Use any accurate method ofmeasurement desired. A planimeter whichmeasures the area of a plane figure as amechanically coupled pointer traverses thefigure’s perimeter, is quite accurate andshould be used, if available. However,several other methods arc suitable for fieldestimation.

Counting-squares method. To make a hastyapproximation of an area, transpose the out-line of the watershed to graph paper (orother suitable grid). Count the number ofwhole squares and estimate the values ofthe partial squares Multiply the total num -ber of counted squares by the number ofcounted square feet represented by a singlesquare. Then convert the measurement insquare feet to acres (1 acre = 43,560square feet), Figure 6-13, page 6-18, showsthis technique.

Drainage 6-17

Page 115: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-13. Area measurement - counting-squares method

6-18 Drainage

i.I

.. ~

,.

" III

IiI 10IIII

..

Scale: Large squares - 1 sq in Small squares - 1/100 sq in

I I TT T

Calculation.:

Approximate number of large squares = 5 = 5 sq in Approximate number of small squares = 564 = 5.64 sq in Approximate area = 10.64 sq in

Example:

If one aquare repre .. nt. 10.000 actual aq ft on the ground. then the delineated are. rapre.ent.:

10.64(10.0001 2 .... = ._ acre. 43.580

I

---

Page 116: Army Construction Manual FM5 430 Vol1 Entire

Geometric-shapes method. This method in-volves estimating the watershed shape interms of rectangles, triangles, or trapezoids.Using the formulas below for determiningthe areas of these geometric shapes, deter-mine the area of each shape and then totalall areas to estimate the area of the water-shed. This technique is shown in Figure6-14, page 6-20.

Rectangle:Area = base x height or A = bh

Triangle:Area = base x height or A = bh

TrapezoidArea = sum of bases x height

or A =

Stripper method. The stripper method is avariation of the geometric-shapes method.This method is shown in Figure 6-15, page6-21. Approximate the area by drawing aseries of lines that are equidistant (stripperwidth) across the delineated area. Thenmeasure the lines and total all of them.L = total of the lengths, This method ismore applicable for field estimations. Use astripper width of 1 inch.

The total of the lengths (L) is then multi-plied by the stripper width. This would rep-resent the total area on the map in squareinches. Since the value of 1 square inchon the map would represent the map scalesquared on land, the acreage can be foundby multiplying L (in inches) x stripper width(in inches) x (map scale in feel per inch

and dividing the product by 43,560acre.

Example:

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Solution:

Step 1.

Step 2.

Step 3.

ESTIMATING THE QUANTITY OF RUNOFF

Drainage systems must be designed to ac-commodate the peak flow generated byrunoff from contributing watersheds duringthe design storm, Many techniques arcavailable for determining the peak flow, butmost arc too complex for general field use.

This manual will demonstrate the most com-on method for estimating runoff—the ra-tional method.

DESIGNING DRAINAGE STRUCTURESFOR MAXIMUM RUNOFF

To accommodate the peak flow of thedesign storm, design structures must pro-vide a sufficient cross-sectional area andlongitudinal slope for passing storm runoff.If pending or flooding of adjacent areasmust be prevented, the design must be forpeak flow. At the same time, watervelocities generated at peak flow must notbe so great as to cause damage to thedrainage structure or excessive erosion andscouring 10 the protected facility.

Determine the capacity of drainage struc-tures by calculating the runoff from allcontributing drainage areas. Specific proce-dures for designing open channels and cul-verts are discussed later in the chapter.

L = 12.5, map scale = 175 ft/in, stripperwidth = 1 inch (in)

Drainage 6-19

Page 117: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-14. Area measurement - geometric-shapes method

6-20 Drainage

T I I I I

Scale: Large squares - 1 sq in ,.,. Small squares - 1/100 sq in

I I I I I I I T T • I T T T I I I

, _I I I I I I T T T T T

111111111111. R 11.IIIUlIIIIIIIII

6' ~"" 1

1 3 "..

11111111lt111 m 11111111111111111_11111111 111.1111111111111111111111111111111111

Calculations: Ar.a '1 = trapezoid = 'h (3.90 + 3.10)1.94 = 6.79 sq in Area 112 = triangle = ~ fO.6)fO.93) = 0.23 Iq in Ar.a '3 = trapezoid = 'h (0.5 + 0.34)1.35 = 0.57 sq in Ar.a '4 = rectangl. = 0.30 • 1.58 = 0.47 sq in Ar.a .5 = trapezoid = 'h (1 .43 + 0.75) 0.86 = 0.93 sq in Ar.a '8 = trap.zoid = 'h !2.37 + 1.65) 0.41 = 0.82 Iq in Ar.a 17 = trapezoid = 'h (1.85 + 0.94) 0.50 = 0.69 sq in Total ar.a = 10.6 IQ in

E.ampl.: If on. squar. r.pr ... nts 10.000 actual sa ft on tha ground. than tn. designated ar.a repr ... nts: 10.6 x 10.000 ---'---~-'- = 2.41 acr.s

43,660

Page 118: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-15. Area measurement - stripper method

Drainage 6-21

3.6 3.1

1.0 + 5.3 + 5.3 + 3.1 + 3.6 + 3.8 + 2.4 = 24.5 In

2: lengths = 24.5 In

Step 1. Step 2. Step 3.

24.5 In x 1 In .. 24.5 In2

24.5 In2 x (285 ft/ln)2 = 1,990,012.5 ft2

1,990,012.5 ft2 = 45.7 acres 43,560 ft2/acre

Map scale: 1 in = 285 ft

Page 119: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

ESTIMATING RUNOFF USING THE RATIONAL METHOD

ESTIMATING PRINCIPLES

The rational method is used to estimate theexpected peak storm runoff at a givendrainage basin outlet. Much of the input tothe formula is based on judgment. There-fore, it is imperative that sound engineeringjudgment be used to determine the inputdata.

ASSUMPTIONS

The rational method is based on the follow-ing underlying assumptions and limitations:

• The area is not greater than 1,000 acresand is regular in shape, with ahomogeneous cover and soil type.

Ž The entire drainage area is contributingrunoff to the outlet point when peakrunoff is obtained.

• The design rainfall intensity is uniformover the entire drainage area (that is,the rainfall is uniform over time andspace).

• There are no active streams drainingthe area. (If an active stream drains thebasin, use the hasty method found inFM 5-34.)

FORMULA

The rational method uses the following for-mula:

where—

Q =C =I =A =

Q = CIA

peak runoff in cfsrunoff coefficientintensity of rainfall in in/hrdrainage area in acres

The following conversion factor is applied tothis formula:

This is so close to unity that no correctionfactor is added; hence, the name rational(because a rational conversion of units] isused.

FORMULA VARIABLES

The rational formula has three variables.The C and I variables are explained here.The A variable is explained later in thischapter.

The C Variable

The runoff coefficient, or C variable, ac-counts for losses from precipitation. The Cvariable is the decimal fraction of theamount of water expected to run off relativeto the amount of precipitation. It can be ex-pressed as the ratio—

Table 6-1 gives conservative values of C.Knowledge of an area’s USCS classification(for example, GMd) or an estimate of thesoil’s perviousness allows selection of a Cvalue. C values appear in the table formanufactured surfaces and for woodedareas as well. An area of SP soil (a per-vious, sandy soil with a slope less than orequal to 2 percent) with turf has a C factorof 0.10; that is, only 10 percent of the rainfalling on this soil will actually run off.

Table 6-1. Runoff coefficients

6-22 Drainage

Page 120: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The remaining 90 percent becomes lost torunoff through infiltration and other fac-tors. At the other extreme, an asphalt pave-ment has a C value of 0.95. Only 5 per-cent of the rain falling on asphalt will belost. The remaining 95 percent is expectedto become runoff.

NOTE: C values given in Table 6-1 areactually maximums of ranges of allowablevalues for the cover or soil categories.Using the maximum value, a conservative“worst-case” design runoff is calculated.To use values less than the maximumsgiven in the table, refer to a reliable civilengineering text dealing with hydrology.The table is arranged with three columnsfor varying slope conditions.

C Versus Slope

As terrain becomes steeper, water flowssooner and more rapidly. This allows lesstime for infiltration to occur and results inthe C value becoming larger for the naturalcover or soil categories. For this reason,whenever the average slope of an area ex-ceeds 2 percent, an adjustment must bemade.

Table 6-1 is arranged with three columnsfor different slope conditions and their cor-responding runoff coefficients, Use thecolumn that corresponds with the averagepercentage of slope.

The C for a turfed soil is different from theC for bare soil. The turf (grass or otherground cover) exerts a drag on water, caus-ing slower flow and providing more time forinfiltration to occur; hence, a lower Cresults. Denuded soil (soil from which theturf or cover has been removed) requires anincreased C because a swifter flow willresult and less time will be available for los-ses to occur. If one cover type has morethan one flow path, average the slopes anduse the appropriate column in Table 6-1.

Example:

Flow path 1A = 2.3 percent and flow path1B = 1.9 percent.

Solution:

C for Nonhomogeneous Areas

One of the assumptions made by the ration-al method is that there is a homogeneouscover and soil type throughout the area.Quite often this is not the case, especiallyin areas where humans have exerted theirinfluence on the topography.

If one type of cover and soil predominatesin 80 percent or more of the area, the areais called simple and the C value for thatpredominant soil and cover type controls.If no one type of cover and soil typepredominates in 80 percent or more of thetotal area, the area is complex and the Cvalue must be weighted; that is, the Cvalue has to be adjusted to account for theproportion of C contributed by each sub-area.

To help understand this, imagine a complexarea with one subarea of average turf andthe other of bare soil. The slope of thebare soil does not affect how fast (or slow)the water runs off the turfed area and, as aresult, how much of the water soaks intothe turfed area. The converse is also true.The slope of the turfed area does not affectthe speed or amount of water that runs offthe bare soil area. Table 6-1 shows Cvalues with and without turf.

Weight the C value by multiplying the cor-rected C values by the area (in acres) thatthe C values affect. Then total theproducts and divide by the total acreage.Expressed mathematically, the formula is—

where—

C value and area for first subareaC value and area for second sub-

area

Drainage 6-23

Page 121: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The I Variable If a 30-minute-duration storm sweeps over

As explained previously in this chapter, rain- the same area in a uniform fashion, the en-

fall intensities can be determined from pin-point source data or isohyetal maps. Theformer method provides more accurateresults if reliable data is available. Thetask of calculating the critical duration forany given drainage area is detailed here.

Time of Concentration

Under the assumptions listed at the begin-ning of this section and with the intensity-duration relationships presented earlier,only one particular storm will give a maxi-mum discharge (Q) for a given area. Thisparticular storm is the one that rains overthe entire area being drained for a period oftime just long enough to fill the outlet withrunoff from all segments of the area at thesame time. This time is called the areaTOC. A storm of shorter duration than thisTOC would not last long enough for therunoff from the more distant segments ofthe area to reach the outlet. The outletwoulrd be filled only with the runoff fromnearby segments. Therefore, runoff wouldnot be maximum

In Figure 6-16, all of the area below the 10-minute line will drain in 10 minutes orless. Runoff from the area between the 10-and 20-minute lines will reach the outlet innot less than 10 minutes but will havedrained in not more than 20 minutes.Similarly, the runoff from the area betweenthe 20- and 30-minute lines will reach theoutlet in not less than 20 minutes nor more[ban 30 minutes. At the end of 30minutes the entire area is draining. There-fore, the TOC at the outlet for this area is30 minutes.

If a storm of 20-minute duration sweepsover the area in a uniform fashion, only afraction of the total area inside the 20-minute boundary simultaneously con-tributes runoff to the outlet at the end ofthe storm. All runoff from the upper thirdof the area reaches the outlet after the rain-fall has ceased and after much of the loweracreage has finished contributing runoff.

tire area contributes runoff to the outlet inthe 30-minute time frame (the TOC men-tioned above).If a storm with a duration longer than theTOC occurs, the drainage designer can easi-ly picture (using the standard intensity-duration curve) that the intensity, I, will beless than the I of the 30-minute storm. Ex-amination of the rational-method equation,Q = CIA, reveals that since C and A wouldnot change as I decreases, Q must decreaseas well. The critical-storm duration whichyields the design Q must then be equal tothe contributing area’s TOC.

Determining TOC

Determine the area TOC by determining rep-resentative flow paths. A flow path is thepath that a typical drop of water will followfrom the time it hits the ground until itreaches the area outlet, The flow path iscalled representative, because not alldrainage areas are as regular in shape asthe area in Figure 6-16. The path selectedmust be representative of the time at whichmost of the area will be contributing waterto the outlet point. Establishing repre-sentative flow paths is based largely on ex-perience and judgment (trial and error).

Figure 6-16. TOC, regular area

6-24 Drainage

Page 122: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Unlike the area depicted in Figure 6-16, thearea in Figure 6-17 is irregular as mostnatural areas will be, In irregular areas, itis especially critical that the flow paths cho-sen truly represent the time required formost of the area to drain. All the area be-low the 10-minute line will drain in 10 min-utes or less. The area between the 10- and20-minute lines will drain in not less than10 minutes nor more than 20 minutes andso forth up to the 40-minute line. Flowlines a, b, and c have been determined; 90percent of the total area (90 acres) lies be-low the 30-minute line and will drain in 30minutes or less. Water from the remaining10 acres will reach the outlet in not lessthan 30 minutes nor more than 40 min-utes. Flow lines a and c should be chosenas the representative flow paths and usedto determine the TOC because they are in-dicative of the time it will take for most ofthe water from the area to reach the outlet,Line b is not representative.

For simplicity, in this example let C arbitrar-ily equal 1.0 and assume that the 1-hour, 2-year intensity is 2,0 inches per hour. If a40-minute-duration storm occurs, in 40 min-utes the entire area will be wet and contrib-uting water to the outlet point, The stand-ard intensity-duration curve in Figure 6-4,

Figure 6-17. TOC, irregular area

page 6-9, shows that the I for a 40-minutestorm is 2.7 inches per hour; therefore, theestimated runoff is—

Q = CIAQ = (1.0)(2.7 in/hr)(100 acres) = 270 cfs

A storm of 30-minute duration will have anintensity of 3.2 inches per hour. At theend of 30 minutes, 90 percent of the area(90 acres) will be contributing water to theoutlet and the volume will be—

Q = CIAQ = (1.0)(3.2 in/hr)(90 acres) = 288 cfs

which is larger than the 270 cfs estimatedfor the entire area.

Flow paths must be chosen that representthe time required for most of the area todrain. As shown above, a shorter storm ofhigher intensity may cause a larger flow. Af-ter all the chosen paths have been timed,the times should correspond to each otherwithin a few minutes. If times are not rela-tively close, make a careful check to deter-mine why, and assess the area to determinewhich of the times will produce the criticalflow. Apply rainfall adjusted to this criticalduration over the entire watershed. The de-sign runoff from the watershed in Figure 6-17 would be—

Q = CIAQ = (1.0)( 3.2 in/hr)(100 acres) = 320 cfs

After representative flow paths have been es-tablished, estimate the time it will take forwater to reach the outlet if it travels alongthe established path. To do this, determine(through observation) the nature of the sur-face cover and the slope of the flow path.Slope affects the velocity of the water inthat the steeper the slope, the faster thewater runs. Water will also travel fasteracross a paved area than across a grassyarea of the same slope because grass slowsthe flow. Flow is slower over bare soil thanover pavement but faster than grass. Flowin a ditch is more rapid than overland flowover turfed, bare, or compacted gravelsurfaces.

Drainage 6-25

Page 123: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Estimating Flow Time for Single Covers Notice that there is a series of curves, each

After establishing the location, the cover, with linear and curvilinear portions. The

and the slope of a flow path, Figure 6-18 slope of the curve indicates the velocity at a

can be used to estimate the travel time given point along the flow path. In the cur-

along the flow path. It is important to un- vilinear portion, the slope is initially zero

derstand what the illustration is depicting and gradually steepens until it becomes

as well as how to use it properly. linear. This represents the fact that water

Figure 6-18. Flow travel time

6-26 Drainage

UIOO

1400

1200

1000 --;: .g "0 c: en

;:;: lOO CD > 0

eoo

200

o ~ o

~ ~ I~ I~ I~

I~.~ ... . ~ -f9 •

M ~ 1:11 I~ I~ I~~' I~ I . §

l:a 1=:"1 .. ~ 1:1

tIf+ mm

E

rll I mr rll,

, r rn

LA

::oIo"'l

10 20 eo Time of concentration - min

NOTE: It Is valid to Interpolate between percent slope curves.

Average

turf

Sparse

turf

Bare

soil

Compacted gravel

Paved areas

Page 124: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

initially moves very slowly and begins topick up speed only as its accumulateddepth increases. It is initially slow flowingin a laminar or sheet-flow manner andgradually becomes turbulent (and faster) asit progresses downhill. At some point, theturbulent-flowing water reaches somesteacly-state velocity. It is apparent fromFigure 6-18 that the slope and “slickness”of the flow path dictate how quickly thetransition occurs from slow-moving laminarflow to rapid, fully developed turbulent flow

To estimate the travel time in sheet-flowconditions, use Figure 6-18. Enter theright-hand vertical edge at the appropriatecover type of the flow path. Proceedhorizontally to the left until reaching thecurve labeled with the slope of the path.Follow the curve up or down until youreach the intersection of the horizontal lineequaling the flow-path length, which isdetermined on the left-hand vertical edge.Read the travel time, which is found bydrawing a line vertically from the intersec-tion to the lowermost axis. Some examplesof the use of this graph are as follows:

TravelPath Cover Length Slope Time

(ft) (%) (rein)

1 Sparse 800 3,0 19turf

2 Paved 500 1.5 8area

3 Average 600 2.5 26turf

Note that it was necessary to interpolate tofind the travel time for path 3. It is validto interpolate between labeled lines, butnever extrapolate above or below the limit-ing-curve values. Use the limiting curve inthat situation To estimate the travel timein ditch-flow conditions, usc Table 6-2.Using the slope of the flow path, enter thechart, then read the right-hand columnunder velocity. To calculate the velocity,divide the length of the path by the velocityobtained from the chart.

Example:

Path 1B

Cover - DitchLength - 1,015 ftSlope - 0.9%Chart velocity - 135 feet per minute (fpm)

Table 6-2. Estimating flow velocity

Drainage 6-27

Page 125: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Solution: Arid partial travel times to get the totaltravel time:

= 7.5 minutes (min)

Estimating Flow Time for Multiple Covers

In many cases, a flow path traverses morethan one cover type. Estimating travel timeaccurately then becomes more complicatedbecause it is not appropriate simply to addtimes obtained from Figure 6-18, page 6-26.Laminar flow occurs only once along a flowpath, no matter how many cover types aretraversed. For subsequent covers, it be-comes necessary to estimate flow velocityusing Table 6-2, page 6-27.

To estimate travel time in a ditch, useTable 6-2. Enter the table using the slopeof the flow path. Then read right to thevelocity column and find the velocity in feetper minute. By knowing the flow-pathlength and the table velocity, the travel canbe calculated.

Example:

Assume that paths 1 and 2 from the preced-ing example were actually the upper andlower lengths of one combined flow path.To estimate their combined travel time, firstestimate each separately in the order thewater would flow through them.

Solution:

Estimate the travel time of path 1. Sincepath 1 is uphill from path 2, nothing haschanged from before. The travel timeremains 19 minutes. Estimate the traveltime of path 2. Remember that the flowentering at the upstream end of path 2 is already moving. To estimate travel time,divide the length of the path by the es-timated velocity listed in Table 6-2. In thiscase, for a 500-foot, paved path at 1.5 per-cent—

Travel time =

(Note that path 2 had an 8-minute traveltime when considered alone.)

Travel time = 19 min + 3.0 min = 22 min

It may be helpful, at times, to estimate thetravel time through a culvert. A reasonableassumption of culvert velocity is 5 feet persecond (fps) (300 fpm), although moreprecise determinations can be made with in-formation presented later in this chapter.

Selecting Design TOC

The usual procedure is to establish severaltrial flow paths that are thought to be repre-sentative of the area and determine a traveltime for each path. Compare the time forwater to travel along each of the flow pathschosen. If the times arc within a fewminutes of each other, select the longesttime as the area TOC. If the times arc notwithin a few minutes of each other, make acomplete analysis of the area. New flowpaths may be needed to determine which ofthe times is representative of the bulk ofthe area draining. The largest repre-sentative time is chosen as the design TOC.

The A Variable

The drainage area, A, (the area contributingstorm-water runoff to the culvert or ditchbeing designed) must be calculated inacres, This procedure was presented earlierin this chapter.

APPLYING THE RATIONAL METHOD

Application of the rational method of es-timating drainage varies according to thetype of drainage area. One type is a single,independent area which does not receiveany drainage from an upstream area.Another type is a dependent or successivearea that receives runoff from another area.

Single Areas

The rational method of estimating singleareas is reasonably simple and straight-forward, if it is done methodically. Thesteps are summarized in the proper order.lf this summary is followed step-by-step,

6-28 Drainage

Page 126: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

the procedure will be correct and the esti-mate obtained will be as valid as the judg-ments that are made.

Step 1. Delineate the area to determine thearea contributing runoff to your project loca-tion. Refer to page 6-13, Delineating Water-sheds.

Step 2. Delineate subareas by soil or covertype. Refer to page 6-15.

Step 3. Determine acreage for each basinand subarea. Refer to page 6-17.

Step 4. Classify the drainage basin as sim-ple or complex. A simple watershed hasone cover or soil type over 80 percent of itstotal area. A complex watershed has no sin-gle cover or soil type covering at least 80percent of its total area.

Step 5. Determine representative flowpaths. Refer to the information on pages6-24 and 6-25.

Step 6. Divide flow paths into two sections:laminar and ditch flow. As a rule ofthumb, use 500 feet plus or minus 200 feetas a point where laminar flow will changeto ditch or steady-state flow. Generally,overland flow concentrates into natural rivu-lets or channels after roughly 500 feet oftravel. This distance may vary up to sev-eral hundred feet either way, dependingupon such factors as soil type, vegetation,and slope, It is always best to visually in-vestigate on-site to look for evidence of chan-neling, and take measurements accordingly.However, since in this problem it is not pos-sible to visually investigate the drainagearea, clues to determine when overland flow(sheet flow) ends and ditch flow beginsmust come from topographic informationalone. Some of these clues may be the be-ginning of uphill swales or flow paths thatconverge in a swale. This convergence maytake place in a valley where multiple pathsmeet.

Step 7. Determine the slope of eachsection of flow path. See page 6-25.

Step 8. Determine the average slope of thebasin or each subarea based on flow paths.Define the slope as being either 2%, > 2%and < 7%, or 7%.

Step 9. Find the C value of the basin oreach subarea based on soil or cover typeand slope from Table 6-1, page 6-22. Se-lect C from the appropriate column in Table6-2, page 6-27, making sure that you pickthe right C-value column. Notice that thecolumns are arranged with respect to slopeand cover type.

Calculate if the area is complex.

Step 10. Determine the travel time foreach flow path and select the longest flowpath as the basin TOC. Refer to sheet flowon page 6-27 and ditch flow in Table 6-2.

Step 11.storm on6-3, page

Step 12.

Find I for a 2-year, 60-minutethe world isohyetal map (Figure6-7).

Adjust I based on the TOC (step10), using Figure 6-4, page 6-9.

Step 13. Calculate Q using C from step 12,and A from step 3 as follows: Q=CIA.

Example:

Estimate the amount of runoff expected toarrive at the culvert in Figure 6-19, page6-30.

The location is Giessen, Germany, and thedesign life is two years.

NOTE: A number of steps, quantities,and calculations will be “given” to illus-trate the process.

Solution:

Step 1. Delineate the area. (Given for thisexample. )

Step 2. Delineate the subareas by soil orcover type. (Given for this example.)

Drainage 6-29

Page 127: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-19. Delineating runoff area

Step 4. Classify the drainage basin as

Step 3. Determine the acreage for each simple or complex. Divide the largest soil

basin or subarea. The following acreage is or cover group (the GMd soil] with turf sub-

given for this example: area equaling 47.9 acres by the total area,48.8 acres.

Average turf GMd 47.9 acresCompacted gravel 0.9 acreTotal acreage (A) 48.8 acres

6-30 Drainage

Page 128: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Since the percentage is greater than 80,this area will be treated as a simple areaconsisting of 48.8 acres of turfed GMd soil.

Step 5. Determine the representative flowpaths. It is necessary to determine theaverage slope of the entire simple areashown in Figure 6-19. In order to do this,use representative flow paths, If the north -south running swale is imagined as thedividing line, approximately one-third of thewatershed area lies to the west (left) andtwo-thirds to the east (right). To determine

an average slope, the number of slope meas-urements taken on the western slopeshould be balanced by twice that numbertaken from the east. Figure 6-20 reflectsthis guideline, showing three slope measure-ments, two on the east and one on the west.

NOTE: The selection of representativeflow paths is a judgment call based onthe best evaluation of the topographic fea-tures.

Figure 6-20. Determining average slope

Drainage 6-31

Page 129: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Step 6. Divide flow paths into two sections:sheet and ditch flow. Generally, overlandflow concentrates into natural ditches after500 feet. Path 1 changes to ditch flow inthe valley where it slopes down. See sec-tion A of Figure 6-20, page 6-31. The sameis true for path 2. By looking at the con-tour lines near path 3, we can see they arerelatively flat. Flow occurs across a widearea, and no clear point can be seen wherethe flow changes. A good estimate wouldbe at 575 feet.

Step 7. Determine the slope of each flowpath. The representative flow pathsselected in an earlier step, if properlyselected, can provide very good slope infor-mation with a minimum of effort. Otherslope lines may be selected for practice andto gain confidence in using this procedure.Remember to maintain the 2-to-1 balancein finding slopes in this basin and to deleteredundant information. The slope must bemeasured over a path that water would ac-tually follow as it flows downhill. Normally,all work would be performed on one con-solidated map. For instance, to determinethe slope for path 1A—

This procedure is repeated for every flowpath illustrated in Figure 6-20.

A tabular solution is recommended to deter-mine TOC.

Length Slope TimePath Cover (ft) (%) (min)

1A Average 575 5.9 14.5turf

1B Ditch 1,015 0 9 7.5section (135 fpm)

22.02A Average 640 5.2 16.5

turf2B Ditch 1,285 0.8 9.9

section (130 fpm)26.4

3A Average 575 5.0 16,0turf

3B Ditch 650 2.3 3.02section (215 fpm)

19.02

The slope of the original path 3 is un-changed, remaining at 3.6 percent. Paths2A and 2B are now one single path, 2, withan average slope of 2.3 percent. (Theaverage of 5.2 percent and 0.8 percent isnot 2.3 percent.) Redetermine the overallslope (as done earlier). The earlier path 1Bhas been deleted, leaving only the originalpath 1A (with S = 5.9 percent) as the newpath 1. The reason for deleting 1B is thatit provides the same information alreadyprovided by the new path 2. Path 2B couldhave been deleted instead of path 1B withno change to the final result.

Step 8. Determine the average slope of thebasin or subarea based on flow paths.With the three flow paths now determined,the average slope of the simple area is—

Step 9. Find the C value of the basin orsubarea based on soil or cover type andslope from Table 6-1, page 6-22. Since weknow that the average slope is 3.93 per-cent, we can use Table 6-1. Using thecolumn marked slope >2% and <7% withturf, we have a C value of 0.35.

Step 10. Determine the travel time of eachflow path and select the longest flow-pathtravel time as the basin TOC. Times forpaths 1B and 2B were obtained by dividingtheir flow lengths by approximate velocitiesobtained from Table 6-2, page 6-27. Thetravel times for each of the complete flowpaths (22.0, 26.4, and 19,02 minutes,respectively) are obtained from Figure 6-18,page 6-26. The variation between the smal-lest and largest time, although not small, isnot excessively large, either. Perhaps path1 is not representative and some ditch flowoccurs along path 3 that could not be deter-mined from the topographic informationavailable. Both of these possibilities arelikely to be true. However, without an ac-tual field investigation to justify revisingeither path 1 or 3, accept the travel timesalready determined and select the largest asthe basin TOC. Thus, TOC = 26.4 minutes.

6-32 Drainage

Page 130: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Step 11. Determine the I value for a 2-year, 60-minute storm. To determine factorI, a source of rainfall data is necessary.The choice is between using pinpoint data(the most accurate means of determining 1)or referring to an isohyetal map. Since pin-point data is not available, use an isohyetalmap. Refer to the isohyetal map in Figure6-3, page 6-7. Knowing that the airfield islocated near the demilitarized zone (DMZ) inKorea, as shown in Figure 6-3, rainfall in-tensity of the 1-hour, 2-year storm is deter-mined to be 2.5 inch per hour or—

Step 12. Adjust the I value. To determineI, must be adjusted so that itsduration is equal to the basin TOC, 26.4minutes. Use the set of standard intensity-duration curves in Figure 6-4, page 6-9, tomake the adjustment. Using curve 5 (for2.5 inches per hour) and sliding along untilthe 26.4-minute imaginary vertical line is intersected, the intensity (adjusted to 26.4minutes) is found to be 4.2 inches perhour; thus--

Step 13. Calculate Q using C from step 9, from step 12, and A from step 3.

All the variables have been determined tosolve the equation Q = CIA, as follows:

C = 0.35I = 4.2 in/hrA = 48.8 acresQ = 0.35 x 4.2 in/hr x 48.8 acresQ = 71.74 cfs

The determinationto the example.

If area 5 had been

or 71.7 cfs

of Q is the final solution

a complex area, steps 1,2, 3, and 5 would be unchanged. The onlydifference would occur in step 4, whichwould be changed as follows:

Step 4 (for a complex area). An foreach soil or cover area must be determined(except for manufactured covers). A C

value for each soil or cover must be deter-mined based on the average slope for eachcover area. Once all C corrections aremade, then an area-weighted C or canbe determined. would be used in solv-ing Q = CIA.

Successive Areas

Up to this point, the drainage areas dis-cussed have been single, independentareas, whether simple or complex, These in-dependent areas do not receive runoff froman upstream area. Some drainage systems,however, consist of a series of drainageareas with upstream areas dischargingrunoff into lower areas. The areas receivingthis runoff are called dependent areas. Therunoff accumulates and increases in its pas-sage through the system.

Sometimes, two or more areas dischargerunoff into the same dependent downstreamarea. Such contributing areas arc calledparallel areas.

Unfortunately, the increase in runoff is notthe simple summation of the peak runoff ofeach individual area. The individual peakflows arc acted upon by various factors, in-cluding storage and peak-tlow reductionwhile in the drainage network, Also, thepeak flow from upstream areas and thepeak flow from downstream, dependentareas will probably not arrive at the loweroutlet simultaneously. Hence, the totalpeak flow must be less than the total of theindividual peak flows.

Calculating TOC

Because of the accumulation of peak flowin successive areas, calculation of TOC forthose areas must be different from themethod used for single, independent areas.To estimate the amount of the accumulatedrunoff with some precision, a procedure hasbeen developed to recalculate TOC for eachof the successive drainage areas as watertravels downstream. Naturally, as TOC in-creases, rainfall intensity, I, decreases.

The term TOC must be modified to reflectcalculation differences. Consider two areas,an upstream area W and a downstream

Drainage 6-33

Page 131: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

area X, as shown in Figure 6-21. Themaximum travel time from the mosthydraulically remote represen [alive pointsin this series of two areas to the outlet ofarea X is defined as TOC. The maximumrepresentative flow times for runoff originat-ing in both areas (X and W) to arrive al[heir respective outlets (X and W) arcdefined as inlet time X and inlet time W,respectively.

The TOC at teh outlet upstream in area Wis given as which equals inlet timeW for this independent area. The’ ditch time(DT) or transit time through area X, fromoutlet W to outlet X, is The total ofthese two elements isinlet

Figure 6-21. Schematic example forsuccessive areas

To a designer engaged in sizing the culvertwhich serves as outlet W, the TOC wouldsimply be However,when sizing culverts that occur furtherdown in successive areas (for instance, theculvert at outlet X), the designer requiresthe time it takes water to arrive from themost hydraulically remote location, whichmight be in either area X or area W. Todetermine this maximum representativetime the designer must compare thetravel times for runoff origination in bothareas.

The travel time for waler originating in areaW and arriving at outlet X is equal 10 theinlet lime at area W (which is the same as since area W is dependent) plus thetransit time as the water flows in a ditchthrough area X. This composite time,called inlet must be compared tothe time for water that originates in area X,or inlet , the maximum repre-sentative time for water to arrive at outletX, is the larger time value identified in thecomparison.

Estimating Successive Area Runoff

The modified definition of TOC is applied inestimating runoff for successive areas. Thiscalculation requires collection of certain es-sential data and application of the prin-ciples used for single areas, appropriatelymodified, to determine the desired Q.

Preparatory Work.

Step 1. Delineate every subarea in theseries of areas.

Step 2. Determine the intensity of the 2-year, 60-minute rainfall.

Step 3. Determine A, C, and inlet time.For each subarea, deter,ome the acreage(A); variable C, corrected for slope andweighted (as necessary); and the inlet time.

Step 4. Determine the DT (or transit time).

For each dependent subarea, the DT isdetermined from the upper outlet 10 the

6-34 Drainage

Page 132: Army Construction Manual FM5 430 Vol1 Entire

lower outletfpm, unless

Determining

using culvert flow (assume 300you have more precise data).

Specific Q, Working systemati-cally, start at the uppermost subarea andproceed downstream. Refer to Figure 6-21and note that subarea W is upstream fromsubarea X.

Step 1. Determine the subarea TOC usingthese simple rules:

The rule for an independent subarea is—

The rule for a dependent area is—

Compare inlet with inlet timeSelect the larger value of based onthe comparison.

Step 2. Adjust

Step 3. Calculate Q for subarea W.

Step 4. Proceed downstream to subarea Xand repeat steps 1, 2, and 3.

Step 5. Total the accumulated runoff, Toget the total runoff at the Outlet of subareaX, use the following equation:

Step 6. Continue working downstream.Proceed until the runoff at the lowest outletin the series is calculated. Use thedrainage basin’s corresponding rainfall in -tensity for the I value; use the total area forall basins and the subareas for the area. Avalue, in the rational-method formula.

NOTE: Remember that when using the ra-tional method, the area limit is 1,000acres. Always check the accumulatedacreage to ensure that it does not exceed1,000 acres.

FM 5-430-00-1/AFPAM

Example:

32-8013, Vol 1

Using the rational method and Figure 6-22,page 6-36, determine the runoff, in cfs, ex-pected at culverts 3 and 4 at the Span IIArmy Airfield at Giessen, Germany. Thesoil type is GMd.

Solution:

Step 1. Delineate the area; it is found tohave the following:

Subarea A.

Compacted gravel 6.2 acres SimpleAverage turf 0.2 acre Area

6.4 acresSubarea B.

Compacted gravel 0.9 acre SimpleAverage turf 12.5 acres Area

13.4 acres

Step 2. Delineate subareas by soil or covertype. (See step l.)

Step 3. Determine acreage for each basinor subarea. (This informationstep 1,)

Step 4. Classify the basin asplex.

Subarea A.

is given in

simple or com-

Compacted gravel 6.2 acresAverage turf 0.2 acre Simple

Total 6.4 acres

6.2 acres/6.4 acres = 0.97 or 97%

Subarea B.

Compacted gravel 0.9 acreAverage turf 12.5 acres Simple

Total 13.4 acres

12.5 acres/13.4 acres = 0.93 or 93%

Step 5. Determine representative flowpaths. See Table 6-3, page 6-37 (given in-formation).

Step 6. Divide flow paths into two sections:sheet flow and channel flow. See Table 6-3(given information).

Drainage 6-35

Page 133: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-22. Successive areas - example

Step 7. Determine the slope of each sec- Both of these paths will have an averagetion of the flow path. slope of less than 2 percent. Subarea 2

has three major paths. Path 2 has anStep 8. Determine the average slope of the average slope of 2.3 percent, path 3 has anbasin or each subarea, There are two average slope of 2.4 percent, and path 4paths in subarea 1, paths 1A and 1B. has an average slope of 2.6 percent. (See

6-36 Drainage

Page 134: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-3. Determining travel time

Figure 6-22. ) Using this information, wecan now get an average slope for paths 2,3, and 4.

Average Slope =

Average slope for subarea 1 = < 2%Average slope for subarea 2 = 2.4%

Step 9. Find the C value for each subarea,Subarea A has compacted gravel with anaverage slope less than 2 percent. UsingTable 6-1, page 6-22, we find that the Cvalue is 0.70. Likewise, the C value for sub-area B, GMd with average turf with a slopeof 2.4 percent, is 0.35.

Step 10. Deter mine the travel time of eachflow path and select the longest flow-pathtravel time as the TOC. Obtain sheet-flowtimes from Figure 6-18, page 6-26, andditch-flow travel time from Table 6-2, page6-27. Determine the travel times and ditchtime from Table 6-3.

Ditch =

=

Ditch velocity =3.8 min188 fpm at 1.8%and 194 fpm at 1.9%

Inlet time A = 16.3 minInlet time B = 25.3 min

Step 11. Determine I and (I value forGiessen, Germany is 1.7 in /hr from localrainfall records.)

Subarea A.

Subarea B.

Compare inlet = 25.3 min with + DT = 16.3 + 3.8 = 20.1 min

Select the larger value of = 25.3 minand = 1.8 in/hr

Step 12. Adjust I based on TOC using Fig-ure 6-4, page 6-9. (This step was includedin step 11.)

Step 13. Determine runoff.

To calculate runoff in subarea A, use—

= 0.70( 2.6 in/hr)(6.4 acres)= 11.6 cfs

To calculate runoff in subarea B, use—

= 0.35( 1.8 in/hr)(13.4 acres)= 8.4 cfs= 11.6 cfs= 11.6 + 8.4 = 20 cfs

NOTE: Although path 4 was used to ob-tain an accurate slope average, it is notused for travel time. The situation, asdrawn on the map, clearly shows thatpath 4 could not be chosen for the TOC.

Drainage 6-37

Page 135: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SECTION II. OPEN-CHANNEL DESIGN

An open channel is a conduit with a free- The size, the shape, the method of construc-water surface used to convey water. The tion, and the location of a ditch are deter-most common is a ditch, which is an open mined largely by its purpose. These fac-channel cut into the soil. If so desired, the tors, once determined, will influence theditch can be lined along the bottom from design capacity and maintenance require-bank to bank. ments.

DESIGN FACTORS

LOCATION

There are three main types of ditches usedin road and airfield construction.

An interceptor ditch is generally located ona hillside above a roadway or other featurerequiring protection. Its function is to inter-cept runoff and direct the flow to a moredesirable location. It is usually locatedabove sidehill cuts to prevent erosion of thecut.

A side ditch is located along the side of aroad. It collects runoff from the road andadjacent areas and transports it to a cul-vert or diversion ditch.

When the Topography allows, a diversionditch is built to transport water away fromroadways or airfields. It can be used inconjunction with interceptor and sideditches to transport water between culvertsor to divert an existing stream channelaround a project.

CROSS SECTION

The location and peak quantity of runoff ex-pected will determine the ditch cross-sec-tional area required. The most commonshapes of cross sections—triangular (sym-metrical and nonsymmetrical), trapezoidal,and segmental-are shown in Figure 6-23.

In the TO, the shape of a ditch is also dic-tated, to a great extent, by the choice of en-gineer equipment available for its construc-tion. Two items of equipment are uniquelysuited for speedy ditch excavation: the

motor grader and the wheeled tractor-scraper. Other items of equipment that canbe used to excavate a ditch section includethe backhoe; bulldozer; front-end loader;trenching machine; and crane equippedwith a dragline, clamshell, or shovel front.

Figure 6-23. Ditch cross sections

6-38 Drainage

Page 136: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

However, production rates for these itemsare relatively low compared to the grader orscraper; hence, the grader or scraper ismore likely to be used.

Triangular or V ditches are commonly in-stalled to handle flows up to 60 cubic feetper second. The road grader is welldesigned to quickly excavate the necessarycross section to handle this flow, providedthat the ditch is built in soil rather thanrock. Grader efficiency drops significantlywhen cross sections of larger dimensionsare required.

For flows larger than 60 cubic feet persecond, the trapezoidal ditch is commonlyspecified. The flat bottom and midsectionof this ditch can be excavated rapidly by awheeled scraper, and the side slopes can bedressed back by subsequent passes of aroad grader.

Smaller bottom widths can be providedusing any of the previously mentioneditems of construction equipment, includingthe road grader with its blade turned to ahigh angle. Production rates, however, willbe much lower than those of the wheeledscraper.

Note that the 60 cubic feet per secondguideline is flexible. If scrapers are notavailable to excavate a ditch carrying 100cubic feet per second but a grader is, com-mon sense dictates that the grader be usedto construct an oversized V ditch ratherthan using low-production-rate equipmentto construct a trapezoidal ditch,

The segmental-ditch shape results when ex-plosives arc used to create the ditch. Thistechnique is often used when the terrain istoo soft to support excavating math inery.Ditches cut by hand will often bear thisshape as well.

SIDE-SLOPE RATIOS

Ditches have two sides and two associatedside-slope ratios. Side slope is the slope ofthe banks of the channels, normally ex-pressed as a ratio of feet horizontal to feetvertical. For example, 3:1 is a side slope of3 feel horizontal to 1 foot vertical. Whenthe sidewalls on opposite sides are inclined

equally, the ditch is called symmetrical.Nonsymmetrical ditches have side slopesthat differ.

The designer selects appropriate side-sloperatios. The selection is critical to ensurethat the ditch serves its purpose. Ditchsidewalls that are too steep invite excessiveerosion and are likely to cause the ditch toclog with sediment. Even more serious isthe risk of a severe accident, if a vehicleshould run into the ditch and becomeentrapped or overturn because the sideslope is too severe. Only one side slope isrequired for symmetrical ditches. Forclarity, the terms front slope or ditch slopeand back slope are used to differentiate be-tween the dissimilar slopes. Figure 6-24,page 6-40, illustrates this terminology.

The sidewall of a roadside ditch located ad-jacent to the shoulder is called the frontslope of the ditch. The far slope, called theback slope, is simply an extension of thecut face in an excavation. The followingrules of thumb are applicable only in shal-low ditches in relatively flat terrain:

Ž Roadside ditches may be cut nonsym-metrically at 3:1/1:1 (front slope/backslope).

NOTE: For calculation purposes, thehorizontal component of the roadsideditch will be referred to as X. Likewise,the horizontal component on the backslope will be referred to as Y. (See Figure6-23.)

• Diversion ditches may be cut symmetri-cally at 1:1.

Ž Ditches intended to be subject to crosstraffic may be cut symmetrically at 3:1or more gently.

In most cases, interceptor and diversionditches are installed far enough from thetraveled way not to present a hazard topassing vehicles on the roadway or aircrafton the runway. Since there is very littledanger from either side, symmetrical side-slope ratios are specified for these types ofditches.

Drainage 6-39

Page 137: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-24. Definition sketch

Tables 6-4 and 6-5 are also useful in select-ing front slopes for fill sections.

TYPES OF FLOW

Several types of flow are associated withopen channels. Some of these types occursimultaneously in the same channel. Anunderstanding of these types of flowand their interrelationship is essential tothe effective design of drainage systems.

An open-channel flow has a free surface andno hydraulic pressure. Some examples ofopen-channel flow include ditches, canals,streams, and culverts not flowing full. Em-pirical formulas with experimentally derivedcoefficients are used in designing an openchannel. These hydraulic formulas reflectcertain hydraulic theories and assumptionsgoverning design analysis of free-flow chan-nels.

A steady flow is assumed in an open chan-nel with a uniform depth during the designperiod. Changes in flow are generally slow,and any errors that may be introduced bythis assumption are not significant.

A continuous flow is assumed according tothe principle of the conservation of mass.

A uniform flow is assumed when the depthof water throughout a channel is constantin dimension and slope. This means thatthe slope of the water surface is the sameas the slope of the channel bottom. This as-sumption is essentially correct for channelsof moderate slope and length. Flows inditches, canals, and rivers are uniform, butflows over spillways or waterfalls are notuniform.

The strength of viscosity forces and hencethe thickness of moving fluid, determinewhether channel flow is turbulent orlaminar.

Turbulent flow is assumed for purposes ofopen-channel design. This type of flow oc-curs when viscosity forces are relativelyweak and the individual water particlesmove in random patterns within the ag-gregate forward-flow pattern.

Laminar flow occurs when viscosity forcespredominate and the particles of the fluidmove in smooth, parallel paths. An exampleof this type of flow is honey poured from acontainer; honey has high-viscosity strengthcompared to water. The only type oflaminar flow considered in this manual issheet flow, which occurs where depth is ex-tremely shallow. It is assumed that the flow

6-40 Drainage

Page 138: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-4. Recommended requirements for slope ratios in cuts and fills - homogeneous soils

Table 6-5. Recommended requirements for slope ratios in cuts - rock with beddingor other planes of weakness

Drainage 6-41

Page 139: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

in natural and designed channels will besteady, continuous, uniform, and turbulent.

DESIGN EQUATIONS FOR OPENCHANNELS

This section deals with open-channel designequations. Because of the variables and as-sumptions to be made, trial techniques arerequired to determine the shape and depthof a particular channel before a final solu-tion is reached.

Continuity Equation

The equation of continuity is expressed asfollows:

where—

Q = rate of flow in cfsA = cross-sectional area in sq ftV = velocity in fps

Manning’s Velocity of Flow Equation

Many empirical equations have beenproposed for determining turbulent flow.The most widely used is the equationpresented by Manning in 1889. It states—

or, after transposing,

where—

V = velocity of flow in fpsR = hydraulic radiusor

cross-section area of waterR = wetted perimeter

S = slope or grade of the channel in feetper foot (ft/ft)

n = roughness coefficient or friction factor,which depends upon the material compris-ing the

NOTE:

channel lining

When using metric units—

Manning’s equation can easily be solvedmathematically using the equation. How-ever, to assist in the design of open chan-nels, the equation has been prepared as anomograph. (See Figure 6-25.)

Roughness Coefficient (n)

The roughness or resistance coefficient is ameasure of the resistance to flow caused bysurface-contact irregularities. It varies withsoil type, channel condition, and type ofditch lining used. Use Table 6-6 to es-timate the roughness coefficient, n, used inthe solution of the equation. The coeffi-cient can be changed only if the ditchlining is changed or modified. The effect ofthe roughness coefficient on velocity can bealtered by changing the side slopes of theditch, thereby changing the water con tactarea. Changing the roughness coefficient inthis way changes the ditch capacity.

Longitudinal Slope or Grade (S)

Under normal conditions, the ditch slope(the longitudinal fall of the channel in feetper foot or in percentage) will be deter-mined by the slope of the terrain. Forshort ditch lengths only, a variation fromthe natural slope of the terrain can beachieved by modifying the cutting depth ofthe ditch. By varying the cutting depthwithin the ditch length, the slope can be in-creased or decreased independently of theterrain slope.

In channel design, slope percentage and theresulting change in velocity are importantconsiderations. Slopes over 2 percent mayhave too high a velocity, resulting inerosion. Slopes under 0.5 percent willgenerally have too low a velocity, resultingin sedimentation deposits. Deposition (thedepositing of sediment on the bottom of theditch) normally occurs at velocities below 3feet per second.

Velocity of Flow (V)

Many ditches with differing side slopes andcross-sectional areas of flow will carry thesame rate of runoff on a similar longitudinalslope. In each case, however, the velocity offlow will be different. Since excessivevelocity in a ditch will cause erosion and

6-42 Drainage

Page 140: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-25. Nomograph for Manning’s equation

Drainage 6-43

03 0.2 50

E f 1.486 2/3 'h qua Ion: V= -n- R S 40 0.2

0.3

30

001 0.10 0.4

0.09 0.08 Q)

20 0.5 :§ 0.07

Cl 006 c

0.6 ·2 "-

0.05 "- ::l

0.7 I-

0.04 "-0.8

'" 09y 0.02

0.03 0.9

"" Y 1.0 10 ....

~ "9 q(t 0.02

"" /' 8 0.03

a: ./" >

"" /'/ 7

Cl) j ./" 6 0.04

B 0.01 Cl) ,/" C ::l 20 5 0.009 'C ~ E 0.05 "- 0.008 f! ~~~9 (jJ'?J Q) !

0.007 . ~ %0 . 4 :Sl a; :; c:,~ i 0.06 Q) 0.006 as / 8 "-- "t)

.5 0.005 >. 3/ 0.07 :::t ",

! 3 .2 0.08 Cl)

4 0.09

0.10 5 2

0.002 6

Example jsee dashed line):

Given V = 2.9 7 S = 0.003 0.20

n = 0.02 8

0.001 9 Find: R 1. Line from S value to -0.0009 10 n value intersects 1.0

0.0008 turning line. establishing 0.9 0.0007 turning point. 2. Line from V value 0.8 0.30 0.0006 through turning point

0.0005 intersects hydraulic radius scale at R = 0.6

0.6 0.0004 foot.

0.0003 20 0.5 -0.40

Page 141: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-6. Values for Manning’s n and maximum permissible velocities of flow in open channels

possibly damage adjacent structures, it Ž If velocity (V) increases, erosion in-must be contained within limits. Table 6-6 creases.lists the maximum permissible velocities,depending on soil and other factors.

Velocity Relationships

• As slope increases, velocity (V) increases.

• As quantity of runoff (Q) increases whilearea (A) remains constant, velocity (V)increases.

Ž If Manning’s n increases, velocity (V)decreases.

Hydraulic Radius (R]

The hydraulic radius (R) is the area of thewater cross section of the ditch divided byits wetted perimeter, calculated as shown inFigure 6-26. It relates the surface area offriction resistances with the volume ofwater being carried by the ditch. Thehydraulic radius can be calculated using anelectronic calculator as shown in Figure 6-27, page 6-46.

6-44 Drainage

Page 142: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-26. Hydraulic radius

DESIGN CONSIDERATIONS

There are certain factors known for eachditch being designed. Each of these factorswill affect design details. Items such as thelocation, the peak flow or runoff carried,the effect of terrain on slope, and the soiltype or material to be used to line the ditchall have a bearing on channel design.

LOCATION

The location of the ditch will determine itsgeneral shape and the side slopes to beused in its design.

QUANTITY OF RUNOFF (Q)

Designers must know the quantity of runoffthe channel will have to carry. Usually,this is estimated using the rational methodof runoff determination. However, it mayalso be estimated based on knowledge ofthe slope, the diameter, and the type of cul-verts used to discharge into the channel.The value of Q will also determine whichtype of ditch section, triangular ortrapezoidal, will be used. This depends onwhether Q is greater than or less than 60cubic feet per second.

SLOPE (S)

The slope will be determined by the terrain.In general, the slope used will be thenatural ground slope. Small modificationsof the slope can be made for short ditch sec-tions.

PROPOSED DITCH LINING

The ditch lining determines the velocity androughness coefficient or resistance factor, n.(See Table 6-6.)

Table 6-6 gives maximum erosion velocitiesfor each type of soil and lining. The lowervelocity on the chart indicates the velocityat which erosion will start occurring insome portion of the ditch. At the highvelocity value, the entire length of the ditchwill probably be eroding.

Table 6-6 also provides Manning’s rough-ness coefficient (n) which represents the fric-tion resistance of the ditch, channel, orstream for various soil types and linings.Use the average value of n for design pur-poses.

Drainage 6-45

Page 143: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-27. Calculating hydraulic radius

DESIGN TECHNIQUES

Once design considerations have been ex- Step 1. Determine the peak volume ofamined, the interactive design procedure storm-water runoff, Q. Calculate the totalcan begin. area(s) contributing flow to the ditch. (Use

the rational method.) Using the appropriate

DESIGN STEPS formula, find Q.

The steps used in design follow: Step 2. Determine the slope, S, in feet perfoot. If the slope is already known as a

6-46 Drainage

Page 144: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

percentage, it may be converted to units offeet per foot by simply dividing by 100.

Step 3. Select trial values for resistance, n,and velocity, V. From Table 6-6, page 6-44,select a value of the resistance or rough-ness coefficient, n, and a velocity, V, for thesoil type in which the ditch is to be con-structed.

The initial trial velocity should be held to 1.feet per second below the high value.Usually, the channel will be carrying lessthan design flow, reducing the velocity andmaking sedimentation likely. If a highvalue is chosen for the design velocity, thisdeposited material will be removed by thewater during a peak flow without causingextensive damage to the channel.

Step 4. Determine the hydraulic radius.From the slope, S; Manning’s n; and thevelocity, V; find the hydraulic radius of theditch, using the nomograph or equation.

Call this to distinguish it from the Rvalues in Appendix C of this manual, whichwill be

Step 5. Determine the type of ditch crosssection. Where Q is greater than 60 cubicfeet per second, use a trapezoidal ditch.Where Q is equal to or less than 60 cubicfeet per second, use a triangular ditch.Whether the ditch is symmetrical or non-symmetrical will depend on the specific loca-tion.

Step 6. Select the appropriate hydraulicradius and area table, From Appendix C,select the appropriate hydraulic radius andarea table for the desired ditch cross sec-tion. Identify the column headed with thetentative side-slope ratios. Enter the table, locating the value of that cor-responds with Then find the cross-sec-tional area and ditch depth corresponding

to and In using the tables, if theexact value is not available, use thenext smaller value listed in that column.

Step 7. Calculate Q.Q = AWV, where area,

Use the equationand velocity, V,

are determined in steps 6 and 3, respective-ly. If the calculated Q from step 7 is notmore than 5 percent greater than thedesign Q, the ditch selected can be used. Ifthe calculated Q is more than 5 percentgreater than the design Q, reduce thevelocity and repeat steps 4, 5, 6, and 7.

If the calculated Q is smaller than thedesign Q by more than 5 percent, increasethe velocity, However, do not make it anylarger than the maximum for the soil orlining based on Table 6-6. If the calculatedQ is still less than the 95-percent limit, thecross section must be increased by flatten-ing the side slopes or by increasing the bot-tom width (if a trapezoidal section is used).

Step 8. Provide freeboard. Add 0.5 foot tothe water depth to provide freeboard.Freeboard is the additional ditch depth overthat required to carry the design flow. Thisadded depth allows the ditch to carry thedesign capacity, even with sediment in theditch bottom. The total depth, includingfreeboard, will be the cutting depth and thedepth at which the ditch grade will be set.

Example:

Design a ditch to carry a peak volume ofstorm-water runoff equaling 47,3 cfs from aculvert to a stream that is 289 feet fromthe outlet of the culvert. The ditch invert(or bottom) elevation at the outlet of the cul-vert will be 7.0 feet above sea level. Theditch invert will be constructed above thestream high watermark at an elevation of5.5 feet above sea level. The ditch liningwill be the bare (unturfed) GMd soil, as ex-cavated.

Slope = invert at culvert or 7.0 ft - 5.5 ftdistance from culvert to stream

Soil (GMd): V = 3 to 5 fps (Table 6-6)= 0.024 (Table 6-3, page

Drainage

6-37)

6-47

Page 145: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Solution (Nomograph and Table Method):

The solution of a ditch problem is always atrial technique in which several values ofvelocity arc used. Tables are recommendedto tabulate the results. The tables shouldbe similar to the ditch design work sheetshown in Table 6-7.

Step 1. Select a ditch. Since design flow,Q, is less than 60 cubic feet per second,the ditch should be triangular. The chan-nel is not a roadside ditch, so it should besymmetrical. Select side slopes for a 3:1 tri-angular ditch for the first trial. (This as-sumes that periodic vehicular crossings areexpected.) These factors can be changed ifthe ditch design is not suitable. Enter theinformation in the columns under ditchselection on the ditch design work sheet.

Step 2. Select the velocity. The erosionvelocity for the soil is 3 to 5 feet persecond. This means that at 3 feet persecond the soil in the ditch may begin toerode, and at 5 feet per second the wholeditch will be eroding. Since it is preferablenot to exceed the of 5 feet per second,the best initial choice is usually 1 feet persecond lower than or 4 feet persecond. Enter this figure on the designwork sheet.

Step 3. Determine the hydraulic radius, from the nomograph. Using thenomograph (Figure 6-26, page 6-45), first lo-cate a turning line. The line is in the cen-ter on the nomograph. Find the turningpoint by locating the slope, S (in feet perfoot), in the left column of the chart andthe roughness coefficient, n, in the rightcolumn. Draw a straight line to connectthe two points. The point at which the newline crosses the turning line is the turning

point. This turning point will remain (hesame as long as neither S nor n changes.The hydraulic radius, Rm, is found by con-necting the velocity (in the second columnfrom the right) and the turning point bydrawing a straight line through to the Rscale. Then read the hydraulic radius (R)in the second column from the left. Thisgives the required R for any given V inManning’s equation. In this example, R =0.86. Enter this value on the work sheet.

The R value can be computed by using thecalculator method shown in Figure 6-27,page 6-46.

Step 4. Find the hydraulic radius, inthe ditch table. Locate the appropriatetable among Tables C-2 through C-10 in Ap-pendix C of this manual. There are fourtypes of tables: V-triangular or symmetri-cal, V-triangular or nonsymmetrical,trapezoidal-symmetrical, and trapezoidal-nonsymmetrical. For this example, useTable C-2 for a symmetrical V ditch.

Locate the pair of columns representing theside slopes of the ditch being designed (forexample, 3:1). Locate the values thatfall above and below, or the one that is ex-actly equal to, the value found from thenomograph of Manning’s equation. In thisexample, the = 0.86 cannot be found in

these columns, but the values 0.85 and0.90 arc given, Use the lower value (0.85)on the work sheet.

Step 5. Record the area and depth. With = 0.85, the corresponding area found in

Table C-2 is 9.72 square feet, and thedepth (d) found in the column at the far leftis 1.8 feet, Record these values under theappropriate headings on the ditch designwork sheet.

Table 6-7. Ditch design work sheet

6-48 Drainage

Page 146: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1 /AFPAM 32-8013, Vol 1

Step 6. Check for Q. Check to see if thisparticular ditch will mcct the requirementsof the design by performing the calcula -t ions-

Q =

Q = (9.72 sq ft)(4.0 fps)Q = 38.9 cfs

This calculated quantity of flow (Q) mustfall within 5 percent of the design flow of47,3 cubic fect per second, or between 44.9and 49.7 cubic feet per second. If this re-quirement is not met, as in this case, try anew velocity. If the calculated Q is lessthan 95 percent of the design flow, use ahigher velocity. For this example, since38.9 is less than 44.9 cubic feet per second(the lower limit of the acceptable range), avelocity of 4,5 feet per second would be anacceptable assumption for the next trial.

V = 4.5Rm = 1.0R t = 0.95

= 12.0 sq ft. d = 2.0 ftQ = (4.5 fps)(12.0 sq ft)Q = 54.0 cfs, which exceeds 49.7

cfs, so the ncx[ trial velocity must be lessthan 4.5 fps: try 4.2 fps.

V = 4.2= 0.92= 0.90= 10.83 sq ft, d = 1.9 ft= (4.2 fps)(10.83 sq ft)= 45.5 cfs

Q is greater than the lower limit of 44.9and less Lhan the high limit of 49.7. Thisditch is within the range and thus meetsthe ditch water depth and velocity require-ments. Enter this value of 9 on the ditchdesign work sheet.

Step 7. Determine if the ditch is ap-propriate. This process describes a sym-metrical, triangular ditch in GMd soil, witha slope of 0.0052 feet per foot and 3:1 sideslopes. It carries 45.5 cubic feet persecond runoff with a water depth of 1.9 feetand a velocity of 4.2 feet per second.

Since the velocity in the ditch is greaterthan 3 fps, the ditch can be considered self-

cleaning and requires little maintenance.Peak runoff will remove any silt buildupfrom the channel bottom. With V = 4.2 feetper second, there may be some erosion ofthe ditch, but it should not be a significantmaintenance problem. The shape, lining,and slopes are acceptable.

Step 8. Determine the cutting depth. Thewater level in the ditch should be at least0.5 foot below the edge of the ditch as asafety factor. Accordingly, the cuttingdepth is the water depth plus 0.5 foot offreeboard.

Cutting depth = d + freeboard

Using the rutting depth just calculated,

Cutting depth = 1.9 + 0.5= 2.4 ft

Since there are 2.5 feet (8.0 - 5.5 = 2.5) ofavailable cutting depth at the end of theditch, the design is acceptable.

Conclusion: Use this ditch.

Alterna Live Solution (Calculator Method):

If it is more convenient to use the cal-culator method than the nomographmo the fol-lowing procedure is used:

Step 1. Select a ditch. As before, the ditchis V- type and symmetrical. Assume sideslopes of 3:1 have been selected for thetrial cross section.

Step 2. Select the velocity. The assumedtrial velocity should always be 1 feet persecond less than the maximum erosionvelocity of the soil. In this case, it will be 4feet per second.

Step 3. Determine the hydraulic radius, Rm.

where—

V = 4 fpsn = 0.024S = 0.0052 ft/ft

Drainage 6-49

Page 147: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Stcp 4. Determine the area of water,and depth of water, d. As explained in Fig-ure 6-28—

= 1/2(xd + yd)d for any triangular ditch.

For this problem, x = 3, y = 3

= l/2(3d + 3d)d= l/2(6d)d= 3d2

Figure 6-28. Determination of the area of atriangular ditch

The wetted perimeter (wp), as explained inFigure 6-29, is—

w p . Cl+ C2 = ( x d )2+ d + (yd)2+ d

Substituting values of x and y–

Figure 6-29. Determination of the wettedperimeter of a triangular ditch

Therefore, the hydraulic radius (Rm) is—

For depth (d), the depth of water for theconditions assumed in step 3, is calculated.Since Rm = 0.848 from step 3, and Rm isalso equal to 0.474d, the depth of water (d)can bc computed.

This allows to be computed.

Step 5. Check for Q.

The Q calculated for the ditch must bewithin ± 5 percent of the design Q of 47.3cfs, or between 44.9 and 49.7. The calcu-lated ditch Q is 38.4, which is less thanthe lower limit and is unacceptable. Sincethe calculated Q is below the lower limit,raise the velocity for the next trial calcula-tion. For the second trial, the assumedvelocity will be 4.5 feet per second.

6-50 Drainage

Page 148: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Step 6. Make a second trial calculation.

Q is too high; try V = 4.2 fps.

Step 7. Make a third trial calculation.

Q is acceptable, because it is between thelimits.

Step 8. Determine the ditch. With the Qbeing acceptable, the ditch will have awater depth of 1.92 feet and side slopes of3:1. Additional depth must be added to thewater depth for freeboard. This additionaldepth can be selected depending upon theconditions external to the ditch but cannotbe less than 0.5 foot. Therefore—

Cutting depth = water depth (d) + 0.5= 1.92 + 0.5= 2.42 ft or 2.4 ft

The velocity of 4.2 feet per second is accept-able. Some erosion may be anticipated, butit will not be serious. In addition, becauseof the high velocity, the flow will clean outthe sediment from- previous low flow,

SPECIAL CHANNELS

Some facilities will have special typeschannels where surface runoff will becepted and removed. These channels

ofinter-will

be similar to open channels, except they

will tend to be very wide and shallow. Todetermine runoff capacity (in cfs) in thistype of channel, open channel hydraulics,as previously discussed, must be modified.

Gutters

Gutters are shallow, paved drainage chan-nels used in more permanent constructionadjacent to paved or hard-surfaced areas.They provide positive removal of runoff,protection for easily eroded soils adjacent tothe pavement, and prevention of softeningof turf shoulder areas commonly caused bya large volume of runoff from adjoiningpavements.

A cross section of a typical runway gutter isshown in Figure 6-30, page 6-52. This gut-ter conforms to US Air Force safety require-ments and design charts of that particulargutter. Safety and operational require-ments for fast landing speeds make itdesirable to provide a continuous, lon-gitudinal grade in the gutter. Close con-formity to the runway gradient requires theuse of sump inlets (drop inlets covered bygratings). A sufficient number of inletsshould be provided in the gutter to preventthe depth of flow from exceeding 3 inches.

Median Channels

Channels will be placed down the center ofmedians, dual roads, runways, taxiways,and other similar structures. These than -nels will be symmetrical but very wide andshallow. The input flow into such channelsis from surfaced and unsurfaced areas ad-jacent to the channel. The flow can bedetermined by the rational method. Sincethe factors of slope (S), Manning’s n, flow(Q), and the general width are known, thedepth can be determined by trial using theflow equation or nomograph for flow inopen channels.

BERMS

The uncontrolled inflow from drainage areasadjacent to open channels has been asource of numerous erosion failures. Com-bating this problem requires special con-sideration during the design of the surfacedrainage system. Local runoff inflow can

D r a i n a g e 6 - 5 1

Page 149: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 332-8013, Vol 1

Figure 6-30. Typical run way gutter

be particularly detrimental. Because of nor-mal irregularities in grading operations,runoff becomes concentrated and causes ex-cessive erosion as it flows over the sides ofthe channel. Experience shows that con-structing a berm (raised lip), Figure 6-31,prevents this problem. Place the berm,usually made of earth, at the top edge ofthe channel. This berm prevents inflowinto the channel except at designatedpoints where an inlet, properly protectedagainst erosion, is provided.

Where excavated material is wasted, as in alevee or dike parallel to the channel, theremust be frequent openings through thelevee to permit inflow to the channel. Asuitable berm allows a minimal amount ofexcavated material to flow back into thechannel. This prevents sloughing from thespoil bank into the channel.

Runoff, Q, from the area is determined bythe rational method. This runoff is col-lected and conveyed by the channel formed

6-52 Drainage

Page 150: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-31. Typical berm emplacement

by the berm. The factors of Q, n, S, andwidth are used to solve for depth by thetrial method.

CONSTRUCTION AND MAINTENANCEOF CHANNELS

Ditch construction normally requires eithera grader or a scraper. Sometimes, thesetwo items arc used in combination. Depending on the location, other factors must beconsidered in designing and buildingditches.

Interceptor ditches should be set on grades,thus allowing for quick removal of water

without erosion. When the grade is not suf-ficient to permit quick water removal, theditch may require an asphalt or concretelining. Berms may be constructed on thedownhill side of interceptor ditches, asshown in Figure 6-31, to prevent overflowand excessive erosion of the downhill slopes.

Abrupt changes in a ditch's normal flow pat-tern will induce turbulence and cause exces-sive erosion. These conditions develop mostfrequently at channel transitions, junctions,and storm drain outlets. Accordingly, spe-cial attention must be given to these loca-tions during design.

Drainage 6-53

Page 151: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Channel maintenance problems exist in alldrainage systems. The basic design of theditch must consider these maintenanceproblems before they arise. Therefore, desig-ners must have a thorough understandingof the two basic ditch maintenance prob-lems: sedimentation and erosion. Channelprotection and ditch shape, when usedtogether, control maintenance problemsmost effectively.

SEDIMENT CONTROL

Water flowing overland tends to carry sedi-ment into any open channels. When thevelocity in the channel is 3 fps or less, thissediment can be deposited in the channel.Since most storms are less intense than thedesign storm, the channel bottom may ac-cumulate a large volume of loose sediment.When peak flow does occur, the velocityshould be great enough to scour the chan-nel bottom clean of loose sediment. If thesediment is not removed, it will compactand gradually reduce the depth of theditch. At peak flow, the ditch may overflowand cause damage to adjacent structuresbefore the channel is cleaned out; therefore,the channel should be kept clean throughmaintenance.

When designing channels, keep peakvelocity flow above 3 fps. This keeps thechannel self-cleaning. A higher velocity ispreferred, but such velocity must not ex-ceed the maximum velocity for the soil.(See Table 6-8.) When the soil type re-quires a maximum allowable velocity under3 fps, sedimentation will be a maintenanceproblem. One solution is to line the ditchwith asphalt or concrete. This reduces thecoefficient of friction, thus increasing thevelocity. When sedimentation is expectedand linings cannot be used, increase the al-lowable freeboard to eliminate overflow.

EROSION CONTROL

Water flowing through open channels is tur-bulent. This turbulence increases as thevelocity increases. Together, velocity andturbulence erode and carry away the soil ofthe channel and endanger nearby struc-

tures such as roads, bridges, and culverts.Velocity and turbulence may also endangerthe channel itself. In addition, the erodedmaterial may sometimes be deposited withinthe channel in areas where it will causedamage. In these cases, channel main-tenance and repair will be a constant con-cern.

Erosion most commonly occurs when thevelocity of flow exceeds the velocity atwhich the soil of the channel will erode.Table 6-8 shows the maximum velocities.Erosion can be prevented by lowering thevelocity below the soil-erosion velocity.This can be accomplished by lining thenatural channel material with a moreerosion-resistant material or by reducingthe side slopes. Table 6-9 shows the recom-mended side slopes. Erosion should be con-sidered and accounted for in the design ofchannels.

Table 6-8. Suggested maximum velocities

6-54 Drainage

Page 152: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-9. Recommended side slopes

Decreasing the Hydraulic Radius

Reducing the hydraulic radius will decreasethe velocity. This decrease in hydraulicradius can be accomplished by increasingthe wetted perimeter, wp, in relation to thearea, A (while the Q remains constant).This can be done by widening the ditch, flat-tening the side slopes, or widening the bot-tom. This increases the wetted perimeterwithout materially increasing the area. Therequired changes in ditch design are deter-mined by the trial approach, since theamount of runoff, Q, must be retainedwhile reducing the velocity.

Lining the Channel

Erosion can be controlled by lining the bot-tom and sides of the channel.

Grass or Turf

Since natural linings take considerable timeto grow or effort to place, they are seldomused in the TO.

Riprap

Riprap lining involves placing rocks or rub-ble in the bottom and on the sides of theditch to prevent soil erosion. Rocks shouldbe hand-placed in at least two layers andcompacted individually. Riprap not onlyprevents erosion but decreases velocity inthe channel because of its high n value.Riprap also helps prevent erosion whenmaking transitions from paved to soilditches or from other high-velocity ditchesto those in which lower velocity is required.Gabions are another method of lining

ditches. Details on riprap and gabions aregiven on pages 6-116 through 6-123.

Pavement

When the design and construction are doneproperly, paving the ditch with asphalt orconcrete will prevent erosion. Because ofthe low n values of different types of pave-ment, velocity may increase too much, caus-ing erosion where the pavement ends. Spe-cial protection, such as a stilling basin orrock lining, may be required at this point toslow the velocity before allowing the flow tocontinue into the natural soil channel. Be-cause of pavemen 1’s low n values, it can beused effectively to increase flow velocities ifthey are too low, thus preventing deposition.

Installing Check Dams

The water velocity in a channel can also bereduced by decreasing the slope. However,except for local variations, building ditchesat slopes other than that of the surround-ing ground is impractical, One method fordecreasing the slope is to install checkdams or weirs, as shown in Figure 6-32,page 6-56. Check dams should be con-sidered when the slope ranges between 2and 8 percent. Channels with slopes of 2percent or less generally do not require ex-tensive erosion controls. With slopes in ex-cess of 8 percent, it is usually moreeconomical to pave the ditch with asphaltor concrete than to build check dams.

Design

Correct spacing between check dams can bedetermined by using the following formula:

where—

S = spacing, in feet, between check dams(This value should not be less than 50feet.)

H = height from the channel bottom to thelower edge of the weir notch (This valueshould not be greater than 3 feet unlessthe dam is to be structurally designed.To prevent unnecessary work, the practi-cal lower limit for H is 1 foot.)

Drainage 6-55

Page 153: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-32. Check-dam design

6-56 Drainage

~ A - % grade of road centerline

-- ~ ------ --- --

·1 Spacing in feet Spacing .. l00H -----------

A-B

H is expressed in feet

Page 154: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

A = slope of the original ditch in percent

B = desired slope in percent (This valueshould be set at 2 percent. This is themaximum slope that will not require addi-tional erosion control.)

Example:

Original slope = 5%

Desired slope = 2%

H = 3 ft

Find S.

The spacing between check dams is 100feet. To prevent erosion of the sides of thechannel at the check dam, a weir notch isbuilt in the center of the dam. The weirnotch must be designed to carry the flow inthe ditch. Weir-notch dimensions forvarious flow rates are given in Table 6-10.

Maintenance

Erosion is a common problem with checkdams. It usually occurs when the weir

Table 6-10. Discharge for weir notches in check dams

Drainage 6-57

Page 155: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

notch is too small or is clogged with debrisso that water flows over the top of the dam.Scour begins on the area exposed to thehydraulic jump. If allowed to continue longenough, the erosion will extend to the areaaround the dam, as seen in Figure 6-33. Ifthis occurs, there will be more damagecaused to adjacent structures than if thedam had never been installed.

Some protection usually takes the form ofan extended horizontal or sloping apron.Scour can also be prevented by anchoringthe sides and bottom into at least 2 feet ofcompacted material. Then place riprapalong at least 4 feet of the downstreamchannel. These construction techniqueswill prevent scour and undercutting.

Figure 6-33. Check-dam maintenance

6-58 Drainage

Page 156: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SECTION III. CULVERTS

A culvert is an enclosed waterway used topass waler through an embankment or fill.The flow in a culvert depends upon severalfactors, including the lining, slope, head-walls, wing walls, and downstream condi -

tions. Accordingly, culvert types and con-struction procedures are discussed prior toconsidering culvert hydraulics and designfeatures.

CULVERT TYPES AND DESIGNS

PERMANENT CULVERTS

Permanent structures can be constructedfrom corrugated metal pipe (CMP), concretemultiplate pipe arch, vitrified clay (VC),polyvinyl chloride (PVC], or other material.

Corrugated-Metal-Pipe Culverts

Because it is commercially available innumerous shapes, lengths, and diameters,CMP is commonly used in military construc-tion. For TO construction, CMP is made ofan aluminum-and-steel alloy. It comes innestable half sections that, when as-sembled, give 2-foot effective lengths. It isavailable in the diameters and gages listedin Table 6-11. The minimum diameterrecommended is 18 inches for lenghts up to20 feet and 24 inches for all other lengths.Small diameters may become clogged withdebris and are difficult to maintain.

Specific construction techniques areemployed in placing CMP. A retaining wallcalled a headwall is placed at the upstreamend of the culvert. Headwalls arc alwaysused upstream; they arc desirable but notmandatory for the downstream end. The

headwall supports the soil mass at the endof the culvert and helps to protect againsterosion.

CMP joints must be lapped so that waterflowing through the culvert passes over thejoint rather than into it. Failure to proper-ly overlap the pipes will tend to force theflowing water through the joints and intothe fill. All joints must be sealed, preferab-ly with caulk or bituminous material. Ifjoints are not sealed, voids may be gener-ated around culverts, causing collapse ofthe fill. To increase the velocity for agreater quantity of flow, line the culvertwith asphalt. Commercial CMP is availablewith asphalt linings.

Assembling Nestable CMP

CMP has flange-type fittings which arc easi-ly fastened together by nuts and bolts thatcome with the sections. Vise grips and aratchet set make assembly faster and easier.

Table 6-11. Sizes of corrugated metal pipe

Concrete-Pipe Culverts

When available, precast concrete pipeshould be used instead of CMP for culverts.It has two advantages over CMP. First, it isstronger and requires less cover than CMPto support the same load, Second, the inte-rior surface of concrete pipe is smoother(Manning’s n = 0.013) than CMP (Manning’sn = 0.024). Because of these advantages,concrete pipe of the same diameter andslope as CMP will carry a higher flow.

Concrete pipe is fabricated in circular andnoncircular cross sections, It is availablein many lengths and widths. Seal joints be-tween the sections to prevent excessiveleakage and subsequent weakening of the

Drainage 6-59

Page 157: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFP 93-4, Vol I

fill section Substantial headwalls are re-quired at both ends to prevent separationat the joints. Start assembly downstreamand work upstream, ensuring male endspoint downstream.

Concrete-Box Culverts

Consider concrete-box culverts where thefull area of the waterway must be used.One advantage is that the box can bedesigned to withstand external loads withlittle or no cover. Box culverts are especial-ly adaptable to rock sites, since the bottomof the culvert can be placed directly on therock.

Concrete-box design requires knowledge ofconstruction techniques for reinforced con-crete structures. Box culverts can beprecast, but construction in the TO willprobably require that they be cast in place.

EXPEDIENT CULVERTS

Expedient field-type culverts are built ofmaterial available on-site such as logs, oildrums, and sandbags filled with a sand-ce-ment mixture. Some examples of culvertsbuilt of these materials appear in Figures6-34, 6-35 and 6-36. Expedient culvertsbuilt and sized properly should serve untilpermanent structures can be built. Forevaluating hydraulics, end areas equivalent10 CMP can be used for similar slopes.

CULVERT CONSTRUCTION

Proper placement is one of the most impor-tant factors during culvert construction. Itis a major contributor to survival of theculvert under adverse conditions. Somethings to consider in placing culverts arcculvert alignment: slope; fill placement; com-paction under, around, and over theculvert; culvert length; and protectionagainst erosion.

Alignment

The relationship of the culvert to thestreambed is of major importance. Im-proper location can cause the stream toseek an alternative path other than the cul-vert. This could quickly close a road or air-

field to traffic. To lessen this effect, usethe alignment techniques shown in Figure6-37, page 6-62.

To maintain an existing drainage pattern,place the culvert directly in the streambed,as in view (A) of Figure 6-37. Even thoughthis may be diagonal to the fill, if thehydraulics of the channel are not changed,the stream will not change its direction.

Prevent the stream from shifting its courseat the culvert inlet or outlet. Sometimesthe structure will cut across a streammeander as in view (B) of Figure 6-37This leads to doubt as to where to lay theculvert in the streambed. In this case, it isbest to cut a new channel 10 lead thestream away from the structure. The oldstreambed must be filled and dammed witherosion-resistant material at the junction ofthe old and new channels. The dam can bebuilt of sandbags, logs, riprap, or othersimilar material.

Provide a smooth transition into and out ofthe culvert. The structure may cut acrossa bend of the stream, as in view (C) of Fig-ure 6-37, with a straight run of the streamthrough the structure. If the bend is closeto the structure, it is preferable to recut thestream as shown, and lay the culvert inthe new streambed. Care should be takento fill in and dam the entrance to the oldstreambed and the junction of the twostreambeds, as descibed above.

Move the water past the project as quicklyas possible. When the channel flows paral- -lel. to the structure, erosion will even tuallyoccur. To prevent erosion, dig a new chan-nel routing the flow through the culvertand away from the structure, as shown inview (D) of Figure 6-37. Again, be sure tO

fill and dam the old streambed at the junc-tion point.

The alignment of ditch relief culverts isshown in Figure 6-38, page 6-63. Theamount of flow and the slope of the ditchdetermine the spacing between culvert in-lets. On a road with a 5-percent grade,relief culverts should be spaced 500 feet

6-60 Drainage

Page 158: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-34. Oil-drum culvertFigure 6-35. Landing-mat and sandbag culvert

Figure 6-36. Log culverts

Drainage 6-61

Page 159: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-37. Culvert alignment

apart. On an 8-percent grade, spacing Slopeshould be reduced to 300 feet. Culverts normally should be installed with

the invert of both the inlet and the outlet ofthe culvert at streambed or channel eleva-tion. The invert is the lowest point in the

6-62 Drainage

Erosion channel

Use longer culverts in

natural channel

Bad alignment Good alignment

(A) Maintain existing drainage pattern

Dam

(8) Prevent stream from shHtlng Its course at Inlet or outlet

Dam Fill old channel

Dig new channel

4-+---· --- . ----

Dam

--..... 11:, I

(C) Ensure smooth transition at Inlet and outlet

I I I I I __ ---1I~-IL ___ _

I I , I I I

Fill old channel

(0) Move water past project as soon as possible

Page 160: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-38. Ditch relief culverts

internal cross section of an artificial chan-nel or the bottom of the culvert. The nor-mal grade of the culvert can be modified bytwo techniques, as shown in Figure 6-39.

• Drop inlets can be used to lower theinlet of the culvert, This will tend toreduce the slope of the culvert. An ex-ample of a drop inlet is shown in view(A) of Figure 6-39 and a discussionbegins on page 6-89.

Figure 6-39. Changing normal grade of culvert

Ž The outlet of the culvert can be raisedto reduce the slope, as shown in view(B) of Figure 6-39.

For culverts to be self-cleaning, flowvelocity should be at least 3 fps. Toachieve this velocity, the culvert should notbe set on less than a 0.5 percent grade, ifpracticable. To prevent excessive outletvelocity, the culvert grade should not ex-ceed 2 percent.

In general, free-falling outlets and culvertswith slopes of more than 2 percent will re-quire outlet erosion protection. In moun-tainous country where there are excessivestream slopes or in fills across dry valleys,culverts may have to be set at grades otherthan the terrain or streambed slope. In theTO, it may be advisable to accept theerosion problem and install the culvert witha slope for an excess of 2 percent. Thiswill help to prevent a blockage caused bydebris passing through the pipe.

Depth of Fill

The distance measured from the culvert in-vert to the edge of the shoulder or top ofthe fill, as shown in Figure 6-40, page 6-64, is the depth of fill. The depth of fillmust be equal to or greater than the coverplus the pipe diameter. Otherwise, asmaller diameter culvert or a drop inletmust be used. For a road culvert made ofCMP, the largest diameter allowable mustequal two-thirds the minimum fill depth.

Cover

The depth of compacted soil from the top ofthe culvert (crown) to the finished construc-tion grade is called cover. The culvert andthe surrounding compacted soil must havesufficient strength to carry the compacted.soil backfill (dead loads) and the wheel andimpact loads (live loads) of the traffic. Liveloads are more damaging than dead loadson culverts under shallow cover, and deadloads are more damaging than live loads onculverts under deep cover. Accordingly,both minimum protective cover and maxi-mum permissible depths of backfill must beincluded in design considerations for cul-verts. During construction, provide

Drainage 6-63

Page 161: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-001/AFPAM 32-8013, Vol 1

Figure 6-40. Culvert specifications for CMP

adequate additional cover to protect the cul-vert from damage in places where heavyconstruction equipment will be crossing fre-quently.

The minimum cover required to protect theculvert pipe against live loads will dependupon the type of load. For road culverts,the minimum cover is one-half the diameterof the culvert, or 12 inches, whichever isgreater. The cover over culverts used in air-fields must be specifically designed for theheaviest aircraft using the facility. Table6-12 lists characteristics of US aircraft.Use this table to determine the landing-gearconfiguration, wheel loads, and culvertweight type. This will, in turn, allow you toselect the proper fill requirements categoryin Table 6-13, page 6-66, or Table 6-14,page 6-67.

Tables 6-13 and 6-14 give the cover require-ments for culverts under airfields. Thesetables are composed of a series of chartsbased on aircraft load and gear configura-tions. Each of these charts is headed by a

culvert weight type. These charts are goodfor 5,000 pounds more than listed. (For ex-ample, the chart headed “60,000-lb Single-wheel” is good for single-wheel loads up toand including 65,000 pounds.)

Each chart is subdivided into columnsheaded by culvert pipe diameters, in inches,and rows based on the gage of the metal.Use linear interpolation for the incrementaldiameters not listed. The body chart givesthe cover required, in feet, for the diameterand gage of pipe concerned.

To use these tables, find the chart that ap-plies to the particular aircraft wheel or gearload and landing-gear type. Then use Table6-12 to find the appropriate culvert type.When the proper chart is located, readdown the left column of the table to deter-mine the appropriate row for the gage con-cerned. When the proper row has beenfound, read horizontally to the right andfind the minimum cover, in feet, under thecolumn headed with the pipe diameter in

6-64 Drainage

Page 162: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-12. Characteristics of US aircraft

Drainage 6-65

Load on main Culvert WT Aircraft Name Max wt (kip) Gear type gear (klps) type

A·7 Corsair 11 42 S 18 2 A·10A (CAS) 51 S 23 2 A·37B Dragonfly 15 S 7 1

F·111A/D/E (VGF) 100 S 44 4 F·111 F (VGF) 100 S 48 4 F·4C/D/E/G Phantom I1 58 S 25 3 F·14C Tomcat 72 S 34 4 F·15A/B Eagle 56 S 25 2 F·15C/D ... 68 S 30 2 F·15E 81 S 35 2 F·16A (LWF) 33 S 14 2 F-18 Hornet 20 S 9 1

A\ I ""f'"\. Harrier 28 DU·S(BiC) 10 2 I-\V-OC

AV-16A Advanced Harrier 30 11 2

B-1 (Adv S8) 477 T-T·TA 222 15 B-52G/H Stratobomber 488 T-T 265 16

FB·111A (VGSB) 114 Single 54 5

C-5B Galaxy 840 T~DE-TA 400 15 C·9A Nightingale 108 Twin 52 7 C-17 ~-- 580 T-TA-TR1 267 15 C-130E Hercules 175 S-TA 84 13 HC-130H Hercules 175 S-TA 84 13 KC-135A Stratotanker (707) 301 T-TA 142 14 t"_1.d 1 A IQ C+orlift.or ~')~ TTA 1';:,) 1,4 ,...,-- I""T I r'\IU VU;UUlLQ"1 vc;.v J - J f"\ l..Jv I~

VC-137B (707) 334 T-TA 167 14

E-3A (707 AWACS) 323 T-TA 155 14 E-4B (747 AABNCP) 800 DU-T·TA 372 16

SR-71C (ASR) 170 Triple 77 9

OV-10A/B Bronco 14 DU-S(TA) 55 1

I1 UV-18A Twin Otter 13 Single 6 11

Page 163: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-13. Minimum cover requirements, in feet, for airfields (CMP)

question. Two examples of this tabulation 60,000-lb single-tandem—12-gage pipe.follow. (Use 60,000-lb single-tandem assembly

Example 1:

C130E Hercules—12-gage pipe; from Table6-12, page 6-65, C130E requires culvert WTtype 13.

(assy), chart 13.)

6-66 Drainage

Page 164: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-14. Minimum cover requirements, in feet, for airfields (reinforced concrete pipe)

From chart: Example 2: 60,000-lb single-wheel—8-gagepipe. (Use chart 5 in Table 6-13,)

Drainage 6-67

Page 165: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The maximum permissible depth of fill as shown in Figure 6-40, page 6-64. The(cover) for CMP is given in Table 6-15 for bedding is formed and shaped to fit the bot-steel and Table 6-16 for aluminum alloy. tom of the culvert. In addition, the founda-Reinforced concrete pipe made under stand- tion is cambered (curved slightly upward),ard specifications can be used in fill up to as shown in Figure 6-41 along the center-50 feet. line of the culvert to allow for settlement

and to ensure tightness in the joints. AtBedding (Foundations) no time should the invert elevation increase

The minimum bedding depth for pipe cul- as the flow proceeds downstream.

verts is one-tenth the diameter of the pipe

Table 6-15. Maximum permissible cover for CMP

6-68 Drainage

Page 166: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-16. Maximum permissible cover for corrugated aluminum-alloy pipe

Culverts are constructed on firm, well-com-pacted foundations. The composition of thesoil on the bottom of the stream should bedetermined. Good granular material will berequired to form a proper compacted andshaped bed. If a stream bottom is com-posed of poor material, such as organic mat-ter, muck, silt, or large material that could

Figure 6-41. Elevation of center section ofpuncture the CMP, remove and replace thematerial. The depth of material to be

culvert

Drainage 6-69

Page 167: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

removed will depend upon information fromborings. When the bearing strength of thesoil is completely inadequate and unevensettlement is expected provide cradlefootings. These footings may require pilingas shown in Figure 6-42, Footings used fortimber culverts as shown in Figure 6-43,can also be adapted for various types of cul-verts and soils.

Culverts can be placed on properlyprepared rock foundations, Trench therock and backfill with firmly compacted soilfor bedding the culvert, as shown in Figure6-44.

Figure 6-43. Footings for timber culverts

Figure 6-44. Concrete-culvert installation inrock

Backfill

Take care in backfilling around the culvert,since the backfill supports the culvertagainst soil pressure generated by surfaceloads as shown in Figure 6-39, page 6-63.The soil selected should be placed carefullyin well-compacted layers kept at the sameelevation on both sides of the culvert. Com-paction is done in 6-inch layers if hand- orair-operated or if other mechanical tampersare used. If logs, hand tamping, or otherexpedient methods are used, place the soilin 4-inch layers. Carry the compactionfrom the culvert bed material to 12 inchesor one-half the diameter above the top ofthe culvert (whichever is greater).

Figure 6-42. Cradle footings

6-70 Drainage

Page 168: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Length

Culvert length is determined by the widthof the embankment or soil mass throughwhich the culvert carries water. Culvertsthat do not include a downstream headwallmust be long enough 10 extend a minimumof 2 feet beyond the toe of the embankmentto prevent erosion.

Headwalls, Wing Walls, and Aprons

Hcadwalls and aprons arc constructed toguide water into the culvert, prevent or con-trol erosion, reduce seepage, hold the soilin place, and support the ends of the cul-vert. Headwalls close to roads should notprotrude above the shoulder grade. Theyshould be at least 2 feet outside theshoulder so they do not present a traffichazard.

Use headwalls on the upstream end of allculverts. If possible, use a headwall on thedownstream end as well. When concretepipes arc used, headwalls are mandatory atboth ends. Headwalls, both upstream anddownstream, should have wing walls orretaining walls set at an angle 10 the head-wall, This will help support the fill andd irect the water flow to prevent erosion.The upstream wing wall will guide thewater into the culvert and assist in improv-ing the culvert hydraulics. The downstreamwing wall, combined with an apron, willhelp reduce the velocity of the stream, andthereby lessen erosion al the outletIdeally, headwalls and wing walls should bereinforced concrete or mortared stone.Standard designs are in the TM 5-302series manuals. They can, however, bemade of expedient material such as lumber,logs, or sandbags. These structures areshown in Figure 6-45. For speedy construc-tion in the TO, sandbags filled with a soil-and-cement mixture may provide the bestheadwall possible.

When headwalls arc not used on the down-stream end, the culvert should projectbeyond the toe of the fill at least 2 feet.Use riprap to protect the projecting area cul-vert riprap, as shown Figure 6-46, page6-72. Figure 6-45. Headwalls and wing walls for

culverts

Drainage 6-71

Page 169: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-46. Culvert outlets without headwalls

Erosion Control

Culverts discharging into open channelsshould have antiscour protection to preventerosion. Two types of channel instabilitycan develop downstream from culvert andstorm-drain outlets. These conditions,known as gully scour and scour hole, areshown in Figure 6-46. Predict the type ofscour for a given field situation by compar-ing the original or existing channel slope ordrainage basin downstream of the outlet towhat is required for stability.

Gully scour is expected when channel flowexceeds that required for stability. Itbegins at a point downstream where thechannel is stable and progresses upstream.If sufficient differential in elevation exists

between the outlet and the stable channel,the outlet structure will be completelyundermined. Erosion of this type may beconsiderable, depending on the location ofthe stable channel section relative to theoutlet in both the vertical and downstreamdirections. View (A) of Figure 6-47 illus-trates this condition.

A scour hole or localized erosion, as shownin view (B] of Figure 6-47, is to be expectedif the downstream channel is stable. Theseverity of damage to be anticipateddepends on existing conditions or thosecreated at the outlet. In some instances,the extent of the scour hole may be insuffi-cient to produce either instability of the em-bankment or structural damage to the out-

6-72 Drainage

Page 170: Army Construction Manual FM5 430 Vol1 Entire

Figure 6-47. Types of scour at culvert outlets

let. However, in many situations, flow con-ditions produce scour that erodes the em-bankment and causes structural damage tothe apron, end wall, and culvert. This typeof outlet erosion of the bottom of the ditchand of the side banks is shown in Figure6-48.

Erosion is best controlled by two methods:velocity reduction and channel protection.Reducing the slope of the culvert reducesthe velocity. This solution, however, mayrequire a larger pipe since it changes thecapacity of the culvert.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Headwalls, wing walls, or channel liningscan absorb the energy of flowing water andreduce its velocity to acceptable levels.When wing walls are not provided, line thestream bank and bottom for some distancedownstream with riprap or other material.Ditch linings were described in greaterdetail earlier in this chapter.

CULVERT DESIGN

The hydraulic load on a culvert is theamount of water that will flow to the ul-vert inlet, either as direct surface or chan-nel-stream flow. Surface flow is determinedby the rational and channel-flow-equationsmethods discussed earlier.

Hydraulics of Culverts

Culvert quantity of flow (Q) is the amountof water the culvert will carry in a unit oftime. This capacity is expressed in cfs.For a particular culvert of known size (A),shape, and interior roughness (n), the dis-charge capacity is controlled by one ormore of the following factors:

•inlet.

Height of the water above the culvert

Hydraulic gradient (S) of the culvert.

Length (L) of the culvert.

Elevation of the tailwater at the culvertoutlet.

Figure 6-48. Outlet erosion

Drainage 6-73

Page 171: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The type of inlet is not generally consideredin military culvert design. However, itshould be remembered that the dischargecapacity of a culvert will be increased by asmooth, transition type of inlet with head-walls and wing walls. For construction inthe TO, the culvert should have a designcapacity sufficient to pass the peak runofffrom the design storm.

Hydraulic Gradient

The hydraulic gradient (S) of a culvert isone of the culvert discharge capacity con-trols. It can be satisfactorily estimated asthe slope in ft/ft. The gradient is calcu-lated by dividing the head (H) on a culvertby the culvert length (L): S = H/L. Thehead is the difference in elevation betweenthe following:

• The two ends of a culvert, if both theinlet and the outlet are not submerged.

• The water surface directly above theinlet and the top of the outlet, if theinlet is submerged and the outlet is notsubmerged.

The hydraulic gradient and head areillustrated in Figure 6-49.

The normal flow pattern for culverts, forwhich Table 6-17 is used, is shown by view(A) of Figure 6-49, In this case, the wateris at crown elevation al the inlet, and theoutlet is free-flowing.

An accumulation of water at the inlet of theculvert is called ponding. When pendingoccurs, the outlet will normally be free-flow-ing, but the water will be at some depthabove the inlet. When this depth at theinlet is 1.2D or less (where D is the dia-meter of the culvert), use Table 6-17 todirectly determine Q and V. When thewater depth at the inlet invert is greaterthan 1.2D and the outlet is free-flowing,use a nomograph (Figure 6-50, page 6-76)to determine Q, and use the continuityequation Q = VA to determine the velocity.

When both the inlet and the outlet are com-pletely submerged, use Figure 6-50 ex-clusively.

• The water surface directly above theinlet and the outlet, if both the inlet andoutlet arc submerged.

Figure 6-49. Hydraulic gradient, S, and heads, H, for culverts

6-74 Drainage

Page 172: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-17. Capacity and critical slope of culverts*(Manning’s n of 0.012, 0.018, and 0.024)

Drainage 6-75

SLOPE 4PERCENTJ 8 10 12 15 18 21

0 .• 3~1 0*1 431*I~ 1 06 09 1.6 2.6 45 6.8 10 =... lit.

0.8

0.4

0.6

0.8

1.0

1.2

1 0 .• ' To' 2.'

0.6 I 11 I 2-0.7

0.8

1.4 0.9 1.6

:: 1 :: I'" I 0.4 0.4

0.6

0.8

1.0

1.2

1.4

1.6

7.5

4.5 7.1 11

2.4

DIAMETER Of PIPE 4INCHES)

24 30 36 42 48 54

n = 0.012

151 26

1 40 I

59

1 83 1110

' 6- 7- 8- 9--- 10-

15 26 40 59 83 110

n = 0.01'

11 20 I I .a 1 92 1 23

I I I I I n = 0.024

72

60 66 72 78 84 90 98

140 '180 , 230 I 280 1330 1400

, 470

120 I 1601 9-- --- 10= ... _-

~--

220 270 330 400 470 12

230 .J!2.. 330 400 470

140 180 230

I I I I 98 160 190 230 280 330

190 230 280 340 390

210 250 310 370 430

220 270 320 3 450

230 11

280 330 400 .£!L 12 ~ 280 330 400 470

190 230 280

U 0.9 1.5 2.5 83 110

:: 1 ':: 1 :: tm :: ri: 1 :: 1 'f'I"1 1 1 1 1 1 1 1 1 1 1

:: 1 :: 1 ~ :: 1"-1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3.2

·Culverts with free outlet with water Burface at inlet same elevation as top of pipe and outlet unsubmerged.

NOTES;

1. V.lue. ar. In cta.

3. StHper .'ope. than 'cr't,c." do not r •• ult In Incr •••• d dl.ch.rge.

4. Numb.r.d '.t.pped" IIn •• Indlc.te .ppoxlm.t. v.locltle. In fp •.

5. Manning'. n = 0.012 applle. to clay or concrete pipe; excellent condition of .urfaclng alignment.

8. M.nnlng'. n " 0.018 applle. to CMP; Inv.rt paved 10 50% of diameter.

7. Manning'. n .. 0.024 appll •• to CMP; .t.ndard unpaved.

Page 173: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-50. Nomograph for culverts flowing full with ponding inlets

6-76 Drainage

0.25

03

0.5

-= U 09

CD UI

Cl c C

CD

-= a. 0

"0 ~

III U CD I'll ~ CD

1:: ~ ...

------ --.,Q CD .,. > CD "3 ..... Cl () ....

..... I'll ~ u UI '5 c Cl

-iij CD 0

3 The head al entrance (h,' muSI ellcead

4 velocIty head plus entrance loss.

5 Compute °i V= -

A

Increase seClion If necessary_ unlil hi > 0.022 V 2

for CMP hi > 0.017 V2 for others.

a 2

3

4

5

6

7 8 9 10

20

30

40

50

00008 CO' It),... o It) 8

N

o g~g 8

Allowable headwater

For free oullet. use H' for H, H' may be approlllmated as H" less an assumed vertIcal d,ameler

Page 174: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Critical Slope

For a given size, A, of the culvert and agiven head, H, on the culvert, the dischargecapacity of the culvert will increase as thehydraulic gradient increases, Thiscontinues until the hydraulic gradientbecomes equal to or greater than thecritical slope, Sc. As the hydraulic gradientis increased beyond the critical slope,culvert discharge remains constant. Thearea decreases because the pipe does notflow full, and the velocity of flow in theculvert increases because V = Q/A. Thecritical slope is the maximum discharge.

Roughness

For the selection of the pipe roughnessvalues (n values) for flow determinationrefer to the footnotes to Table 6-17, page6-75.

Box-Culvert Flow

Flow characteristics of box culverts may bedifferent from those of pipe culverts, eventhose with the same slope, lining, and inletand outlet conditions. Flow, Q, can bedetermined as previously noted, for theconditions of inlet and outlet waterelevations.

Assuming that the water elevation of theinlet is at the top of the box and the outletis free-flowing, the difference in inflowcharacteristics between pipe and boxculverts of the same material and slope isnegligible. Box-culvert sizes can thereforebe determined by computing thecross-sectional area required for a pipe andthen desgning a box of the same material,slope and cross-sectional area.

When the water elevation is above the topof the box inlet, usc the nomograph inFigure 6-50. In this case, make trialsolutions until there is correlation betweenthe box size and pending depth.

Design of Culverts with Submerged Inlets

Submerging of the culvert inlet results inpending at-the site. The elevation of thepond surface, which will determine thedepth of submergence, is a function of the

extent of the pond, the requirement ofsafety to the structure, and the time it willtake to empty the pond. These factors aredetermined by the runoff rate, the pondvolume, and the culvert-flow rate. They arederived using the following steps:

Step 1. Determine the rate of runoff (Q)the culvert must drain or, in the case ofpending, the inlet drain capacity, Qd.

Step 2. Determine the length of the culvert.

Step 3. Determine the head on the culvert.

Step 4. Using Figure 6-49, page 6-74,determine the size and type of pipe or boxculvert required to handle the quantity offlow, Q.

To use this table, enter the nomograph(Figure 6-50) at the intersection of thelength for the type and size of culvert (forexample, point A in the nomography).Extend the line horizontally to theturning-point line (point B in thenomography), and extend the line to theculvert head, H, in feet (point C in thenomography). Find the discharge, Q, incubic feet per second, for the pipe selectedat the intersection with the discharge line.

Step 5. Compute the discharge velocity, V,in fps. Use the equation, V = Q/A. If thedischarge velocity is greater than themaximum permissible velocity for theoutfall or the height of the water, in feet,above the top of the culvert inlet is lessthan 0.022(V2) for CMP or 0.0 17(V2) forconcrete pipe or boxes, either select pipesof larger diameter or decrease the slope ofthe culvert.

Example (Submerged Inlet, UnsubmergedOutlet):

Determine the most economical pipe sizeand number of pipes required for a culvertacross an airfield. The following are knownconditions:

The outfall from the culvert is a naturaldrainage channel with dense turf in aGP soil.

Drainage 6-77

Page 175: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013,

Ž The design flow, Q, is 210 cfs.

Vol 1

Ž 42-inch and 48-inch concrete pipes areavailable.

Solution:

Step 1. Q = 210 cfs (given).

Step 2. L = 180 feet (given).

Step 3. Determine head, H.

H 42-in = 598.6 ft - (593.0= 2. 1 ft

H 48-in = 598.6 ft - (593.0= 1.6 ft

ft + 3.5 ft]

ft + 4.0 ft)

Step 4. Determine the size and number ofpipes required to handle the flow, Q.

(a) On the cast-concrete-pipe portion ofthe nomograph, draw a horizontal line fromthe intersection of the 180-ft L line and the42-in pipe line (point A) to theturning-point line (point B). From B, drawa line to an H of 2.1 ft (point C). Theintersection of this line with the “Q” portionof the nomograph shows the maximumdischarge of one 42-in pipe to be about 78cfs. For 210 cfs, three would be required.

(b) Similarly, for the 48-in pipe, 180 ftlength, and 1.6 ft H, proceed from D to Eto F and find that one 48-in pipe wouldhave a capacity discharge of about 92 cfs.Again, three would be required for 210 cfs.

Step 5. Compute the discharge velocity, V,and check for excessive outlet velocity.Check smaller pipe.

(a) Since three pipes are used, assumeeach will carry one-third the total Q or 70cfs, whichever is greater.

(b) If the pipe flows full, the exit velocityis—

(c) If the exit velocity is based on a designflow of 70 cfs, the pipe would be flowingonly partially full and the exit velocitywould be 9.2 fps. This velocity is greaterthan when the pipe flows full because theresistance to flow decreases until the pipeis flowing approximately 0.8 full.

(e) Since allowable outfall velocity is ex-ceeded and < 0.017 use three 48-inch pipes as the most economical availablesize.

Design of Pipe Culverts with Unsub-merged Inlets

The factors to be applied to the design ofthese culverts arc determined as follows:

Step 1. Determine the rate of runoff. Usethe area the culvert must drain. This willbe the required capacity, of the culvert.

Step 2. Determine culvert use. Will it beused for a road or for an airfield?

Step 3. Calculate the critical dimensionsfrom the cross sections. See Figure 6-51.Determine the length in place (LIP) and thefill critical

Step 4. Determine the largest pipe for thefill. Begin from the cross section at theoutside edge of the shoulder. Consider onlypipes that are available and for which coveris adequate.

For roadway loadings, the maximum culvertdiameter is equal to two-thirds of theminimum fill (FT from Figure 6-51, page6-79). The cover required for culvertprotection is equal to one-half the diameterof the culvert or 12 inches (whichever isgreater).

For runways and taxiways sustainingaircraft wheel loads, refer to Table 6-12,page 6-65, for the wheel loads and Table

6-78 Drainage

Page 176: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 3-8013, Vol 1

Ž

Ž

Ž

Ž

Ž

(Fill 1) = roadway elevation at the outer edge (EL1- the elevation at the toe of the slope (EL2),

(Slope horizontal distance on the Inlet side of the road) = Fill 1 x the “X” value (horizontalcomponent of the Inlet side slope ratio).

(Fill 2) = roadway elevation at the outer edge of the road on the outlet side ( EL3) – theelevatlon at the toe of the slope on the outlet end,

(Horizontal distance of the roadside slope on the outlet end) = Fill 2 x the “Y” value (horizontalcomponent of the outlet side slope ratio).

S (Slope) = the difference between EL2 and EL4 divided by the sum of S1 + TW (top width across theroad) + S2.

(Fill 3) = fill amount from the existing ground on the inlet side to the culvert inlet.

(Fill Total) = Fill 1 + Fill 3.

LIP (Length In Place) = S1 + TW + S2 + 21.

(Fill Critical) = Fill total minus DP (diameter of the pipe).

Figure 6-51. Calculating cover

Drainage 6-79

Page 177: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

6-13, page 6-66, or Table 6-14, page 6-67,for the minimum cover required.

Step 5. Determine the culvert capacity,and outlet velocity. Use values based onculvert material and slope and Table 6-17,page 6-75.

Step 6. Determine the number of culvertpipes required. Divide the area runoff, Q,by the pipe capacity, Round up to thenext whole number.

Step 7. Determine the order length (OL).The OL is calculated by multiplying thenumber of pipes (NP) times the LIP times awaste factor of 1.15, (See step 3 for theLIP and step 6 for the NP.)

Step 8. Determine the maximum permis-sible discharge velocity, Use Table6-6, page 6-44, to calculate for thechannel lining into which the culvert outletwill discharge. Determine the correct pipeto be used. Apply the following criteria inyour

Ž

calculations:

Be sure the outlet velocity is equal to orless than the maximum velocity of thechannel lining into which the culvertoutlet will discharge, If outlet velocityexceeds the soils the outlet mustbe protected against erosion.

Use the least number of culvert pipespossible to carry the total flow and stillbe consistent with the above criteria.

Example (Unsubmerged Inlet):

Determine the most economical pipe sizeand the quantity of pipe required for aculvert located under a runway, with thegeneral data cross section given below. Themaximum using aircraft weight cIass forthis example will be an SR-71C.

No headwall will be constructeddown-stream. The following are knownconditions:

• Aircraft SR-71C. (Refer to Tables 6-12and 6-13, pages 6-65 and 6-66.)

• Culvert weight type = 9.

• Q to be handled by culvert = 32 cfs.

Ž Soil type is bare SC; therefore, the maxi-mum allowable outlet velocity = 3-4 fps.

• Pipe sizes available: 24-, 30-, 36-, and42-inch CMP, 10 gage.

Referring to Figure 6-52, note that thefollowing information is required beforedesign can be accomplished:

Ž

Ž

Horizontal length of one culvert, L.

Slope of culvert pipe needed to deter-mine the flow characteristics of variouspipe diameters (see Table 6-17, page 6-75) and which is a portion of thecritical fill depth,

Critical fill depth, in order to deter-mine if the cover over the pipe meetsthe requirements of Table 6-13.

Solution:

Step 1. Determine the runoff rate. Givenfor this example, Q = 32 cfs.

Step 2. Determine airfield culvert use.

Step 3. Calculate the critical dimensions.Computations should be made in thefollowing sequence (see Figures 6-52 and6-53):

• Determine the difference in elevation be-tween the edge of the runway and theculvert upstream invert.

= 607.00 - 600.80 = 6.20 ft

• Determine the horizontal distance be-tween the culvert invert and theshoulder edge.

= F1 x X= 6.20 X 10 = 62 ft

6-80 Drainage

Page 178: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-52. Unsubmerged inlet culvert problem

Ž

(Fill 1) = roadway elevation at the outer edge (EL1 – the elevation at the toe of the slope

(Slope horizontal distance on the Inlet side of the road) = Fill 1 x the “X” value (horizontalcomponent of the inlet side slope ratio).

(Fill 2) = roadway elevation at the outer edge of the road on the outlet side (EL3) – theelevation at the toe of the slope on the outlet end.

(Horizontal distance of the roadside slope on the outlet end) = Fill 2 x the “Y” value (horizontalcomponent of the outlet side slope ratio).

S (Slope) = the difference between EL2 and EL4 divided by the sum of S, + TW (top width across theroad) + S2.

(Fill 3) = fill amount from the existing ground on the inlet side to the culvert inlet

(Fill Total) = Fill 1 + Fill 3.

LIP (Length In Place) = S1 + TW + S2 + 21.

(Fill Critical) = Fill total minus DP (diameter of the pipe).

Figure 6-53. Calculating cover (sample problem)

Drainage 6-81

Page 179: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Ž Determine the difference in elevation be-tween the edge of the runway and theculvert outlet and fill slope.

607.00 - 599.62 = 7.38 ft

• Determine the horizontal distance be-tween the edge of the runway and the in-tersection of the culvert and fill.

7.38 X 10 = 73.8 ft

• Determine the actual slope of the cul-vert.

S = E L2 - EL4S 1 + T W + S2

S = 600.8 - 599.62 1.1862 + 100 + 73.8 235.8

= 0.005 or 0.5%

Ž Determine the incremental elevation dif-ference between the elevation of theupstream invert and the invert of theculvert at the critical fill section.

0.005 ft/ft = 0.5 percent

62 X 0.005 = 0.31 ft

• Determine the depth of critical fill sec-tion.

6.2 + 0.31 = 6.51 ft (Lenglh of horizontal projection of the culvert.) Theupstream invert elevation to downstream in-vert elevation is—

LIPLIP = 62 + 100 + 73.8 + 2 = 237.8 ft:

(Round Up to 238 ft)

NOTE: These computations depict thecross section and Figure 6-53, page 6-81,summarizes the calculations.

From these calculations, it has beendetermined that—

– The actual length of the culvert is235.8 feet, rounded up to an evenvalue of 236 feet. A 2-foot projectionis added because there is to be nodownstream headwall. This gives aculvert length of 238 feet for a singlepipe.

– The slope of the culvert is 0.005 footper foot or 0.5 percent.

– The depth of fill at the critical sectionis 6.5 feet (rounded to the nearesttenth of a foot).

Step 4. Determine the largest pipe for thefill. Prepare a table as shown in Table6-18 and fill in all known values. Start byentering the largest pipe available, intothe table. Subtract Dp from total fill, F-T, toget fill critical, represents theactual cover over the pipe at the criticalsection. Compare to cover required,

To find for aircraft, refer to Table 6-12,page 6-65, which indicate that an SR-71Caircraft has a culvert weight type (WT) of 9.The CMP available is 10 gage. With thisinformation, refer to Table 6-13, page 6-66,and select chart 9, corresponding to culvertWT 9. The diameters and cover are givenin chart 9 under the 10-gage line. Startingwith the largest pipe available, 42-inch or3.5 feet, is 4.0 feet (interpolated betweenpipe diameters.) Enter this value in Table6-18. The 42-inch pipe (3.5 feet) cannot beused because its actual cover is 3.01 feetagainst a required cover of 4.0 feet. Repeatthe process using the next smaller pipeavailable, 36-inch pipe. It has a of 3.51feet and a of 3.5 feet. This pipe willwork.

Step 5. Determine the culvert capacity.Use Table 6-17, page 6-75, to find thecapacity and velocity for the 36-inch pipe.

6-82 Drainage

Page 180: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-18. Unsubmerged inlet sample data

The slope of the culvert is 0.5 percent.Entering the graph from the top (pipedameter), move down the column until youintersect with the slope in the left-handcolumn. This will slate the quantity of flowin the pipe. The velocity of flow is shownby following the respective shaded orunshaded areas down and to the left untilit ends in the velocity column, 4 feet persecond.

The 36-inch pipe has a capacity of 27.5cubic feel per second for the 0.5 percentslope. The velocity indicated is 4 feet persecond.

Step 6. Determine the number of piperequired to carry the flow by dividing thetotal (Q) of 32 cubic feet per second (step 1)by the pipe capacity, 27.5 cubic feet persecond (step 5) and rounding up to thenext whole pipe. For this example, thenumber of pipe required is 32/27.5 = 1.2or two 36-inch diameter pipes.

Step 7. The next step is determining thelength of pipe to be ordered. The orderlength is calculated by multiplying NP(Step 6) times LIP (step 3) times a wastefactor (WF). Since pieces of material willbe damaged in manufacturing, handling,transporting, and assembling, an additionalamount over the actual in-place length willbe required. This value has beendetermined to be 15 percent of the totallength of pipe required. For this project,the pipe selected will be 36 inches indiameter with a length in place of 476 feet.The length to order will be—

NP x LIP x WF2 x 476 x 1.15 = 1,094.8 ft

The pipe comes in 2-foot increments;therefore, the value of 1,094.8 is roundedup to the next even value, or 1,096 feet ofpipe.

Drainage 6-83

Page 181: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

P O N D I N G A R E A S

Ponding is the accumulation of runoff atthe inlet of a drainage structure resultingfrom the inability of the system todischarge more of the runoff than the ratedcapacity of the structure.

Military drainage structures in the TO aredesigned to discharge the runoff based onthe 2-year design storm which, bydefinition, is expected to be equaled orexceeded at least once in the design period.Thus, a storm more severe than the designstorm may occur and generate excessiverunoff, overloading the drainage structures.In anticipation of this event, design theareas around the inlets of drainagestructures to accommodate a certainamount of pending.

In some cases, due to limitations in culvertcover and space, terrain conditions, time,materials, or other conditions, a systemmay not be able to take care of the runofffrom the design storm. To provide for this,include sufficient pending areas in theoriginal plan to prevent flooding of vitalareas. The pending areas store excessrunoff until the intensity of the stormdecreases and the structure can handle theflow.

When possible, military drainage systemsarc designed to pass the runoff from thedesign storm without pending. However,some provision for pending may be made inthose areas where flooding for a period oftime will not affect the facility’s operationalstatus.

The following specifications are generallyadhered to in the design of pending areasfor military installations:

• The edge of the pond must be at least75 feet from the edge of the pavementwhen used for runway and taxiwaydesign.

• When a pond is used with road fills orembankments, the depth of the pondwill be determined by the porosity of the

fill, the amount of freeboard required toprevent overtopping of the road, theheight of the headwall and wing wall,and the time allowed for the pond toempty. When pending is anticipated,the adjacent fill side slope should bemade less steep to prevent the slough-ing of saturated fill.

The pond must be drained beforedamaging infiltration of the subgradecan occur. The actual time duringwhich pending is allowable will dependupon the type and condition of the soilin the pending area and the embank-ment. In general, this period will be nomore than four hours from the start ofthe storm.

In designing pending areas, the followingassumptions are made to simplify thecalculations and to retain satisfactoryaccuracy:

Ž A culvert discharges its design capacitybefore runoff starts to accumulate atthe inlet and form a pond.

• An increase in the head because ofpending does not increase the dischargecapacity of the culvert.

The determination of permissible volume,the preparation of runoff curves, and thesoil analysis must be done before designingpending areas to meet the above specifica-tions and assumptions.

PERMISSIBLE VOLUME

The volume of permissible pending isdetermined by the elevations of the areaavailable for such pending and thesurrounding areas. A contour map showingthe final grading plan is required tocompute the volume of permissible pending.By inspection, a contour line may beselected to provide a pending area located asafe distance or elevation from thepavement. Pending volumes may becomputed from the con tour map by theaverage-end-area method. This method is

6-84 Drainage

Page 182: Army Construction Manual FM5 430 Vol1 Entire

the average of the areas, in square feet,enclosed by two adjacent contour lines andmultiplied by the contour interval in feet.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

feet. The 64-foot contour line encloses10,000 square feet. It should be noted thatthe contours are concentric: the 66-footcontour -line area includes the areabounded by the 64-foot contour line.

where—

V = volumeA = area of

feetB = area of

feetb = vertical

in cubic feetthe first contour in square

the next contour in square

distance, in feet, betweencontours (contour interval)

As an example of computing the volume forpending, consider the contours shown inFigure 6-54. Water can be safely ponded tothe 66-foot contour line. The bottom of theinlet end of the culvert is at an elevation of62 feet. Use a planimeter, or any othermethod, to determine the total areaenclosed by each contour. In this case, the66-foot contour line encloses 25,000 square

The total volume of the pending area is—

10,000 + 35,000 = 45,000 cubic feet

A further example of the computation ofpending volumes by the average-end-areamethod is shown in Figure 6-55, page 6-86.Assume that the pending area extends tothe 68-foot contour line. Determine thevolume of the pond. The 68-foot lineencloses a total area of 30,000 square feet.

Figure 6-54. Pending area

Drainage 6-85

Page 183: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Volume 62-64 = 10,000 cubic feetPrepare a cumulative runoff curve based on

Volume 64-66 = 35,000 cubic feet

Volume 66-68 = 2 x 30,000 + 25,0002

= 55,000 cubic feet

The total volume available for pending willbe 10,000 + 35,000 + 55,000 = 100,000cubic feet, if the pending area extends tothe 68-foot contour line.

RUNOFF CURVES

TO determine the amount of water an areawill contribute to a pond, a cumulativerunoff curve must be plotted. Thefollowing example shows how such a curveis prepared:

Example:

An area has 33.3 acres, consisting of 23.3acres of impervious soil and 10 acres ofpaved surface. The weighted C value is0.75, the TOC is 13 minutes, and the loca-tion intensity is 2.2 inches per hour for a1-hour storm with a 2-year frequency.

Figure 6-55. Pending area enlarged

the-data given. Pending may be requiredreduce the culvert size.

Tabulation of Data—Rational Method

All data required to plot a cumulative

to

runoff curve, using the rational method, isshown in Table 6-19. Each column isprepared as follows:

Column 1 is a tabulation of time inminutes. Any similar combination of timeincrements can be used as long as enoughproperly spaced points are obtained to plota smooth curve. The cumulative runoffcurve is constructed by plotting time, inminutes (column 1), against volume incubic feet (column 6).

Column 2 is the product of the runoffcoefficient, C (as determined for the areausing the rational method), and the area inacres.

Column 3 is the intensity, in inches perhour, for each one of the minute values ofcolumn 1. These values are obtained fromthe standard intensity-duration curvenumber 2.2 in Figure 6-4, page 6-9. Thevalue of 2.2 is the location intensity, ininches per hour, of the 1- hour, 2-yearstorm as specified in the given conditions.

Column 4 is the rate of runoff, Q, in cfs,for the entire interval of time shown incolumn 1. It is obtained by multiplyingcolumns 2 and 3 (Q = CIA).

Column 5 is the time, in seconds, given incolumn 1.

Column 6 is the quantity of water suppliedto the pond for the time given in column 1.For the first five minutes of rainfall, thequantity of water entering the pond is givenby—

Column 6 = (column 4)(column 5)

Column 6 = (163)(300) = 48,900 cubic feet

6-86 Drainage

Page 184: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 6-19. Cumulative runoff data tabulation, rational method

After 20 minutes from the start of rainfall,the volume of water would be equal to105 x 1,200 or 126,000 cubic feet, if nowater was released from the pond.

Preparation of Cumulative Runoff Curve

The cumulative runoff curve is obtained byplotting the volume (column 6, Table 6-19)obtained by the rational method, on the ver -tical axis and the time, in minutes (column1, Table 6-19), on the horizontal axis. Thecumulative runoff curve for the data listedin Table 6-19 is shown in Figure 6-56, page6-88.

Analysis of Cumulative Runoff Curve

Based upon the data given in the problem,the flow for the culvert design shown in Fig-ure 6-55 would be determined as follows:

Q = CIA

where—

C = 0.75I = 4.9 for a TOC of 13 minutes and a

location intensity of 2,2 inches per hour forthe 1-hour, 2-year storm

A = 33.3 acres

Q = 0.75 x 4.9 x 33.3 = 122.4 cfs. Thenumber of culverts at a slope of 1.2 percent(Figure 6-55) when Q = 122.4 would be asfollows:

30-inch pipe at 24 cfs = 6 pipes36-inch pipe at 38 cfs = 4 pipes42-inch pipe at 57 cfs = 3 pipes48-inch pipe at 80 cfs = 2 pipes60-inch pipe at 140 cfs = 1 pipes

These pipes in the above sizes and quan-tities will pass the flow without pending.

ANALYSIS FOR PONDING

The safe volume for pending is 100,000cubic feet. The requirement is to reducethe flow past the outlet point by using asingle culvert and allowing pending at theinlet.

Table 6-17, page 6-75, reveals that a30-inch CMP culvert (n = 0.024) on a1.2-percent slope discharges 24 cfs. Assum-ing that the pipe always discharges at therated capacity, the cumulative discharge isa straight-line function for any time intervalwith a line passing through the origin.

Drainage 6-87

Page 185: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-56. Cumulative runoff curve

Continue these straight lines so that theyintersect thew cumulative runoff curve. Atthe point of intersection. the cumulativefunff will have equaled the cumulativeamount of water passed by the culvert.From then on, there will be no pending.

Knowing how long the pond will exist be-hind the inlet, next determine whether ornot the pending area is large enough. Fig-ure 6-56 shows that the greatest verticaldistance betweem the cumulative runoffcurve and the 30-inch cumulative dischargevolume is line P. Line P represents the max-imum volume of water ponded behind the30-inch culvert.

Measuring line P by the vertical scale usedin Figure 6-56 indicates that the maximumpending volu une will be 115,000 cubic feet.a 42 minutes the cumulative supply curveshows that 175,000 cubic feet of water havebeen supplied to the pond by the rain-

storm. At the end of 42 minutes, the30-inch culvert has theoretically been ableto discharge 60,000 cubic feet. Therefore,the difference between the quantity sup-plied (175,000 cubic feet) and the quantitydischarged (60,000 cubic feet) is 115,000cubic feet, which must still be in the pond.

In view of the fact that the safe pendingvolume is only 100,000 cubic feet, 30-inchCMP is unsatisfactory because the safepending volume would be exceeded.

Make the same calculations for 36-inch cul-vert. In this case, the pond volume will be75,000 cubic feet with a pond time of 95minutes. Since the safe pending volume of100,000 cubic feet and the 4-hour limit onthe pending time arc not exceeded the36-inch culvert is satisfactory. In addition,the excess volume of 25,000 cubic feet willbe available for storms that may exceed thedesign storm.

6-88 Drainage

Page 186: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

ADVANTAGES OF PONDING

Although pending is an added safeguardagainst the effects of storms more severethan the design storm, its primary use is asan economy measure. Pending allows forreductions in the size of culvert pipe neces-sary to handle runoff. However, if addition-al pipe or other construction is required forpending, check the additional cost againstthe savings in reduction of pipe size. Pond-ing appreciably reduces pipe sizes for areas

that have a short TOC. For longer TOCs,pending has little or no effect on pipe sizes.The use of pending as an economy measureis often restricted by the area available forpending. This area should be sufficient tosatisfy the requirements of the designstorm, It should also have enough reservecapacity to take care of storms more in-tense than the design storm, Facilities forpending should be coupled with initial grad-ing operations, if possible, to secure themost efficient use of personnel and equip-ment.

DROP INLETS AND GRATINGS

Drop inlets, vertical entrances to a culvertor a storm drain, may be used to lower theelevation of the culvert inlet below ditchelevation. This is done where fill does notprovide sufficient cover or where dischargevelocity is erosive and can be controlledonly by changing the slope. For stormdrains (underground culverts or conduitsdesigned to carry surface runoff), drop in-lets are used to collect surface runoff frompaved and turfed areas, street gutters, andditches. A typical drop inlet is shown inFigure 6-57, page 6-90.

A framework of bars, or a perforated platecalled a grating] passes the storm runoffinto a drop inlet. The grating serves asboth a filter and a cover for the inlet. Grat-ings arc shown in Figure 6-58, page 6-91.

CONSTRUCTION OF DROP INLETS ANDGRATINGS

Drop inlets should always be protected withsome type of grating. An expedient gratingcan easily be fabricated using reinforcementbars welded together. These gratingsshould be spaced to readily admit debriswhich will pass unobstructed through theculvert. A drop inlet may be constructed ofconcrete, brick, timber, or CMP sections.

Inlet grating should be fabricated of steelbars, steel plate, cast iron, or reinforcedconcrete with adequate strength to with-stand the anticipated load. The loads may

range from the weight of debris collectedover the grating to vehicle or aircraft wheelloads.

Inlet grating should be placed 0.2 footbelow the grade. This will allow for the set-tlement of the area around the grating andwill provide a sumped area to ensure com-plete drainage around the grating and posi-tive interception of surface and gutterrunoff.

To determine the proper size of grating-

1. Determine the peak rate of runoff,from the area that drains into the dropinlet. This will be the required dischargecapacity, Q, of the grating.

Q,

2. Determine the load (depth of water orhead) on the grating at times of peakrunoff. When a drop inlet is used in aditch, gutter, or pending area, the head willbe the depth of water running in the ditchor gutter, or the depth of the pond.

3. Knowing the head, H, and the designdischarge capacity, Q, refer to Table 6-20,page 6-91, to select the minimum size grat-ing required.

4. Multiply the required grating size bythe appropriate safety factor to determinethe actual grating size to use.

Drainage 6-89

Page 187: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

A safety factor of 50 percent (1.5 x totalgrating area) for paved areas and 100 per-cent (2 x total grating area) for turfed areasshould be added to the grating-area meas-urement to compensate for debris caught inthe openings.

Grating openings should be at least 18 in-ches long and should be placed parallel tothe direction of flow.

The area of the grating openings is es-timated at 50 percent of the total gratingarea. When using bars with large openings,determine the area of grating openings.

Figure 6-57. Drop inlets

6-90 Drainage

Page 188: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-58. Grating heads

MAINTENANCE OF DROP INLETS ANDGRATINGS

Drop inlets and gratings require continuousmaintenance because debris collects at theopenings. A maintenance schedule must beestablished to check and clean debris fromthe inlets and gratings. If these openingsare not kept clean, a pond could form atthe inlet, resulting in damage to nearbystructures. This damage could consist ofsaturation of the subgrade by the pond ordirect flooding of adjacent areas. Periodicmaintenance of drop inlels should includeremoving the cover and inspecting andcleaning the chamber.

Expedient drop inlets of the type shown inFigure 6-39, view (A), page 6-63, must becovered with bars, If the box is left open, itwill tend to fill with debris making cleaningdifficult, especially if a pond has developed.

Table 6-20. Discharge capacity of square grate inlets

Drainage 6-91

Page 189: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SUBSURFACE DRAINAGE

SUBSURFACE DRAINAGE CRITERIA

When surface failures prove that naturalsubsurface drainage is inadequate, it be-comes necessary to determine if a subsur-face drainage system is needed, and if so,what type to install. Generally, subsurfacedrainage may be divided into three classes:base drainage subgrade drainage, and inter-cepting drainage.

Base drainage generally consists of subsur-face drainpipes laid parallel and adjacent topavement edges with pervious material join-ing the base and the drain. Figure 6-59shows a typical section of base drainage.

Base drainage is required where frost actionoccurs in the subgrade beneath the pave-ment and where ground water rises to thebottom of the base course through naturalconditions or from ponding of surfacerunoff. Where pavement becomes temper-arily inundated and there is little possibilitythat the water will drain from the base intothe subgrade base drainage will be re-quired. Table 6-21, page 6-94, establishesthe criteria to follow in these cases.

Base drainage is also required at the lowpoint of longitudinal grades in excess of 2percent where the subgrade coefficient ofpermeability is less than 1 x 10 -3 fpm. Thecoefficient of permeability, a property ofeach soil type, is defined as the dischargevelocity at a unit hydraulic gradient. Deter-mine the coefficient of permeability experi-mentally, either by laboratory test or by anactual field test of the soil involved. Thecoefficient is expressed in units of velocitysuch as fpm or centimeters per second(cm/see). Base drainage is required if thesubgrade coefficient of permeability issmaller than the coefficient of permeabilityindicated in Table 6-22, page 6-94.

Subgrade drainage is required for per-manent construction when seasonal fluctua-tions of groundwaler may be expected torise to less than 1 foot below the bottom ofthe course. Figure 6-60, page 6-95, shows

a typical example of a subgrade drainagesection. Figure 6-61, page 6-96, will serveas a guide for spacing drains. Thesedrains, although similar to base drains,have a larger area of filter material in con-tact with the subgrade.

Intercepting drainage is required whenwater seeping into a pervious layer willraise the groundwater locally to a depth ofless than 1 foot below the bottom of thebase course. This condition is often en-countered in thin, pervious soil layers; in ex-posed rock cuts; or in seepage fromsprings. A typical intercepting drainage sec-tion is shown in Figure 6-62, page 6-97.

SUBSURFACE DRAINAGE TECHNIQUES

Subsurface water can be controlled througha combination of techniques. The techni-ques and combinations depend on theconditions existing in the area to bedrained. The techniques that follow shouldbe considered when planning and designingsubsurface drainage.

Depth of Base Course

The base course may be built up to a speci-fied depth above the groundwater table.Generally, the finished grade must be atleast 5 feet above the mean groundwatertable level. This technique is feasiblewhen—

Ž A gravity drainage system is impractical.

Ž The condition to be controlled is limitedto a small area such as a narrow swampcrossing.

• Adequate base-course material is avail-able.

Deep Ditch

Where ditches will not interfere with opera-tions or become a hazard to traffic, deep V-ditches with free outfall may be feasible.Easily built and readily enlarged, theseditches provide positive interception and

6-92 Drainage

Page 190: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-59. Typical base drainage installations

drainage of subsurface water before itreaches the area to be protected. Erosion,maintenance, traffic, and right-of-way arefactors to be considered before using thissolution,

Natural Drainage Channels

Where possible and practical, water in exist-ing natural drainage channels should belowered when corresponding effectivelowering of the groundwater table willoccur. This technique may be particularlyeffective in pervious soil.

Drainage 6-93

Page 191: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-801 3, Vol 1

Table 6-21. Base drainage criteria for K

Blind Drains

Blind or French drains are constructed byfilling a ditch or trench with broken orcrushed rock. The top surface of the rockmay be left exposed so that the trench willact as a combination surface and subsur-face drain, or the rock may be covered by arelatively impervious soil so that no surfacewater can penetrate. The latter is thegeneral practice. In general, French drainsare not recommended for permanent con-struction because they tend to silt up overtime, In TO construction,often used as a substituteopen-joint pipe or on filterwith such piping.

these drains arefor perforated ormaterials used

Subsurface Pipe

In cases where a V-type or other open-ditchtype drainage system is not practical, itmay be necessary to resort to constructionof subsurface drainage. Failure of the sub-surface system stemming from impropercontrol of the grade, the bedding, the pipeplacement, the placement of filter material,or other installation work gives no warningprior to failure. Such failure is extremelydifficult to repair when discovered.

The most common form of subsurface drain-age is perforated pipe. Where the perfora-tions do not extend completely around thecircumference of the pipe, the pipe is gener-ally laid with the holes down and the jointsclosed. Materials used in manufacturingthis type of pipe arc corrugated metal, castiron, vitrified clay, nonreinforced concrete,bituminized fiber, and asbestos cement.

Bell and spigot pipes can be laid with openjoin ts. If the filter material has been proper-ly designed, collars are not needed over thejoints. This type of pipe is generally madeof vitrified clay, nonreinforced concrete, orcast iron.

Table 6-22. Drainage characteristics of soil

6-94 Drainage

Page 192: Army Construction Manual FM5 430 Vol1 Entire

Figure 6-60. Typical subgrade drainage installation

Porous concrete pipe is laid with closedjoints. It collects water by seepage throughthe wall of the pipe and should not be usedwhere sulfated waters may cause disintegra-tion of the concrete.

Farm tile is laid with butt joints slightlyseparated to permit collection of waterthrough the joint. Because of its low resis-tance to high-impact loads, farm tile is notrecommended for use on airfields.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Materials commonly used in manufacturingfarm tile are clay or concrete.

Combination Drainage System

Combination drains, which attempt to hand-le both surface runoff and subsurface waterin the same pipe system, are recommended.Surface runoff often carries sediment andsoil from the drained area into the system.This clogs the system and causes flow stop-page. For this reason, subsurface drainagesystems using some form of piping are

Drainage 6-95

Page 193: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-80133 Vol 1

Figure 6-61. Types of subsurface drainage

generally sealed so that surface runoff can- PIPE-LAYING CRITERIAnot enter. The only drainage system whichwill satisfactorily handle both surface

There are essentially four different types of

runoff and subsurface water is the open pipe available for subsurface drainage, as

channel or ditch.previously mentioned. They should be laidaccording to the following specifications:

6-96 Drainage

Page 194: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-62. Typical intercepting drainage installations

• The minimum slope for subdrainagepipe is a 0.15-foot drop in elevation per100 feet of length, The elevation of apipe at any particular location is gener-ally specified by the invert elevation, inwhich the invert is defined as the lowestpoint in the internal cross section of thepipe at the particular location.

Ž Manholes should be provided at inter-vals of not more than 1,000 feet, withflushing risers between manholes andat dead ends as shown in Figure 6-60,page 6-95.

• Pipe should be at least 6 inches in dia-meter with 6-inch pipe being used forall drains. With long intercepting lines

Drainage 6-97

Page 195: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

or extremely severe groundwater condi-tions, 8-inch or larger pipe may benecessary.

Ž The center of subgrade drains should belocated at least 1 foot below the bottomof the base course and not less than 1foot below the groundwater table. Nor-mally, subgrade drains are requiredonly at the edges of pavement areaswhere the soil is pervious and drainswell. However, local groundwater condi-tions and base and subgrade soil char-acteristics may require closer spacing ofthe drains, When the drain dischargesinto a culvert or any considerably largerpipe, it should discharge above thewater level in the larger pipe. When thedrain discharges into a pipe of equal oronly slightly larger size, it is generallybetter 10 bring the drain in above thereceiving drain and make a vertical con-nection between the two. This will pre -vent the water from backing up in thedrainage pipe since these pipes rarelyflow full

Ž When the impervious layer is at areasonable depth, intercepting drainsshould bwe placed in the imperviouslayer below the intercepted seepagestratum. The quantity of water col-lected by an intercepting drain is dif-ficult to determine, but in general, 6-inch pipe is sufficient for lengths up1,000 feet.

VERTICAL WELLS

Vertical wells arc sometimes constructedallow trapped subsurface water to passthrough an impervious soil or rock layer

to

to

toa lower, freely draining soil layer. If drain-age is obstructed, additional wells are builtor the pocket is drained with an easilymaintained lateral subdrain system. Verti-cal wells S are often used in northern lati-tudes where deep freezing is common.They permit fast runoff from melting snowto get through the frozen soil and reach apervious stratum. Under such conditions,the bottoms of these wells are treated with

calcium chloride or a layer of hay toprevent freezing.

FILTER MATERIAL

A layer of filter material approximately 6inches deep should be placed around allsubsurface piping systems. The selection ofthe proper filter material is very importantsince it determines, to a great extent, thesuccess or failure of the drainage system.The improper selection of filter material cancause the drainage system to become in-operative in one of three ways:

• The pipe may become clogged throughinfiltration of small soil particles.

• Particles in the protected soil may moveinto or through the filters, causing in-stability of the surface.

• Free groundwater may not be able toreach the pipe.

Criteria have been developed, based uponthe mechanical-analysis soil curve, to pre-vent the above failures.

A great deal can be learned about gradationcharacteristics of a particular soil by observ-ing the soil curves on the mechanicalanalysis chart. Well-graded soils generallyhave a smooth, grain-size curve with grad-ual changes of slope. Poorly-graded, uni-form soils generally have a very steep grain-size curve. Skip-graded soils have a grain-size curve with a characteristic hump in it.The filter material in skip-graded soil tendsto segregate during placement. The grain-size curves in Figure 6-63 show variousgradation characteristics.

A coefficient of uniformity, value of lessthan 20 is desirable to prevent segregationof coarse and fine-grain particles, especiallyduring placement. For the same reason,skip-graded material should not be used.Placing the filter material while it is wetcan reduce segregation.

Filter material can clog a pipe by movingthrough the perforations or openings.

6-98 Drainage

Page 196: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-63. Mechanical analysis curves for filter material

Prevent this by using the following specifica-tions:

For a slotted opening—

For a circular hole—

Use the following methods to prevent par-ticles from the protected soil from movinginto or through the filter or filters:

and

To permit free water to reach the pipe, thefilter material must be many times morepervious than the protected soil. This con-dition is fulfilled when—

If it is not possible to secure a mechanicalanalysis of available filter materials andprotected soil, concrete sand with mechani-cal-analysis limits as shown in Figure 6-63may be used. Experience has indicatedthat a well-graded concrete sand is satisfac-tory as a filter material in most sandy, siltysoils.

Drainage 6-99

Page 197: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

STEPS IN FILTER DESIGN

Obtain a mechanical analysis of each sandysoil from several readily available sources.Obtain a mechanical analysis of the sub-grade soil (protected soil) at the bottom ofthe trench which will be in contact with thefilter material.

Plot the mechanical analysis of each soil onsemilogarithm paper and draw a curve foreach soil.

From the mechanical-analysis curve foreach soil, determine the diameter, in mil-limeters (mm), of the particle of eachsample. Ten percent of these particles arefiner (by weight) The subscript “10”indicates the percentage, by weight, of thesoil sample which is finer (smaller indiameter) than the particle in sizeSimilarly, determine the and particle size for each soil.

Determine the slot width or hole diameter,in millimeters, of the type of pipe to beused.

Check the coefficient of uniformity, CU, toensure—

Check the design criteria for clogging ofpipe openings to ensure—

(1)

(2)

Check the design criteria for movement ofparticles from the protected soil (subgrade)through the filter material to ensure—

(1)

(2)

Check the design criteria for relative per-viousness to ensure—

Select that filter material which best meetsthe above criteria.

Install pipe to grade, bedded and sur-rounded with the selected filter material asshown in Figure 6-58, 6-59, or 6-60, pages6-91, 6-93, and 6-95, respectively.

SELECTING FILTER MATERIALS

Filter material should be selected with aview toward the simplest construction andthe lowest cost. To further this end, try touse only one layer. If several layers of filtermaterial are required, one layer should beconfined to the region around the pipe open-ings and another layer placed between itand the protected soil, as shown in Figure6-59, page 6-93. In this case, the designerselects a filter material for use around thepipe according to the filter design formulas.The second filter material is then designedto protect both the inner filter material andthe surrounding soils. In other words, thedesign of a multilayer filter for a subdrainsystem should proceed outward from the in-side filter material to the subgrade soilbeing protected.

Example (Selecting Filter Material):

A suitable filter material must be selectedfor a 6-inch pipe with 1/4-inch diameterperforations to protect a subgrade soil withan E curve (shown in Figure 6-63, page6-99). The soils represented by curves Aand B are readily available from local bor-row pits.

Tabulate data from the mechanical-analysiscurves.

6-100 Drainage

Page 198: Army Construction Manual FM5 430 Vol1 Entire

Check the coefficient of uniformity of bothsoils.

Soil A

Soil B

Thus, both soils A and B satisfy the requirement that the coefficient of uniformity beless than 20.

Apply design criteria to soil A,

Should be 5 toprevent movementsubgrade soilsthrough the filter.

2.20.09

= 24 .4 which is not < 5.

Soil A is unsuitable because movement of

of

the subgrade soil through the filter materialis possible.

Apply design criteria to

(filter)(protected soil)

soil B.

Should be 5 toprevent movement ofsubgrade soilsthrough the filter.

which is < 5.

(filter) Should be 25 to(protected soil) prevent movement of

subgrade soilsthrough the filter.

1.00042 = 2 3 . 8 which is < 25.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Should be 5 topermit water move-ment through thefilter.

0.300.01

= 30 which is > 5.

Should be > 1.0to prevent cloggingof the pipe.

Note that the soil particle size is usuallygiven in millimeters, while the hole size isusually given in inches. The two dimen-sions must be expressed in compatibleunits before the preceding formula is used.To make this conversion, multiply the sizeof the pipe perforations, in inches, by 25.4which represents the number of millimetersper inch. For example, with soil B underdiscussion—

which is > 1.0.

Thus, soil B satisfies all the criteria for agood filter material while soil A dots not.

INSTALLATION OF A SUBDRAINAGESYSTEM

The most efficient and most practical typeof subdrainage system is one which ade-quately performs the operations for which itwas intended and, in addition, was installedwith the care and skill consistent with itspurpose. Any attempt to lower the qualityof construction or to usc a sketchy or inade-quate subdrainage system can result in dis-astrous failures. Conversely, any attemptto install an elaborate system of under-ground piping where a simple V ditchwould serve as well is inadvisable.

Drainage 6-101

Page 199: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SECTION IV. SURFACE DRAINAGE DESIGN IN ARCTIC ANDSUBARCTIC REGIONS

APPLICABILITY

This section discusses the problems in-volved in the design of drainage facilities inarctic and subarctic regions. While thedesign data presen ted has been developedprimarily for Alaska, the methods used aregenerally applicable to other arctic and sub-arctic regions.

Arctic

Arctic is defined as the northern regionwhich the mean temperature for thewarmest month is 50º Fahrenheit (F) orless, and the mean annual temperature

in

i sbelow 32º F. In general, the arctic coin-cides with the tundra region north of thelimits of trees.

Subarctic

Subarctic is defined as the region adjacentto the arctic where the mean temperature is32° F or below for the coldest month and50° F or above for the warmest month, andwhere less than four months have a meantemperature above 50º F. In general, the

subarctic coincides with the circumpolarbelt of dominant coniferous forests.

HYDRAULIC CRITERIA FOR COLDCLIMATES

Rainfall

A study of rainfall intensity-frequency datarecorded at arctic stations indicates a con-siderable variance between the average in-tensity of rainfall for a period of one hourand the average precipitation rates of com-parable frequency for a duration of lessthan one hour. This is evidenced whencompared with similar rainfall in the con-tinental United States (CONUS). Evenwithin the area of Alaska, there was anoticeable difference between the rains atJuneau and those at Fairbanks. Thehigher values for rainfall intensity wereused to develop design intensity-duration(supply) curves, which are shown in Figure6-64, For design purposes, a minimumrainfall rate of 0.2 in/hr is recommended,even where maps of intensity-frequency

Figure 6-64.

6-102 Drainage

Intensity-duration curves, arctic and subarctic

Page 200: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Design-storm index. One-hour rainfall inten-sities having various average frequencies ofoccurrence in the arctic and subarcticregions of Alaska are shown on maps in Fig-ure 6-65, page 6-104. This figure, onwhich rainfall depth curves are superim-posed, is known as a design-storm index.The curves are labeled by the one-houramounts of rainfall that are represented;these, in turn, are coordinated with the in-tensity-duration or supply curves of Figure6-12, page 6-17, Figures 6-64 and 6-65,used in combination, provide a meanswhereby rainfall intensities sufficien tly ac-curate for runoff computations for any dura-tion may readily be determined.

Elevaton and physiographic orientation.Present information is insufficient to estab-lish quantitative conclusions of the effectsof elevation and physiographic orientationfor all locations. At the time a site isunder investigation, it would be helpful toobtain even a short record of rainfall there.Such a record may be compared with theconcurrent portion of a nearby long recordand proper frequency values assigned toevents in the short record, For example, atemporary gage might have a maximumhourly value of 0.60 inch some summer,and the same storm might produce thesummer’s maximum hourly value of 0.40 ata nearby long-record station. Similar com-parison of other storms for the brief parallelrecord might confirm the ratio of 6 to 4 asan expression of the difference in the orien-tation, exposure, and elevation of the twostations. This ratio could then be appliedto the known 2-year, 1-hour value of thelong-record station to get the estimated2-year, 1-hour value for the short-recordstation, If the long-record station has a2-year, 1-hour value for the constructionsite, it would be 6/4 of 0.5 or 0.75. Arran-gements usually can be made for borrowtnga rain gauge for temporary use from themeteorological agency of the area in whichthe project is to be located.

Infiltration

In permafrost areas, infiltration for designpurposes should be considered zero. In

other areas, a good guide may be obtainedwhen test borings are made, Values normal-ly would not exceed about 0.5 inch perhour for coarse sands and gravels andwould be as low as 0.1 inch per hour forclayey soils with low permeability.

STORM-DRAIN DESIGN

The type and capacity of storm-drainfacilities required are determined primarilyby the promptness with which design-stormrunoff must be removed in order to avoidserious interruption or hazard in the use ofimportant operational areas as well asprevent serious damage to pavement sub-grades. It is presumed that all phases ofsite reconnaissance have been carefully com-pleted and that information is availablewhich shows topography, natural drainagepatterns, groundwater conditions, andseasonal frost and permafrost levels.

Basic Considerations

Even though rainfall magnitudes are smallin arctic and subarctic regions, drainage isan important factor in selecting an airfieldsite and planning the construction. Theplanner should be aware of several featuresrelated to drainage in order to ensure a suc-cessful design. These features include thefollowing:

• Sites should be selected in areas wherecuts or the placement of base-coursefills will not intercept or block obviousexisting natural drainage ways,

• Areas with fine-textured, frost-suscep-tible soils should be avoided, if possible,In arctic and subarctic regions, mostsoils are of single-grain structure with avery small percentage of clay. As a con-sequence, cohesive forces between grainparticles are very small and the materialerodes easily. Frozen, fine-textured soilprofiles may also contain large amountsof ice lenses and wedges.

• If the upper surface of the permafrostlayer is deep and if provisions are madefor lower temperatures, design featuresof a drainage system may be similar to

Drainage 6-103

Page 201: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

NOTES:

1. Observation of rainfall at National Weather Service stations provides the basic data for this figure. Thesestations are not located in the more elevated regions; consequently, wide deviations from the charted values mayexist at altitudes above 2,500 feet.

2. The influence of local topographic characteristics should be taken into account and evaluated at the time ofdrainage design.

3. The lines of equal half-hour rainfall magnitudes correspond to the intensity-duration curves shown in Figure 6-64.

4. The once-in-50-years amount can be estimated by multiplying the once-in-2-years amount by the factor 2.2

Figure 6-65. Design-storm index for Alaska

6-104 Drainage

............ ". ' ... " ........... ' ......... ':.:::.:'.:.:.' ..

Once In 2 years Once In 5 years

Once In 10 years Once In 20 years

Legend

Approximate southern limit of the Arctic Approximate southern limit of the permafrost Approximate southern limit of area covered

Page 202: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

those used in frost regions of the UnitedStates.

• The flow of water in a drainage channelhas an accelerating effect on the thaw-ing of frozen ground. This may causethe surface of the permafrost to dip con-siderably beneath streams or channelswhich convey water. Bank sloughingand significant changes in channelgrades become prominent. Sloughing isoften manifested by wide cracks parallel-ing the ditches. For this reason,drainage ditches should be located asfar as practicable from runway and roadshoulders.

• In many subarctic regions, freeingdrainage channels of drifted snow be-comes a significant task before breakupeach spring. In these areas, it is ad-vantageous to have ditch shapes andslopes sufficiently wide and flat to ac-commodate heavy snow-moving equip-ment. In other locations where flow comtinues year round, narrow, deep ditchesare preferable to avoid icings.

• Large, cut sections should be avoided inplanning the drainage layout. Thawedzones or water-bearing strata may be encountered and later cause seriousicings. Vegetative cover in permafrostareas should be preserved to the maxi-mum degree practicable. Where dis-turbed, it should be restored as soon asconstruction permits,

• Inlets to closed conduits are commonlysealed before freeze-up and openedprior to breakup each spring.

• Fine-grained soils immediately above areceding frost zone arc very unstable.Consequently much sliding and cavingis to be expected on unprotected ditchside slopes in such soils.

• Locating ditches over areas where per-mafrost lies on a steep slope should beavoided if possible. Slides may occurbecause of thawing and consequent wet-

ting of the soil at the interface betweenfrozen and unfrozen ground.

• Maintenance equipment for drainagefacilities should include heavy snow-removing apparatus and a steam boilerwith accessories for steam thawing ofstructures which have become cloggedwith ice. Pipes for this purpose areoften fastened inside the upper portionsof culverts prior to their placement.

Grading

Proper grading is a very important factorcontributing to the success of a drainagesystem. The development of grading anddrainage plans must be carefully coordin-ated. In arctic and subarctic regions, it isnecessary to eliminate soft, soggy areas.

Temporary Storage

Trunk drains and laterals should have suffi-cient capacity to accommodate the projectdesign runoff. Do not consider supplemen-tary pending above the drain inlets in air-field drainage designs for the arctics andsubarctic. Formulate plans in sufficientdetail to avoid flooding even during the timeof actual construction.

ICINGS

An icing is an irregular sheet or field of icewith no uniformity as to shape, thickness,or size. All icings are similar with regardto laminated structures, indicating that ir-respective of shape, thickness, size, orcause, the actual process of formation isthe same. Thin films of water traverse overlayers of ice or other material and, when ex-posed to the cold air, freeze and form thefirst or an additional layer of ice. As waterflow continues, the process is repeated, andan icing with horizontal laminations con-tinues to grow until either the source ofwater supply is depleted or warmer weatherbegins.

Types of Icings

For the purpose of analysis, icings may bedivided into three groups, dependingon the nature of the source of water

Drainage

largely

6-105

Page 203: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

supply For icings formed along rivers orstreams and adjacent areas having a sourceof water above or below the riverbed, theterm river icing applies. If the source isIrom groundwater flow above permafrost,ground icing is the term most commonlyused This term should not be confusedwith ground ice. which is often encounteredin the arctic and subarctic as deposits infine-graincd soils. The term spring icingshould be confined to when the source ofwa ter is from subpermafrost levels or sub-permafrost water under hydrostatic pres-sure. Spring icings are commonly largeand thick. Human activity can disturb theground regime sufficiently to cause or ac-celerate the formation of all types of icings.

River icings. Most arctic and subarcticstreams carry large loads of sediment whichare not fed into the channels in uniformquantities Consequently, the rivers arequite wide and relatively shallow. Manyrivers have a braided pattern of severalsmaller streams within the confines of themain channels. These streams frequentlyshift in transverse position and often do soduring one period of high flow. Winter flowis ordinarily very small and shallow. Freez-ing penetrates to the bottom of shallowstreams quite readily, but the river dis- -charge continues as groundwater flowbeneath the riverbed. Because of thermaleffects of flowing water, the soil belowstreambeds is unfrozen to greater depthsthan soil located elsewhere Consequently,It here is a large space for groundwaterstorage and flow above the permafrost andbelow all riverbeds. The head motivatingground water flow is ordinarily quite largeand can result in large pressures above sec-it ions where the groundwater flow isretarded.

Groundwater-flow retardation is a naturalprocess at many river sections because riverbeds arc not homogeneous in water-carry -ing capacity. Freezing of the water reduceschannel area and capacity in some sectionsmore than in others. The formation ofanchor ice on the bottom of the streambedresults in fur her constriction of the chan-nel cross-section area. The water then

finds avenues of escape to the top of the icevia weak points, cracks, and fissures.Here, exposed to the cold atmosphere, thewater quickly freezes in thin sheets. Thisaction is progressive, and icing continues toincrease in thickness until the supply ofwater is exhausted or finds a new outlet, oruntil the beginning of warmer weather. Abridge may shade the streambed and alsoprevent the deposition of snow. Freezingthen would be more rapid beneath thebridge than at either upstream or down-stream locations. Subsequent penetrationsof frost would diminish groundwater -flowcapacity at the bridge section and inducethe formation of an icing above or at thesite. These icings can be of various shapesand sizes, depending upon the valley topog-raphy, the depth of the snow, the intensityof cold, the water supply, and other factors.

Ground icings. Ground icings may take theform of mounds having considerable thick-ness but small areas. They may also formas crustations if groundwater flow is in-duced to the surface at points which arenot of great lateral spacing but are of aboutequal elevation, In addition to a supply ofwater, there is another requisite to the for-mation of an icing—an area where thewater can be exposed to the cold atmos-phere. A pavement kept clear of snow of-fers an excellent site over which flowingwater can spread out into a thin film andthen freeze. Icings from groundwatcr abovethe permafrost arc not likely to occur in thearctic, as the permafrost there is too closeto the surface to permit any appreciablestorage in the active layer. This occurrenceis most severe in the southern zones of thesubarctic and on slopes which face south.Groundwater flow may be induced to thesurface in various ways. It is not essentialthat the seasonal frost reach the perma-frost, although this very effectively blocksgroundwater flow. Partial freezing of the ac-tive layer reduces the area of the sectionwhich ground water must pass. The path ofleast resistance may lead to the groundsurface via a frost crack or fissure orthrough holes which have previously beenmade by burrowing animals Water comingto the surface in this way may flow

6-106 Drainage

Page 204: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

considerable distances down slopes beneatha snow blanket without freezing.

Various met hods have been tried to preventthe occurrence of such icings. Some ofthese have met with partial success. Thefrost belt or dam has been advocated byRussian investigators, but this method iseffective for only a few years. The thawingin summer is accelerated at the site of thefrost dam, and eventually the permafrostdegrades sufficiently to permit groundwaterflow below the frost dam. Fences and bar-riers have been used quite effectively underspecial circumstances.

Spring icings. Icings that occur from ar-tesian, subpermafrost water and springs areordinarily quilt thick and cover consider-able area. Reference is often made to theicing in the Momy River Valley of Siberia.This spring icing is about 15 miles longand 3 miles wide, with an average thick-ness of about 12 feet. It does not melt andform each year. Spring icings can be con-trolled quite readily. The temperature ofthe water emerging from the ground is or-dinarily quite high and the water does notfreeze quickly if confined to a conduit. Insome cases, an insulated conduit may be re-quired to convey the spring water to loca-tions where the formation of icing will dono damage.

Measures Against Icings

River icings. In the case of river icings,depths to permafrost are ordinarily toolarge to be blocked effectively by acceleratedfreezing such as is induced by the frostdam or- bell, In addition, the subbed riverflow is often in excess of what can be

stored as ice above the location of thebridge to be protected. The control of rivericings then must be concerned with an in-sulation of streambeds at the critical sec-tion.

Ground icings. Ground icings can be con-trolled to some extent by inducing the iceto form upstream from the site in question.This can be accomplished by the installa-tion of frost belts. In open terrain, somesuccess can be achieved by merely keepingsnow removed from a strip crossing the af-fected area in a direction transverse togroundwater flow. Groundwater flow willbe blocked by freezing and forced to the sur-face upstream from the cleared area. Thesnow-free area also provides a cold spaceon which surface flow can spread out andfreeze. If necessary, the depth of stored icecan be increased by erecting some barrierto the flow, such as an ordinary wooden-stave snow fence on top of the ice initiallyformed at the site of the frost belt. Be-cause the process employs the removal ofsnow, it is essential to shift the position ofthe belt from year to year in order not tounduly influence the depth to permafrost.In timbered regions, it is obviously neces-sary to maintain the frost belt at one loca-tion to save the expense of tree removal.

Spring icings. If the source of water form-ing the icing is a spring, then it is neces-sary to resort to drainage or diversion tocontrol the occurrence. This sometimes re-quires insulated channels. In the case ofsprings, flows are ordinarily too large to per-mit a storage of icc at or upstream from thesite.

FORDS, DIPS, CAUSEWAYS, AND BRIDGES

FORDS situation, and the terrain configuration

A ford is a shallow place in a waterwaymake its use necessary and practical.

where the bottom, either naturally or byhuman improvement, permits the passage

An increase in water depth can close a fordfor a considerable time. Streams in moun-

of personnel and vehicles. A ford is used tainous and desert country are subject toinstead of a bridge when time limitations,the lack of structural materials, the tactical

sudden changes in depth. The increase in

Drainage 6-107

Page 205: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

depth can be so sudden as to endanger per-sonnel or vehicles in the ford.

Stream bottoms can be of such materialthat much effort is required to make fordsusable.

Reconnaissance

Route reconnaissance should include theselection of possible ford sites. Special em-phasis is placed on the requirements to bediscussed in this section, Ford reconnais-sance and required reports are covered inFM 5-36.

Requirements

The characteristics of a good ford are aslow current (usually less than 2 miles perhour); low, sloping banks; good approaches;and a uniformly increasing bottom depthwith a firm bottom material. Requirementsof width depth, and bank slopes for fordsare given in Table 6-23.

Location. A desirable location for a ford isin the reach of the stream between bends.At this location, the bottom depth is con-stant between the banks with only a slightchannel in the center. The influence of

ly adaptable for improvement. In addition,the variation in the shape of the banks isnot as pronounced in the reach area as itis at the bend.

Bottom Material. For a natural ford, the bot-tom material should be hard, durable, andinterlocking. Such material will resist cut-ting by wheeled traffic and erosion. Thegeneral terrain will determine the bottomcondition, as follows:

Ž In mountainous country, suddenfreshet floods can transport largeboulders and stones along the bottom.This material is deposited at the pass-ing of high water or at locations wherethe widening of the stream reduces thevelocity. It may be necessary to removethis material before traffic can cross theford,

• In terrain of moderate or gentle slopes,the velocity will tend to prevent deposi -tion of fine material. This tendency andthe scouring action of the water willleave a good, firm bottom. The bottommaterial may be disturbed by traffic andwill require protection.

river action on possible fording locations is Ž In slightly sloping or flat terrain,shown in Figure 6-66. Because of the in-creased velocity of the water, bends result

streams meander and have low velocity.

in a deep channel that is difficult to im-In addition, there is sometimes a high

prove. In the reach, the center channel iswater table. In such cases, the bottom

not so deep or sharp and therefore is readi-material may be very soft. Such

Table 6-23. Requirements for military fords

6-108 Drainage

Page 206: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

material will require a completely im-proved ford with special emphasis onbottom requirements, Timber, lumber,matting, gravel, or gabions can be usedto improve trafficabilty.

High-Water Determination. Table 6-23 indi-cates that a maximum water depth of 2 feetis allowable for truck traffic. To ensuremaximum usc of the ford, it is necessary todetermine the depth at which the streamwill flow at frequently recurring times. Es-

in Figure 6-67, page 6-110, can be made bydirect stream observation, as follows:

Base Flow. Base flow is the normal flowthat occurs in a stream when there hasbeen no recent rain. The depth of this flowis dependent upon the quantity ofground water.

High-Water Flow. During the year, manyrainfalls normally occur that cause flowsabove the base level, The velocity of such

timates of various depths of flow, as shown flows generates a slight erosion cut, as

Figure 6-66. River action

Drainage 6-109

Page 207: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-67. Stream cross section

shown in Figure 6-67. The occurrence ofsuch flows tends to prevent the growth ofvegetation. Since these flows can occurwith relative frequency during the year, thedepth of these flows could control the useof the ford. In the event the depth isgreater in places than the fording depth oftrucks (see Table 6-23, page 6-108), it maybe necessary to fill these gaps with rock orgravel, However, such filling might causethe velocity of flow over the ford to be in-creased to the point that vehicles wouldhave difficulty using the ford.

Flood Flow. In the absence of records, it isnecessary to check stream banks forevidence of floodwater levels. The highestlevel of flood that occurs within a period oftwo years is of particular interest. Thebend of a stream, especially with a highbank on the outside of the bend, wouldshow an erosion cut that can be used todetermine the flood level, as shown in Fig-ure 6-67.

Approaches. Carefully note the height ofthe bank and the type of soil. This informa-tion helps to determine construction require-ments.

Stream Velocity. The normal stream velocityat the fording site should not exceed 3 fps.

This velocity would, in most cases, occur atlow or moderate levels.

Cross Section. Make a cross section of aford location similar to Figure 6-66, page6-109 and Figure 6-67. Include full detailsof bank slopes, bottom slopes, bottom varia-tions, and water depth. In addition, deter-mine the average velocity of the streamfrom measurements taken at equal intervalsacross the stream.

Channel Condition. Make a record of thecharacter of the streambed. Include vegeta-tion density and type, whether or not thechannel is scoured, and the type of soil.This information will determine the value ofManning’s n.

CONSTRUCTION

Two phases of construction are required forfords—the development of the approachesand the preparation of the bottom.

The maximum slopes for ford approachesshould be as recommended in Table 6-23.Place material cut from the banks off to theside and not in the stream, where it mayform an obstruction. Because traffic willwet the slopes and cause eventual deteriora-tion, provision should be made for protect-ing the surface.

6-110 Drainage

Page 208: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Ford-bottom preparation will depend uponsite conditions. Fill short, deep gaps withrock or gravel, preferably retained by wiremesh. Soft, mud bottoms can be improvedby covering the bottom first with willow,brush mattresses, or timbers, and sub-sequently with metal planking, rock, orcoarse gravel. Even a hard and tenaciousbottom deteriorates under traffic conditionsand requires protective maintenance.

Consider these factors when raising the bot-tom of the ford:

• The depth upstream from the ford in-creases in proportion to the amount ofrise of the bottom of the ford.

• The velocity of flow over the ford in-creases at an increased fording depth sothat vehicles may be difficult to operateand control.

MARKING

Place marking posts at each end of the fordand at as many intermediate points as maybe necessary. Mark a post at each endwith an index to indicate depth. Warningnotices should be clearly and prominentlyplaced to alert drivers that flooding canoccur suddenly and without warning.

MAINTENANCE

Examine fords after each flooding. Repairscour damage upstream and downstreamwith riprap, Remove boulders and otherdebris to provide a clear passage forvehicles,

DIPS

Dips are paved fords used for the crossingof dry, wide, and shallow arroyos in semi-arid regions subject to flash floods.

Reconnaissance

The preferred location of a dip is in thestraight run of an arroyo or wash, Deter-mine the width between the banks and thetop elevation of the banks. In addition,check the area above the dip site to deter-mine if pending will occur and to what level.

Determine the type of soil in the banks andbottom for construction requirements. Inaddition, note the size and type of bottomrock. This type of information gives an in-dication of the volume and velocity of flashfloods which move or carry large material.

Investigate the area, especially the banks,to determine the general flash-flood highwatermark. This information on the area ofthe waterway, along with an approximationof velocity as indicated by the rock or otherdebris on the bottom, gives some indicationof the volume of flow. This information willbe necessary if bridging is required.

Construction

The subgrade should be of erosion-resistantmaterial or a rock-compacted base, and itshould be set between the cutoff retainingwalls. The pavement should be of concreteor compacted macadam. The general con-struction is shown in Figure 6-68.

Other factors of importance are as follows:

• The site should be in the reach of thestream and well away from any bends.There is more erosion in bends than instraight stretches. If a very severe floodoccurred, a structure placed in a bendmight be destroyed.

• The structure should be set at rightangles to the flow to reduce scour.

Figure 6-68. Cross section of dip section

Drainage 6-111

Page 209: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Ž The structure must be set at true dry-streambed level to avoid scour erosionor silting. Under no circumstancesshould the structure be set above dry-streambed level.

Marking

The marking for dips is the same as forfords.

Maintenance

Dips, like fords, must be examined aftereach flooding, and scour damage upstreamand downstream should be repaired withriprap, Remove boulders and other debris.When macadam is used, it can be an-ticipated that holes may be scoured in theroadway. Consider stockpiling rock ad-jacent to the area for immediate main-tenance repair.

CAUSEWAYS

When it is essential to keep a roadway openduring floods of medium intensity, a raisedcauseway can be used in place of a ford ordip, This type of structure must be well

sited, carefully designed to pass the flow,and strongly built, It must incorporate asufficient waterway at streambed level topermit the passage of the design volume offlow before the flood level reaches the top ofthe structure. A typical design is shown inFigure 6-69, The main design features of acauseway follow.

Cross-Sectional Area

A sufficient cross-sectional area must beprovided to ensure that the flood level willnot submerge the structure. Consider thefollowing basic elements:

• The size and number of culverts orother elements must be sufficient topass the flow. When the water elevationupstream and downstream is above theculvert crown, pipe equations should beused for flow design,

• The inverts or lowest parts of the cul-verts must be set at streambed level.

Ž The cover over the stream must be suffi-cient to protect the waterway againsttraffic loads,

Figure 6-69. Overflow (causeway)

6-112 Drainage

Page 210: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Embankment

Protect both the upstream and downstreamfaces of the embankment against scour anderosion. Heavy flooding or overtopping ofthe structure will require complete protec-tion in the form of a concrete or rock-gabion facing. To further prevent excessivescour and erosion, carry the protectivefacings below the streambed and providethem with aprons. Anchor the ends of thestructure securely into the banks in such away that there is minimum obstruction towater flow.

Guardrails

Provide guardrails to guide and direct traf-fic. Because the structure can be over-topped, be sure to provide for ready replace-ment of the guardrails.

Maintenance

Inspect the structure for scour or erosionafter each flow (hat causes partial submer-gence or overtopping. Repair any damageimmediately otherwise, at the next heavyflow, the structure could be destroyed.Stockpiling of heavy rock and gabions ateach end of a structure may be required.

BRIDGES

This section presents elements of bridgedesign other than the requirements forstructural design Bridges must conform tothe requirements of stream hydraulics inthe same way as all cross-stream structuressuch as fords, dips, and causeways.

Location

The location of a bridge should be awayfrom bends in the straight section or reach

of the stream (Figure 6-66, page 6-109). Inthis location, there are moderate, evendepths from bank to bank. The deep chan-nel tends to be in the center. Abutmentswill be placed on the edge of the stream.Because of the even distribution of flow,scour and erosion at the stream pier andbank abutments arc not expected to be soexcessive as to cause maintenance problems.

Height

The height of a bridge depends upon theflood-flow, high watermark. The height ofthat mark will determine the profile or su- -perstructure level of the bridges as follows:

Ž When the flood-flow, high watermark isabove the banks, a high-profile or high-level bridge must be constructed tokeep the superstructure above the floodlevel. This type of bridge is well abovebank level and may require a consider-able length and height of approach.

Ž When the flood-flow, high watermark isbelow bank level. a low-profile or low-level bridge can be constructed. Thistype of bridge presents fewer problemsthan the high -level bridge, since ap-proach ramps will not have to be con-structed.

Abutments

The location of bridge abutments dependsupon an analysis of the flood level and thecross section of the stream (Figure 6-70).Analysis proceeds as follows:

Abutments placed at 1A and 1B of Figure6-70 present the most direct solution be-cause they are located on high, dry ground,

Figure 6-70. Waterway cross section at bridge site

Drainage 6-113

Page 211: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Use of these locations, however, may neces-sitate more construction effort because ofthe increased length of the bridge. This in-creased length could result in the need forintermediate piers and spans. With thismethod, the full river waterway will be usedfor the passage of flood water.

Abutments placed at 2A and 2B wouldreduce construction time because fewer in-termediate piers and spans would be re-quired. In addition, the fill in areas 1A-2Aand 1B-2B could be accomplished as thebridge is constructed. As can be seen fromthe figure, this placement reduces the crosssection of the waterway, The following tech-niques could be used to accommodate thisreduction in an available cross-sectional

Ž

area:

Ž The elevation of the bridge superstruc-ture could be raised to account for therise in the flood level. In this case, usesubstantial abutments that are wellprotected against end scour.

• The superstructure elevation could beleft substantially at the original level,and approach ramps over areas 1A-2Aand 1B-2B could be constructed ascauseways to allow for flow. Care mustbe taken to ensure that there is no ex-cessive scour or erosion below the cul-vert outlet that would affect the road-way.

Ž The roadway approaches in areas 1A-2Aand 1B-2B could be depressed belowthe superstructure level. In this case,the excess flood flow would pass overthe roadway approaches, thus relieving

EROSION

Erosion must be controlled to maintain aneffective and clear drainage system with aminimum of maintenance and to reduce haz-ardous dust conditions. Erosion may occurat any point where the force of movingwater exceeds the cohesive strength of thematerial with which the water is in contact.Proper design of side slopes in cut and fillsections (based on the type of soil) will

6-114 Drainage

the bridge flow. If this action is taken,the roadway may not be usable at alltimes. Since overflow is anticipated, theconstruction of these approaches issimilar to construction of causewayswithout the culverts. If the bridge isdesigned properly, with fording depthsas outlined in Table 6-23, page 6-108, itmay be usable during floods under ex-treme conditions.

When a depressed roadway or an ele-vated superstructure is used, the ap-proach to the bridge must have a gentleslope to prevent vehicle impact on theabutment and to ensure traffic visibility.

Drainage

The soil behind bridge abutments can be-come saturated because of rain or other con-ditions. This saturation can take placewhether the approach road is at the naturalgrade of the soil or it is a filled approach.When saturation occurs, static hydraulicpressure on the back face of the abutmentgenerates additional overturning movement.With wood abutments, this condition isrelieved naturally. However, if concreteabutments are used, the pressures can berelieved as follows:

Step 1. Use weep holes to pierce thements with bagged gravel backing onsoil side.

abut-the

Step 2. Place gravel backing against thelower part of the abutment drained by a per-forated pipe at the footing elevation. Setthe pipe to drain out at the sides of theabutment.

CONTROL

reduce the need for extensive erosion con-trol measures. However, additional controlis usually required. Most methods of con-trol are based on dissipating the energy ofwater, providing an erosion-resistant sur-face, or some combination of these techni-ques. This chapter acquaints the militaryengineer with the means available to reduceor eliminate the erosive force of water.

Page 212: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

NONUSE AREAS AND OPEN CHANNELS

Terracing is a control measure designed todissipate the energy of overland flow in non-use areas. Turfing, paving, Gunite lining,and placing riprap are control methodsdesigned to cause turbulence and to in-crease retardation, thereby dissipating theenergy of flow in open channels such asditches and pjpe outfalls. In cases whereeven riprap will be eroded, the use ofgabions is a speedy and relatively inexpen-sive means of dissipating energy.

TERRACING

A terrace is a low, broad-based earth leveeconstructed approximately parallel to thecontours of the topography. A terraceeither intercepts and holds the water untilit infiltrates the soil or moves it as overlandflow to a suitable discharge point. A hardy,vigorous turf should be planted to hold the

Figure 6-71. Terrace spacing and gradients

disturbed soil in place. Vertical spacingand longitudinal gradients of terraces aregiven in Figure 6-71.

TURFING

Ditches are often protected by placingstrips of sod (held in place by woodenboards or stakes) perpendicular to the flowpath at intervals along the ditch, as shownin Figure 6-72.

PAVING AND GUNITE LINING

Ditches having grades in excess of 5 per-cent usually require paving or a Gunitelining. Where a slope equals or exceeds 5percent, paving must be extended downslope at least to the point in the ditch atwhich the erosive energy of the water is con-trolled or absorbed without erosion damage.

Figure 6-72. Erosion-control checks

Drainage 6-115

Page 213: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Paving with either asphalt or portland-ce-ment concrete provides superior erosion-resistant linings in gutters, ditches, and out-fall structures.

Gunite lining of ditches controls erosion ef-fectively. Gunite is a mixture of portland ce-ment and sand with water added justbefore the mixture is sprayed from a high-pressure nozzle onto the surface being pro-tected. The Gunite lining is formed oversteel mesh placed over the bottom andsides of the ditch. Gunite is sprayed to athickness of 1 to 1 1/2 inches, with thesteel mesh located midway in the thickness.Human resources, time, material and equip-ment expenses usually limit the use ofpaving or Gunite linings to only the mostdemanding conditions in TO airfield con-struction.

PLACING RIPRAP

Riprap protection should be provided ad-jacent to all hydraulic structures. Whenplaced on erodible surfaces, it preventsscour- al the ends of the structure. Thisprotection is required on the bed and banksfor a sufficient distance to establish velocitygradients and turbulence levels at the endof the riprap.

Riprap can also be used for lining the chan-nel banks to prevent lateral erosion and un-desirable meandering. Provide an expan-sion either horizontally or vertically (orboth) immediately downstream fromhydraulic structures such as drop struc-tures or energy dissipators. The expansionallows the flow to expand and dissipate itsexcess energy in turbulence rather thandirectly on the channel bottom and sides.Riprap has been known to fail from-

Ž Movement of the individual stonesa combination of velocity and tur-bulence.

from

• Movement of the natural bed materialthrough the riprap, resulting in slump-ing of the blanket.

• Undercutting and leveling of the riprapfrom scour at the end of the blanket.

Consideration must be given to the selec-tion of an adequate size of stone, the use ofadequately graded riprap, the provision of afilter blanket, and the proper treatment ofthe end of the riprap blanket.

Selection of Size

Curves for the selection of stone size re-quired for protection, with Froude numbersand depths of flow in the channel shown,are shown in Figure 6-73.

Two curves are given. One is for riprap sub-jected to direct flow or adjacent tohydraulic structures such as side inlets,confluences, and energy dissipators, whereturbulence levels are high. The other is forriprap on the banks of a straight channelwhere flows are relatively quiet and parallelto the banks.

With the depth of flow and average velocityin the channel known, the Froude numbercan be computed from the following equa-tion:

value can be determined from the ap-propriate curve.

Curves for determining the riprap size re-quired to prevent scour downstream fromculvert outlets with scour holes of variousdepths are shown in Figure 6-74, page6-118. Make the thickness of the riprapblanket equal to the longest dimension ofthe maximum size of stone or 1.5 times

whichever is greater.

When the use of large rock is desirable butimpractical, substituting a grouted reach ofsmaller rock in areas of high velocities orturbulence may be appropriate. Groutedriprap should be followed by an ungroutedreach.

A well-graded mixture of stone sizes ispreferred to a relatively uniform size ofriprap. A recommended gradation is shownin Figure 6-75, page 6-119. In certain loca-tions, the available material may dictate thegradation of riprap to be used. The

6-116 Drainage

Page 214: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-73. Recommended riprap sizes for open channels

gradation should resemble the recom- plot. If the gradation of the available riprapmended mixture as closely as possible. is such that movement of natural materialConsider increasing the thickness of the through the riprap blanket would be likely,riprap blanket when locality dictates using place a filter blanket of sand, crushed rock,gradations with a larger percentage of small gravel, or synthetic cloth under the riprap.stone than shown by the recommended The usual blanket thickness is 6 inches,

Drainage 6-117

0.7

0.5

0.1

0.05

Energy dlsslpators

d \j

Open channels

Stone diameter (50. percent size) Depth of flow Average velocity In channel

0.01 L.-_____ -L ___ .L._---l_-1_-L~_L_..L_L _____ ..J

0.1 0.716\7

F=~

05 2

Page 215: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-74. Recommended riprap sizes for culvert outlets

although a greater thickness is sometimesnecessary.

Design

An ideal riprap design would provide agradual reduction in riprap size until thedownstream end of the blanket blends withthe natural bed material. Unless this isdone, turbulence caused by the riprap islikely to develop a scour hole at the end of

the riprap blanket. However, the extra ef-fort required to provide gradual reductionin riprap size is seldom justified. Doublethe thickness of the riprap blanket at thedownstream end to protect against under-cutting and unraveling. An alternative is arubble blanket of constant thickness andsuitable length, dipping below the naturalstreambed to the estimated depth of bottomscour.

6-118 Drainage

Page 216: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 6-75. Recommended gradation of stones for riprap

GABIONS

Gabions are large, steel, wire-mesh baskets,usually rectangular and variable in size,designed to solve erosion problems at a lowcost, Widely used in Europe, gabions arenow accepted in the United States as a valu-able and practical construction and main -tenance tool. They can be used in place ofsheet piling, masonry construction, or crib-bing.

Description and Assembly

Gabions are supplied from manufacturersin flat, folded bundles. For ease in hand-ling and shipping, the number of gabionsper bundle varies according to the size ofthe gabions. The box gabion is a rectan-gular cage or basket formed of woven,hexagonal, galvanized steel, wire mesh with4- to 8-inch openings and divided by dia-phragms into cells. To assemble, remove asingle gabion from the bundle and unfold iton a hard, flat surface to straighten un-necessary creases and kinks. Fold the

Drainage 6-119

Page 217: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

front, back, and end panels to a right angleto form a box, as shown in Figure 6-76.Securely lace the vertical edge anddiaphragms with binding wire,

Figure 6-76. Assembly of a gabion

Installation

Before placing the gabions, make theground surface relatively smooth and even.Place the assembled gabions in positionsingly or wired together in groups suitablefor handling. It is convenient to place thegabions front-to-front and back-to-back toexpedite the stone-filling and lid-lacingoperation. Lace the basket along theperimeter of all contact surfaces. Wherethere is more than one course of gabions,the base of the empty gabions placed ontop of a completed row must be tightlywired to the latter as shown in Figure 6-77.

When using 3-foot-high gabions, place themempty and lace for approximately 100 linearfeet. Anchor the first gabion firmly andapply tension to the other end with a come-along or by other means to achieve theproper alignment. Anchoring can beaccomplished by partially filling the firstgabion with stone. While the gabions are

being stretched, inspect all corners to makesure the lacing is secure and the cornersare closed. Keep gabions taut while theyare being filled with stone.

Where water, soil, and atmospheric condi-tions allow, galvanized wire mesh can havea life of 40 years or more, For soils andwater showing a pH factor of less than 7 ormore than 12, plastic-coated wire must beused to form gabions.

Filling Procedures

The best filling material is one that allowsflexibility in the structure and, at the sametime, fills the gabion compartments with aminimum of voids and maximum weight.Ideally, the stone should be small, justslightly larger than the size of the mesh(usually 4 to 8 inches). The stone shouldbe clean, hard, durable, and resistant toweathering and frost action.

Fill the gabions to a depth of 1 foot. Thenplace one connecting wire in each directionand loop around two meshes of the gabionwall, as shown in Figure 6-77. Repeat thisoperation twice or until the gabion is filled;then fold the top shut and wire it to theends, sides, and diaphragms.

Pack the stone inside the compartment astight as practical, To protect the verticaldiaphragm during the filling operation, tem-porarily place rebars and lace them alongthe upper edges.

Some manual stone adjustment is requiredduring the filling operation to preventundue voids. Fill the gabion slightly over-full and allow for subsequent settlement;then lace the lid down with binding wire tothe tops of all the sides and to the tops ofthe diaphragm panels. Since it is neces-sary to stretch the lid to fit the sides exact-ly, use a short crowbar or special tooldesigned for this purpose.

The strong interconnection of all units in agabion structure is an important feature. Itis essential that the lacing be done properly.Adjoining gabions are wired together bytheir vertical edges. Empty gabions,

6-120 Drainage

Page 218: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

stacked on filled gabions, arc wired to thefilled gabions at front and back.

Gabions may be filled by almost any type ofearth-handling equipment such as apayloader, crane, conveyor, or modified con-crete bucket. The use of rounded stone, ifit is available, reduces the possibility ofdamage to the galvanized wire duringmechanical filling.

When the depth of the water is too great forthe gabions to be filled on site, fill them ata dry location nearby and place them under-water by crane or barge,

Figure 6-77. Assembly and construction of gabions

Drainage 6-121

Page 219: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Maintenance and Repair

Maintenance and repair are simple proce-dures; therefore, gabions are inspected atleast once a year. Holes can be patchedwith small panels of mesh, and brokenwires can be repaired by using the methodshown in Figure 6-78.

Thickness

The thickness of gabions may be calculatedby considering the gradient of the channel,the steepness of its slope, the type ofmaterial forming the banks and bed, andthe curvature of its course. A 12-inch-deeplining is suggested for channels havingreasonably straight alignment, side slopesof less than 35 degrees, and a flow velocityof about 10 fps, as shown in Figure 6-79.Use an 18-inch gaion lining for curvedchannel sections with a side slope of 45degrees. Use 36-inch stepped-back gabionprotection for sharper side slopes. For asteep channel slope, a combination of liningand weirs may be required.

In the case of easily erodible soil, a layer offilter material or permeable membrane ofcloth woven of synthetic fibers is required.The gabion should be filled with stonesmall enough to allow at least two overlap-ping layers,

In designing a gabion-lined channel, theroughness factor or coefficient (n) inManning’s formula may be assumed to bebetween 0.025 and 0.030, If the gabionsare grouted, the roughness factor can be as-sumed to be between 0.012 and 0.018.

Figure 6-78. Method of repairing a broken wire

Figure 6-79. Typical channel lining usinggabions

Gabion-lined channels may be designedusing Manning’s equation and the proce-dures for open -channel design.

Uses

Gabions can be used in the following ways:

• Protective and antierosion structures onrivers (for example, revetments, groins,or spurs).

• Other antierosion structures (for ex-ample, weirs, drop structures, andcheck dams).

Ž Channel linings.

• Seashore protection.

• Low-water bridges or fords.

• Culvert headwall and outlet structures.

• Bridge abutments and wing walls.

It is often necessary to modify the jnlet andoutlet of a culvert by using transition struc-tures to reduce entrance losses and to in-hibit erosion. Therefore, the two most com-mon devices for which gabions are used areheadwalls and outlet aprons.

Headwalls or wing walls are designed toprotect the slopes of an embankmentagainst scour, to increase culvert efficiencyby providing a flush inlet as opposed toprojecting one, to prevent disjointing of sec-tional-pipe culverts by anchoring the inlet

6-122 Drainage

Page 220: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

and outlet, and to retain the embankmentslope. These structures are built in avariety of shapes: straight, L-shaped,flared, and warped. A typical plan using aheadwall and an outlet apron with a culvertis shown in Figure 6-79. Straight head-walls arc generally used on small, roadsideculverts under driveways and in small chan-nels having a low approach veloc ly. Theyarc also recommended where there is a tendency for lateral erosion to develop at theoutlet.

An apron is often required at the outlet of aculvert to reduce the outlet velocity andthereby inhibit scour. Gabions are welladapted for use here because of their rough-ness, flexibility, and durability. See Figure6-80.)

Table 6-24 indicates the type of gabionprotection required for various ranges of out-let velocities

Figure 6-80. Culvert inlet or outlet using gabion headwall and channel lining

Table 6-24. Requirements for gabion protection

Drainage 6-123

Page 221: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

CULVERT OUTLETS

Most culverts operate under free outfall con-ditions (that is, there is no control of tail-water), and the discharge possesses kineticenergy in excess of that occurring naturallyin the waterway. This excess kinetic energymust often be dissipated to control damag-ing erosion. The extent to which protectiveworks are required for energy dissipationdepends on the amount of excess kineticenergy and the characteristics of thematerial in the outlet channel. In general,scour occurs at average velocities in excessof about 1.5 fps in uniform-graded sandand cohesionless silts, 2.5 fps in well-graded sand, 3.0 fps in silty sand, 4.0 fpsin clay, and 6.0 fps in gravel. Thesevelocities should be used only as a generalguide.

If possible, make a study of local materialto determine its erosion tendencies prior toa decision on the degree of protection re-quired. The study should consider threetypes of outfalls offering three degrees ofprotection: plain outlets, transitions, andstilling basins. Plain outlets provide noprotective works and depend on naturalmaterial to resist harmful erosion. Transi-tions provide little or no dissipation on theworks themselves but result in a spreadingof the effluent jet to approximate the cross-section flow of the natural channel, thusreducing the concentration of energy priorto releasing the flow to the outlet channel.Stilling basins result in dissipation of ener-gy on the protective works.

PLAIN OUTLETS

If the discharge channel is in rock or amaterial highly resistant to erosion, specialerosion protection is not required. Thistype of outlet should be used only if thematerial in the outlet channel can with-stand velocities about 1,5 times the velocityin the culvert, At such an outlet, sideerosion from eddy action or turbulence ismore likely to prove troublesome than bot-tom scour.

Can tilevered culvert outlets may be used todischarge a free-falling jet onto the bed ofthe outlet channel. As a result, a plungepool will be developed. The depth and sizeof the plunge pool depend on the energy ofthe falling jet at the tailwater and theerodibility of the bed material.

TRANSITIONS

Outlet headwalls and wing walls serve thedual purpose of retaining the embankmentand limiting the outlet transition boundary.Erosion of embankment toes can be tracedto eddy attack at the ends of such walls. Aflared transition is effective if it is propor-tioned so that eddies induced by the ef-fluent jet do not continue beyond the endof the wall or overtop a sloped wall.

As a guideline, it is suggested that theproduct of velocity and flare angle not ex-ceed 150 degrees. For example, if effluentvelocity is 5 fps, each wing wall may flare30 degrees; but if velocity is 15 fps, theflare should not exceed 10 degrees. Unlesswing walls can be anchored on a stablefoundation, a paved apron between thewing walls is required. Special care mustbe taken in the structure design topreclude undermining.

A newly excavated channel may be expectedto degrade, Proper allowance for this actionshould be included in establishing theapron elevation and depth of cutoff wall.Warped end walls provide excellent transi-tions that result in the release of flow in atrapezoidal cross section which ap-proximates the cross section of the outletchannel. A warped transition is made atthe end of the curved section to reduce thepossibility of overtopping as a result of su -perelevation of the waler surface. A pavedapron is required with warped end walls.Riprap is usually required at the end of atransition-type outlet.

6-124 Drainage

Page 222: Army Construction Manual FM5 430 Vol1 Entire

STILLING BASINS

At culvert outlets where a high concentra-tion of energy or easily eroded materialsmake excessive erosion likely, a stillingbasin or other energy-dissipating device isrequired. For TO construction, riprap orsimple, concrete stilling basins are usuallyrequired. There are many types of energy-dissipating devices such as hydraulic-jumpbasins, roller buckets, flip buckets, impact-energy-dissipating devices, and stillingwells. In unusual cases involving majorstructures, the use of a special type of

FM 5-430-00-1/AFPAM 32-8013, Vol 1

device should be considered. Three types ofdissipators which may offer a solution arethe hydraulic-jump stilling basin, withdetails developed at the St, Anthony FallsHydraulic Laboratory; the impact-energy dis-sipator, with details developed at thehydraulic laboratory of the Bureau ofReclamation; and stilling wells, These dis-sipa tors are beyond the scope of TO con-struction, Design procedures are not in-eluded in this manual.

Drainage 6-125

Page 223: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

7

Soils Trafficability

Basic Trafficability Factors

Critical Layer

Instruments and Tests for Trafficability

Measuring Trafficability

Application of Trafficability Procedures in Fine-Grained Soils and Remoldable Sands

Self-Propelled, Tracked Vehicles and All-Wheel-Drive Vehicles Negotiating Slopes

Operation in Coarse-Grained Soils

Trafficability Data

Soil-Trafficability Classification

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SOILS TRAFFICABILITY

Soils trafficability is the capacity of soils to support military vehicles. This chapter includes information on the following topics:

• Operating and maintaining the soil-trafficability test set.

Ž Measuring trafficability with the results of the tests performed by the conepenetrometer and remolding equipment.

Ž Making trafficability estimates from terrain data (topography and soil data) andweather conditions. The procedures in this chapter are conservative estimates for fielduse. Engineers must be cautious as the calculated results can vary by 20% or morefrom changes in tire pressure and deflection. Plan for the unexpected!

This chapter discusses the trafficability of fine- and coarse-grained soils. Organic soils[muskeg.) and snow are not discussed.

The trafficability of fine-grained soils (silts and clays) and sands that contain enoughfine-grained material to behave like fine-grained soils when wet is more difficult to as-sess than trafficability in coarse-grained soils (clean sands). Relationships thatdescribe the soil-vehicle interactions are based on soil shearing-resistance measure-ments made with the cone penetrometer and corrected for soil remolding under vehicletraffic by the remolding index [RI) procedures.

The information presented in this chapter is limited to problems associated with soils.It does not include problems associated with natural or man-made obstacles (such asforests or ditches) nor Information on vehicle characteristics (such as the maximum tiltor side angle at which a vehicle can climb without power stall or overturning), Thebasic principles for the procedures presented are sound for temperate and tropicalclimates and for soils that have been subjected to freeze-thaw cycles, if they are notfrozen at the time of testing and passage of traffic.

Originally, this chapter was designed to permit calculation ns of trafficability by field per-sonnel with only a hand-held calculator. Performances were estimated for a minimumnumber of vehicle passes (1) or a maximum of 50 vehicles in the same ruts, Todaymost relations are used for one pass and the combined effects on vehicle performanceof terrain features such as soil, vegetation, and slope can only accurately be deter-mined through the use of the computerized Army mobility prediction system containedin the NATO Reference Mobility Model (NRMM). The engineering relationships whichproduce vehicle speed predictions or GO/NO GO performance based on measured ter-rain and vehicle characteristics are contained in the NRMM. This chapter only intro-duces fundamental relationships, terminologies, and illustrations of this computerized,comprehensive mobility evaluation tool. Most military units have access to NRMMrelationships through personal computer-based NRMM versions of mobility predictionssuch as the Comprehensive Army Mobility Modeling System (CAMMS).

Soils Trafficability 7-1

Page 224: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

BASIC TRAFFICABILITY FACTORS

The following factors impact soil traf-ficability:

SOIL STRENGTH

Bearing and traction capacities of soils arefunctions of their shearing resistance.Shearing resistance is measured by thecone penetrometer and is expressed interms of cone index (CI). Because thestrength of fine-grained soils (silts andclays) may increase or decrease whenloaded or disturbed, remolding tests arenecessary to measure any loss of soilstrength expected after traffic. The fine-grained soil CI multiplied by the RIproduces the rating cone index (RCI) usedto denote soil strength corrected for remold-ing. A comparison of the RCI with thevehicle cone index (VCI) indicates whetherthe vehicle can negotiate the given soil con -dition for a given number of passes. For ex-ample, if a soil has a CI of 120 and an RIof 0.60 in its critical layer, the soil strengthmay be expected to fall to 120 times 0.60,or an RCI of 72, under traffic. Therefore,such soil is not trafficable for vehicles withVCIs greater than 72. If a vehicle has aminimum soil-strength requirement of 72for one pass, its is 72 and an RCI of72 is required for the vehicle to completeone pass without immobilization. AppendixD of this manual summarizes VCIs formilitary vehicles.

STICKINESS

Stickiness may seriously hamper vehiclesoperating in wet, fine-grained soil. Underextreme conditions, sticky soil can accumu-late in a vehicle’s running gears, makingtravel and steering difficult. Normally,stickiness is troublesome only when it oc-curs in soils of low-bearing capacity (nor-mally, fine-grained soils).

SLIPPERINESS

Excess water or a layer of soft, plastic soilof low LL overlying a firm layer of soil canproduce a slippery surface. Such a condi-tion may make steering difficult or may im-mobilize rubber -tired vehicles. Vegetation,especially when wet and on a slope, maycause immobilization of rubber-tiredvehicles. Slipperiness is troublesome, evenwhen associated with soils with high-bear-ing capacities.

VARIATION OF TRAFFICABILITY WITHWEATHER

Weather changes produce changes in soiltrafficability. Fine-grained soils increase inmoisture during rainy periods. This resultsin slipperiness, stickiness, and decreasedstrength. Dry periods produce the oppositeeffects. Loose sands improve trafficabilitythrough an increase in cohesion duringrainy periods and return to the loose, lesstrafficable state during dry periods. Traf-ficability characteristics measured on agiven date cannot be applied later unlessfull allowance is made for the changes insoil strength caused by weather. Freezingand thawing conditions can cause extremevariations in the trafficability of soils.Several inches of frozen soil may carry alarge number of extremely heavy vehicles.However, when this same material is thaw-ing, it may be impassable to nearly allvehicles. Snow cover can have a significant teffect on the depth of freezing. The ab-sence of snow allows frost to penetratemore deeply into the soil. Techniques havebeen developed for predicting the effects ofweather on soil trafficability. These techni-ques are part of the comprehensive NRMMand are not included in this publication.

7-2 Soils Trafficability

Page 225: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

CRITICAL LAYER

The critical layer is the layer in the soil profile, the vehicle type andthat supports the weight of the vehicle in number of passes required.question. The critical layer’s depth varies marizes these variations forwith the soil type, the soil’s strength military vehicles.

Table 7-1. Critical-layer depth variations

weight, and theTable 7-1 sum-common

INSTRUMENTS AND TESTS FOR TRAFFICABILITY

This section contains general informationregarding the soil-trafficability test set. Thespecific use, operating instructions, andtest procedures for the soil-trafficability testset are described in detail in Appendix E ofthis manual. Sieve-analysis tests, plasticitytests, and other field identification tests arcdescribed in Chapter 2 of FM 5-530.

Trafficability measurements are made withthe soil-trafficability test set. This set con-sists of one canvas carrying case, one conepenetrometer with 3/8-inch steel and 5/8-inch aluminum shafts and a 0.5-square-inch cone, one soil sampler, remoldingequipment (which includes a 3/8-inch steelshaft and a 0.2-square-inch cone, a 5/8-inch steel shaft with foot and handle, a 21/2-pound hammer, a cylinder and basewith pin), and a bag of hand tools. Theitems are shown in Figure 7-1 in theirproper places in the carrying case. The setis carried on the back as shown in Figure 72, page 7-4. The complete set weighs 19pounds. Figure 7-1. Soil-trafficability test set

Soils Trafficability 7-3

Page 226: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The primary instrument of the soil-traf-ficability test set is the cone penetrometer.It is shown in Figures 7-3 and 7-4 and Fig-ure 7-5, page 7-5. It is used to determinethe shearing strength of low-strength soils.There is also a dynamic cone penetrometer,but this instrument is used to determineshear strength of high-strength soils suchas those found in the base courses of roadsand airfields. (The dynamic cone penetro-meter is currently developmental and hasonly limited fielding.) The dynamic conepenetrometer is described in detail in Appen-dix E. The cone penetrometer consists of a30-degree cone with a 1/2-inch-square basearea, a steel shaft 19 inches long and 3/8inch in diameter, a proving ring, amicrometer dial, and a handle. When thecone is forced into the ground, the provingring is deformed in proportion to the forceapplied.

Figure 7-2. Carrying asoil-trafficability test set

Figure 7-3. Cone penetrometer

Figure 7-4. Using a conepenetrometer in the upright position

7-4 Soils Trafficability

Page 227: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 7-5. Using a cone penetrometer in the prone position

The amount of force required to move thecone slowly through a given plane is indi-cated on the dial inside the ring. This forceis an index of the soil’s shearing resistanceand is called the soil’s CI in that plane.The dial’s range is 0 to 300 pounds persquare inch (psi). (The actual load appliedto the cone penetrometer is 0 to 150pounds, since the instrument uses a 1/2-square-inch base.) The proving ring andhandle are used with a 3/8-inch-diametersteel shaft and the 0.2-square-inch cone for

remolding tests in remoldable sands. Thecone penetrometer cannot be Used tomeasure gravels. Gravels arc considered ex-cellent for 50 passes, and any problems canbe determined by visual observation.

The specific use, operating instructions,and test procedures for the cone pene-trometer as well as the remainder of thesoil-trafficability test set are described indetail in Appendix E.

MEASURING TRAFFICABILITY

Whenever reconnaissance parties have timeto take trafficability measurements, theyshould obtain data to determine the num-ber and type of vehicles that can cross thearea and the slopes they can climb. Theprocedures for measuring trafficability aredescribed in this section. Remember thatmeasurements are valid only for the time ofthe measurement and short periods there-after, provided no weather changes occur.

RANGE OF CONE INDEXES

A CI ranging between 10 and 300 in thecritical layer is required to support mostmilitary vehicles. Except for a few vehicles,a CI below 10 is considered to be a nontraf-ficable area and a CI above 300 is con-sidered trafficable to all but a few vehiclesfor 50 passes. These limits usually make itpossible, while gathering data for traffica-

bility evaluation, to classify large areas asabove or below the critical range without ex-tensive testing.

NUMBER OF MEASUREMENTS

The number of measurements taken isdetermined by the time available, the judg-ment of the range of soil strengths, and thegeneral uniformity of the area. Traffica-bility-measuring instruments are designedfor rapid observations. The accuracy of theaverage of any series of readings increaseswith the number taken. Variations in softsoils require that at least 15 readings betaken to establish a true average CI at anyspot at a given depth. The 15 readingsshould be distributed throughout a uniformarea,

Soils Trafficability 7-5

Page 228: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

If time is not available to take a large num-ber of measurements, use judgment to re-duce the number according to the followinginstructions:

• If CIs are between 0 and 150, enoughreadings should be taken to assure ac-curate coverage of the area. Readingsshould be made at enough locations toestablish the area boundaries and theaverage CI within close limits. Four tosix sets of readings should be made ateach location. Remolding tests (in thecase of fine-grained soil and remoldablesand) should be run at a sufficient num-ber of locations to establish the range ofRIs If a tentative route can be selectedin the field, penetrometer and remoldingmeasurements should be made atclosely spaced intervals to locate anysoft spots. Where CIs are less than 10,readings should be limited to the num-ber needed to establish the nontraffica-ble-area limits. No remolding tests arerequired.

• If the CI ranges from 150 to 200, selectenough locations to verify the area lim-its. Three or four sets of readingsshould be made at each location. Forfine-grained soils and remoldablesands, remolding tests should be madeat the first two or three locations. Ifthese show an RI of 0.90 or more, addi-tional remolding tests are not needed.If the RI is below 0.90, sufficient remold-ing tests should be made to establishthe range for the area. This can be es-tablished with tests at approximatelysix locations.

Ž If the CIs are above 200, a few pene-trometer readings will usually verify theextent of the area. Two sets of profilereadings taken at each location shouldbe adequate. Remolding tests on soilfrom the critical layer (fine-grained soilsand remoldable sands) should be madeat the first two or three locations. Ifthese show an RI of 0.80 or more, no ad-ditional remolding tests are needed.Sufficient tests should be made to estab-

7-6 Soils Trafficability

lish the range for the area if the RI is be-low 0.80. This can be established withtests at approximately four locations.

Example:

Using the work sheet in Figure 7-6, fivetests down to 24 inches were completed ata selected site. The corresponding pene-trometer readings are listed in the blocksfor the corresponding depth and test. Forexample, in test number 1 the 0-inch read-ing is 58, the 6-inch reading is 63, and soon. The individual depth readings are thenadded and averaged, as in the 0-inch layer.(Always round down.)

Solution:

The numbers in the numerator are the indi-vidual readings. The number in the denomi-nator represents the number of tests con-ducted. The resulting quotient is the aver-age CI for that depth.

After all individual readings are added to-gether, they are averaged with the readingabove and below to obtain the average CIfor that layer. In the case of the 0- to6-inch layer, the 66 and 71 are added andthen averaged [68). The 68 is the CI forthe 0- to 6-inch layer, Readings are thenaveraged for the 6- to 12-inch layer andso on.

NOTE: Intermediate values for the 3-,9-, and 15-inch depths (fine grains and re-moldable sands) can be interpolated whenthe vehicle types under consideration re-quire them.

Continuing with the example above, theM929 dump critical layer for one vehicleand for 50 vehicles is 9-15 inches. (To de-termine the critical layer, refer to the sec-tion on critical layers in this chapter, page7-3.) Because the readings on the conepenetrometer are taken at the 0-, 6-, 12-,18-, and 24-inch depths, the 3-, 9-, 15-, and21-inch readings must be interpolatedwhere necessary.

Page 229: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 7-6. Trafficability test data form

Soils Trafficability 7-7

TRAFFICABILlTY TEST DATA

b. n.A ; AT DEP"H

a. TEST NUMBERS o· I I 12" -

AVERAGE ~l.p 71 75 75 e,2. <[ORMAl") 'IItIQRU·.,

c.Cl 1 • 14-

Id. CI..,o • 74-7~-:J'f 7 -IS 1

75""6(71 ...• '.. .............. ..!

JD 74- ...•............. e. CRITICAllAYER FOR 1 VEHICLE "

1-15' f. CRITICAL LAYER fOR 50 VEHICLES 9-/5"/'

4. 1!~lVIn. n ... ,INO£X (D,I '11 .re:

a. LAYER 9-/5" LAYER 7-IS1( LAVER 7- 15'"/1 LAYER

b. DEPTH BEFORE AFTER BEFORE AFTER BEfORE AFTER BEFORE AFTER

o· 5'6 ct ~7 71 93 I 1"

~fD 73 75 85 2" <03 15"" 7( 77 f~ r ~5 77 73 e)l5 9-4-4" 7" 61 78 SS ?7

c. AVERAGE 75 ~4- 71 78 9Cf \. \4-d. RI " After

8e'iOr"i! e. RI FOR 1 VEHICLE f. RI fOR 50 VEHICLES

f • $2S' I g. RATING CONE INDEX (RCI)

RCI.-C11XRI,- 74->(1 :::i4-RCI50 • CI50 X Rlso· 74-x, ': 74- i. WEATHER CONDITIONS (Describe)

~ LOuT) y /4-tJi) c::::..OOL-j. VEHICLE CONE INDEX {V Cl)

VC'1· 3f ICG Cl > VC,

742'- 3J71 -""-~pY/ f'. 43 0 F '!:14/NtE.D lA ,TfH,J L-.4?r z4 Ho~

IFG & RS RCI ~ VCI

14-..L~ro VC150· ~6

I k. TYPE OF SOIL one) ../ FG

WILL 1 VEHICLE IU~'" fr. • one) I vi vu I NO I. ~~~Il I PROfiLE I vi /'1 Will • ~< "UU ,... TVT y:s 1 NOl( <" r( ~ 7 . '7

CG

ABNORMAL

00 Form 2641, AUG 93 \

Page 230: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

To find the 3- to 9-inch layer, the ]CI read-ings for the 0- to 6-inch and the 6- to 12-inch layers are added together and then av-eraged:

70 becomes the CI for the 3- to 9-inchlayer. For the 9- to 15-inch layer, the 6- to12-inch and 12- to 18-inch layers will be in-terpolated:

The CI for the 9- to 15-inch layer is 74.

STRENGTH PROFILE

Normal Strength Profile in Fine-Grainedsoils and Remoldable Sands

In a soil with a normal strength profile, theCI readings either increase or remain con-stant with each increment of depth. Anarea with a normal strength profile is

shown in Table 7-2. CIs should be mea-sured at 6-inch increments down to 18inches in the early stages of area reconnais-sance. If these measurements consistentlyreveal that the profile is normal, only read-ings in the critical layer need to be re-corded.

For a tracked vehicle weighing less than100.000 pounds, such as the M113A3 ar-mored personnel carrier (APC), readings arerecorded for the 6- and 12-inch depths. Ina normal profile, remolding tests should berun only on samples taken from the normalcritical depth for the vehicle in question,since a decrease in RI with increasing depthis not common. The RCI for this layer isused as the criterion of traffic ability for thisparticular vehicle.

Abnormal Strength Profile in Fine-Grained Soils and Remoldable Sands

An abnormal strength profile has at leastone CI reading that is lower than the read-ing immediately preceding it. An area with

Table 7-2. Examples of normal- and abnormal-soil strength profiles

7-8 Soils Trafficability

Page 231: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

an abnormal strength profile is shown in Ta-ble 7-2.

When an abnormal strength profile exists,CI readings should be made and recordedat 6-inch increments from the top of thenormal critical layer (6-inch depth for theM113A3 APC) to 6 inches below the bottomof the normal critical layer (18 inches forthe M113A3 APC).

Remolding tests must be run on samplesfrom the normal critical layer and also fromthe 6-inch layer below it. The lower RCI isused as the trafficability measurement. Low-ground-pressure tracks are an exception tothis rule. The 3- to 9-inch layer is alwaysused as the critical layer for these vehicles.

Strength Profile in Coarse-Grained Soils

As indicated in Table 7-1, page 7-3, thecritical layer for most vehicles in coarse-grained soils is the 0- to 6-inch layer. Mostcoarse-grained soils have a normal strengthprofile with a large increase in strengthwith depth when compared to fine-grainedsoils. For this reason, CI measurementsshould be taken at 3-inch increments to 18inches or until the maximum capacity (300CI) of the penetrometer has been reached.

Usually, fewer penetrations are required toestablish an average because coarse -grainedsoil areas generally are more uniform thanfine-grained soils and remoldable sands.The RI tests are not required. The strengthmeasurements in a coarse-grained soil areaare shown in Table 7-2.

RATING CONE INDEX

The RCI defined earlier is the CI that will re-sult under traffic. This value is comparedto the VCI to determine the trafficability ofthe area for a specific vehicle,

Example:

The following fine-grained soil areas are tobe investigated for trafficability for vehicleswith a normal critical layer of 6 to 12inches. Because area A in Table 7-2 has a

normal profile, a remolding test was runonly for the 6- to 12-inch layer. The RCIfor area A is 60 (the average of 50 and 70)x 0.90 = 54. In area B, remolding testswere necessary for both the 6- to 12-inchand 12-to 18-inch layers. In this area, theRCI of the 6- to 12-inch layer is 60 (the av-erage of 75 and 45) x 0.90 = 54, and theRCI of the 12-to 18-inch layer is 40 x 0.90= 36. The RCI of the 12- to 18-inch layer,36, is the governing value for the trafficabil-ity in area B.

Example:

Using the work sheet in Figure 7-6, page7-7, the critical layer for one or 50 M929dumps is 9 to 15 inches.

Samples are removed from the critical layer.For the 9- to 15-inch layer, three tests wereconducted, each yielding different results.The average of these results is determined,and this number becomes the RI for thatlayer.

(1.14 exceeds 1.0, so use 1.0.) The is74 and the is 74. The is 30,and the is 68. Comparing theto the and the to the it isdetermined that one M929 dump can crossthe area and 50 M929 dumps also cancross the area because the RCI values aregreater than or equal to the VCI values.

Usually a mixture of vehicles will passthrough an area, not a column of one vehi-cle type. Therefore, the VCI and criticallayer will be determined for the critical vehi-cle.

To estimate how many vehicles will cross anarea when the RCI is less than the orto see what the VCI for less than 50 vehi-cles will be, use the following formula:

will give an increment for one vehicle

that, when added to the will give theAVCI for any amount of vehicles up to 50.

Soils Trafficability 7-9

Page 232: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Example:

Estimate how many M1A1 tanks can crossa level area with fine-grained soil where theCI is 65 and the RI is 0.80 in the criticallayer. For simplicity, we have used this ap-proach on trafficability research. In ac-tuality, the strength increment decreases aspasses increase; for example, more strengthis required for lower passes than for higherpasses, so that more remolding occurs atlower passes than at higher passes. The dif-ferences are not linear but can be es-timated in the manner shown here.

Each vehicle adds 0.66 to the

To estimate the number of vehicles that canpass, add 0.66 to until the number isequal to the RCI or one more increase willexceed the RCI. (Remember, this is only anestimate.)

OTHER TRAFFICABILITY EVALUATIONFACTORS

In addition to the CI of an area, considerthe factors that follow when evaluating traf-fixability.

Slope

The steepest slope, or ruling grade, thatmust be negotiated should be determinedby studying a contour map. For travel overslopes, the CI requirements must be in-creased over those required for level terrain.

Stickiness

Stickiness occurs in all fine-grained soilswhen they are wet. The greater the plas-

ticity of the soil, the more severe the effectsof stickiness. Stickiness adversely affectsthe speed and control of all vehicles butwill not cause immobilization except for thesmallest tracked vehicles. The worst sticki-ness is nothing more than a nuisance tolarger, more powerful military vehicles.Removing fenders will reduce stickiness ef-fects on some vehicles. Instruments formeasuring the effects of stickiness on theperformance of vehicles have not yet beendevised.

Slipperiness

Like stickiness, the effects of slipperinesscannot be measured. Soils that are coveredwith water or a layer of soft, plastic soilusually are slippery and often cause steer-ing difficulty, especially in rubber-tiredvehicles. Immobilization can occur whenslipperiness is associated with low-bearingcapacity. The adverse effects of slipperi-ness are more severe on slopes. Sometimesslopes with adequate soil strength will notbe passable because of slipperiness.Chains on rubber-tired vehicles usually im-prove mobility in slippery conditions. Thefollowing categories are used to rate slipperi-ness:

Condition SymbolNot slippery under any conditions NSlippery when wet PSlippery at all times S

Vegetation

The effects of vegetation on trafficability arenot within the scope of this manual,but some points are worthy of mention,Dense grass, especially if wet, may provideslippery conditions. Additionally, soilstrength requirements will be greater thannormal if small trees or thick brush mustbe pushed down by the vehicle.

Organic-Soil Areas

Much of the terrain in northern latitudes isblanketed with a layer of organic materialcomposed of roots, mosses, and othervegetation in various stages of decomposi-tion, Limited testing with military vehiclesreveals that low-ground-pressure, tracked

7-10 Soils Trafficability

Page 233: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

vehicles, such as the M973 small-unit sup-port vehicle (SUSV), can travel 50 passesover organic mats that are more than 6inches thick.

Usually, high-ground-pressure vehicles cantravel only a few passes before they breakthrough and become immobilized. Wheeledvehicles usually cannot travel on most ofthese organic-soil areas. Cone indices de-note the relative strength of organic soils.However, the soil-strength vehicle perform-ance relations for organic soils are not as

well defined as for fine-grained and coarse-grained soils.

Other Obstacles

A complete assessment of the traffic abilityof a given area must include an evaluationof obstacles such as forests, rivers, boulderfields, ditches, and hedgerows. Exact ef-fects of such obstacles on the performanceof vehicles are determined by the compre-hensive NRMM but are not within the scopeof this manual.

APPLICATION OF TRAFFICABILITY PROCEDURES INFINE-GRAINED SOILS AND REMOLDABLE SANDS

The procedures presented in earlier sections the soil to withstand 1 or 50 passes of theof this chapter are intended for use in tacti- same vehicle (or vehicles with smaller cal operations. Criteria have been estab- or operating at a slow speed in thelished so that when a given area’s RCI is same ruts (in the case of 50 passes) and toequal to or higher than the VCI for 1 or 50 permit stopping and resumption of move-passes of the selected vehi- ment, if necessary.cle, sufficient strength will be available in

SELF-PROPELLED, TRACKED VEHICLES AND ALL-WHEEL-DRIVEVEHICLES NEGOTIATING SLOPES

The maximum slope negotiable and themaximum towing force or gross vehicleweight for the RCI are essentially equal.Therefore, when the RCI is known, the maxi-mum slope negotiable by a given vehicle for50 passes (or by 50 similar vehicles instraight- line formation) can be estimatedfrom Figure 7-7, page 7-12. The differencesin the properties of various soils producesome differences in vehicle performance, soNRMM actually predicts performance in fine-grained soils based on specific soil type.

Example:

Estimate the maximum slope an M1A1 tankcan climb for 50 passes where the slope con-sists of a fine-gralned soil with a CI of 100and an RI of 0.85 in the critical layers.

Solution:

RCI = 100 X 0.85 = 85RCI. = RCI - = 85-58 = 27

Using Figure 7-7, the maximum slopeequals 50 percent. The maximum slope theM1A1 can negotiate under the given condi-tions is 50 percent.

Example:

Estimate the maximum slope an M9235-ton cargo truck can climb for 50 passeswhere the slope consists of a remoldablesand whose CI is 93 and RI is 1.00 in thecritical layer.

Solution:

RC = 93 x 1.00 = 93 = RCI - = 93 - 68 = 25

Soils Trafficability 7-11

Page 234: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 7-7. Fifty-pass performance curves for self-propelled vehicles operating infine-grained soils or remoldable sands

In Figure 7-7, at = 25, the maximumslope is 35 percent. The maximum slopethe M923 truck can climb under the statedconditions is 35 percent.

ONE-PASS PERFORMANCE

The following information is used to deter-mine if various vehicles can make a singlepass over different types of terrain:

Self-Propelled, Tracked Vehicles and All-Wheel-Drive Vehicles on Level Terrain

The ability of a given vehicle to make onepass on a straight line on level terrain is as-sured if the RCI of the area is greater thanthe VCI for one pass The ofmost military vehicles are listed in Appen-dix D.

Example:

Estimate if an M1A1 tank can complete onepass on a level, fine-grained soil with a CIof 50 and an RI of 0.70 in the critical layer.(Use Appendix D to determine the VCI.)

Solution:

Because the RCI is greater than the (35 is greater than 25), the M1A1 tank cancomplete one pass. Immobilization of avehicle probably will occur when the RCI isless than the Immobilization mayoccur even when the RCI is slightly greaterthan the if water on the soil surfacecauses excessive sinkage or slipperiness.

7-12 Soils Trafficability

Page 235: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 7-8. One-pass performance curves for self-propelled vehiclesoperating in fine-grained soils or remoldable sands

Self-Propelled, Tracked Vehicles and All-Wheel-Drive Vehicles Up Slopes

The maximum slope negotiable and the max.imum towing force (as a percentage of grossvehicle weight) for the same are essen-tially equal. Therefore, when the RCI isknown, the maximum slope negotiable by agiven vehicle for one pass in a straight lineup a slope can be determined by using theinformation in Figure 7-8.

Example:

Determine the maximum slope an M1A1tank can climb on one pass where the slopeconsists of fine-grained soil with a CI of100 and an RI of 0.85 in the critical layer.

Solution:

Using Figure 7-8, at = 60, the maxi-mum slope = 63 percent. Under the statedconditions, the maximum slope the M1Altank can negotiate is 63 percent.

Example:

Determine the maximum slope an M923truck can climb on one pass where theslope consists of a remoldable sand withCI of 93 and an RI of 0.40 in the criticallayer.

a

Soils Trafficability 7-13

Page 236: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Solution:

In Figure 7-8, page 7-13, at = 7, themaximum slope = 21 percent. Under thestated conditions, the M923 truck canclimb a slope less than or equal to 21 per-cent.

Vehicles Towing Trailers on Level Terrainand Up Slopes

One-pass performance of vehicles towingtrailers is predicted using the comprehen-sive NRMM and is beyond the scope of thismanual. The prediction system is not aswell validated as that for single, self-propelled vehicles. Although the procedurefor determining the for combinations oftrucks or tractor-trailers is not discussed,the of commonly used combinationvehicles are listed in Appendix D.

Vehicles Towing Other Vehicles on LevelTerrain

When the RCI is equal to the VCI, the soilhas just enough shear strength for thevehicle to overcome its motion resistance.If the vehicle must tow another vehicle, ad-ditional shear strength is required toproduce the thrust needed to overcome themotion resistance (or required towing force)of the towed vehicle. Thus, RCI - VCI, or is a measure of additional shearstrength that allows the vehicle to develop atowing force.

Curves that predict the maximum towingforce that can be developed by three typesof self-propelled vehicles on level terrain arepresented in Figure 7-7, page 7-12. Themaximum towing force (expressed as a per-centage of vehicle gross weight) is related to Curves that predict the force re-quired to tow vehicles of various weightsand types on level terrain are shown in Fig-ure 7-8, where required towing force (ex-pressed as a percentage of vehicle grossweight) is related to RCI. When a vehicle isrequired to develop a given towing force,the necessary RCI can be determined.

When the RC1 is known, the ability of onevehicle to tow another can be determined.

The determination of VCI for towed tractorsand self-propelled vehicles with nonpoweredwheels requires calculations on an axle-by-axle basis and is beyond the scope of thismanual; therefore, in examples involvingvehicles towing other vehicles always referto the towed vehicles as “inoperable,powered vehicles.” The following para-graphs give examples of the application ofvehicle performance criteria for both 1 and50 passes, using Appendix D and Figures 7-7 through 7-10, pages 7-12 through 7-17:

Procedures used in the examples shouldnot be extended to the development of asingle VCI for a tractor-trailer combinationvehicle. Such development can be reliablymade only through the integration of com-plex considerations which are beyond thescope of this manual. However, some com-monly used truck-trailer combinationvehicles are listed in Appendix D, wheretheir VCIs are used in the same way theVCIs for other vehicles are used to predicttheir performance on level terrain.

Example:

Estimate if an M1A1 tank can tow anM923, 5-ton cargo truck for 50 passes on alevel, fine-grained soil where the CI is 100and the RI is 0.80 in the critical layer forthe tank, and the CI is 60 and the RI is0.80 in the critical layer for the truck.

Solution:

From Appendix D:

For the M1A1 tank—

For the M923 truck—

RCI for the tank = 100 x 0.80 = 80RCI for the truck = 60 x 0.80 = 48

7-14 Soils Trafficability

Page 237: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The maximum towing force (T1) of the tankis read from the curve in Figure 7-7, page 7-12, labeled “Tracked vehicles with grousersless than 1 1 /2 inches. ” Using this curve,where the = 80 - 58 = 22, it is es-timated that the tank can tow 25 percent ofits weight. Thus, 25 percent of 125.000 =0.25 x 125.000 = 31.250 lb.

The required towing force (T2) of the M923truck is read from the curve in Figure 7-8,page 7-13, for 30,000 lb for wheeledvehicles. On this curve, at RCI = 48, T2 =49 percent of 32,500 = 0.49 x 32,500 =15,925 lb,

Because the available towing force (31,250lb) of the M1A1 tank is greater than the re-quired towing force (15,925 lb) for theM923 truck, the tank can tow the truckunder the stated conditions.

Example:

Estimate if an M923, 5-ton cargo truck cantow an M1A1 tank for 50 passes on a level,fine-grained soil whose shear strength (CI =95 and RI = 1.00) is the same for the criti-cal layers for both vehicles. The vehiclesare the same as those in the previous ex-ample.

Solution:

RCI = 95X 1,00=95 = 95 - 68 = 27 for the M923 truck

The maximum towing force (Tl1 of theM923 truck is read from the curve labeled“Wheeled vehicles” in Figure 7-7. On thiscurve, = 27, T1 = 37 percent of 32,500= 0.37 x 32,500 = 12,025 lb.

The required towing force (T2) of the M1A1tank is read from the curve in Figure 7-8that is labeled “75,000 lb” for trackedvehicles. On this curve, at RCI = 95, T2 =18 percent of 125,000 lb = 0.18 x 125,000= 22,500 lb.

Because the available towing force (12,025lb) of the M923 truck is less than the re-quired towing force (22,500 lb) of the M1A1tank, the truck cannot tow the tank.

Vehicles Towing Other Vehicles Up Slopes

The maximum slope a vehicle towinganother vehicle can negotiate is estimatedusing the following formula:

Where—

T1 = the maximum towing force (in lb) ofthe towing vehicle

T2 = the force (in lb) required to tow thetowed vehicle on level terrain

W1 = weight (in lb) of the towing vehicle

W2 = weight (in lb) of the towed vehicle

NOTE: This formula does not apply toslippery surfaces.

Example:

Estimate the maximum slope that can benegotiated by an M1A1 tank towing anM923 truck for 50 passes, where the slopeconsists of fine -grained soil whose shearstrength is such that the CI is 100 and theRI is 0.85 in the critical layer for the tank,and the CI is 80 and the RI is 0.80 in thecritical layer for the truck.

Solution:

Using Figure 7-7, the maximum towingforce (Tl) of the MlA1 tank at = 27 is45 percent of 125,000 = 56,250 lb.

In Figure 7-9, page 7-16, the requiredtowing force (T2) of the M923 truck at RCI= 64 is 38 percent of 32,500 = 0.38 x32,500 = 12,350 lb.

Soils Trafficability 7-15

Page 238: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 7-9. Fifty-pass performance curves for vehicles towedin level, fine-grained soils or remoldable sands

Thus, the maximum slope negotiable by the Solution:M1A1 tank towing the M923 truck underthe given conditions is 28 percent.

Example:

Estimate the maximum slope negotiable byan M923, 5-ton cargo truck towing anM998 high mobility, multipurpose wheeledvehicle (HMMWV) for 50 passes, where theslope consists of fine-grained soil with a CIof 120 and an RI of 1.00 in the criticallayer. The M998 is a wheeleda gross weight of 7,500 lb.

7-16 Soils Trafficability

vehicle with

Using Figure 7-7, page 7-12, where theis 52, the maximum towing force (T1)

for the truck is 47 percent, 0.47 x 32,500 =15,275 lb.

Page 239: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Using Figure 7-9, the required towing force(T2) of the M998 at RCI = 120 is 13 percentof 7,500 = 0.13 x 7,500 = 975 lb.

Thus, the maximum slope negotiable by theM923 truck towing an M998 HMMWVunder the given conditions is 36 percent.

Vehicles Towing Inoperable, PoweredVehicles on Level Terrain [One Pass]

vehicle to overcome its motion resistance.If the vehicle is required to tow anothervehicle, additional shear strength is re-quired to produce the necessary thrust toovercome the motion resistance (or requiredtowing force) of the towed vehicle. Thus,

which is the additionalshear strength that allows a vehicle todevelop a towing force when required (forone pass).

Two performance curves, one for self-propelled, tracked vehicles and one for self-propelled, wheeled vehicles, are shown in,

When the RCI is equal to the the soil Figure 7-8, page 7-13. The maximum

has enough shear strength for a giventowing force (expressed as a percentage ofthe vehicle’s gross weight) that can be

Figure 7-10. One-pass performance curves for vehicles towedin level , f ine-grained soi ls or remoldable sands

Soils Trafficability 7-17

Page 240: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

developed by a vehicle on level terrain is re-lated to The performance curve for allvehicles when towed on level terrain isshown in Figure 7-10, page 7-17, where therequired towing force (expressed as a per-centage of the vehicle’s gross weight) is re-lated to When the RCI is known, theability of one vehicle to tow another can beestimated,

Example:

Estimate if an M1A1 tank can tow an M923,5-ton cargo truck for one pass on level, fine-grained soil whose shear strength is suchthat the CI is 100 and the RI is 0.70 in thecritical layer for the tank, and the CI is 50and the RI is 0.70 in the critical layer forthe truck.

Solution:

For the M1A1 tank, = 25, grossweight = 125,000 lb, and grousers areless than 1 1 /2 inches. For the M923truck, = 30 and gross weight = 32,500lb. (See Appendix D.)

For the M1A1 tank, RCI = 100 x 0.70 = 70and = 70 - 25 = 45. In Figure 7-9,page 7-16, at = 45, the maximumtowing force (T1) = 63 percent of 125,000 =0.63 X 125,000 = 78,750 lb.

For the M923 truck, RCI = 50 x 0.70 = 35and = 35 - 30 = 5. In Figure 7-10, at = 5, the required towing force (T2) =25 percent of 32,500 = 0.25 x 32,500 =8,125 lb.

Because the available towing force (78,750lb] of the tank exceeds the required towingforce (8,125 lb) of the truck, the tank cantow the truck under the stated conditions.

Example:

Estimate if an M923, 5-ton cargo truck cantow an M1A1 tank for one pass on level,fine-grained soil whose CI is 95 and RI is1.00 in the critical layer for each vehicle.

Solution:

For the M923 truck, = RCI - =95 - 30 = 65. In Figure 7-8, page 7-13, at = 65 the towing force (T1) = 54.6 per-cent of 32,500 = 0.546 x 32,500 = 17,745 lb.

For the M1A1 tank, = RCI - =95 - 25 = 70. In Figure 7-10, at RCIX = 70the required towing force (T2) = 8 percent of125,000 = 0.08 X 125,000 = 10,000 lb.

Because the available towing force of thetruck (17,745 lb) exceeds the force ( 10,000lb) required to tow the tank, the truck cantow the tank under the stated conditions.

Vehicles Towing Inoperable, PoweredVehicles Up Slopes

The maximum slope a vehicle towing an in-operable, powered vehicle can climb is es-timated using the following formula:

Where—

T1 = the maximum towing force (inlb) of the towing vehicle

T2 = the force (in lb) required to tow theinoperable, powered vehicle on level terrain

W1 = weight (in lb) of the towing vehicle

W2 = weights (in lb) of the towed vehicles

NOTE: The relation does not apply to slip-pery surfaces.

Example:

Estimate the maximum slope that can benegotiated by an M1A1 tank towing anM923 truck on one pass, where the slopeconsists of fine-grained soil with a CI of 100and an RI of 0.85 in the critical layer foreach vehicle

Solution:

RCI = 100 X 0.85 = 85

For the M1A1 tank, = RC1 - =85 - 25 = 60. In Figure 7-8, at = 60the maximum towing force (T1) = 63 per-cent of 125,000 = 0.63 x 125,000 = 78,750lb.

7-18 Soils Trafficability

Page 241: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430 -00-1/AFPAM 32-8013, Vol 1

For the M923 truck, = RCI -85 - 30 = 55, In Figure 7-10, page 7-17, at = 55, the required towing force (T2).8.3 percent of 32,500 = 0.083 x 32,500.2,698 lb.

Thus, the maximum slope negotiable by theM1A1 tank towing the M923 truck underthe given conditions is 48 percent.

CLASSES OF VEHICLES

Appendix D contains a list of vehiclesdivided into four classes: self-propelled,tracked vehicles; self-propelled, wheeledvehicles: construction equipment; and truck-trailer combinations. Each vehicle is iden-

itified by its standard nomenclature. Appen-dix D also includes performance categoriesfor each vehicle and each vehicle’s VCI for1- and 50-pass performance.

PERFORMANCE CATEGORIES

Military vehicles can be divided into sevenarbitrary categories according to the mini-mum CI requirementsThe range of and for eachcategory (exceptions are numerous) areshown in Table 7-3.

Determination of VCIs for New or Un-listed Vehicles

For conventional-type vehicles not shown inAppendix D, the following procedure can beused to calculate the VCI: First, a mobilityindex (MI) is calculated for each vehicle.

Table 7-3. Military vehicles and VCI and category of each vehicle

Soils Trafficability 7-19

Page 242: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Although the NRMM calculates actual VCIs based on an axle-by-axle basis, the VCI can be es-timated by using the following steps to calculate the MI and VCI for each type of vehicle, as-suming equal wheel or track loads and all wheel drive: (The NRMM adjusts for uneven loadsand differences in tire pressures. With the newer trucks the may vary 20% with tirepressure changes ONLY.)

NOTE: These formulas could be used to determine estimates of VCI and adjusted by20% to reflect that drivers of trucks with central tire inflation will reduce as required.

Self-Propelled, Tracked Vehicles.

Step 1. Determine the MI.

Step 2. Use Figure 7-11 to convert the MI to VCI. [For MIs above 40, the can be ob-tained from the equation = 25.2 + (0.454 x MI).]

Self-Propelled, Wheeled Vehicles.

(1) All-wheel-drive vehicles.

Step 1. Determine the MI.

7-20 Soils Trafficability

Page 243: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 7-11. Estimated relation of a Ml to a VCI

Soils Trafficability 7-21

wherein contact

pressure = factor

gross weight in lbs

tire width in inches x outsidedtameterof tires in inches number oif tires 2 x

weight factor: Weigh t range Obs)· Weigh t factor equations

less than 2,000 2,000 to 13,500 13,501 to 20,000 greater than 20,000

• gross vehicle weight (lbs) number of axles

Y = 0.553X Y = 0.033X + 1.050 Y = 0.142X - 0.420 Y = 0.278X - 3.115

where X = gross vehicle weight (kips) number of axles

Y = weight factor 10 + tire width in inches

tirefactor= 100

grouser factor: with chains = 1.05 without chains = 1.00

160r-----.-----1I----~----,,~----r_----._----,_----_r--_r~--_r~

140~----;------t------r--f~A------+------~----4---~t+--~~~--~

120~----4------+----

00

E ::J E 80 'c .s ~ 60

40r-----~-+--++------~~--4-~--

20r----7~f---~~--~~--4-----~----~----~----_+----_+----~

10 20 30 40 60 80 70 80 90 100

VCI

Page 244: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Step 2. Enter Figure 7-11, page 7-21, to convert the MI to VCI. [For MIs above 40, the can be obtained from the equation = 25.2 + (0.454 x MI)].

(2) Rear-wheel drive vehicles only. If the vehicle being considered is not equipped with anall-wheel drive, the MI is computed according to the formula for all-wheel-drive vehicles, thenmultiplied by 1.4 to obtain the VCI.

(3) Half-tracked vehicles. The all-wheel-drive formula is used to obtain the VCI of half-tracked vehicles by assuming that the vehicle has wheels instead of tracks on the rear end.The wheels are assumed to be of the same size and have the same load as the front wheels,A grouser factor of 1.1 is used

Towed, Tracked Vehicles.

Step 1. Determine the MI.

(to account for increased traction provided by the rear tracks).

7-22 Soils Trafficability

Page 245: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Step 2. Use Table 7-4, page 7-24, to convert the MI to VCI. [For MIs above 40, the VCI canbe obtained from the equation VCI50 = 25.2 + (0.454 x MI)].

Towed. Wheeled Vehicles,

Step 1. Determine the MI.

clearance = clearance in inches

Step 2. Use Table 7-5, page 7-25, to convert the MI to VCI. [For MIs above 40, the VCI50

can be obtained from the equation VCI50 = 25.2 + (0.454 x MI)].

Limitations. MIs and resultant VCIs from determination of probable RCI that will per-trailers (towed, tracked and towed, and mit a trailer to complete 25 to 40 passeswheeled vehicles) may be used only for without the axle or undercarriage dragging.

Soils Trafficability 7-23

Page 246: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 7-4. Tracked vehicles

NOTE: For Mls above 180, the VCI is obtained from the following equatlons:(1 Pass) VCI1 = 11.48 + 0.2 Ml - {39.2/(Ml + 3.74)}(50 Passes) VCI50 = 28.23 + .43 Ml - {92.67/(Ml + 3.67)}

7-24 Soils Trafficability

Mobility Index vs Vehicle Cone Index For One and Fifty Pas ...

MI VCI VC I.., MI VCI VC I.., MI VCI VC I ... MI VC I, VCI.., MI VC~ VC ....

0 0.0 1.5 33 12.6 30,3 66 19.7 45.9 99 26.4 60,6 132 33.1 75.1

1 1.3 4.1 34 12.8 30.8 67 19.9 46.4 100 26.6 61.1 133 33.3 75.6

2 2.2 6.3 35 13.0 31.3 68 20.1 46.S 101 26.8 61.5 134 33.5 76.0

3 3.0 8.1 36 13.3 31.S 69 20.3 47.3 102 27,0 62.0 135 33.7 76.4

4 3.7 9.6 37 13.5 32.3 70 20.5 47.7 103 27,2 62.4 136 33.9 76.9

5 4.3 11.0 38 13.7 32.8 71 20.7 48.2 104 27.4 62.8 137 34.1 77.3

6 4.8 12.2 39 13.9 33.3 72 20.9 48.6 105 27.6 63.3 138 34.3 77.7

7 5.3 13.4 40 14.1 33.6 73 21.1 49.1 106 27.8 63.7 139 34.5 78.2

8 5.7 14.4 41 14.4 34.3 74 21.3 49.5 107 28.0 64.2 140 34.7 78.6

9 6.1 15.3 42 14.6 34.8 75 21.5 50.0 108 28.2 64.6 141 34.9 79.0

10 6.5

I 16.2 43 14.8 35.2 76 21.7 50.4 109 28.5 65.1 142 35.1 79.5

I 11 6.8 17.0 44 15.0 , 35.7 77 21.9 50.9 110 28.7 65.5 143 35.3 79.9

12 7.2 17.8 45 , 5,2 36.2 78 22.1 51.3 111 28.9 65.9 144 35.5 80.4

13 7.5 18.6 46 15.4 36.7 79 22.3 51.8 112 29.1 66.4 145 35.7 80.8

14 78 19.3 47 15.7 37.2 80 22.5 52.2 113 29.3 66.8 146 35.9 81.2

15 8.1 20.0 48 15.9 37.6 81 22.7 52.7 114 29.5 67.2 147 36.1 81.7

16 8.4 20.7 49 16.1 . 38.1 82 23.0 53.1 115 29.7 67.7 148 36.3 82.1

17 8.7 21.4 50 16.3 38.6 83 23.2 53.6 116 29.9 68.1 149 36.6 82.5

18 8.9 22.0 51 16.5 39.0 84 23.4 54.0 117 30.1 68.6 150 36.8 83.0

19 9.2 22.6 52 16.7 39.5 85 23.6 54.4 118 30.3 69.0 151 37.0 83.4

20 9.5 23,2 53 16.9 40.0 86 23.8 54,9 119 30.5 69.4 152 37.2 83.8

21 9.7 23.8 54 17.1 40.4 87 24.0 55.3 120 30.7 69.9 153 37.4 84.3

22 10.0 24.4 55 17.4 40.9 88 24.2 55.8 121 30.9 70.3 154 37.6 84.7

23 10.2 25.0 56 17.6 41.4 89 24.4 56.2 122 31.1 70.8 155 37.8 85.1

24 10.5 25.5 57 17.8 41.8 90 24.6 56.7 123 31.3 71.2 156 38.0 85.6

25 10.7 26.1 58 18.0 42.3 91 24.8 57.1 124 31.5 71.6 157 38.2 86.0

26 11.0 26.6 59 18.2 42.7 92 25.0 57.6 125 31.7 72.1 158 38.4 86.4

27 11,2 27.2 60 18.4 43.2 93 25.2 58.0 126 31,9 72.5 159 38.6 86.9

28 11.4 27.7 61 18.6 43.6 94 25.4 58.4 127 32.1 72.9 160 38.8 87.3

29 , 1.7 28.2 62 18.8 44.1 95 25.6 58.9 128 32.3 73.4

30 11.9 28.8 63 19.0 44,6 96 25.8 59.3 129 32.5 73.8

31 12.1 I 29.3 64 19.2 45.0 97 26.0 59.8 130 32.7 74.2

32 12.4 I 29.8 65 19.4 45.5 98 ,

26.2 60.2 131 32.9 74.7

Page 247: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 7-5. Wheeled vehicle

NOTE: For Mls above 160, the VCI is obtained from the followlng equations:(1 Pass) VCI1 = 11.48 + 0.2 Ml - {39.2/(Ml + 3.74)}(50 Passes) VCI50 = 28.23 + .43 Ml - {92.67/(Ml + 3.67)}

Soils Trafficability 7-25

Mobility Index v. Vehicle Cone Index For One and Fifty Passes

MI VCI VClao MI VCI. VC I... MI VCI. VC 1.0 MI VCI. VC I ... MI VC~ VC I...

0 1.0 3.0 33 17.0 39.9 66 24.1 55.3 99 30,9 69,9 132 37,6 84.3

1 3.4 8.8 34 17.2 40,4 67 24,3 55.7 100 31,1 70,3 133 37.8 84.7

.2 5.0 12.8 35 17.5 40.9 68 24.5 56.2 101 31.3 70,8 134 38.0 85.2

3 6.3 15.6 36 17.7 41.4 69 24.7 56.6 102 31.5 71,2 135 38.2 85.6

4 7.2 17.9 37 17.9 41.9 70 25.0 57.1 103 31,7 71,6 136 38,4 86,0

5 8.0 19.7 38 , 8.1 42.4 71 25.2 57.5 104 31.9 72.1 137 38.6 86.5

6 8.7 21.2 39 18.4 42.8 72 25.4 58.0 105 32.1 72.5 138 38.8 86.9

7 9.2 22.6 40 18.6 43.3 73 25.6 58.4 106 32.3 73.0 139 39.0 87.4

8 9.7 23.7 41 18.8 43.8 74 25.8 58.9 107 32.5 73.4 140 39.2 87.7

9 10.2 24.8 42 19.0 44.3 75 26.0 59.3 108 32.7 73.8 141 39.4 88.2

10 10.6 25.8 43 19.2 44.7 76 26.2 59.8 109 32.9 74.3 142 39.6 88.6

11 11.0 26.6 44 19.5 45.2 77 26.4 60.2 110 33.1 74.7 143 39.8 89.1

12 11.4 27.5 45 19.7 45.7 78 26.6 60.6 111 33.3 75.2 144 40.0 89.5

13 11.7 28.3 46 19.9 46.1 79 26.8 61.1 112 33.5 75.6 145 40.2 90.0

14 12.0 29.0 47 20.1 46.6 80 27.0 61.5 113 33.7 76.0 146 40.4 90.4

15 12.4 29.7 48 20.3 47.1 61 27.2 62.0 114 34.0 76.5 147 40.6 90.8

16 12.7 30.4 49 20.5 47.5 82 27.4 62.4 115 34,2 76.9 148 40,8 91.3

17 13.0 31.1 50 20.8 48.0 83 27.6 62.8 116 34.4 77.3 149 41.0 91.7

18 13.3 31.7 51 21.0 48.5 84 27.8 63.3 117 34.6 77.8 150 41.2 92,1

19 13.6 32.3 52 21.2 48.9 95 28.0 63.7 118 34,8 78.2 151 41.4 92.6

20 13.8 32.9 53 21.4 49.4 86 28.2 64.2 119 35,0 78.6 152 41.6 93.0

21 14.1 33.5 54 21.6 49.8 87 28.4 64.S 120 35,2 79.1 153 41.8 93.4

22 14.4 34.1 55 21.8 50.3 88 28.6 65.1 121 35.4 79,5 154 42.0 93.9

23 14.6 34.S 56 22.0 50.8 89 28.9 65.5 122 35.6 80.0 155 42.2 94.3

24 14.9 35.2 57 22.2 51.2 90 29.1 65.9 123 35,8 80.4 156 42.4 94,7

25 15.1 35.8 58 22.4 51.7 91 29.3 66.4 124 36,0 80.8 157 42.6 95.2

26 15.4 36.3 59 22.7 52.1 92 29.5 66.8 125 36,2 81.3 158 42.8 95.6

27 15.6 36.8 60 22.9 52.6 93 29.7 67.3 126 36.4 81.7 159 43.0 96.0

28 15.8 37.3 61 23.1 53.0 94 29.9 67.7 127 36.6 82.1 160 43,2 96.5

29 16.1 37.9 62 23.3 53.5 95 30.1 68.1 128 36,8 82.6

30 16.3 38.4 63 23.5 53.9 96 30.3 68.6 129 37.0 83,0

31 1,. ,. ..... .., <>" "'., ., CA A " .. ....... .,

I 69.0

I 130 37.2 83.4

I I I I ,\,I.v \oOlQ.ol:I

I .,..

I ,v. I

I .......

11

>:11

I vv."

32 16.8 39.4 65 23.9 54.8 98 30.7 69.5 131 37.4 83.9

Page 248: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

OPERATION IN COARSE-GRAINED SOILS

Coarse-grained soils present trafficabilityproblems different from those encounteredin fine-grained soils. Some important dif-ferences are—

• Coarse-grained soils do not respond tothe remolding test (except for highlysaturated sands).

• Wheeled-vehicle performance is affectedmore by tire-inflation-pressure changeson coarse-grained soils than on fine-grained soils.

• Level, coarse-grained soils seldom causeimmobilization of tracked vehicles or all-wheel-drive wheeled vehicles whenoperating at low tire-inflation pressures.

• The first pass over a coarse-grained soilarea is the most critical, and sub-sequent passes are usually assured ifthey are made in the first-pass ruts.

Coarse-grained soil in the dry state is easilyrecognizable. It is the round, granularmaterial found on most beaches and insand dunes. When wet, however, it may beconfused with remoldable sand or even fine-grained soil. Because coarse-grained soilsdo not remold there is no need to conductthe remolding test. Use RCI for fine-grained soils and CI for coarse-grained soils(assume RI = 1.0.)

Use the following procedure to ensure thesoil in question is coarse-grained: Push thepenetrometer into the soil. If the color ofthe soil near the penetrometer immediatelybecomes lighter, the internal drainage isgood, which signifies a coarse-grained soil,Another test is to confine a soil sample inthe remolding cylinder and attempt topenetrate it with the cone penetrometer. Ifthe soil is coarse-grained, it will be difficultor impossible to penetrate.

The presence of vegetation in coarse-grained-soil areas indicates the soil is stabilizedand is of high trafficability. This effect isreflected in high CI readings. Testing to

date has not permitted development of CIperformance relations for tracked vehiclesbecause all tracked vehicles have been ableto travel on all level, coarse-grained soils en-countered. Furthermore, the effects of soilstrength on the performance of a giventracked vehicle are minimal.

One-pass performance of all-wheel-drivevehicles has been determined. In mostcases, the first pass is the most critical,and subsequent passes are assured if thefirst pass is successful,

ALL-WHEEL-DRIVE VEHICLES ON LEVELTERRAIN

The ability of a given vehicle to travel onepass in a straight line over level terrain isgenerally assured if the CI of the area isgreater than the VCI. The prediction of theperformance of a wheeled vehicle in sandsis a complex interplay among many vehiclecharacteristics including tire size, tire pres-sure, the number of tires, tire construction,vehicle characteristics, and the soil condi-tion (in terms of soil strength and moisturecontent). Since most natural, sandy soilscontain fine-grained materials that causethe soil to behave like a fine-grained soil,only dry-to-moist, poorly-graded sands (SP)are evaluated using coarse-grained vehicleperformance relationships in NRMM orCAMMS.

Other sandy soils with appreciable quan-tities of fine material (SM, SC, SM-SC) aretreated in the NRMM as fine-grained soils.The need to evaluate the interplay amongterrain and vehicle characteristics requiresthat the coarse-grained soil predictiverelationships be computerized into theNRMM. Therefore, these relationships can-not be simplified to a point where theycould be displayed as figures in this chap-ter. The relationships do follow the trendsof the fine-grained relationships, and theycompute a minimum soil strength require-ment for traffic based on measuredCI (RI is considered 1.0 or greater for these

7-26 Soils Trafficability

Page 249: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

soils). Speed predictions can then be madefor these areas.

In coarse-grained soils, the performance ofwheeled vehicles is generally affected mostby tire pressure. To optimize vehicle perfor-mance, tire pressures should be reduced tomud, sand, and snow pressure, at a mini-mum, or to the emergency tire pressures ifspeed is not a requirement. In this man-ner, vehicle ground pressure is decreasedfrom on-road, and vehicle traction is maxi-mized for the terrain conditions encountered.

TRACKED VEHICLES ON LEVELTERRAIN

As a general rule, tracked vehicles are ableto travel on all level, coarse-grained soilsregardless of soil strength. Performancepredictions in the NRMM are made for twocategories of tracked vehicles; flexible,found on most military vehicles, or gir-

derized, found on most bulldozer-typevehicles.

Vehicles with girderized tracks generallyproduce higher tractive forces on SP soilsthan do flexible-tracked vehicles.

CALCULATIONS OF VEHICLE CONEINDEX

Calculation of a coarse-grained VCI for avehicle configuration is considered beyondthe scope of this manual. These predic-tions are made using the comprehensiveNRMM. In general, wheeled vehiclesoperating in sands should use the lowesttire pressures possible and all-wheel-drivefor maximum off-road performance. Theuser should be aware that immobilizationcan easily occur in these soils, especially ifthe soils are dry and loose, and shouldprepare for such emergencies. Trackedvehicles generally do not suffer immobi-lization on level SP soils.

TRAFFICABILITY DATA

The objective of mapping trafficability datais to provide commanding officers with anestimate of an area’s trafficability prior toactual operation. The estimate consists ofplacing symbols that describe the traffica-bility of a small area at strategic points onexisting maps as shown in Figure 7-12,page 7-28. The maps produced by the tech-niques described in the following para-graphs are elementary compared with thecomplicated and comprehensive maps nowin production for use with the NRMM.

ESTIMATING

Trafficability can be estimated if weatherconditions, soils, and area topography aregenerally known. Weather and climatic in-formation usually are available, even forremote areas, from meteorological records,climatology textbooks, or personnel inter-rogation. Soils and topography data maybe obtained from topographic, soils, and

geologic maps; aerial photos; or interroga-tion.

The accuracy of the trafficability estimatedepends on the type, quantity, and accur-acy of the available data. The analyst’sability to interpret the data is also impor-tant, especially if soil types must bededuced from geological maps and airphotos.

Weather Conditions

For estimating trafficability, consider onlytwo general weather conditions—the “dryseason” and the “wet season.”

Dry Season. A dry season is defined as atime when climatic and vegetation factorscombine to produce, in general, low soilmoistures. For temperate, humid climates,such as the United States east of the Missis-sippi River, the dry season is from aboutthe first of May to the first of November. Inthis season, evaporation of water from the

Soils Trafficability 7-27

Page 250: Army Construction Manual FM5 430 Vol1 Entire

Figure 7-12. Photomap with trafficability data

FM 5-430-00-1/AFPAM 32-8013, Vol 1

7-28 Soils Trafficability

Page 251: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

soil is high because of long days, hightemperatures, and few clouds, and water israpidly extracted from the soil andtranspired to the atmosphere by growingplants. A dry season may also occur atother times of the year as a result of longperiods of fair weather. Areas of aridclimates may be considered to be constantlyin a dry season.

During the dry season, fine-grained soilsand remoldable sands of any type usuallyare trafficable and, in general, are of highertrafficability than dry, coarse-grained soils.The trafficability of dry, coarse-grained soilsis poorer than that of all wet, coarse-grained soils except quicksand. Even inthe dry season, trafficability of any type ofsoils is affected by a high water table thatresults from underground springs, low-lyingand poorly drained soils, or any other cause.

Wet Season. A wet season is defined as atime in which weather conditions combineto produce high soil moistures. In temper-ate, humid climates, the wet season ex-tends from about the first of November tothe first of May. During the wet season, fre-quent rains, low temperatures, heavy cloudcover, and the absence of growing plantstend to keep soil moisture near a maximumvalue. Melting of snow and thawing of pre-viously frozen soils may also produce wetsoil conditions. Wet seasons may occur atany time as a result of prolonged rains,floods, or irrigation. Adding moisture to asoil affects the strength of that soil; the ef-fect differs with soil types.

Topography and Classification of Soils

The configuration of the soil surface andsoil types in a given area are determinedfrom the sources that follow.

Aerial Photos. Elevations and slopes can beestimated by personnel who are properly in-structed to read (with the aid of stereopairs)and interpret information in aerial photos.Accurate elevations and slopes can be ob-tained with mechanical equipment byoperators trained to use such equipment.Locations of rivers, forests, escarpments,

and embankments can also be obtainedfrom aerial photos.

The techniques for identifying soils fromaerial photos are so complex that only well-trained personnel can fully use aerialphotos for this purpose. However, somegeneral information can be obtained by per-sonnel with a minimum of training. For ex-ample, orchards are usually planted in well-drained, sandy soils; vertical cuts areevidence of deep loessial (silty) soils; andtile drains in agricultural areas indicate thepresence of poorly drained soils (probablysilts and clays).

In a given photo, light color tones generallyindicate higher elevations, sandier soils,and lower soil moisture than those signifiedby dark color tones. However, the samecolor tone may not signify the same condi-tions in the same photo and may signify anentirely different condition in another aerialphoto. In addition, natural soil tones maybe obscured and modified by tones createdby vegetation (natural and cultivated),plowed fields, and cloud shadows.

Geologic Maps. Geologic maps show parentmaterial and age data. With that informa-tion and a general knowledge of climate,topography, and vegetation, trained analystscan estimate the soil types likely to befound in the area.

Soils Maps. Trafficability can be estimatedrapidly from maps that delineate surfacesoils according to the USCS, although thesemaps are scarce. The more common typesof soils maps are those using an agricul-tural system of soil classification. In forma-tion from agricultural maps must be trans-lated into engineering terms before a traf-ficability estimate can be made. No exactmethod exists for doing this, but analystsfamiliar with the classification systems canusually make good translations. For ex-ample, the term “loam” in the agriculturalclassification system usually includes CLand ML soils in the USCS.

Topographic Maps. Physical features suchas rivers, streams, cultivation, forests, and

Soils Trafficability 7-29

Page 252: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

roads can usually be identified from atopographic map. Estimates of surfaceslopes can be made from the contour lines(lines passing through points of equal eleva-tion).

For trafficability classification purposes,topography has been divided into two clas-ses: low topography and high topography,Low-topography areas are those at compara-tively low elevations with respect to sur-rounding terrain, and high-topographyareas are those at comparatively high eleva-tions. Absolute elevation has no sig-nificance in identifying the topographyclass. Low-topography areas are usuallypoorly drained and have water tables occur-ring within 4 feet of the surface at sometime during the year. High-topographyareas are usually medium-well to well-drained and do not have water tableswithin 4 feet of the surface at any timeduring the year.

TRAFFICABILITY MAPS

A wide variety of mobility-related productscan be obtained from computerized mobilitymodels such as the NRMM or CAMMS.Input terrain data includes land use: ter-rain slope; obstacles; soil types; vegetationtype, density, and spacing; surfacegeometry; linear and hydrologic featuredata; and road and trail data. This data isused by the models with input vehicle datato make speed or GO/NO GO predictionsfor each individual terrain unit (on a quadsheet) formed by the complex interplay ofthe input variables. Visual displays or hardcopies of the video displays can be used forsuch tasks as vehicle and terrain analysis,operational planning, route selection, con-voy planning, or unit-movement prepara-tion.

Comparison visual products can also be ob-tained to show quad-sheet-sized differencesin the mobility performance levels of red orblue vehicles to contrast the performancesof a vehicle in a variety of configurations,such as with different tire pressures, withand without towed loads, or with differentload configurations. The derived displayscan then be enlarged via “zoom” techniques

to precisely plan the optimum route for theconfiguration.

Cross-country traverse or route movementscan be configured to show the additive ef-fects on vehicle speeds of mined areas,obstacles emplaced, choke points, or gapcrossings, together with changes in vehicleconfigurations which may result as a conse-quence of offensive or defensive actionsduring tactical or combat operations. Themodels may also be used by materiel andhardware developers to determine the ef-fects of proposed designs or changes onmanual vehicle performances. Thus, theuses and displays achievable through theNRMM or CAMMS computer models arebasically limited only by the imagination orrequirements of the user.

As an example of hard-copy outputs fromthe mobility models, three graphicalproducts are presented in Figures 7-13through 7-15, pages 7-31 through 7-33, asthey would appear on the console of aCAMMS computer. Figure 7-13 depicts thecross-country speed performance of a USArmy M1A1 tank in Germany. The dif-ferent cross-hatched areas are used todepict cross-country mobility rates of 0-10,10-20, 20-30, and greater than 30kilometers per hour (kph) for the tank. Theshading and the speed increments are ar-bitrary. The initial assessment of the dis-play in Figure 7-13 would indicate theplatoon can move across this quad atgreater than 30 kph except for scatteredareas where speeds will drop to 20-30 kph.River and stream crossings will be requiredin west-east movement across the quad,and these crossings will require 30 minutesexcept for a few crossing points whichwould require “zoom”’ techniques to locate.Scattered NO GO areas should be avoided,especially those concentrated in the upperportion of the quad. On-road mobility inmost areas should exceed 10 kph,

Figure 7-14 is a display of potential landingzones from CAMMS for the same areas asin Figure 7-13. The potential landing-zonemap indicates primarily unfavorable landing-zone sites, with favorable sites located inthe northwest third and southeast corner of

7-30 Soils Trafficability

Page 253: Army Construction Manual FM5 430 Vol1 Entire

Figure 7-13. Off-road speed

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Soils Trafficability 7-31

>- • .J ....... I: lLl,'j') ~lJr .:cor

1:,1 o I'....; W).;.V OH.;. z ..... :r: W • .J lJ.J 0 ..... 1-Z LCJ (') oo:~ U!: I:~I

11. 'Q

II: Ca. L1J 1: I)) (.:J

Il: o .... ~ 1.t.J:Z:L1J lJ.J t: :=-11. 0 11: 1)"1

o 11: o ~ I ....

I!.. '1: LL .... I:' 4:

I!I .::C I!I I!I Il...

I:!:) "J (1) ~ .... .... :t-

....

..... ~ Ul :T E

't:I Cl) Cl) Cl.. (I)

I::;) 't:I I:!:) 1':1 e :T :t:

0

~ ..... (1) t!. ,)')

~ ((I ::;, .~ lI..:

1:1) 0') ((,

Page 254: Army Construction Manual FM5 430 Vol1 Entire

Figure 7-14. Potential landing zones

FM 5-430-00-1/AFPAM 32-8013, Vol 1

7-32 Soils Trafficability

w .... z ()

1:- Il: r-.J

I!:I

W 1:.,:1 ,!, ~ .. _J .'-'. (.;! Z :C lLJ (I:. '1: .... ., .....

Cl! LJ:r: Il: Cl

.1: ():r: w z I :: . • 1: r-

~: .1: '1: ...J I~" C) U ~-~ Z !.J.J )- '_' ...J :r l:.J

U:.~- '1: Il::: 7: ... -4 r: ..... ....... r-!.J.J _J W r- Ij)

C) ~ ... I- z w W W rL ...J :z: CC ':I~I z r- I:. ....

• :) (J)- - , Cl ...J .:. -(J!:: (I) -:' rL I)) In

I (.:. Z w .... ...J

W r!j If) ...J .1: [- rn Il:

.1: Cl I~I Z LJ::: Il::: :=-

'1: w Cl '1: • rn r- :: . lL.

\." :l:: '1: .1: Z -, = lL. ::0 -,rolrmD~ !: ::: I ::

Il: ~.,:-

..... :r .....

" . {Ij ",," ___ I~I

3:::::::::::::~::::::::::::::' " " " " t " I •

11.1i~~ ...... .!)

::t-

.!) ,!)

::t-

,'-:1 ,'-:1 1~r.1

(I) ,'-:1 0:(1

b') (J)

Cl) Cb c: 2 tn c:

=t; c: .! -as ;; c: ~ 0 Cl

o:t .... ~

e :::J .~ LL:

Page 255: Army Construction Manual FM5 430 Vol1 Entire

Figure 7-15. USCS soil-type descr

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Soils Trafficability 7-33

r

)_.~ 1-..

r: W LI) u::aI: ,I: 0 r:

:r:a: o ,'.J W:''-v Uj~ Z ....... r:

Ll... ..... ~ o Q)

~w 00

I,lJ W

ZLl...

0:'­ZoI: oI:...J 0) ()

· ............... ---'---... -.::-:.:~ ........ -................... -... ---~ '-............ -... , .--

· ............ -..... -"-"'-a._ ... :~-; -"'-"".--- ---......... _-- .• ~ '.. ..-.-......... -~.:. ............. _-... ~ ~ ". -.-.... -.-...... -. '-.. . ........... ....

"'::-"'-'~~'-'.-::::::.'.'.~.'. ""-.-.. -.. -..... ~.-........ . .-.. --..... --.--.... -.. --.--~

............... -.• .-..... '-'" ---'-... -. .... _-._- .. -.. .. ..... _-... __ ...

""- -'--""""'--~ .. ~ .. '~.' · "" -... _-..... -"""-..... ' .. .• -~-~.-......•...... -.. ,

...... -.. -... ~ .•.. '----..... .

.'. "

, -. ..... :r

W -l 'I: () Ij)

(Ij !:-____ I~I

:::!-"

"

"

"

"

--"'--- -.. , -"-' .. -.. '-.. ............ ... '--.. '-..... -" ........ ._--.... <::::::> :: ~.

"

-,

"

"

"

"

"

"

"

"

"

". "

"

" .'

.... I:!:) :::!-

I ,!:II I~I

:::!-

,'5'.1 ,'5'.1 (1'.1

':c' ,'5'.1 (1'.1

(£, fJ) {(J

~')

0')

c:: . 2 .... .~ '-(,) Cl)

~ Cb

~ ..!.. . ... () Cl)

Cl) (,)

~ Iti .... r-!..

I!

~

Page 256: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-80132, Vol 1

the quad. This display helps guide theuser to the most suitable sites for landing-zone construction.

Figure 7-15, page 7-33, is a display ofUSCS soil-type descriptions from CAMMSfor the same area as in Figures 7-13 and 7-14, pages 7-31 and 32. This display indi-cates the locality of soil types that may beuseful in scouting for constructionmaterials or sites more suitable for roadand airfield construction.

Thus, the mobility analysis is now a verypowerful tool for the military planner. It in-tegrates natural features of the landscapewith vehicle parameters to produce mobilityproducts which can be used by materieldevelopers, planners, war garners, or com-bat soldiers in the field to plan real-timered and blue actions in terrains around theworld.

MANUALLY MAPPING SOIL CONDITIONSAND TRAFFICABILITY

Although mapping soil conditions and traf-ficability through manual means is rarelydone since the development of computerizedmobility models, it is important that the pro-cedure be presented should the need everarise. The following paragraphs describethe proper procedure in detail:

VCIs vary widely, and it is desirable topresent basic terrain data that can be com-pared directly with VCIs. The four basicterms describing trafficability are: soiltype, RCI, slope, and slipperiness.

The soil-type condition is shown by A, B, C,or D (as defined in Table 7-6); RCI is shownby a single number; slope, in percent, isshown by a single number; and slipperinessis shown by N, P, or S. (Stickiness effectsare not considered significant enough to in-clude on maps.) The four factors may bepresented (as in Figure 7-12, page 7-28) infractional form with two items in thenumerator and two in the denominator.

Example:

In the fraction

B is the soil type condition (from Table7-5, page 7-25), 80 is the RCI, 25 is a 25-percent slope, and S is a slippery surface.

Solution:

To interpret the meaning ofB - 8 025 - S,

first find in Figure 7-7, page 7-12, thefor the three vehicle types on 25-percentslopes. For wheeled vehicles, = 17; forconventional, tracked vehicles, = 13;and for long-grousered, tracked vehicles,

= 11. Then, for each type of vehicle,find the . Thus, the area is trafficablefor wheeled vehicles with less than63 = RCI - or = 80-17),for conventional, tracked vehicles with

less than 67, and for long-grousered,tracked vehicles with less than 69.

Since the slope may be slippery, the opera-tions officer should order all wheeledvehicles to be equipped with tractiondevices and should expect some sliding andsteering difficulty. The photomap in Figure7-12 shows how areas can be delineated inthis manner.

Example:

Fifty M60 tanks (102,000 lb) and 50 M923trucks (32,500 lb) are to be moved frompoint X to point Y in the area shown in Fig-ure 7-12. Movement must be cross-countrybecause the roadnet is heavily mined.

Solution:

Step 1, From Appendix D:

Vehicle

Tank 20 48Truck 30 68

Step 2. Examine the possibility of single-file travel through flat terrain. All vehiclescan negotiate areas 1 and 6. The RCI of 50for area 3 will allow passage of all 50 tanksbut not all 50 trucks. The tanks canproceed in single file from X through areas1, 3, and 6, consecutively to Y. However,

7-34 Soils Trafficability

Page 257: Army Construction Manual FM5 430 Vol1 Entire

et-season trafficability characteristics of fine-grained soils and remoldable soils

FM

5-430-00-1/AF

PA

M 32-8013, V

OL

1

So

ils T

rafficability

7-35

Table 7-6. Wet-season trafficability characteristics of fine-grained soils and remoldable soils

Slipperi- Sticki-

t

Probable I Probable Probable ness ness Group Soils USCS Cl Range RI Range RCI Range Effects Effects Concepts

A I Well-graded gravels GW 35 to 100 Not Not Slight to None Will support Poorly graded gravels CP applicable applicable none continuous traffic of Well-graded sands SW tracked military Poorly graded sands SP vehicles or aJl-wheeI-

drive trucks with high-flotation tires. Performance will increase with a decrease in tire pressure. Moist sands are good, dry sands only fair. Wheeled vehicles with standard tires may be immobilized in dry sands.

B Inorganic clays of high CH 55 to 165 0.75 to 65 to 140 Severe to Severe to Usually will support plasticity (heavy clays) 1.35 slight slight more than 50 passes

of military vehicles. Going will be difficult at times.

C Clayey gravels, gravel-sand- GC 85 to 175 0.45 to 45 to 125 Severe to Moderate to Often will not support clay mixtures 0.75 slight slight 40 to 50 passes of

Clayey sands, sand-ctay SC military vehicles but mixtures usually will support

Gravelly clays, sandy clays, CL limited traffic. Going inorganic clays of low to will be difficult in medium plasticity, lean most cases. clays, silty clays

D Silty gravels, gravel-sand IGM 85 to 180 0.25 to 2~ to 120 Moderate to Slight Usually will not silt mixtures 0.85 slight support 40 to 50

Silty sands, sand-silt mixtures SM passes of military Inorganic silts and very fine ML, CL-ML vehicles. Often will

sands, rock flour, silty or not permit even a clayey fine sands or clayey single pass. Going silts with slight plasticity will be difficult in

Inorganic silts, micaceous or MI most cases. diatomaceous fine sandy or silty soils, elastic silts

Organic silts and organic silly I OL clays of low plasticity I

Organic clays of medium to OM high plasticity, organic silts

Page 258: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

the trucks will have to fan out and usemore lanes with less than 50 vehicles insingle file to ensure passage through area 3( to 30, RCI less than 50). The slipperi-ness of area 3 may present an insurmount-able problem for the trucks unless tractiondevices are available.

An alternative route that would be safe forall vehicles would be through areas 1, 5,and 6, consecutively, provided the slope ofarea 5 can be negotiated. For this example,it is assumed that the combination of60-percent slope and other terrain obstaclesin areas 2 and 4 would not allow travelthrough them.

Step 3. Check the slope-climbing ability(using Figure 7-7 and Figure 7-8, pages 7-12 and 7- 13) of both vehicle types in area

1 PassVehicle Slope

5:

Tank 30% 6 6 + 2 0 = 2 6Truck 30% 11 11 + 30 = 41

50 PassesVehicle Slope

T a n k 30% 15 15 + 48 = 63Truck 30% 20 20 + 68 = 88

The tanks can negotiate the 30-percentslope in single file (available RCI of 80 isgreater than the required RCI of 63). Alltrucks cannot negotiate the slope in singlefile (available RCI of 80 is less than the re-quired RCI of 88), but they can fan out andnegotiate the slope on a one-pass basis(available RCI of 80 is greater than the re-quired RCI of 41). The conclusion is thatall vehicles could travel from X to Y

through areas 1, 5, and 6, respectively,provided caution is used with the trucks.This route is shown as a dashed line.

This example indicates the usefulness ofmapped trafficability data in planning opera-tional exercises.

The presentation of trafficability data forstrategic purposes is most effective whenone vehicle is used as a standard, referencevehicle. For example, if the vehicle selectedhas a VCI of 49 and the information onthat specific vehicle is presented, traffica-bility data for that vehicle can be general-ized and considered applicable to allvehicles with a VCI of 49 or less.Recommended techniques of mapping traf-ficability data follow:

• The base of the map should be a stand-ard topographic map printed in a graymonochrome with streams in a strongblue color.

• The four soil-slope combinations shouldbe shown as trafficability symbols, as in-dicated in Table 7-7. (See previousweather conditions.)

• Obstacles should be indicated by redadded numbers circled in red.

• Forests should be indicated by ap-propriate open-type patterns in stronggreen.

Ž The reverse of the trafficability mapshould contain an inset map of the prin-ciple physiographic provinces,landforms, geologic areas, and relateddata used in making the analysis. Theinset map should show in detail all im-portant data on soils, topography, andobstacles that cannot readily be shownon the face of the map.

SOIL-TRAFFICABILITY CLASSIFICATION

Soil classification of a specific area can be raphy (high or low) has been identified, andaccomplished rapidly for seasonal (high- the VCI for vehicle category has beenmoisture) conditions when the soil has been determined (from Table 7-3, page 7-19, orclassified in terms of the USCS, the topog- Appendix D) or computed, when necessary,

as previously described.

7-36 Soils Trafficability

Page 259: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 7-7. Trafficability symbols

FINE-GRAINED SOILS

The trafficability classification of fine-grained soils is shown in Table 7-8, page7-38.

The interpretation of the example shown inthe “Low Topography, High Moisture Condi-tion” graph of Table 7-8 for a level area ofMH soil follows:

• Vehicles with a or equal toor greater than 84 will have a less than50 percent probability of traversing thearea.

• Vehicles with a or equal toor greater than 56, but less than 84,will have a probability equal to orgreater than 50 percent, but less than 5percent, of traversing the area.

• Vehicles with a or equal toor greater than 18, but less than 56,will have a probability equal to or

greater than 75 percent, but less than90 percent, of traversing the area.

Vehicles with a or less than • 18 will have a probability equal to orgreater than 90 percent, but no morethan 100 percent, of traversing the area.

COARSE-GRAINED SOILS

The trafficability classification of coarse-grained soils can be obtained from Figure7-16, page 7-39. The classification inter-pretation is the same as for the traffica-bility of fine-grained soils from Table7-8. To use Figure 7-16, identify only thecoarse-graincd soils (location and origin)and determine the VCIs from the equationpresented earlier in this chapter. Figure7-16 applies to wheeled vehicles only. Theeffect of the strength of coarse-graincd soilson tracked-vehicle performance is negligible.

Soils Trafficability 7-37

Page 260: Army Construction Manual FM5 430 Vol1 Entire

ble 7-8. Soil-trafficability classification in U

SC

S term

s

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

7-38 S

oils

Trafficab

ility

Table 7-8. Soil-trafficabi/itv classification in uses terms

Vehicle category Soli Strenath measurements Effects of

I 1 I I 3 I 4 I 5 I I type Probable ranae 1 Mean I Slipper- I Stick- 2 6 7 symbol Cl I RI I RCI RCI Iness 2 lness VCI 50

Ffl 40H .1 80 ·1 100 120m T 140 160 180 12001

I I I I I I I ItGH TOPOGRAPHY, WET-SEASON CONDmON

GGW,GP NONE NONE sw,sp NONE NONE SP-SM 125-241 1_19-2_17 196-316 256 NONE NONE GM 230 NONE NONE SM 130 - 224 o_n -1.83 137 -267 212' NONE NONE CH 167-217 0_84 - 1.10 158-210 184 SLIGHT MOOERATE GC 165' SLIGHT SLIGHT se 127-231 g~:~:~ • 104-~ 156 SLIGHT SLIGHT MH 151 -211 • 64-160 112' SLIGHT SLIGHT CL 123-211 0.59-0.95 82-180 131 SLIGHT SLIGHT SM-SC 147-185 0.47-1.13 65-211 138 SLIGHT NONE loll 118-224 0.46-1.02 67-189 128 SLIGHT NONE CL • 101. 111 -209 0.44 -072 54-136 95 SLIGHT NONE

LOW TOPOGRAPHY, WET.sEASON CONDIllON

GW,GP NONE NONE SW,SP NONE NONE SP-SM 300 0.94 262 282' NONE NONE CH 98-194 0.74-1.14 81-193 137 SEVERE SEVERE GC 130' MODERATE MODERATE SC 97-257' 0.59 -121' 61 - 255' 158' MODERATE MOOERATE SM-se 160-216' 0.45 - 1.31' 72-208' 140' SLIGHT NONE MH 94-170 0.51 -0.99 48-162 105 SEVERE MOOERATE GM 125' SLIGHT NONE SM 109 - 217 029-1.03 34 -188 111 SLIGHT NONE CL 90-188 0.46 - 0.88 46-146 96 MODERATE MOOERATE lolL 102 - 200 027-0.81 34-134 64 MODERATE SLIGHT CL lolL 85-165 0.31 - 0.69 34-96 65 MODERATE SLIGHT OL 95-135 0.38-0.74 41-89 65 MODERATE SLIGHT OH 64-1~ 0.32-0.78 li: ~1~ ~. MODERATE SLIGHT Pt 76-90 0.45-0.67' MODERATE SLIGHT

LOW TOPOGRAPHY, ItGH MOISTURE CONDITION GW,GP NONE NONE SW,SP NONE NONE CH 69-167 0.64 - 1.02 48-146 97 SEVERE SEVERE GC 90' SEVERE MOOERATE se 88' SEVERE MOOERATE $M-se 150-182' 0.45- 0.63 • 66-98' 82' MODERATE SLIGHT MH 83-151 0.46- 0.92 43-123 83 SEVERE SEVERE CL 71-165 0.42- 0.80 39-117 78, SEVERE MOOERATE SP-SM ~, SLIGHT NONE GM SLIGHT SLIGHT SM 81-183 0.15-0.87 12-126 69 SLIGHT SLIGHT 101. 81-171 0.26- 0.60 22-88 55 SEVERE SLIGHT CL-1oI. 71-155 g:~.O.53 26-66 46 SEVERE SLIGHT OL 87' 49' 49' MOOERATE SLIGHT OH 42-1~ 0.26- 0.66 21-49 35 SEVERE SLIGHT Pt 76-90 0.45 - 0.61' 41-51' 46' SEVERE SLIGHT

NOTE: Vehicle calegory and Cl range are given in Table 7-3, page 7-19. Probability (Pr) of a vehicle (or 50 vehicles) traversing level terrain 'Based on +1 and -I standard deviation from the mean. 'Applies only to wheeled vehicles without traction devices. 'Estimllted from lextural, plllsticity, and organic properties of soil under given moisture condition. 'Based on analysis of less than five samples.

c::=J ExceDenl 90% ~ 100% So 100% C Good reliability, based on analysis of data

c::J Good 75% So Pr < 90% ~ Fair 50% ~Pr < 75% = Fair reliability, based on judgement

-A vehicle with a VCI of 60 would have a 50 to 75% chance of "GO" on an ML soil of _ Poor 0% So Pr < 50%

low topography, wet-season condition.

Page 261: Army Construction Manual FM5 430 Vol1 Entire

Figure 7-16. T

rafficability classification of dry-to-moist, coarse-grained soils

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

So

ils T

rafficability

7-39

Coarse-grained soli Location Origin

Beach Quartz

Beach Coral

Beach Volcanic

Desert Quartz

Vehicle cone index (VClpS)

o 20 40 60 80 100 120

I I

Probability (Pr) of wheeled vehicle traversing level terrain

I .~ k{{{{:]

~ -Excellent ~ 90-,. ~ Pr 100-,.

Good 75.,. '.S.. Pr < 90.,.

Fair 50." ~ Pr < 75".

Poor 0.,. ~ Pr < 50.,.

Figure 7-16. Trafficability classification of dry-to-moist, coarse-grained soils

Page 262: Army Construction Manual FM5 430 Vol1 Entire

CHAPTER 8

nance, Repair, and Rehabilitation of Roads, Airfields, and HeliportsMaintenance and Repair Considerations Maintenance and Repair Operations Road Maintenance Airfield and Heliport Maintenance

FM 5-430-00-1/AFPAM 32-8013, Vol 1

MAINTENANCE, REPAIR, ANDREHABILITATION OF ROADS,AIRFIELDS, AND HELlPORTS

Maintenance is the routine prevention and correction of normaldamage and deterioration (from use and the elements) to keeproad and airfield surfaces and facilities in usable condition.Repair is that work necessary (other than maintenance) to correctdamage caused by abnormal use, accidents, hostile forces, andsevere weather. Repair includes the resurfacing of a road orrunway when maintenance can no longer accomplish its purpose.Based on this manual, rehabilitation is the restoration of cap-tured airfields and heliports to usable condition. Rehabilitationresembles war-damage repair except that it is accomplishedbefore occupancy.

MAINTENANCE AND REPAIR CONSIDERATIONS

The purpose of all maintenance and repairactivities is to keep roads, airfields, or otherinstallation surfaces in as usable and assafe a condition as the situation permits.Prompt and adequate maintenance is impor-tant. Once surface deterioration or destruc-tion has started, it can proceed very rapid-ly. Postponing minor maintenance jobs canresult in the development of major repairjobs involving the subgrade, base course,and surface.

Use the following guidelines when perform-ing maintenance and repair work:

• Ensure that maintenance and repair ac-tivities interfere as little as possiblewith the normal flow of traffic. When-ever feasible, plan and perform main-tenance and repair activities to permitat least partial use of the facility. Whenit is necessary to close the facility to alltraffic, select alternative facilities or per-form repair work at night or during

periods of reduced activity. Reopen thefacility as soon as practicable.

• Remedy the cause before repairing theproblem. For example, surface repairsmade on a defective subgrade arewasted. All maintenance and repairjobs should include an investigation tofind the cause of the damage ordeterioration. To ignore the cause is toinvite the prompt reappearance ofdamage. Ignore the cause only whenmaking temporary repairs to meet imme-diate, minimum needs under combat orother urgent conditions.

• Maintain and repair existing surfaces asclosely as possible to the original con-struction in strength, appearance, andtexture. Spot strengthening may createdifferences in wear and traffic impactthat can harm adjoining surfaces. Also,uniformity simplifies maintenance andrepair operations.

Maintenance, Repair, and Rehabilitation 8-1

Page 263: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• Prioritize the needed repairs based onthe tactical requirements, the trafficvolume, and the hazards that resultfrom complete failure of the facility. Forexample, roads used for tactical-opera-tions support take priority over less

essential facilities. One pothole in aheavily used road that is in otherwiseexcellent condition takes priority overrepairs to less heavily used roads inpoor condition.

MAINTENANCE AND REPAIR OPERATIONS

Maintenance and repair operations includemany tasks besides improving the pavementcondition. To ensure a comprehensive main-tenance and repair operation, incorporatethe following tasks:

The

Routine inspections.

Material stockpiling.

• Maintenance and repair of all relateddrainage systems.

• Maintenance and repair of the actualpavement, including dust and mud con-trol and snow and ice removal.

• Miscellaneous tasks, including themaintenance and repair of necessarybuildings, structures, and utilities, andthe operation of necessary utilities.

MAINTENANCE INSPECTIONS

purpose of maintenance inspections isto detect early evidence of defects before ac-tual failure occurs. Frequent inspectionsand effective follow-up procedures preventminor defects from becoming major repairjobs. Inspect surface and drainage systemscarefully during rainy seasons and springthaws and after heavy storms.

Surface Inspection

Surface defects can usually be attributed toexcessive loads, inferior surfacing material,poor subgrade or base conditions, inade-quate drainage, or a combination of theseconditions. Surface inspections should in-clude a complete inventory of the currentpavement defects. Careful investigation ofthe causes of the defects will allow for time-ly maintenance to prevent the pavementdefects from requiring repair.

Drainage Inspection

Ensure that all drainage channels andstructures arc unobstructed. Check cul-verts and drainage lines for structuraldamage. Inspect check dams for debris andexcessive erosion. Investigate water pond-ing on or adjacent to surfaced areas. In-spect the system drainage during or afterevery storm. Also, thoroughly inspect thesystem in late fall to prepare for winter andin early spring to ensure minimum springbreakup difficulties. Inspect subsurfacedrains at least twice a year.

MATERIALS FOR MAINTENANCE

Generally, materials required in the main-tenance and repair of roads and airfieldsarc the same as those used in new construc-tion. Open pits and prepare stockpiles ofsand and gravel; base material; andpremixed, cold patching materials at con-venient places and in sufficient quantitiesfor emergencey maintenance and repair. Ar-range stockpiles for quick loading andtransporting to the road or runway. Buildonc of the several types of trap-and-chutecombinations described in Chapter 5 of TM5-332 for sand, gravel, and base materials,Premixed. cold patching material may beprepared as explained in Chapter 9 of TM 5-337. Maintain small quantities of aggregatein dry storage for concrete patching.

DRAINAGE MAINTENANCE

Defective or inadequate drainage causesmost pavement failures and deterioration.Pending or delayed runoff of surface waterallows seepage into the pavement structureunless the surface is tightly sealed.

8-2 Maintenance, Repair, and Rehabilitation

Page 264: Army Construction Manual FM5 430 Vol1 Entire

Surface Drainage

Mark areas where pending occurs on sur -faced areas. Correct such problems by fill-ing or raising depressions and by providingoutlets for water blocked by high shoulders.Control penetration of storm water throughpavement by scaling joints and cracks.Keep unpaved roads and airfields crownedto prevent water from remaining on theroad or airfield where it will saturate andweather the surface. Maintain crowns andsuperelevations with graders or drags.

Shoulders

Keep shoulders smooth and graded so waterwill drain from the surfaced area towardthe ditch. Replace eroded shouldermaterial on paved surfaces with newmaterial. Material cleaned out of ditchescan often be used 10 rebuild shoulders.Shoulders should be kept bladed flush to,or slightly below, the edges of the pavementand should slope away from the pavementto prevent water seepage into the subgrade.

Drainage Ditches

Keep drainage ditches clear of weeds.brush. sediment. and other debris thatobstruct water flow. Maintain ditches as toline and grade. Correct sags and minorwashouts as they occur. Side ditches canusually be maintained with graders.

When cleaning and shaping, avoid unneces-sary blading or cutting that destroysnatural ground cover. Where possible,develop dense sod to stabilize open ditches.Where vegetation is not effective because ofsoil or moisture conditions, erosion may becorrected by lining the ditch with riprap, as-phalt-coated membrane, or concrete.

Inspect check dams in side ditches andclean them regularly. The weir notch of acheck clam must be kept clean or water willcut into the surfaced area at the edge ofthe dam (Figure 8-1). The aprons of checkdams must also be maintained, and pavingmaterial must be replaced when washedout. Dikes or berms may be required alongthe tops of high-fill slopes to prevent gulliesand washes.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 8-1. Check dam

Cut-slope interceptor ditches must be con-sidered for all side-hill and through cuts toprevent gully washing and erosion from thetop of the cuts. If benching or terracinghas been used in the design of the cut, en-sure that the top of each bench is slopedback into the cut to provide for properdrainage. Also ensure that each bench topis wide enough to maintain that drainagewith earthmoving equipment. A good ruleof thumb is to make benches at least aswide as a dozer blade. Figure 8-2, page8-4, illustrates proper terraced side-hill-cutdrainage.

For proper design considerations of cutslopes, refer to Chapter 10 of FM 5-410.

Culverts

Keep culverts clear of debris and sediment(Figure 8-3, page 8-4). This prevents waterfrom cutting around or undermining the cul-verts. Inspect culverts frequently to deter-mine whether they arc func-tioning proper-ly. Cleaning by hand is usually necessaryafter heavy rains.

NONPAVED SURFACES

Basic maintenance of nonpaved surfaces in-cludes shaping the cross section to main-tain adequate drainage anti a smooth, com-pacted surface.

Maintenance, Repair, and Rehabilitation 8-3

Page 265: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 8-2. Side-hill terracing

Equipment

Most surface maintenance consists of lightscraping with grader blades and drags. Mul-tiple-blade drags of iron or iron-shod, heavytimber may be used for normal scraping.Drags are frequently used to float mud andwater off a road and to prevent corrugation

Figure 8-3. Culvert entrance

or washboardingof drag is shown

Materials

of the surface. One typein Figure 8-4.

Materials removed from ditches, other thansilt, some clays, and all organic soils (OL,OH, Pt), may be used on shoulders andtraveled ways. Dispose of silt depositswhen removed; they are not suitable for con-struction. After heavy storms and springthaws, additional material may need to behauled in.

Procedures

Keep traffic areas and shoulders free ofpotholes, ruts, and irregularities. Lightblading will prevent corrugation or wash-boarding. Work from the ditches to the cen-ter of the road to ensure good drainage andproper road crowning. Since loosened, drymaterial cannot be compacted, blading ordragging should be done during or soonafter rains. For prolonged dry spells orwhen surface material will not compact,add water or moist subsurface material

8-4 Maintenance, Repair, and Rehabilitation

Page 266: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 8-4. Improvised road drag

with a rototiller, plow, or scarifier beforecompaction.

Compaction of the graded surface materialwill reduce maintenance and repair for non-paved surfaces. The type of roller used willvary with the material compacted. The cor-rect moisture content will result in themost economical compaction.

Soft spots, indicated by rutting or shovingof the surface, are generally caused by ex-cess moisture, poor subsurface drainage, orunstable material. Determine the source ofexcess moisture and correct the drainage.On traffic areas, cobbles may be used to sta-bilize small areas of failure. Where surfacefailures are caused by pockets of mulch orpeat, it may be necessary to remove the

objectionable material and replace it with amore stable material. When adequaterepairs cannot be made, soft spots can betemporarily reinforced by adding crushedrock or clean gravel.

Keep non paved surfaces crowned to preventwater from remaining on the surface andsaturating the soil. Maintain the crownand superelevation with drags or graders.

Dust control may be a problem under someconditions. Spraying with water or a bitu-minous stabilizer is the most commonlyused method of controlling dust. Dust con-trol is discussed further in Chapter 12 ofFM 5-430-00-2/AFPAM 32-8013, Vol 2.

Examples of road repairs are shown in Fig-ure 8-5, page 8-6.

OILED SURFACES

The routine maintenance of oiled surfacesconsists of shaping and patching. Shapingis done with graders or drags. Patchingmay be done with a mixture of the soil andoil. Oiling is necessary each year becauseoiled surfaces frequently break up in thespring and become very rough. Thoroughscarifying. blading (or dragging), and reshap-ing is necessary before oiling each year.

GRAVEL SURFACES

Maintenance procedures for gravel surfacesare much the same as for nonpaved sur-faces. Continual shaping is needed to main-tain a smooth surface and a uniformcrown, and the drainage system must bekept functioning.

Surface Maintenance

Heavily-traveled, graveled surfaces requireconstant attention by maintenance patrols.Intensive maintenance is required when thesurface is first open to travel. Bumps com-pacted at this time remain in the surfaceand can be corrected only by scarifying oradding more material. Blade or drag thesurface soon after rain until all ruts andholes are filled. Do not work on a dry

Maintenance, Repair, and Rehabilitation 8-5

Page 267: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 8-5. Road maintenance problems and proper corrective action

surface. Maintain a crown of at least 1/2inch per foot. Multiple blade drags or sleddrags can be used for routine maintenance,but graders are necessary for heavy reshap-ing work.

Keep a slight excess of gravel available atthe edges of the roadway and blade ituniformly over the surface in wet weather.Stockpile additional materials in advance offall and winter and prolonged wet periods.Material added or spread on the surfaceduring warm, dry weather is of little value.

Repair of Potholes

Most potholes are caused by material dis-placed by traffic. Initially they are shallowand are readily filled by blading when thesurface is moist. Deep holes require fillingwith additional material. New materialshould be moistened and compacted.

Treatment of Corrugations

All gravel surfaces tend to develop trans-verse or nearly transverse waves, called cor-rugations, which may progress into ruts asdeep as 4 inches and from 1 1/2 to 3 feetapart. After this stage, they become majorgrooves needing extensive repair.

Some blade equipment inherently chattersand starts slight irregularities, especiallywhen the operator attempts to move aheavy cut. Corrugations often appear tostart from small holes or depressions madewhen the road is wet or from an obstruc-tion such as a stick or rock. Other con-tributing factors are a soft subgrade, poorgrading of the gravel, poor binder, and aninsufficient amount of binder.

Corrugations can be prevented to a consider-able extent by frequent maintenance and bythe careful use of maintenance equipment.Once corrugations form, they can be

8-6 Maintenance, Repair, and Rehabilitation

Page 268: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

removed only by thoroughly scarifying,reshaping, and compacting. Regrading, asthis is called, should begin with a thoroughcleaning and reshaping of the shouldersand ditches, continuing across the entireroadway.

Use of Calcium Chloride

Calcium chloride may be applied to a gravelsurface to control or eliminate dust, preventthe loss of material under the whipping ac-tion of traffic, and aid in maintaining adense surface. The usual method is toapply 1 pound of calcium chloride persquare yard in the late spring and 1/2pound per square yard twice during thesummer season. However, the amount ofrain, the volume of traffic, and the charac-ter of the gravel affect the quantities re-quired. Calcium chloride is corrosive tometal surfaces and may require more main-tenance for aircraft and vehicles.

The best time to apply calcium chloride isfollowing a rain and after necessary bladingor dragging is completed. If the applicationcannot be deferred until rain occurs, waterthe surface before applying the calciumchloride. For best results, apply calciumchloride before the traffic area becomes dryand dusty.

PROCESSED MATERIAL SURFACES

Traffic areas composed of processedmaterials (crushed and screened rock,gravel, or slag) are maintained by methodssimilar to those used on gravel surfaces.When coarse, processed materials are used,surface failures are usually in the form ofsharp-edged holes caused by poor drainage.Repairs require cleaning the holes down tothe solid subgrade and ensuring that nosilt, mud, or water remains. Subgraderepairs are then made with a well-gradedsoil aggregate. Surface repairs should con-sist of a well-tamped or rolled-in-place,coarse-graded aggregate of the same grada-tion as the original surrounding surface.

BITUMINOUS SURFACES

The maintenance and repair of bituminoussurfaces are discussed in Chapter 9 ofTM 5-337. Some considerations applicableto bituminous-surfaced traffic areas follow.

Inspection

Maintenance patrols should frequently in-spect bituminous pavements for early detec-tion of failures. Small defects quicklydevelop into large ones, resulting in pave-ment failure unless promptly corrected.Small crews using hand tools can quicklymake minor repairs with a minimum inter-ruption of traffic. Large, bituminousrepairs require more time, personnel, andequipment. Such repairs also interfere withtraffic. In extreme cases, detours may berequired to avoid complete traffic stoppage.

Patches

All patches should be trimmed square oroblong with straight, vertical sides runningparallel and perpendicular to the centerlineof the traffic area, as explained in Chapter9 of TM 5-337.

Temporary Repairs

Any stable material may be used for tem-porary repairs in combat areas or wheresuitable material is not available and thetraffic area must be patched to keep trafficmoving, Good-quality soil and masonry,such as concrete rubble, are suitable forthis purpose. All such patches must bethoroughly compacted and constantly main-tained with replacement material. More per-manent patching should be accomplishedas soon as possible.

Maintenance of Shoulders

Blade shoulders so water drains from thesurface and all ruts and washouts arefilled. Grade shoulder material flushagainst or slightly below pavement edges torestrict water seepage to the subgrade andto prevent breaking of the pavement edgecaused by traffic driving off the pavementonto the shoulder. Replace material dis-placed from shoulders with material hauledin, as required.

Maintenance, Repair, and Rehabilitation 8-7

Page 269: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

STABILIZED SOIL SURFACES

Maintenance of mechanically-stabilized soilsurfaces and sand-clay surfaces is essential-ly the same as that for nonpaved and gravelsurfaces. Procedures described for gravelsurfaces arc applicable to surfaces that con-tain considerable coarse aggregate. Proce-dures described for nonpaved surfaces areapplicable to surfaces that contain little orno coarse aggregate. Bituminous surfaces,soils, and soil-cement may require addition-al maintenance as described in the para-graphs that follow.

Potholes

Clean potholes and trim them rectangularlywith straight, vertical sides running paralleland perpendicular to the centerline. Thisprovides a shoulder against the movementof the patch. Fill the potholes with a stabi-lized mix of the same character as the ad-jacent sound area. This material should bethoroughly compacted in place, one thinlayer at a time.

Ravels

Edge raveling is caused by water softeningthe foundation material. Before proceedingwith the patching operations, reconstructthe shoulder or lower the subdrainage sothis condition will not recur. Then buildup the foundation. The patching mixtureshould conform 10 the surrounding area, asfor pothole repair.

CORAL SURFACES

The maintenance of well-built coral trafficareas is relatively simple. Use fresh, rawcoral of the proper moisture content for therepair material. Maintenance is best doneduring or after a rain while the coral is wet.Fill low spots, ruts, and potholes by shovel-ing or dumping coral directly from a truckonto the low spots. Such patches, if rolledwhile wet, will bond onto the originalmaterial almost without a mark. Salt wateris usually available where coral is available,and salt water makes a better bond thanfresh water.

Occasional blading and rolling are neces-sary to maintain a proper crown and asmooth surface. In dry seasons, sprinklingis necessary to maintain a proper crown, asmooth surface, and high stability and tominimize dust. The traffic areas hold upwell in wet seasons. An asphalt treatmentmay be justified in prolonged dry seasons,if dust and raveling become serious. Care-ful attention to shoulders and to thedrainage system is essential.

RIGID PAVEMENTS

Maintenance of rigid pavements is coveredin Chapter 15 of TM 5-337. Frequently in-spect concrete pavement to detect earlysigns of failure, and make prompt repairsto prevent minor defects from spreading.

CRATER REPAIR

Bombs, shells, land mines, and crateringcharges can produce extensive craters intraffic areas. Surface damage does notpresent any unusual repair problem, but ex-plosions may displace or destabilize largeareas of the subgrade. Drainage may alsobe disrupted, allowing water penetrating thebroken surface to accumulate and furthersoften the subgrade. Satisfactory repairs re-quire the restoration of subgrade stabilityto support traffic and prevent undue sur-face settling after repairs have been com-pleted.

Use the following procedures for craterrepairs:

1. Remove, from around the edge of thecrater, all surfacing that is damaged or notfirmly bonded to the base course.

2. Trim the surface and base course to asound, vertical edge.

3. Remove water, mud, and debris fromthe crater.

4. Fill the crater with successive 6- to8-inch layers of suitable material to theoriginal level of the subgrade. Compactionis essential; each layer must be thoroughly

8-8 Maintenance, Repair, and Rehabilitation

Page 270: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

tamped with hand or pneumatic tampingtools. After the material has reached asuitable level, compaction equipment can bepulled through or driven across the crater.

5. Repair the base course and wearingsurface.

Gravel, rock, masonry debris, sandy soil, orother suitable, stable materials can be usedto fill craters, as shown in Figure 8-6.Material blown from craters can be used formuch of this fill. In an emergency.

material from the shoulders of roads or air-fields may be borrowed and replaced later.When the situation permits and whereenemy action may be anticipated, stockpilesor material pits should be prepared at con-venient sites. Alternate layers of sandbagsand tamped earth allow good subgrade com-paction where other equipment or materialsare not available.

For a detailed discussion of specific craterrepair techniques used in air-base damagerepair, refer to Training Circular (TC) 5-340.

Figure 8-6. Crater backfill materials

ROAD MAINTENANCE

The importance of preventive maintenance gineer units. Under the pressure of combatand the necessity for prompt maintenanceof all types cannot be overemphasized.Neglect and delay permit the traffic andweather to turn minor defects in 10 majorproblems. Progressive failure of roads is aserious matter. The more serious a failureis, the more quickly it deteriorates.

In forward areas, extensive repairs are oftennecessary before roads can be used. Ex-pedient work is usually done by combat en-

conditions, temporary repairs are madehurriedly using the materials most readilyavailable. Such repairs are intended onlyto meet immediate minimum needs. As theadvance units move forward, other engineerunits lake over the work of additionalrepair and maintenance. Epedient repairspreviously made arc supplemen ted orreplaced by more permanent work. Sur-faces are brought to a standard that willwithstand the required use and main-tenance becomes routine.

Maintenance, Repair, and Rehabilitation 8-9

Page 271: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

MAINTENANCE PATROLS

Adequate maintenance requires a workablemaintenance organization. Usually engineerunits establish a patrol system to handlethe roadnet for which the unit is respon-sible. It is desirable to use squads aspatrols and thus retain unit integrity, witheach squad commanded by its squad leaderand using its regular table(s) of organiza-tion and equipment (TOE). The platoon fur-nishes reinforcements (personnel or equip-ment) as needed.

Assign each patrol to a specific area. Or-ganize as many patrols as necessary to ade-quately cover the total area of responsibi-lity. It is sometimes necessary in forwardor heavy-traffic areas to provide enoughpatrols to put the maintenance function ona 24-hour-a-day basis.

Personnel and Equipment

Two plans are presented for the organiza-tion of maintenance patrols. Consider themerits of each plan with respect to themaintenance problems of the situation andthe personnel and equipment available forthe patrols.

One patrol consists of a normal squadequipped with a dump truck, a grader, andhand tools. This patrol can handle all themaintenance and minor repairs normally encountered on a 5- to 15-mile stretch ofroad. The number of people in a squad “canbe decreased and more miles can be as-signed to a patrol expected to cover astretch of permanent pavement in good con-dition and not heavily traveled. If a patrolis to cover a poor dirt road accommodatingheavy traffic, more personnel will be fur-nished by the platoon and fewer miles willbe assigned.

Another plan calls for the assignment of apatrol of one to three people, a grader, andhand tools. This crew can handle theroutine maintenance on a 12-mile stretch ofaverage earth, gravel, or water-boundmacadam road. However, the crew must besupplemented with a truck and repair crew

whenever material must be hauled or sur-face patching accomplished.

Winter weather; severe storms; heavy,destructive enemy action; and other condi-tions demand that the patrols be reinforcedwith additional personnel and equipment orthat the assigned areas be reduced and thenumber of patrols increased. Special condi-tions often call for special equipment.

Duties

The duties of maintenance patrols are as fol-lows:

• Clean out drainage facilities.

• Mow grass and weeds.

• Repair minor washouts and potholes.

• Maintain the road surface; for example,eliminate ruts, potholes, and wash-boards.

Ž Maintain road shoulders and ditches.

Ž Make frequent, thorough inspections ofroad conditions, and report to higherheadquarters any need for repair workmore significant than the patrol isequipped or manned to handle.

Inspection and Supervision

An officer or senior noncommissioned of-ficer (NCO) is assigned several patrols to su-pervise, assist, and inspect. Normal unit or-ganization should be retained as much aspossible. A platoon leader should beresponsible for the patrols composed of per-sonnel from his command.

REPAIR CREWS

The engineer sending out maintenancepatrols should keep sufficient equipmentand personnel available to send out repaircrews to handle those situations reportedby the patrols. The repair crew composi-tion will be dictated by the needs of the par-ticular job in terms of equipment and per-sonnel. Frequently, the regular main-tenance patrol can work with the repair

8-10 Maintenance, Repair, and Rehabilitation

Page 272: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

crew, but other maintenance and inspectionof the patrol’s area must not be neglected.

MAINTENANCE WITH TRAFFIC

Give full consideration to the importance ofkeeping traffic flowing with a minimum ofinterference or delay. Maintenance ofshoulders and ditches can normally be per-formed without interference from, orhindrance to, traffic. Repairs to otherdrainage structures may delay traffic orslow other repair work. Permanent repairsare often postponed so that temporary andemergency repairs can be made in order tomaintain traffic flow.

Traffic Control

Repairs should be made on one-half the sur-face at a time when surface repairs willdeny traffic the use of sections of the pave-ment. Block off short sections and postguides to regulate traffic and avoid delay.

When single-lane traffic must be used, con-trol traffic by the baton method. With thismethod, a flagman is placed at each end ofthe single-lane traffic section. The flagmanat one end of the section has a baton orsome other distinctive marker. Workingunder a prepared plan, all vehicles travelingin one direction are stopped, while thosetraveling in the opposite direction are per-mitted to go through. After a suitable timeinterval, the flagman on the open end of thesection gives the baton to the driver of thelast vehicle permitted to go through. Uponarrival at the other end of the section, thedriver of the last vehicle gives the baton tothe flagman. Vehicles are then permitted totravel in the opposite direction until all wait-ing vehicles have passed through and thedriver of the last vehicle carries the batonto the other end of the section. Thisprocess continues as long as necessary.

Sometimes two-way traffic can be main-tained through blocked-off sections bydiverting one stream of traffic to theshoulder of the road. Grading and stabiliza-tion of the shoulder with gravel or bitumin-ous material may be justified in such in-stances. Repairs to be performed during

traffic flow should be carefully planned;proper procedures should be selected; andall labor, material, and equipment shouldbe on hand to complete the work as rapidlyas possible.

Bypasses and Detours

Bridge or pavement failures or the destruc-tion of part of a roadway by floods or com-bat action may make part or all of the road-way impassable to traffic. In such cases, abypass or detour around the damaged orobstructed area is necessary. The construc-tion of a short bypass around an obstruc-tion may be preferable to a longer detouron existing roads. A detour may also beused while a bypass is being constructed.Base the decision upon traffic interference,the work involved, and the time available.

Conduct a reconnaissance to determine thebest possible route when establishing adetour. The road should be as short as pos-sible and must be in condition, or be put incondition, to handle traffic for the periodwhen it will be used. Use existing roadswhen possible. Construct short sections ofconnecting roads, if necessary.

Check and repair bridges or reinforce themwith timber or planking. Clean and repairculverts. If the need for a detour is an-ticipated, complete this work beforehand.Detour roads are usually subjected toheavier loads and more traffic than theirdesign specifications. Because increasedmaintenance is usually required to keepdetours passable, stockpile surfacingmaterial along the route, carefully planmaintenance operations, and keep laborand material constantly available.

Place signs at detour entrances, road inter-sections, and turns to direct traffic. Postwarning signs at dangerous points. Placeother signs or markings, as required, to en-sure minimum traffic delay. Install bar-ricades at each end of the road sectionunder repair. Refer to Chapter 8 ofFM 5-36 for the types and posting of roadsigns.

Maintenance, Repair, and Rehabilitation 8-11

Page 273: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Safety of Maintenance Personnel

Give special attention to the safety of main-tenance personnel working where trafficmoves past or around them. Use restrictivespeed and warning signs, barricades, andflagmen to control traffic and lessen thedanger to maintenance personnel. Instructcrew members to avoid stepping into thetraveled way and to be continually alert topassing traffic. Conspicuously mark main-tenance vehicles operating in or on the edgeof the roadway with red flags, flashing redlights, or similar devices.

WINTER MAINTENANCE

Winter weather may present special prob -lems in TO maintenance. Regions of heavysnowfall require special equipment andmaterial to keep pavement and traffic areasin usable condition. Low temperaturescause icing of pavements and frost on sub-grade structures. Alternate freezing andthawing may damage surfaces and tend toblock drainage systems with ice. Springthaws may result in both surface and sub-grade failure. Winter maintenance consistschiefly of removing snow and ice, sandingicy surfaces, erecting and maintaining snowfences, and keeping drainage systems freefrom obstruction.

Preparation for Winter

Organize snow-removal crews and placeequipment in readiness. Stockpile abra-sives and chemicals in locations where theywill be required. Perform late fall main-tenance before the winter freeze. Continuewith routine maintenance of ditches andshoulders as far into the winter as possible,so that the drainage system will be in thebest possible condition for the spring runoff.

Keep earth and gravel surfaces smooth andshaped to prevent moisture from enteringthe subgrade. Smoothing and shaping alsoprevent snowplow blades from beingobstructed by rough, frozen shoulder andsurface material. In areas of heavy snow-fall, outline bridges, culverts, and narrowplaces in the road with poles that extend

above the snow, and mark these locationsfor maintenance crews.

Snow Fences

Conduct reconnaissance before winter todetermine where snow fences will be neededto control drifting snow. Because it is fineand compacts into a dense mass, driftedsnow obstructs traffic more than an equaldepth of freshly fallen snow. Drifts formwhen wind-borne snow is picked up inopen spaces, loses velocity, and is depositedin sheltered places. Danger spots, there-fore, are roads at ground level or in cuts ad-jacent to large, open areas. Drifts alsoform in the lee (down-wind side) of build-ings, signboards, and similar wind barriers.Similarly, high snowbanks left close to theroad by snowplows furnish both the condi-tions and the material for extensive drifting.Snow fences are not normally required nearhigh fills, in wooded or brushy areas, orwhere vegetation prevents snow from drift-ing on the road.

Placement. Place snow fences on thewindward side of roads according to prevail-ing winds (Figure 8-7). The height of thefence determines the distance it is to beplaced from the traveled way. Generally,the proper distance is 20 times the heightof the fence. This distance is increasedwhere winds are of high velocity. Accordingto the above ratio, a 4-foot fence erected1 foot above the ground should be placed atleast 80 feet beyond the point where drift-ing is to be prevented. In extreme cases, adistance as great as 300 feet may benecessary.

Fences should be as long as possible with-out any holes or openings. Openings pro-vide for dispersion of snow on the back sideof the fencing. The effect of a snow fencein controlling drifts caused by a road cut isshown in Figure 8-8. Two or more parallelfences may be required, but one tall fenceis generally better than two short ones. Iffences are set too far away, they have littleor no effect in reducing drifts. If fences areplaced too close to the road, drifts to theleeward side of the fence fall on the road.

8-12 Maintenance, Repair, and Rehabilitation

Page 274: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 8-7. Location of snow fences

Figure 8-8. Snow fence control of road cutdrifts

windward side. In regions of heavy snow,use long posts so that fencing may beraised on the posts as the season progres-ses. This will increase snow storage to theleeward side. Install fencing with the bot-tom about 6 inches above ground level toprevent the ends of the pickets from freez-ing fast and to prevent the fence from chok-ing with snow. Frozen ends make it dif-ficult to raise the fence and may cause thepickets to break when swayed by the wind.Brace the posts according to the anticipatedwind velocities.

Types of Snow Fences. Commercial snowfences are commonly used. They consist ofmetal posts and wooden laths or metal pick-ets about 5 feet long, woven together withwire. Such fencing is portable, easilyerected and dismantled, and may be rolledup and stored in the summer. Permanentsnow fences include open-board fences onposts and evergreen or deciduous shrubhedges. Plastic snow fencing is lighter andmore efficient than wooden fencing.

Other types of snow fencing include woodslats or pressed-steel slats mounted on col-lapsible A-frames, worm fences, and brushor branches suspended on wire. Localmaterials, such as corn stalks, brush, andcoarse grass anchored in place by wire orwood, may be used. Figure 8-9, page 8-14,shows three types of snow fences.

Erection. Erect snow fences before theground is frozen. Drive metal posts intothe ground and mount wire fencing on the

Maintenance. Inspect snow fences afterheavy storms. Repair broken ties andbraces, and straighten blown-down sec-tions. Raise fences to exceed the height ofaccumulated snow on the leeward side.Lowering of fences may be required aftermidseason thaws or long periods of settling.

Removal and Storage. Remove snow fencesin the spring and repair damaged sections.The fences are frequently stored on dun-nage at the drift location for use the follow-ing winter.

Snow Removal

Prompt snow removal is essential to preventtraffic interference and ice formation on theroad. Begin removal operations when thesnow starts. The amount of equipmentnecessary depends on the intensity of thestorm. If possible, store equipment at inter-vals along road sections or roadnets thatare to receive early attention, and haveoperators ready to move promptly when asnowstorm arrives.

Maintenance, Repair, and Rehabilitation 8-13

Page 275: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 8-9. Types of snow fences

Provide for relief crews, since snow-removalequipment must frequently be operated ona 24-hour basis during periods of heavystorms. Use snowplows to patrol areas orsections of roads that are subject to driftingin windy weather. Standard snow-removalequipment consists of various attachmentsmounted on trucks or similar prime movers.These include one-way, reversible, androtary-type straight blades; straight under-body blades; V-type plows; and rotarysnowplows. These items are described inChapter 11 of TM 5-624. Graders, dozers,and loaders are also useful in snowremoval. Improvised equipment, such asdrags, may be used in expedient situations.

Use comparatively light and fast snow-removal equipment for light snowfalIs andat the beginning of severe storms. Useheavier equipment to widen traffic lanesand for heavy snowfalls. Continue snow-removal operations until the snow has beenpushed back, leveled, or hauled to a

disposal point. When snow removal isdelayed or interrupted, the snow may be-come too deep for available equipment tohandle, drifting may worsen, or wet snowmay freeze.

Trucks with 2 1/2- to 5-ton capacities andequipped with one-way blades are bestadapted for long stretches of roads. Thisequipment travels at speeds of 15 to 25miles per hour (mph), removes snow fromthe road before it is compacted, andprovides an open track for traffic.

Use 5- to 10-ton trucks equipped witheither straight or V-shaped blades forheavier snowfalls and to widen traffic lanes.This equipment operates at about 15 mph.Use V-shaped plows to break through heavydrifts. Use either straight or V-shapedplows equipped with side wings to push thesnow beyond the shoulder line, to preventdrifting, and to provide room for additionalsnow storage.

8-14 Maintenance, Repair, and Rehabilitation

Page 276: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Trucks used for plowing generally carryabrasives as a ballast for better traction.Tractors are sometimes required for heavysnows and drifts. Graders are satisfactoryfor light snow. In areas of very heavy snow-fall, rotary plows and blowers may beneeded.

Surface Ice Control

The formation of road ice resulting frompacked snow, slush, or melting snowbanksis prevented if snow removal is effectivelyperformed and drainage is provided. Whenpossible, push snowbanks away frompavements so that melted water will notrun onto cleared surfaces.

Use plows and graders to remove slushfrom the road to prevent freezing and icingor to remove ice that has previously formed.Use care to avoid damaging the pavement.Dry snow compacts under traffic but canusually be loosened and bladed off withoutdifficulty. Wet snow or slush, if it is al-lowed to freeze in place, sticks tightly to thepavement and cannot be easily removedwithout a period of warm weather or theuse of salts.

Various conditions cause icing of road sur-faces. Dangerous icing is more likely tooccur during the late fall and early springwhen frequent temperature changes occur.Midday thawing and night freezing is a com-mon cause of icing. Rain; sleet; or light,wet snow falling on cold pavement can formice films too thin to be removed by mechani-cal means and can make long sections ofthe road hazardous. Curves and grades arecritical points under icing conditions, andhigh-crowned roads can become difficult totravel at any point when iced over.

Use of Salts. At the beginning of a storm,apply sodium chloride or calcium chlorideto wet snow and sleet to keep it in aslushy condition and prevent it from stick-ing to the surface. Limit the use of saltson concrete pavements to one or two ap-plications per year or the pavement will pitand scale. Salts do not damage bituminoussurfaces. To prevent blockage of the drainsby freezing. place bags of salts at drain

inlets or catch basins so they do notobstruct flow.

Use of Abrasives. Treat icy pavements withabrasives and salts to reduce slipping andskidding. Sand, both treated and un-treated; cinders; and crushed rock or slagscreenings are commonly used. Othermaterials include pea gravel, coal stock,and coke screenings. The choice of mater-ials is based on the availability and thelength of the haul. Sharp, angular materialembeds itself readily, and dark-coloredmaterial absorbs the most heat from thesun. Untreated materials are fairly effectiveon compacted snow but are easily blown orthrown from the traveled way.

For the most effective use, mix calciumchloride with abrasive material. The cal-cium chloride causes the abrasive to embedin the ice and improves surface traction.Treat abrasives with 40 to 75 pounds of cal-cium chloride per cubic yard for stockpil-ing, and add another 25 to 50 pounds percubic yard of calcium chloride when apply-ing it to a road. Sodium chloride may beused in place of calcium chloride but is notrecommended for temperatures below 10° F.

Store abrasive materials where they arequickly available when needed. Establishstockpiles for hand application at criticallocations such as steep grades and curves.Make wider distribution with trucks byeither hand or mechanical spreading. Heat-ing an abrasive material before placing it onthe road will allow it to melt into the iceand prevent it from being forced out bytraffic.

Mechanical Removal of Ice. Graders cansometimes remove ice that is not tightlybonded to the road surface. Extremely icyconditions can be reduced by using scari-fiers or rotary tillers equipped with specialteeth. Exercise extreme care not to damagethe road surface.

Correction of Spring Breakup Problems

In regions subject to frost and snow, springis a critical time in the maintenance of

Maintenance, Repair, and Rehabilitation 8-15

Page 277: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

pavement and other traffic areas. Abnor-mal and repetitive traffic loads during thespring breakup period may cause subgradepumping of concrete surfaces and break-through of bituminous surfaces. Meltingice and snow, spring rains, and frost leav-ing the ground all have a tendency to sat-urate permeable surfaces. Drainageobstructions may raise the water table andmake subbases unstable.

Ditches. When the spring thaw begins,open ditches at critical points so thatmelted water will not flow onto the road.Outlets of cuts and road sections next tosnowbanks require special attention. Asthe snow begins to melt, snowplows or grad-ing equipment may be required to clearsnow from the shoulders to avoid erosion.Handwork is usually required to clear theshoulders and open ditch outlets. Removeaccumulations of ice in culverts and smalldrainage structures by hand or thaw themwith truck-mounted steamers.

Frost Heaves. Frost heaves are indicatedby the localized raising of road surfacesand pavements. Damage occurs as a resultof the heaving of the subgrade soil due tothe formation of ice lenses. This expandingsubgrade causes an upheaval of the surfaceand subsequent reduction in overallstrength. Frost heaves are most prevalentin silt and clay subgrades.

Frost Boils. Frost boils are indicated by thebreaking up of a localized section of roadsurfaces and pavements when subjected totraffic. During thawing, the melted waterproduces a fluid subgrade condition withvery limited or no supporting capacity. Thetraffic imposes a force on the pavement andthus to the excess water in the subgrade.This in turn exerts an equalizing pressurein all directions. This pressure is relievedthrough the point of least resistance (upthrough the pavement surface) andproduces a small mound similar in ap-pearance to an oversized boil.

Frost boils are often large and deep enoughto make the road impassable until repaired.Repairs may be made by one or a combina-tion of the following procedures:

• Bridge soft spots with timber, landingmats, sapling mats, corduroy, or otheravailable material. Store materials inadvance at or near load sections wherefrost boils may occur. Such repairs aretemporary; therefore, remove the mater-ial when the road thaws and dries.

Ž Patch soft spots with crushed rock orgravel. Place large rocks in soft spotsand cover them with smaller ones. It isbetter to remove soft, water-soakedmaterial beforehand, although moretime is required.

•For best results, provide adequatedrainage along with the repair work tocorrect the cause of the problem.Remove soft material and dig an outletditch to one shoulder. A temporarybridge of planks or other material per-mits traffic to pass. The excavated softspot and the ditch are backfilled withrock, gravel, or other suitable material.Drainage tile may be installed in theditch before backfilling.

Preventive Maintenance

The best maintenance of any road is preven-tive maintenance. During the springbreakup, the best maintenance of a roadsubject to frost heaves and boils is to pro-hibit all traffic during the critical 2- or3-day period. Methods to eliminate or mini-mize the damaging effects of frost action arediscussed further in Chapter 12 of FM5-430-00-2/AFPAM 32-8013, Vol 2.

FORDS AND BRIDGES

The approaches and bottoms of fords mustbe kept smooth and clear of large bouldersand debris. Replace marking posts thathave been knocked down or washed out.Refer to FM 5-446 for additional informa-tion.

Frequently inspect bridge abutments,trestles, piers, and trusses for damage anddeterioration. Repair defects at the earliestopportunity. The maintenance crew normal-ly obtains help to rebuild or repair thebridge.

8-16 Maintenance, Repair, and Rehabilitation

Page 278: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

AIRFIELD AND HELlPORT MAINTENANCE

Airfield and heliport maintenance is theresponsibility of the primary user. For AirForce air bases, such maintenance is nor-mally clone by an Air Force civil engineeringsquadron (CES) or similar unit. Army air-fields and heliports arc normally main-tained by Army engineer units. When therepair and rehabilitation requirements ofAir Force bases exceed the immediate, emergency-damagce recovery capability of the airbase, Army engineer units will be assignedto perform the work.

AIR BASE DAMAGE REPAIR •

The immediate, emergency-damage recoveryof air bases generally is considered to bethe minimum work required to permitaircraft to land and take off.

The Air Force is primarily responsible forthe emergency repair of the air base. Thisincludes the emergency repair of the airbase paved surfaces, which is called rapidrunway repair (RRR). This is accomplishedthrough the employment of Air Force basecivil engineering troop assets; prime baseengineer emergency forces (Prime BEEF),and rapid engineering deployable heavyoperational repair squadrons, engineering(RED HORSE) units. The Army is respon-sible for semipermanent construction, thebyond-emergency repair of the air baseand, upon request, emergency repairswhich exceed the Air Force’s capability.Joint service regulation AR 4 15-30/AFR 93-10 specifics these repair respon-sibilities for each service.

Army Responsibilities for Air BaseDamage Repair (ADR)

The Army provides engineer support to theAir Force overseas. It ensures that unitsare equipped, manned, and trained to sup-port Air Force needs. This support in-cludes—

• Assisting in emergency repair of war-damaged air bases where requiremen tsexceed the Air Force’s organic repaircapability.

Repairing and restoring damaged airbases with beyond-emergency repairs.

Developing engineer designs, plans, andmaterials to meet Air Force needs asagreed upon by the Air Force. Wherepracticable, designs will be based onthe Army Facilities Component System(AFCS).

Supplying construction materials andequipment, except for that provided bythe Air Force.

Upon request, assisting within theircapabilities in the removal of UXOdeclared safe by EOD personnel andlimited damage assessment operations.

Managing and supervising the repairand restoration of war damage per -formed by Army personnel. The AirForce base comma nder sets thepriorities for air base repair.

Air Force Responsibilities for ADR

The Air Force provides military troop en-gineering support from its resources. TheAir Force ensures that units arc equipped,manned, and trained adequately to supportits needs. This support includes—

Emergency repair of war damage to airbases.

Organizing host-nation support (over-seas).

Force beddown of units and weapon sys-tems, excluding Army base developmentresponsibilities.

Operation and maintenance of facilitiesand installations.

Crash recue and fire suppression.

Managing force beddown and the emer-gency repair of war damage.

Supplying material and equipment to •perform its engineering mission.

Maintenance, Repair, and Rehabilitation 8-17

Page 279: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• Providing logistical support to the Armyfor all classes of supply except II, V, VII,and IX.

• Conducting damage assessment andremoval of UXO.

• Providing nuclear, biological, chemical(NBC) collective shelters and estab-lishing and operating personnel andequipment decontamination sites forthe air base and the Army. There areshortages of these assets on air bases,and support to army units may belimited.

Air base support agreements may be estab-lished in some theaters between the AirForce and the host nation where ADR sup-port capability exists. These host-nationsupport agreements may include equipment,materials, and manpower assets.

For a detailed description of personnel,equipment, and material requirements andcritical path schedules for repair of run-ways cratered by high-explosive bombs,refer to AFR 93-2. For a further, detaileddiscussion of general ADR, refer toTC 5-340.

TURF SURFACES

Plant grass to provide a turf surface onshoulders and all graded areas. Turf aidsin camouflage, reduces dust, and minimizeserosion. Turf surfaces are limited to areaswhere the climate and soil are favorable.Table 8-1 gives the characteristics of manynative grasses to aid in selecting propergrass seed or sod.

MUD CONTROL

Mud on the runway creates slippery sur-faces that impede takeoff and increase thedifficulties and dangers of landing. Muddytaxiway and runway surfaces decrease tirelife and increase the wear and maintenanceof brakes. Flying mud particles may dam-age propellers, rotors, and jet engines.Removing mud from wheels, struts, and

fuselage is an additional maintenance bur-den.

Mud on airfield and heliport surfaces iseither deposited by vehicular traffic from ad-jacent muddy areas or caused by subgradefailure because of excess moisture and thepumping of mud to the surface under traffic.

Enforce mud discipline by limiting access totaxiways only to required service vehicles.Also, remove mud from the wheels and un-dercarriages of vehicles before they enterthe taxiway. The most satisfactory solutionis to provide surfaced service roads to allhardstands.

Repairs

Localized soft or muddy spots in an other-wise satisfactory surface are repaired byreplacing the unsatisfactory subgradematerial with a more suitable one. If themuddy areas are widespread, it may benecessary to stop all traffic until the sur-face dries. In extreme conditions, resurfac-ing may be necessary.

Mud Removal

In some instances, surfaces may be kept inoperational condition by removing the sur-face mud. Remove mud by hand shoveling,blading, or dragging. Light mud or slush issometimes removed by hand or with rotarybrooms.

When a grader is used on a landing-matsurface, take precautions to prevent theblade from tearing the surfacing. A satisfac-tory method is to bolt a 4- by 12-inchhardwood moldboard over the cutting edgeand extending 2 inches below it. Thisprovides a scraping edge with sufficientspring to remove the mud from irregular-ities in the landing mat, yet soft enough toprotect the mat. A piece of 1/2-inch rub-ber belting (or the cap from a worn tire)bolted between the blade and the mold-board and extending an inch below the cut-ting edge makes an effective squeegee forremoving light mud and slush. Graderoperations for removing mud and slushfrom the runway are similar to thoseemployed for snow removal. Start in the

8-18 Maintenance, Repair, and Rehabilitation

Page 280: Army Construction Manual FM5 430 Vol1 Entire

Table 8-1. C

haracteristics of grasses

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

Main

tenan

ce, R

epair,

and

R

ehab

ilitation

8-19

Table 8-1. Characteristics of grasses

RuI.tane. Nam. of gra .. grouped by region to traffle Drought Acid Rat. of M.thod of

sm __ ju-m ___ of aultablllty _M and Pr.ferred .011 t.xtur. ,..I.tlInce tol.rane. .atabll.". .at.bO.". tor worlc

mDWIng men' m.nt _ .. _--- ---

TURF GRASSES

COOL, HUMID REGION 1-1. Kentucky bluegrass (Poapratensis) Good Loam. clayey loam I FaW Slow Seed, sod Fat or I Number 2

spring 2. Creeping red fescue and chewing Traffic, Sandy to gravelly Good Good Fast Seed Early fal White cIowr and

fescue (Festuca rubra and festuca good loam number 1 rubra lallax) Mowing,

lair 3. Smooth brome (Bromus inermis) Good Various Good Medium, Seed I Spring I Mix with native grass

last WARM, HUMID REGION

4. Bennuda grass (Cynodon dactylon) Excellent Sandy to clayey loam Excellent Fast Sprigs, sod, Spring or I Seed alone or with or seed summer carpet grasses

5. Common carpet grass (Axonopus Good Moist days, dayey Fair Medium, Seed, sod Spring or Seed alone or with alfinis) loam last summer carpet grasses

6. St Augustine grass (Stenotaphrum Fair Moist, various Fair Fast Sprigs Spring or secundatum) summer

DRY REGION

7. Buffalo grass (Buchloe dactylokles) Excellent I Clayey loam to loam I Excellent I ----- Medium, Block. sod I Spring I Seed blue grama last between buffalo-

grass-sod blocks

ROUGH TURF AND BUNCH GRASSES

COOL, HUMID REGION

8. Common ryegrass (LoIium multi- Good Various Good Good Fast Seed FaD or I Number 9 tIorum and L perenne) spring

9. Orchard grass (Dactylis glomerata) Fair loam to day Good Excellent Fast Seed Fall or Number 8 spring

WARM, HUMID REGION

10. Hairy crabgrass (Dig itaria I Excellent loam to day Excellent Fast Hayseed· I Summer sanguinais) ing

11. Bluestem (broom sedge) (Andropogan) Fair loam to day Excellent Excellent Medium Hayseed· Fan ing

12. Korean lespedeza (lespedeza Excellent loam to day Excellent Medium Seed Spring stipulacea)

DRY REGION

13. l.iUIe bluestem (And ropogon Moist, sandy to loamy Seed, hay· Spring , Other grasses suited scoporius) seeding to soil

14. Blue grama (Bouteloug gracilis) loam to day Seed, hay· Spring Seed between blocks seeding 01 buffalo grass

15. Crested wheatgrass (Agropyron Clayey loam to loam Slow Seed Spring Other native grasses cristatum)

..

Page 281: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

center of the runway and proceed progres-sively to the edge, overlapping several feelon each pass.

SNOW REMOVAL AND ICE CONTROL

Snow removal methods, the order of opera-tions, and the assignment of equipment arcestablished in advance of the winter season.Factors to be considered in planning thesnow-handling program are climatic cond-tions the average snowfall, the aircraft tobe accommodated, the equipment available,and the camouflage requirements. Aircraftmay be equipped with either wheels or land-ing skis. Ski-equipped aircraft operate suc-cessfully on packed snow. Aircraft withlanding wheels cannot operate in more than3 inches of loose snow. This limitation ap-plies to fresh snow on a clear runway, freshsnow on previously packed snow, or meltingsnow previously packed on a runway. Forcamoflage it is undesirable to remove allsnow from a runwav when the surroundingterrain is blanketed with snow.

Controlling with Equipment

Equipment useful for handling snow in-cludes rubber-tired tractors, scoop loaders,graders rotary brooms, and band brooms.Supplementary equipment may includesingle-wing one-way, and reversible snowplows: V type plows; rotary plows; blowers;rollers; and other snow-removal equipment.

Packing

In regions of heavy snowfalls withprolonged cold weather relatively free fromsudden thaws. snow may be handled bypacking. The runway, shoulders, and asmuch adjacent area as practical arc pack-ed. Rolling begins as soon as 3 inches ofsnow have fallen and continues during thesnowfall. Snow is packed by rollers drawn

behind a tractor with snow treads.

Smoothing is done with a drag equippedwith metal cutting edges on the front andrear or with a grader. Usually one tractoris used to pull both the drag and therollers, with the drag ahead of the rollers.

Rollers can be made to any desirablediameter and length with a shell of 10-gagecorrugated steel. The shell is supported onan axle by two structural frames, orspiders, at the third points, and two steel-plated bulkheads at each end. One platehas a hole to permit filling the roller withsand to increase its weight.

Clearing and Removing

Snow clearing and removal are requiredwhere climatic conditions will not permitpacking or where snowfalls arc in excess ofthat which can be packed on the runway.Remove light snowfalls with a grader orrotary broom. Very light snowfalls can beblown off the runway by the prop wash ofSeveral aircraft lined up along one edge.Remove heavy snowfalls with truck-mounted plows, rotary snowplows, rubber-tired tractors, or scoop loaders. Drifts maybe opened by a truck or tractor with aV-type blade or by a rotary snowplow.

Equip trucks with tire chains and carry bal-last for traction while plowing. Keep allblades about 1/2 inch above the runwaysurface. especially if the surface is a land-ing mat. This clearance is accomplished byrunners mounted at each end of the blade.

The assignment of plows varies with thecondition at each air field and the type ofequipment available. Arranging the plowsinto units simplifies coordination of snowremoval with the control tower. Ordinarily,on c- way, truck -mounted snowplows operatein echelon to expedite snow removal.Remove snow near landing lights and otherobstructions with a blower, if available, orby hand.

The rapid removal of snow requires a rotaryblower, snow loader, or other special equip-ment. Trucks used for hauling snow arcequipped with nigh sideboards. Tractor-drawn sleighs built of lumber may be usedas an expedient hauling device or to supple-ment snow-handling trucks.

Abating Ice Conditions

Sprinkle ice coatings on runways, taxiwavs,and hardstands with urea, coarse sand, or

8-20 Maintenance, Repair, and Rehabilitation

Page 282: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

cinders, spread by hand or by mechanicalspreaders. If practical, heat abrasivesbefore spreading. Remove accumulatedabrasives in the spring by brooming, iceconditions on airfields used by jet aircraftarc a very serious problem becauseabrasives cannot be used. Do not usesodium chloride and calcium chloride forice control without approval because thesesalts may promote corrosion of metalaircraft parts.

MAINTENANCE DURING FLYINGOPERATIONS

Coordinate maintenance and repair workduring flying operations, and plan the workfor minimum interference with air andground traffic. Much of the maintenancework may need to be done at night orduring inclement weather in order not to in-terfere with flying operations.

Do not leave equipment hazardous toaircraft on the runway or other areas.Clearly mark construction or repair areason the runway so that they are visible fromthe air. Mark repairs on taxiways so thatthey are visible to pilots while taxiing.

REHABILITATION OF CAPTUREDAIRFIELDS

Ž

The decision to rehabilitate a capturedenemy airfield and the decision as to thetype and construction standard of therehabilitated field are Air Force and Armyresponsibilities. The work is ordinarily ac-compi shed by a combat-heavy engineer bat-talion. The engineer mission is to convertthe existing facilities, which arc usuallydamaged, to the standard decided upon bythe Air Force and Army, with a minimumoutlay of labor, equipment, and materials.Considerable discretion must be exercisedin applying standard specifications to cap-tured airfields. No large-scale relocation offacilities should be undertaken merely toconform to standard patterns, if the exist-ing patterns will serve the same purpose in

a satisfactory manner. Sensible, existingsubstitutions and deviations from specified

arrangements must be recognized and ac-cepted.

An appraisal of the damage done to a cap-tured field precedes the decision torehabilitate it. Occasionally, it is necessaryto expend more effort to restore a badlydamaged airfield than to construct a newone. The damage to the installation in-cludes war damage by our forces in any bat-tle for the airfield and the deliberatedamage that the enemy did before yieldingthe field to our forces. Complete destruc-tion of an airfield is a major undertaking;therefore, the enemy will likely resort to oncor more of the following less destructivemeasures:

Placing delayed-action bombs, mines,and booby traps.

Demolishing drainage systems and pave-ments.

Placing obstacles and debris in the run-way.

Plowing turfed areas.

Flooding surfaced areas.

Blowing craters in runways, taxiways,and handstands.

Demolishing buildings, utilities, andsimilar installations.

Assume these damages were inflicted whenconducting such reconnaissance.

Use the criteria that follow to prioritizerehabilitation operations:

• When restoring a captured airfield, thefirst priority is to establish minimumfacilities and utilities to include the es-tablishment of a minimum operatingstrip for immediate operation of friendlyaircraft. This also includes removingUXO, delayed-action bombs, mines, andbooby traps from the traffic areas; clear-ing debris from those areas; and repair-ing craters on the runway and taxiway

Maintenance, Repair, and Rehabilitation 8-21

Page 283: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

surfaces. Promptly repair the drainagesystem. Concentrate runway work firston a minimum operating strip; second,on an access route; and finally, on othertraffic areas. Give early attention to theprovision of suitable sanitary and waterfacilities. Chapter 7 of TC 5-340 givesdetailed information regarding theseareas.

Ž

• The second priority is improvements tothe minimum operational facilities. Re-store remaining runways, taxiways,hardstands, parking aprons, access andservice roads, and fuel and bombstorage areas before rehabilitatingother, less vital facilities.

The third priority is the repair of build-ings such as the control tower, opera-tional buildings, crew shelters, com-munication centers, and other main-tenance facilities.

The fourth priority is the camouflage ofinstallations; the restoration of utilities(making use of any utility map and anyavailable citizen labor familiar with theinstallation’s utilities); and the repair orestablishment of bathing, dining, andrecreational facilities. A completecleanup of the grounds, including theremoval of debris and seeding and sod-ding, is the last phase of a rehabilita-tion project.

8-22 Maintenance, Repair, and Rehabilitation

Page 284: Army Construction Manual FM5 430 Vol1 Entire

CHAPTER 9

Road Design

Geometric Design

Vertical Alignment

Structural Design

Spray Applications and Expedient-Surfaced Roads

Use of Polymer Cells (Sand Grit) to Build Roads in Sandy Soils

Surface Treatments

Construction Methods

General Road Structural Design

FM 5-430-00-1/AFPAM 32-8013, Vol 1

ROAD DESIGN

Road selection and design depend on the nature of the subgrade; thetraffic and drainage conditions; the construction time available; thesupply of local and imported materials; and the engineer equipment,personnel, and expertise available. The completed design must thenmeet the requirements for the given load class and allow safe andefficient traffic movement.

The load-carrying capacity of a road surface depends on continuous,stable support furnished by the subgrade. Subgrade stability requiresadequate drainage and proper load distribution by the surface and basecourses. Surface and base courses of sufficient thickness and qualityto spread the wheel loads over the subgrade are necessary so that theapplied stress is less than the unit load capacity of the subgrade. inareas where seasonal freezing and thawing occur. the load-carryingcapacity of inadequately designed or improperly constructed roads canbe dramatically decreased to the extent that failure may occur.

For safe and speedy traffic movement, the geometric design requirementfor given road classes must be met. In a combat zone, military urgencydictates rough, hasty work designed to meet pressing needs. An im-proved network of well-surfaced, high-quality roads may be required inrear areas and near major airfields, ports, and supply installations.Road design uses stage construction for the progressive improvementof the road to meet increased traffic demands. Road design also usesmany technical terms. Figures 9-1 and 9-2, page 9-2, show terms usedto designate road features and components. In addition to this chapterTM 5-337 provides additional detailed information on the design ofbituminous and concrete-surfaced roads.

GEOMETRIC DESIGNThe geometric design process begins with 1. Draw the proposed centerline on thegood-quality topographic surveys. In most topographic survey.cases, a minimum 5-foot contour interval isrequired to clearly describe the terrain. 2. Plot the centerline on plan-and-profileThe design process can be described in the paper.following steps:

Road Design 9-1

Page 285: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-1. Road nomenclature

3. Calculate grades, the degree of curva- 5. Adjust the centerline, if possible, toture of horizontal curves, and curve lengths reduce any calculated grades and limitof vertical curves. horizontal and vertical curves that exceed

4. Compare the values of step 3 with thethe specifications.

military road specifications stated in Table9-1.

Figure 9-2. Road cross section and nomenclature

9-2 Road Design

Page 286: Army Construction Manual FM5 430 Vol1 Entire

Table 9-1. G

eometric design data for m

ilitary roads

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

Ro

ad D

esign

9-3

Deeign COntr ..... nd Elements

Oeeign Cont .....

1. Traffic compos"",n

A .. ,,1IlI" ddy trallic (ADn (45% lrucks) Design hourly volume (DHV) Sight distance restriction, %

2 Design speed M, mph (kph) Average running speed, mph (kph)

Cr......s.ctlon Elementa

3. Pavements

Minimum width of traffic lane, It (m) with barrier eurb without barrier curb

(1)

(2)

(3)

Minimum distance belween curb tac"", It (m) Lateral clearance from edge

01 trallle lane to obstructIOns, It (m) Normal cross slope (crown slope) rate

4. Shoulders

Minimum width w/O barrier curbs, It (m) Normal cross slope, rate Type, (perm road)

5. Bridge clearance (perm)'

6. Curb oIIsellor barrier curb, It (rn)

Allgnmenl Elements

7. Sight distance

Minimum stop sight distance, It (m) Minimum pass sight distance. It (m)

8. Horizontal alignment

Maximum horizontal curvature Pavement widening, It (m)

9. Vertical alignment

Grade

Maximum grade, % Crtlcal length, It (m) Minimum grade, %

Vertical curves

Overt (crest) vertical curve k, It (m) Invert (sag) vertical curve k. It (m) Absolute minimum length. It (m)

(4)

(5) (6)

(7)

(8)

Table 9-1. Geometric design data for military roads

Cl ... A Cl ••• B Ct ... C Cl ... ° (4 lIone) (2 Lane) (2 L""e) (1 Lane)

3,400-6,700 935-3,400 2QO.935 Under 200 51(}I,OOO 14(}510 30·140 Under 30 4(}0 80-0 80-40 100

60 (97) 60 (97) 40 (64) 30 (48) 45 (72) 45 (72) 35 (56) 25 (4q

12 (3.658) 12 (3.658) 10 (3046) 10 (3.048) 12 (3.658) 12 (3,658) 10 (3048) 10 (3.048) 53 (16.154) 29 (8,839) 25 (7.620! 15 (4.572)

6 (1.829) 6 (1.829) 6 (1 829) 4 (1.219) 0.0104-0.0108 0.0104·00206 o 0208- 0 0417 0,0208·0.0417

10 (3.048) 10 (3.048) 6 (1 829) 4 (1.219) 0.0417-0.0625 0.0417·00625 00417-0.0625 0,0417·0,0625 Dustless SlAble Compacted $O~ Cam peeted .o~

2.5 (0,762) 2.5 (0.762) 2.0 (0610) 2.0 (0,6H))

475 (144.780) 475 (144.780) 275 (83 820) 200 (80.960) N/A 2, lOO (640.081) 1,500 (457201) N/A

55" 55" 14.5' 26.7' None None 2·4 (0610-1.12'9) 2-5.5 (0610·

1676)

6 6 10 15 700 (213.360) 700 (213 360) 450 ('37 160) 250 (76.200) 03 03 03 0.3

lOO (48.768) lOO (48768) 55 (16764) 35 (10.668) 105 (32.004) 105 (32 004) 55 (16764) 28 (8,534) 180 (54,664) 180 (54.864) 120 (36 576) BO (24,384)

Remarks:

(1) The DHV shown for all roads IS in total vehicles per hour for all lanes in both directions. The OHV IS

approximately 15 percent of the ADT

(2) The values shown lor this term Indicate the combined effecl$ 01 horizontal (CUrY6) and vertical (grade) alignment on capacity. A value of zero percent indicates an absolutely straight, nat alignment with no restriction on sight distance, A value of 100 percent indicates a road W1th numerous sharp curves and grade changes on wtllcn the sight distance IS less than 1,500 1t(457,20t m) at any point on the road

(3) If the anticipated traffic includes a Significant number of vehICles having widths in excess 01 8.5 It (2.591 m). the traffic lanes should be widened in the amount by which the vehicle width exceeds 8.5 It (2.591 m),

(4) There should be a color or texture contrast between traffc lane and shoulder surfaces.

(5) Values shown are calculated on basis of maximum rate of super elevation of 0.100.

(6) Pavement widening lor a class C or class 0 road varies 2105,5 It (0610 to 1.676 m) as the curvature varies trom 2 to 26.7", Values obtained may ba rounded off to the nearest 0.5 ft (0. I 52 m).

(7) The term critical length is used to indICate the maximum length of a designated upgrade upon wtllch a k>aded truck can operate wrthout an unreasonable reduction in speed. Crtical lengths may be increased at an approximate rate 01 50 It (15,240 m) per percent decrease In grade from the values shown.

(8) The minimum lengths of vertical curves are determined by multiplying k by the algebraic differences In grades (in percent)

Notes:

1. A!fj can be seen, cap.citiea are shown _ a range of values. " maximum (or minimum) de.gn values shown .re rigidly adhered to, then the reautbint ""pKiIy 01 Ihe road wMI be on Ihe lower aide 01 Ihe ""pKiIy r.nge. Therefore, discretion should be uaed in selecting design values by avoiding maximums or minimums whenever possible.

2. Tumout. shoutd be provided at 1/4-mile (402.250 m) interv". on cla ... O rowl ..

3. Curba will gen",.ily not be provided in open .rea ..

"Bridge clearance (permanent) width of the Iraveled way should be equal to the WIdth of the lanes plus 5 It (1.524 m) 12.5 It (0762 m)] on each side; 14.75 It (4.498 m) vertical ctearance,

Page 287: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

6. Plot new tangents (straight sections ofroad) on the plan and profile in those loca-tions where horizontal and vertical curvesexceed the military road specifications.

7. Design horizontal and vertical curvesfor all tangent intersections.

8. Plot newly designed curves on the planand profile.

9. Develop a mass diagram for the project.Balance the cuts and fills and optimizeruling grade and earthwork volumes.

10. Design superelevations (curve bank-ing) and widening for all horizontal curves.

11. Draw typical cross sections.

12. Design the required drainage struc-tures and bridges.

SELECTION OF ROAD TYPE

Structural characteristics should accom-modate traffic volumes throughout theroad’s design life. Table 9-1, page 9-3,shows four possible road types. They arebased on expected traffic volumes and showthe values for the design control elementsfor each road class. The capacities arcshown as a range of values. Only road clas-ses B, C, and D apply to TO construction.If the maximum (or minimum) design valuefor the various criteria is always adheredto, the resulting vehicle capacity of the roadwill be on the lower side of the range. Usediscretion by designing the road to the bestpossible standard in a given road class.

DESIGN CALCULATION

The values in Table 9-1 for each geometricfeature must be attained to ensure that thedesired road will have a capacity equal toor greater than either the average daily traf-fic (ADT) or design hourly volume (DHV)shown. The first step in the design of aroad is to estimate the daily or hourly num-ber of vehicles in a military organization.Where this cannot be done, the number ofvehicles organic to the units that will use

the road, multiplied by a factor of two, issuggested as a reasonable estimate. Thisconservatively assumes that each vehicleuses the road twice (one round-trip) per day.

Figure 9-3 shows the relationship betweenDHV and sight distance restriction. Ifeither anticipated DHV or ADT is knownand the sight distance restriction can be es-timated from preliminary plans, the neces-sary road type can be determined from Fig-ure 9-3. If ADT or DHV and the road typedesired are known, sight-distance-restric-tion requirements can be determined fromFigure 9-3.

A range of possible DHV values is given foreach road classification in Table 9-1. Theactual DHV for a road is a function of thesight-distance-restriction factor, which alsohas an allowable range for each type ofroad. The DHV varies directly with achange in the sight-distance-restriction fac-tor. Figure 9-3 shows this straight-linerelationship.

After the sight-distance-restriction factor isdetermined from the design plans of an as-sumed road class, the actual DHV is deter-mined to ensure that the capacity is ade-quate.

Example:

A road is to be designed for a military or-ganization having approximately 250vehicles.

ADT = 250 x 2 = 500 and DHV = 0.15 x500 = 75. The 0.15 factor clusters the traf-fic into rush hours. Otherwise, the hourlyvolume = 500 vehicles (per day)/24 hours(per day) - 21 vehicles per hour.

Solution:

The calculated DHV of 75 could be met bya class C road. Therefore, assuming aclass C road is used, plan-and-profiledesigns could be drawn and a sight-restric-tion factor can be determined from thedesign.

9-4 Road Design

Page 288: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Sight distance restriction, percent

Figure 9-3. Interpolation of DHV for selection of road class (not to scale)

From Figure 9-3, a sight-distance-restric-tion factor of 62 percent is determined(based on a class C road and a DHV of 75).Using Figure 9-3, the maximum sight-dis-tance-restriction factor for a class C road is80 percent. This provides a DHV for aclass C road of only 30. Since the sight-dis-tance-restriction factor for the example (62percent) is less than the maximum of 80,this meets the initial requirement of theDHV being greater than or equal to 75.Therefore, the class C road assumption isadequate. If a DHV of 75 could not behandled by the class C road, it would benecessary to construct a class B road.

ESTIMATING CAPACITY

The information in Figure 9-3 and Table 9-1, page 9-3, is adequate for the geometricdesign of military roads. However, addition-al information is available in TM 5-822-2.The information can be used to evaluate thecapacity of existing roads by obtaining per-tinent characteristics and comparing themto the values in Table 9-1. If the data doesnot conform to that shown for a given roadtype, use discretion in estimating the roadtype and ADT or DHV to which the databest conforms. The volume and capacityvalues in Table 9-1 are for roads of a givenclass when they are new or in good condi-tion. As the road surface deteriorates, theroad is less able to accommodate the traffic

Road Design 9-5

Page 289: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

for which it was designed. Plan and carryout a maintenance program to keep theroad in good condition.

GRADE AND ALIGNMENT

Before building a road or an airfield, the en-gineer must determine the best vertical andhorizontal alignment of the facility con-cerned. Design both horizontal and verticalalignment to keep sight distance restric-tions to a minimum. Define the route by aseries of straight lines and curves to meetthe stated mission and capacity. Thisprovides the shortest, most efficient routethat requires the least construction effort.Define the route vertically in a series ofgrades and curves that fall within accept-able specifications and requirements.Horizontal and vertical alignment are inter-related and must be considered concurrent-ly. However, the principles on each arebest studied separately. Horizontal and ver-tical curves of all types are discussed in FM5-233.

HORIZONTAL ALIGNMENT ANDHORIZONTAL CURVES

The principles of horizontal alignment aresummarized as follows:

Tangents (straight sections of road) shouldbe as long as possible, because the shortestdistance between two points is the connect-ing straight line. Terrain conditions, how-ever, seldom permit the construction of aroute between two points in one tangentline. Therefore, the engineer should makeeach tangent as long as possible, limit thenumber of curves, and provide long straightstretches, thereby improving the routecapacity.

Make curves as gentle as possible. Long,gentle curves increase the capacity of theroadway by permitting higher speeds. Theyalso provide a safer path of travel for thevehicle. Making gentle, horizontal curveswill increase the curve length, therebydecreasing the tangent length. However,this reduction in tangent length is minor

compared to the benefits gained by reduc-ing the total number of curves.

Tangents should intersect other roads andrailroads at right angles. Military roads nor-mally supplement existing roadnets andhave intersections at one or both ends ofthe military road. Operating efficiencyusually is improved when these intersec-tions approach right angles.

Frequently used horizontal curves areshown in Figure 9-4. The most commonare the simple curve, the reverse curve, thecompound curve, and the spiral curve.

• A simple curve uses the arc of a circleto provide a smooth transition betweentwo tangents. This curve is used fre-quently in the TO because it fills theneeds of the low-speed design roads nor-mally used and is easy to construct. Areverse or compound curve can bedesigned using the same basic equa-tions.

Ž A reverse curve uses two simple curvestangent to a common line at a commonpoint. Their centers are on oppositesides of the common line. The radii ofthe curves may or may not be equal inlength.

Figure 9-4. Types of horizontal curves

9-6 Road Design

Page 290: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

•A compound curve has two simple cur-ves tangent to a common line at a com-mon point. The centers of these curvesare on the same side of the commonline, and the curves have radii of dif-ferent lengths.

• A spiral curve is a simple curve in thecenter with parts of a spiral on eachend to smooth transition to the tangent.The spiral is used only on high-speedroads (classes A and B). Detailed stepsfor the design and layout of spiral tran-sition curves are in FM 5-233. Lowdesign speeds of class-C and -D roadsdo not require spiral transition sections.

ELEMENTS OF A HORIZONTAL CURVE

The following are elements of a simple,horizontal curve as shown in Figure 9-5:

• The PC is the point where the curvebegins or leaves tangent A—the tangentnearest the origin of stationing (station0 + 00) or start of the project.

•The PT is the point where the curveends or joins tangent B.

• The PI is the intersecting point of twotangents that must be connected by ahorizontal curve.

Ž

The tangent distance (T) is the distancefrom the PI to the PC or from the PI tothe PT.

The radius (R) of curvature is the radiusof the circle whose arc forms the curvefrom the PC to the PT.

The length of curve (L) is the distancefrom the PC to the PT along the curve,measured as an arc or as a series of100-foot arcs. Railroad engineersmeasure L as a series of 100-footchords.

The angle of intersection (I) is the ex-terior angle at the PI formed by tan-gents A and B. The central angle, be-tween the radius points at O, is equal tothe exterior angle.

The external distance (E) is the distancefrom the PI to the midpoint of the curve.

The long chord (C) is the straight-linedistance from the PC to the PT.

The middIe ordinate (M) is the distancefrom the midpoint of the curve to themidpoint of the long chord.

Figure 9-5. Elements of 8 simple, horizontal curve

Road Design 9-7

Page 291: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

DEGREE OF CURVATURE

The connecting curve between two tangentsmay be short and sharp or long and gentle,depending on the properties of the circlechosen. Sharpness is defined by the radiusof the circle. For example, a curve may becalled a 150-foot curve. However, a curveis seldom referred to by its radius becausethe center of the curve is often inaccessibleon the long, gentle curves used on modernhighways. The more practical and commonreference term for defining curve sharpnessis the degree of curvature (D). The degreeof curvature is established as a whole orhalf degree. The degree of curvature maybe stated in terms of either the arc or thechord.

Arc Definition

The degree of curvature, D, is that anglewhich subtends a 100-foot arc along thecurve. (See Figure 9-6.) This definition isused by state highway departments and theCorps of Engineers in road design.

Chord Definition

The degree of curvature, D, is the anglewhich subtends a 100-foot chord on thecurve. (See Figure 9-7.) This definitionresults in a slightly larger angle than thearc method, and it is used by the railroadindustry and the Corps of Engineers in rail-road design.

The difference between the arc and chorddefinitions is very slight and nearly insig-

EQUATIONS FOR SIMPLE,HORIZONTAL-CURVE DESIGN

Figure 9-6. Arc definition for degree ofcurvature

nificant (frequently well below 1 percent) forTO construction. However, because the arcdefinition is the most widely used proce-dure in road design, only its definition willbe used throughout the rest of the chapter.

The two methods commonly used to solvehorizontal curve problems are the 1-degree-curve method and the trigonometricmethod. Both methods may be used withthe same degree of accuracy. The 1-degree-curve method requires the Functions of a1-Degree Curve table shown in Appendix Fof this manual.

Appendix F is based on the trigonometricrelationships for a curve of D = 1°. Curvesof different degrees of curvature can bereadily designed because of the propor-tionality between all curves and the l-de-gree curve. For example, a curve of D =15° has one-fifteenth the L, E, T, and Mvalues as for a 1-degree curve (D = 10). Theonly information needed to obtain the L, E,T, and M values for a 1-degree curve is theangle of intersection (I), and I is alwaysknown at the onset of the design process.The trigonometric method requires a cal-culator with trigonometric functions ortrigonometric tables found in TM 5-236 orany surveying manual.

Figure 9-7. Chord definition for degree ofcurvature

9-8 Road Design

Page 292: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Radius of Curvature

As previously described in the arc defini-tion, D is that angle subtended by a 100-foot arc on a circle. By comparing the 100-foot arc and the total circumference of thecircle, an equation for R is developed interms of D.

Tangent Distance

In the right triangle shown in Figure 9-5,page 9-7, the vertices are at PC (or PT), PI,and O. The tangent distance (T) is foundusing the 1-degree-curve method, as follows:

is found in Appendix F, Table F-1, for agiven I. Use Table F-2 to determine thechord correction.

External Distance

Using the 1-degree-curve method (refer toFigure 9-8), the external distance (E) isfound as follows:

Middle Ordinate

Using the 1-degree-curve method (refer toFigure 9-8), the middle ordinate (M) isfound as follows:

Length of Curve (L)

Measure the length of the curve in 100-footarcs. Because D subtends a 100-foot arc,the total number of such arcs in a horizon-tal curve must be the number of times thatD can be included in the central angle I.

The central angle subtended by the entirehorizontal curve has sides that are radii tothe PC and PT. Both of these radii are per-pendicular to the tangents that form the

Figure 9-8. Derivation of external distance

Road Design 9-9

Page 293: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

intersection angle I. The quadrilateralformed by the four points of PI (180°-I), PC(900), O (I), and PT (90°) must total 360°.1(180-I) + 90 + I + 90 = 360.] Hence, thecentral angle is equal to the angle of inter-section I.

DESIGNING HORIZONTAL CURVES

The engineer designing horizontal curvesmust know two facts about the curve fromthe preliminary survey: the location andstation of the PI and the angle between in-tersecting tangent lines (I). The curves canbe designed after this information is ob-tained.

Ž

The first step is to determine the desiredsharpness of the curve. This is defined bythe radius or the degree of curvature.Topographic conditions govern the final loca-tion of the centerline and sharpness of thecurve. A maximum or minimum tangentdistance may fit the terrain conditions, orthere may be a limit on the external dis-tance or the middle ordinate. If a restric-tion exists, solve for the degree of curvatureby transposing the equations previouslygiven. Where no terrain condition dictatesthe sharpness of the curve, choose a degreeof curvature within allowable specifications.

When choosing a degree of curvature,remember that gentle curves are moredesirable. However, these long curves mayincrease surveying and construction time,materials, and effort required. There is norestriction on the length of the curve withrespect to a minimum degree of curvature.However, the maximum allowable degree ofcurvature is specified by the road classifica-tion. Table 9-1, page 9-3, specifies the max-imum degree of curvature for each class ofroad as stated in the row titled “Maximumhorizontal curvature.”

After the degree of curvature is selected,determine the stations of the PC and thePT. Next, design the curve except for thecalculations needed to locate stationingpoints of the curve between the PC and PT.The following steps show the design of

horizontal curves using the 1-degree-curvemethod:

1. Find the degree of curvature, D, by oneof three methods:

• If the curve is unrestricted,

where R = the radius of the curve

If the curve is restricted by the tangentdistance,

where—

tangent distance for a 1-degree curve(found in Appendix F, based on the angle ofintersection)

restricted tangent distance for ahorizontal curve

Ž If the curvedistance,

is restricted by the external

where—

external distance for one-degree curve(found in Appendix F, based on the angle ofintersection)

= restricted external distance fora horizontal curve

2. Round up the degree of curvature to thenext half degree when possible.

3. Determine the length of the tangent.

4. Find the stationing of PC.

PC = P I - T

9-10 Road Design

Page 294: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

5. Calculate the length of the curve.

6. Find the stationing of PT.

P T = P C + L

Horizontal-Curve Design Examples

This section describes the horizontal-curvedesign procedures for three common situa-tions:

• No terrain restriction which limits T orE.

• Terrain restriction of the tangent dis-tance.

Ž Terrain restriction of the external dis-tance.

Example:

Degree of Curvature with No Terrain Restric-tion. Figure 9-9 illustrates the followingcomputations:

Given: I = 50°, PI at 14 + 28

Find the station and location of PC and PTfor a class C road.

Solution:

A degree of curvature, D, of 6° is selectedas a flat, gentle curve. D = 6° is far belowthe maximum allowable of D = 14.5° forclass-C roads and is slightly sharper thanthe maximum allowable of D = 5.5° forclass-B roads.

Figure 9-9. Horizontal curve with nosharpness restriction

PC = PI - T = (14 + 28) - (445.29')= (9 + 82.71)

PT = PC + L = (9 + 82.71) + (833.33')= (18 + 16.04)

The station of the PT is determined by ad-ding the curve length to the station of thePC, not by adding T to the station of the PI.However, the actual point of the PT is foundby measuring a distance T (at angle I) fromthe PI. The station is the distance from thepoint of origin at station (0+ 00), asmeasured along the centerline.

Example:

Terrain Restriction of the Tangent Distance.Figure 9-10 illustrates the following com-putations:

Given: I = 32°, PI at 25 + 87, is 282'(due to bridge)

Find the station and location of PC and PT.

Solution:

Knowing that T must not exceed 282 feetand that the D that will give this value is

Figure 9-10. Horizontal curve with restrictionon tangent

Road Design 9-11

Page 295: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

probably not equal to a whole or half de-gree, it is necessary to first find which Dgives 282 feet foroff, as shown.

and then round it

If the value of T was specified as exactly282 feet (as opposed to a maximum orrestricted value), the value for D of 5°50'must be used. Rounding D up to the nexthalf degree (D = 6°) will slightly sharpen thecurve and will reduce T slightly below the282-feet maximum.

Increasing the degree of curvature decreasesthe values of the radius and tangent dis-tance and vice versa. When the degree ofcurvature was changed from 5°50’ to 6°00',it caused the radius and the tangent dis-tance to decrease from 983.5 feet to 954.9feet and 282 feet to 273.8 feet, respectively.Therefore, if the maximum value of the tan-gent distance is used to determine a trialvalue of D, the rounding must be to thenext higher half degree. If minimum valueof the tangent is given, the rounding is tothe next lower half degree.

Example:

Terrain Restriction on the External Distance.Figure 9-11 illustrates the following com-putations:

Given: E 85 feet, I = 80°, Sta PI at 43 +32.75

If E exceeds 85 feet, the road centerline willbe closer than 25 feet to the building.

Find the station and location of PC and PT.

Solution:

Because the limiting value for the externaldistance and the value used to get this trialvalue of D are maximums, it is necessary toround to the next higher half degree, there-by decreasing T and E.

Figure 9-11. Horizontal curve with restrictionon the external distance

9-12 Road Design

Page 296: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Station Adjustments Due to Curve Instal-lationHorizontal curves occasionally are designedat the site by the surveying team. Whenthis is done, the route is staked out andstationed progressively along the centerlinefrom the point of origin of the project. It isnot necessary to calculate station adjust-ments required by the shortening of theoverall centerline length by a distance of2T-L. However, when horizontal curves aredesigned in the office with data supplied bythe preliminary survey, the adjustmentsmust be calculated.

When the preliminary tangent alignment ofa route is first determined and stationingalong the tangent lines is accomplished, thestation of any point represents its distancefrom the point of origin as measured alongstraight lines only. When a horizontalcurve is installed and becomes the center-line of the route, the stationing distancefrom the PC to the PT is shortened by 2T-Lfor each horizontal curve.

In Figure 9-5, page 9-7, the initial center-line distance from the PC to the PT ismeasured along the two tangents and isequal to 2T. When the curve is installedand the new centerline is created, the finalcenterline distance from the PC to the PTbecomes L. At this point, the centerline sta-tioned ahead would need to be restationedor adjusted in some manner. To preventrestaking the rest of the project centerline,an adjustment is made to the constructionstake at the PT. The method of adjustmentwill produce a stationing equation at thepoint of adjustment that will satisfy boththe stationing back and the stationingahead. The equation will have a stationwhich corresponds with the correct stationto the rear (or back) and the correct stationforward (or ahead). The equation will bewritten on the construction stake as follows:

where—

PT = point of tangentEQ = equationBK = correct station backAH = correct station ahead

Equations most often will occur at the PTbut may be used anywhere an adjustmentto the centerline stationing is required. Theequation indicates that an adjustment tothe centerline stationing has occurred forsome reason. For example, if the surveycrew accidently placed two centerline stakeswith the same station number, say 13 + 00,the equation stake would look like this:

The adjustments shown in the precedingequation indicate that the total length ofthe road has been shortened by the dif-ference of 24 feet in the first example andlengthened by 100 feet (or one station) inthe second example.

Equations normally are shown in the profilesection of the plans as a gap in the gradewith the back and ahead stations writtenout.

Field Methods of Curve Layout

The location and station of the PC and PTof a horizontal curve constitute only twopoints on the curve. They do not adequate-ly define the necessary construction. Thefollowing methods are applicable to militaryconstruction for locating points on thecurve:

Arc Method. When the radius of a curve isless than 100 feet and topographic condi-tions permit, locate the center of the circleand swing an arc to locate a curve or fillet,Curves with a small radius are seldom usedexcept at street intersections and for filletsbetween hardstands, taxiways, or otheroperational features of an airfield.

External-Distance Method. For short curveswhere three points are adequate for the con-struction standard desired, calculate the ex-ternal distance and use it to locate the cen-ter of the curve. This method is not recom-mended for precise construction or for longcurves. It is impractical when the terrainon the curve side of the PI is difficult tonegotiate and measure.

Deflection-Angle Method. This method ofcurve layout usually is the fastest and most

Road Design 9-13

Page 297: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

exact method, particularly for curves with along radius. In the arc definition, a deflec-tion angle is the angle formed between atangent line and a chord from the samepoint. (See Figure 9-12.)

Figure 9-12. Deflection angle

In triangle OAB—

NOTE: In other words, the deflectionangle is always one-half the interceptedcentral angle.

If the initial arc is 100 feet long, the centralangle will be the degree of curvature D, andthe deflection angle will be one-half the de-gree of curvature D, or D/2, as shown inFigure 9-13. With the addition of each 100-foot arc, the total central angle increases byD and the total deflection angle increasesby D/2.

Figure 9-13. Deflection angles for 100-footarcs

When laying out a curve, it is common prac-tice to locate stakes at every full station.In view of this and because the PC of anycurve rarely falls on an even station, thefirst arc will be something less than 100feet in length (called a subarc). The deflec-tion angle for the subarc to the first full sta-tion is the same proportion of D/2subarc is to 100 feet (Figure 9-14).

that the

Figure 9-14. Subarc deflection

Once located at a full station, the

angles

curve con -tinues by 100-foot arcs. Therefore, thecentral angle increases by D and the deflec-tion angle increases by D/2 (Figure 9-15).

Figure 9-15. Calculation of chord lengths

The length of the chord for a 100-foot arcon the curve is equal to 2R Sin (D/2).For the first and last arcs, which are al-most always less than 100 feet, themeasured chord Is equal to 2R Sin[(D/2)(L/100)] where L is the distance fromthe PC or PT to the closest full station.

9-14 Road Design

Page 298: Army Construction Manual FM5 430 Vol1 Entire

A summary of the deflection-angle andchord-length calculations is shown in Fig-ure 9-16.

Figure 9-16. Deflection-angledeterminations

and chord-length

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Example:

In the example of a horizontal curve withno terrain restrictions, the station of PC is9 + 82.71, the station of PT is 18 + 16.04,and the deflection angles and chord distan-ces are shown in Table 9-2. A useful checkon the long series of computations is thatthe final deflection angle from the PC to thePT must always equal I/2. This is basedon the previously stated principle that thedeflection angle (from PC to PT) is one-halfthe total angle subtended (I). This check isillustrated in Table 9-2 for d = 25° = 1/2 =500/2 for station, (18 + 16.04), which is thePT.

Layout TechniquesWhen using the deflection-angle method,set the transit up at the PC. Set zero onthe vernier, sight the PI (or take a back-sight down the centerline), and turn thefirst deflection angle. Measure the subarcdistance along the instrument’s line ofsight. To locate the second point on the

Table 9-2. Deflection angles and chord distances

Road Design 9-15

Page 299: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

curve (station 11 + 00), turn the seconddeflection angle (the angle is measured turn-ing from the PI to station 11 + 00) with thetransit still at the PC. Measure the intersec-tion of this line of sight and the 100-footarc from the preceding station to locate sta-tion 11 + 00. Lay out the rest of the curvein this manner.

If the curve is long so that the transit mustbe moved or if an obstruction prevents aclear line of sight, move the transit to an in-termediate station. The same deflectionangles previously calculated may be used tolocate the rest of the curve. (See Figure9-17.)

If station 17 + 00 cannot be sighted, movethe transit to station 16 + 00. Set zero onthe vernier, backsight the PC, and turn theangle 21°31'6" to sight station 17 + 00. Fig-ure 9-17 shows that angle D must beturned for the transit at station 16 + 00 tobecome tangent to the curve at that point.Once the transit is tangent to the curve,angle D/2 must be turned to locate thenext station because the arc is 100 feetlong. The total angle turned is + D/2,which is as originally calculated.

Frequency of Placing Survey Stakes (InFeet)

Horizontal curves should be staked at aminimum interval of 100 feet. The stakinginterval on horizontal curves should bebased on the degree of curvature and canbe determined from the following table:

Degree ofCurvature Radius Staking(100’) (meters) interval

0 to 3° > 1,910’ 100’> 3° to 8° 1,910’ to 721’ 50’> 8° to 16° 720’ to 360’ 25’> 16” < 360° 10’

Horizontal Curve Design Using MetricUnits

The design of horizontal curves usingmetric units is essentially the same as inEnglish units. The only difference lies inthe relationships of arc length to the degreeof curvature as shown in Figures 9-18a,9-18b, and 9-18c.

NOTE: The functions of a 1° curve tableare also applicable to metric design basedon the relationship shown in Figure9-18b. However, if designing usingmetric units, the lengths of T, E, M, andR are in meters.

Figure 9-17. Obstruction on a curve

9-16 Road Design

Page 300: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-18a. D based Figure 9-18b. D based Figure 9-18c. D basedon a 100-ft arc on a 100-m arc on a 20-m arc

If you design the curve based on m,but intend on staking at an interval of20 m, you must determine the degree of cur-vature based on 20 m to determinethe correct deflection angles. A summary ofthe deflection-angle and chord-length cal-culations based on is shown in Fig-ure 9-18d.

Frequency of Placing Survey Stakes (InMeters)

Horizontal curves should be staked at amaximum interval of 20 meters (m). Thestaking internal on horizontal curves should

be based on the degree of curvature andcan be determined from the following infor-mation:

Degree ofCurvature Radius Cord Lengths(100’) (meters) (meters)

0 to 3° >585 20>3° to 8° 585 to 221 10>8° to 16° 220 to 110 5>16° <110 5

NOTE: is the distance from the PC or PT to the closest full station.

Figure 9-18d. Deflection-angle and chord length selection based on

Road Design 9-17

Page 301: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

VERTICAL ALIGNMENTThe capabilities of vehicles or aircraft usingany particular road or airfield determinethe maximum allowable grades that shouldbe established. However, other factors maybe considered. Excessive grades can be in-stalled where speed and capacity are not es-sential. Whenever possible, grades shouldbe less than the prescribed maximumvalues stated in Table 9-1, page 9-3.

Within limitations imposed by various othercriteria, place tangent grade lines so thatearthwork is minimized. The earthwork re-quired in most road-construction projects isusually the largest, single work item. Any-thing that reduces earthwork will improvejob efficiency and economy. Attempt tobalance the earthwork operations betweencut and fill in any area, within thecapabilities of available equipment. Whendrawing the grade lines, the engineer canusually do this balancing by inspection,keeping the profile area of cut equal to theprofile area of fill. These areas are notnecessarily proportional to the actualvolumes involved, but they serve as a basisfor comparison. It is impractical to baIancea volume of cut with an equivalent volumeof fill at a distance beyond the haulingcapabilities of the available equipment.

Along any proposed route will be points atwhich the elevation is already fixed. Inter-sections with existing roads and railroadcrossings present predetermined elevationsthat the engineer must meet when locatingthe tangent grade lines.

In addition to the controlling specificationsfor grades, other criteria may control theplacement of grade lines. These criteria in-clude the minimum allowable gradients, themaximum allowable change in grade at anyIntersection point, the permissible depth ofcut or fill, and the maximum gradients inapproaching bridges or points of intersec-tion.

PLOTTING A PROFILE VIEW

The profile of a road or airfield is a sideview of the project. It represents thehorizontal distance, or stations, as abscissa(x axis) against the elevations at these sta-tions, which are plotted as ordinates (yaxis). When a horizontal alignment is setand the project stationed, determine theelevation of critical points along the center-line. Engineers usually calculate the eleva-tion at all half and full stations, PVC, PVT,and HP and LP elevations.

A break point where the prevailing grademakes an appreciable change should be sta-tioned and the elevation ascertained. Themost common procedure for determining ex-isting terrain elevations is by a ground sur-vey. However, it is possible to obtain eleva-tions for specific points from a contour mapon which the proposed horizontal alignmenthas been plotted. Unless the scale of thecontour map is large, this method is inac-curate and should be used only for prelimi-nary planning and initial location. Thecenterline profile may not represent the typi-cal or prevailing condition across the entiresection at any particular point. This errormay be noticeable when the section is wide,as for an airfield. In such cases, additionalprofiles may be needed along the shoulderline. It is also possible to make a typicalprofile that represents the average elevationacross the entire section.

PLOTTING TRIAL GRADE LINES

After studying the profile, determine the tan-gent grade lines. These grade lines serveas the proposed final profile of the project.It is possible for rough, pioneer construc-tion to follow existing contours with a littlesmoothing of rough spots. Such a routeprovides a rough and relatively unsaferoadbed that is not capable of carrying alarge volume of traffic. A well-designedroute has a series of tangent grades with asmooth transition between them. These tan-gent grade lines can be determined with agood profile.

9-18 Road Design

Page 302: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

GRADE DETERMINATION

The degree of steepness measured lon-gitudinally is normally defined as the per-centage of grade. It is established as arelationship between vertical rise or fall foreach 100-foot horizontal distance and is ex-pressed as a percentage (per 100).

The equation for determining grades is—

where—

G = percentage of gradeV = rise or fall between the two pointsH = horizontal distance between the two

points

NOTE: V and H must be in the sameunits.

To differentiate between rising and fallinggrades along the centerline, a plus sign isused to denote rising grades in the direc-tion of increasing stations and a minus signis used 10 denote falling grades.

VERTICAL CURVES

After grade lines are placed, define theroute vertically in a series of grade lines(straight segments of constant grade) be-tween points of vertical intersection.Design a transition that provides smooth,easy movement from one grade line toanother at these intersections. The verticalcurves used for this transition and its per-tinent dimensions are easily calculated.

Types of Vertical Curves

Two types of vertical curves must be con-sidered: overt and invert. (See Figure9-19.) Overt curves are commonly calledcrest curves, and invert curves are referredto as sag curves. Both types are designedthe same way but different specificationsgovern their dimensions.

Elements of Vertical Curves

Figure 9-20 shows a typical vertical curveinstalled between two grade lines. Theparts of a vertical curve include the follow-ing:

Figure 9-19. Types of vertical curves

• The PVI is the intersection of two gradelines. This station is always read fromthe profile view.

• The PVC is the point along the firstgrade line at which the vertical curvebegins. The grade line is tangent to theparabolic curve at this point. By con-vention. the PVC is always one-half thelength of the vertical curve from thePVI, measured horizontally.

• The PVT is the point along the secondgrade line at which the vertical curveends. It has the same properties as thePVC.

Ž The percentage of grade (G) on thegrade line nearest the point of origin iscalled G1, and the other grade line per-centage is called G2. These two gradelines, which are tangent to the paraboliccurve at the PVC and PVT, intersect atthe PVI.

Figure 9-20. Elements of a vertical curve

Road Design 9-19

Page 303: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

• The length of vertical curve (L) is thehorizontal distance from the PVC to thePVT. The walking distance along the ac-tual curve has no significance. The PVIis horizontally midway between the PVCand PVT. Therefore, the distance fromthe PVC to the PVI is L/2, and the dis-tance from the PVI to the PVT is alsoL/2.

• Offsets are the vertical distancesfrom the grade lines to the verticalcurve. The heights of offsets are com-puted for selected points along thelength of the vertical curve. Theselected points are usually at every sta-tion and half station.

• The maximum offset (MO) is the offsetat the PVI. It is always the greatest off-set along the vertical curve.

Design of Vertical Curves

The design of vertical curves includes twotasks-determining the curve length and cal-culating the heights of a sufficient numberof offsets to adequately define or locate thefinal grade line.

Length Determination. It is possible todesign vertical curves to be long and gentle(flat) or short and abrupt. This is done byvarying the curve length. Depending on thefacility to be constructed and the standardsof construction desired, there are certainlimitations on curve length. Minimumlengths usually are specified.

Change of Grade The difference ingrade between the two grade lines is calledthe change of grade. This difference, whichIs symbolized as is computed as

which represents the absolute value of The curve installed between two

grade lines with a large which mightoccur at the top of a steep hill, is longerthan the curve required between two gradeswith a smaller

Allowable Rate of Change of Grade [r).Criteria have been established to ensurethat the rate at which the change ingradient is made throughout a verticalcurve is consistent with the operating char-

acteristics of the vehicles or aircraft usingthe facility. One criterion (called “r”) is ex-pressed as an allowable rate of change ofgrade for a specific horizontal distance. Forexample, with a criterion of 0.5 percentchange in grade over 500 feet, a of 1.0percent requires a curve length of 1,000feet. However, r is usually expressed as theallowable gradient change in 100 feet oflength. The term “r” is frequently used forairfield vertical curve design.

Sight Distance (S). When an overt curve istraversed, the ability of the driver to seedown the road or airfield is curtailed. If avertical curve is quite short, the distancethat can be seen ahead becomes criticallyshort. Reduced speed is required to reducethe safety hazard. Sight distance dependsupon the design speed permitted.

Vertical-Curve-Length Factor (k). This factoris used when determining road verticalcurve lengths. It is equal to the horizontaldistance, in feet, required to effect a 1-per-cent change in gradient while providing theminimum stopping distance.

Determination of the Vertical Curve Length.Determine the vertical curve length byusing the vertical-curve-length factor (seeTable 9-1, page 9-3) for the given class ofroad (A, B, C, or D) and for the type ofcurve. The factor “k” is used in the follow-ing equation:

where—

L = length of vertical curve in 100-foot sta-tions

k = vertical-curve-length factor (Table 9-1) = change of grade

If length L, as computed, is not in wholestations, round up to the next full 100-footstation. The length derived by this proce-dure is compared to the absolute minimumlength found in Table 9-1.

9-20 Road Design

Page 304: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Knowing the curve length and the station ofthe PVI, compute the station of the PVCand the PVT.

PVC = PVI - L/2PVT = PVI + L/2

Offset Determinations. For the curve to bedefined, the engineer must determine eleva-tions at various locations along the curve.In order to do so, the engineer must deter-mine the offset which is the vertical dis-tance from the original grade line to thedesigned curve.

Maximum Offset. As previously stated, theMO will always be located at the PVI. Thefollowing formula is used to calculate MO:

where—

MO = vertical height of the maximumoffset in feet

L = length of vertical curve in sections = change of grade in percent

Intermediate Offsets. Offsets at locationsalong the curve other than the PVI arereferred to as intermediate offsets. Since itis common practice to stake vertical curvesat whole and half stations, intermediate off-sets are determined at every whole and halfstation along the curve. Use the followingformula to calculate the intermediate offsets:

where—

= offset at a distance, d, from the PVCor PVT in feet

d = selected distance (in stations) fromthe PVC or PVT at which an offset distanceis to be calculated

L = curve length in stations= change of grade in percent

Since and L have been determined priorto using this equation, the term is aconstant. Finding the offsets is a simplematter of varying the value of d.

NOTE: The offsets at equal distancesfrom the PVC or PVT are equal. In otherwords, the offsets are symmetric aboutthe PVI. (This does not mean that theresulting curve is symmetric (unless = Thus, the offset for only one sideof a vertical curve needs to be calculated.Therefore, the above equation can beused to calculate the offset at any pointwithin the vertical curve.

Elevations Along Vertical Curves. Verticalcurves have the shape of a parabola. Usethe following equation to calculate eleva-tions along the vertical curve:

Invert curve:

Overt curve:

where—

change in elevation + offset

change in elevation + offset

change in elevation - offset

change in elevation - offset

y = elevation of point on curve in feetd = horizontal distance of point on curve

from PVC or PVT in stations= change of grade in percent= percent slope of first grade line= percent slope of second grade line

Elev PVC = elevation at point of verticalcurve in feet

High or Low Point of a Vertical Curve.When the tangent grades areequal, the high or low point of the curve oc-curs at the PVI. (See the following example:)

Road Design 9-21

Page 305: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-11/AFPAM 32-8013, Vol 1

When the tangent grades are the same sign(both positive or both negative), the highand low points correspond with either thePVC or PVT. (See the following example:)

When the tangent grades are unequal, thehigh or low point of the curve always fallson the flatter of the two grades. (See thefollowing example:)

To determine the location along the curve ofthe maximum (or minimum) elevation, usethe following equation:

where—

d = horizontal distance along curve fromPVC (or PVT) in stations

L = length of vertical curve in stationsG = percent slope of flattest grade = change of grade in percent

Cut or Fill Values. By using the calculatedcurve elevations and the existing groundelevations, we can determine the cut or fillvalues to place on the grade stakes for con-struction operations. The ground elevationscan be determined from the profile view es-tablished from the initial survey. The dif-ference in elevation between the curve andthe ground elevation constitutes the cut orfill value. For example, if the ground eleva-tion at a point on a curve was 86 feet andthe curve elevation at that point was 82feet, the construction stake would indicatea cut of 4 feet (86 feet - 82 feet).

Design Steps.

The following steps show the design proce-dure for vertical curve:

1. Compute the change of grade.

2. Compute the vertical curve length (L).

Round up to the next higher full station (ifpossible).

3.

4.

5.

6.

7.

8.

Determine the PVC.

Determine the PVT.

Determine the elevation of PVC.

Determine the elevation of PVT.

Determine the maximum offset (MO).

Determine final curve elevations. Com-pute at every half station and full stationalong the curve.

a. Determine grade-line elevations (GLEs).

b. Determine intermediate offsets

c. Determine curve elevations.

9-22 Road Design

Page 306: Army Construction Manual FM5 430 Vol1 Entire

9. Determine the location of maximum (orminimum) elevation, if required.

10. Determine the highest (lowest) eleva-tion, if required.

Example:

Complete the design of a vertical curve to in-elude PVC, PVT, and offsets, with cuts andfills determined every 50 feet (one-half sta-tion).

Given:

The unit survey section has completed acenterline survey for a proposed verticalcurve. The road is class D.

Solution:

PVI = 5 + 00, elevation = 73.00’

= +3.1%, = -5.75%

(1) Determine

= 8.85%

(2) Determine L.

From Table 9-1, page 9-3, k for crest verti-cal curve on a class-D road is 35.

Use L = 4, stations = 400’

(3) Determine the PVC.

= (3 + 00)

(4) Determine the PVT.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

(5) Determine the elevation of PVC.

(6) Determine the elevation of PVT.

(7) Determine the maximum offset (MO).

(8) Determine final curve elevations.

(a) Determine GLEs (Figure 9-21).

(b) Determine intermediate offsets

NOTE: The term /2L becomes a con-stant (1.106).

Figure 9-21. Compiling vertical curve designdata

Road Design 9-23

Page 307: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Where—

= offset from the GLE to the curved = distance, from the PVC or PVT in sta-

tions

(9) Determine the location of the maxi-mum or minimum elevation, if required.

(The maximum or minimum elevation is al-ways on the flattest grade when gradeshave opposite signs.)

Station maximum elevation point =PVC + d (or PVT - d)

Station maximum elevation point =( 3 + 0 0 ) + ( 1 + 4 0 ) = 4 + 4 0

(10) Determine the highest elevation, ifrequired.

NOTE: + or - is determined by inspection.

y = 66.80 + 4.34 - 2.17 = 68.97

Vertical Curve Through a Known Point.When the vertical curve must go through aknown point and the known point is at thePVI, the length of the curve can be deter-mined using the following formula:

When the known point is at a locationother than the PVI, the length of the curvecan be determined using the following for-mula:

Where—

A = horizontal distance from PVI to knownpoint

= offset between elevation of known pointand GLE of known point

NOTE: must be entered as a decimal.

Once the length of the curve has been deter-mined, the remainder of the design must becompleted according to the vertical curvedesign procedures previously outlined.

Example:

A new road with a PVI at station 12 + 50and an elevation at 73.00 feet is to passover a 24-inch culvert at station 11 + 00.The invert of the culvert is at elevation 85.8feet.

Solution:

Determine the length of the vertical curverequired to clear this culvert with 1 foot ofcover.

1. Determine the horizontal distance (A)from the PVI to the known point.

A = 1,250’ - 1,100’ = 150’

2. Determine (as a decimal).

9-24 Road Design

Page 308: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

3. Determine the elevation of the verticalcurve required to clear the culvert with 1foot of cover (at the known point).

= 85.8’ + 2.0’ (pipe diameter) +1.0’ (cover required)

4. Determine the GLE at the known point(directly below the culvert).

GLE =known point)

GLE

GLE = 85.15’

5. Determine the offset between theelevation of known point and the GLE ofknown point.

= 88.8’- 85.15’ = 3,65’

6. Determine the length of the verticalcurve.

= 388.48’ + 246,82’= 635.30’

Vertical-Curve Design Using Metric Units.The design of vertical curves using metricunits is the same as in English units. Theonly difference lies in the use of meters asunits of measurement for elevations and dis-tances.

Frequency of Placing Survey Stakes. Verti-cal curves should normally be staked at 50-foot (every half station) or 10-meter inter-vals. On extremely rugged terrain, the inter-val should be reduced.

THE CROWNED SECTION

The typical cross section of a road is thecrowned cross section. The amount ofcrown provided depends on the type of sur-face used. Normal crown slopes are pro-vided in Table 9-1, page 9-3. Figure 9-22shows a typical cross section for a class-Aroad. If the road is to be surfaced, the sub-grade and the finished surface till have thesame crown.

SUPERELEVATION

The outer edge of a road is elevated tobalance the overturning forces experiencedby a vehicle rounding a horizontal curve. The amount of superelevation is governedby the degree of curvature (or the curveradius) and the design speed. Detailed in-formation for designing superelevation on

Figure 9-22. Normal crown cross section for a class-A road

Road Design 9-25

Page 309: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 9-4 lists pavement widening require-ments. As shown in Figure 9-24, the transi-tion from a normal cross section on a tan-gent (A-A) to a fully superelevated, widenedcross section on a curve (D-D) is a uniform,gradual change. The length of highwayneeded to accomplish this transition isgiven in Table 9-3. Two-thirds of thespecified transition length is affected on thetangent and one-third is affected on the

curves is in FM 5-233. Table 9-3 lists su-perelevation rates and appropriate transi-tion lengths to develop the superelevatedsection as a function of the design speedand degree of curvature. Figure 9-23shows a class-A road section with a super-elevated curve.

As a safely factor, the pavement width onthe inside lane of a curve is increased. Theamount of increase is governed by the de- curve.gree of curvature and the design speed.

Table 9-3. Superelevation lengths and transition lengths

cross sectionFigure 9-23. Superelevated

9-26 Road Design

Page 310: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 9-4. Pavement widening

Figure 9-24. Method for transition (not to scale)

STRUCTURAL DESIGN

In the TO, few roads receive a bituminousor portland-cement concrete surface. Mosttwo-lane roads are surfaced with sand,gravel, crushed rock, or the best locallyavailable material. Expedient surfacingmethods are used when required.

This section describes the procedures to im-prove natural earth surfaces and to resur-face them with sand, gravel, or other materi-als. Included are some common methods of

expedient surfacing, guidance, and criteriato determine thickness requirements for bi-tuminous pavements in the TO. The designof mixes and aggregates and the proceduresfor placing bituminous and concrete sur-faces are in TM 5-337. For subgrade andbase-course requirements, refer to Chapter5 of this manual. Additional information inChapter 12 of FM 5-430-00-2/AFPAM32-8013, Vol 2, supplements the frost-de-sign procedures in this chapter.

Road Design 9-27

Page 311: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Road surfaces in the TO consist of earth inthe most expedient circumstances. Whenin-place soil is not strong enough, it maybe chemically or mechanically stabilized orcovered with a bituminous surface treat-ment. As time becomes available, earthenroads can be improved for increased trafficloads by covering them with material from aborrow pit or with processed material.

E A R T H

Earthen roads consist of native soils gradedand drained to form a surface for carryingtraffic. They are designed to satisfy immedi-ate traffic needs and provide a subgrade forsurfaces of better quality. Their use isgenerally limited to dry weather and lighttraffic. For continued use, periodic main-tenance by graders and drags is necessaryto maintain a high crown and smooth sur-face for draining surface water. Dust con -trol must also be provided in dry climatesor during dry weather.

Earthen roads become impassable in wetweather because of the rutting action ofheavy traffic. Generally, they are used incombat areas where speed of constructionis required with limited equipment and per-sonnel. They are also used as haul roadsin construction areas and as service roadsfor military installations.

TREATED SURFACE

Earthen roads may be treated withbituminous materials to control dust and towaterproof the surface. This helps preventsoftening of the surface in wet weather.Treated surfaces are most successful withsilt or clay soils. The bituminous materialshould be of low viscosity and should con-tain a wide range of volatile materials oflight fractions. Slow-curing liquid asphaltsare frequently used, particularly grades SC-70 and -250. Medium-curing cutback as-phalts, grades MC-30, -70, and-250, have also been used successfully.Road tars have been used to some extent,especially RT-1.

Many residual oils from oil refineries havebeen used in this work. In only expedientsituations, waste military oils (such ascrankcase oils) can be used. The amountof oil ranges from about 1/2 to 1 gallon persquare yard and is applied in two or threeincrements, depending on the type and con-dition of the oil. The serious environmen-tal, ecological implications of these methodsmust be considered. Also, using thesemethods will greatly impair the ability ofbituminous admixtures and surface applica-tions to properly cure, if applied later.

STABILIZED SOIL

Bituminous, stabilized soil mixtures andsoil-cement are used as road surfaces tocarry light traffic in expedient situations forrelatively brief periods. Mechanically stabi-lized soil mixtures are widely used as sur-faces for military roads under favorable con-ditions. Requirements for mechanically sta-bilized surfaces are discussed below:

Gradation requirements for mechanicallystabilized soils used directly as surfaces areshown in Table 9-5. Mixtures that have amaximum size of aggregate of 1 to 1 1/2 in-ches are preferred because the large par-titles tend to work to the surface under traf-fic. Somewhat finer soil is desirable in amixture that will serve as a surface com-pared with one used for a base. The finersoil makes the surface resistant to theabrasive effects of traffic and to the penetra-tion of precipitation. Such a surface will

Table 9-5. Suggested grading requirementsfor gravel and composite-type surface course

of processed materials

9-28 Road Design

Page 312: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

also more easily replace (by capillary action)moisture that is lost by evaporation.

Road surfaces require an LL of 35 or lessand a PI ranging between 4 and 9. Forbest results, the PI of a stabilized soil thatwill function first as a wearing surface andthen as a base, with a bituminous surfaceto be provided later, should be 5 or less.The LL should be less than 25. Compac-tion, bearing value, and frost action are im-portant considerations for surfaces of thistype.

SAND CLAY

One type of mechanically stabilized soil sur-face is called a sand-clay road. It consistsof a natural or artificial mixture of sandand clay that is graded and drained to forma road surface. Although difficult to ob-tain, the PI should be less than 5 and LLless than 25, in case this layer becomes asubbase after placing additional layersabove the sand clay. The gradation require-ments for a typical sand-clay surface are inTable 5-4, page 5-12, under the column for1 -inch sand-clay. The addition of finegravel (slightly larger than the No. 4 sieve)usually adds stability.

Sand-clay roads will carry light trafficreasonably well and heavy traffic exceptunder bad weather conditions. The amountof moisture these roads absorb determinestheir stability under traffic loads. Dust con-trol, blading, and dragging are needed.Sand-clay roads withstand traffic betterthan ordinary earthen roads, but their useis limited to areas where a suitable mixtureof sand and clay occurs naturally or wherea deficiency of either is readily corrected.As a base course for future surfacing, sand-clay roads produce poor results, unless theplasticity can be reduced by adding a chemi-cal stabilization agent such as lime.

to fine, with a maximum allowable size of 1inch. Recommended gradation require-ments for a gravel surface are given inTable 9-6. A natural pit- or bank-rungravel may meet these requirements withoutfurther processing other than screening.Some pit- or bank-run gravels may requireboth screening and washing to meet the re-quirements. River-run gravels normally re-quire the addition of binder to the soil, asdo mechanically stabilized soil mixtures.River-run gravels may also require crushingto provide a rough, angular surface ratherthan the natural, smooth surface charac-teristic of river-run materials. The abilityto carry heavy, sustained traffic depends onthe strength and hardness of the gravel, thecohesiveness of the clay binder, the thick-ness of the layer, and the stability of thesubgrade. These roads can be built rapidly,even in cold weather. Organizational equip-ment of combat engineer units is readilyadapted to hauling and placing a gravel sur-face.

Like other untreated surfaces, gravel roadsrequire considerable maintenance such asblading and dust control in dry weather.During wet weather, proper maintenance isdifficult, especially under heavy traffic.Gravel road surfaces with low plasticitymake excellent base courses for later-stagepavements.

Table 9-6. Suggested grading requirementsfor coarse-graded type surface course of

processed materials

GRAVEL

Gravel roads consist of a compacted layerof gravelly soil that meets the plasticity re-quirements for mechanically stabilized soilmixtures. The gravel is graded from coarse

Road Design 9-29

Page 313: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

PROCESSED MATERIALS requirements in Table 9-6, page 9-29. Theinformation presented here about gravel

Processed materials are prepared by crush-ing and screening rock, gravel, or slag. A

roads generally applies to roads ofprocessed materials. When gravel or sand-

composite-type surface material should clay is available, processed materials shouldmeet the gradation requirements of Table not be used except when their use will save9-5, page 9-28. A coarse-graded type of time and effort. surface material should meet the gradation

EXPEDIENT-SURFACED ROADS

Several types of roads are considered ex-pedient surfaced. These are unsurfacedroads and roads where some material hasbeen placed on the natural soil to improvethe roadway. Types of expedient-surfacedroads include corduroy, chespaling, landingmats, Army track, plank tread, wire mesh,snow and ice, and sand grid.

CORDUROY-SURFACED ROADS

A corduroy road is an expedient road whichuses logs or small trees as the road surface(decking). This method of construction isused in extremely muddy terrain whenthere is a sufficient supply of naturalmaterial. There are three types of corduroyconstruction: standard corduroy, corduroywith stringers, and heavy corduroy.

Standard CorduroyThe most frequently used corduroy road,shown in Figures 9-25 and 9-26, is built of6- to 8-inch diameter logs about 13 feetlong. The logs are placed across the roadsurface adjacent to each other from butt totip. Along the edges of the roadway, place6- to 8-inch-diameter logs as curbs and

Figure 9-25. Standard corduroy

attach them in place with driftpins. Drivepickets about 4 feet long into the ground atregular intervals along the outside edge ofthe road to hold the road in place. To givethis surface greater smoothness, fill thegaps between logs with brush, rubble, ortwigs. Cover the whole surface with a layerof gravel or dirt. Construct side ditchesand culverts as for normal roads.

Corduroy with Stringers

A more substantial corduroy road is madeby placing log stringers, as shown in Figure9-27, parallel to the centerline on about 3-foot centers. Lay a standard corduroy overthem, Securely pin the corduroy decking tothe stringers, and prepare the surface asdescribed in the preceding paragraph.

Heavy Corduroy

Sleepers (heavy logs 8 to 10 inches indiameter) are used for heavy corduroyroads. The sleepers must be long enoughto span the entire road. Place the sleepersat right angles to the centerline on 4-footcenters. Build a corduroy with stringers,as shown in Figure 9-28, on top of thesleepers.

Figure 9-26. Standard corduroy - oblique view

9-30 Road Design

Page 314: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-27. Corduroy with stringers

Figure 9-28. Heavy corduroy

Choice of Corduroy Type

Generally, softer ground requires a heaviertype of corduroy. The stringers andsleepers do not increase the bearing

capacity of the decking. They serve as acrib, keeping the road surface above thelevel of the surrounding mud. They sinkinto the ground until a stratum capable ofsupporting the load is reached. On fairlyfirm ground, the standard corduroy may beadequate; on softer ground, stringers areneeded, Portable corduroy mats can beprefabricated and put down quickly whenneeded, They are made by wiring 4-inch-diameter logs together.

Diagonal corduroy is preferred for heavytraffic. It is made by placing the decking atan angle of 45 degrees to the centerline.This modified construction is applicable toall three corduroy types. The angled deck-ing decreases the impact load because eachlog supports only one wheel at a time andthere is longitudinal and lateraltribution.

CHESPALING

Chespaling is a hasty expedienteither mud or sand. It is madegreen saplings, preferably aboutches in diameter and 6 1/2 feet

weight dis-

used infrom small,1 1/2 in-long. They

are wired together to form a 12-foot-longmat as shown in Figure 9-29. Chespalingis often rolled into bundles and carried oneach wheeled vehicle. The mats are used to

Figure 9-29. Chespaling

Road Design 9-31

Page 315: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1 /AFPAM 32-8013, Vol 1

cross sandy terrain or to get out of mud.Some mats are constructed from dimen-sioned timbers wired together to resemble apicket fence. A variation slightly more effec-tive for crossing sand is made by attachingchicken-wire netting to the bottom of themats.

To build a chespaling road, lay a doublerow of mats, each mat having its long axisparallel to the centerline with a 1-foot over-lay at the centerline. Wire the matstogether. Keep the road wet to prevent thesaplings from becoming brittle and breaking.

Bamboo mats are an excellent chespaling-type expedient for beach roadways. Thesemats are light and comparatively strong.They are made by splitting 2-inch bamboorods and weaving them into a mat in a man-ner similar to rug weaving. Soak the rodsbefore weaving, and keep the mats moistwhile they are in use. An 11- by 4-footmat takes about 15 man-hours to con-struct. The mats are placed with the longdimension parallel to the centerline. Themats remain serviceable for three or fourmonths on firm ground or sand. Bamboomats can also be used over mud.

LANDING MATS

The demand for rapidly constructed air-fields led to the development of several pori-able, metal landing mats. When metal air-field landing mats became a standard supp-ly item in the TO, they were quickly put touse on beaches as well as on airfields.They are still the foremost expedient forcrossing sandy terrain. Landing-matdesigns fabricated from aluminum alloyscan support heavier loads. They also pro-vide smoother surfaces and have a lowerweight per square foot.

When used on sand, place the metal land-ing mats directly on the sand to the lengthand width desired. If pierced steel mats areused, place an impervious membrane underthe mat to smooth and firm the subgrade,thus improving the road.

Place the mat so that its long axis is per-pendicular to the flow of traffic. If a widthgreater than the effective length of oneplank is required, use half sections to stag-ger the joints. A second layer of the steelmat, laid as a treadway over the initiallayer, increases its effectiveness.

Landing mats tend to curl at the edges.This problem can be overcome by anchoringthe edges properly. Screw-type earthanchors furnished with the mat sets pro-vide the best means of anchoring. Anothermethod of securing the edges is to use acurb of timber on the outside edge of theroad and either wire it tightly to buried logslaid parallel to the road or stake it. Onetype of landing-mat surface is shown in Fig-ure 9-30. If MO-MAT (a reinforced plasticmaterial) is available, it may be used as aroadway surface for vehicular traffic.

ARMY TRACK

A portable timber expedient called Armytrack, shown in Figure 9-31, can be used topass vehicles across sandy terrain. Thetrack consists of 4- by 4-inch or larger tim-bers threaded at each end onto a 1/2-inchwire rope or a 3/4-inch hemp rope. Thetimbers resemble railroad ties, and a cableruns through them on each side. Spacethe timbers so that the smallest-wheeledvehicle using the road can obtain traction.Drill cable holes at a 45-degree angle to thecenterline so the cable will bend. This prac-tice will prevent individual timbers frommoving together. Anchor the cables secure-ly at both ends. Fill spaces between thetimbers with select material to smooth outthe surface.

PLANK-TREAD ROAD

The plank-tread road is shown in Figure 9-32, page 9-34. To construct a plank-treadroad, first place sleepers 12 to 16 feet long,perpendicular to the centerline on 3- to 4-foot centers, depending on the loads to becarried and subgrade conditions. (Iffinished timber is not available, logs may beused as sleepers.) Then place 4- by 10-inch planks parallel to the line of traffic to

9-32 Road Design

Page 316: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-30. Landing-mat road

Figure 9-31. Army track

Road Design 9-33

Stakes

Sand

Metal landing mat

:::.,.... ---...~ -:-::::--­..... ..-- ..

1/2" wire cable or 3/4" nemp rope

Page 317: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-32. Plank-tread road

form two treads about 36 inches apart.Stagger the joints to prevent forming weakspots. If desired, 6-inch curbs may be in-stalled on the inside of the treads.

Use plank roads for crossing short sectionsof loose sand or wet, soft ground. Whenbuilt with an adequate base, plank roadslast for several months. Planks 3 to 4 in-ches thick, 8 to 12 inches wide, and atleast 13 feet long arc desirable for flooring,stringers, and sleepers. When desired, 3-by 10-inch planks (rough, not finished) canreplace the 4- by 10-inch timbers shown inFigure 9-33. Rough 3- by 8-inch and 3- by10-inch planks can be cut to order.

Position stringers in regular rows parallel tothe centerline, on 3-foot centers, with stag-gered joints. Lay floor planks across the stringers with about 1-inch gaps whenseasoned lumber is used. The gaps allowfor swell when the lumber absorbs mois-ture. Spike the planks to every stringer.

Place 6-inch-deep guardrails on each side,with a 12-inch gap left between successivelengths of the guardrail for surface-waterdrainage. Place pickets along each side at15-foot intervals to hold the roadway inline. Where necessary, use corduroy orother expedient cross sleepers spaced on

Figure 9-33. Construction details for a plank road

9-34 Road Design

Page 318: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

3- to 5-foot centers to hold the stringers inplace and to gain depth for the structure.

For drainage, construct the base for aplank road with a transverse slope insteadof a center crown. To provide a smoother-riding surface, place treads parallel to theline of traffic over the floor planks.

WIRE-MESH ROAD

Most wire-mesh surfaces are expedientmeasures. Applied directly to the subgrade,they provide passage for a limited numberof vehicles for a short time. Longer life canbe obtained by proper subgrade prepara-tion, multilayer or sandwich construction,and frequent staking. Wire-mesh roadsshould never be crossed by other roads un-less planking or some such material isplaced over the mesh to protect it.

Chicken wire, expanded metal lath (used forplastering walls), and chain-link wire meshmay be used as road expedients in sand.Mesh surfaces should not be used onmuddy roads because they prevent grading

and reshaping of the surface when ruts ap-pear.

Any wire-mesh surface is much more effec-tive if a layer of burlap or similarmembrane material is placed underneath itto help confine the sand. (See Figure 9-34.)Lighter forms of wire mesh, such as chick-en wire or cyclone fencing, require an extralayer. Often a sandwich type of construc-tion is used-one layer of wire mesh fol-lowed by one layer of burlap, then a secondlayer of wire mesh.

Wire mesh must be kept taut. Anchor theedges of a wire-mesh road at 3- to 4-foot in-tervals. Diagonal wires crossing the center-line at a 45-degree angle and attachedsecurely to buried pickets reinforce thelight mesh.

SNOW AND ICE ROADS

In regions with heavy snowfall and wheretemperatures are below freezing for ex-tended periods, expedient roads can be con-structed over the snow. When the road is

Figure 9-34. Construction details for a wire-mesh road

Road Design 9-35

Page 319: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

laid out, make grades and curves as gentleas possible. Compact the snow until it iscapable of supporting the weight ofvehicles. Add water on the compactedsnow and allow it to freeze to produce ahard surface. Frozen lakes or streams canbe used to move traffic, but first carefullyreconnoiter the route for quality of ice,thickness, cracks, and shore conditions.Determine the load-bearing capacity eitherby an actual test or by consulting Table 9-7.

Table 9-7. Load capacity of ice

USE OF POLYMER CELLS (SAND GRID) TO BUILDSANDY SOILS

Trafficability over sandy soils is difficult tomaintain. The soil strength is adequate,but the soil will displace under a load, dueto its cohesionless nature. Wheeledvehicles arc particularly affected. In orderto improve trafficability, sand-grid baselayers can be used.

Sand grid involves the confinement and com-paction of sand or sandy soils in intercon-nected cellular elements called grids toproduce a load-distributing base layer.Uses of the grid include road and airfieldpavements, airfield crater repair, erosioncontrol, field fortifications, and expedientdike repair.

Plastic grids (national stock number (NSN)5680-01-198-7955) are manufactured andshipped in collapsed 4-inch thick, 110-pound sections. (See Figure 9-35.) Eachexpanded grid section is 8 by 20 feet andcontains a honeycomb arrangement of cells.Each cell has a surface area of 39 squareinches and a depth of 8 inches. Grids aredelivered in 3,000-pound pallets, each con-taining 25 collapsed 8- by 20-foot sections.

A sand-asphalt surfacing

ROADS IN

is incorporatedwithin the top portion of the sand-gridcells. Its function is to seal the sand intocells and provide a wearing surface formoderate amounts of rubber-tired traffic.The sand-asphalt surfacing is formed byspraying a suitable liquid-asphalt cement,emulsion, or cutback (rapid-curing (RC) 250at 165+0 F is preferred) on the surface of

Figure 9-35. Plastic grids

9-36 Road Design

Page 320: Army Construction Manual FM5 430 Vol1 Entire

the sand-grid layer. The asphalt usedshould penetrate into the top 1/2 to 1 inchof sand in the cells. Over a sand subgrade,such a sand-grid road is capable of han-dling over 10,000 passes of heavy truck traf-fic, including tandem-axle loads of up to53,000 pounds. Avoid tracked vehiclestraveling over this road, as their tracks willeasily damage the grid cells.

The following are the procedures for emplac-ing sand grid.

EQUIPMENT RECOMMENDED

Equipment recommended for the emplace-ment of sand grid includes bulldozers;smooth-bucket (no teeth) scoop loaders;rough-terrain forklifts; vibratory rollers;water distributors; bituminous distributors;long-handled, round-pointed shovels; and3/8-inch by 8-foot by 4-foot plywood sheets.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SITE PREPARATION

Site preparation includes the following steps:

1. Perform normal cut or fill operations toreach desircd road grade.

2. Back blade the surface for smoothness.

3. Compact the sand subgrade at a mois-ture content approaching saturation usingthe vibratory roller.

GRID INSTALLATION

Grid installation includes the followingSteps:

1. Set up stakes and string lines in 8-footby 20-foot boxes. See Figure 9-36 forlayout patterns.

2. Deliver grid pallets with the forklift.

Figure 9-36. Sand-grid layout patterns

Road Design 9-37

Page 321: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

3. Expand each grid section using threepeople on each end, pulling outward toslightly over 20 feet, then shaking the sec-tion in midair to obtain uniform cell open-ings. (See Figure 9-37.) Place the sectionwhere string lines dictate, (8-foot by 20-fool steel frames can be ordered.)

4. Shove sand from road shoulders intoeach end cell and approximately every fifthsirtc-edge cell to anchor the grid in place.

5. To construct joints between grids, uscsmall, 3/8-inch plywood sheets 10 allow sol-diers to stand on top of the unfilled grid, al-lowing access to the joint cells. For endjoints, the rounded end cells from differentsections should touch each other. For lon-gitudinal (side-by-side) joints, interlock the“welded” cell portions of each section, as iffitting a puzzle. Fill the jointed cells withsand.

6. Level the joints by placing plywood overthe joints and having soldiers walk on topof the plywood.

7. Completely fill each grid using scooploaders. (See Figure 9-38.) Drop the sandvertically into the cells from a height of atleast 2 feet. Do not push the sand forwardor the cells will be displaced. Overfill gridsby 2 to 4 inches so scoop loaders canoperate on the sand-filled grid layer withoutdamaging any cells. Have scoop loadersvary wheel paths to achieve uniform initialcompaction of the road.

8. If water is readily available, wet thesand using a water distributor. This willsignificantly aid in the compaction process.

9. Compact the road surface with one ortwo passes of the vibratory roller.

Figure 9-37. Plastic sand-grid section emplacement

9-38 Road Design

Page 322: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-38. Sand-grid road - filling cells with sand

10. Remove excess sand from the grid sur- 13. Apply a very light coat (1/4 inch) offace with a grader or by back blading with blotter sand using shovels.a smooth-bucket scoop loader. Do not usea bucket with teeth, as cell damage can 14. Compact the road using one pass of aresult.

11. Recompactthe vibratory roller.9-40.)

nonvibrating roller. Vibrating the road atthis point will break the asphaltic bonds,

the road with one pass of(See Figure 9-39, page 15. Apply and compact a 3-inch surface

coat of 1-inch (maximum) gravel, if avail-able. This layer will add a protective cover

12. Spray the asphalt product on the road material over the sand-grid road, significant-surface and allow enough time for the as- ly increasing the road life.phalt product to completely soak into thegrid structure (usually about 10 hours).(See Figure 9-40, page 9-40.)

Road Design 9-39

Page 323: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-39. Sand-grid road - compacting sand with roller

Figure 9-40. Sand-grid road - spraying asphalt coating

9-40 Road Design

.....

- ------- }--. --- - ----.--

Page 324: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

SPRAY APPLICATIONS AND SURFACE TREATMENTS

Surface treatments are the most economicaltroop-constructed surfaces. They requirethe fewest resources and minimal qualitycontrol effort, and they are placed in theshortest period of time. Surface treatmentsrange from single, light applications ofbituminous material to multiple surfacecourses made up of bitumen and ag-gregates. Surface treatments can bedivided into two categories: sprayed treat-ments and sprayed bitumen with an ag-gregate surface.

Spray applications provide soil or ag-gregate surfaces with the following:

• Prime coat (waterproofing).

• Tack coat (binding bituminous pave-ment to surface).

• Dustproofing.

Sprayed bitumen with an aggregate surfaceprovides a waterproof, abrasive, wear -resis-tant surface with no structural strength.Bitumen with aggregate surface pavementswill be either of the following:

• Single surface treatment.

• Multiple surface treatment.

Bituminous materials are either tars, road-tar cutbacks, asphalt cement, asphalt cut-backs, or asphalt emulsions. Uses ofbituminous materials are shown in Figure9-41, page 9-42. Asphalt cement is theheavy material left at the end of thepetroleum distillation process. Crude oil isrefined into gasoline, kerosene, diesel,motor oil, asphalt, and many otherproducts as shown in Figure 9-42, page 9-43. Asphalt cement may then be furthermodified by cutting back the asphalt withsome petroleum product, specifically naph -tha, gasoline, kerosene, or diesel, to forman asphalt cutback. Asphalt may also be-come an emulsion by mixing asphalt ce-ment, water, and an emulsifying agenttogether with variable-speed pumps to forman asphalt water suspension. Emulsionsare either anionic (carrying a negative

charge) or cationic (carrying a positivecharge).

Tars are the residue from the high-tempera-ture conversion of coal to coke. (See Figure9-43, page 9-44.) They may be modified bycutting them with a light to medium coaloil to form a road-tar cutback. Tars do notdissolve in petroleum products. They be-come soft and bleed at high temperaturesand are brittle at cold temperatures. Be-cause of their susceptibility to temperaturechange, tars normally arc used only inareas where fuel spills are commonplace,such as tank farms, fuel depots, andaircraft refuel points.

FIELD IDENTIFICATION

Field identification consists of a series ofsimple tests designed to identify an un-known bitumen product in the field. Thepurpose of these tests is to determine theuses of a bituminous material and how touse it safely, rather than the exact specifica-tions to which it conforms. Field-identifica-tion procedures are applicable to both tarsand asphalts.

Bituminous materials are often found stock-piled in unmarked or incorrectly markedcontainers. This leads to confusion anddelay in construction since the varioustypes and grades of bituminous materialare manufactured for a specific purpose.

Field identification is important to themilitary engineer because—

• Once the type and grade of material areknown, the type of surface that can beconstructed may be determined. Thesafety procedures to be followed alsodepend on the material identification.

• Once the surface type is known, the con-struction procedure may be outlinedand scheduled for a specific target date.

• Once established, the procedure willdetermine the proper equipment for thejob.

Road Design 9-41

Page 325: Army Construction Manual FM5 430 Vol1 Entire

Figure 9-41.

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

9-42 R

oad

D

esign

TYPE ASPHALt CEMENTS CUTBACK ASPHALTS EMULSIFIED ASPHALTS TARS 1 OF Y18COSITY

GRADED CONSTRUCTION -ORIGINAL

ASPHAlT-AGGREGATE MIXTURES CONCRETE AWJ ~ ~ ~ ~ ~ HOT lAID PlANT MIX

PAVEMENT BASE AWJ SURFACES HIGHWAYS AIRPORTS X " PARKING AREAS X DRIVEWAYS CURBS X '" HlUSTAIAL FLOORS BlOCKS GROINS X DAMFACNJS IX CANAl AND RESERVOR LINNGS X X

COLD - LAID PLANT MIX PAVEMENT BASE AWJ SURFACES OPEN.QRADEO AOCiREGATE' WELl..QRADEO AOOREOATE' PATCHING. "'ED~TE USE PATCHING. STOCKPIlE

MIXED -IN - PLACE (ROAD MIX) PAVEMENT BASE AWJ SURFACES OPEN· ORAOED AOGREGATE' WEll • ORAOED AOGREGATE' SAND X X SANDY SOIl X

PA TCHIiIO, .. MEDIATE USE PATCHING. STOCKPIlE

ASPHALT-AGGREGATE APPUCA TlONS(SURFACE TREATMENl)

SNJLE SURFACE TREATMENT X X MUL Tf'I.E SlRFACE TREATMENT AOClRIEBA TE SEAL SAWJSEAL SlURRYIEAL

(PENETRATION tAACADAM)

PAVEMENT BAlES LAAOEV008 8IoIAI.L YODe I x

ASPHAlTAPPUCA~ (SURFACE TREATMENl)

FOG SEAL PRIME COAT, OPEN SURFACES PlUME COAT, TIOHTSURFACES TACK COAT OUST LAYING MUlCH

(MEMBRANE) CANAL N«J RE8ERYOIA LININGS XI EMIINIOoIENT ENVELOPES XIX

(CRACK FIWNG) AIIPHAL T PAVEMENT I

PORTlN«JCEMiNTCONCAETEPAVEMENT 4 r I • E ..................................... ·,.."NqUiNd

10-..... ... _.- .. -.IoIIod ........ IO-.

VI8COIIITY PENElRATDH IW'D ORADED ORADED CU'lING ~IIIDUE (RC)

IIII! ~Ji!§§11 ii~ Ji!i§B X X XI .. 1 X X

IX X IX X X

X X X X X X X

X X X X X x

X l( X

X X W X

X X lC ix" x~

X ~-

X X X X X X X X

X It X X It X X

I I XIX

I X ixl T

X X

l(

I X T I x x TT

I I I I 4 I'

1 FOR USE IN COLD CLltAATES

4 RUBBER ASPHALT COMPOUNDS

MEDIUM 8t.OW I CU'lING CU'lING ANDHIC CATlONIC ( ..... (8C)

j·8 i I ~ a ...

!iI Ji! i ~'B Ji!i § I iiiiiii !:::: ............ CD ~ ~ ~~~~~~~~~-;~~ I- Nft .. ..,.,... •• ___ a:

IX X l( X

!

X X

-x-: X X X ...... X X l( IX IX IX X IX )( X It X X X X X X X X X X X X X X x

x X III IX X X X X X X X X X X X X X X X X X X X lC It X

X l( X X X x x X X XX ,,,- X X X X X X x-l[ xy

I X X X X X X X X X X X X X X X

X X X X X X X X X X :1 t: X x 11

X X X X X X X x

I I I I I I I I X XIX I I x X

T I X X X XI I I I X XI

2 2 2 2 X X X X

X X X X X X 2 2 X • I. X X X X X X X X

• z • • x X X X X X

I I I I I I T I I I I I I I I

I I J_ L~l~. I I I I I I I I I I

A FOR USE IN BASES IN COLD CUtAATES 2 DIWTED WITH WATER 3 SlURRY MIX

• Emullitlad asphaIIs shown ani AASHTO and ASTM grIIdn and may not Include HI grades produced in aI geographic areas.

Figure 9-41. Use of bituminous materials

Page 326: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-42. Petroleum-asphalt flowchart

Road Design 9-43

OIL WELL

This simplified graphic chart shows the Int8fl'81atlonshlps of petroleum products, with gasoline, 011 and asphalt flowing from the same oil well.

FUEL OIL

ASPHAL T CEMENTS

'2.. __ -""""'1'- KEROSINE

~--~ UGHT BURNER 011

DIESEL OIL

LUBRICATING 01'

UQUID ASPHALTIC MATERIALS

RC-3000

SLOW­CURING

ASPHALTS

MEDIUM­CURING

ASPHALTS

GAS

PETROlEUM Lp~~n ~ .......... ~ •• ~ M-l00 1~150 200-300

RAPID­CURING

ASPHALTS

SAND AND WATER OXIDIZED ASPHALTS

SS-K 5S-Kh

ANIONIC EMULSIFIED ASPHALTS

CATIONIC EMULSIFIED ASPHALTS

Page 327: Army Construction Manual FM5 430 Vol1 Entire

Figure 9-43.

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

9-44 R

oad

D

esign

BITUMINOUS

COAL

STORAGE

OECANTATION

COKE OVEN PLANT

STORAGE TUBE STILL

FRACTIONATING COLUMN

TAR REFINERY

R88IduaI Tar

COKE {

Metallurgical Coke

Domestic Coke

LIGHT OIL {

Benz_ Toluene Xy~ne,~entNaph~

Coumarone Resins

GAS {

Illuminating Gas,Fuet Gas

Suller,Cyanogen Compounds

LIQUOR {

Iq.Ja Ammonia, Anhydrous Ammonia

Ammonium Sulfate

LIGHT OIL

IEDIUIIOIL

HEAVY OIL

~{Light and Heavy Solvents I PRocESSI~ Counwone-Indens Resins

fPhenola Pyridine Bases I PROCESSING ~ ~,creosote Creosote, Anthracene I PROCESSI~G}- Special Huxing oils

• •• (RTCB5 Cold patching, Seal coal and Road Mix

\. RTCB6 Cold patdling, Seal coat and Road Mix

~~

::> 0

VARIOUS DEGREES 0 i:i OF DISTILLATION

~I~ -.., !- t I ~!~= I [ ~= 11 ~';;..I

SATURANTS ROOFING ELECTRODES PAINTS ELECTRODES CORE COMPOUNDS

COATINGS ENAMElS RUBBERCOMPOUNDS FUEL

BRIQUETTES

RT 1 Dust Laying

RT 2 Prime Coating RT 3 Prime Coating IIIId Surface Treatments RT 4 Prime Coating and Surface Treatments

RT 5 Surface Treatments and Road Mixes

RT 7 ATe) AT 8 Surface TraMnentI, Seal Coalll and Road Mixes

RT g

RT 10) Seal CoaIII Tar Conc:reee and Hot ........... RT11 ' ~.

RT 12, ,........, MIadIm,r. Conc:reee,and HotRapars

Figure 9-43. Tar simplified flowchart

Page 328: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Field tests may be performed to identify thebituminous paving material as asphalt ce-ment, asphalt cutback, asphalt emulsion,road tar, or road-tar cutback. In addition,it is necessary to identify as closely as pos-sible the viscosity grade of the bitumen. Inorder to distinguish among the several as-phaltic and tar products, it is necessary toknow something of their origin, their physi-cal properties, and the manner in whichthey are normally used. The identificationprocedure outlined in Figure 9-44, page9-46, is based upon the physical propertiesof these materials.

Asphalts and Tars

The first procedure in the identification ofan unknown bituminous material is todetermine whether it is an asphalt or a tar.Asphalts and tars may be differentiated bya simple volubility test. To perform thetest, simply attempt to dissolve an un-known sample (a few drops, if liquid, orenough to cover the head of a nail, if solid)in any petroleum distillate. Kerosene,gasoline, diesel oil, or jet fuel is suitable forthis test. Since asphalt is derived frompetroleum, it will dissolve in the petroleumdistillate. Road tar will not dissolve. If thesample is an asphalt, the sample distillatemix will consist of a dark, uniform liquid.If it is a road tar, the sample will be adark, stringy, undissolved mass in the distillate. A check can be made by spotting apiece of paper or cloth with the mix. Thevolubility test provides a positive method ofidentification.

Grades of Asphalt Cement

The various grades of asphalt cement aredistinguished principally by their hardness,as measured by a field penetration test ex-plained in TM 5-337. This information maybe sufficient for planning or, in some cases,actually starting emergency construction.

Asphaltic Cutbacks

The pouring or nonpouring quality is oneway to distinguish between an asphalt ce-ment and a cutback or emulsion. Asphaltcement is cutback with a petroleum distil-late to make it more fluid. If the material

does not pour, it is an asphalt cement.Note that at 77° F, even the softest asphaltcement will not pour or deform noticeably ifthe container is tilted. If it pours, it is acutback or emulsion. If it is soluble ordilutable in water, it is an emulsion. In ad-dition, the manner in which it pours willfurnish a clue to its grade.

To determine whether a cutback is a RC as-phaltic cutback or not, the smear test isperformed. This is done by making auniform smear of the substance on a pieceof glazed paper or other convenient, nonab -sorbent surface. This will give the volatilematerials, if present, a chance to evaporate.Since RCs are cut back with a very volatilesubstance, most of the volatiles will evap-orate within 10 minutes. The surface ofthe smear will then become tacky. This isnot true of the lighter grades of medium-and slow-curing asphaltic cutbacks (MCsand SCs), which remain fluid and smoothfor some time. An MC will not result in atacky surface for a matter of hours; for SCmaterials, several days may be required.

To identify an 800- or 3,000-grade MC orSC cutback, a prolonged smear test is used.This process is necessary because thesegrades of MCs and SCs contain such smallquantities of cutterstock that they, too, maybecome tacky in the 10-minute periodspecified above. A thin smear of thematerial is made on a nonabsorbent surfaceand left to cure for at least 2 hours. Bythe end of that time, if the material beingtested is an RC, the smear will have curedand will be hard or just slightly sticky.However, if the material being tested is anMC or SC, the smear will not be cured andwill still be quite sticky. If the material isan RC 3,000, it will cure completely in 3hours, whereas an RC 800 will take about6 hours. Even after 24 hours, an MC orSC will still be sticky.

Since MCs are cutback with kerosene andSCs with oil, this fact may be employed todifferentiate between them. Heat is used todrive off the kerosene, if present, and makeit show up in the form of an odor. It isbest to heat the unknown sample in a

Road Design 9-45

Page 329: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-44. Identification of unknown bituminousmaterials

9-46 Road Design

40-85 Hard AC 40

Dissolves asphalt

Solubility test in petroleum distillate

Beads emulsion

(Color test) - dark brown (Water mixing test) - mixes with water (Flame test) - will not burn Sand coating test

Pour test

Will not pour asphalt cement

Penetration test

85-150 Medium AC 20/30

Will not mix RS

Will pour asphaltic cutback

(Determine viscosity 30-3,000)

150-300 Soft AC 5/10

Tacky RC

Smear test

Oily MC or SC

Heat odor test

Kerosene/petroleum smell MC

Will mix MS or SS

No odor SC

1-3 RT

Tacky RTCB

Strings tar

Pour test

4-7

Smear test

8-12 RT

Oily RT

Page 330: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

closed container in order to capture the es-caping vapors, being careful not to applytoo much heat. If the sample is an MC, itwill have a strong petroleum or keroseneodor. On the other hand, if the sample isan SC, no kerosene or petroleum odor willbe detected. It might smell somewhat likehot motor oil. The ability to distinguish anRC from an MC and an SC from either, isperhaps as important as any other part offield identification.

Asphalt Emulsions

Another asphaltic material used in pavingwork is an asphalt emulsion, which is amixture of asphalt, water, and an emulsify-ing agent. It is easy to identify, since it isusually distinguished by its dark browncolor, while the other bitumens are black,If mixed with kerosene or some otherpetroleum distillate, the emulsion can bedetected by the appearance of small blackglobules or beads which fall to the bottomof the container. If mixed with water, anemulsion will accept the extra water andstill remain a uniform liquid. The otherbitumens will not mix with water. Since anemulsion contains water, a small piece ofcloth saturated with it will not burn if aflame is applied. The other bitumens willburn or flame. After it has been estab-lished that the material is an emulsion, itis still important to know whether or notthe emulsion is a mixing grade. The bestway to tell if the emulsion is a mixing grade(slow-setting (SS) or medium-setting (MS)) isto try to mix a small amount (6 to 8 per-cent, by weight) with damp sand using ametal spoon. A rapid-setting (RS) emulsioncannot be mixed; it breaks immediately,gumming up the spoon with the relativelyhard original asphalt cement. A SS or MSemulsion mixes nicely, coating the sand.Be careful not to add too much emulsion tothe sand. This will saturate the sand andnot give conclusive results. No further iden-tification is necessary, since both MS andSS grades are largely used for the samejobs.

Road Tars

If the unknown bituminous material did notdissolve in the volubility test but formed a

stringy mass, as shown in Figure 9-44, thematerial is a tar. The next step is to deter-mine its viscosity grade by the pour test.By comparing the flow to that of commonmaterials, such as water or honey, the vis-cosity of the tar may be closely estimated.The grades vary from road tar (RT)-1 to RT-12. If the identified tar has a viscosity inthe range of RT-4 to RT-7 material, asmear test must be performed to determinewhether it is a road tar or a road-tar cut-back. The smear test is performed in themanner previously described for cutback as-phalt. A great increase in stickiness inabout 10 minutes identifies a road-tar cut-back. No apparent change in consistencyafter 10 minutes indicates a road tar. Itdoes not matter which grade of cutback isavailable, since both are used under ap-proximately the same conditions.

AGGREGATE IDENTIFICATION

The aggregate must also be tested to deter-mine its suitability for bituminous construc-tion. The desirable characteristics of an ag-gregate used in bituminous construction in-clude—

• Angular and rough.

Ž Tough, hard, and durable.

• Clean and dry.

• Hydrophobic.

Available aggregate may not always have alldesirable characteristics. An aggregatemeeting most of the requirements is usuallyselected, unless rejected for reasons suchas availability, length of haul, or difficultyin conducting borrow-pit or quarry opera-tions.

Angular and Rough

The aggregate in a pavement must transmitthe traffic load to the base, usually by theinterlocking and surface friction of the dif-ferent particles. Angular particles with arough texture arc best for this purposesince they do not tend to slide past eachother. More binder may be required since

Road Design 9-47

Page 331: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

the angular shape has a greater surface-area-per-unit volume than a round particle.

Tough, Hard, and Durable

The aggregate must withstand loads withoutcracking or being crushed. Resistance toweathering is also a function of thedurability. The resistance-to-wear of an ag-gregate can be determined by the Los An-geles Abrasion Test, if the equipment isavailable. The equipment and proceduresare detailed in the American Association ofState Highway and Transportation Officials(AASHTO) method T96. The equipment forthe above test is usually not available forfield testing. The Mob’s hardness scalemay be used to determine the hardness ofthe aggregate. The Mob’s scale ranges from1 for talc or mica to 10 for diamond. Bytrying to scratch the aggregate or the com-mon materials and vice versa, it is possibleto establish which is harder; from thisanalysis the hardness of the aggregate canbe determined. If both materials scratcheach other, the hardness of each is thesame. Be sure to rub the “scratch” mark tosee that it is really a scratch and not a pow-dering of the softer material. Some com-mon materials and their hardness are:fingernail, about 2: copper coin, between 3and 4; and knife blade, nail, and windowglass, about 5.5. If the material can bescratched with one of these common items,it is considered to be soft. If it cannot bescratched, it is considered to be hard.

Clean and Dry

The bituminous binder must penetrate intothe pores of the aggregate and adhere tothe surface of the particles. Coated (withclay or dust) or water-filled aggregate willprevent the penetration or the adherence ofthe binder and result in stripping of thebinder. For hot mixes, the aggregate mustbe hot as well as dry. If the aggregate isnot clean, it should be washed either aspart of the crushing operation or by spread-ing it on a hard surface and hosing it withwater. When washing is impractical, dryscreening may remove a great deal of dustand clay. Hand picking may be necessaryif no other method can be used. The ag-gregate should be made as clean as pos-

sible with the equipment and manpoweravailable.

Hydrophobic

Affinity for water can make an aggregate un-desirable. If the aggregate is porous and ab-sorbs water easily (hydrophilic), the bindercan be forced out of the pores. When thishappens, the bond between the aggregateand binder weakens and breaks and strip-ping occurs. Stripping is the loss of thebituminous coating from the aggregate par-ticles due to the action of water, leaving ex-posed aggregate surfaces. One of the follow-ing three tests can be used to determinethe detrimental effect of water on abituminous mix:

Stripping Test. A test sample is preparedby coating a specific amount of aggregatewith bituminous material at the applicabletemperature for the grade of bitumen to beused. The mixture is spread in a loose,thin layer and air-cured for 24 hours. Arepresentative sample is placed in a jar (upto no more than one-half of its capacity)and covered with water. The jar is closedtightly and allowed to stand 24 hours. Atthe end of 24 hours, the jar with thesample is vigorously shaken for 15 minutes.A visual examination is made to determinethe percentage of exposed aggregate surfacewhich is reported as percent stripping.

Swell Test. Asphaltic mixtures containingfines of doubtful quality are sometimesmeasured for swell as a basis for judgingthe possible effects on a pavement. Thistest is more frequently used with dense-graded mixtures using liquid asphalts. Asample of the mix is compacted in a metalcylinder and cooled to room temperature.The specimen and mold are placed in a panof water and a dial gage is mounted abovethe sample in contact with the surface. Aninitial reading is taken. The specimen is al-lowed to soak for a specified period (usually24 hours) or until there is no further swell-ing. Another reading of the dial is taken.The difference in reading is the swell of themixture. Experience has shown thatbituminous pavement made with clear,sound stone; slag; or gravel aggregate and

9-48 Road Design

Page 332: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

mineral filler produced from limestone will Aggregates of doubtful character should beshow test values of less than 1.5 percent. tested for conformance to ASTM tests.

CONSTRUCTION METHODS

PRIME COAT

A prime coat is used when a surface treat-ment or pavement is placed on a soil or ag-gregate base. The prime coat shouldpenetrate the base about 1/4 inch, fillingthe voids. The prime coat acts as awaterproof barrier to prevent moisture thatmay penetrate the wearing surface fromreaching the base. Also, the bitumen actsas a bonding agent, binding the particles ofthe base to the wearing surface. Plan prim-ing operations so that there will always bean adequate amount of cured, primed baseahead of the surfacing operations; but notso far ahead that the base will become dirtyor completely cured (dead). To preserve thebase, a prime coat should be applied assoon as the base is ready; however, theprime coat will lose its effectiveness as abonding agent if the wearing surface is notplaced soon after curing.

Base Preparation

The base should be well-graded, shaped tothe desired cross section, compacted to thespecified density, well-drained, free from ex-cessive moisture but not completely dry,and swept clean. The surface of the baseshould be broomed if it contains an appreci-able amount of loose material, either fine orcoarse, or if it is excessively dusty. Whenbrooming is omitted, apply a prime coat tothe base and lightly roll it with apneumatic roller, or use a light sprinklingof water to settle the dust. Sprinkling isusually undesirable; but when it is neces-sary, lightly apply a spray of water at therate of approximately 0.2 gallon to 0.3 gal-lon per square yard, depending on the con-dition of the base, the temperature, and thehumidity. Completely cover the base with aminimum amount of water and allow it tobecome dry or almost dry before applyingthe prime coat so that it will absorb the

prime material. If the base is too wet, itwill not take the prime properly and themoisture will tend to come out, particularlyin hot weather, and strip the prime fromthe base during construction. Rains alsotend to strip the prime from a base thatwas too wet when primed. Heavy rainsmay also strip a properly primed base tosome extent, but less than an improperlycured base. In general, the lowest accept-able moisture content for the upper portionof the base course prior to priming shouldnot exceed one-half of the optimum mois-ture content. On the other hand, if thebase dries out completely, cracks maydevelop and a heavy rain may then causeswelling and loss of density. See Chapter 5of this manual for subgrade, subbase, andbase-course preparation.

Materials

Bituminous materials used for prime coatswill depend on the condition of the soil baseand the climate. In moderate and warmclimates, RT-2, RT-3, RT-4, MC-30, MC-70,SS-1, SS-1h, cationic slow-setting emulsifiedasphalt (CSS)-1, and CSS-1h are satisfac-tory. In cold climates, rapid-setting asphaltcutbacks, such as RC-70 and RC-250, haveproved more satisfactory. If the climate isvery cold, the prime coat may be eliminatedbecause it is likely to be extremely slow incuring. RT-2 and MC-30 are satisfactoryfor a prime coat used on a densely gradedbase course. MC-70 is generally used onloosely bonded, fine-grained soils, such aswell-graded sand. MC-250 is usually satis-factory for coarse-grained sandy soils.

The formula used to determine the quantityof prime coat material required is—

Road Design 9-49

Page 333: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

where—

L = length of untreated surface in feetW = width of untreated surface in feet

("+2" in the formula is to include for over-spray of shoulders 1 foot on both side ofthe road. )

AR = application rate of prime coat in gal-lons per square yard

NOTE: AR for dense soils = 0.2, AR forsoils with a lot of cracks = 0.5

LF = handing loss factor for prime coat(usually 1.05 - 1.10)

= quantity of prime-coat material ingallons

Example:

Compute the quantity (in gallons) of prime-coat material required to prime an un-treated surface with dense soil. The sur-face is 1,000 feet long and 12 feet wide.Use a loss factor of 1.05.

Solution:

= 326.67 or 327 gallons

TACK COAT

A tack coat is a sprayed application of abituminous material that is applied to an ex-isting wearing surface of concrete, brick,bituminous material, or binder coursebefore a new bituminous pavement isplaced over the existing surface. The pur-pose of the tack coat is to provide a bondbetween the existing pavement and the newsurface. The tack coat should becometacky within a few hours. A tack coat isnot required on a primed base unless theprime coat has completely cured and be-come coated with dust. Figure 9-45 showsthe sequence of operations for the applica-

tion of a tack coat. Operation of asphalt-surface-treatment equipment is explained inFM 5-434.

The procedure for estimating the bitumenrequired for a tack coat is similar to thatdescribed for a prime coat except that thetack coat is generally applied only over theproposed width of the pavement. The for-mula used to determine the quantity oftack coat required is--

where—

L =W =

AR =ions per

LF =ually 1.05)

= quantity of tack coat material in gallons

length of treated section in feetwidth of treated section in feetrate of application of bitumen in gal-square yardhandling loss factor for bitumen (us-

The tack coat is generally applied only overthe width of the existing area that is to besurfaced. A tachometer chart may be usedto establish the rate of application, Theusual rate of application vatries between0.05 and 0.25 gallon per square yard. Ona smooth, dense, existing surface, the mini-mum rate of 0.05 gallon per square yardshould produce a satisfactory bond. If thesurface is worn, rough, and cracked, themaximum rate of 0.25 will probably be re-quired. An extremely heavy tack coat maybe absorbed into the surface mixture result-ing in a bleeding and flushing action andloss of stability. Roll the surface lightlywith a rubber-tired roller or truck tires foruniform distribution of the bituminousmaterial.

Example:

Compute the quantity (in gallons) of tack-coat material required to cover a worn,rough, and cracked surface. The surface is1,000 feet long and 12 feet wide. Use aloss factor of 1.05.

9-50 Road Design

Page 334: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-45. Tack-coat sequence of operations

Solution:

= 350.0 gallons (gal)

DUSTPROOFING

Dustproofing consists of spraying an un-treated surface with a diluted, slow-settingasphalt emulsion or a low-viscosity cutbackThe asphalt and dilutent penetrate the finesoil particles and adhere to the dust par-ticles.

An asphalt cutback is usually sprayed at arate of 0.1 to 0.5 gallon per square yard

. When using an emulsion, diluteit with up to five parts of water by volume.Diluted-emulsion rustproofing treatmentsusually require several treatments. Thedust stirred by traffic between applicationseventually conglomerates and no longerrises. This is an effective treatment in verydusty areas where one application of cut-back asphalt is insufficient. In all cases,lay a test strip to determine what applica-tion rate will be the most effective. Apply

with either an asphalt distributor or some-thing as simple as a common watering can.Rustproofing is usually a short-lived solu-tion and project plans should includeregular inspections and maintenance, as re-quired.

SPRAYING ASPHALT WITHCOVERED-AGGREGATE AND SINGLE

AND MULTIPLE SURFACE TREATMENTS

A sprayed asphalt with a cover-aggregatesurface treatment consists of an applicationof asphalt followed by an application of ag-gregate. If the process is repeated, theresulting surfaces arc referred to as double,triple, quadruple, and so on, surface treat-ments, depending on the number of applica-t ions.

Apply these surface treatments on aprimed, nonasphaltic base; an asphalt basecourse; or any type of existing pavement.This type of surface treatment, with a goodprime coat (see preceding paragraph),provides the lowest-cost waterproof coveringfor a road surface. With good aggregate,this type of surface treatment will economi-cally provide a wearing surface to meet theneeds of medium and low volumes of traffic.

Road Design 9-51

Page 335: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

This type of surface treatment is very use-ful as a wearing surface on base courses inthe staged construction of highways pend-ing placement of asphalt-concrete surfacecourses.

Limitations in the use of sprayed asphaltwith cover-aggregate surface treatmentsare—

Ž Weather conditions must be favorable.

Ž The surface on which the asphalt issprayed must be hard, clean, and dryfor the surface treatment to adhereproperly.

Ž The amount and viscosity of the asphaltmust be carefully balanced with the sizeand amount of cover-aggregate to as-sure proper retention of the aggregate.

• Heavy, high-speed traffic tends to dis-lodge the aggregate from the asphalt.

Because of these limitations, consider usingplant-mix surface treatments when theabove conditions are anticipated.

Single Surface Treatment

A single surface treatment usually consistsof a sprayed application of a bitumen andan aggregate cover one stone thick. Sur-face treatment may be referred to as a sealcoat, armor coat, or carpet coat. A singlesurface treatment, shown in Figure 9-46, isusually less than 1 inch thick. Surfacetreatments serve only as an abrasive andweather-resisting medium that waterproofsthe base. They are not as durable asbituminous concrete and may require fre-quent maintenance. Although they are notrecommended for airfields, they may beused as an expedient measure. They areparticularly suitable for TO construction be-cause they can be laid quickly with a mini -mum of materials and equipment, con-structed in multiple layers with little inter -ference to traffic, and used as the first stepin stage construction. Surface treatmentwill not withstand the action of metalwheels on vehicles, tracked vehicles, or non-skid chains on vehicle wheels. Do not at-

tempt surface treatments when the tempera-ture is below 50° F.

The three requirements for a surface treat-ment arc as follows:

• The quality of the bitumen must be suf-ficient to bold the stone without sub-merging il.

Ž Sufficient aggregate must be used tocover the bitumen.

• The base course on which the surfacetreatment is laid must be sufficientlystrong to support the anticipated trafficload.

Uniformly graded sand or crushed stone,gravel, or slag may be used for surfacetreatments. The purpose of the surfacetreatment dictates the size of aggregate tobe selected. For example, coarse sand maybe used for scaling a smooth, existing sur-face. For a badly broken surface, the maxi-mum size of the aggregate should be about3/4 inch; the minimum size should passthe No. 4 sieve. Surface treatments includethe following: dust palliatives, prime coats,and sprayed asphalt with a cover aggregate(single and multiple surface treatments).

Material

RC and MC cutbacks, road tars, rapid-set-ting emulsions, and asphalt cements maybe used for surface treatment. RC cut-backs are most widely used because theyevaporate rapidly and the road can beopened to traffic almost immediately afterapplying the surface treatment. Viscositygrades of the bitumen depend on the size ofaggregate used as cover stone. The largerparticles of aggregate require a bitumen ofhigher viscosity so that the bitumen willhold the aggregate. For example, RC-70 orRC-250 may be used with coarse sand for asurface treatment to seal cracks in an other-wise satisfactory surface. For resurfacing abadly cracked or rough surface, RC-800 orRC-3,000 may be used with 3/4-inch ag-gregate.

To assure uniform distribution, the bitumenshould be applied with a bituminous

9-52 Road Design

Page 336: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-46. Single surface treatment

distributor. The quantity of the bitumen re-quired is based on the average particle sizeof the cover stone. The bitumen must besufficient to hold the aggregate in placewithout leaving a sticky surface. The aggre-gate must not be completely submerged inthe bitumen. One-quarter-inch aggregateshould be submerged approximately 30 per-cent: 3/8-inch aggregate, 32 percent; 1/2-inch aggregate, 35 percent; and 3/4-inch ag-gregate, 43 percent. Approximately 1 gallonof bitumen is usually used for 100 poundsof aggregate. The recommended rate ofbitumen application is given by the follow-ing formula:

Example:

Compute the recommended rate of bitumenapplication, in gallons per square yard, if

30 pounds of aggregate are required tocover an area of 1.0 square yard.

Solution:

Requirements for a Surface Treatment

In bituminous surface treatments, the unitquantities of bitumen and aggregate can bedetermined by a test strip, by the specifica-tions of the job, or by adding approximately1 gallon of bitumen for every 100 pounds ofaggregate or 0.1 gallon of bitumen for every10 pounds of aggregate. The weight of theaggregate, one stone deep, required to cover1 square yard is determined by spreadingthe aggregate to be used a depth of onestone over a measured surface, weighing it,and computing the amount in pounds persquare yard.

Road Design 9-53

Page 337: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

The formula used to determine the quantityof binder material required for a surfacetreatment is—

where—

L = length of treated surface in feetW = width of treated surface in feet

= application of bitumen in gallonsper lb of aggregate (usually 1 gal per 100 lbaggregate or 0.01 gal per lb)

= application of aggregate in lb persquare yard

LF = handling loss factor for bitumen = quantity of binder material required

in gallons9 = square feet per square yard

conversion factor

Example:

Compute the required quantity of bindermaterial needed for a single surface treat-ment. The surface is 1,000 feet long and12 feet wide. Use a bitumen applicationrate of 0.01 gal per lb of aggregate and aloss factor of 1.05. The aggregate is 3/8-inch crushed stone with a unit weight of100

Solution:

Determine the application rate of the ag-gregate in pounds per square yard.

Now determine the binder quantity.

Multiple Surface Treatment

When a tougher, more resistant surface isdesired than that obtained with a single sur-face treatment, a multiple surface treatmentmay be used. A multiple surface treatmentis two or more successive layers of a singlesurface treatment (as shown in Figure 9-47). Smaller particles of aggregate and cor-respondingly less bitumen are used for eachsuccessive layer. Although multiple surfacetreatments are usually more than 1 inchthick, they are still considered surface treat-ments because each layer is usually lessthan 1 inch and the total surface treatmentdoes not add to the load-carrying capacityof the base.

The first layer of a multiple surface treat-ment is laid according to instructions pre-viously given for a single surface treatment.Loose aggregate remain ing on the first layermust be swept from the surface so that thelayers may be bonded together. As statedpreviously, the size of the aggregate and theamount of the bitumen will decrease foreach successive layer. For the secondlayer, the bitumen will usually be reducedto one-third or one-half the amount of thefirst application. The aggregate used in thesecond application should be approximatelyone-half the diameter of that used in thefirst application. The final application of ag-gregate should be swept clean, if necessary,so that an even layer of aggregate willremain. It should also be rolled with apneumatic roller so that the aggregate willbecome embedded in the bitumen. Afterthe surface is rolled and cured, it is readyfor traffic. If the multiple surface treatmenthas been laid on an airfield, loose aggregatemust be swept from the surface so that itwill not damage the aircraft. Final sweep-ing is also recommended for roads.

CONSTRUCTION OF SURFACETREATMENTS USING SPRAYED

ASPHALT WITH COVERED AGGREGATE

Weather

Weather conditions are an important factorfor success in the construction of sprayedasphalt with covered-aggregate surface treat-

9-54 Road Design

Page 338: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-47. Multiple surface treatment

ments and seal coats. For best results inaggregate retention, the pavementtemperature should be relatively highduring the application of the seal coat andconsiderably lower before fast traffic is al-lowed to use the new seal coat. A certainamount of curing, or setting, is requiredeven with the heaviest liquid-asphalticmaterials. This curing takes place bestwhen the air temperature is well above 50°F and the relative humidity is low, A sur-vey of surface treatments rated excellentshows more than 85 percent were placed inthe hot summer months. Every effortshould be made to plan the work for place-ment in summer weather. After completionof the surface treatment, traffic should becontrolled until the surface has cured.

Aggregate

Once an aggregate has been selected foruse based upon the desirable charac-teristics, it is then necessary to determine

what quantity of the aggregate will be re-quired for a specific job. When placing asurface treatment with an aggregate cover,the quantity of aggregate required can bedetermined from the following formula:

where—

L = length of treated surface in feetW = width of treated surface in feetLF = handling loss factor for aggregate (10

percent or 1.10). = application rate for aggregate = quantity of aggregate in tons

The materials for a multiple surface treat-ment are determined by the same methodas above except that the results are multi-plied by the number of treatment passes,The aggregate size (not quantity) must becut in half for the second layer and eachlayer thereafter.

Road Design 9-55

Page 339: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Spreading Aggregate. Before the applicationof asphalt begins, an adequate aggregatespreader should be available and properlyadjusted for the aggregate actually to beused. The spray-bar width of thebituminous distributor should be equal tothe width of the aggregate being spread inone pass. Normally, this is the width ofone traffic lane. An adequate supply of ag-gregate should be on hand to cover the as-phalt that has been spread, without inter-ruption, in the shortest practical time afterthe asphalt hits the surface. In addition,the aggregate spreader should be filled, inplace, and ready to spread aggregate beforecommencing the asphalt spray. A commonfault is to operate the distributor too farahead of the aggregate spreader.

Aggregate spreaders vary from a simple, con-trollable gate box attached to the dumptruck, to very efficient, self-propelled unitswhich apply the larger-size aggregate on thebottom and the finer on top. The more effi-

cient, self-propelled units are mostdesirable.

Standard, Hopper-Type Aggregate Spreaders.The standard aggregate spreader shown inFigure 9-48 can handle aggregate which ran-ges from sand to 1 1/2-inch gravel. Therate and depth of application depend uponthe gate opening. The width of spread maybe varied from 4 to 8 feet in 1-foot incre-ments. Depending upon the manufacturer,the spreader has either two or four wheels.It hooks on the rear of a 5-ton dump truckand the truck backs up. This allows the ag-gregate to be spread on the bitumen aheadof the truck tires, thus preventing pickup ofthe bitumen. As a safety precaution, menshould not be allowed to stand on the ag-gregate, either in the truck or in thespreader, at any time.

Rolling. Pneumatic-tire rollers should beused for surface-treatment construction.Steel-wheeled rollers are not recommendedfor rolling, but if they are all that is avail-

Figure 9-48. Typical hopper-type aggregate spreader

9-56 Road Design

Page 340: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

able, rollers should not be so heavy as tocrush the aggregate particles. Pneumatic-tire rollers are essential to firmly embed theaggregate into low areas or graded deform-ities that would normally be bridged overby use of steel-wheel rollers and to produceconformity across the width of the roadway,particularly over the outer quarters of thesurface where there is the least traffic. Therollers should be heavy enough to properlyimbed the aggregate, but rolling should bestopped as soon as crushing becomes evi-dent. When double or triple surface treat-ments are used, each course should berolled before subsequent applications of as-phalt. When an asphalt fog seal is used, itshould be applied after the rolling is com-pleted.

Traffic Control. It is extremely importantthat traffic be controlled to prevent loss ofaggregate. One method of controlling trafficis to form a single line of traffic behind apilot vehicle with a red flag between stopsat each end of the work area.

The Asphalt Distributor

The asphalt distributor is the key piece ofequipment in the construction of surfacetreatments. It consists of a truck (or atrailer) equipped with a mounted, insulatedtank with a heating system, usually oil-burning, with direct heat from the flue pass-ing through the tank. It is further suppliedwith a power-driven pump, suitable to hand-le products ranging from light, cold-applica-tion liquid asphalt to heavy asphalt ce-ments heated to spraying viscosity. At-tached to the back end of the tank is a sys-tem of spray bars and nozzles throughwhich the asphalt is forced under pressureonto the construction surface. The con-struction of the spray bars should be suchthat there will be full circulation of the as-phalt through the bar when not spraying.These spray bars should have a minimumapplication width of 8 feet. On larger equip-ment, the spray bars will cover as much asa 24-foot width in one pass when equippedwith a suitable capacity pump. The heightof the spray bar determines the type ofcoverage: singlelap, as shown in

lap, double lap, or tripleFigure 9-49. A suitable

Figure 9-49. Spray bar coverage

thermometer should be installed in thetank to readily ascertain the temperature ofthe contents. A connection should be avail-able to attach a hose for a single- or double-nozzle outlet to cover areas not reached bythe spray bars or as a means of forcing astream of asphalt to a desired point as insubsealing rigid, slab pavements. Dis-tributors are made in sizes ranging from800- to 4,000-gallon capacity. Some main-tenance distributors as small as 400 gal-lons are available.

It is essential that the distributor becapable of distributing the asphalt uniform-ly over the surface to be treated. For bestresults in surface treatments, observe thefollowing points:

• Maintain uniform pressure and tempera-ture on all spray nozzles. The fan of thespray from each nozzle must be uniformand set at the proper angle with thespray bar (according to themanufacturer’s instructions) so that thespray fans do not interfere with eachother.

• Maintain the spray bar at the properheight above the road surface (accord-ing to the manufacturer’s instructions)10 provide complete and uniform overlapof the spray fans.

Ž Ensure that the distributor road speedis uniform.

Ž Before beginning work, check thespread of the distributor spray bar.

Road Design 9-57

Page 341: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Valve action should be instantaneous,both in opening and closing. The spray-ing operation should be inspected fre-quently to ensure that the nozzles arethe proper height from the road surfaceand working fully. An otherwise goodjob may be spoiled if one or more spraynozzles are clogged.

MAINTENANCE AND REPAIRBITUMINOUS SURFACES

Inspection

OF

Maintenance patrols frequently inspectbituminous pavements for early detection offailures. Small defects quickly develop intolarger ones under the effects of weather andtraffic and may result in pavement failureunless promptly corrected. Minor repairsare quickly made with small crews andhand-tools, with a minimum interruption oftraffic. Larger bituminous repairs requiremore time, personnel, and equipment, andmay result in interference with traffic or, inextreme cases, require construction ofdetours to avoid complete stoppage.

Patches

All patches should be trimmed square oroblong with straight, vertical sides running

parallel and perpendicular to the centerlineof the traffic area.

Temporary Repairs

Any stable material may be used for tem-porary repairs in combat areas or wheresuitable material is not available and thetraffic area must be patched to keep trafficmoving. Good-quality soil and masonry orconcrete rubble are suitable for this pur-pose. All such patches must be thoroughlycompacted and constantly maintained withreplacement material. More permanentpatching should be accomplished as soonas possible.

Maintenance of Shoulders

Shoulders are bladed to facilitate drainageof rainwater from the surface. Ruts andwashouts are filled. Shoulder material iskept graded flush against pavement edgesto restrict seepage of water to the subgradeand to prevent breaking of the pavementedge by traffic driving off the pavementonto the shoulder. Material displaced fromshoulders is replaced with new material asrequired.

GENERAL ROAD STRUCTURAL DESIGN

TO roads will normally be designed as un-surfaced, aggregate, or flexible-pavement sys-tems. The design procedure for each typefirst involves assigning a class (A - G) desig-nation to the road based upon the numberof vehicle passes per day. A design cate-gory (I - VII) is then assigned to the trafficbased upon the composition of the traffic.A design index (1- 10) is determined fromthe design category and road class. This de-sign index is used to determine either theCBR strength requirements of the unsur-faced roads or the thickness of the aggre-gate surface or flexible-pavement system re-quired above a soil with a given CBRstrength.

NOTE: As mission requirements change(a forward-area road becomes a rear-arearoad), the road class and design indexwill change. The design procedures out -lined in this section allow for the easyupgrading of roads as the mission chan-ges. This ensures the ability to easilyconvert an unsurfaced road to an ag-gregate-surfaced road to a flexible-pave-ment road without major changes in thedesign procedure.

CLASSES OF ROADS

The classes of roads vary from A to G.Selection of the proper class depends uponthe traffic intensity and is determined fromTable 9-8.

9-58 Road Design

Page 342: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 9-8. Road-class selection criteria

DESIGN INDEX

The design of roads will be based on adesign index representing all traffic ex-pected to use the road during its life. Thedesign index is based on typical magnitudesand compositions of traffic reduced toequivalents in terms of repetitions of an18,000-pound, single-axle, dual-wheel load.For designs involving pneumatic-tiredvehicles, traffic is classified into threegroups, as follows:

• Group 1. Passenger cars and panel andpickup trucks.

• Group 2. Two-axle trucks (excludingpickup trucks).

• Group 3. Three-, four-, and five-axletrucks.

Traffic composition will then be groupedinto the following categories (summarizedfor easy reference in Table 9-9):

Ž Category I. Traffic composed primarilyof passenger cars and panel and pickuptrucks (Group 1 vehicles) but contain-ing not more than 1 percent two-axletrucks (Group 2 vehicles).

• Category II. Traffic composed primarilyof passenger cars and panel and pickuptrucks (Group 1 vehicles), and contain-ing as much as 10 percent two-axletrucks (Group 2 vehicles). No trucks

Table 9-9. Pneumatic-tired traffic categoriesbased on traffic composition

having three or more axles (Group 3vehicles) are permitted in this category.

Ž Category III. Traffic containing asmuch as 15 percent Group 2 but withnot more than 1 percent of the total traf-fic composed of trucks having three ormore axles (Group 3 vehicles).

• Category IV. Traffic containing asmuch as 25 percent Group 2 but withnot more than 10 percent of the totaltraffic composed of trucks having threeor more axles (Group 3 vehicles).

• Category IVA. Traffic containing morethan 25 percent Group 2 or more than10 percent trucks having three or moreaxles (Group 3 vehicles).

design index to be used, if designing aTheroad for the usual pneumatic-tired vehicles,will be selected from Table 9-10 based on

Table 9-10. Design index for pneumatic-tiredvehicles

Road Design 9-59

Page 343: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

the road class (A to G) and category (I toIVA) .

Where tracked vehicles or forklift trucks areinvolved in the traffic composition, the fol-lowing three considerations apply:

• Tracked vehicles not exceeding 15,000lb and forklift trucks not exceeding6,000 lb are treated as two-axle trucks(Group 2 vehicles) in determining thedesign index.

Ž Tracked vehicles exceeding 15,000pounds but not 40,000 pounds andforklift trucks exceeding 6,000 poundsbut not 10,000 pounds are treated asthree-axle trucks (Group 3 vehicles) indetermining the design index.

• Traffic composed of tracked vehicles ex-ceeding 40,000 pounds and forklifttrucks exceeding 10,000 pounds hasbeen divided into the three categoriesshown in Table 9-11.

Table 9-11. Tracked-vehicle and forklift trafficcategories

Roads sustaining traffic of tracked vehiclesweighing less than 40,000 pounds andforklift trucks weighing less than 10,000pounds will be designed according to thepertinent class and category from Table 9-10, page 9-59. Roads sustaining traffic oftracked vehicles heavier than 40,000pounds and forklifts heavier than 10,000pounds will be designed according to thetraffic intensity and category from Table 9-12.

NOTE: DO NOT include any wheeledvehicles in the total number of trackedvehicles and forklifts when using Table9-12.

Design Life

The life assumed for design is less than orequal to 5 years. For a design life of morethan 5 years, the design indexes in Tables9-10 and 9-12 must be increased by one.Design indexes below 3 need not be in-creased.

Entrances, Exits, and Segments

Regardless of the design class selected forhardstands, special consideration should begiven to the design of approach roads, exitroads, and other heavy-traffic areas.Failure or poor performance in these chan-nelized traffic areas often has greater im-pact than localized failure on the hardstanditself.

Since these areas will almost certainly besubjected to more frequent and heavierloads than the hardstand, the design indexused for the primary road should be usedfor entrances and exits to the hard stand.

Table 9-12. Design index for tracked vehicles and forklifts

9-60 Road Design

Page 344: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

In the case of large hardstands having mul-tiple uses and multiple entrances and exits,consideration should be given to partition-ing and using different classes of design.The immediate benefits that would accrueinclude economy through elimination of ex-cessive design in some areas and better or-ganization of vehicles and equipment.

UNSURFACED ROADS

An unsurfaced road is one in which the in-place natural soil or borrow soil is used asthe road surface. Typically, the construc-tion effort required includes only clearingand grubbing followed by scarifying grad-ing, and compacting.

Designing unsurfaced roads consists of thefollowing steps:

1. Estimate the number of passes of eachtype of vehicle expected to use a road on adaily basis.

2. Select the proper road class based uponthe traffic intensity from Table 9-8, page9-59.

3. Determine the traffic category basedupon the traffic composition criteria shownin Table 9-9, page 9-59.

4. Determine the design index from Table9-10, page 9-59, or Table 9-12.

5. Read the soil-surface strength requiredto support the design index from Figure9-50.

6, Check whether the design (compacted)CBR value of in-place soil exceeds the CBRvalue required. If the in-place design CBRvalue is less than the CBR required, theengineer must decide whether 10 decreasethe design life or improve the in-place soilto meet the CBR required by one of thefollowing methods: soil stabilization, soiltreatment, or placing aggregate.

7. Determine the required unsurfaced-soilthickness. Given the required CBR fromstep 6 and the design index from step 4,the required unsurfaced-soil thickness ordepth of compaction can be obtained fromFigure 9-51, page 9-62.

Example (Unsurfaced-Road Design):

To illustrate the procedure for determiningsoil-surface strength requirements, assumethat an unsurfaced road is to be used oneyear. The road will be subjected to the fol -lowing average daily traffic:

Figure 9-50. Unsurfaced-soil strength requirements

Road Design 9-61

Page 345: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-51. Unsurfaced-soil thickness requirements

quired. If not, consider using either soil

Solution:

1. Determine the average daily traffic(given).

2. Select road class E from Table 9-8, page9-59, based upon 230 vehicles per day.

3. Select traffic category IVA, based uponthe percentage of Group 3 vehicles.

4. The design index is 3 from Table 9-10,page 9-59.

5. The soil-surface strength reequirementfor a design index of 3 is 10.8 CBR.

6. Check to ensure the design CBR valueof the in-place soil exceeds the 10.8 CBR re-

stabilization or an aggregate road.

7. Determine the required unsurfaced-soilthickness from Figure 9-51. Given a designindex of 3 and a required CBR of 10.8, therequired thickness from Figure 9-51 is 6 in-ches.

AGGREGATE-SURFACED ROADS

The design of aggregate-surfaced roads issimilar to the design of unsurfaced roads.However, in aggregate-surfaced roads.Layers of high-quality material are placedon the natural subgrade to improve itsstrength.

Materials

Materials used in aggregate roads mustmeet the requirements as stated in Chapter5 of this manual and in the followingparagraphs. The materials should havegreater strength than the subgrade andshould be placed so that the higher-qualitymaterial is placed on top of the lower-quality material.

9-62 Road Design

Page 346: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 9-13. Compaction criteria and CBRrequirements for an aggregate road structure

NOTES:1. All lifts in a road design must be at least 4inches.2. A cohesive soil is one with a PI above 5.3. A cohesionless soil is one with a PI of 5 or less.4. Percent compaction Is compared to theCE 55 curve according to ASTM D1557.

Select and Subbase Materials

Select and subbase materials used in ag-gregate and flexible-pavement roads mustmeet the requirements of Table 9-13.

Base Course

Only good-quality materials should be usedin base courses of heavy-duty aggregateroads. Specifications for graded, crushed

aggregate; lime rock; and stabilized ag-gregate may be used without qualificationfor design of roads, streets, and parkingareas.

Specifications for dry and water-boundmacadam base courses may be used fordesign of heavy-duty roads only when thefollowing two conditions arc satisfied:

• The cost of the dry or water-boundmacadam base does not exceed the costof a stabilized, aggregate base course.

Ž The construction unit has the equip-ment and expertise to place a macadamsurface (wet or dry) to acceptable stand-ards of smoothness and grade.

Design CBR of Base Course. Where sub-base material is used for base-course con-struction, the base course CBR must be atleast 50 and the material must conform tothe gradation and Atterberg limit require-ment for a 50-CBR subbase as shown inTable 9-14. Otherwise, the design CBR ofthe base course must meet the require-ments of Table 9-15, page 9-64.

Gradation Requirements. Gradation requ ire-ments for aggregate-surfaced roads and formacadam base courses are given in Chapter5.

Table 9-14. Maximum permissible values for subbases and select materials

Road Design 9-63

Page 347: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 9-15. Assigned CBR ratings for base-course materials - aggregate-surfaced road

Thickness Requirements. Thickness require-ments for aggregate-surfaced roads aredetermined from Figure 9-52, page 9-65, fora given soil strength and design index. Theminimum thickness requirement will be 4inches.

Figure 9-52 provides the thickness of ag-gregate based on CBR and design index.The thickness determined from the figuremay be constructed of compacted granularfill for the total depth over the compactedsubgrade or in a layered system of granularfill with subbases for the same total depth.The layered section must be checked to en-sure that an adequate thickness of materialis used to protect the underlying layerbased on the CBR of the underlying layer.The granular fill may consist of base, sub-base, and select material, provided the top4 inches meet the gradation requirement ts

Compaction Requirements

Cornpaction requirements for the subgradeand granular layers are expressed as a per-cent of maximum CE 55 density as deter-mined by using MIL-STD-621 Test Method100.

Normal Subgrades. Compact the subgradeto 90-percent CE 55 density for cohesivesoils (PI>5; LL>25) and 95-percent forcohesionless soils

NOTE: It may be possible to compact thesubgrade material to the required density

in its natural state. However, in cases wherethe moisture content is out of the specifica-tion range, it may be necessary to scarifythe soil (thereby aerating the soil to adjustthe moisture content) and then compact.This process is called scarify and compactin place (SCIP).

Special Subgrades. The procedures for com-pacting subgrades of clays that losestrength when remolded, silts that becomequick when remolded, and soils with expan-sive characteristics are described in Chap-ter 5 of this manual.

Subgrade in cuts and fills must have den-sities equal to or greater than the valuesshown in Table 9-13, page 9-63, exceptthat fills will be placed at no less than 95percent density for cohesionless soils or 90percent for cohesive soils.

Where this is not the case for cuts, the sub-grade must (1) be compacted from the sur-face to meet the densities shown; (2) beremoved and replaced, in which case the re-quirements given above for fills apply; or (3)be covered with sufficient select material,subbase, and base so that the uncompactedsubgrade is at a depth where the in-placedensities are satisfactory.

Depth of Compaction. Compact the sub-grade to the depth specified in Table 9-16,page 9-66, for cohesive soils (PI > 5) andTable 9-17, page 9-66, for cohesionlesssoils (PI 5).

NOTE: When depth of compaction fromTable 9-16 or 9-17 is not feasible or at-tainable in cut sections, perform a 6-inchSCIP and continue design based on theuncompacted subgrade CBR.

Select Materials. The procedure is the sameas for the subgrade.

Subbase. Compact the subbase to not lessthan 100-percent CE 55 density.

Base Course. Compact the base course tothe maximum degree practicable but notless than 100-percent CE 55 density.

9-64 Road Design

Page 348: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-52. Design curves for aggregate-surfaced roads.

Road Design 9-65

100--------~----~--~--~_r~_r~r_----r_--r_--~r_~r__,

~~------~--~~_4--+_4_4_+_rt----~--t_--_t--_r__1 ~~-------+----~--~~--+-+-~rr----~--1_----r_--r_~ ro~------~--~~_4--+_4_4_+_rt----~--t_--_t--_r__1

~~~----~--~~-4--+-~4_+_rt----~--t_--_t--_t__;

a: B

8~--------+_----+_~~~~~~~~~~~~--_+----_+--_;--~

7~--------~----~~--~~~~~~~~~~~~--~----_+----~~

6~--------+_----+_--~~~~~~~~~~~--_+----_T--_;--_;

2 3 4 5 6 7 8 9 10

Thickness, inches

15 20 40 50

Page 349: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM

Table 9-16. Required

32-8013, Vol 1

depth of subgrade compaction for roads, cohesionless soils

Table 9-17. Required depth of subgrade compaction for roads, cohesive soils (PI>5)

Design Steps for Aggregate-SurfacedRoads

1. Estimate the number of passes of eachtype of vehicle expected to use the road ona daily basis.2. Select the proper road class based uponthe traffic intensity from Table 9-8, page9-59.

3. Determine the traffic category basedupon the traffic-composition criteria givenin Table 9-9, page 9-59.

4. Determine the design index from Table9-10, page 9-59, or Table 9-12, page 9-60.

5. Check soils and construction aggregatesusing standard criteria in Tables 5-4, page5-12; 9-14, page 9-63; and 9-15, page 9-64.

6. Determine the depth of compaction forthe subgrade soil from Table 9-16 or 9-17,

7. Determine the total road-structure thick-ness and cover requirements.

a. Enter Figure 9-52, page 9-65, for eachlayer of soil or aggregate with the followinginformation:

—Design index.—Design CBR values for subgrade, se-

lect, and subbase materials.

b. Determine the minimum cover thick-ness, in inches, for each layer of the aggre-gate road structure.

8. Determine the required percent compac-tion in terms of CE 55 for each layer fromTable 9-13, page 9-63.

9-66 Road Design

Page 350: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

9. Draw the section of the aggregate roadstructure, as shown following.

Example (Aggregate-Road Design):

An aggregate-surfaced road is to be used fortwo years. The road will be subjected to—

AverageVehicle Daily TrafficM998 HMMWV 10

M929 5-ton 25dump truck(dual axle)

M729 combat 35engineer vehicle(CEV) (60-tontracked vehicle)

Available material CBR:Natural subgrade = 5 (clay, PI = 15)Design (compacted) subgrade = 8Clean sand subbase = 30Lime rock = 80; meets gradation requirementfor maximum size aggregate of 1".

Solution:

1. Number of daily passes = 70 (given).

2. Select road class F from Table 9-8, page9-59, based upon average daily traffic of 70.

3. Select traffic category VII from informationpreviously given, based upon the presence ofthe 60-ton tracked vehicle.

4. Select design index of 9 from Table9-12, page 9-60. NOTE: You must round theaverage daily tracked-traffic value of 35 tothe next higher value (40) in Table 9-12.

5. Clean sand CBR 30. (Suitable for subbaseCBR 30.) Crushed rock CBR 80. (Suitablefor base course.)

6. Depth of compaction based on CBR 5 forcompacted subgrade is 15 inches. (See Table9-17.

7. Determine the road-structure thickness re-quired to support a design index of 9.

a. First, look at the required road thicknessif the subgrade was not compacted to thedesign CBR. In this case, the natural subgradeCBR 5 is used in Figure 9-52. This results ina required total thickness of 16 inches, asshown.

b. Now, look at the required thicknesswhen the subgrade is compacted, In thiscase, the design subgrade CBR = 8 is usedin Figure 9-52, resulting in a required totalthickness of 12 inches, as shown.

Road Design 9-67

Page 351: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Notice how compacting the subgrade greatlyreduces the required thickness of the covermaterial. This is why the subgrade is al-ways compacted.

c. Finally, look at the total thickness andrequired cover for each layer when the sub-grade is compacted and a clean sand subbasewith CBR 30 is used. First, the design sub-grade CBR 8 is used in Figure 9-52, page 9-65,to determine the 12-inch total thickness re-quired above the compacted subgrade. Next,the clean sand CBR 30 is used in Figure 9-52to determine the required cover of 4 inchesabove the subbase. This results in the section,as shown.

Notice how the addition of the clean sandsubbase reduces the required thickness ofthe mom expensive lime rock.

9-68 Road Design

8. The required percent compaction of eachlayer is determined from Table 9-13, page9-63, as follows:

Crushed rock base course: 100-105 percentClean sand subbase course: 100-105 percentCompacted subgrade-since the PI = 15, it is acohesive soil: 90-95 percent

9. Draw the section of the aggregate roadstructure. Since two sections weredesigned, one with a subbase and onewithout, both should be drawn.

a. First, design the section without the sub-base layer.

b. Now, the design the section with thesubbase layer.

Page 352: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Given that the base-course material is moreexpensive than the clean sand subbase, sec-tion b would be the most economical design.Note, however, that all possible design sec-tions for the available materials must beevaluated economically. There may be rareinstances where the subbase material maybe more expensive than the base course.In that case, only the base course wouldused.

BITUMINOUS PAVEMENTS

be

Bituminous-, or flexible-, pavement designspermit the maximum use of readily avail-able local construction materials. They areeasier to construct and upgrade than rigidpavement designs. Thus, they permitgreater flexibility in responding to changesin the tactical situation.

Flexible-pavement design procedures are dif-ferent from airfield design procedures. Thischapter is limited to flexible-pavement de-signs for roads. Chapter 12 of FM 5-430-00-2/AFPAM 32-8013, Vol 2 covers airfieldflexible-pavement designs. TM 5-822-6 cov-ers rigid-pavement designs.

Pavement Types and Uses

The descriptions, uses, advantages, and dis-advantages of bituminous pavements andsurfacing presented in TM 5-337 are applica-ble to TO construction except as modified inthe following paragraphs. However, whensurfacing for steel treads is necessary, usean asphalt cement with a penetration gradeof 50-60 or 60-70, depending on the climateor season.

Special consideration must also be given tothe design and construction of bituminouspavements that will be subjected to trafficof tanks and solid, rubber-tired vehicles.Most often the number of passes of tanksand solid, rubber-tired vehicles governs thebituminous-pavement design.

Hot-Mix, Bituminous-Concrete Pavements.Dense-graded, hot-mix. bituminous-concretemixtures are well-suited for paving heavy-duty traffic roads with volumes of 3,000

vehicles or more per day. Where conditionswarrant, use these mixtures to pave roadshaving traffic volumes of less than 3,000 ve-hicles per day. Select exact percentages ofbituminous materials on the basis of designtests described in TM 5-337.

Cold-Laid, Bituminous-Concrete Plant Mix.Where hot-mix, bituminous-concrete mix-tures are not available, use cold-plant, bitu-minous concrete to pave areas subject topneumatic-tired traffic only.

Sheet Asphalt, Stone-Filled Sheet Asphalt,Sand Asphalt, or Sand-Tar Mixes. Fine-ag-gregate mixes may be used for binder andsurface courses of roads with traffic vol-umes of 2,000 or fewer vehicles per daywhen sand or other suitable fine aggregatesare the only aggregates available. Thesemixes should not be used as surface orbinder courses for roads or industrial-usepavements designed for solid, rubber-tiredor steel wheels. In all cases, mixturesmade with these aggregates should conformto the criteria for low-pressure tires (100psi or less), based on laboratory tests.

Penetration Macadams. Do not use penetra-tion macadam for paving any areas subjectto traffic from tracked vehicles.

Bituminous Road Mix. Use road mix as awearing course for TO roads or as the firststep in stage construction for more perma-nent roads. When the existing subgradesoil is suitable or satisfactory aggregates arenearby, road mixing saves time in handlingand transporting aggregates as comparedwith plant mixing. When properly designedand constructed, the quality of road mix ap-proaches that of cold-laid plant mix. Roadmix is used for binder and surface courses.It is generally considered inferior to plant-mix pavements manufactured in standardplants because of the less accurate control.

Flexible-Pavement Structure

A typical flexible-pavement structure is shownin Figure 9-53, page 9-70, and illustrates theterms used to refer to the various layers.

Road Design 9-69

Page 353: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

NOTE: Not all layers and coats are present In everyflexible-pavement structure. Intermediate courses may beplaced In one or more lifts. Tack coats maybe required onthe surface of each intermediate course.

Figure 9-53. Flexible-pavement design

A bituminous pavement may consist of oneor more courses depending on stage con-struction features, job conditions, and theeconomical use of materials. The pavementshould consist of a surface course, an inter-mediate (binder) course, and a levelingcourse, when needed. These should bethick enough to prevent displacement ofthe base course because of shear deforma-tion, to provide long life by resisting the ef-fects of wear and traffic abrasion, to be wa-terproof, and to minimize differential settle-ments.

Sources of Supply

If time and conditions permit, investigatesubgrade conditions: borrow areas; and allsources of select materials, subbase, base,and paving aggregates before designing thepavement. In determining subgrade condi-tions in cut sections of roads, conduct testborings deeper than the frost penetrationdepth. The minimum boring should neverbe less than 4 feet below the final grade.

Materials

Materials used in flexible pavements mustmeet the requirements as stated in Chapter5 and in the following paragraphs:

Select Materials and Subbase

Select materials and subbases used in bitu-minous pavements must meet the same re-quirements as for aggregate-surfaced roadsas indicated in Table 9-14, page 9-63.

Base Course

The base course used in bituminous pave-ments must meet the same requirements asfor aggregate-surfaced roads as indicatedpreviously. except as noted below.

Design CBR of Base Course. Where sub-base material is used for base construction,the base course CBR must be at least 50and the material must conform to the Atter-berg limit requirement for a 50-CBR sub-base as shown in Table 9-14. Otherwise,the design CBR of the base course mustmeet the requirements of Table 9-18.

Base Course Gradation Requirements. Thegradation requirements of the base courseare as indicated in Chapter 5 of this manual.The base course for a flexible pavement mustmeet the same gradation requirements ofTable 5-4, page 5-12, since the flexible pave-ment will transfer most of the shear stresscaused by the load directly to the base course.

Table 9-18. Assigned CBR ratings for basecourse materials - bituminous-surfaced road

9-70 Road Design

Page 354: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Minimum Base-Course Thickness. The mini-mum allowable thickness of the basecourse will be as shown in Table 9-19; ex-cept that in no case will the total thicknessof pavement plus base for classes Athrough D roads be less than 6 inches.

Bituminous-Pavement Mix. Bituminous-pave-ment-mix design consists of selecting the bi-tumen and aggregate gradation, blending ag-gregates to conform to the selected grada-tion, determining the optimum bitumen (as-phalt cement) content, and calculating thejob mix formula. Bituminous-mix design isbeyond the scope of this manual and is de-

underlying layer based on the CBR of theunderlying layer.

Compaction Requirements

Compaction of the subgrade, subbase, andbase course must meet the same require-ments as for aggregate-surfaced roads. Inaddition, an asphalt base course and pave-ment must be compacted to CE-55 densityof 98-100 percent. The compaction criteriaand CBR requirements for a bituminouspavement are summarized in Table 9-20,page 9-73.

Bituminous-Pavement Design

Design Requirements. Flexible-pavement de-

Bitumininous-Pavement Thickness Require-

scribed in detail in Chapter 4 of TM5-337.

ment. Thickness design requirements aregiven in Figure 9-54, page 9-72, in termsof CBR and the design index determined.Minimum thickness requirements areshown in Table 9-19.

Note that each layered section must bechecked to ensure that an adequate thick-ness of material is used to protect the

sign must provide the following:

Ž

Sufficient compaction and testing of thesubgrade and each layer during con-struction to prevent objectionable settle-ment under traffic.

Adequate drainage of the base course,when frost conditions are a factor, toprovide for drainage of the base courseduring spring thaw.

Table 9-19 Minimum thickness, in inches, of pavement and base for conventional pavements

Road Design 9-71

Page 355: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure 9-54. Thickness design requirements for flexible pavements

9-72 Road Design

Page 356: Army Construction Manual FM5 430 Vol1 Entire

Table 9-20. Compaction criteria and CBRrequirements for a flexiblew-pavement structure

Adequate thickness above the subgradeand above each layer together with ade-quate quality of the select material, sub-base, and base courses to prevent detri-mental shear deformation under trafficand, when frost conditions are a factor,to control or reduce the effects of frostheave or permafrost degradation.

A stable, weather-resistant, wear-resis-tant, waterproof, nonslippery pavement.

Design Steps.

1. Estimate the number of passes of each typeof vehicle expected to use the road on a dailybasis.

2. Select the proper road class based uponthe traffic intensity from Table 9-8, page 9-59.

3. Determine the traffic category basedupon the traffic-composition criteria givenpreviously.

4. Determine the design index from Table9-10, page 9-59, or 9-12, page 9-60.

5. Check soils and construction aggregatesusing standard criteria in Tables 5-9, page5-12; 9-14, page 9-63; and 9-18, page 9-70.

6. Use Table 9-16 or 9-17, page 9-66, todetermine compaction depth of thesubgrade.

FM 5-430-00-1/AFPAM 32-8013, Vol 1

7. Determine the total road-structure thick-ness and cover requirements.

a. Enter Figure 9-54 for each layer ofsoil or aggregate with the following informa-tion:

• Design index.

Ž Design CBR values for subgrade, select,and subbase materials.

b. Determine the minimum cover thick-ness, in inches, for each layer of the roadstructure through Figure 9-54 and Table9-19, page 9-71.

8. Determine the required percentcompaction in terms of CE 55 for eachlayer from Table 9-20.

9. Draw the section of the bituminous-pavement road structure. (See below.)

Road Design 9-73

Page 357: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Example (Bituminous-Pavement Design):

Design the most economical bituminouspavement for a 3-year design life capable ofsustaining the following traffic:

Vehicle Average Daily Traffic

5. Check soils and construction aggregate.

a. Where can the CBR 30 material beused? Table 9-14, page 9-63, indicates thismaterial can be used only as a selectmaterial (CBR 20) because the PI exceeds 5.

M998 HMMWV 1,000

M35A2 2 1/2-ton truck 500(dua l ax le )M113A3 (13 tons) 40M1A1 20

The soils data are—

Subgrade:CL material, PI = 12, W = 14 percentNatural CBR = 5Compaction at 90- to 95-percent CE 55,CBR = 7

B o r r o w :CBR 30 at 90- to 95-percent CE 55W = 8 percent, LL = 15, PI = 540 percent passing No. 10 sieve, 12percent passing No. 20 sieve

CBR 35 at 100- to 105-percent CE 55W = 8 PERCENT, LL - 15, PI = 540 percent passing No. 10 sieve, 10percent passing No. 20 sieve

Base: GP material at CBR 50 (meets grada-tion)

Solut ion:

1. Total average daily traffic = 1,560 (given).

2. Select road class E from Table 9-8, page9-59, based upon average daily traffic of1,560.

3. Select traffic category VII based uponthe presence of the M1A1 tank.

4. Select design index 9 from Table 9-12,page 9-60. Notice that the number ofvehicles per day (20) in this table refers tothe M1A1 only, since the M113A3 is con-sidered as a Group 3 vehicle because of itsweight.

b. Where can the CBR 35 material beused? Table 9-14 indicates that thismaterial can be used as a subbase with aCBR 30 design because of the percent pass-ing the No. 10 sieve.

6. The required depth of subgrade compac-tion = 15 inches.

7. Determine the total thickness and coverrequirements.

a. From Figure 9-54, page 9-72, the re-quired cover for each layer is determinedfor design index of 9.

LayerCompactedsubgrade, CBR 7

Required AfterCover Rounding

18" 18"

b. From Table 9-19, page 9-71, the re-quired minimum thickness for the basecourse and surface asphalt is determinedfor design index of 9.

8. From Table 9-20, page 9-73, the re-quired compaction is determined for eachlayer.

9-74 Road Design

Page 358: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

9. Draw the section of the bituminous-pavement road structure.

Shoulders and Similar Areas. These areasare provided only for the purpose of mini-mizing damage to vehicles using them ac-cidentally or in emergencies; therefore, theyare not considered normal, vehicular trafficareas. Normally only shoulders for class Aroads will be paved. Others will be sur-faced with soils selected for their stabilityin wet weather and will be compacted as re-quired. Dust and erosion control will beprovided by means of vegetative cover,anchored mulch, coarse-graded aggregate,or liquid palliative. Shoulders will notblock base-course drainage, particularlywhere frost conditions are a factor. Wherepaving of shoulders is deemed necessary,the shoulders will be designed as a class Froad or street.

Special Considerations for Open StorageAreas. In the design of open storage areas,consideration will be given to any specialrequirements necessary because of the useof a particular area. In repair yards, for in-stance, the final-surface texture will be onethat will promote quick drying and will notcontribute to the easy loss of nuts, bolts,and tiny parts. Mixtures in such areas willcontain approximately 50 percent coarse ag-gregate. Areas subject to an appreciableamount of foot traffic will be designed toavoid the occurrence of free bituminousmaterial on the surface.

SPECIAL DESIGN CONSIDERATIONS

Special design considerations include frostdesign, stabilized-base design, and geotex-tile design.

Frost Design

Normally, frost effects are not considered aspart of the design in TO road construction.However, in the event that extremely severehost conditions exist or that frost design isdirected, an outline of the frost-design pro-cedure is included in Appendix G of thismanual.

Stabilized-Soil Design

The use of stabilized-soil layers (asdescribed in Chapter 5 of this manual andin FM 5-410) within a road structureprovides the opportunity to reduce the over-all thickness required to support a givenload. To design a road containing stabi-lized-soil layers requires the application ofequivalency factors to a layer or layers of aconventionally designed pavement.

To qualify for application of equivalency fac-tors, the stabilized layer must meet ap-propriate strength and durability require-ments. An equivalency factor representsthe number of inches of a conventionalbase or subbase which can be replaced by1 inch of stabilized material. Equivalencyfactors are determined as shown on Table9-21, page 9-76, for bituminous-stabilizedmaterials and from Figures 9-55 and 9-56,page 9-76, for materials stabilized with

Road Design 9-75

Page 359: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table 9-21. Thickness criteria

Equivalency Factors

Material Base Subbase

All-bituminous concrete 1.15 2.30GW, GP, GM, GC 1.00 2.00SW, SP, SM, SC - - 1.50

cement, lime, or a combination of fly ashmixed with cement or lime. The selectionof an equivalency factor from the tabulationis dependent upon the classification of thesoil to be stabilized. The selection of anequivalency factor from Figures 9-55 and 9-56 requires that the unconfined compres-sive strength (as determined according tothe American Society of Testing andMaterials Standatd (ASTM) D1633) be

Figure 9-55. Equivalency factor for subbasesoils stabilized with cement, lime, or cement

and lime mixed with fly ash

known. The equivalency factors from Fig-ure 9-55 are for subbase materials, andthose from Figure 9-56 are for basematerials.

Minimum Thickness. The minimum thick-ness requirement for a stabilized base orsubbase is 4.0 inches. The minimum thick-ness requirements for an asphalt pavementare the same as shown for convention pave-ments in Table 9-19, page 9-71.

Application of Equivalency Factors. The useof equivalency factors requires that a roadbe designed to support the design-load con-ditions. If using a stabilized base or sub-base course, the thickness of a convention-al base or subbase is divided by theequivalency factor for the applicable stabi-lized soil. The following are examples forthe application of the equivalency factors:

Figure 9-56. Equivalency factors for basesoils stabilized with cement, lime, or cement

and lime mixed with fly ash

9-76 Road Design

Page 360: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Example 1:

Assume an aggregate-surfaced road hasbeen designed which requires a total thick-ness of 14 inches above the CBR 6 sub-grade. The minimum thickness of the 80CBR base is 7 inches and the 15 CBRsubbase is 7 inches. It is desired to re-place the base and subbase with a lime-sta-bilized gravelly soil having an unconfinedcompression strength of 950 psi.

Solution:

From Figure 9-55 the equivalency factor forthe subbase is 2.20. From Figure 9-56, theequivalency factor for the base is 1.10.Therefore, the thickness of the stabilizedsubbase is 7.0 inches/2.20 = 3.18 inches,and the thickness of the stabilized base is7.0 inches/1.10 = 6.36 inches. However,since the minimum lift thickness is 4inches, the stabilized subbase must be 4.0inches instead of 3.18 inches. In addition,the stabilized base lift must be rounded upto the nearest full inch, so 6.36 inches isrounded up to 7 inches. Therefore, the fi-nal thickness is 7.0 inches of base + 4.0inches of subbase = 11.0 inches of lime-sta-bilized gravel.

Example 2:

Assume a conventional flexible pavementhas been designed which requires a totalthickness of 16 inches above the subgrade.The minimum thicknesses of the asphaltconcrete and the base are 2 and 4 inches,respectively, and the thickness of the sub-base is 10 inches. It is desired to replacethe base and subbase with a cement-stabi-lized, gravelly soil having an unconfinedcompressive strength of 890 psi.

Solution:

From Figure 9-55, the equivalency factor fora subbase having an unconfined compres-sive strength of 890 is 2.0: and from Figure9-56, the equivalency factor for the base is1.0. Therefore, the thickness of the stabi-lized subbase is 10 inches/2.0 = 5.0 inches,and the thickness of the stabilized base

course is 4 inches/1.0 = 4.0 inches. The fi-nal section would be 2 inches of asphaltconcrete and 9 inches of cement-stabilized,gravelly soil. The base-course thickness of4.0 inches would also have been requireddue to the minimum thickness of the stabi-lized base. The subgrade still has anequivalent cover of 16 inches within thenewly designed 2 inches of asphalt concreteand 9 inches of cement-stabilized, gravellysoil.

Example 3:

Assume a conventional flexible pavementhas been designed which requires 2 inchesof asphalt-concrete surface, 4 inches ofcrushed stone base, and 6 inches of sub-base. It is desired to construct an all-bitu-minous pavement.

Solution:

The equivalency factor from data in Table9-21, for a base course is 1.15 and for asubbase is 2.30. The thickness of asphaltconcrete required to replace the base is 4inches/ 1.15 = 3.5 inches and the thicknessof asphalt concrete required to replace thesubbase is 6 inches/2.30 = 2.6 inches.Therefore, the total thickness of the all-bitu-minous pavement is 2 + 3.5 + 2.6 or 8.1inches, which would be reduced to 8.0inches.

Geotextiles

The term geotextile refers to any permeabletextile used with foundation, soil. rock,earth, or any other geotechnical, engineer-ing-related material as an integral part of ahuman-made project, structure, or system.Geotextiles are commonly referred to as geo-fabrics, engineering fabrics, or just fabrics.They serve four prlmary functions:

Ž Reinforcement.

• Separation.

• Drainage.

• Filtration.

Road Design 9-77

Page 361: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

In many situations, the use of these fabricscan replace soil, saving time, materials, andequipment costs. In TO construction, theprimary concern is with separating and rein-forcing low load-bearing soils to reduce con-struction time.

Geotextile design is an emerging technology.As such, each geotextile manufacturer usesits own design procedure, and a generaldesign procedure using the design criteria

established in previous sections has yet tobe established. Nonetheless, Appendix H ofthis manual outlines a typical geotextiledesign procedure. Note that Appendix Hdescribes only one design procedure, andthe particular geotextile used in construc-tion may require alterations to this proce-dure. Additional details on geotextiles andtheir use are in Chapter 11 of FM 5-410.

9-78 Road Design

Page 362: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX A - METRIC CONVERSIONS

MULTIPLY BY TO OBTAIN BY TO OBTAINMULTIPLY

acre feetacresacresacresacresacresatmospheresatmospheresatmospheresatmospheres

43,56043,5604,0471.562 x 105,645.384,84076.029.9233.9014.70

cubic feetsquare feetsquare meterssquare milessquare varassquare yardscm of mercuryinches of mercuryfeet of waterpounds per sq in

cubic yardscubic yardscubic yards per mincubic yards per min

0.7646202.00.453.367

cubic metersgallonscubic feet per secgallons per sec

decigramsdecilitersdecimetersdegrees (angle)degrees (angle)degrees (angle)dekagramsdekalitersdekametersdramsdrams

0.10.10.1600.017453,6001010101.7720.0625

gramslitersmetersminutesradianssecondsgramslitersmetersgramsounces

barrelsboard feetBTUBTUBTUBTU per minBTU per minBTU per minbushels

31.5144 sq in x 1 in0.2520778.22.928 x 100.023560.0175717.571.244

gallonscubic incheskilogram caloriesfoot poundskilowatt hourshorsepowerkilowattswattscubic feet

9.486 x 10 BTUergs

1

fathomsfeetfeetfeetfeet of waterfeet per minfeet per minfeet per minfeet per secfeet per secfeet per secfeet per secfeet per 100 feetfoot poundsfoot poundsfoot poundsfoot poundsfoot poundsfoot pounds per minfoot pounds per minfoot pounds per minfoot pounds per minfurlongs

6030480.360333043350.50800.016670.011361.0970.592118.290.681811.286 x 101.356 x 105.050 x 103.241 x 103.766 x 101.286 x 103.030 x 103.241 x 102.260 x 1040

feetmetersvarasyardslb per sq incm per sq infeet per secmiles per hourkm per hourknots per hourmeters per minmiles per hourpercent gradeBTUergshorsepower hourskilogram calorieskilowatt hoursBTU per minhorsepowerkg calories per minkilowattsrods

centarescentigramscentiliterscentimeterscentimeterscentimeterscentimeterscentimeter gramscentimeter gramscm of mercurycm of mercurycm of mercurycm of mercurycm of mercurycm per secondcircular milscord feetcordscubic cmcubic cmcubic cmcubic cmcubic feetcubic feetcubic feetcubic feetcubic feetcubic feetcubic feet per mincubic feet per mincubic feet per mincubic feet per mincubic inchescubic inchescubic inchescubic meterscubic meterscubic meterscubic meterscubic yards

square metersgramslitersinchesmetersmilsmillimetersmeter kilogramspound feetatmospheresfeet of waterkg of sq meterspounds per sq ftpounds per sq inmeters per mmsquare milscubic feetcubic feetcubic inchescubic metersgallonsliterscubic cmcubic inchescubic meterscubic yardsgallonsliterscubic cm per secgallons per secliters per seclb of water per mincubic cmcubic feetquarts (liquid)cubic cmcubic feetcubic yardsgallonscubic feet

0.010.010.39370.01393.7101 x 107.233 x 100.013160.4461136.027.850.19340.60.78544 ft x 4 ft x 1 ft8 ft x 4 ft x 4 ft6.102 x 101 x 102.642 x 10

2.832 x 101,7280.028320.037047.48128.32472.00.12470.472062.416.395.787 x 100.017321 x 1035.311.308264.227

10gallonsgallonsgallonsgallonsgallonsgallons per mingillsgrains (troy)grains (troy)grains (troy)gramsgramsgramsgramsgramsgramsgramsgram calories

3,7850.13372313.785 x 104,951 x 102.228 x 100.1183

cubic cmcubic feetcubic inchescubic meterscubic yardscubic feet per seclitersgrains (av)gramspenny weights (troy)dynesgrains (troy)kilogramsmilligramsouncesounces (troy)poundsBTU

1

15.4310

0.064800.04167980.7

100.035270.032152.205 x 103.968 x 10

Metric Conversions A-1

Page 363: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

METRIC CONVERSIONS (continued)

TO OBTAINMULTIPLY BY TO OBTAIN MULTIPLY BY

102.344 x 10

5.600 x 1062.43

kilometers per hourkilowattskilowattskilowattskilowatt hourskilowatt hoursknotsknots

gram centimetersgram centimetersgrams per cmgrams per cu cm

kilogram calorieskilogram meterspounds per inchpounds per cu ft

0.539656.924.425 x 101.3413,4152.655 x 101.8531.152

knots per hourBTU per minft pounds per minhorsepowerBTUfoot poundskilometers per hourmiles per hour

hectareshectareshectogramshectolitershectometershectowattshorsepwerhorsepowerhorsepowerhorsepowerhorsepowerhorsepowerhorsepower

2.4711.076 X 1010010010010042.4433,0005501.01410.700.7457745.7

acressquare feetgramslitersmeterswattsBTU per minft pounds per minft pounds per sechorsepower (metric)kg calories per minkilowattswatts

links (engineer’s)links (surveyor’s)litersliterslitersliters per minuteliters per minute

127.9210

0.26421.0575.885 x 104.403 x 10

inchesinchescubic centimetersgallonsquarts (liquid)cubic feet per secgallons per sec

metersmetersmetersmetersmetersmetersmicronsmilesmilesmilesmiles per hourmiles per hourmiles per hourmilliersmilligramsmillilitersmillimetersmillimetersmillimetersmilsmilsminutes (angle)minutes (angle)myriagramsmyriametersmyriawatts

1003.280839.3710

101.093610

5,2801.60931,7601.4671.60930.8684

0.10.0393739.370.002540102.909 x 1060101010

centimetersfeetincheskilometersmillimetersyardsmetersfeetkilometersyardsfeet per secondkilometers per hourknots per hourkilogramsgramsliterscentimetersinchesmilscentimetersinchesradiansseconds (angle)kilogramskilometerskilowatts

inchesinchesinchesinchesinches of mercuryinches of mercuryinches of waterinches of waterinches of waterinches of waterinches of water

2.540100.030.033421.13370.730.0024580.07355

centimetersmilsvarasatmospheresfeet of waterpounds per sq ftatmospheresinches of mercuryounces per sq inpounds per sq ftpounds per sq in

0.57815.2040.03613

9.486 x 10100.7376

joulesjoulesjoulesjoulesjoulesjoules

BTUergsfoot poundskilogram calorieskilogram meterswatt hours

2.390 x 100.10202.778 x 10

980,6651 x 102.20461.102 x 103.9683,0881.588 x 101.162 x 100.069729.302 x 109.807 x 101 x 100.062439.678 x 103.281 x 102.886 x 100.20481.422 x 1010

103,281100.6214

kilogramskilogramskilogramskilogramskilogram calorieskilogram calorieskilogram calorieskilogram calorieskilogram calories per minkilogram meterskilogram meterskilograms per cubic meterkilograms per cubic meterkilograms per sq meterkilograms per sq meterkilograms per sq meterkilograms per sq meterkilograms per sq meterkiloliterskilometerskilometerskilometerskilometers

dynesgramspoundstons (short)BTUfoot poundshorsepower hourskilowatt hourskilowattsBTUergsgrams per cu cmpounds per cu ftatmospheresfeet of waterinches of mercurypounds per sq ftpounds per sq inliterscentimetersfeetmetersmiles

nautical milesnautical miles

1.1522.027

milesyards

ouncesouncesouncesouncesounces (fluid)ounces (troy)ounces (troy)ounces (troy)ounces (troy)

8437.528.350.06251.80548031.10200.08333

dramsgrainsgramspoundscubic inchesgrams (troy)gramspennyweights (troy)pounds (troy)

perches (masonry)pints (dry)pints (liquid)pounds

24.7533.6028.87444,823

cubic feetcubic inchescubic inchesdynes

A-2 Metric Conversions

Page 364: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

METRIC CONVERSIONS (continued)

MULTIPLY BY TO OBTAIN MULTIPLY BY TO OBTAIN

1.19664027.88 x 102.5903,613,040.453.098 x 102.066 x 1090.83613.228 x 101.16640.159210

poundspoundspoundspound feetpound feetpounds feetpounds of waterpounds of waterpounds of waterpounds per cubic footpounds per cubic inchpounds per footpounds per square footpounds per square footpounds per square inchpounds per square inchpounds per square inchpounds per square inchpounds per square inch

453.61632.171.356 x 10

gramsouncespoundalscentimeter dynescentimeter gramsmeter kilogramscubic feetcubic inchesgallonskg per cubic metergrams per cu cmkilograms per meterfeet of waterkilograms per sq meteratmospheresfeet of waterinches of mercurykg per square meterpounds per sq ft

square meterssquare milessquare milessquare milessquare milessquare milessquare yardssquare yardssquare yardssquare yardssquare yardssteradianssteres

square yardsacressquare feetsquare kilometerssquare varassquare yardsacressquare feetsquare meterssquare milessquare varashemispheresliters

13,8250.13830.0160227.680.119816.0227.681.4880.016024.8820.068042.3072.038703.1144

905,4001.57167.2057.75

57.303,4380.063750036046,28360.10470.016671.745 x 100.016672.778 x 103606.28316.5

temperture (deg C) + 273temperature (deg C) + 17.8temperature (deg F) + 460temperature (deg F) - 32tons (long)tons (long)tons (metric)tons (metric)term (short)tons (short)tons (short) per sq fttons (short) per sq fttons (short) per sq fttons (short) per sq in

1

1 0

absolute temp (deg Ctemperature (deg F)absolute temp (deg F)temperature (deg C)kilogramspoundskilogramspoundskilogramspoundskg per sq meterpounds per sq inkg per sq meterpounds per sq in

1.810.5551,0162,240

2,205907.22,0009,76513.891.406 x 102,000

quadrants (angle)quadrants (angle)quadrants (angle)quarts (dry)quarts (liquid)

degreesminutesradianscubic inchescubic inches

radiansradiansradiansreamsrevolutionsrevolutionsrevolutionsrevolutions per minuterevolutions per minuterevolutions per minuterevolutions per min per minrevolutions per min per minrevolutions per min per minrevolutions per secondrevolutions per secondrods

degreesminutesquadrantssheetsdegreesquadrantsradiansdegrees per secondradians per secrev per secondradians per sec per secrev per min per secrev per sec per secdegrees per secondradians per secondfeet

2.7777 feetvaras

wattswattswattswattswattswatt hoursweeks

0.056921044.261.341 x 10103.415168

BTU per minergs per secondfoot pounds per minhorsepowerkilowattsBTUhours

91.443360.9144

centimetersfeetinchesmeters

yardsyardsyardsyards

4.848 x 100.15501002.296 x 100.092903.587 x 100.12960.1116.4526,944 x 10247.110.76 x 101 x 100.38611.196 x 102.47 x 1010.7643.861 x 10

seconds (angle)square centimeterssquare centimeterssquare feetsquare feelsquare feetsquare feetsquare feetsquare inchessquare inchessquare kilometerssquare kilometerssquare kilometerssquare kilometerssquare kilometerssquare meterssquare meterssquare meters

radianssquare inchessquare millimetersacressquare meterssquare milessquare varassquare yardssquare centimeterssquare feetacressquare feetsquare meterssquare milessquare yardsacressquare feetsquare miles

Metric Conversions A-3

Page 365: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

METRIC CONVERSIONS (continued)

A-4 Metric Conversions

One unit (below) i equals • mm cm m km I

Millimeters (mm) 1

0':1 0.001 0.000001

Centimeters (cm) 10 1 0.01 0.00001 Meters (m) 1,000 100 1 0.001 Kllometers (km) 1,000,000 100,000 1000 1

One unit (below) equals • g kg Metric ton --Grams (a) 1 0.001 0.000001 KIlograms (kg) 1000 1 0.001 Metric tons 1000000 1000 1

Units of centimeters

Fractions of an Inch

Inch 1/16 1/8 3/16 1/4 5/16 3/8 7/16 1/2 Cm 0.16 0.32 0.48 0.64 0.79 0.95 1.11 1.27

Inch 9/16 5/8 11/16 3/4 13/16 7/8 15/16 1 Cm 1.43 1.59 1.75 i 1.91 2.06 2.22 2.38 2.54

Length

Inches --------------------------. cm

cm ----------------------. Inches

~F~e~et~--------------------· m m ---------------0. Feet

Yards m

L!m~ __ ===~· Yards Miles -- km

1 I j

j km .... Miles

Otv i 1 2

.3 4 5 6 7 8 9 10

120

130 140 ;50 160 .70 80

.90 100

0.62 1.61 1.09 0.91 3.28 0.30 1.24 3.22 2.19 1.83 6.56 0.61 1.86 4.83 3.28 2.74 9.84 0.91

i 2.49 6.44 4.37 3.66 13.12 1.22 1 3.11 8.05 5.47 4.57 16.40 1.52

3.73 9.66 6.56 5.49 19.681

, 1.83 i 4.35 11.27 7.66 6.40 2297. 2.13 ! 4.97 12.87 8.75 7.32 2625 i 2.44 : 5,59 14.48 9.84 8.23 29.531 2.74

6.21 16.09 10.94 9.14 32.81 3.05 ! 1243 32. 19

i1 2187 18.29 65.62 6.10

18.64 48.28 32.8127.43 98.42 9.14 2485 64.37 4374 36.58 131.2~ 12.19 3107 80.47 54.68 45.72 164.0~ 15.24 3728 96.56 65.62 54.86 196.85 18.29 4350 112.6 76.55 64.00 229.66 21.34 4971 128 7 87.49 73.15 262.47 24.38 55.92 144.841 98.42 82.30 295.28 27.43 62.14 160.941109.36 91.44328.08 30.48

!

0.39 2.54 0.79 5.08 1.18 7.62 1.57 10.16 1.97 12.70 2.36 15.24 2.76 17.78 3.15 20.32 3.54 22.86 3.93 25.40 7.87 50.80

11.81 76.20 15.75 1 01.~~ 19.68 127.V\ 23.62 15~.~~ 27.56 177.0\ 31.50 203.~~ 35.43 228.6\ 39.37 254.0(

Weight

Ounces • g

la • Ounces Pounds • kg ka • Pounds Short • Metric

j ton ton Metric -+ Short

1 ton ton IOtv ~

1 1.10 0.91 2.20 0.45 0.04 28.4 2 2.20 1.81 4.41 0.91 0.07 56.7 3 3.31 2.72 6.61 1.36 0.11 85.0 4 4.41 3.63 8.82 1.81 0.14 113.4 5 5.51 4.54 11.02 2.67 0.18 141.8 6 6.61 5.44 13.23 2.72 0.21 170.1 7 7.72 6.35 15.43 3.18 0.25 198.4 8 8.82 7.26 17.64 3.63 0.28 226.8 9 9.92 8.16 19.84 4.08 0.32 255.2 10 11.02 9.07 22.05 4.54 0.35 283.5 20 22.05 18.14 44.09 9.07 0.71 567.0 30 33.07 27.22 66.14 13.61 1.06 850.5 40 44.09 36.29 88.18 18.14 1.41 1,134.0 50 55.12 45.36 110.23 22.68 1.76 1,417.5 60 66.14 54.43 132.28 27.22 2.12 1,701.0 70 77.16 63.50 154.32 31.75 2.47 1,984.5 80 88.18 72.57 176.37 36.29 2.82 2,268.0 90 99.21 81.65 198.42 40.82 3.17 2,551.5 100 110.20 90.72 220.46 45.36 3.53 2835.0

Volume

Cu . cu ft cu yd meters cu yd • cu ft cu

j meters

cu ft _ cu yd cu

1 1 meters atv ! ~

1 0.037 0.028 27.0 0.76 35.3 1.31 2 0.074 0.057 54.0 1.53 70.6 2.62 3 0.111 0.085 81.0 2.29 105.9 3.92 4 0.148 0.113 108.0 3.06 141.3 5.23 5 0.185 0.142 135.0 3.82 176.6 6.54 6 0.212 0.170 162.0 4.59 211.9 7.85 7 0.259 0.198 189.0 5.35 247.2 9.16

'18 0.296 0.227 216.0 6.12 282.5 10.46

19 0.333 0.255 243.0 6.88 317.8 11.77 1110 0.370 0.283 270.0 7.65 353.1 13.07 20 0.741 0.566 540.0 15.29 706.3 26.16 30 1.111 0.850 810.0 22.94 1,059.4 39.24 40 1.481 1.133 1,080.0 30.58 1,412.6 52.32 50 1.852 1.416 1,350.0 38.23 1,765.7 65.40 60 2.222 1.700 1,620.0 45.87 2,118.9 78.48 70 2.592 1.982 1,890.0 53.52 2,472.0 91.56 80 2.962 2.265 2,160.0 61.16 2,825.2 104.63 90 3.333 2.548 2,430.0 68.81 3,178.3 117.71 100 3.703 2.832 2,700.0 76.46 3531.4 130.76

Page 366: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX B - GEOMETRIC FORMULAS

(6) Regular polygons. The area of any regular polygon (all sides equal, all angles equal) is equal to the product ofthe square of the lengths of one side and the factors. Example problem: Area of a regular octagon having 6-inchsides is 6 x 6 x 4.828, or 173.81 square inches. See factors in table.

Geometric formulas B-1

Page 367: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

GEOMETRIC FORMULAS (continued)

B-2 Geometric formulas

a

Given A B

a,b tanA.! b tan B.-b a

a,e slnA.! cosB.! c c

A,a 90· A

A.b 90· A

A,e 90· A

Oblique triangle

Given To find

A B

a,b,c A~ B~ COS_. AA COS2- uC l I:IV

a,A,e I I

a,b,A i B beinA I sn _--

a a,b,c tanA. asln C I

I b-acoo C I

i.rf-tf SinA-~

tf.rf-El

rf-rf+tf

Right triangle

To find

C a

90

90

90

90 b tan A

90 c sin A

s b c Sin A - Sin B .. Sin C

S s+b+c os 2

C

col}-~ ~ all

180· (MB)

c b CosA.-c a

TsnA -b

b

asin B sin A

b e area

VEl+tl ab 2

Vrf-El !vcll 2

a cot A a El cot A sin A 2 _b_ tl tan A coo A 2

c cos A rf sin 2A 2

if- b2 + ~ - 2bcCosA

if .. if + ~ - 2ac Cos B

cl .. if + if - 2ab Cos C

c area

.; s(s-a)(s-b)(s-c)

asin C ; sin Bsin C sin A 2sinA

beinC sinB

v; + tl- 2ab cos C absin C 2

Page 368: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1GEOMETRIC FORMULAS (continued)

Geometric formulas B-3

Degree Degree of Angle Sine COMcant Tangent Cotangent Secant Cosine of Angle

0 0.000 0.000 1.000 1.000 90

1 0.017 57.30 0.017 57.29 1.000 1.000 89

2 0.035 28.65 0.035 2S.64 1.001 0.999 88

3 0.052 19.11 0.052 19.08 1.001 0.999 87

4 0.070 14.34 0.070 14.30 1.002 0.998 86

5 0.087 11.47 0.087 11.43 1.004 0.996 85

6 0.105 9.567 0.105 9.514 1.006 0.995 84

7 0.122 8.206 0.123 8.144 1.00S 0.993 83

8 0.139 7.185 0.141 7.115 1.010 I 0.990 82

9 0.156 6.392 0.158 6.314 1.012 0.988 81

10 0.174 5.759 0.176 5.671 , .015 0.985 80

11 0.191 5.241 0.194 5.145 1.019 0982 79

12 0.208 4.810 0.213 4.705 1.022 0.978 78 I

13 0.225 4.445 0.231 4.331 1.026 0.974 77

14 0.242 4.134 0.249 4.011 1.031 0.970 76

15 0.259 3.864 0.268 3.732 1.035 0.966 75

16 0.276 3.628 0.287 3487 1.040 0.961 74

17 0.292 3.420 0.306 3.271 1.046 0.956 I 73

18 0.309 3.236 0.325 3.078 1.051 0.951 72

19 0.326 3.072 0.344 2.904 1.058 0.946 71

20 0.342 2.924 0.364 2747 1.064 0.940 70

21 0.358 2.790 0.384 2.605 1.071 0.934 69

22 0.375 2.669 0.404 2.475 1.079 0.927 68

23 0.391 2.559 0.424 2.356 1.086 0.921 67

24 0.407 2.459 0.445 2.246 1.095 0.914 66

25 0.423 2.366 I

0466 I 2.145 1.103 0.906 65 ;

26 I 0438 2.281 0.488 2.050 1.113 0.899 64

27 0454 2.203 0.510 1.963 1.122 0.901 63

28 0.469 2.130 0.532 1881 1.133 0.883 62

29 0.485 2.063 0.554 1804 1.143 0.875 61

30 0.500 2.000 0.577 1.732 1.155 0.866 60

Degree D~~;' 11 of Angle Cosine Secant Cotangent Tangent COMC8nt Sine of A

TRIGONOMETRIC FUNCTIONS

Page 369: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

GEOMETRIC FORMULAS (continued)

B-4 Geometric formulas

Degree ! I Cotangent I Degree

of Angle Sine Cosecant Tangent Secant Cosine of Angle

31 i

0.515 1 942 0.601 1.664 , .167 I 0.857 59 ! I I

32 0.530 I 1.887 0625 1.600 1.179 0.848 58

33 0.545 1.836 0649 1.540 1.192 0.839 57

: 34 0.559 1.788 0.675 1.483 1.206 0.829 56

35 0.574 1.743 0.700 1.428 1.221 0.829 55

36 0.588 1.701 0.727 1.376 1.236 0.809 54

37 0.602 1.662 0.754 1.327 1.252 0.799 53

38 0.616 1.624 0.781 1.280 1.269 0.788 52

39 0.629 1.589 0.810 I 1.235 1.287 0.777 51

40 0.643 1.556 0.839 1.192 1.305 0.766 50

41 0.656 1.542 0869 1.150 1.325 0.755 49

42 0.669 1.494 0900 1.111 1.346 0.743 48

43 0.682 1.466 0.933 1.072 1.367 0.731 47

i 44 i 0.695 1.440 0.966 1.036 1.390 0.719 46

45 0707 1.414 1.000 1.100 1.414 0.707 45

Degree I ! Degree !

ot Angle Cosine Secant Cotangent ! Tangent Cosecant Sine of Angle

TRIGONOMETRIC FUNCTIONS

Page 370: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX C

HYDROLOGIC AND HYDRAULIC TABLES AND CURVES

PRECIPITATION TABLES

Table C-1, page C-2, provides local data foruse in designing drainage systems as dis-cussed in Chapter 6.

HYDROLOGIC SUPPLY CURVES FOROVERLAND FLOW

Figures C-1 through C-7, pages C-7through C-13, represent the peak runoffrates from individual storm events ofvarious durations, all of which have thesame average frequency of occurrence.

These curves are computed from Horton’sequation given in Chapter 6, using a retar-dance coefficient in n = 0.04 and hydraulicgradient S = 1 percent.

HYDRAULIC CHARACTERISTICS OFSELECTED DRAINAGE CHANNELS

Tables C-2 through C-10, pages C-14through C-22, present commonly used ditchsections, with cross-section areas andhydraulic radius, to facilitate selection ofditch size and shape.

Hydrologic and Hydraulic Tables and Curves C-1

Page 371: Army Construction Manual FM5 430 Vol1 Entire

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

C-2 H

ydro

log

ic and

Hyd

raulic T

ables an

d C

urves

Table C-1. Mean monthly, maximum monthly, and maximum 24-hour precipitation for selected stations throughout the world

-- -------~ -~ --

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Oec Annual f-------.

ALASKA Barrow

Mean O~ 15 0~2O 0.13 0.12 0.14 026 0.89 0.73 0.49 0.56 0.20 0.36 4.23 24·hour maxImum 0.70 0.23 0.28 020 0.30 0.36 0.84 0.43 1.00 0.41 0.26 026 1.00 Mean snowfall 2.60 2.70 2.00 2.70 1.80 0.40 1.00 070 0.30 7.90 4.30 3.90 33.00

Ketchlkan: Mean 13.62 11.16 1213 10.88 8.39 6.60 807 11.61 12.22 20.18 19.96 15.86 150.68 24 ·hour maxImum 5.87 5.36 5.70 4.44 5.87 425 334 807 606 7.04 7.14 5.33 807 Mean snowfall 10.00 7.10 4.70 0.60 0.40 0 0 0 0 0.20 0.90 7.40 32.30

Teller (65" 16' N. 166° 20 W)

Mean 1.13 0.53 0.34 0.69 0.51 0.62 188 148 1.74 0.71 0.79 0.52 10.94 24·hour maximum 2.10 0.58 0.35 0.70 0.80 0.50 1.00 1.10 2.20 0.50 0.72 0.55 2.20 Mean snowfall 12.00 710 6.70 6.50 2.40 0 0 0 0.20 2.20 7.50 8.20 52.90

Dutch Harbor Mean 6.32 6.12 4.92 4.19 4.33 2.82 189 2.45 5.45 7.39 5.81 6.92 58 61 24 ~hour maxImum 3.73 3.75 2.47 3.46 2.74 300 1.60 208 2.53 3.08 3.22 2.31 3.75 Mean snowfall 15.60 1970 10.50 6.70 0.10 T 0 0 T 0.50 5.80 10.80 69.70

I----~ -

CANADA Edmonton. Alberta:

Mean 0.76 0.67 067 0.80 1.86 3.26 3.57 2.47 1.40 0.74 0.73 0.75 17.67 24~hour maxImum 0.70 0.80 0.60 0.83 2.80 2.20 2.16 2.68 1.37 1.03 0.80 0.70 2.80

St Johns. Newfoundland: Mean 5.39 5.08 4.53 4.25 3.54 3.54 374 3.58 3.78 5.39 6.06 4.92 53.80 Maxlmum 11.38 12.84 8.84 8.79 7.11 7.83 7.72 9.76 11.42 13.11 12.27 14.05 69.05 24·hour maximum 2.44 3.31 1.81 2.99 3.62 2.01 2.28 1.54 2.36 2.80 3.35 3.15 3.62

CENTRAL AND SOUTH AMERICA

Puerto Barrios. Guatemala (15" 35' N. 88C 35 W)

Mean 11.46 886 3.82 3.70 7.99 10.63 16~50 18.62 9.06 7.20 15.47 11.46 124.77 Maxlmum 25.94 26.97 12.43 14.65 18.15 18.15 25.08 29.58 18.54 23.95 32.69 19.93 158.10 24·hour maximum 6.75 6.55 5.30 4.69 3.61 4.25 494 5.20 6.59 5.55 7.80 11.18 11.18

Fortaleza. Brazil (3° 42' S. 38' 30 W)

Mean 3.35 6.93 11.77 13.46 9.61 4.72 213 1.10 0.67 0.51 0.55 1.54 56.34 MaxImum 18.27 25.12 26.61 32.40 26.14 15.90 10.43 6.61 2.99 3.58 3.78 8.98 109.41 24 ·hour maxImum 7.40 701 9.61 9.45 5.75 350 2.80 276 1.57 2.17 1.81 5.20 9.61

'-Years

Recorded

26 18·19 21·23

30·32 2930

-----

8·13 6·10 5·9

19·23 19·23 1923

15

52 57 73

7 19 13

:::?

72 72 59

Page 372: Army Construction Manual FM5 430 Vol1 Entire

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

Hyd

rolo

gic

and

H

ydrau

lic T

ables

and

C

urves

C-3

Table C-1. Mean monthly, maximum monthly, and maximum 24-hour precipitation for selected stations throughout the world (in inches) (continued)

- .. -,_ .. - .. Years

Jan Feb Mar Apr May Jun Jul Aug Sap Oct Nov Dec Annual Recorded

EUROPE AND ICELAND london. England

Mean 1.88 1.57 1.56 1.60 1.75 2.03 2.24 2.23 1.95 2.61 2.28 2.29 23.99 62 Maximum 4.88 4.13 3.94 3.98 409 7.20 4.88 6.SO 5.71 5.91 3.98 6.38 38.19 68

24·hour maximum 1.60 1.10 090 1.20 180 2.40 2.30 HID 1.60 140 1.30 1.SO 2.40 65

Berlin, Germany'

Mean 1.69 1.38 1.57 1.54 189 2.36 3.07 2.32 1.69 1.77 1.69 1.89 22.86 80

MaXImum 3.94 4.88 5.28 4.17 5.71 5.59 9.06 657 4.25 5.28 4.65 4.49 31.61 80

24·hour maximum 0.97 0.85 O.SO 155 1.27 1.73 2.59 2.66 1.77 099 1.28 0.62 2.66 15

Prague. Czechoslavakia'

Mean 0.87 0.83 1.10 1.54 2.36 2.76 2.56 2.24 1.65 1.22 1.18 094 19.25 70

MaJOmum 2.36 2.01 2.40 4.33 6SO 618 567 4.80 5.35 4.17 3.70 3.27 2752 70

24·hour maximum 0.53 0.56 0.73 1.30 1.28 1.98 2.17 1.57 1.60 1.22 1.13 0.80 2.17 15

Budapest. Hungary:

Mean 1.46 1.22 1.77 2.28 2.91 2.91 2.09 1.97 201 2.60 2.09 1.89 25.20 35

MaJOmum 394 3.11 4.33 3.82 5.51 8.31 7.05 5.04 4.88 5.16 5.79 4.29 37.05 31

24 -hour maximum 1.34 1.38 1.26 1.69 1.69 2.20 252 331 2.44 1.61 1.57 1.SO 3.31 30

Helslnki, Finland:

Mean 1.77 1.46 1.38 1.42 1.77 181 2.24 2.91 2.52 2.60 2.48 2.01 2437 71

Maximum 4.61 3.62 4.45 3.94 4.16 4.61 7.56 6SO 591 5.79 5.94 4.76 33.90 87

24·hour maximum 0.73 0.83 0.96 1.46 1.48 1.87 1.82 164 2.12 212 1.13 1.56 2.12 36

Trondheim. Norway

Mean 3.43 2.87 2.24 181 1.SO 1.73 2.24 2.95 3.27 3.39 3.11 2.56 3110 SO

Maximum 11.45 8.80 8.31 6.37 4.07 4.54 4.64 640 6.62 8.78 9.95 8.64 56.67 44

24·hour maximum 1.68 1.91 1.96 0.99 130 1.00 1.66 2.23 1.42 2.24 1.85 2.58 258 31

Corfu. Gree<:e Mean 7.72 6.11 4.18 3.70 245 1.05 0.28 0.56 2.62 502 7.05 9.54 SO.48 38 Maximum 17.13 11.26 922 13.35 4.09 4.75 1.14 4.29 6.65 21.SO 15.39 13.95 66.75 26

24·hoUf maxll1lum 5.47 3.23 2.17 2.83 1.85 1.61 102 3.35 3.23 5.91 5.08 3.90 5.91 26

Stockholm. Sweden

Mean 0.98 0.91 1.08 107 1.44 1.63 2.37 259 175 1.98 1.53 1,31 18.64 51

Maximum 3.35 3.90 3.03 3.54 3.31 5.08 7.28 484 5.67 6.85 3.15 3.07 28.27 51

24·hour maximum 0.53 0.84 0.81 1.46 162 1.26 262 269 1.66 1.29 159 1.14 2.69 38

ReykjaVIk. Iceland

Mean 3.86 3.31 2.72 2.44 1.89 1.93 1.89 201 3.54 3.43 3.74 3.SO 34.20 SO Maximum 6.21 9.54 7.21 5.90 2.95 3.64 4.63 649 5.99 7.12 6.87 7.35 SO 83 19

24·hoUf maximum 1.30 1.36 2.23 0.87 0.78 1.16 1.07 1.18 1.07 1.30 1.73 2.'7 2.23 19

Page 373: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/A

FPA

M 32-8013, V

ol 1

C-4 H

ydro

log

ic and

Hyd

raulic T

ables an

d C

urves

!

Table C-1. Mean monthly. maximum monthly. and maximum 24-hour precipitation for selected stations throughout the world (continued)

Years

Feb Mar Apr May Jun Jul Aug Sep Ocl Nov Oec Annual Recorded

ASIA Sapporo, HokkaKlo (Japan):

Mean 3.50 2.50 2.40 2.20 270 280 3.30 3.70 5.00 4.60 4.40 400 4009 30 Maximum 8.20 4.60 5.50 500 4.90 730 820 1120 1100 1180 8.30 7.80 53.50 22 24·hour maximum 2.80 190 180 420 2.80 470 490 430 4.60 4.00 1.70 290 490 44

Urakawa, Hokkaido (Japan)

Mean 1.60 0.90 2.10 3.10 380 3.40 510 630 460 440 4.20 2.10 41.80 6 Maximum 2.60 160 2.60 550 5.30 140 1580 9.10 6.10 5.70 7.00 2.70 55.20 6 24.nour maximum 1.00 0.60 1.10 1.40 1.80 2.00 580 3.50 2.40 2.60 2.00 1.10 5.80 6

Kobe, Honshu (Japan) Mean 1.90 2.20 3.60 ~.OO 490 8.20 6.00 4.60 7.70 4.80 2.60 1.80 5330 Maximum 3.40 5.90 6.50 856 980 1480 11 80 9.60 6.60 10.80 6.00 3.90 65.60 24·hour maximum 160 2.30 2.50 2.50 340 5.90 4.60 4.60 7.80 3.90 2.70 1.80 7.80

Hamada, Honshu (Japan) Mean 4.50 3.90 4.60 500 4.90 170 750 4.60 8.20 5.10 4.20 4.60 64.80 .*~ . Maximum 6.90 7.30 7.10 8.60 9.60 2230 18.60 12.00 20.00 10.90 750 9.10 92.50 24·hour maximum 2.00 2.60 2.00 2SO 390 430 800 8.90 5.40 3.30 1.90 2.20 8.90 ... ,

Gensan. Korea Mean 1.20 1.47 1.78 2.76 341 474 1046 1209 7.02 3.33 2.SO 1.39 52.15 21 Maximum 326 5.11 5.33 708 590 12.26 16.33 21.33 16.43 17.94 5.65 7.07 79.89 21 24-hour maJ<lmum 2.90 2.90 3.80 4.60 500 480 6.90 7.70 9.60 8.80 3.40 330 9.60 29

Yunnan, China (25' 01' N. 1020 54' El:

Mean 0.35 0.55 0.67 0.75 421 622 874 858 4.96 2.91 181 043 40.18 32 Maximum 2.17 2.32 2.91 280 1268 2256 18.11 15.67 11.61 7.56 6.85 1.81 61.02 32 24·hour ma)omum 1.22 1.06 1.26 1.14 260 961 429 4.49 4.53 280 2.87 1.30 9.61 32

Hongkong. China Mean 1.27 175 2.93 5.44 1150 1552 1501 14.22 10.11 4.55 1.70 115 85.16 53 Maximum 843 7.94 11.48 1716 48.84 34.38 30.08 34.31 30.60 23.98 882 4.90 11972 47 24-hour maximum 3.92 2.18 3.78 6.22 2050 12.63 21.02 11.14 7.96 11.50 5.88 3.58 21.02 53

Tientsin. China Mean 0.16 0.09 0.37 0.63 1.13 2.46 7.00 5.SO 1.76 0.59 0.39 0.15 20.23 44 Maximum 0.91 0.62 1.73 1.89 2.28 696 1446 11,39 5.26 1.64 1.89 046 28.70 20 24·hour maximum 0.64 O.SO 1.37 122 1.90 309 477 4.89 2.31 1.26 1,13 028 4.89 22

Urga, Mongolia (4r 55' N, 106< SO' El

Mean 0.04 0.03 0.06 0.22 0,34 0.96 2.91 1.91 0.76 0.20 0.15 010 768 15 Maximum 0.16 0.13 0.37 079 135 340 6.47 4.33 2.09 0.66 1.38 089 1369 15 24·hour maximum 0,09 0.06 0.17 031 067 107 2,86 2,38 1.61 0.33 0.69 069 2.86 10

Page 374: Army Construction Manual FM5 430 Vol1 Entire

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

Hydrologic and H

ydraulic Tables and C

urves C-5

ASIA (continued) Singapore. China:

Mean Maximum 24-hour·maximum

Dairen. Manchuria: Mean Maximum 24-hour maximum

Manchouli: Mean Maximum 24-hour maximum

Aden. Arabia: Mean Maximum 24-hour maximum

Cherrapun ji. India: Mean Maximum 24-hour maximum

Karachi. Pakistan: Mean Maximum 24-hour maximum

T richinopoly. India Mean Maximum 24-hour maximum

AFRICA Casablanca. Morocco

Mean Maximum 24·hour maximum

Huambo. Angola: Mean Maximum 24·hour mW(lmum

Cairo. Egypt: Mean Maximum 24-hour maximum

Table C-1. Mean monthly, maximum monthly. and maximum 24-hour precipitation for selected stations throughout the world (continued)

Jan Feb Mar Apr May Jun Jul Aug Sep Qct Nov Oec

9.88 6.62 7.40 7.64 6.65 6.85 6.77 7.95 6-17 8.07 9.92 10.55 14.13 24.98 19.74 14.92 10.79 14.08 13.56 1081 17.26 12.06 15.15 16.91 6.93 4.30 4.88 2.97 4.92 3.46 3.91 417 5.20 6.02 4.02 4.35

OSO 0.30 0.70 1.00 1.70 1.80 6.40 5.10 4.00 1.10 1.00 O.SO 190 1.10 3.SO 2.60 4.30 3.30 16.00 15.30 1270 2.30 270 0.90 1.40 1.10 1.80 1.90 2.20 2.70 7.SO 6.40 4.10 1.50 1.80 0.60

010 0.10 0.10 0.10 0.60 1.70 2.90 2.40 130 0.30 0.20 0.10 0.40 0.20 O.SO 0.70 2.30 4.30 6.10 5.60 3.30 1.50 0.60 0.40 0.10 0.10 0.30 0.40 1.30 1.90 1.10 2.30 1.40 1.00 O.SO 0.20

0.30 0.20 0.40 0.20 0.10 0.10 0.03 0.10 0.10 0.10 0.10 0.10 3.31 1.58 6.57 3.87 1.40 1.34 0.62 1.97 1.36 2.23 1.28 1.55 2.20 1.40 3.00 2.60 1.40 1.00 0.60 140 1.30 2.20 0.80 1.10

0.45 2.72 9.38 28.19 46.28 95.92 98.51 7984 37.98 21.26 3.23 0.31 8.07 5.39 19.65 52.05 128.27 169.92 147.44 97.83 99.41 51.73 14.02 9.61 1.12 1.32 2.80 10.20 16.90 36.40 21.08 22.61 24.66 21.62 3.23 0.15

0.48 0.36 0.21 0.11 0.06 0.57 3.10 1.69 0.65 0.02 0.13 0.20 3.38 2.94 3.83 4.75 1.85 10.59 18.63 14.15 15.35 1.56 4.66 2.58 0.39 1.15 0.21 0.70 0.15 2.04 7.86 5.41 8.11 0.52 0.86 1.83

0.96 0.48 0.40 1.79 3.18 1.48 1.47 388 4.65 7.08 5.54 2.77 8.02 3.06 1.26 7.88 10.76 3.66 3.30 9.61 10.80 27.43 13.68 12.98 4.32 1.86 0.67 3.74 7.21 1.87 2.12 3.81 3.26 12.56 6.21 5.34

203 1.98 2.37 124 0.78 0.22 0 001 042 1.21 2.76 2.59 4.71 4.92 7.02 3.96 2.62 0.89 0.01 0.16 2.19 4.68 7.26 7.69 1.14 1.13 0.76 1.24 3.01 0.26 0.11 0.04 1.80 1.27 2.54 2.58

8.71 8.87 8.42 606 1.OB 0 0 009 0.82 5.14 8.94 9.48 17.40 19.87 12.02 10.93 6.93 0 0 036 2.48 10.53 12.38 14.93 131 104 1.SO 1.20 0.28 ---- 0.49 3.04 2.43 2.63

0.24 0.16 0.20 008 0.08 0.04 0 0 0 0.08 O.OB 0.20 1.14 0.63 1.02 047 0.51 OOB 0 0 0 0.55 0.59 1.06 1.70 0.61 0.85 0.81 1.11 0.52 0 0 0 0.57 038 1.15

Annual

95.07 14.03 6.93

24.10 44.30 7.50

9.90 14.40 2.30

1.80 8.57 3.00

424.07 560.27 36.40

7.58 28.00 8.11

33.68 51.11 12.56

15.61 21.28

3.01

57.61 87.00

----

1.16 2.48 1.70

Years Recorded

52 21 21

25 19 25

20 20

7

.... '.---_.-

20 20

5

83 83 18

61 18 18

22 28 10

6 6 2

26 21 26

.:'

}:

it~ .. :." ::::;.

I.l!· :;:.:. ::::::

~r ~:~:~ t~~

I :.;:.:.

!~~~~

I

Page 375: Army Construction Manual FM5 430 Vol1 Entire

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

C-6 H

ydro

log

ic and

Hyd

raulic T

ables an

d C

urves

~-

Table C-1. Mean monthly, maximum monthly, and maximum 24-hour precipitation for selected stations throughout the world (continued)

~ ~ ~~ -_.- -~ _ .. -- "" ~ ... .,." -

Jan Feb Mar Apr May Jun Jul Aug Sep Ccl Nov Dec Annual

FORMER SOVlfT UNION Vladivostok~

Mean 0~50 0.60 0.80 130 2~50 3~50 3~60 540 480 2~00 110 0~70 27BO Maximum 150 '~90 4~90 3~00 5~20 760 9~20 16.70 13~30 4.70 no 1.90 24-hour maximum 090 1.30 2~90 1~00 170 2 BO 3~ 10 3~60 440 2~80 5~20 1.20 5~20

Gizhiga (62 02 N. 160 40' E)

Mean 0~30 0~30 0.40 0~30 0~40 070 1 ~ 70 180 120 1.00 0~60 040 9~ 10

Maximum 1.60 100 1 ~20 0~90 1.20 1 ~50 390 340 300 1 ~80 1 ~80 1 ~60 ~ ... 24-hour maximum 0~40 0.40 0~80 0~60 0~40 0~60 '~80 090 o BO 1 ~ 10 050 0.60 1 ~BO

Irkutsk Meak 0~39 0~29 0~2B 0~24 1 ~50 217 346 3~ 11 169 075 0~67 063 15~51

Maximum 094 0.87 0.71 1.38 4~29 6.10 8.90 5~32 4~ 13 I.B5 1.50 2.68 2268 24-hour maximum 0.34 0.22 0.31 0.54 1.71 1.94 2~39 2.68 1 ~35 0~81 051 0.31 2.68

Odessa. Mean 1.00 1.00 0.95 0.94 1.05 '~98 1 ~59 096 0~82 1 ~ 12 085 1.11 13.37 Maximum 3.98 3.74 2.52 4.02 4.80 6.57 4~65 5.95 5~71 4.21 3.58 3.74 24.88 24·hour maximum 1.20 0~99 1.36 085 0~85 1 ~58 2~98 1.28 194 222 0~78 0~62 2.98

Kola: Mean 0.50 0~84 0.49 0~62 1.25 1 ~24 2.27 194 1 '73 1.26 1.31 0.90 14~35

Maximum 1 ~28 2.41 1.11 2.14 2.35 3.13 4~45 4~37 352 1.92 2.37 248 2033 24-hour maximum 041 0.77 0.28 0.58 0.75 0.78 107 112 O~ 73 0~76 0.63 0.65 1.12

Saturn: Mean 10.07 7.33 5.90 5.84 3.41 6.75 6~30 9~24 1194 947 12.88 10.43 99.56 24-hour maximum 266 2.14 2.89 2~90 3.87 5.82 5.79 4~07 4~64 4~34 3~36 3.01 5.82

Stavropol: Mean 126 1.14 1.34 2.24 2~91 4.06 3.23 1 ~69 2~32 1 ~46 213 1.73 25.51 Maximum 4.21 2.49 3.66 5.08 6.73 7.80 6.38 4~ 17 465 2.91 4.45 5.63 32.99 24~Hour maximum 143 0.58 1.30 1.50 1 ~29 3.75 3.11 235 2.31 1.19 1.17 1.04 3.75

Tiflis Mean 0.59 0.87 1.06 232 3.15 2.91 ,~ 77 146 205 1.57 1.38 0.87 20.00 24-hour maximum 0.54 0.61 0.75 118 211 2.65 1.30 1.43 191 1.24 1.14 1.80 2.65

--

Years Recorded

38 10

16 16 14

,-<-

35 30

18 35 18

18 18 18

10

26 26 18

18 18

Page 376: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/A

FPA

M 32-8013, V

ol 1

Hyd

rolo

gic

and

H

ydrau

lic T

ables

and

C

urves

C-7

Table C·1. Mean monthly, mmdmum monthly, and maximum 24-hour precipitation for selected stations throughout the world (in Inches) (continued)

Jan Feb Mar AJ". May Jun Jul Aug Sep Cct Nov Dec Annual

NEW ZEALAND. AUSTRALIA. AND

NEW GUINEA Finschafen. New Guinea (6- 03' S, 147" 52' E):

Mean 3.13 4.02 3.94 8.56 13.60 17.44 17.62 19.82 13.43 14.70 9.36 4.61 130.23

Maximum 7.56 10.59 8.31 17.86 29.64 29.09 29.61 35.43 31.58 41.61 :~.23 12.36 181.22

24-hour maximum 2.11 4.17 2.64 8.82 6.88 5.83 9.57 6.73 7.44 19.65 7.83 4.49 19.65

Darwin, Australia: Mean 15.83 12.87 9.88 4.17 0.67 0.16 0.08 0.12 0.51 2.17 4.88 10.39 61.73

Maximum 27.86 Z2.65 21.88 23.74 10.27 1.53 2.56 3.00 2.31 6.28 '14.57 22.38 87.22

24-hour maximum 11.65 5.12 7.17 4.:25 1.18 1.34 1.69 106 1.97 3.58 2.76 7.87 11.65

Da/y Waters. Australia; Mean 6.21 6.45 4.79 1.IIlO 0.16 0.32 0.06 0.14 0.27 0.83 2.06 4.08 26.37

Maximum 23.16 13.22 14.50 4.:39 0.28 0.46 0.56 0 0.93 1.42 '10.42 15.76 43.25

24-hour maximum 1.74 3.25 2.80 2.78 0 0.11 0.28 0 0.79 0.30 1.34 3.60 3.60

Brisbane, Australia: Mean 6.50 5.40 5.70 3.!90 2.80 2.70 2.20 2.00 2.00 250 3.80 4.90 45.40

Ma>dmum 27.72 40.39 34.04 15.:;?8 13.85 14.03 8.46 14.67 543 9.99 112.40 13.99 88.26

24-hour maximum 18.30 10.60 11.20 5.l50 5.60 6.00 3.50 4.90 2.50 3.70 4.50 6.60 18.30

Wellington. New Zealand; Mean 3.30 3.19 3.29 3J!O 4.76 4.87 5.55 4.43 3.99 4.19 3.44 3.30 48.11

Maximum 10.13 8.89 9.94 12.15 11,80 9.53 12.17 9.88 11.05 12.94 9.99 12.46 67.68

24-hour maximum 4.50 6.30 5.70 4.!;K) 5.70 3.00 3.10 3.70 380 3.50 2.70 3.50 6.30

ARCTIC (not included previously)

Jan Mayen (70° 59' N, 8 0

2O'W):

Mean 1.54 1.69 1.10 O.!M 0.51 0.59 0.79 1.06 2.52 2.20 1.42 0.98 15.34

Maximum 3.41 4.09 3.03 3.1)7 1.41 1.82 4.05 4.05 4.75 4.80 3.66 4.14 ~---

Coopermine. Canada: Mean 0,44 0.56 0.73 0.152 0.52 0.86 1.34 1.76 1.19 1.01 0.80 0.53 10,46

Maximum 074 2.10 1.95 3.jl5 0.89 2.34 1.84 3.20 1.95 2.23 2.20 0.90 ----Mean snowfall 3.50 5.60 7.30 6J~ 3.90 2.90 0.10 0.40 470 9.10 8.60 5.30 58.20

Uelen. Siberia; Mean 0.63 056 039 0.4~9 0.43 0.50 161 1.79 2.09 1.85 0.54 0.96 11.84

Maximum 2.28 1.85 0.67 0.08 1.08 0.94 2.11 2.64 4.70 6.18 0.88 2.38 - .. AWf8.ge thickness of 12.80 17.60 20.30 21.!iO 17.70 1.80 0.10 1.70 4.60 8.50 .........

snow cover at Anadyr ANTARCTIC

Little America: 1929 snowfall (unmelted 7.30 12.70 24.20 5.00 7.60 16.20 8,90 11.30 2.40 2.00 2.90 2.30 103.50

depth in inches)

Vears Recorded

15 15

.. -.. ~

52 58 28

43 12

3

83 I

91 63

69 69 63

7 16

5 7

8 8

~- --

1

Page 377: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure C-1. Rates of overland flow corresponding to standard supply curves,0.4 and 0.6; n = 0.40, S = 1 percent

supply curve number

C-8 Hydrologic and Hydraulic Tables and Curves

~

o :s o

.r:.

W a. I/) Q) .r:. u c c

15 c 2 '0 Q)

~.r------,-------r------T-----~r-----~-------r------,-----~

~~~~-+------+-----~-------+------~------+-----~~----~

5UPPL Y CURVE NO .. 0.4

1.1~--~--~~----~-------r-------;------~r-------1--------+------~

1.0 ...-......,I-...:.:f----"-..ck-----t----t----t----+-----+-----I

0.0 o 10

IIOf)

30 40 ~o

Duration of supply in minutes

Duration of supply in minutes

Note: L:... effective length of overland or channel flow, in feet. tc = critical duration of supply, In minutes, assuming surface

storage as negligible. o = rate of supply, in inches per hour.

eo

Page 378: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure C-2. Rates of overland flow corresponding to standard supply curves, supply curvenumbers 0.8 and 1.0; n = 0.40, S = 1 percent

Hydrologic and Hydraulic Tables and Curves C-9

SUPPLY CURVE NO. 0.8

10 20 30 ~O ~O 60 70 10

i)uration of supply in minutes ... ~ ~~------r-------r-----~r-----~~----~-------r-------r-------' en Q)

.r:: u .!:

~ ~L-------~-------+-------i--------+-------1--------t-------lr-------1 c 2 '0 Q)

~ E :J E .~

:::2

SUPPLY CURVE NO. 1.0

3~~~~----+-----4-----~-----r-----+-----t-----1

2

IZOO

10 20 30 40 ~o

Duration of supply in minutes

Note: L = effective length of overland or channel flow, in feet. tc = critical duration of supply, in minutes, assuming surface

storage as negligible. a = rate of supply, in inches per hour.

eo 70 10

Page 379: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure C-3. Rates of overland flow corresponding to standard supply curves, supply curvenumbers 1.2 and 1.4; n = 0.40, S = 1 percent

C-10 Hydrologic and Hydraulic Tables and Curves

... CD a.

J3 ... o :; o

.s::. Q) a.

10

SUPPLY CURVE NO. 1.2

20 30 40 ~o eo 70 10

Duration of supply in minutes

~ ~r-------'--------r-------r-------r-------r-------r-------r------~ Q) .s::. t) c c

~ 4~---4~~------~------~------~------~------~------~------~ c 2 '0 SUPPLY CURVE NO. 1.4 Q)

~ 3~~~~~--~~~------~------~------~------~------~------~ E ::::J E .~

::!:

10 20 30 40 ~o

Duration of supply in minutes

Note: L = effective length of overland or channel flow, in feet. tc = critical duration of supply, in minutes, assuming surface

storage as negligible. o = rate of supply, in inches per hour.

eo 70 eo

Page 380: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure C-4. Rates of overland flow corresponding to standard supply curves, supply curvenumbers 1.6 and 1.8; n = 0.40, S = 1 percent

Hydrologic and Hydraulic Tables and Curves C-11

e~----~-----r-----r----~----~r---~r-----r-----'

5~~~4-----~----~-----+-----;----~r---~r---~

SUPPLY CURVE NO. 1.6

4~~~~~---+----~r-----~-----r-----+-----;----~

2

Cl)

u C1l

Ci> c. (/) -0

Cs ::; 10 20 30 40 50 eo 70 0 Duration of supply in minutes .J::.

Ci> C. (/) Cl)

.J::. e 0

.£ c

:a:: 0

5 c 2 '0 SUPPLY CURVE NO. 1.8 Cl)

~ 4

E ::J E .~

3 ~

2

°0~~---1~0----~20------3~0-----4~0------~Lo-----eo~----~7~0----~80

Duration of supply in minutes

Note: L = effective length of overland or channel flow, in feet. tc = critical duration of supply, in minutes, assuming surface

storage as negligible. a = rate of supply, in inches per hour.

Page 381: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure C-5. Rates of overland flow corresponding to standard supply curves, supply curvenumbers 2.0 and 2.2; n = 0.40, S = 1 percent

C-12 Hydrologic and Hydraulic Tables and Curves

~

~ o r:.

ID a. C/) Q) r:. u c c

=1= o c ;: '0 Q)

~ E ~

E .~

~

7r-----~----._----._----,_----_r----~----_,----_,

.~~~+_----~----~----~----~----_+----_1----~

SUPPLY CURVE NO. 2.0'

~~~~~----+-----+-----~-----r-----+----~-----;

0~ ____ L-____ L-__ ~ ____ ~ ____ ~ ____ ~ ____ ~ ____ ~

o 10 20 30 40 110 70

Duration of supply in minutes

7~----r-----r----'-----'----_'----_'----~-----'

.~~~~----+-----+-----~----~-----r-----+-----i

SUPPLY CURVE 'NO. 2.2

10 20 30 40 60 70 ee

Duration of supply in minutes

Note: L = effective length of overland or channel flow, in feet.

tc = critical duration of supply, in minutes, assuming surface storage as negligible.

a = rate of supply, in inches per hour.

Page 382: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure C-6. Rates of overland flo w corresponding to standard supply curves, supply curvenumbers 2.4 and 2.6; n = 0.40, S = 1 percent

Hydrologic and Hydraulic Tables and Curves C-13

ar---~----~----~----~--~~--~----~--~

'~~~----~----4-----+---~~---+----~--~

SUPPLY CURVE NO.2.4

.......... -+++.

.I (I) ... 0 tG ....

Z ~

ti 0 ... ::l 0

.J::. .... 10 20 30 ~

40 :!IO 60 70 ac Vl Duration of supply in minutes (I)

.J::. a 0 c c

:g ., c 2 SUPPLY CURVE NO. 2.6 ..... 0 (I) • ~ E s ::l E .~

~ .. 3

Z

o~--~-----L----~--~----~ ____ ~ ____ ~ __ ~ o 10 20 30 40 !l0 60 70

Duration of supply in minutes

Note: L = effective length of overland or channel flow, in feet.

tc = critical duration of supply, in minutes, assuming surface storage as negligible.

a = rate of supply, in Inches per hour.

eo

Page 383: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Duration of supply in minutes

Note: L = effective length of overland or channel flow, in feet.tc = critical duration of supply, in minutes, assuming surface

storage as negligible. = rate of supply, in inches per hour.

Figure C-7, Rates of overland flow corresponding to standard supply curves, supply curvenumbers 2.8 and 3.0; n = 0.40, S = 1 percent

C-14 Hydrologic and Hydraulic Tables and Curves

Page 384: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-2. Hydraulic radius (R) and area (A) of symmetrical triangular channels

Hydrologic and Hydraulic Tables and Curves C-15

----WP

~ R= A/WP

[Depth, Slope ratio

d 1:1 It:l 2:1 2i:l 3:1 11:1 (feet) " JI A JI A R A It A R A It

0., 0.25 0.18 0.38 0.21 0·50 0.22 0.63 0·23 o·n 0.2Il 1.00 o.a 0.6 0.36 0.21 0.5' 0·25 0·72, 0.21 0·90 0.26 1'.08 0.26 I." o.~ 0.7 0.49 0.25 ' o.~ 0.29 0.98 0.31 1.23 0.32 1.41 0·33 1.96 o.~

, ,-0.8 0.61. 0.26 0.96 0·33 1.26 0.36 1.60 0·37 1·92 0·38 2.56 0.39 0.9 0.81 0.32 1.21 0·37 1.62 o.lto 2.03 0.112 2.113 0.113 3.~ 0.1t4 1.0 1.00 0.35 1.;0 0.112 2.00 0 •• , 2. SO o.,w; 3.00 0.47 11.00 0.119

1.1 1.21 0·39 1.82 0.116 2.112 0·119 3.03 0.51 3.63 0.)2 11.811 0.53 1.2 1." 0.42 2.16 0.;0 2.88 0.511 3.60 0.56 ~.)2 0.57 5.76 0.58 1·3 1.69 0.116 2·54 0.54 3·38 0.58 4.23 0.60 5·01 0.62 6.76 0.63

1.4 1.96 0.;0 2.94 0.58 3·92 0.63 4.90 0.65 5·88 0.66 7.811 0.68 1.5 2.25 0.53 3.38 0.62 11·50 0.67 5.63 .0.70 6.n 0.71 9.00 0.73 1.6 2.56 0.57 3.a- 0.61 5·12 0·72 6.40 0.7\ 7.68 0.76 10.2Il 0.78

1.7 2.89 0.60 4.~ 0.71 5.78 0.76 7.23 0.79 8.67 o.eo 11·56 0.83 1.8 3.~ 0.61. 4./36 0·75 6.48 0.80 8.10 0.811 9.72 0.85 12·96 0.87 1·9 3.61 0.67 5.1!.2 0.79 7·22 0.85 9.03 o.ea 10.8,3 0·90 111.411 0.92

2.0 11.00 0.71 6.00 Q.83 8.00 0.90 10.00 0.93 12.00 0·95 16.00 0·97 2.' 6.25 0.88 9.38 1.011 12·50 1.12 15.63 1.16 18·n 1.19 25.00 1.21 3·0 9.00 1.<:6 13.;0 1.25 lB. 00 l.~ 22. SO 1·39 rtr.oo 1.42 36·00 1.116

).S 12.2S 1.211 18.)1) 1.IlS ill. SO 1.% )0.62 1.62 )6.7S 1.66 1.9.00 1.70 ~.o 16.00 1.U 211.00 1.66 ,)2.00 1.78 1.0.00 1.8S 118.00 1.90 6U.00 1.9b

5:1 6:1 7:1 8:1 9:1 10:1 It. R A R A R It. It A R A R

0.5 1.25 0.25 1.50 0.25 l·n 0.25 2.00 0.25 2.~ 0·25 2. SO 0.25 0.6 1.eo 0.29 2.16 0·30 2.52 0.30 2.88 0.30 3· 0·30 3.60 0·30 0·7 2.115 o.~ 2.94 0·35 3.113 0.35 )·92 0.35 4.111 0·35 ·.90 0·3~

0.8 3.3) 0·39 3.811 0·39 4.118 0.40 ,.12 0.40 5.76 O.lto 6.a.o 0.40 0.9 4.05 0." ~./36 0." 5.61. 0.115 6.118 0.45 7.29 0.45 8.10 0.45 1.0 5.00 o.~ 6.00 0.119 7.00 0.119 8.00 o·SO 9.00 o·SO 10.00 O.SO

1.1 6.05 0.5' 1.~ 0.54 8.il7 O.~5 ).68 0.55 1O.~ 0.55 12.10 0·55 1.2 1·20 0.59 8.64 0.59 10.06 0.59 ,u.52 0.60 12.96 0.60 14.40 0.60 1.3 8.115 0.64 10.14 0.64 11.83 o.~ 13·52 0.611 15.21 0.65 1.6.90 0.65

1.4 9.80 0.69 1l.76 0.69 13·72 0.69 15.68 0.69 17.~ 0.70 19.60 0.70 1.~ 1l.25 0.7\ 13.50 0.711 15.75 0.7\ lB. 00 0.7\ 3)·25 o·n 22.50 o·n 1.6 12.80 0.18 15.36 0·79 17.92 0.79 20.118 0·79 23.011 0.80 25.60 tr.eo

1.1 14.45 0.83 17.)4 0.811 20.23 0.811 23.12 0.811 2i.Ol 0.811 26.90 0.85 1.8 1.6.20 0.88 19." 0.89 22.68 0.89 25·92 0.89 29.16 0·89 )2.110 0.90 1.9 18.05 0.93 21.66 0.911 25·rtr 0.911 26.88 0.911 32.119 0.911 36.10 0·95

2.0 20.00 0.98 ~.OO 0·99 26.00 0·99 )2.00 0·99 36.00 0·99 lto.OO 1.00 2·5 )1.25 1·23 37.50 1·23 It). 75 1.~ SO. 00 l.a 56.2'5 l • .211- 62.50 l.a 3·0 115·00 1.117 54.00 1. .... '3.00 l.1I8 72.00 1.~ 81..00 l.~ 90.00 l.49

).S 61.2S l.n 7).50 1.72 8S.7S 1.7) 98.00 1.11. 1l0.2$ 1:.71.. 122. SO 1.71. 1..0 8O.(YJ l.96 96.00 1.97 112.00 1.98 128.00 1.98 w..00 1.98 160.00 1.99

Page 385: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-3. Hydraulic radius (R) and area (A) of nonsymmetrical triangular channels

C-16 Hydrologic and Hydraulic Tables and Curves

----wp ~ ~ ~ ,- -~

~i R= AiWP

[ De~tht i

Slope ratio

1:1 - 3:1 It:l - 3:1 2:1 - 3:1 2t:l- 3:1 4:1 - 3:1 5:1 - 3:1 (fe et) A R A R A R A R A R A R

0·5 0.50 0.22 0.56 0.23 0.63 0·23 0.69 0.23 0.88 0.24 1.00 0.24 0.6 0.12 o.~ 0.81 o.zr 0.90 0.26 0·99 0.28 1.26 0.29 1.44 0·29 0.7 0.98 0.31 1.10 0.32 1.23 0.32 1.35 0.33 1.72 0.34 1.96 0·34

0.8 1.28 0.35 1.44 0.36 1.60 0.37 1.76 0.38 2.P4 0.38 2.56 0·39 0·9 1.62 0.39 i.82 0.41 2.03 0.42 2·23 0.42 2.84 0.43 3·24 0.4.4 1.0 2.00 0.44 2·25 0.45 2.50 0.46 2.75 0.47 3.50 0.48 4.00 0.48

1.1 2.42 0.48 2.12 0.50 3·03 0.51 3·33 0·52 4.24 0.53 4.84 0·53 1.2 2.88 0.52 3.24 0.54 3.60 0.56 3.96 0.56 5.04 0.58 5.76 0.~8 1·3 3·38 0.51 3.80 0.59 4.23 0.60 4.65 0.61 5·92 0.63 6.76 0.63

1.4 3.92 0.61 4.41 0.63 4.90 0.65 5·39 0.66' 6.86 0.67 7.84 0.68 ~.~ 4.50 0.66 5.06 0.68 5.63 0.69 6.19 ! 0.70 7.88 0.72 9·00 0.73 - -- - -- ~ -" A _4 L 1.ft l.b

5.18 6.48 1.22

1

u. (U 1 0.14 0.79 0.83

'" ..,. .. .y "t. . n .,c: A06 " '7'T ,,, ~ ".'7'T -- .. v.

::~ 1 ;:231 ::~ 1 ~:: 1 o.~ 11::~2 1 ::~~ 1 ::~ 1 :.~~ 1 0.82 8.10 0.83 8.91 0.85 11.34 0.86 12.96 0.87 0.86 9.03 0.88 9.93 0.89 12.64 0.91 14.44 0.92

8.00 8.82 9.68

10.58 1l.52 12.50

13.52 14.58 15.68

0.87. 0·92 0.96

1.01 1.05. 1.09

1.14 1.18 1.22

16.82 1.27 18.00 1.31

I

9.00 9.92

10.89

1l.90 12.96 J.J..c6

15·21 16./jO 11.64

0.91 10.00 0.95 1l.03 1.00 12.10

1.~ 13.23 1.09 14.40 1.13 15.63

1.J.8 16.90 1.22 18~23 1.zr 19.60

1.31 21.03 1.36 22.50

I

0·93 11.00 0.97 12.13 1.02 13·31

1·07 14.55 1.11 15.84 1.·16 17·19

1.20 18.59 1.25 20·05 1.30 21.56

1.}4 23.13 1.39 24·75

I I

0.94 0.99 1.03

1.08 1.13 1.17

1.22 1.27 1.32

14.00 15.44 16.94

0.96, 16.00 1.00 17.64. 1.06 19.36

18.52 1.10 20.16 1.15 21.87 1.20

23.66 1.25 25.52 1.30 27.44 1.35

1.36 29.4.4 1.41 31.50

I

0·97 1.02 1.07

1.11 1.16 1.21

Page 386: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-4. Hydraulic radius (R) and area (A) of symmetrical trapezoidal channels(2-foot bottom width)

Hydrologic and Hydraulic Tables and Curves C-17

----wp

(:::1"' .... _ .,..t:", Depth, UE

d 1 :1 li'l 2: 1 2t'l .3:1 4:1 (feet) A R A R A R A R A R 1\ R

0.5 1.~S 0.37 1.38 0.36 1.50 !0.35 1.63 0.35 1.75 0 • .34 2.00 0.33 0.6 1.56 0.42 1.74 0.42 1.92 10.41 2.10 0.40 2.2a 0 • .39 2.(,4 0.3n 0.7 1.89 0.47 2.14 0.47 2.20 0.44 2.63 0.46 2.87 0.45 3.36 CI.43

0.8 2.24 0.53 2.56 0.52 ... Of') ,..,. ... ~ ~'" " .. I ~ .... n .. n ,. 1'- n I.!'

I ;/..00 V,;)" ) .~V V,;tl ).;14- ..,.;'\1 ..".\1 v._

0.9 2.61 0.51 3.01 0.57 3.42 0.57 3.B3 0.56 4.23 0.55 5.04 o.SJt 1.0 3.00 0.62 3.50 0.62 4.00 0.02 4.50 0.61 5.00 0.60 G.oo 0.59

1 .1 3.41 0.67 4.02 0.67 4.63 0.67 5.23 0.66 5.84 0.65 7.05 0.64 1.2 3.84 0.71 4.56 0.72 5.28 0.72 6.00 0.71 6.72 0.70 8.16 0.69 1.3 4.29 0.76 5.14 0.77 5.98 0.77 6.83 0.76 7.67 0.75 9.36 0.74

I 1.4 4.76 0.80 5.74 0.81 6.n. 0.81 7.70 0.81 8.68 0.80 10.64 0.79 1.5 5.25 0.84 6.38 0.86 7.50 0.86 8.63 0.86 9.75 0.85 12.00 0.84 ! .6 5.76 0.88 ].04 0.9! 8.32 0.91 9.60 0.90 10.88 0.90 13.1/4 0.88

1.7 6.29 0.92 7.74 0.95 9.18 0.96 10.63 0.95 12.07 0.95 14.96 0.93 1.8 6.84 0.96 8.46 1.00 10.08 1.00 11.70 1.00 13.32 1.00 16.56 0.98 1.9 7.41 1.00 9.22 i,04 i i.02 LOS ii,8) i.OS i4.G3 i .04 i8.24 LO)

2.0 8.00 1.04 10.00 1.09 12.00 1.10 14.00 1.10 16.00 1.09 20.00 1.08 2.5 11.25 1.24 14.38 1.30 17.50 I. 33 20.63 1.33 23.75 1.33 30.00 1. 33 3.0 15.00 1.43 19.50 1.52 4.00 1.56 28.30 1.57 33.00 1.57 42.00 1.57

5 :1 6:1 7 :1 8:1 9:1 10:1 A R A R A R fI R A R A R

o.~ 2.25 0.32 2.5~ 0.3\ 2·Z5 0.30 3.00 0.30 tU 0.2~ t~~ 0.2~ 0.6 3.00 0.37 3.36 0.36 3.72 0.35 4.08 0.35 0.34 0.34 0.7 3.85 0.42 4.34 0.41 4.83 0.41 5.32 0.40 5.81 0.39 6.30 0.39

1\ D I. On. ft J., r 1.1. 1\ I.£. t:. nD 1\ I,L t:. .. ., ,.. I.I!' .. ..c. " ',r n nn " 1.1 .. v." ... gU u ... , :;I._ v ..... U.Ug v ...... u./I> u ... ;) ,.;,u u.";J u • ..,,, v._

0.9 5.85 0.52 6.66 0.51 7.47 0.51 8.28 0.50 9.09 0.50 9.90 0.49 1.0 7.00 0.51 8.00 0.56 9.00 0.56 10.00 0.55 11.00 0.55 12.00 0.54

1.1 8.25 0.62 9.47 0.62 10.6B 0.61 t/ .89 0.60 1/3.10 0.60 14.31 0.59

I 1.2 9.60 0.67 ! 1.04 0.67 12.48 0.66 13.92 0.65 15.36 0.65 16.80 0.64 1.3 11.05 0.72 i2.74 0.72 14.43 0.71 16.12 0.70 17.81 0.70 19.50 0.69

1.4 12.60 0.77 14.50 0.77 16.52 0.76 18.48 0.75 20.44 0.75 22.40 0.74 1.5 14.25 0.B2 16.50 0.81 lB.75 0.81 21.00 0.80 23.25 0.80 25.50 0.79 1.6 16.00 0.87 18.56 0.86 21.12 0.86 23.68 {) .85 26.24 0.85 28.80 0.84

1.7 17.B5 0.92 20.74 0.91 23.63 0.91 26.52 0.90 29.41 0.90 32.30 0.89 1.8 19.80 0.97 23.011 0.9(, 26.28 0.96 29.52 0.95 32.76 0.95 36.00 0.94 1.9 21.85 1.02 25.46 1.01 ?CI r.,., 1.0! 32.08 J .00 ~t:. .. 0 ! .00 ~o on n ''''

I . .",."'" .;IV.6-;;} ~;7.7V \,I.;};]

2.0 24.00 1.07 28.00 1.06 32.00 1.06 36.00 1.05 40.00 1.05 44.00 1.04 2.5 36.25 1.32 1;2.50 1. 31 43.75 I. 30 ~5.o0 1.30 61.25 1. 30 67.50 1.29 3.0 Si .00 I.~(, bO.OO 1.5:) CS.oo 1.5~ 78.00 1.55 87.00 1.54 96.00 1.54

Page 387: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

C-18

Table C-5. Hydraulic radius (R) and area (A) of symmetrical trapezoidal channels(4-foot bottom width)

Hydrologic and Hydraulic Tables and Curves

----wp

Depth, 1 :I It-I

ff.~tl A R A R O.~ 2.25 0.'+1 2.)8 0.41 0.6 2.16 0.48 2.94 0.48 0.1 3.29 0.55 3.54 0.54

0.8 3.84 0.61 4.16 0.60 0.9 4.41 0.67 4.82 0.66 1.0 5.00 0.73 5.50 0.72

1.1 5.61 0.79 6.22 0.78 1.2 6.24 0.84 6.96 0.84 1.l 6.89 0.90 7.74 0.89

1.4 7.56 0.95 B.5ft 0.94 1.5 8.25 1.00 9.38 1.00 1.6 8.96 LOS 10.24 1.05

1.7 9.69 1.10 11.14 1.10 1.8 10.44 LIS 12.06 1.15 1.9 11.21 l.20 13.02 1.2"0

2.0 12.00 1.24 14.00 1.25 2.5 16.25 1.47 19.38 1.48 3.0 21.00 1.68 25.50 1.72

5 : I b:1 A R A R

0.5 !.25 0.3& 3.50 0.35 0.6 4.20 0.42 4.56 0.40 0.7 5.25 0.47 5.74 0.46

0,8 6.40 0.53 7.04 0.51 0.9 7.65 0.58 8.46 0.56 1.0 9.00 0,64 10.00 0.62

1.1 10.45 0.69 11.66 0.67 1.2 12.00 0.74 13.44 0.72 1.3 13.65 0.79 15.34 0.77

1.4 15.40 0.84 17.36 0.8) 1.5 17.25 0.89 19.50 0.88 1.6 19.20 0.94 21.76 0.91

1.7 21.25 1.00 2it.14 0.98 1.8 23.40 1.05 26.64 l.o) 1.9 2S .65 1.10 2~6 1.08

2.0 28.00 l.IS 32,00 1.14 2.5 41.25 1.40 47.50 I. )0 3.0 57.00 1.65 66.00 1.(,4

A=lld2 .4d

WP:2d~ +4 R= A/WP

SlOna I atio l.: I 2 '1

A R A R 2.50 0.40 2.6) 0.39 3.12 0.47 3.30 0.46 3.78 0.53 4.03 0.52

4.48 0.59 4.80 0.58 5.22 0.6S 5.63 0.64 6.00 0.71 6.50 0.69

6.82 0.76 7.43 0.75 7.68 0.82 8.40 . 0.80 8.58 0.87 9.43 0.86

9.52 0.9) 10.50 0.91 ~O.50 0.98 11.63 0.96

1.52 1.0) 12.80 1.01

2.58 1.08 14.03 1.07 13.68 1.14 15.30 1.12 4.82 1.19 16.63 1.17

\6.00 1.2" 18.00 1.22-22.50 1.48 25.63 1.47 30.00 1.72 34.50 1.71

7 :1 6: A a A R

;.75 0.34 4.00 0.33 4.92 0.39 5.28 0.38 6.23 0.45 6.72 0.'+4

7.68 0.50 8.32 0.49 9.27 0.55 10.08 0.55

11.00 0.61 12.00 0,60

12.87 0.66 14.08 .0.65 14,88 0.71 16.32 0.70 \7.03 0.76 18.72 0.75

19.32 0.81 21.28 0.80 ~1.75 0.86 24.00 0.85 ~4.32 0.91 26.88 0.90

27.0, 0.96 29.92 0.95 29.80 1.01 33.12 1.00 32.87 I.OG 36.48 1.05

36.00 1.12 40.00 1.10 53.75 1.37 Gcc.oo 1.35 75.00 1.6) 31).1i0 1.62

3:1 4:1 A R A R 2.75 0.39 3.00 0.)7 3.48 O • .ItS 3.SIt 0.43 4.27 0.50 4.76 0.49

5.12 0.57 5.76 0.54 6.03 0.62 6.SIt 0.60 1.00 0.68 8.00 0.65

8.0) 0.73 9.24 0.71 9.12 0.79 10.56 0.76

10.27 0.8lt 11.96 o.BI

1148 0.89 I) .'+4 0.86 12.75 0.94 15.00 0.92 14.08 1.00 16.64 0.97

15.47 1.05 18.36 1.02 16.92 1.10 20.16 1.02 18.43 1.15 22.04 1.12

20.00 1.20 24.00 1.17 28.75 I . .ItS 35.00 1.42 39.00 1.70 48.00 1.67

9 :1 \0 :1 A R A R 4.25 0.;2 4.50 0.32 5.64 0.38 6.00 0.37 7.21 0.43 7.70 0.43

8.96 0.49 9.60 o.~ 10.89 0.54 11 .70 0.53 13.00 0.59 '''.00 0.58

15·.29 0.64 16.50 0.63 17.76 0.69 19.20 0.68 20.41 0.74 22.10 0.73

23.24 0.79 25.20 0.78 26.25 0.84 28.50 0.S3 29.44 0.89 32.00 0.89

32.81 0.94 35.70 0.!!4 36.36 0.99 39.60 0.99 ~O.09 1.04 43.70 1.04

44.00 1.09 11S.00 1.09 66.25 1.311 72.50 I .3'. 93.00 I.G2 102.00 I.i"

Page 388: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-6. Hydraulic radius (R) and area (A) of symmetrical trapezoidal channels(6-foot bottom width)

Hydrologic and Hydraulic Tables and Curves C-19

----wp

lDepth. SIOIUl ro tlO

d J : I 1'1 '1 2 :1 2.i'l 3! 1 4 :1 (feen A R A R A R A R A R A R

0.5 3.25 0.44 3.38 0.43 3.50 0.42 ).63 0 .... 2 3.50 0.41 4.00 0,40 0.6 ].96 0.51 4.14 0.51 4.32 0.50 4.50 0.49 4.68 0.i+B 5.04 0.46 0.7 4.69 0.59 4.94 0.58 5.18 0.57 5.43 0.56 5.67 0.54 6.16 0.52

0.8 5.44 0.66 5.76 0.65 6.08 0.63 6.40 0.62 6.72 0.61 7.).6 0.58 0.9 6.21 0.73 6.62 0.72 7.02 0.70 7.43 0.68 7.83 0.67 8.64 0.Q.4 1.0 7.00 0.79 7.s0 0.]8 8.00 0.76 8.50 0.75 9.00 0.73 10.00 0.70

1.1 7.81 0.86 8.42 0.85 9.02 0.83 9.63 0.80 10.23 0.19 11.44 0.76 1.2 8.64 0.92 9.36 0.91 0.08 0.89 10.80 0.61 11.52 0.85 12.96 0.62 1.3 9.49 0.98 10.)4 0.91 1.18 0.95 12.03 0.93 12.87 0.91 14.56 0.87

1.4 10.36 1.04 11.)4 1.03 2.32 1.00 13.30 0.98 14.28 0.96 16.24 0.9) 1.5 11.25 1.10 12.38 1.08 3.50 1.06 14.63 1.04 15.75 1.01 18.00 0.98 1.6 12.16 1.16 n.44 1.14 .... 72 1.12 16.00 1.09 17.28 1.07 19.84 1.03

1.7 1).09 1.22 14.54 1.20 15.98 1.17 17.4) 1.15 18.87 1.13 21.76 1.09 1.8 14.0It 1.27 15.66 1.25 17.28 1.23 18.90 1.20 20.52 1.18 23.76 1.14 1.9 15.01 1.32 16.82 1.30 18.62 1.28 20.43 1.25 22.2) 1.24 25.84 1.19

2.0 16.00 1.37 18.00 1.36 ~o.oo 1.)4 22.00 1.)1 24.00 1.29 28.00 1.24 2.5 21.25 1.61 24.38 1.61 27.50 1.60 30.63 l.se 33.75 1.55 40.00 1.50 3.0 27.00 1.86 31.50 1.87 )6.00 1.85 40.50 1.8) 45.00 1.80 54.00 1.76

5 : b: 7: ~_:I 9: 10:1 A 1\ A 1\ A R A " A R A R

; 0.5 4.25 0.38 4.50 0.37 4.75 0.36 5.00 0.)6 5.25 0.35 5.50 0.34 0.6 5.90 0.45 5.76 0.43 6.12 0.42 6.i+B 0.41 6.84 0.41 7.20 0.40 0.7 6.65 0.51 7.14 0.49 7.63 o.i+B 8.12 0.47 8.61 0.46 9.10 0.45

0.8 B.oO 0.56 8.64 0.55 9.28 0.54 9.92 0.53 10.56 0.49 11.20 0.51 . 0.9 9.45 0.62 10.26 0.61 11.07 0.59 11.88 0.58 12.69 0.57 13.50 0.55

1.0 11.00 0.68 12.00 0.66 t3.00 0.65 22.12 0.63 15.00 0.62 16.00 0.6\

t • 1 12.65 0.73 13.86 0.12 15.07 0.70 16.28 0.69 17.49 0.67 18.70 0.67 1.2 14.40 0.79 15.84 0.77 17.28 0.75 18.72 0.74 20.16 0.75 21.60 0.72 1.1 16.25 0.85 17.94 0.82 19.63 0.80 21.32 0.79 23.01 0.78 24.70 0.77

1.4 18.20 0.90 20.16 0.87 ;22 .12 0.B5 24.08 0.84 26.04 0.8) 2B.oo 0.82 1.5 20.25 0.95 22.50 0.92 ;74.75 0.91 27.00 0.90 29.25 0.88 31.50 0.B7 1.6 22.40 l.ttO 24.96 0.98 !27.52 0.96 39.08 0.95 32.64 0.93 35.20 0.92

1.7 24.l15 \.06 27.54 1.03 30.43 1.01 33.32 1.00 36.21 0.97 39.10 0.97 1.8 27.00 1.11 30.24 1.08 33.48 LOG :)6.72 1.08 39.96 1.04 43.20 \.02 1.9 29.45 1.16 33.06 1.14 36.67 1.12 40.28 1.10 113.89 i.09 47.50 1.07

2.0 32.01) 1.21 36.00 1.19 L;O.OO 1.17 I~I.OO 1.15 IIU.OO 1.13 52.00 1.12 2.5 46.25 1.47 52.50 1.45 58.75 1 .I,u 65.00 1.'10 71.7.5 1.39 77.50 1.33 3.0 63.00 1.72 12.00 1.70 81.00 I. 71 !';o.oo I.~S 99.00 l.G6 108.00 I .6~

Page 389: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-89013, Vol 1

Table C-7. Hydraulic radius (R) and area (A) of symmetrical trapezoidal channels(8-foot bottom width)

C-20 Hydrologic and Hydraulic Tables and Curves

,---WP A ~ d " A= xd

2 + 8 d LI "--_... x WP= 2d~ + 8

lXd-Le'~ R=A/WP

Depth, Slope ratio d 1 :I li'l Z :1 2i" ~:I '+: 1

{feet} A R It R A R A R A R A R OS 4.25 0.'+5 4.}8 o.4S 4.50 0.44 4.63 0.43 4.75 a.ll) 5.00 0.41 0.6 5.16 0.5) S.:J' 0.S3 5.52 0.52 S.70 0.51 5.88 0.50 6.2" 0.'+8 0.1 6.09 0.61 6.)\ 0.60 6.58 0.5' 6.83 0.58 7.01 0.57 7.56 0.55

0.8 7.04 0.69 7.36 0.68 7.68 0.66 8.00 0.65 8.32 0.64 8.96 0.61 0.9 8.01 0.76 8.42 0.75 8.82 0.73 9.22 0.72 9.63 0.70 10.44 0.68 1.0 9.00 0.83 9.50 0.82 10.00 0.80 10.50 0.78 11.00 0.77 12.00 0.74

1.1 10.01 0.90 10.62 0.89 11.12 0.87 11.83 0.85 12.43 0.83 \3.64 0.80 1.2 I' .04 0.97 11.76 0.95 12.48 0.93 13.20 0.91 13.91 0.89 15.36 0.86 1.3 12.09 1.04 12.94 1.02 13.78 1.00 14.63 0.98 15.97 0.95 17.16 0.92

1.4 13.16 1.10 14.14 1.08 15.12 1.06 16.10 1.04 17.08 1.01 '9.04 0.97 1.5 14.25 1.16 15.38 1.14 16.50 1.12 17.63 1.10 18.75 1.07 21.00 1.03 1.6 15.36 1.23 16.64 1.21 17.92 1.18 19.20 1.16 20.48 1.13 23.04 1.09

1.7 16.49 1.29 17.44 1.27 19.38 1.24 20.83 1.22 22.27 1.19 25.16 I. '4 1.8 17.64 1.35 19.26 1.;3 20.88 1.30 22.,0 1.11 29.12 1.2lt 21.36 l.lQ 1.9 18.81 1.41 20.63 1.40 22.42 1.36 24.23 1.33 26.03 1.30 29.64 1.25

2.0 20.00 1.46 22.00 1.45 24.00 1.42 26.00 1.39 28.00 1.)6 )2.00 1.31 2.5 26.25 1.76 29.38 1.72- )2.50 1.69 35.6) 1.66 ;8.75 1.6) 45.00 1.57 3.0 33.00 2.00 31.50 1.99 42.00 1.96 46.50 1.93 51.00 1.89 60.00 1.83

5: 1 6:1 7 :1 8:1 .2: I ID :1 A R A R A R A R A R A fl

. O.S 5.25 0.40 5.50 0.39 5.75 o.~ 6.00 0.37 6.25 0.3& 6.50 0.36 0.6 6.00 0.47 6.96 0.44 7.32 0.44 7.68 0.43 8.04 0.43 8.40 0.42 0.7 8.05 0.53 8S4 0.52 9.03 0.50 9.52 0.49 10.01 0.48 10.50 0.'+8

0.8 9.60 0.59 10.24 0.58 10.88 0.56 11.20 0.5'* 12.16 0.54 12.80 0.53 0.9 11.25 0.65 12.06 0.64 1l.87 0.63 13.68 0.61 14.49 0.60 15.30 0.59 1.0 13.00 0.71 14.00 0.70 15.00 0.68 16.00 0.66 17.00 0.65 18.00 0.64

1.1 llt.S5 0.77 H>.of> 0.75 17.27 0.73 18.48 0.72 19.69 0.71 20.90 0.69 1.2 16.80 0.83 18.24 0.81 19.68 0.79 21.12 0.77 n.5G 0.76 24.00 0.74 1.3 18.85 0.88 20.54 0.80 22.23 0.84 23.92 0.83 25.61 0.81 27.30 0.~9

1.4 21.00 0:92 22.96 0.91 24.92 0.90 26.88 0.88 28.84 0.86 30.80 0.84 1.5 23.25 1.00 25.50 0.97 27.75 0.95 ,0.00 0.93 32.25 0.91 34.50 0.90 1.6 25.60 1.05 28.16 1.03 30.72 1.00 33.28 0.98 35.84 0.97 38.40 0.96 1.7 28.25 1.11 30.94 1.08 33.85 1.06 3u.72 1.04 39.6\ 1.02 42.50 1.01 1.8 30.60 1.Tu 33.84 1.13 37.08 1.11 M.32 1.08 43.56 1.07 46.80 1.06 1.9 33.25 1.22 36.86 1.18 40.47 1.16 44.08 1.14 47.1)9 1.12 51.30 J.lt

2.0 36.00 1.28 40.00 1.24 44.00 1.21 48.00 1.19 '52.00 1.18 56.00 1.16 2.5 57.25 1.54 57.50 1.50 63.75 1.48 70.00 1.45 7":;.25 1.43 82.50 1.42 3.0 69.00 1.80 78.00 1.77 8] .00 I.]ll 9:.>.00 1.70 105.00 1.70 114.00 1.69

Page 390: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-8. Hydraulic radius (R) and area (A) of symmetrical trapezoidal channels(10-foot bottom width)

Hydrologic and Hydraulic Tables and Curves C-21

Depth, Slope ratio

cl 1:1 li:1 2:1 21:1 3:1 11:1

(feet) -A It A It .. It A- B A R A It

0.5 '·25 o.WI '.38. O.WI 5.50 0.45 5.63 0." 5·TS 0."",,, 6.00 0.112 0.6 6.)6 o.~ 6.5" 0.511 6.72 0·53 6.90 0.52 7.08 0·51 7.U 0.50 0.1 1.~ 0.63 7.7\ 0.62 7.98 0.61 8.2,3 0.60 8 .... 7 0·59 8.96 0.57

0.8 8.~ 0.11 8.96 0.70 9.26 0.68 9.60 0.6'7 9.92 0.66 10.56 o.~ 0., ,.81 0.76 10.22 0.77 10.62 0.76 J.l.01 0.74 ll .... ) 0·73 12.~ 0:10 1.0 1l.00 0.86 1l.50 0.85 12.00 0.B3 12·50 0.81 13·00 O.eo 1 .... 00 0.77

1.1 12.21 0·93 12.82 0·92 13.1.2 0.90 1 .... 03 0.88 1 .... 63 0.86 15.811 0.83 1.2 13." 1.00 1 .... 1.6 0.99 1 •• 88 0.97 15.60 0·95 16.32 0·93 17.76 0.89 1.3 liJ·69 1.07 15.5" 1.06 16.)8 1.01. 17.23 1.01 18.07 0·99 19.76 0.95

l.~ 15.96 1.1_ 1.6.94 1.13 17·92 1.10 lB. 90 1.08 19.88 1·05 21.811. 1.01 1.5 17·25 1.21 lB.)8 1.19 19.50 1.17 3>.63 1.14 21.15 1.12 ~.OO 1.07 1.6 18.$6 1.'i!B 19.$4 1.as 21.12 1.2,3 22.40 1.20 2,3.68 1.18 as.~ 1.13

1.7 19.&9 1.3- 2l.,Y. 1.32 22.78 1.29 ~.23 1.26 25.67 1.~ 26.$6 1.19 1.8 21." 1.~1 22.86 1.39 2ff.108 1.36 as.l0 1.33 '27.72 1.)0 30.96 1.25 1.9 22.61 1.47 ~."2 1 .... 5 26.22 1.42 26.03 1.39 29.83 1·35 33." 1.)0

'2.0 ~.OO 1.53 as. 00 1.51 26.00 1.108 )0.00 1." 32.00 1. ... 1 36.00 1.)6 2., 31·25 1.83 34.38 1.81 37.50 1.77 40.63 1.73 "3.75 1·69 50.00 1.6) 3.0 39.00 2.11 1,3.50 2.09 108.00 2.05 52.50 2.01 57.00 1·97 66.00 1·90

5:1 6:1 7:1 8:1 9:1 10:1

A Il A Il A R A It A- ft A ft 0., 6·25 0._1 6.50 0.110 6.15 0.40 7·00 0.39 7·25 0·38 7.50 0·37 0.6 1.80 o.W! 8.1.6 0.-7 8.52 0.46 8.88 0.45 9.~ 0.-... 9.60 0.-... 0.7 9.It, 0·55 9.94 0.5'" 10.i!.3 0.52 10·92 0.51 U.41 0·50 11.90 0.1·9

0.8 11.21) 0.62 11.~ 0.60 12.48 0·59 13·12 0.57 13.76 0.56 1 .... 1+0 0·5' 0.9 13·05 0.68 13.86 0.66 14.67 0.65 15.~ 0.63 16.29 0.62 17.10 0.61 1.0 15.00 O.'J'If 16.00 0.72 17.00 0.70 16.00 0.69 19·00 0.68 m.oo 0.66

1.1 17·05 0.80 18. as 0.78 19.47 0.76 3'.>.68 0·75 21. SI] 0·73 23·10 0.72 1.2 19.21) 0.85 3>.~ o.~ 22.08 0.82 23.52 0.80 24.96 0·79 as. 40 0.77 1.3 21.45 0.92 23.1" 0·90 2ff.83 0·87 as·52 0.136 g). 21 0.8Il 29·90 0.63

1 .... 23.80 0.98 25.76 0·95 ra·72 0·93 29.68 0·91 31.~ 0.89 33.60 0.88 1., as. 25 1.011 23.50 1.01 30·75 0·99 33·00 0.'/7 35·25 0·95 37·50 0·93 1.6 g). 80 1.10 31.36 1.06 33·92 1.01. 36.W! 1.02 39.~ 1.00 41.60 0.99

1.1 )l.45 1.15 34.34 1.12 37·23 1.09 1+0.12 1.cr{ 4).01 1·05 45.90 1.04 1.8 ~.m 1.21 31·" 1.17 i1C.68 1.15 4).92 1.1) 47.16 1.11 50·40 1.09 1·9 31·05 1.as 40.66 1.2,3 ".ra 1.20 47·88 1.18 51.lI.9 1.1.6 55·10 1.14

2.0 Ita. 00 1·32 ".00 1.26 48.00 1.25 52.00 1.23 56.00 1.21 60.00 1.20 2.5 $6·25 1.58 62.50 1·55 68.15 1.52 15·00 1."9 81.25 1.I~7 87.50 1.il5 ].0 15·00 1.85 811..00 1.81 93·00 1·77 102.00 1.75 lll.oo 1·73 120.00 1.71

Page 391: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-9. Hydraulic radius (R) and area (A) of nonsymmetrical trapezoidal channels (2-footbottom width)

C-22 Hydrologic and Hydraulic Tables and Curves

..... -2·

Depth d :) - }:I It'l-3'1

I (feet) R A R 1.0 At.OO 0.61 It.2S 0.61 1..1 4.62 0.66 It.92 0.66 1.2 5.28 0.70 5.64 0.71

I .. ) 5.98 0.75 6.40 0.76 1.4 6.72 0.80 7.21 0.80 1.5 7.50 0.85 8.06 0.85

1.6 8.32 0.89 8.96 0.91 1.7 9.18 0.94 9.90 0.95 t.8 10.08 0.99 10.89 1.00

1.9 11.02 , .03 11.92 1.04 2.0 12.00 1.07 13.00 1.09 2.2 14.08 1.17 15.29 1.19

2.4 16.32 1.26 17.76 J.28 2.6 18.72 1.35 20.41 1.37 2.8 21.2.8 1.43 23.2'+ 1.'+6

3.0 24.00 1.52 26.25 1.5'+ 3.5 31.5.0 1.76 }It.57 1.78 4.0 !to.DO 1.97 44.00 2.00

A= t dZ(x+y) +2d

WP 11 d cvI'+;'! • ."ti'+xI')+ 2

R 11 A/WP

SIODe rj1tlo 2:1 - 3:1 Zt'l- 3'1 q!l-}:I

A R A R A R 4.50 O.bl 4.75 0.6~ 5.50 0.59 5.23 0.66 5.53 0.66 6.44 0.64 6.00 . 0.71 6.36 0.70 7.44 0.68

6.83 0.76 7.25 0.75 8.52 0.73 7.70· 0.81 8.19 0.81 9.66 0.79 8.63 0.85 9.19 0.85 10.88 0.84

9.60 0.91 10.24 0.90 12.16 0.90 10.63 0.95 11.35 0.95 13.52 0.94 11.90 1.01 12.51 1.00 14.94 0.98

12.83 I.OS 13.73 I.OS 16.lt4 1.03 14.00 1.10 15.00 1.10 18.00 1.09 16.50 1.19 11.71 1.19 21.34 1.19

19.20 1.28 20.64 1.29 24.96 1.28 22.10 1.37 23.79 1.38 28.86 1.38 25.20 1.48 27.16 1.48 33..04 1.48

28.50 1.57 )0.75 1.57 37.50 1.57 37.63 1.80 40.70 1.81 49.88 1.81 ltB.OO 2.02 52.00 2.03 64.00 2.04

5:1-3:1 A R 6.00 0.58 7.04 0.63 8.16 0.68

9.)6 0.74 10.64 0.79 12.00 0.84

13.44 0.88 . 14.96 0.93 16.56 0.98

18.24 1.03 20.00 1.08 2).76 1.18

27.84 1.27 32.2'+ 1.37 36.76 1.48

42.00 1.57 56.01 1.81 72.00 2.04

Page 392: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table C-10. Hydraulic radius (R) and area (A) of nonsymmetrical trapezoidal channels (4-footbottom width)

Hydrologic and Hydraulic Tables and Curves C-23

Depth, d 1:1 - 3:1 It:l- 3:1

. (fe~t) A R A R 1.0 b.OO 0.70 6.25 0.69 1.1 6.82 0.75 7.12 0.75 1.2 7.68 0.80 8.04 0.80

1.3 8.58 0.86 9.00 0.86 1.4 9.52 0.91 10.01 0.91 1.5 10.50 0.97 11.06 0~97

1.6 11.52 1.02 12.16 1.02 1.7 12.58 1.06 13.30 1.07 1.8 13.38 1.10 14.49 1.12

1.9 14.82 1.17 15.72 1.17 2.0 16.00 1.21 17.00 1.22 2.2 18.48 1. 31 19.69 1.32

2.4 21.12 1.41 22.56 1.42 2,6 23.92 1.51 25.61 1.51 2.8 26.88 1.60 28.84 1.61

3.0 30.00 1.69 32.25 1.71 3.5 38.50 1.93 41.57 1.94 4.0 48.00 2.15 52.00 2. I 7

A= td2(x+y) +2d

wp= dcVi"+7+~)+-4 R = A/WP

Slo~_e ratio 2: 1 -3:1 2,:1 3,1 4: 1-3: 1

A R A R A R 6.50 0.69 G.75 O.b!i 7.50 0.66 7.43 0.75 7.73 0.74 8.64 0.72 8.40 0.81 8.76 0.79 9.84 0.78

9.43 0.85 9 .. 85 0.85 11.12 0.81 10.59 0.92 10.99 0.90 12.46 0.88 11.63 0.96 12.19 0.95 13.88 0.93

12.80 1.01 13.44 1.00 15.36 0.98 14.03 1.07 14.75 1.06 16.92 1.04 15.50 1.13 16.11 1.11 18.54 1.08

16.63 1.17 17.53 1.12 20.24 1.13 18.00 1.22 19.00 1.21 22.00 1.18 20.90 1.32 22.11 1. 31 25.74 1.29

24.00 1.41 25.44 1.41 '29.76 I.>a 27.30 1.51 28.99 1.51 34.06 1.49 30.80 1.62 32.76 1.61 38.64 1.59

1.71 36.75 I

34;50 1.71 43.50 1.68 44.63 1.95 47.70 1.95 56.a8 1.93 56.00 2. la 60.00 2.18 72 .00 2.16

5 :1-3:1 A R 8.00 0.65 9.74 0.70

10.56 0.76

11.96 0.81 13.44 0.a7 15.00 0.92

16.64 0.96 la.36 1.01 20.16 1.07

22.04 1.12 ~4.00 1.17 28.16 1.28

32.64 1.37 37.44 1.47 42.36 1.~7

48.00 1.66 63.07 1.92 80.00 2.15

Page 393: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX D

CONE INDEX REQUIREMENTS

Fine-Grained Soils

Tracked Vehicles

VehicleWeight

Vehicle Description (kips)

Amphibious vehicles

Carrier, cargo, amphibious, 10.9tracked, M116

Landing vehicle, tracked, 97.5command, M5(LVTP5A1(CMD))

Landing vehicle, tracked, 87.8personnel, M5 (LVTP5A1)

7

20

19

18

49

45

Armored bulldozers

Bulldozer, earthmoving tank, 116.0 23 53tank-mtd, M9 (tank, combat,105-mm gun, M60, and M60A1)

Tractor, armored, combat 35.6 18 41earthmover (ACE), M9

NOTES:

1. Items listed include selected self-propelled vehicles as of January 1993. Certainitems in final development or undergoing field testing have been included where thetype of classification is pending.

2. The VCIs have been calculated from the formulas, curves, and tables in NRMM. Thevehicle weight was based on normal design loads or combat weights, equipment, cross-country tire pressures, and crews as the conditions would be under full operationaldeployment in typical off-road movements. Trucks which could operate at lower tirepressures would generate slightly lower VCI values with increased tire deflection.

3. Amphibious vehicles and engineer tractors have grousers greater than 1 1/2 inches;all other tracked vehicles have grousers less than 1 1/2 inches.

4. One kip equals 1,000 pounds (US customary).

Cone Index Requirements D-1

Page 394: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Tracked Vehicles (continued)

VehicleWeight

Vehicle Description (kips)

Combat vehicles

Armored reconnaissanceairborne assault vehicle(General Sheridan), M551

Howitzer, heavy, self-propelled, full- tracked,8-in, M55 (T108)

Howitzer, heavy, self-propelled, 8-in, M110(T236E1)

Howitzer, medium, self-propelled, 155-mm, M109(T196E1)

Howitzer, light, self-propelled,full-tracked, 105-mm, M37

Howitzer, light, self-propelled,full-tracked, 105-mm,

M52M52A1

Howitzer, light, self-propelled,105-mm, M108

LAV-25, 8x8, light, armoredvehicle

Mortar, infantry, self-propelled, full-tracked,107-mm (4.2-in), M84

Tank, combat, full-tracked,90-mm gun,

M48M48CM48A1M48A2M48A2CM48A3 (M48A1E2)M48A5

Tank, combat, full-tracked,105-mm gun,

M60M60A1M60A3

35.8

98.0

58.5

53.2

46.0

53.053.046.9

27.7

47.1

99.099.0

104.0105.0105.0104.0106.0

110.0116.0110.0

15

20

20

25

N/A

N/AN/AN/A

32

N/A

20202121212122

212220

35

47

47

57

58

464654

72

46

47474949494950

485146

D-2 Cone Index Requirements

Page 395: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Tracked Vehicles (continued)

VehicleWeight

Vehicle Description (kips)

Combat vehicles continued

Tank, combat, full-tracked,120-mm gun,

M lM1A1M 1A2

Vehicle, combat engineer,full-tracked, 165-mm gun,M729 (basic M60A1 tank)

A r m o r e d v e h i c l e b r i d g e s

Launcher, M48 tank chassis,transporting

Launcher, M48 tank chassis,transporting, with bridge,armored vehicle launched,scissoring type, class 60,60-ft

Launcher, M60A1 chassis,transporting

Launcher, M60A1 chassis,transporting with bridge,armored vehicle launched,scissoring type, class 60,60-ft

Carriers

Carrier, cargo, tracked,6-on, M548

Carrier, command post, light,tracked,

M577M577A1

Carrier, personnel, full-tracked, armored,

M113M113A1M113A2M113A3

115.0 23125.0 25140.0 28115.0 N/A

96.0

128.0

86.3

115.9

28.0

23.924.4

22.623.423.423.6

N/A

N/A

15

22

N/A

1717

N/AN/AN/AN/A

54586454

49

65

36

51

37

4040

48494949

Cone Index Requirements D-3

Page 396: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Tracked Vehicles (continued)

VehicleWeight

Vehicle Description (kips)

Carriers (continued)

Infantry fightingM2A1M2A2

Multiple Launch

Recovery vehicles

Recovery vehicle,

vehicle,

Rocket System

full-

Trucks

tracked, medium, M88Recovery vehicle, full-

tracked, light, armored,M578

Wheeled Vehicles

Truck, utility, 1/4-ton,4x4, M151

Truck, utility, 1 1/4-ton,4x4 M998 (HMMWV)

Truck, cargo, 1 1/4-ton,6x6, M561

Truck, cargo, 1 3/4-ton,4x4, M 1028 commercialcargo vehicle (CUCV)

Truck, cargo, 2 1/2-ton,6x6, M34

Truck, cargo, 2 1/2-ton,6x6, M35A 1

Truck, cargo, 5-ton, 6x6M923

Truck, cargo, 8-ton, 4x4M520

Truck, cargo, 10-ton, 6x6M125M125A1

Truck, cargo, 10-ton, 8x8M977

Truck, cargo, 5-ton, 6x6M 1084

utility

50.266.054,2

112.0

54.0

3.1

7.5

9.6

9.3

17.2

19.2

32.5

43.4

49.549.560.4

35.8

151615

21

21

19

20

19

31

27

26

30

43

373736

25

353735

50

49

44

47

44

70

61

59

68

97

848479

57

D-4 Cone Index Requirements

Page 397: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Wheeled Vehicles (continued)

VehicleWeigh t

Vehicle Description (kips)

Trucks (continued)

Truck, cargo, 24x4, M1078

Truck, dump, 26x6, M47

l/2-ton, 21.8 25 57

1 /2-ton, 19.2 28 64

Truck, dump, 5-ton, 6x6,M51M51A2M929

Truck, tractor, 5-ton, 6x6M52 (w/o payload)M52A1 (w/o payload)

Truck, tractor, 10-ton, 6x6M123 (w/o payload)M123C (w/o payload)M123D (w/o payload)

Truck, van, expansible,2 1/2-ton, 6x6, M292

Truck, van, shop, 2 1/2-ton, 6x6, M109A1

Truck, van, shop, 2 1/2-ton, 6x6, M220

Truck, wrecker, crane,2 1/2-ton, 6x6, M108

Truck, tractor, wrecker,medium, 5-ton, 6x6, M246(w/ payload)

Truck, wrecker, medium,5-ton, 6x6, M543

Palletized Loading System,10 x 10

32.732.732.7

17.817.8

28.930.230.225.1

21.0

20.4

19.8

44.8

34.4

86.6

323230

2121

212222

N/A

N/A

N/A

N/A

32

N/A

34

727268

4848

48505076

65

62

63

73

76

77

Cone Index Requirements D-5

Page 398: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX E

SOIL-TRAFFICABILITY TEST SET

Trafficability measurements are made withthe soil-trafficability test set. This set con-sists of one canvas carrying case, one conepenetrometer with 3/8-inch steel and 5/8-inch aluminum shafts and a 0.5-square-inch cone, one soil sampler, remoldingequipment (which includes a 3/8-inch steelshaft and a 0.2-square-inch cone, a 5/8-inch steel shaft with foot and handle, a 21/2-pound hammer, and a cylinder andbase with pin), and a bag of hand tools(which includes one combination spannerwrench and 1 /4-inch screwdriver; two open-end wrenches, 1/2 by 9/16; one 6-inchStillson wrench; one 3/16-inch Allenwrench; and one 2-inch screwdriver with a1/8-inch bit). The items are shown in their

proper places in the carrying case in FigureE-1, SC-6635-98-CL-E02-HR gives com-ponent listings and stock numbers.

CONE PENETROMETER

The cone penetrometer is shown in FigureE-2, page E-2. It consists of a 30-degreecone with a 1/2-inch-square base area, asteel shaft 19 inches long and 3/8 inch indiameter, a proving ring, a micrometer dial,and a handle.

Use of the Cone PenetrometerInspect and adjust the cone penetrometerprior to use. Using an operator’s assistant

Figure E-1. Soil Trafficability test set

Soil Trafficability Test Set E-1

Page 399: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure E-2. Cone penetrometer

which measurements can be made andrecorded and usually diminishes thelikelihood of errors.

Inspection. Inspect the penetrometer beforeusing it to make sure that all nuts, bolts,and joints are tight and that the dial-gagestem contacts the proving-ring bearingblock.

Zeroing. Allow the penetrometer to hangvertically from its handle, and rotate thedial face until 0 is under the needle. Whenthe instrutment is kept vertical between thefingertips and allowed to rest on its cone,the dial will register about 2 to 4 pounds—the total weight of the instrument—or 4 to8 on the dial.

Operation. Operate the penetrometer as fol-lows:

1. Place one hand over the other on thehandle, palms down, and approximately atright angles as shown in Figure E-3. Thisminimizes eccentric loading of the provingring and helps keep the shaft vertical.

2. Apply force until slow, steady down-ward movement occurs.

3. Take a dial reading just as the base ofthe cone becomes flush with the ground sur-face. To do this, watch the cone descenduntil an instant before the cone base is ex-pected to be flush with the ground surface,then immediately shift the vision to the dialface. Continue the slow, steady, downwardmovement and take successive dial readings

Figure E-3. Using a cone penetrometer in theupright position

E-2 Soil Trafficability Test Set

Page 400: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

at appropriate 6-inch intervals to a depth of18 inches, If it is necessary to stop thedownward progression of the conepenetrometer for any reason, progress maybe resumed with no adverse effects on thecone penetrometer readings. Progressionshould be stopped between depths so thatthe next reading is taken only afterdownward progression has resumed. For ex-ample, when only one person is on the traf-ficability reconnaissance, it may be con-venient to make two cone penetrometer read-ings, stop the penetration to record thereadings, resume the penetration to obtaintwo additional readings, then stop to record.

Precautions. Observe the following precau-tions when operating a penetrometer:

• Keep the instrument vertical.

• Do not attempt to take readings higherthan the capacity of the dial (300). Thismay overstress the proving ring.

• If dial capacity is exceeded at less than18 inches of penetration, make anotherpenetration nearby. The cone may bestriking an isolated rock fragment orother object.

• Withdraw the instrument by the shaft,never by the ring or the handle. Pullingthe handle may stretch the proving ring.

• Read the CI only at the proper depth. Ifreadings are made as little as 1/4 inchfrom the proper depth and recorded asbeing at the proper depth, an average ofsuch readings will not accurately reflectthe average strength. Carelessness inmaking proper depth determinations isprobably the greatest source of error inusing the penetrometer.

Training Penetrometer Operators

Train operators in areas that have uniformsoil conditions. The instructor should takeapproximately 50 sets of readings equallyspaced over the area. The average CI for 6-inch layers should be computed and usedas standards or references. The traineeshould be instructed in all proper techni-

ques of operation. He should practicepenetration, observed by a qualified instruc-tor, until he becomes familiar with the tech-niques of operation. The trainee shouldthen make 50 sets of readings, using an as-sistant to record them. The average CIs ob-tained by a trainee should be compared tothe standard. If the trainee’s readingsdeviate widely, the causes for the deviationsshould be sought and corrected.

In a uniform area, a 5-percent deviation iswide. The most probable cause of error iscarelessness in determining the properdepth. The rate of progression recom-mended is such that four readings (surface,6, 12, and 18 inches) can be measured in15 seconds during a continuous penetrationin soft soil. Slower or faster penetrationrates will reflect lower or higher values,respectively, but the discrepancies will notbe large. The CI is also insignificantly af-fected by the variation in the rate ofpenetration for the same operator or be-tween experienced operators. However, ifdeviations persist, check the possibility ofcone-penetrometer mechanical imperfec-tions, Inspect the dial face to ensure thatits position has not shifted around thedial’s shaft and that the needle is not stick-ing or has not slipped on its shaft. Any ofthese conditions could cause an improperzero setting. Secondly, inspect the provingring. A damaged or overstressed ring mightrequire recalibration. Finally, check to en-sure the Instrument was properly zeroed.The micrometer dial stem may not havebeen in good contact with the proving-ringbearing block when the instrument waszeroed.

Care and Adjustment of the Penetrometer

Keep the penetrometer free from dirt andrust and keep all parts tight. Frequentlycheck the instrument and rezero, if neces-sary. Ensure no grit is caught between thestem of the dial and the lower mountingblock.

Dial Care. The micrometer dial is a sensi-tive instrument that should be protectedagainst water and rough use. Never im-merse it in water, and wipe it dry as soon

Soil Trafficability Test Set E-3

Page 401: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

as possible after use in rainy weather.When the dial is transported by truck, wrapit in paper or cloth.

Bearing-Block Adjustment. If either or bothbearing blocks become loosened and moved,adjust them so that they lie on the samediameter of the ring. Retighten them andrecalibrate the proving ring. Do notcalibrate while on reconnaissance. Instead,note all readings made in the field afterbearing blocks have been removed and cor-rect them according to the calibration madelater.

Cone Replacement. Considerable use of thesame cone may result in a rounding of itspoint, but it will not affect the accuracy ofthe instrument, However, if the base of thecone has had excessive wear or is deformedby hard use, replace the cone.

Proving-Ring Recalibration. The calibrationwill remain true for the life of the instru-ment unless the bearing blocks are movedor the ring is overstressed (deformed by ahard knock or subjected to extreme chan-ges in temperature or other unusualstrains). If the ring needs recalibration,complete the following steps:

1. Remove the handle and shaft,

2. Place the lower mounting block of thering assembly on a smooth, horizontal sur-face.

3. Check the bearing-block alignment andtightness. Both blocks should be on thesame diameter of the ring. Use a draftingtriangle or a carpenter’s square for thisoperation. The bolts should be snug.

4. Ensure that the stem of the dial bearsfirmly on the lower bearing block. Ensurethat the dial arm has sufficient travel avail-able for the full range of motion (ap-proximately 1/10-inch deflection) of theproving ring. The dial can be moved up ordown by adjusting the two nuts on thethreaded stud that holds the gage in posi-tion. Both nuts should be tight when infinal position.

5. Zero the dial by rotating its face so that0 is under the needle.

6. Add the load in 10-pound incrementsup to 150 pounds. Mark or note theneedle’s position on the dial after the addi-tion of each load increment. Any of the fol-lowing loading methods may be used:

• Add deadweights to the top of the ringassembly. If a plate is used to hold theweights, its weight should be con-sidered in the first 10-pound load.

Ž Use any of the load machines commonlyused in laboratory work to apply theload.

Ž Place the ring assembly on a set of plat-form scales. Apply the load incrementswith a jack and measure them with theplatform scales.

7. Remove the load in 10-pound incre-ments, noting the position of the needleafter the removal of each increment.

8. Make the load run at least twice, usingthe average of the needle position for eachincrement as the final point.

9. Expect some variation in needle posi-tion; it will not be significant.

10. Establish 10-pound intervals on thedial face and mark them 20, 30, 40, so on,to 300. Each interval should be subdividedseparately because the arcs for various 10-pound intervals are not necessarily thesame.

NOTE: If the instrument cannot becalibrated or the proving ring is severelydamaged, the instrument will need to beturned in for repair.

SOIL SAMPLER

A piston-type soil sampler, as shown in Fig-ure E-4, is used to extract soil samples forremolding tests.

E-4 Soil Trafficability Test Set

Page 402: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure E-4. Soil sampler and sampling cylinder

Operation

The soil sampler is used in the followingway:

1. Loosen the knurled handle of the soilsampler so the piston rod will move freely.Hold the sampler firmly in both hands andforce it into the soil vertically (Figure E-5).Do not twist the sampler while pushing itinto the soil. Sometimes two people areneeded to force the sampler into firm soils.

2. After locking the piston rod by turningthe knurled handle, twist the sampler slight-ly and withdraw.

3. Deposit the sample directly into theremolding cylinder.

Figure E-6, page E-6,for using the sampler

shows the techniquein a prone position.

Figure E-5.

Care

Operating the sampler in theupright position

to keep the inside of the sam-It is essentialpling tube, the piston ring, and the leatherwasher clean. After 5 to 25 samplings,

depending upon the type of soil, completethe following cleaning procedures:

1. Immerse the tube first in water andthen in fuel oil. Work the piston up anddown five or six times in each liquid.

2. Wipe off the excess fuel oil, and squirtlight machine oil into the tube.

3. If the sampler becomes stiff and hard towork, remove the tube, disassemble andthoroughly clean the piston, and oil theleather washer. Tube walls and cuttingedges are soft and should be handled with

Soil Trafficability Test Set E-5

Page 403: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure E-6. Using the sampler in a proneposition

care. The cutting edges will require shar-pening from time to time.

Adjustment

Adjust the piston-rod length to keep theface of the piston flush with the cuttingedge of the tube when the piston-rod hand-le (disk) is fully depressed. To do this,loosen the setscrew on the handle, screwthe handle up or down to the correct posi-tion, and retighten the setscrew.

Remolding test

The equipment for the remolding test,shown in detail in Figure E-7 and in use inFigures E-8 through E-11, pages E-7through E-9, consists of the following:

Figure E-7. Remolding test equipment

Ž A steel cylinder approximately 2 inchesin diameter and 8 inches long, mountedon an aluminum base.

• A 2 1/2-pound steel drop hammer slid-ing on an 18-inch steel shaft with ahandle.

Ž A cone penetrometer

A cone penetrometer may be equipped withan aluminum shaft (5/8-inch in diameter)or a steel shaft (3/8-inch in diameter) witha 0.5-square-inch cone (for fine-grainedsoils) or a more slender steel shaft with a0.2-square-inch cone (for remoldablesands). The penetrometer is used tomeasure soil strength in the cylinder beforeand after remolding. The sampler (Figure

E-6 Soil Trafficability Test Set

Page 404: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure E-8. Operating the remolding testequipment to obtain a soil sample

E-4, page E-5) is used to obtain the soilsample from the critical layer and place itin the remolding cylinder.

Test Procedure for Fine-Grained Soils

The following remolding test is performedfor fine-grained soils:

1. Take a sample from the critical layerwith the sampler as shown in Figure E-8,eject it directly into the remolding cylinderas shown in Figure E-9, page E-8, and

push it to the bottom of thethe foot of the drop-hammer

2. Measure the strength

cylinder withshaft.

with thepenetrometer (steel shaft) by taking CI read-ings as the base of the cone enters the sur-face of the soil sample and at each succes-sive inch, to a depth of 4 inches, as shownin Figure E-10, page E-9,

3. Apply 100 blows with the drop hammerfalling 12 inches as shown in Figure E-11,page E-9.

4. Measure the remolded strength fromthe surface to the 4-inch depth at 1 -inch in-crements, as was done before remolding asshown in Figure E-10.

NOTE: Some samples are so hard theycannot be penetrated the full 4 inches.In such cases, the full dial capacity (300)is recorded for each inch below the lastreading obtained.

To find the remolding index, take the sumof the five CI readings after remolding anddivide by the sum of the five readingsbefore remolding.

Test Procedure for Remoldable Sands

The test procedure for remoldable sands isgenerally the same as that for fine-grainedsoils. However, the CI measurements aremade with the slender shaft and 0.2-square-inch cone, and the sample is remolded byplacing a rubber stopper in the top of theremolding tube and dropping it (along withthe cylinder and base) 25 times from aheight of 6 inches onto a firm surface, suchas a piece of timber. Some remoldablesands with a large amount of fines (morethan 12 but less than 50 percent) reactvery much like fine-grained soil, When test-ing a remoldable sand with a large amountof fines, run both the fine grains and remol-dable sands tests, and use the lower remold-ing index. Continue to use the more criti-cal test throughout the area.

Soil Trafficability Test Set E-7

Page 405: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure E-9. Operating test equipment to load the cylinder

E-8 Soil Trafficability Test Set

Page 406: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure E-10. Measuring cone index in a remolding cylinder

Figure E-11. Applying hammer blows with remolding equipment

Soil Trafficability Test Set E-9

Page 407: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX F

CURVE TABLES

FUNCTIONS OF A1-DEGREE CURVE

The long chords (C), middle ordinates (M),externals (E), and tangent distances (T) inTable F-1, pages F-2 through F-30, are fora 1-degree curve, based on the arc defini-tion (5,729.578-foot radius). To find thecorresponding functions of any other curve,divide the tabular values by the degree ofcurvature.

CORRECTIONS FOR TANGENTS ANDDISTANCES

Complete the following steps to determinethe degree of curvature for all curves otherthan the 1-degree curve:

1. Determine the value corresponding tothe given intersection angle from Table F-1.

2. Divide this value by the given degree ofcurvature.

3. Add the correction derived from TableF-2, pages F-30 and F-31.

Curve Tables F-1

Page 408: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve

F-2 Curve Tables

C,• Long M,• Middle E,• External T,• Tangent Degrees Minutes Chord Ordinate Distance Distance

0 0 0.000 0.0000 0.0000 0.0000

;0 16.666 0.0060 0.0060 8.3333

20 33.333 0.0242 0.0242 16.6667

30 49.999 0.0545 0.0545 25.0001

40 66.666 0.0969 0:0969 33.3337

50 83.332 0.1515 0.1515 41.6674

1 0 99.998 0.2181 0.2181 50.0012

10 116.664 0.2969 0.2969 58.3353

20 133.330 0.3878 0.3878 66.6696

30 149.995 0.4908 0.4908 75.0042

40 166.660 0.6060 0.6060 83.3392

50 183.325 0.7332 0.7333 91.6744

2 0 199.989 0.8726 0.8727 100.0101

iO "'04 ~ ~tr:." .. IV"A" .. 1\I').A1l 1 nil ':IA~I) c;.IO.O;h) I.Vc;.~1 I.U'''''''' IVU.~UL.

20 233.317 1.1877 1.1879 116.6827

30 249.980 1.3634 1.3638 125.0198

40 266.642 1.5513 1.5517 133.3574

50 283.304 1.7513 1.7518 141.6955

3 0 299,965 1.9633 1.9640 150.0342

10 316.626 2.1875 2.1884 158.3736

20 333.286 2.4238 2.4249 166.7136

30 349.945 2.6723 2.6735 175.0544

40 366.604 2.9328 2.9343 183.3959

50 383.261 3.2055 3.2073 191.7381

4 0 399.918 3.4903 3.4924 200.0812

in A-4t:. J:7A '1 71171 3.7896 208.4251 IV ...,.IU.""''''' ...,.IU' ,

20 433.230 4.0961 4.0991 216.7700

30 449.884 4.4172 4.4207 225.1157

40 466.537 4.7505 4.7544 233.4624

I I 50 I 483.190 I 5. 0958 1 5.1003 1 241.8100 11

Page 409: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-3

C" Long M,. Middle E,. External T,o Tangent Degrees Minutes Chord Ordinate Distance Distance

5 0 499.841 5.4532 5.4584 250.1587

10 516.491 5.8228 5.8287 258.5085

20 533.140 6.2044 6.2112 266.8593

30 549.788 6.5982 6.6058 275.2113

40 566.435 7.0041 7.0127 283.5645

50 583.081 7.4221 7.4317 291.9188

6 0 599.725 7.8521 7.8629 300.2744

10 616.369 8.2943 8.3063 308.6313

20 633.010 8.7486 8.7620 316.9894

30 649.651 9.2150 9.2298 325.3490

40 666.290 9.6935 9.7099 333.7099

50 682.928 10.1841 10.2022 342.0722

7 0 699.564 10.6868 10.7067 350.4360

10 716.199 11.2016 11.2235 358.8012

20 732.832 11.7284 11.7525 367.1680

30 749.464 12.2674 12.2937 375.5363

40 766.094 12.8185 12.8472 383.9063

50 782.723 13.3817 13.4130 392.2778

8 0 799.350 13.9569 13.9910 400.6511

10 815.975 14.5443 14.5813 409.0260

20 832.599 15.1437 15.1838 417.4027

30 849.220 15.7552 15.7987 425.7811

40 865.840 16.3788 16.4258 434.1614

50 882.458 17.0145 17.0652 442.5435

9 0 899.075 17.6623 17.7169 450.9275

10 915.689 18.3222 18.3810 459.3134

20 932.301 18.9941 19.0573 467.7013

30 948.912 19.6782 19.7460 476.0912

40 965.520 20.3743 20.4470 484.4831

50 982.126 21.0825 21.1603 492.8770

Page 410: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-4 Curve Tables

Cl. Long Ml• Middle El. External Tl• Tangent Degrees Minutes Chord Ordinate Distance Distance

10 0 998.731 21.8027 21.8860 501.2731

10 1,015.333 22.5351 22.6240 509.6713

20 1,031.933 23.2795 23.3744 518.0716

30 1,048.531 24.0359 24.1372 526.4742

40 1,065.126 24.8045 24.9123 534.8790

50 1,081.720 25.5851 25.6999 543.2861

11 0 1,098.311 26.3778 26.4998 551.6956

10 1,114.900 27.1825 27.3121 560.1073

20 1,131.486 27.9993 28.1368 568.5215

30 1,148.070 28.8282 28.9740 576.9381

40 1,164.652 29.6691 29.8236 585.3572

50 1,181.231 30.5221 30.6856 593.7788

12 0 1,197.807 31.3872 31.5601 602.2029

10 1,214.382 32.2643 32.4470 610.6295

20 1,230.953 33.1534 33.3464 619.0588

30 1,247.522 34.0546 34.2582 627.4908

40 1,264.088 34.9679 35.1826 635.9254

50 1,280.652 35.8932 36.1194 644.3628

13 0 1,297.213 36.8305 37.0688 652.8029

10 1,313.771 37.7799 38.0307 661.2458

20 1,330.326 38.7413 39.0050 669.6916

30 1,346.879 39.7148 39.9920 678.1402

40 1,363.429 40.7003 40.9914 686.5917

50 1,379.975 41.6978 42.0035 695.0462

14 0 1,396.519 42.7074 43.0281 703.5037

10 1,413.060 43.7289 44.0653 711.9642

20 1,429.598 44.7626 45.1150 720.4277

30 1,446.133 45.8082 46.1774 728.8943

40 1,462.665 46.8659 47.2524 737.3641

50 1,479.194 47.9356 48.3400 745.8371

Page 411: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-5

· " ...... ' .':' ....... : . .;:':.::':.:.;.':-:;.':-::-::::::-::::';::;.,::-: .. :.

Cl' Long M1• Middle El' External T1• Tangent Degrees Minutes Chord Ordinate Distance Distance

15 0 1,495.719 49.0173 49.4403 754.3132

10 1,512.242 50.1110 50.5532 762.7926

20 1,528.761 51.2168 51.6787 771.2753

30 1,545.277 52.3345 52.8169 779.7613

40 1,561.790 53.4643 53.9679 788.2507

50 1,578.300 54.6060 55.1315 796.7434

16 0 1,594.806 55.7598 56.3078 805.2396

10 1,611.309 56.9256 57.4968 813.7393

20 1,627.808 58.1034 58.6986 822.2425

30 1,644.304 59.2931 59.9132 830.7492

40 1,660.796 60.4949 61.1404 839.2595

50 1,677.285 61.7087 62.3805 847.7735

17 0 1,693.771 62.9344 63.6334 856.2911

10 1,710.252 64.1722 64.8990 864.8124

20 1,726.731 65.4219 66.1775 873.3375

30 1,743.205 66.6836 67.4688 881.8663

40 1,759.676 67.9573 68.7730 890.3990

50 1,776.143 69.2429 70.0900 898.9355

18 0 1,792.606 70.5406 71.4199 907.4760

10 1,809.066 71.8502 72.7626 916.0203

20 1,825.522 73.1717 74.1183 924.5686

30 1,841.974 74.5053 75.4869 933.1210

40 1,858.422 75.8508 76.8684 941.6774

50 1,874.866 77.2082 78.2629 950.2379

19 0 1,891.306 78.5777 79.6703 958.8025

10 1,907.742 79.9590 81.0907 967.3713

20 1,924.174 81.3524 82.5241 975.9443

30 1,940.602 82.7576 83.9705 984.5215

40 1,957.026 84.1749 85.4299 993.1030

50 1,973.445 85.6040 86.9024 1,001.6889

Page 412: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-6 Curve Tables

Cl' Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

20 0 1,989.861 87.0451 88.3879 1,010.2791

10 2,006.272 88.4981 89.8865 1,018.8738

20 2,022.680 89.9631 91.3982 1,027.4729

30 2,039.082 91.4400 92.9230 1,036.0764

40 2,055.481 92.9288 94.4609 1,044.6845

50 2,071.875 94.4296 96.0120 1,053.2972

21 0 2,088.265 95.9423 97.5762 1,061.9145

10 2,104.650 97.4669 99.1536 1,070.5364

20 2,121.031 99.0034 100.7441 1,079.1630

30 2,137.408 100.5518 102.3479 1,087.7943

40 2,153.779 102.1121 103.9649 1,096.4304

50 2,170.147 103.6843 105.5952 1,105.0713

22 0 2,186.510 105.2684 107.2387 1,113.7171

10 2,202.868 106.8645 108.8955 1,122.3677

20 2,219.221 108.4724 110.5656 1,131.0233

30 2,235.570 110.0922 112.2490 1,139.6839

40 2,251.914 111.7239 113.9458 1,148.3494

50 2,268.253 113.3675 115.6559 1,157.0201

23 0 2,284.588 115.0229 117.3793 1,165.6958

10 2,300.917 116.6903 119.1162 1,174.3766

20 2,317.242 118.3695 120.8665 1,183.0626

30 2,333.562 120.0605 122.6302 1,191.7539

40 2,349.877 121.7635 124.4074 1,200.4504

50 2,366.187 123.4783 126.1980 1,209.1522

24 0 2,382.492 125.2050 128.0021 1,217.8593

10 2,398.792 126.9435 129.8198 1,226.5719

20 2,415.087 128.6939 131.6509 1,235.2898

30 2,431.377 130.4561 133.4957 1,244.0133

40 2,447.661 132.2302 135.3539 1,252.7422

50 2,463.941 134.0161 137.2258 1,261.4767

Page 413: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-7

Ct• Long Mt' Middle Et' External Tt' Tangent Degrees Minutes Chord Ordinate Distance Distance

25 0 2,480.215 135.8138 139.1113 1,270.2168

10 2,496.484 137.6234 141.0105 1,278.9625

20 2,512.747 139.4448 142.9232 1,287.7140

30 2,529.006 141.2780 144.8497 1,296.4711

40 2,545.259 143.1231 146.7899 1,305.2340

50 2,561.507 144.9800 148.7438 1,314.0027

26 0 2,577.749 146.8487 150.7114 1,322.7773

10 2,593.985 148.7292 152.6928 1,331.5577

20 2,610.217 150.6215 154.6880 1,340.3441

30 2,626.443 152.5256 156.6970 1,349.1365

40 2,642.663 154.4415 158.7198 1,357.9349

50 2,658.877 156.3692 160.7565 1,366.7393

27 0 2,675.086 158.3086 162.8070 1,375.5499

10 2,691.290 160.2599 164.8715 1,384.3667

20 2,707.487 162.2230 166.9499 1,393.1896

30 2,723.679 164.1978 169.0422 1,402.0188

40 2,739.865 166.1844 171.1485 1,410.8542

50 2,756.046 168.1828 173.2688 1,419.6960

28 0 2,772.220 170.1929 175.4031 1,428.5442

10 2,788.389 172.2148 177.5515 1,437.3988

20 2,804.552 174.2484 179.7139 1,446.2598

30 2,820.708 176.2939 181.8905 1,455.1274

40 2,836.859 178.3510 184.0811 1,464.0015

50 2,853.004 180.4199 186.2859 1,472.8822

29 0 2,869.143 182.5005 188.5049 1,481.7696

10 2,885.276 184.5929 190.7380 1,490.6636

20 2,901.402 186.6970 192.9854 1,499.5644

30 2,917.523 188.8128 195.2470 1,508.4719

40 2,933.637 190.9404 197.5229 1,517.3863

50 2,949.745 193.0796 199.8131 1,526.3076

Page 414: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-8 Curve Tables

C10 Long M10 Middle E10 External T10 Tangent Degrees Minutes Chord Ordinate Distance Distance

30 0 ,965.847 195.2306 202.1176 1,535.2357

10 2,981.943 197.3933 204.4364 1,544.1709

20 2,998.032 199.5676 206.7697 1,553.1130

30 3,014.115 201.7537 209.1173 1,562.0622

40 3,030.192 203.9515 211.4794 1,571.0185

50 3,046.262 206.1610 213.8559 1,579.9819

31 0 3,062.326 208.3821 216.2469 1,588.9526

10 3,078.383 210.6149 218.6524 1,597.9304

20 3,094.434 212.8594 221.0725 1,606.9156

30 3,110.478 215.1156 223.5071 1,615.9081

40 3,126.516 217.3834 225.9564 1,624.9079

50 3,142.547 219.6629 228.4202 1,633.9152

32 0 3,158.571 221.9541 230.8987 1,642.9300

10 3,174.589 224.2569 233.3919 1,651.9523

20 3,190.600 226.5713 235.8998 1,660.9822

30 3,206.604 228.8974 238.4224 1,670.0196

40 3,222.601 231.2352 240.9598 1,679.0648

50 3,238.592 233.5845 243.5121 1,688.1177 11

33 0 3,254.576 235.9455 246.0791 1,697.1783

10 3,270.553 238.3181 248.6610 ',706.2467

20 3,286.522 240.7023 251.2578 ',715.323

30 3,302.485 243.0981 253.8695 1,724.4072

40 3,318.442 245.5056 256.4961 ',733.4994

50 3,334.391 247.9246 259.1378 I

',742.5995

34 0 3,350.332 250.3 261.7944 ' , ,751.7077

10 3,366.267 252.7975 I 264.4661 60.824'

20 3;'382.195 255.2513 267.1529 1,769.9485

30 3,398.116 257.7167 269.8548 1,779.0812

40 3,414.029 260.1937 272.5718 ',788.2221

50 3,429.935 262.6822 275.3040 ',797.3714

Page 415: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-9

., ... , ..... ' .... ':'.,':.:>:.:>.

C,. Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

35 0 3,445.834 265.1823 278.0514 1,806.5290

10 3,461.726 267.6940 280.8140 1,815.6949

20 3,477.610 270.2172 283.5919 1,824.8694

30 3,493.487 272.7519 286.3851 1,834.0523

40 3,509.357 275.2982 289.1936 1,843.2438

50 3,525.219 277.8561 292.0175 1,852.4439

36 0 3,541.073 280.4255 294.8568 1,861.6527

10 3,556.921 283.0064 297.7115 1,870.8702

20 3,572.760 285.5988 300.5817 1,880.0964

30 3,588.592 288.2027 303.4674 1,889.3314

40 3,604.417 290.8182 306.3686 1,898.5753

50 3,620.234 293.4451 309.2855 1,907.8281

37 0 3,636.043 296.0836 312.2179 1,917.0899

10 3,651.845 298.7335 315.1659 1,926.3607

20 3,667.638 301.3950 318.1297 1,935.6406

30 3,683.424 304.0679 321.1091 1,944.9296

40 3,699.203 306.7523 324.1043 1,954.2278

50 3,714.973 309.4482 327.1153 1,963.5352

38 0 3,730.736 312.1555 330.1421 1,972.8519

10 3,746.490 314.8743 333.1848 1,982.1779

20 3,762.237 317.6046 336.2434 1,991.5133

30 3,777.976 320.3463 339.3179 2,000.8582

40 3,793.707 323.0994 342.4083 2,010.2125

50 3,809.430 325.8640 345.5148 2,019.5764

39 0 3,825.144 328.6400 348.6373 2,028.9499

10 3,840.851 331.4274 351.7759 2,038.3331

20 3,856.550 334.2263 354.9306 2,047.7260

30 3,872.240 337.0366 358.1015 2,057.1287

40 3,887.922 339.8582 361.2886 2,066.5411

50 3,903.596 342.6913 364.4919 2,075.9635

Page 416: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-10 Curve Tables

Cl' L.ong Ml • Middle El' External Tl • Tangent Degrees Minutes Chord Ordinate Distance Distance

40 0 3,919.262 345.5358 367.7115 2,085.3958

iO 3,934.9i9 348.39i6 370.9474 2,094.838i

20 3,950.568 351.2589 374.1997 2,104.2904

30 3,966.209 354.1375 377.4683 2,113.7529

40 3,981.841 357.0275 380.7534 2,123.2255

50 3,997.465 359.9289 384.0550 2,132.7083

41 0 4,013.081 362.8416 387.3731 2,142.2014

10 4,028.687 365.7657 390.7077 2,151.7048

20 4,044.286 368.7011 394.0590 2,161.2186

30 4,059.876 371.6478 397.4268 2,170.7429

40 4,075.457 374.6059 400.8114 2,180.2776

50 4,091.030 377.5753 404.2127 2,189.8229

42 0 4,106.594 380.5561 407.6307 2,199.3789

10 4,122.149 383.5481 411.0656 2,208.9455

20 4,137.696 386.5515 414.5173 2,218.5228

30 4,153.234 389.5662 417.9859 2,228.1110

40 4,168.763 392.5921 421.4715 2,237.7100

50 4,184.283 395.6294 424.9740 2,247.3199

43 0 4,199.794 398.6779 428.4935 2,256.9407

10 4,215.297 401.7377 432.0302 2,266.5726

20 4,230.790 404.8088 435.5839 2,276.2156

30 4,246.275 407.8912 439.1548 2,285.8698

40 4,261.751 410.9848 442.7429 2,295.5351

50 4,277.217 414.0896 446.3482 2,305.2118

44 0 4,292.675 417.2057 449.9709 2,314.8997

10 4,308.123 420.3331 453.6109 2,324.5991

20 4,323.563 423.4716 457.2682 2,334.3099

30 4,338.993 426.6214 460.9430 2,344.0322

40 4,354.414 429.7825 464.6353 2,553.7661

50 4,369.826 432.9547 468.3451 2,363.5116

Page 417: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-11

C" Long M" Middle E" External T1, Tangent Degrees Minutes Chord Ordinate Distance Distance

45 0 4,385.229 436.1381 472.0725 2,373.2689

10 4,400.622 439.3327 475.8175 2,383.0379

20 4,416.006 442.5385 479.5802 2,392.8187

30 4,431.381 445.7556 483.3605 2,402.6114

40 4,446.746 448.9837 487.1587 2,412.4161

50 4,462.102 452.2231 490.9746 2,422.2328

46 0 4,477.448 455.4736 494.8085 2,432.0615

10 4,492.785 458.7353 498.6602 2,441.9024

20 4,508.113 462.0081 502.5299 2,451.7555

30 4,523.431 465.2920 506.4176 2,461.6209

40 4,538.739 468.5871 510.3234 2,471.4986

50 4,554.038 471.8934 514.2473 2,481.3888

47 0 4,569.327 475.2107 518.1893 2,491.2914

10 4,584.607 478.5392 522.1496 2,501.2065

20 4,599.877 481.8786 526.1281 2,511.1342

30 4,615.137 485.2294 530.1249 2,521.0746

40 4,630.387 488.5912 534.1401 2,531.0277

50 4,645.627 491.9641 538.1738 2,540.9936

48 0 4,660.858 495.3480 542.2259 2,550.9724

10 4,676.079 498.7430 546.2965 2,560.9641

20 4,691.290 502.1491 550.3857 2,570.9689

30 4,706.491 505.5662 554.4936 2,580.9866

40 4,721.682 508.9944 558.6201 2,591.0176

50 4,736.863 512.4336 562.7654 2,601.0617

49 0 4,752.034 515.8839 566.9295 2,611.1191

10 4,767.195 519.3452 571.1124 2,621.1898

20 4,782.346 522.8175 575.3143 2,631.2740

30 4,797.487 526.3008 579.5351 2,641.3716

40 4,812.617 529.7951 583.7749 2,651.4828

50 4,827.738 533.3005 588.0338 2,661.6076

Page 418: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-12 Curve Tables

Cl' Long Ml• Middle El' External Tl• Tangent Degrees Minutes Chord Ordinate Distance Distance

50 0 4,842.848 536.8168 592.3118 2,671.7460

10 4,857.948 540.3441 596.6090 2,681.8983

20 4,873.038 543.8824 600.9255 2,692.0644

30 4,888.117 547.4316 605.2612 2,702.2444

40 4,903.186 550.9919 609.6164 2,712.4383

50 4,918.245 554.5630 613.9909 2,722.6463

51 0 4,933.293 558.1452 618.3850 2,732.8685

10 4,948.331 561.7382 622.7985 2,743.1048

20 4,963.359 565.3422 627.2317 2,753.3554

30 4,978.375 568.9571 631.6845 2,763.6203

40 4,993.382 572.5830 636.1571 2,773.8996

50 5,008.378 576.2197 640.6494 2,784.1935

52 0 5,023.363 579.8674 645.1616 2,794.5019

10 5,038.337 583.5259 649.6936 2,804.8249

20 5,053.301 587.1953 654.2456 2,815.1626

30 5,068.255 590.8756 658.8177 2,825.5151

40 5,083.197 594.5668 663.4098 2,835.8825

50 5,098.129 598.2688 668.0221 2,846.2648

53 0 5,113.050 601.9817 672.6546 2,856.6622

10 5,127.960 605.7055 677.3074 2,867.0746

20 5,142.859 609.4400 681.9805 2,877.5022

30 5,157.748 613.1854 686.6740 2,887.9450

40 5,172.625 616.9417 691.3880 2,898.4032

50 5,187.492 620.7087 696.1225 2,908.8767

54 0 5,202.347 624.4866 700.8777 2,919.3658

10 5,217.192 628.2752 705.6535 2,929.8703

20 5,232.026 632.0747 710.4500 2,940.3906

30 5,246.848 635.8849 715.2673 2,950.9265

40 5,261.660 639.7059 720.1055 2,961.4783

50 5,276.460 643.5377 724.9646 2,972.0459

Page 419: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functlons of a 1-degree curve (continued)

Curve Tables F-13

Cl. Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

55 0 5,291.249 647.3802 729,8448 2,982,6295

10 5,306,027 651.2335 734.7459 2,993.2291

20 5,320.793 655.0975 739.6683 3,003.8448

30 5,335.549 658.9723 744.6118 3,014.4768

40 5,350.293 662.8577 749.5766 3,025.1250

50 5,365.026 666.7539 754.5628 3,035.7896

56 0 5,379.747 670.6608 759.5704 3,046.4706

10 5,394.457 674.5785 764.5995 3,057.1682

20 5,409.156 678.5068 769.6501 3,067.8824

30 5,423.843 682.4458 774.7224 3,078.6133

40 5,438.519 686.3954 779.8163 3,089.3609

50 5,453.183 690,3558 784,9321 3,100.1255

57 0 5,467.836 694.3268 790,0697 3,110.9070

10 5,482.477 698.3084 795,2292 3,121.7055

20 5,497.107 702.3007 800.4107 3,132.5212

30 5,511.725 706.3036 805.6143 3,143.3541

40 5,526.331 710.3172 810.8401 3,154.2043

50 5,540.926 714.3413 816.0880 3,165.0718

58 0 5,555.509 718.3761 821.3583 3,175.9569

10 5,570.080 722.4215 826.6509 3,186.8595

20 5,584.639 726.4775 831.9660 3,197.7798

30 5,599.187 730.5440 837.3036 3,208.7178

40 5,613.722 734.6212 842.6638 3,219.6737

50 5,628.246 738.7088 848.0467 3,230.6474

59 0 5,642.758 742.8071 853.4523 3,241.6392

10 5,657.258 746.9159 858.8808 3,252.6491

20 5,671.746 751.0352 864.3323 3,263.6772

30 5,686.222 755.1651 869.8067 3,274.7236

40 5,700.686 759.3055 875.3042 3,285.7883

50 5,715.138 763.4564 880.8248 3,296.8716

Page 420: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-14 Curve Tables

Cl. Long M1• Middle El. External T1• Tangent Degrees MInutes Chord Ordinate Distance Distance

60 0 5,729.578 767.6178 886.3688 3,307.9734

10 5,744.005 771.7898 891.9360 3,319.0938

20 5,758.421 775.9722 897.5266 3,330.2330

30 5,772.824 780.1650 903.1408 3,341.3911

40 5,787.215 784.3684 8.7785 3,352.5681

50 5,801.594 788.5822 914.4398 3,363.7641

61 0 5,815.961 792.8065 920.1249 3,374.9793

10 5,830.315 797.0412 925.8339 3,386.2137

20 5,844.657 931.5667 3,397.4675

30 5,858.987 805.5419 937.3236 3,408.7407

40 5,873.304 809.8079 943.1045 3,420.0334

50 5,887.609 814.0843 948.9096 3,431.3457

62 0 5,901.901 818.3710 954.7390 3,442.6777

10 5,916.181 822.6682 960.5927 3,454.0296

20 5,930.448 826.9758 966.4709 3,465.4014

30 5,944.703 831.2937 972.3736 3,476.7932

40 5,958.945 835.6220 978.3009 3,488.2052

50 5,973.175 839.9606 984.2529 3,499.6374

63 0 5,987.392 844.3096 990.2297 3,511.0899

10 6,001.596 848.6689 996.2314 3,522.5628

20 6,015.788 853.0386 1,002.2581 3,534.0563

30 6,029.967 857.4185 1,008.3099 3,545.5704

40 6,044.133 861.8088 1,014.3868 3,557.1053

50 6,058.286 866.2094 1,020.4890 3,568.6610

64 0 6,072.427 870.6202 ',026.6166 3,580.2376

10 6,086.555 875.0414 1,032.7696 3,581.8354

20 6,100.670 879.4728 1,038.9482 3,603.4543

30 6,114.771 883.9144 1,045.1524 3,615.0944

40 6,128.860 888.3663 1,051.3823 3,626.7560

50 6,142.936 892.8285 1,057.6381 3,638.4391

Page 421: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013.,Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-15

Cl' Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

65 0 6,157.000 897.3009 1,063.9198 3,650.1437

10 6,171.050 901.7835 1,070.2276 3,661.8701

20 6,185.086 906.2763 1,076.5615 3,673.6182

30 6,199.110 910.7793 1,082.9216 3,685.3884

40 6,213.121 915.2925 1,089.3081 3,697.1805

50 6,227.119 919.8159 1,095.7210 3,708.9948

66 0 6,241.103 924.3495 1,102.1604 3,720.8314

10 6,255.074 928.8933 1,108.6265 3,732.6904

20 6,269.032 933.4471 1,115.1194 3,744.5718

30 6,282.977 938.0112 1,121.6390 3,756.4759

40 6,296.909 942.5854 1,128.1857 3,768.4027

50 6,310.827 947.1697 1,134.7594 3,780.3523

67 0 6,324.732 951.7641 1,141.3602 3,792.3249

10 6,338.623 956.3686 1,147.9883 3,804.3206

20 6,352.501 960.9832 1,154.6438 3,816.3394

30 6,366.365 965.6080 1,161.3268 3,828.3816

40 6,380.217 970.2427 1,168.0374 3,840.4472

50 6,394.054 974.8876 1,174.7757 3,852.5363

68 0 6,407.878 979.5425 1,181.5418 3,864.6491

10 6,421.689 984.2075 1,188.3358 3,876.7857

20 6,435.486 988.8825 1,195.1578 3,888.9462

30 6,449.269 993.5675 1,202.0080 3,901.1308

40 6,463.039 998.2626 1,208.8865 3,913.3395

50 6,476.795 1,002.9676 1,215.7933 3,925.5724

69 0 6,490.537 1,007.6827 1,222.7286 3,937.8298

10 6,504.265 1,012.4077 1,229.6925 3,950.1117

20 6,517.980 1,017.1427 1,236.6852 3,962.4183

30 6,531.681 1,021.8877 1,243.7066 3,974.7496

40 6,545.369 1,026.6427 1,250.7570 3,987.1059

50 6,559.042 1,031.4076 1,257.8365 3,999.4872.

Page 422: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-16 Curve Tables

Cl' Long M,• Middle El' External T,• Tangent Degrees Minutes Chord Ordinate Distance Distance

70 0 6,572.701 1,036.1824 1,264.9452 4,011.8937

10 6,586.347 1,040.9672 1,272.0831 4,024.3254

20 6,599.979 1,045.7619 1,279.2505 4,036.7826

30 6,613.596 1,050.5665 1,286.4475 4,049.2653

40 6,627.200 1,055.3810 1,293.6741 4,061.7738

50 6,640.790 1,060.2053 1,300.9305 4,074.3080

71 0 6,654.365 1,065.0396 1,308.2168 4,086.8682

10 6,667.927 1,069.8837 1,315.5331 4,099.4545

20 6,681.474 1,074.7377 1,322.8797 4,112.0670

30 6,695.008 1,079.6015 1,330.2565 4,124.7059

40 6,708.527 1,084.4752 1,337.6637 4,137.3713

50 6,722.032 1,089.3587 1,345.1014 4,150.0633

72 0 6,735.522 1,094.2520 1,352.5698 4,162.7820

10 6,748.999 1,099.1551 1,360.0691 4,175.5277

20 6,762.461 1,104.0680 1,367.5992 4,188.3004

30 6,775.909 1,108.9907 1,375.1604 4,201.1004

40 6,789.343 1,113.9232 1,382.7528 4,213.9276

50 6,802.762 1,118.8654 1,390.3765 4,226.7823

73 0 6,816.167 1,123.8174 1,398.0317 4,239.6646

10 6,829.557 1,128.7791 1,405.7185 4,252.5747

20 6,842.933 1,133.7506 1,413.4370 4,265.5127

30 6,856.294 1,138.7317 1,421.1873 4,278.4788

40 6,869.641 1,143.7226 1,428.9696 4,291.4730

50 6,882.974 1,148.7232 1,436.7841 4,304.4956

74 0 6,896.292 1,153.7335 1,444.6309 4,317.5467

10 6,906.595 1,158.7535 1,452.5100 4,330.6264

20 6,922.884 1,163.7831 1,460.4217 4,343.7349

30 6,936.158 1,168.8224 1,468.3662 4,356.8723

40 6,949.417 1,173.8713 1,476.3434 4,370.0388

50 6,962.662 ','78.9299 1,484.3536 4,383.2346

Page 423: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-17

Cl. Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

75 0 6,975.892 1,183.9981 1,492.3970 4,396.4598

iD 6,989.107 1,189.0759 1,500.4736 4,409.7145

20 7,002.307 1,194.1633 1,508.5836 4,422.9989

30 7,015.493 1,199.2604 1,516.7272 4,436.3132

40 7,028.664 1,204.3670 1,524.9045 4,449.6576

50 7,041.819 1,209.4831 1,533.1156 4,463.0321

7t:. n ? n&:'A n.t!'n .. I'H A c-nan 0(1 I:. A .. ~COI'\O A A"'~ .. ""L'n IU U ',U;..J41o,,,,UV I.£I ..... OUO"" 1,;;J<tI.~VO "+,"+{O.""O~

10 7,068.086 1,219.7442 1,549.6401 4,489.8722

20 7,081.198 1,224.8890 1,557.9537 4,503.3382

30 7,094.294 1,230.0433 1,566.3018 4,516.8350

40 7,107.375 1,235.2072 1,574.6845 4,530.3628

50 7,120.441 1,240.3806 1,583.1020 4,543.9218

77 0 7,133.492 1,245.5635 1,591.5544 4,557.5121

10 7,146.528 1,250.7558 1,600.0419 4,571.1338

20 7,159.549 1,255.9577 1,608.5647 4,584.7872

30 7,172.554 1,261.1690 1,617.1228 4,598.4725

40 7,185.545 1,266.3897 1,625.7165 4,612.1897

50 7,198.520 1,271.6199 1,634.3459 4,625.9390

78 0 7,211.480 1,276.8595 1,643.0113 4,639.7207

10 7,224.425 1,282.1086 1,651.7126 4,653.5349

20 7,237.354 1,287.3670 1,660.4502 4,667.3818

30 7,250.269 1,292.6349 1,669.2242 4,681.2615

40 7,263.167 1,297.9121 1,678.0347 4,695.1743

.,,, ..,. n..,. ..... n.~ .. i ,303. i987 i,686.88i9 4,709. i202 ;;JV {,£{O.V;;J I

79 0 7,288.919 1,308.4947 1,695.7660 4,723.0996

10 7,301.772 1,313.8000 1,704.6072 4,737.1125

20 7,314.609 1,319.1147 1,713.6455 4,751.1591

30 7,327.431 1,324.4387 1,722.6413 4,765.2397

40 7 -:u.n 'Y-l7 1 -:I.,Q 77.,n 1 7-:11 t:.7A7 .It 770 'lI::.A"l , .V"T"'.~.." ,,v,,,,,, ''"V I,IVI,V''''' """t:I.vv",o,J

50 7,353.028 1 ,335.1146 1,740.7458 4,793.5033

Page 424: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-18 Curve Tables

· ,.-:.:.<:; ... :;.': .. ;..' ............ .

Ct• Long Mt' Middle Et' External Tt' Tangent Degrees Minutes Chord Ordinate Distance Distance

80 0 7,365.803 1,340.4666 1,749.8548 4,807.6867

10 7,378.563 1,345.8278 1,759.0020 4,821.9048

20 7,391.307 1,351.1982 1,768.1874 4,836.1578

30 7,404.035 1,356.5780 1,777.4113 4,850.4458

40 7,416.748 1,361.9670 1,786.6738 4,864.7690

50 7,429.445 1,367.3652 1,795.9751 4,879.1276

81 0 7,442.126 1,372.7727 1,865.3155 4,893.5219

10 7,454.792 1,378.1893 1,814.6950 4,907.9519

20 7,467.441 1,383.6152 1,824.1140 4,922.4180

30 7,480.075 1,389.0503 1,833.5725 4,936.9202

40 7,492.694 1,394.4945 1,843.0707 4,951.4589

50 7,505.296 1,399.9480 1,852.6089 4,966.0341

82 0 7,517.882 1,402.4105 1,862.1872 4,980.6461

10 7,530.453 1,410.8823 1,871.8059 4,995.2951

20 7,543.007 1,416.3631 1,881.4651 5,009.9814

30 7,555.546 1,421.8531 1,891.1650 5,024.7050

40 7,568.069 1,427.3522 1,900.9058 5,039.4662

50 7,580.575 1,432.8604 1,910.6878 5,054.2653

83 0 7,593.066 1,438.3777 1,920.5111 5,069.1024

10 7,605.541 1,443.9041 1,930.3758 5,083.9777

20 7,617.999 1,449.4395 1,940.2823 5,098.8914

30 7,630.441 1,454.9840 1,950.2308 5,113.8438

40 7,642.868 1,460.5376 1,960.2213 5,128.8351

50 7,655.278 1,466.1001 1,970.2542 5,143.8655

84 0 7,667.672 1,471.6717 1,980.3296 5,158.9352

10 7,680.049 1,477.2523 1,990.4478 5,174.0443

20 7,692.441 1,481.8419 2,000.6090 5,189 .. 1933

30 7,704.756 1,488.4405 2,010.8133 5,204.3822

40 7,717.084 1,494.0480 2,021.0610 5,219.6113

50 7,729.397 1,499.6645 2,031.3524 5,234.8808

Page 425: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-19

C1• Long M1• Middle E1• External T1• Tangent Degrees Minutes Chord Ordinate Distance Distance

85 0 7,741.693 1,505.2899 2,041.6875 5,250.1909

10 7,753.973 1,510.9243 2,052.0668 5,265.5419

20 7,766.236 1,516.5676 2,062.4902 5,280.9340

30 7,778.483 1,522.2199 2,072.9582 5,296.3674

,on 7 7an 71 A 1 ""7 AA1 n 2,083.4709 5,311.8423 "TV ',''''''''''' " 1,"''-' ..... "'" I ...,

50 7,802.928 1,533.5510 2,094.0285 5,327.3591

86 0 7,815.125 1,539.2299 2,104.6313 5,342.9179

10 7,827.306 1,544.9176 2,115.2795 5,358.5189

20 7,839.470 1,550.6142 2,125.9733 5,374.1625

'>" "7 o~ .. ~-4 0 1 t:.r:.t:! 'l1 a7 '} 1 'lt:: 71"a " ~Aa A.lLA7 .;3V ',avl.vlu 1,,.J...JU,OtJ I,:;}' Lo, I VV., I L.'<J ...,,_ .... ...,.------ .... ,

40 7,863.749 1,562.0339 2,147.4987 5,405.5780

50 7,875.864 1,567.7570 2,158.3308 5,421.3505

87 0 7,887.962 1,573.4889 2,169.2094 5,437.1665

10 7,900.043 1,579.2296 2,180.1349 5,453.0261

20 7,912.108 1,584.9791 2,191.1074 5,468.9298

30 7,924.155 1,590.7373 2,202.1272 5,484.8777

40 7,936.186 1,596.5043 2,213.1945 5,500.8700

50 7,948.201 1,602.2800 2,224.3096 5,516.9071

88 0 7,960.198 1,608.0645 2,235.4727 5,532.9891

10 7,972.179 1,613.8576 2,246.6841 5,549.1164

20 7,984.142 1,619.6595 2,257.9440 5,565.2892

30 7,996.089 1,625.4701 2,269.2527 5,581.5077

40 8,008.019 1,631.2894 2,280.6104 5,597.7723

50 8,019.932 1,637.1173 2,292.0174 5,614.0832

89 0 8,031.828 1,642.9539 2,303.4740 5,630.4406

10 8,043.707 1,648.7991 2,314.9804 5,646.8448

20 8,055.569 1,654.6530 2,326.5369 5,663.2961

30 8,067.414 1,660.5154 2,338.1437 5,679.7949

40 8,079.242 1,666.3865 2,349.8011 5,696.3412

I I 50 I 8,091.053 I 1,672.2662 I 2,361.5094 I ~ ""704"" n.~~r:: ;;), ( 10<::. :1.;3;;);;) I

Page 426: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-20 Curve Tables

C,. Long M,. Middle E,. External T1• T Degrees Minutes Chord Ordinate Dlatance Distance

90 0 8,102.846 1,678.1545 2,373.2689 5,729.5780

10 8,114.623 1,684.0513 2,385.0797 5.746.2689

20 8,126.382 1,689.9567 2,396.9423 5,763.0086

30 8,138.125 ',695.8707 2,408.8568 5,779.7974

40 8,149.849 1,701.7931 2,420.8236 5~1 50 8,161.557 1,707.7241 2,432.8430 5,813.5232

91 0 8,173.248 1,713.6636 2,444.9151 5,830.4609

10 8,184.921 1,719.6116 2,457.0404 5,847.4487

20 8,196.577 1,725.5681 2,469.2190 5,864.4871

30 8,208.215 ',731.5331 2,481.4514 5.881.5763

40 8,219.836 1,737.5065 2,493.7377 5,898.7166

50 1,743.4883 2,506.0783 5,915.9083

92 0 8,243.026 1,749.4786 2,518.4734 5,933.1517

10 8,254.595 1,755.4773 2,530.9235 5,950.4471

20 8,266.147 1,761.4845 2,543.4286 5,967.7948

30 8,277.681 1,767.5000 2,555.9893 5,985.1952

40 R?RQ 1Q7 1,n3.5238 !> AAA Rn~7 6,002.6486 _, ___ • w_ .. _. ___ I _'¥_ f

50 8,300.696 1,779.5561 2,581.2783 6,020.1552

93 0 8,312.178 1,785.5967 2,594.0072 6,037.7154

10 8,323.641 1,791.6457 2,606.7929 6,055.3295

20 8,335.088 ',797.7030 2,619.6355 6,072.9978

30 8,346.516 1,803.7686 2,632.5355 6,090.7207

40 8,357.927 1,809.8425 2,645.4932 6,108.4985

50 8,369.320 1,815.9247 2,658.5089 6,126.3316

94 0 8,380 .. _ 2,671.5829 6,144.2201

10 8,392.053 ',828.1139 2,684.7156 6,162.1646

20 8,403.393 ',834.2209 2,697.9072 6,180.1653

30 8,414.716 ',840.3361 2,711.1581 6,198.2225

40 8,426.020 i,846.4596 2,724.4687 6,216.3367

50 8,437.307 1,852.5913 2,737.8393 6,234.5081

Page 427: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-21

C1• Long M1• Middle Et' External Tt' Tangent Degrees Minutes Chord Ordinate Distance Distance

95 0 8,448.576 1,858.7312 2,751.2702 6,252.7371

10 8,459.826 1,864.8792 2,764.7617 6,271.0241

20 8,471.059 1,871.0355 2,778.3143 6,289.3694

30 8,482.274 1,877.1999 2,791.9283 6,307.7734

40 8,493.472 1,883.3724 2,805.6040 6,326.2364

50 8,504.651 1,889.5531 2,819.3417 6,344.7588

96 0 8,515.812 1,895.7419 2,833.1419 6,363.3410

10 8,526.955 1,901.9389 2,847.0049 6,381.9833

20 8,538.080 1,908.1439 2,860.9311 6,400.6861

30 8,549.187 1,914.3570 2,874.9208 6,419.4497

40 8,560.276 1,920.5782 2,888.9743 6,438.2747

50 8,571.347 1,926.8074 2,903.0922 6,457.1612

97 0 8,582.400 1,933.0447 2,917.2747 6,476.1098

10 8,593.435 1,939.2900 2,931.5223 6,495.1208

20 8,604.451 1,945.5433 2,945.8352 6,514.1945

30 8,615.449 1,951.8047 2,960.2140 6,433.3315

40 8,626.429 1,958.0740 2,974.6589 6,552.5320

50 8,637.391 1,964.3513 2,989.1704 6,571.7966

98 0 8,648.334 1,970.6366 3,003.7489 6,591.1255

10 8,659,259 1,976.9298 3,018,3948 6,610,5192

20 8,670.166 1,983.2309 3,033.1084 6,629.9780

30 8,681.055 1,989.5400 3,047.8902 6,649.5025

40 8,691.925 1,995.8570 3,062.7406 6,669.0931

50 8,702.777 2,002.1819 3,077.6600 6,688.7500

99 0 8,713.610 2,008.5147 3,092.6488 6,708.4739

10 8,724.425 2,014.8554 3,107.7074 6,728.2650

20 8,735.221 2,021.2039 3,122.8363 6,748.1238

30 8,745.999 2,027.5602 3,138.0359 6,768.0508

40 8,756.759 2,033.9244 3,153.3066 6,788.0464

50 8.767.500 2.040.2964 3.168.6488 6.808.1110

"

Page 428: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-22 Curve Tables

C,. Long M,. Middle E";;;:J T,. Tangent Degrees Minutes Chord Ordinate Dlat Distance

100 0 8,778,222 2,046,6762 3,184,0630 6,828.2~51

10 8,788.926 I 2,053.0638 3,199.5496 6,848.4491

20 8,799,611 2,059.4592 3,215.1090 6,868.7235

30 8,810.278 2,065.8623 3,230.7418 6,889.0687

40 8,820,926 2,072.2732 3,246.4484 6,909.4852

50 8,831.555 2,078.6918 3,262.2291 6,929.9734

101 0 8,842.166 2,085.1182 3,278.0846 6,950.5339

10 8,852.758 2,091.5522 3,294.0151 6,971.1670

20 I 8,863.331 2,097.9940 3,310.0213 6,991.8733

30 8,873.886 2,104.4434 3,326.1035 7,012.6532

40 8,884.421 2,110.9005 3,342.2623 7,033.5072

50 8,894.938 2,117.3653 3,358.4982 7,054.4358

102 0 8,905.436 2,123.8377 3,374.8115 7,075.4395

10 8,915.916 2,'30.3177 3,391.2029 7,096.5188

20 8,926.376 2,136,8054 3,407.6727 7,117.6742

30 8,936.817 2,143.3006 3,424.2215 7,138.9062

40 8,947.240 2,149.8034 3,440.8498 7,160.2152

50 8,957.644 2,156.3138 3,457.5581 7,181.6019

103 0 8,968.028 2,162.8318 3,474.3469 7,203.0667

10 8,978.394 2,169.3573 3,491.2167 7,224.6101

20 8,988.741 2,175.8903 3,508.1681 7,246.2327

30 8,999.069 2,182.4309 3,525.2015 7,267.9350

40 9,009.377 2,188.9789 3,542.3174 7,289.7175

50 9,019.667 2,195.5345 3,559.5165 7,311.5808

104 0 9,029.938 2,202.0975 3,576.7993 7,333.5254

10 9,040.189 2,208.6680 3,594.1662 7,355.5518

20 9,050.421 2,215.2459 3,611.6179 7,377.6607

30 9,060.635 2,221.8313 3,629.1548 7,399.8525

40 9,070.829 2,228.4241 3,646.7777 7.422.1278

50 9,081.004 2,235.02430664.4869 7,444.4873

Page 429: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-23

Cl' Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

105 0 9,091.159 2,241.6319 3,682.2830 7,466.9314

10 9,101.296 2,248.2468 3,700.1667 7,489.4607

20 9,111.413 2,254.8692 3,718.1386 7,512.0759

30 9,121.511 2,261.4988 3,736.1991 7,534.7775

40 9,131.589 2,268.1358 3,754.3489 7,557.5661

50 9,141.648 2,274.7802 3,772.5886 7,580.4423

106 0 9,151.688 2,281.4318 3,790.9187 7,603.4068

10 9,161.709 2,288.0908 3,809.3400 7,626.4600

20 9,171.710 2,294.7570 3,827.8529 7,649.6027

30 9,181.692 2,301.4305 3,846.4581 7,672.8354

40 9,191.654 2,308.1112 3,865.1562 7,696.1588

50 9,201.597 2,314.7992 3,883.9479 7,719.5736

107 0 9,211.521 2,321.4944 3,902.8337 7,743.0802

10 9,221.425 2,328.1968 3,921.8143 7,766.6795

20 9,231.309 2,334.9064 3,940.8904 7,790.3720

30 9,241.174 2,341.6232 3,960.0626 7,814.1584

40 9,251.019 2,348.3472 3,979.3315 7,838.0393

50 9,260.845 2,355.0783 3,998.6979 7,862.0155

108 0 9,270.651 2,361.8165 4,018.1623 7,886.0875

10 9,280.438 2,368.5619 4,037.7254 7,910.2561

20 9,290.205 2,375.3143 4,057.3880 7,934.5220

30 9,299.952 2,382.0739 4,077.1507 7,958.8859

40 9,309.680 2,388.8406 4,097.0142 7,983.3483

50 9,319.388 2,395.6143 4,116.9792 8,007.9102

109 0 9,329.076 2,402.3951 4,137.0464 8,032.5721

10 9,338.745 2,409.1829 4,157.2166 8,057.3347

20 9,348.393 2,415.9777 4,177.4903 8,082.1989

30 9,358.022 2,422.7796 4,197.8685 8,107.1653

40 9,367.632 2,429.5884 4,218.3517 8,132.2347

50 9,377.221 2,436.4042 4,238.9407 8,157.4078

Page 430: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-24 Curve Tables

Ct, Long Mt' Middle Et' External Tt' Tangent Degrees Minutes Chord Ordinate Distance Distance

110 0 9,386.791 2,443.2270 4,259.6364 8,182.6854

10 9,396.340 2,450.0568 4,280.4393 8,208.0681

20 9,405.870 2,456.8934 4,301.3504 8,233.5569

30 9,415.380 2,463.7370 4,322.3703 8,259.1525

40 9,424.870 2,470.5875 4,343.4998 8,284.8556

50 9,434.340 2,477.4450 4,364.7398 8,310.6671

111 0 9,443.790 2,484.3092 4,386.0909 8,336.5877

10 9,453.220 2,491.1804 4,407.5541 8,362.6182

20 9,462.630 2,498.0584 4,429.1301 8,388.7595

30 9,472.020 2,504.9432 4,450.8197 8,415.0123

40 9,481.390 2,511.8349 4,472.6237 8,441.3776

50 9,490.740 2,518.7333 4,494.5430 8,467.8561

112 0 9,500.070 2,525.6386 4,516.5784 8,494.4487

10 9,509.380 2,532.5506 4,538.7308 8,521.1562

20 9,518.670 2,539.4694 4,561.0010 8,547.9795

30 9,527.939 2,546.3950 4,583.3899 8,574.9194

40 9,537.189 2,553.3272 4,605.8983 8,601.9769

50 9,546.418 2,560.2662 4,628.5271 8,629.1528

113 0 9,555.627 2,567.2119 4,651.2773 8,656.4480

10 9,564.816 2,574.1643 4,674.1497 8,683.8635

20 9,573.985 2,581.1234 4,697.1451 8,711.4001

30 9,583.133 2,588.0891 4,720.2646 8,739.0587

40 9,592.261 2,595.0615 4,743.5091 8,766.8404

50 9,601.369 2,602.0405 4,766.8795 8,794.7459

114 0 9,610.456 2,609.0261 4,790.3767 8,822.7764

10 9,619.524 2,616.0183 4,814.0017 8,850.9327

20 9,628.570 2,623.0171 4,837.7554 8,879.2157

30 9,637.597 2,630.0225 4,861.6389 8,907.6266

40 9,646.603 2,637.0345 4,885.6531 8,936.1663

50 9,655.588 2,644.0529 4,909.7990 8,964.8357

Page 431: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-25

Cl' Long Ml• Middle El' External T10 Tangent Degrees Minutes Chord Ordinate Distance Distance

115 0 9,664.554 2,651.0779 4,934.0776 8,993.6359

10 9,673.498 2,658.1095 4,958.4899 9,022.5679

20 9,682.423 2,665.1475 4,983.0370 9,051.

30 9,691.327 2,672.1920 5,007.7198 9,080.8315

40 9,700.210 2,679.2429 5,032.5395 9,110.1651

50 9,709.073 2,686.3003 5,057.4970 9,139.6348

116 0 9,717.915 2,693.3642 5,082.5935 9,169.2415

10 9,726.737 2,700.4345 5,107.8300 9,198.9863

20 9,735.538 2,707.5112 5,133.2077 9,228.8704

30 9,744.318 2,714.5942 5,158.7275 9,258.8948

40 9,753.078 2,721.6837 5,184.3907 9,289.0607

50 9,761.818 2,728.7795 5,210.1984 9,319.3692

117 0 9,770.536 2,735,8817 5,236.1516 9,349.8215

10 9,779.234 2,742,9902 5,262.2516 9,380.4186

20 9,787.911 2,750.1050 5,288.4995 9,411.1618

30 9,796.568 2,757.2261 5,314.8964 9,442.0523

40 9,805.204 2,764.3535 5,341.4436 9,473.0912

50 9,813.819 2,771.4872 5,368.1423 9,504.2797

118 0 9,822.413 2,778.6271 5,394.9937 9,535.6191

10 9,830.987 2,785.7733 5,421.9989 9,567.1105

20 9,839.540 2,792.9257 5,449.1593 9,598.7553

30 9,848.072 2,800.0843 5,476.4761 9,630.5547

40 9,856.583 2,807.2491 5,503.9505 9,662.5100

50 9,865.073 2,814.4201 5,531.5839 9,694.6224

119 0 9,873.542 2,821.5973 5,559.3775 9,726.8932

10 9,881.991 2,828.7806 5,587.3326 9,759.3238

20 9,890.419 2,835.9701 5,615.4 ,791.9155

30 9,898.825 2,843.1657 5,643.7327 9,824.6696

40 9,907.211 2,850.3673 5,672.1804 9,857.5875

50 9,915.576 2,857.5751 5,700.7950 9,890.6706

Page 432: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-26 Curve Tables

C" Long M,• Middle E" External

~ Degrees Minutes Chord Ordinate Distance

120 0 9,923.920 2,864.7890 5,729,5780 9,923.9202

10 9,932.243 2,872.0089 5,758.5305 9,957.3377

20 9,940.544 2,879.2348 5,787.6542 9,990.9246

30 9,948.825 2,886.4668 5,816.9504 10,024.6823

40 9,957.085 2,893.7048 5,846.4206 10,058.6123

50 9,965.324 2,900.9488 5,876.0663 10,092.7159

121 0 9,973.541 2,908.1988 5,905.8888 10,126.9948

10 9,981.738 2,915.4547 5,935.8897 10,161.4503

20 9,989.913 2,922.7166 5,966.0706 10,196.0841

30 9,998.067 2,929.9844 5,996.4328 10,230.8976

40 10,006.200 2,937.2582 6,026.9781 10,265.8925

50 10,014.312 2.944.5379 6,057.7079 10,301.0701

122 0 10.022.403 2,951.8234 6.088.6239 10,336.4323

10 10,030.473 2,959.1148 6,119.7276 10,371.9805

20 10,038.521 2,966.4121 6,151.0206 10,407.7164

30 10,046.548 2,973.7153 6.182.5047 1 0,443.6416

40 10,054.554 2.981.0243 6,214.1813 10,479.7578

50 10,062.539 2,988.3390 6,246.0523 10,516.0667

123 0 10,070.502 2,995.6596 q,278.1193 10,552.5699

10 10,078.444 3,002.9860 6,310.3841 10,589.2692

20 10,086.365 3.010.3181 6,342.8483 10,626.1664

30 10,094.264 3,017.6560 6,375.5137 10,663.2632

40 10,102.142 3,024.9996 6,408.3821 10,700.5613

50 10,109.998 3,032.3490 6,441.4553 10,738.0626

124 0 10,117.834 3,039.7040 6,474.7352 10,775.7689

10 10,125.648 3,047.0648 6,508.2235 10,813.6821

20 10,133.440 3,054.4312 6,541.9221 10,851.8040

30 10,141.211 3,061.8032 6,575.8329 10,890.1365

40 10,148.960 3,069.1810 9578 10,928.6815 I

50 10,156.688 3,076.5643 .---7 10,967.4410

Page 433: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-27

Cl' Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

125 0 10,164.395 3,083.9533 6,678.8577 11,006.4169

10 10,172.080 3,091.3478 6,713.6366 11,045.6112

20 10,179.744 3,098.7479 6,748.6375 11,085.0259

30 10,187.386 3,106.1536 6,783.8625 11,124.6631

40 10,195.006 3,113.5649 6,819.3134 11,164.5247

50 10,202.605 3,120.9817 6,854.9926 11,204.6130

126 0 10,210.182 3,128.4040 6,890.9019 11,244.9299

10 10,217.738 3,135.8318 6,927.0436 11,285.4777

20 10,225.272 3,143.2651 6,963.4199 11,326.2585

30 10,232.785 3,150.7038 7,000.0328 11,367.2744

40 10,240.275 3,158.1480 7,036.8847 11,408.5277

50 10,247.744 3,165.5977 7,073.9777 11,450.0207

127 0 10,255.192 3,173.0528 7,111.3141 11,491.7556

10 10,262.618 3,180.5133 7,148.8963 11,533.7347

20 10,270.022 3,187.9791 7,186.7264 11,575.9603

30 10,277.404 3,195.4504 7,224.8070 11,618.4348

40 10,284.765 3,202.9270 7,263.1404 11,661.1606

50 10,292.104 3,210.4090 7,301.7289 11,704.1401

128 0 10,299.421 3,217.8963 7,340.5750 11,747.3757

10 10,306.716 3,225.3889 7,379.6813 11,790.8700

20 10,313.989 3,232.8868 7,419.0502 11,834.6254

30 10,321.241 3,240.3900 7,458.6842 11,878.6446

40 10,328.471 3,247.8984 7,498.5860 11 ,922.9300

50 10,335.679 3,255.4121 7,538.7581 11,967.4842

129 0 10,342.865 3,262.9310 7,579.2032 12,012.3100

10 10,350.029 3,270.4552 7,619.9239 12,057.4100

20 10,357.172 3,277.9845 7,660.9230 12,102.7870

30 10,364.292 3,285.5191 7,702.2032 12,148.4436

40 10,371.391 3,293.0588 7,743.7673 12,194.3827

50 10,378.467 3,300.6037 7,785.6181 12,240.6071

Page 434: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

F-28 Curve Tables

Cl' Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

130 0 10,385.522 3,308.1537 7,827.7585 12,287.1196

10 10,392.554 3,315.7088 7,870.1913 12,333.9232

20 10,399.565 3,323.2690 7,912.9196 12,381.0208

30 10,406.554 3,330.8343 7,955.9462 12,428.4154

40 10,413.520 3,338.4047 7,999.2743 12,476.1100

50 10,420.465 3,345.9802 8,042.9067 12,524.1076

131 0 10,427.388 3,353.5607 8,086.8467 12,572.4114

10 10,434.288 3,361.1462 8,131.0975 12,621.0245

20 10,441.167 3,368.7367 8,175.6620 12,669.9501

30 10,448.023 3,376.3322 8,220.5437 12,719.1915

40 10,454.857 3,383.9328 8,265.7457 12,768.7518

50 10,461.669 3,391.5382 8,311.2715 12,818.6345

132 0 10,468.459 3,399.1486 8,357.1242 12,868.8428

10 10,475.227 3,406.7640 8,403.3075 12,919.3803

20 10,481.973 3,414.3842 8,449.8246 12,970.2504

30 10,488.697 3,422.0094 8,496.6792 13,021.4565

40 10,495.398 3,429.6394 8,543.8747 13,073.0023

50 10,502.077 3,437.2743 8,591.4148 13,124.8913

133 0 10,508.734 3,444.9141 8,639.3032 13,177.1272

10 10,515.369 3,452.5586 8,687.5434 13,229.7138

20 10,521.981 3,460.2080 8,736.1394 13,282.6548

30 10,528.571 3,467.8622 8,785.0950 13,335.9539

40 10,535.139 3,475.5212 8,834.4139 13,389.6152

50 10,541.685 3,483.1850 8,884.1001 13,443.6425

134 0 10,548.208 3,490.8535 8,934.1577 13,498.0398

10 10,554.709 3,498.5267 8,984.5905 13,552.8112

20 10,561.188 3,506.2047 9,035.4029 13,607.9608

30 10,567.644 3,513.8873 9,086.5988 13,663.4926

40 10,574.078 3,521.5747 9,138.1826 13,719.4111

50 10,580.490 3,529.2667 9,190.1585 13,775.7204

Page 435: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Curve Tables F-29

C,. Long M,. Middle E,. External T,. Tangent Degrees Minutes Chord Ordinate Distance Distance

135 0 10,586.879 3,536.9634 9,242.5308 13,832.4249

." .. n..c:n~nA~ ""J .c:A A ~J':'A~ n 1"\1"\t::. ""11"\..411"\ .. .., oon .c:'U'\1'\ IV I V,w;::h~.c:.~O "'1~""'OO'i( "',.:;",;).vv~v , "'IOO~.;'£"V

20 10,599.590 3,552.3706 9,348.4826 13,947.0372

30 1 0,605.913 3,560.0812 9,402.0710 14,004.9541

40 10,612.212 3,567.7963 9,456.0740 14,063.2842

50 1 0,618.489 3,575.5160 9,510.4962 14,122.0323

136 0 10,624.744 3,583.2403 9,565.3423 14,181.2031

10 10,630.976 3,590.9691 9,620.6172 14,240.8015

20 10,637.186 3,598.7024 9,676.3257 14,300.8324

30 10,643.373 3,606.4402 9,732.4730 14,361.3006

40 10,649.538 3,614.1825 9,789.0639 14,422.2114

50 10,655.680 3,621.9293 9,846.1036 14,483.5698

137 0 10,661.800 3,629.6806 9,903.5975 14,545.3811

." .. " ,..,...., """'., n "''''.., An,...", 9.961.5506 14,607.6505 IV IV,OO(.O';1( ",o.;)( .'hlO"

20 10,673.971 3,645.1964 1 0,019.9685 14,670.3834

30 10,680.023 3,652.9609 1 0,078.8565 14,733.5853

40 10,686.052 3,660.7299 1 0,138.2202 14,797.2618

50 10,692.059 3,668.5032 10,198.0653 14,861.4184

138 0 10,698.043 3,676.2808 10,258,3975 14,926.0609

10 10,704.005 3,684.0628 10,319.2225 14,991.1952

20 10,709.944 3,691.8492 10,380.5463 15,056.8271

30 10,715.860 3,699.6398 10,442.3749 15,122.9626

40 10,721.753 3,707.4348 10,504.7144 15,189.6078

50 10,727.624 3,715.2340 10,567.5710 15,256.7690

139 0 10,733.472 3,723.0374 10,630.9509 15,324.4524

10 10,739.298 3,730.8452 10,694.8606 15,392.6645

20 10,745.100 3,738.6571 10,759.3066 15,461.4117

30 10,750.880 3,746.4733 10,824.2955 15,530.7007

40 10,756.638 3,754.2936 10,889.8340 15,600.5382

50 10,762.372 3,762.1182 10,955.9290 15,670.9310

Page 436: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-1. Functions of a 1-degree curve (continued)

Table F-2.Corrections for Tangents and Externals

F-30 Curve Tables

Page 437: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table F-2. Corrections for Tangents and Externals (continued)

Curve Tables F-31

For externals add--

Angle In Degrees 50 curve 100 curve 150 curve 200 curve 250 curve 300 curve

10 0.001 0.003 0.004 0.006 0.007 0.008

20 0.006 0.011 0.017 0.022 0.028 0.034

30 0.013 0.025 0.038 0.051 0.065 0.078

40 0.023 0.046 0.070 0.093 0.117 0.141

50 0.037 0.075 0.116 0.151 0.189 0.227

60 0.056 0.112 0.168 0.225 0.283 0.340

70 0.080 0.159 0.240 0.321 0.403 0.485

80 0.110 0.220 0.332 0.445 0.558 0.671

90 0.149 0.299 0.450 0.603 0.756 0.910

100 0.200 0.401 0.604 0.809 1.015 1.221

110 0.268 0.536 0.806 1.082 1.355 1.633

120 0.380 0.721 1.086 1.456 1.825 2.197

Page 438: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX G

FROST DESIGN FOR ROADS

FROST-AREA CONSIDERATIONSIn areas where frost effects have an impacton the design of roads, additional considera-tions concerning thicknesses and requiredlayers in the road structure must be ad-dressed. The specific areas where frost hasan impact on the design are discussed inthe following paragraphs: however, a moredetailed discussion of frost effects is pre-sented in Special Report 83-27. For frost-design purposes, soils have been dividedinto seven groups as shown in Table G-1.Only the NFS group is suitable for a basecourse. NFS, S1, S2, F1, or F2 soils maybe used for a subbase course, and any ofthe six groups may be encountered as sub-

grade soils. Soils are listed in approximateorder of decreasing bearing capability dur-ing periods of thaw.

REQUIRED THICKNESS

Where frost-susceptible subgrades are en-countered, the section thickness requiredwill be determined according to the reduced-subgrade-strength method. The reduced-subgrade-strength method requires the useof frost-area soil-support indexes listed inTable G-2, page G-2, and strength curvesshown in Figure G-1, page G-2. The

Table G-1. Frost-design soil classification

Frost Design for Roads G-1

Page 439: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table G-2. Frost-area soil-support indexes ofsubgrade soils

curve, and then moving vertically downwardto determine the design thickness in inches.

required thickness is determined by compar-ing the natural subgrade CBR to the frost-area soil-support index associated to therelevant first group. If the natural sub-grade CBR is less than the frost-area soil-support index then the CBR value governsthe design, and the thickness is determinedfrom Figure G-2. If the natural subgradeCBR is greater than the soil-support index,then Figure G-1 is used. The requiredthickness is determined by entering FigureG-1 at thezontally to

correct design index moving hori-intersect the relevant frost-group

REQUIRED LAYERS IN A ROAD SECTION

When frost is a consideration, the road sec-tion should consist of a series of layers thatwill ensure the stability of the system, par-ticularly during thaw periods. The layeredsystem in the aggregate fill may consist of awearing surface of fine-crushed stone, acoarse-graded base course, and a well-graded subbase of sand or gravelly sand asshown in the following example:

Figure G-1. Frost-design reduced-subgrade-strength curves

G-2 Frost Design for Roads

Page 440: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

To ensure the stability of the wearing sur-face, the width of the base course and sub-base should exceed the final desired surfacewidth by a minimum of 1 foot on each side.

WEARING SURFACE

The wearing surface contains fines to pro-vide stability in the aggregate surface. Thepresence of fines helps the layer’s compac-tion characteristics and helps to provide arelatively smooth riding surface. Its thick-ness will vary between 4 and 6 inches.

BASE COURSE

The coarse-graded base course is importantin providing drainage of the granular fill. Itis also important that this material be NFSso that it retains its strength during springthaw.

SUBBASE

The well-graded sand subbase is used foradditional bearing capacity over the frost-susceptible subgrade and as a filter layer be-tween the coarse-graded base course andthe subgrade. This process prevents the mi-gration of the subgrade into the voids inthe coarser material during periods of re-duced subgrade strength. The materialmust therefore meet standard filter criteria.

The sand subbase must be either NFS, S1,or S2. The filter layer may or may not benecesary depending upon the type of sub-grade material. If the subgrade consistsprincipally of gravel or sand, the filter layermay not be necessary and may be replacedby additional base course material, if thegradation of the base course is such that itmeets filter criteria. However, for finer-grained soils, the filter layer will be neces-sary. If a geotextile is used, the sand sub-base or filter layer may be omitted becausethe fabric will be placed directly on the sub-grade and will act as a filter. If select mate-rials are used, they must be either NFS, S1,S2, F1, or F2 from Table G-1, page G-1.

COMPACTION

The subgrade should be compacted to pro-vide uniformity of conditions and a firmworking platform for placement and compac-tion of the subbase. However, compactionof the subgrade will not change its frost-area soil-support index because frost actionwill cause the subgrade to revert to aweaker state.

THICKNESS OF BASE COURSE ANDFILTER LAYER

The relative thicknesses of the base courseand filter layer are variable and should bebased on the required cover (minimum of 4inches] and economic considerations.

FROST-AREA DESIGN STEPS

Steps 1 through 5 are the same as for regu-lar aggregate-surfaced roads. (Refer toChapter 9, page 9-66.)

6. Determine the applicable frost group forthe subgrade type from Table G-1, page G-1.

7. Determine the frost-area soil-support in-dex from Table G-2, page G-4, based on theapplicable frost group.

8. Determine the required road-structurethickness. First, compare the natural sub-grade CBR to the frost-area soil-support in-dex.

a, If the natural subgrade CBR is lessthan the frost-area soil-support index, thenthe CBR value governs the design, and thethickness is determined from Figure G-2,page G-4, as in nonfrost design.

b. If the natural subgrade CBR isgreater than the frost-area soil-support in-dex, then Figure G-1, page G-2, is used.The required thickness is determined by en-tering Figure G-1 at the design index, mov-ing horizontally to intersect the frost-groupcurve, and then moving vertically downwardto determine the thickness in inches.

9. Determine the required compaction den-sities for each layer from Table 9-12, page 9-63.

Frost Design for Roads G-3

Page 441: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure G-2. Design curves for aggregate-surfaced roads

10. Draw the section of the aggregate road 2. The material should meet gradation re-structure. quirements.

NOTES: 3. After all possible design sections aredetermined, the final section used should

1. All layer depths should be rounded up be determined on the basis of economicto the next full inch for construction pur- analysis.poses.

G-4 Frost Design for Roads

Page 442: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Example (Frost-Area Design):

An aggregate-surfaced road in a frost areais to be used for one year. The road will besubject to—

Vehicles Average Daily Traffic

M998 HMMWV 1,800

M929 5-ton dump 600(2 average trucks)

Available material CBR:Natural subgrade = 4 (Clay PI = 14)Compacted subgrade = 8Fine-graded, crushed rock = 80Coarse-graded, crushed rock = 80Clean sand subbase = 15

Solution:

1. Number of daily passes = 2,400 (given).

2. Select road class D from Table 9-8, page9-59, based on average daily traffic of 2,400.

3. Select traffic category IV from page 9-59, based upon the presence of the 25-per-cent truck traffic.

4. Select design index of 4 from Table 9-9,page 9-60.

5. Natural subgrade CBR = 4.Compacted subgrade CBR = 8

6. From Table G-1, page G-1, the subgradefrost group is F3 based on it being a clay(CL) material.

7. Select frost-area support-index of 3.5from Table G-1, based on frost group F3.

8. Determine the acquired road-structurethickness.

a. First, look at the required road thick-ness if it was not designed for frost. Inthis case, the compact subgrade CBR = 8 isused in Figure G-2, page G-3. This resultsin a required total thickness of 6.25 inches,rounding up to 7 inches as shown below.

b. Now, design the road for frost. In thiscase, the natural subgrade CBR = 4, andthe frost-area soil-support index = 3.5.Since the natural subgrade CBR is greaterthan the frost-area soil-support Index, Fig-ure G-1 is used. A design index of 4 isentered into Figure G-1 resulting in a

Frost Design for Roads G-5

Page 443: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

design thickness of 24.5 inches, roundingup to 25 inches. Notice the rather large dif-ference in design thicknesses between frostdesign and non frost design.

9. Compaction densities for each layer aredetermined from Table 9-12, page 9-63.

Wearing course: at least 100 percent.Base course: at least 100 percent.Subbase course: 100 to 105 percent.Subgrade: 90 to 95 percent for cohesion

soil (PI>5).

10. Draw the section of the frost-area, ag-gregate road structure.

NOTES:

1. The function of the subbase as a filterlayer is not always required, dependingupon the subgrade material. In this case,the subgrade is a CL; therefore, it is re-quired.

2. For economy, the thicknesses of thebase and subbase courses can be ad-justed, so long as the minimum thicknessabove the CBR=15 subbase is maintainedat 4 inches, as determined from Figure G-2, page G-3.

3. An overall minimal thickness layer of4 inches should be maintained.

When using a geotextile as a filter layer, thedesign above could be used by deducting 6inches of the clean sand subbase andreplacing it with a geotextile. The totalthickness above the geotextile must be aminimum of 25 inches. Two alternatedesigns using geotextile are shown in theexample at the bottom of the page.

G-6 Frost Design for Roads

Page 444: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-801, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

APPENDIX H

GEOTEXTILE DESIGN

DESIGN GUIDELINES

The widespread acceptance of geotextiles foruse in engineering designs has led to aproliferation of geotextile manufacturersand a multitude of geofabrics, each with dif-ferent engineering characteristics fromwhich to choose. The design guidelines andmethodology that follow help you select theright geofabric to meet your construction re-quirements.

UNPAVED-AGGREGATE DESIGN

Site Reconnaissance

As with any construction project, a sitereconnaissance provides insight on construc-tion requirements and potential problems.

Determine Subgrade Soil Type andStrength

Identify the subgrade soil and determine itsstrength as outlined in Chapter 9, FM 5-410. If possible, determine the soil’s shearstrength, C, in psi. If you are unable todetermine C, use the nomograph in FigureH-1 to convert CBR value or CI to C.

Determine Permissible Load on the Sub-grade Soil

The amount of loading that can be appliedwithout causing the subgrade soil to fail isreferred to as the permissible stress, S.

Ž Permissible subgrade stress without ageotextile:

S = (2.8)C

• Permissible subgrade stress with ageotextile:

S = (5.0)C

Figure H-1. Determining the soils’s shearstrength by converting CBR value or cone

index

Geotextile Design H-1

Page 445: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Determine Wheel Loads, Contact Pres- • Estimate the area being loadedsure, and Contact Area

Estimate wheel loads, contact pressure, andcontact-area dimensions from TableH-2. For geotextile design, single and dual where = length of one side of the squarewheels are represented as single-wheel contact arealoads (L) equal to one-half the axle load,The wheel load exerted by a single wheel is Determine Aggregate-Base Thicknessapplied at a surface contact pressure (P) Assuming that wheel loads will be appliedequal to the tire inflation pressure. Dual- over a square area, we can use the Bous-wheel loads apply a P equal to 75 percent sinesq theory of load distribution to deter-of the tire inflation pressure. Tandem axles mine the aggregate-section thickness re-exert 20 percent more than their actual quired to support the design load. Bous-weight to the subgrade soil due to overlap- sinesq theory coefficients are found in Tableping stress from the adjacent axle in the H-2.tandem set,

Table H-1. Vehicle input parameters

H-2 Geotextile Design

Page 446: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table H-2. Boussinesq theory coefficients

Ž First, solve for X.

Without a geotextile:

With a geotextile:

Ž Using the calculated values of X and find the corresponding valueof M and from Table H-2.

Ž Then solve for aggregate-base thicknessH and H geotextile.

Without a geotextile:

With a geotextile:

The difference between H and H geotextileis the aggregate savings due to the geotex-tile.

Adjust Aggregate-Section Thickness forAggregate Quality

The design method is based on the assump-tion that good-quality aggregate (minimumCBR value of 80) is used. If lower-qualityaggregate is used, the aggregate-sectionthickness must be adjusted.

Table H-3, page H-4, contains typical com-pacted strength properties of common struc-tural materials. These values are approxi-mations: use more specific data if it is avail-able. Extract the appropriate thicknessequivalent factor from Table H-3, then di-vide H by that factor to determine the ad-justed aggregate-section thickness.

Adjust Aggregate-Base Thickness for Serv-ice Life

The design method assumes that the pave-ment will be subjected to 1,000 passes ofthe maximum design axle load.fic is greater than 1,000 passes,by the following percentages:

2,000 passes 8%5,000 passes 19%10,000 passes 27%

If the traf-increase H

If you anticipate more than 10,000 passes,you need to increase the design thicknessby 30 percent and monitor the performanceof the road.

A second method of determining minimumrequired cover above a subgrade for wheeledvehicles with and without a geotextile re-quires fewer input parameters. Again, useFigure H-1 to correct CBR or CI values to aC value. Determine the permissible stresson the subgrade soil (S) by multiplying C by2.8 without a geotextile and by 5.0 with ageotextile. Select the heaviest vehicle usingthe road and the design vehicle for eachwheel-load configuration: single, dual, ortandem. Enter the appropriate graph (seeFigures H-2, H-3, or H-4, pages H-5through H-7) at S (with and without ageotextile). Round design-vehicle wheelloads to the next higher 5,000-pound incre-ment. Determine the intersection betweenthe appropriate wheel-load curve and S(with and without a geotextile), then readthe minimum required thickness on the leftaxis. Use the greatest thickness values as

Geotextile Design H-3

Page 447: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table H-3. Typical compacted strength properties of common structural materials

the design thickness with and without a ments. The pattern and opening spacinggeotextile. Compare the cost of the mate-rial saved with the cost of the geotextile todetermine if the use of the geotextile iscost effective.

Up to this point in the geotextile-designprocess, you have been concerned with gen-eral design properties for designing un-paved aggregate roads. Now you must de-cide which geotextile fabric best meets yourproject requirements.

TYPES OF GEOTEXTILES

There are two major types of geotextiles:woven and nonwoven. Woven fabrics havefilaments woven into a regular, usually rec-tangular, pattern with fairly even openingspacing and size. Nonwoven fabrics havefilaments connected in a method other thanweaving, typically needle punching or headbonding at intersection points of the fila-

and size are irregular in nonwoven fabrics.

Woven fabrics are generally stronger thannonwoven fabrics of the same fabric weight.Woven geotextiles typically reach peak ten-sile strength at between 5 and 25 percentstrain. Nonwoven fabrics have a high elon-gation of 50 percent or more at maximumstrength.

Table H-4, page H-8, provides informationon important criteria and principal proper-ties useful when selecting or specifying ageotextile for a specific application. Thetype of equipment used to construct a roador airfield pavement structure on top of thegeotextile must be considered. Equipmentground pressure (in psi) is an important fac-tor in determining the geotextile fabricthickness; a thicker fabric is necessary tostand up to high equipment ground pres-sure (see Table H-5, page H-9).

H-4 Geotextile Design

Page 448: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure H-2. Thickness design curve for slngle-wheel load on gravel-surfaced pavements

Once the required degree of geotextile surviv- testing standards, the geotextile will be re-ability is determined, minimum speification quired to withstand to meet use and con-requirements can be established based on struction requirements, you are ready toASTM standards (see Table H-6, page H- either specify a geotextile for ordering or10). When you have determined the set of evaluate on-hand stocks.

ROADWAY CONSTRUCTIONThere is no singular way to construct mad- deeper than 3 or 4 inches (see Figure H-5,ways with geofabrics. However, there are page H-11). Compact the subgrade if theseveral applications and general guidelines soil CBR is greater than 1. The compactionthat can be used. aids in locating unsuitable materials that

may damage the fabric. Remove unsuitableSITE PREPARATION materials where practical.

Clear, grub, and excavate the site to designgrade: fill in ruts and surface irregularities

Geotextile Design H-5

Page 449: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure H-3. Thickness design curve for

When constructing over extremely soft soils(such as peat bogs), surface materials (suchas the root mat) may be advantageous andshould be disturbed as little as possible.

dual-wheel load on gravel-surfaced pavements

grade. The fabric is commonly, but not al-ways, laid in the direction of the roadway.Where the subgrade cross section has largeareas and leveling is not practical, the

Use sand or sawdust to cover roots, stumps, fabric may be cut and laid transverse to theor stalks. This cushions the fabric and roadway. Large wrinkles should be avoided.reduces the potential for fabric puncture. In the case of wide roads, multiple widths ofNonwoven geotextiles are preferred when the fabric are laid and overlapped. Lap lengthsoil surface is uneven. normally depends on subgrade strength.

Table H-7, page H-12, provides general

LAYING OF FABRIC

The fabric should be rolled out by hand,ahead of backfilling, directly on the soil sub-

guidelines for lap lengths.

H-6 Geotextile Design

Page 450: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure H-4. Thickness design curve for tandem-wheel load on gravel-surfaced pavements

LAYING OF BASE

If angular rock is to form the base, it iscommon to first place a protective layer of 6to 8 inches of finer material, Base materialis then end-dumped directly onto the pre-viously spread load, pushed out over thefabric, and spread from the center using abulldozer. Vehicles must not be drivendirectly on the fabric because they might

puncture it. Small, tracked bulldozers(with a maximum ground pressure of 2 psi)are commonly used for spreading. Theblade is also kept high to avoid driving rockdown into the fabric. After spreading, com-paction and grading can be carried out withstandard compaction equipment. If theroadway has side drains, they are con-structed after the pavement.

Geotextile Design H-7

Page 451: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table H-4. Geotextile evaluation

H-8 Geotextile Design

Criteria and Parameter

Design Requirements

Mechanical strength

Tensile strength Tensile modulus Seam strength Tension creep Soil-fabric friction

Hydraulic

Flow capacity

Piping resistance Clogging resistance

Constructability Requirements

Tensile strength Seam strength Bursting resistance Puncture resistance Tear resistance

F - Filtration D- Drainage S - Se?lration R - Reinforcement

Property

Wide-width strength Wide-width modulus Wide width Creep Friction angle

Permeability, Transmissivity Apparent opening size (AOS) Pommetry

, Gradient ratio

Grab strength Grab strength

i Mullen burst ! Red puncture i Trapesoidal tear I

F

x

x x x

x x x x x

Application

D S

x x

x x x x x

x

x x

x x x x x

R

x x x x x

x

x x

x x x x x

Page 452: Army Construction Manual FM5 430 Vol1 Entire

Table H

-5. Required degree of geotextile survivability as a function of cover m

aterial and construction equipment

FM

5-430-00-1/A

FP

AM

32-8013,

Vo

l 1

Geo

textile D

esign

H

-9

Table H-S. Required degree of geotextile survivability as a function of cover material and construction equipment

Cover Material

Fine sand to ±2-inch-diameter gravel, round to subangular

Coarse aggregate with diameter up to one-half proposed lift thickness, may be angular

Some to most aggregate with diameter greater than one-half proposed lift thickness, angular and sharp-edge few fines

NOTES:

6- to 12-lnch Initial LIft Thickness

Low- Medium-Ground- Ground-Pressure Pressure Equipment Equipment <4 psi ?o4 pSi, <8 psi

Low Moderate

Moderate High

High Very High

12- to 18-lnch Initial Lift Thickness

Medlum- Hlgh-Ground- Ground-Pressure Pressure Equipment Equipment ?o4 psi, <8 psi ?8 psi

Low Moderate

Moderate High

High Very High

18- to 24-lnch Initial Lift Thickness Hlgh-Ground­Pressure Equipment ?o8 psi

Low

Moderate

High

1. For special construction techniques such as preruttlng, Increase geotextlle survtvablllty requirement one level.

2. Placement of an excessive Initial cover-material thickness may cause bearing failure of soft subgrades.

>24-lnch Initial LIft Thickness High-Ground­Pressure Equipment ?o8 psi

Low

Low

Moderate

Page 453: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table H-6. Minimum properties required for geotextile survivability

H-10 Geotextile Design

Required Degree Grab Strength 1 Puncture Strength 21 Burst Strength 3 Trap Tear 4

of Geotextile Survivability Ib Ib , psi Ib

Very high 270 110 430 75

High 180 75 290 I 50

Moderate 130 40 210 40

Low 90 30 145 30

i 1 ASTMD4632 2 ASTM D4833 3 ASTM D3786 4 ASTM D 4533, either principal direction

Note: All values represent minimum average roll values (for example, any roll in a 101 should meet or exceed Ihe minimum values in Ihis. lable). These values are normally 20 percenllower Ihan manufaclurer-repor1~ typical values.

Page 454: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Figure H-5. Construction sequence using geotextiles

Geotextile Design H-11

1. Prepare the ground by removing stumps, boulders, and so forth; fill in low spots.

Dump aggregate onto previously placed aggregate. Do not drive directly on the geotextile. Maintain at least 6 to 12 inches cover between the truck tires and the geotextile.

;,\... '.\;.6"- ~

2. Unroll the geotextile directly over the ground to be stabilized. If more than one roll width is required, overlap the rolls. Inspect the geotextile.

4. Spread the aggregate over the geotextile to the design thickness.

~{~;fi:t:~1~;'~7 .. , .... 'l.J\~"I' •. =(.~.~ ....... ~!. J > .:~ c."i ............ :.:~ ,;' ."'~

. '.~ ~.~'):.~~)~ \.~:~ L' (:.~; .~~;.~ ~~ .. ~: r ~ ~~;\~~~; ~.~ ~'I,: __ "" ,e .. '" '\ ' .. 0 ... 0

5. Compact the aggregate using ...... '. ·;·-::7":~i(:. i dozer tracks or a vibratory roller.

Page 455: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Table H-7. Recommended minimum overlap requirements

H-12 Geotextile Design

CBR Minimum Overlap

>2 1 -1.5 feet

1-2 2 -3 feet

0.5 -1 3 feet or sewn

< 0.5 Sewn

AJI roll ends 3 feet or sewn

Page 456: Army Construction Manual FM5 430 Vol1 Entire

AABNCP

AASHO

AASHTO

ABS

AC

ACE

adj

ADR

AFCS

AFM

AFP

AFR

ammo

APC

approx

Apr

AR

ASCE

ASTM

FM 5-430-00-1/AFPAM 32-8013, Vol 1

GLOSSARY

advanced airborne control platform

American Association of State Highway Officials

American Association of State Highway and Transportation Officials

acrylonitrile-butadiene-styrene (plastic)

asphalt cement

armored combat earthmover

adjusted

air base damage repair

Army Facilities Component System

Air Force manual

Air Force pamphlet

Air Force regulation

aggregate

average haul distance

airfield marking and lighting

ammunition

armored personnel carrier

approximately

April

Army regulation

American Society of Civil Engineers

American Society of Testing and Materials

a g g

AHD

AML

Atterberg Limits Soil plasticity test used to measure soil cohesiveness: that is, cohesive orcohesionless,

ATTN attention

Aug August

Glossary - 1

Page 457: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

av absolute volume

average daily traffic (ADT) The anticipated average number of vehicles per day that willuse a completed facility.

banked cubic yardage (BCY) Soil measured in its natural state.

average running speed The speed expected to be maintained by most vehicles. It is equalto the total traveled distance divided by total time consumed.

base course or base Base course consists of well-graded, granular materials that have aliquid limit less than 25 percent and a plastic limit less than 5 percent,The base course is the most important element in a road structure. Itfunctions as the primary load-bearing component of the road, ultimatelyproviding the pavement (or surface) strength. Therefore, it is made of higherquality material than subbase material.

bearing capacity The ability of a soil to support a vehicle without undue sinkage of thevehicle.

benching Terracing on a slope.

berm A raised lip, usually of earth, placed at the top edge of a channel to preventflow into the channel at places not protected against erosion.

bitumen or bituminous The most common type of asphalt surface placed in the theater ofoperations.

Bn battalion

borrow pit An excavated area where material has been dug for use as fill at anotherlocation.

BTU British thermal unit

BVM Bays Village of Maryland

C Celsius

C cut

CAD computer-aided design

CAMMS Condensed Army Mobility Modeling System

California Bearing Ratio (CBR) A measure of the shearing resistance of a soil undercarefully controlled conditions of density and moisture.

CDR commander

CE 55 Laboratory compactive effort (CE) accomplished by the impact of 55 hammerblows per layer.

Glossary - 2

Page 458: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

CES civil engineering squadron

CEV combat engineer vehicle

cf cubic feet

cfs cubic feet per second

CH clays, high compressibility (LL>50)

CI cone index

centerline

CL clays, low compressibility (LL<50)

cm centimeter

cm/sec centimeters per second

CMD command

CMP corrugated metal pipe

co company

coarse-grained soil A free-draining soil of which more than 50 percent by weight of thegrains will be retained on a No. 200 sieve. For traffic ability purposes, theseare dry beach and desert soils usually containing less than 7 percent ofmaterial passing the No. 200 sieve. Gravels are not considered to pose atrafficability problem.

compacted cubic yards (CCY) A measurement of compacted soil.

compaction Process of mechanically densifying a soil, normally by the application of amoving (or dynamic) load.

compactive effort (CE) Method used to compact the soil.

cone index (CI) An index of the shearing resistance of soil. The CI is obtained with acone penetrometer. The number represents resistance to penetration into thesoil of the 30-degree cone with a 1/2-square-inch base area (actual load inpounds on cone base area in square inches), using a dial calibrated toproduce an index of 300 when 150 lb of pressure are exerted on the handle.The CI reading is normally taken at the 0-inch (base of the cone) and atevery 3-inch interval down to 18 inches or until the dial reaches themaximum of 300. A number of tests will be taken and each specifiedinterval reading will be averaged. That average becomes the CI for the inchlevel.

CONUS

CPT

continental United States

captain

Glossary - 3

Page 459: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

critical layer

crown

crown

CSS

cu cm

cu ft

CUCV

culvert

cut or cutting

cut slope

cy

DA

DBH

DD

Dec

deg

dept

The soil layer that determines the rating cone index (for fine-grained soil) orcone index (for coarse-grained soil) of the area considered. Its depth varieswith the soil profile and the weight and type of vehicle. Generally, thecritical layer for fine-grained soils is 6 to 12 inches below the surface whensubjected to passes of a vehicle. For coarse-grained soils, the critical layer isusually from the surface to a 6-inch depth for all vehicular passes.

The difference in elevation between the centerline and the surface edge. Thecrown expedites surface-water runoff on the road. The amount of crowndepends on the surface used. Surfaces such as concrete or bituminousmaterials require little crown because of their impermeability, but permeablesurfaces such as earth or gravel require a large crown.

The outside top of the culvert.

cationic slow setting

cubic centimeter

cubic foot

commercial utility cargo vehicle

An enclosed waterway used to pass water through a structure consisting ofan embankment or fill.

That portion of through construction produced by the removal of the naturalformation of earth or rock, whether sloped or level. The terms sidehill cutand through-hill cut describe the resulting cross sections commonly encountered.

The slope from the top of a cut to the ditch line (bottom of ditch). Sometimesit is called the back slope.

cubic yard

Department of the Army

diameter at breast height

Department of Defense

December

degree

department

design hourly volume (DHV) The number of vehicles that a road may typically be expectedto accommodate in an hour. The DHV is 15 percent of the ADT.

design speed The speed for which a facility is designed. Pertinent geometric features, suchas horizontal curves and grades, may be based on design speed.

Glossary - 4

Page 460: Army Construction Manual FM5 430 Vol1 Entire

FM 5a-a430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

design storm

detention

dia

dip

ditch slope

diversion ditch

DMZ

drop

DT

E

elev

EM

EM

Engr

EOD

erosion

EW

F

F

Feb

fill or filling

fill slope

The storm of greatest intensity for a given period. For example, a “2-yeardesign storm” is a storm expected to be equalled once in 2 years.

The storage of water in depressions in the earths surface.

diameter

A paved ford used for crossing dry, wide, shallow arroyos or washes in semi-arid regions subject to flash floods.

The slope of the ditch extending from the outside edge of the shoulder to thebottom of the ditch. This slope should be relatively flat to avoid damage tovehicles driven into the ditch and to permit easy recovery.

A ditch used to transport water away from roadways or airfields.

demilitarized zone

A structure that absorbs the impact energy of water as it falls vertically to alower level waterway.

ditch time

east

elevation

engineer manual

enlisted member

engineer

explosive ordnance disposal

The transportation of weathered materials by wind or water.

east-west

fill

Fahrenheit

February

Material used to fill a receptacle, cavity, passage, or low place, Usingmaterial to fill a cavity or low place.

The incline extending from the outside edge of the shoulder to the toe (bottom)of a fill.

fine-grained soil A silt or clay soil of which more than 50 percent by weight of the grainswill pass a No. 200 sieve (smaller than 0.074 millimeter in diameter).

Glossary - 5

Page 461: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFAPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

FM field manual

ford A shallow place in a waterway where the bottom permits the passage ofpersonnel and vehicles.

fpm feet per minutefps feet per second

frost action Processes which affect the ability of soil to support a structure whenaccumulated water in the form of ice lenses in the soil is subjected tofreezing conditions.

frost-susceptible soil Soil in which significant ice segregation will occur when thenecessary moisture and freezing conditions are present.

ft feet

FT Fort

ft/ft feet per foot

ft/in feet per inch

square feet per square yard

G gravel

natural

gabion Large, steel wire-mesh baskets filled with stones, usually rectangular inshape and variable in size. They are designed to solve the problem of erosion.

gal gallon

gal/lb gallons per pound

gallons per square yard

GC clayey gravel

geometric design (geometry or geometric features) Refers to all visible features of theroad such as lane width, shoulder width, and alignment.

GLE

GM

gm

GP

grade

ground icing

grade-line elevation

silty gravel

gram

poorly graded gravel

To level off to a smooth horizontal or sloping surface.

An icing whose source of water is from groundwater flow above permafrost.

Glossary - 6

Page 462: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

groundwater table The upper limit of the saturated zone of free water.

gunite A mixture of cement, sand, and water sprayed from a high pressure nozzleonto a surface to protect it.

GW well-graded gravel

HMMWV high mobility, multipurpose wheeled vehicle

HP high point

HW high water

hydraulic gradient The slope in feet per foot of a drainage structure.

hydrologic cycle The continuous process in which water is transported from the oceans to

icing

in

infiltration

in/hr

in situ

interception

Jan

Jul

Jun

kg

kip

km

kph

laminar flow

lat

lb

LIP

the atmosphere to the land and back to the sea.

An irregular sheet or field of ice.

inch

The absorption of rainwater by the ground on which it falls.

inches per hour

Soil in its natural (undisturbed] state.

The holding of rainfall in the leaf canopy of trees and plants.

January

July

June

kilogram

kilopound (1,000 pounds)

kilometer

kilometers per hour

The type of flow that occurs when viscosity forces predominate and theparticles of the fluid move in smooth, parallel paths.

latitude

pound

length in place

Glossary - 7

Page 463: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

liq liquid

LL liquid limit

LOC lines of communication

LP low point

M silt

m meter

Mar March

mass diagram Earthwork volume plotted on graph paper, showing cut and fill operations.

max maximum

maximum towing force (T1) The maximum continuous towing force in pounds a vehiclecan exert. It is expressed as a ratio or percentage of vehicle weight.

MD Maryland

MH silt, high compressibility (LL>50)

mi mile

min minimum

min minute

ML silt, low compressibility (LL<50)

mm millimeter

MO maximum offset

MO Missouri

mobility index (MI) A number that results from a consideration of certain vehicle

MOPP

mph

MS

N

N

N/A

Glossary - 8

characteristics.

mission-oriented protective posture

miles per hour

medium setting

Slipperiness symbol meaning not slippery under any conditions.

north

not applicable

Page 464: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013,Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

NATO

NBC

NCO

NE

NFS

No.

Nov

NP

NRMM

NRS

NS

NSN

Ø

Ott

OL

P

PC

perm

permafrost

PFS

PI

PI

POL

pending

pop

R

Prime BEEF

North Atlantic Treaty Organization

nuclear, biological, chemical

noncommissioned officer

northeast

nonfrost susceptible

number

November

number of pipes

NATO Reference Mobility Model

naval radio station

north-south

national stock number

offset

October

order length

Slipperiness symbol meaning slippery when wet.

point of curvature

permanent

Constantly frozen ground.

possibly frost susceptible

plasticity index

point of intersection

petroleum, oils, and lubricants

The accumulation of water at the upstream end of a culvert.

population

probability

prime base engineer emergency forces

Glossary - 9

Page 465: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

psi pounds per square inch

PT point of tangency

PVC polyvinyl chloride

PVC point of vertical curvature

PVI point of vertical intersection

PVT point of vertical tangency

QSTAG Quadripartite Standardization Agreement

rating cone index (RCI) The measured cone index multiplied by the remolding index (RCI =CI x RI). The RCI expresses the soil-strength rating of a soil area subjectedto sustained traffic.

RC rapid curing

RED HORSE rapid engineering deployable heavy operational repair squadrons, engineering

remoldable sand A poorly drained, coarse-grained soil, usually containing 7 percent ormore material passing a No. 200 sieve. Poor internal drainage increases thewater content greatly influencing the trafficability characteristics andpermitting the remolding test to be performed. When wet, these soils reactto traffic in a manner similar to fine-grained soils and are more sensitive toremolding.

remolding The changing or working of a soil by traffic or a remolding test. The bene-ficial, neutral, or detrimental effects of remolding may change soil strength.

remolding index (RI) The ratio of remolded soil strength to original strength. Soil condit-ions that permit the remolding test to be performed with ease will usuallyresult in a loss of strength.

Reqd required

required towing force (T2) The force in pounds required to tow an operable, poweredvehicle on level terrain.

RI remolding index

riprap Rocks or rubble placed in the bottom and on the sides of a ditch to preventsoil erosions.

river icing An icing formed along rivers or streams and adjacent areas having a sourceof water above or below the riverbed.

roadbed The entire width of surface on which a vehicle may stand or move. Theroadbed consists of both the traveled way and the shoulders.

Glossary - 10

Page 466: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

road classification system An organized list of four road types based on the number ofvehicles each is designed to accommodate in a 24-hour period, Roadcharacteristics are based on average daily traffic.

roadway

RR

RRR

RS

RT

RTCB

RTO

S

S

S2

S3

sand grid

SC

SC

SCIP

SEATO

sec

Sept

SFC

shoulder

The entire width within the limits of earthwork construction and is measuredbetween the outside edges of cut or fill slopes. Roadway width does notinclude interceptor ditches if they fall outside the slopes, The roadway widthvaries from section to section depending on the height of cut or fill, depth ofditches, and slope ratios.

railroad

rapid runway repair

rapid setting

road tar

road tar cutback

radiotelephone operator

Slipperiness symbol meaning slippery at all times,

sand

Intelligence Officer (US Army)

Operations and Training Officer (US Army)

A honeycomb shaped geotextile measuring 20 feet by 8 feet by 8 inches deepwhen fully expanded. It is used to develop a beachhead for logistics-over-the-shore operations. It is also useful in expedient revetment construction.

supply catalog

slow curing

scarify and compact in place

Southeast Asia Treaty Organization

second

September

sergeant first class

That part of the top surface of an approach embankment, causeway, or cutimmediately adjoining the roadway that accommodates stopped vehicles inemergencies and laterally supports base and surface courses.

Glossary - 11

Page 467: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

shoulder slopes These may be the same as the traveled way, but usually they are greaterbecause shoulders are more previous than the surface course.

sight distance restriction factor The percent of the total length of the road on which the

slipperiness

slope

slope ratio

SM

SOP

SP

spring icing

sq

sq ft

sq in

Sr

SS

SSG

sta

STANAG

stickiness

stilling basin

sight distance is less than 1,500 feet.

The low traction capacity of a thin soil surface owing to its lubrication bywater or mud without the occurrence of significant vehicle sinkage.

The inclined surface of an excavated cut or an embankment.

The relative steepness of the slope expressed as a ratio of horizontal distanceto vertical distance. Thus, a 2:1 slope ratio signifies that for every 2 feethorizontally there is a rise or fall of 1 foot. The value of the slope ratio usedin construction depends on the properties of the soil and the vertical heightof the slope. Ditch slopes may also be governed by the amount of water to bedrained and the possibility of erosion.

silty sands and poorly graded sand-silt mixture

standing operating procedure

poorly graded sand

An icing whose source of water is from subpermanent levels.

square

square feet

square inch

senior

slow setting

staff sergeant

station

Standardization Agreement

The ability of a soil to adhere to the vehicle undercarriage or running gear.

A structure used to protect the culvert outlet against erosion.

subbase or subgrade Describes the in situ soil on which a road, airfield, or heliport isbuilt. The subgrade includes soil to the depth that may affect the structuraldesign of the project or the depth at which climate affects the soil.

subsurface water Water beneath the surface of the land.

Glossary - 12

Page 468: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

superelevation The transverse downward slope from the outside to the inside of thetraveled way on a curve. It is usually expressed in inches of drop perhorizontal foot or foot-drop per horizontal foot.

surface course The surface course provides a smooth, hard surface on which the trafficmoves. It may be constructed from asphalt or tar products, concrete, gravel,or compacted earth with certain types of binders. The surface course shouldbe all-weather and should provide for the rapid runoff of water. The use oftreated surfaces is limited to roads that have a long design life. A divisionalroad with a life expectancy of 6 months or less will receive only an earth orgravel surface.

SUSV small-unit support vehicle

SW southwest

SW well-graded sand

T1 maximum towing force

T2 required towing force

TBM temporary bench mark

TC training circular

temp temperature

time of concentration (TOC) The time it takes for an entire drainage basin to begincontributing runoff to a drainage structure.

TM technical manual

TN air transport

TO theater of operations

TOE table(s) of organization and equipment

TP transition point

traction capacity The ability of soil to resist the vehicle tread thrust required for steeringand propulsion.

traffic lane The traffic lane consists of the road surface over which a single lane of trafficwill pass,

transpiration The process by which water that has traveled from the ground through theplant’s system is returned to the air through the leaf system.

traveled way The road surface upon which all vehicles move or travel. For a single-laneroad, the traveled way is the same as one traffic lane. For a multilane road,the traveled way is the sum of the traffic lanes, If a surface course isprovided, it normally extends only across the traveled way.

Glossary - 13

Page 469: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

turbulent flow The type of flow that occurs when viscosity forces are relatively weak andthe individual water particles move in random patterns within the aggregateforward-flow pattern.

US United States

USAES US Army Engineer School

U s e s Unified Soil Classification System

UXO unexploded ordnance

VC vitrified clay

vehicle cone index (VCI) The index assigned to a given vehicle that indicates the minimumsoil strength in terms of rating cone index (or cone index for coarse-grainedsoil) required for one pass or other passes (VCI) of the vehicle.Usually one and fifty passes are used as extremes.

VMC

Vol

W1

W2

w/

w/o

WF

wp

W.R.C.

wt

WT

yd

yr

<

>

visual meteorological conditions

volume

weight of a towing vehicle

weight of a towed vehicle

with

without

waste factor

wetted perimeter

wire rope cable

weight

weight type

yard

year

less than

less than or equal to

greater than

greater than or equal to

change of grade

Glossary - 14

Page 470: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

REFERENCES

SOURCES USEDThese are the sources quoted or paraphrased in this publication.

Standardization Agreements (STANAGs and QSTAGs)

QSTAG 306, Fortification for Parked Aircraft 14 June 1978.STANAG 2929. Airfield Damage Repair. 11 January 1989.STANAG 3346 AML (Edition 4). Marking and Lighting of Airfield Obstructions.

17 October 1988.STANAG 3601 TN (Edition 3). Criteria for Selection and Marking of Landing Zones for Fixed

Wing Transport Aircraft. 2 July 1985.STANAG 3619 AML (Edition 2, Amendment 2). Helipad Marking. 7 October 1980.STANAG 3652 AML (Amendment 3). Helipad fighting, Visual Meteorological Conditions.

1 March 1979.STANAG 3685 AML. Airfield Portable Marking. 26 April 1988.

Joint and Multiservice Publications

AR 415-30/AFR 93-10. Troop Construction and Engineering Support of the Air ForceOverseas. 15 May 1979.

FM 5-430-00-2/AFPAM 32-8013, Vol 2. Planning and Design of Roads, Airfields, and Heli-ports in the Theater of Operations: Volume 2, Airfield and Heliport Design. To be published

within six months.FM 5-530. Materials Testing. (NAVFAC MO-330; AFM 89-3.) 17 August 1987.TM 5-624. Maintenance and Repair of Surface Areas. (NAVFAC MO-102: AFR 85-8.)

31 March 1977.TM 5-822-2. General Provisions and Geometic Design for Roads, Streets, Walks, and

Open Storage Areas. (NAVFAC DM-5.5; AFM 88-7, Chap 5,) 14 July 1987.TM 5-822-5, Pavement Design for Roads, Streets, Walks, and Open Storage Areas.

(AFM 88-7, Chap 1.) 12 June 1992,TM 5-825-2. Flexible Pavement Designs for Airfields. (NAVFAC DM-21.3; AFM 88-6.)

1 August 1978.TM 5-852-7. Surface Drainage Design for Airfields and Heliports in Arctic and SubarcticRegions (AFM 88-19, Chap 7.) 15 April 1981,

Air Force Publications

AFR 93-2. Contingency Response Planning. 19 January 1990.

Army Publications

FM 5-34. Engineer Field Data. 14 September 1987,FM 5-36. Route Reconnaissance and Classification. 10 May 1985.FM 5-233. Construction Surverying. 4 January 1985.FM 5-250. Explosives and Demolitions. 15 June 1992.FM 5-410. Military Soils Engineering. 23 December 1992.FM 5-434. Earthmoving Operations. 30 September 1992.

References - 1

Page 471: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

FM 5-446. Military Nonstandard Fixed Bridging. 3 June 1991.MIL-STD-621. Test Methods for Pavement Subgrade, Subbase, and Base Course Material.

22 December 1964.SC-6635 -98-CL-E02-HR. Hand Receipt Catalog Covering Content of Test Set, Soil.

19 April 1982.Special Report 83-27. Revised Procedures for Pavement Design Under Seasonal Frost

Conditions, US Army Corps of Engineers. Office of the Chief of Engineers, Washington,DC 20314. September 1983.

TM 5-232. Elements of Surveying. 1 June 1971.TM 5-302-Series. Army Facilities Components System: Design. 28 September 1973.TM 5-332. Pits and Quarries. 15 December 1967.TM 5-337. Paving and Surfacing Operations. 21 February 1966.TC 5-340. Air Base Damage Repair (Pavement Repair]. 27 December 1988.

Nonmilitary Publications

ASTM D1557. Soil and Soil Aggregate Mixture Using 10 Pounds 4.54KJ Rammer and 18-Inch457 mm Drop, Moisture Density Relation of 27 Apr 78. 1989.

ASTM D1633. Compression Strength of Molded Soils Cementing Cylinders. 1990.ASTM D3786. Test Method for Hydraulic Bursting Strength of Knitted Goods and Nonwoven

Fabrics: Diaphragm Bursting Strength Tester Method. 1987.ASTM D4533. Test Method for Trapezoid Tearing Strength of Geotextiles. 1991.ASTM D4632. Test Method for Breaking Load and Elongation of Geotextiles (Grab Method).

1991.ASTM D4833. Test Method for Index Puncture Resistance of Geotextiles Geomembranes,

and Related Products. 1988.

DOCUMENTS NEEDEDThese documents must be available to the intended users of this publication.

DA Form 1248. Road Reconnaissance Report. July 1960.DA Form 1711-R. Engineer Reconnaissance Report (LRA). May 1985.DA Form 2028. Recommended Changes to Publications and Blank Forms. February 1974.DD Form 2641. Trafficability Test Data. August 1993

References - 2

Page 472: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013. Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

INDEX

A

AASHTO. See American Association of State Highway and Transportation Officials(AASHTO) method T96.

abnormal strength profile, 7-8

ADR. See airfield and heliport maintenance, air base damage repair (ADR).

ADT. See average daily traffic (ADT).

aerial photo, 7-28

aggregate, 9-55bituminous construction, 9-47desirable characteristics, 9-47identification, 9-47rolling, 9-56spreading, 9-56traffic control, 9-57. See also road maintenance, with traffic and baton method.

AHD. See average haul distance (AHD).

airfield and heliport maintenance, 8-17air base damage repair (ADR). 8-17

Air Force responsibilities, 8-17Army responsibilities, 8-17

ice control, 8-20. See also ice control.maintenance during flying operations, 8-21mud control, 8-18rehabilitation of captured airfields, 8-21snow removal, 8-20turf surfaces, 8-18

alignment, 2-3, 9-6

alluvial terraces, 2-2

American Association of State Highway and Transportation Officials (AASHTO) method T96,9-48

Army track. See roads, Army track.

asphalt distributor, 9-57

asphalt pavement, minimum thickness, 9-71

asphalts and tars, 9-45

average daily traffic (ADT), 9-4

average haul distance (AHD), 3-23

B

balance lines, 3-22

baton method, 8-11. See also road maintenance, with traffic

base course, 5-10compaction, 5-11gradation, 5-11liquid limit, 5-11

Index - 7

Page 473: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

materials, 5-11, 5-12natural materials, 5-13other materials, 5-14plasticity index, 5-11processed materials, 5-13requirements, 5-11

base flow, 6-9

berm, 6-51

bituminousbase, 5-15materials, 9-41pavements, 9-69

cold-laid, bituminous-concrete plant mix, 9-69design, 9-71design steps, 9-73hot-mix, bituminous-concrete, 9-69penetration macadam, 9-69road mix, 9-69sand asphalt mix, 9-69sand-tar mix, 9-69sheet asphalt mix, 9-69stone-filled sheet asphalt mix, 9-69types and uses, 9-69

bituminous surfaces. See maintenance, bituminous surfaces.

blind drain. See subsurface drainage, techniques, blind drains.

box-culvert flow, 6-77

bridge approaches, 2-3

bridges, 6-113. See also road maintenance, fords and bridges.

Bureau of Reclamation, 6-125

burning pits, See forest clearing considerations, waste areas, burning pits,

cC variable, See rational method of estimating runoff, formula variables, C variable.

CAD, See end-area-determination method, computer -aided design (CAD).

calcium chloride, 8-7, See also ice control, calcium chloride and maintenance, gravelsurfaces, use of calcium chloride,

CAMMS. See Condensed Army Mobility Modeling System,

camouflage. See forest clearing considerations, camouflage and tactical considerations,camouflage.

causeways, 6-112

CBR, 5-1. See also design CBR, values and roads, CBR requirements.

cement grades, 9-45

channel flow. See ditches, types of flow, channel.

channelsconstruction and maintenance, 6-53special, 6-51

Index - 2

Page 474: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

gutters, 6-51median, 6-51

characteristics of grasses, 8-19

check dams, 8-3

chespaling. See roads, chespaling.

chord-length calculations, 9-14

CI. See cone index (CI).

clearing equipment. See clearing, stripping, and grubbing; clearing with equipment,

clearing, stripping, and grubbing, 4-1clearing with equipment, 4-6

extreme slopes, 4-12grader, 4-15large trees, 4-9medium trees, 4-8ripper, 4-15Rome plow, 4-10small trees, 4-8tractor-mounted winches, 4-13tree dozer, 4-10truck-mounted winches, 4-14winches, 4-13windrowing. 4-11

clearing with explosives, 4-15boulders, 4-15trees and stumps, 4-15

felling equipment, 4-14limitations of engineer equipment, 4-7, 4-8performance techniques, 4-6proper application of engineer equipment, 4-6removing buried explosives, 4-17

unexploded ordnance (UXO), 4-17removing structures, 4-17removing surface rocks, 4-15stripping, 4-17unsuitable soil, 4-17

climate classifications of forests, 4-1dry forests, 4-2monsoon forests, 4-2rain forests, 4-2temperate forests, 4-1

CMP, See culverts, corrugated metal pipe (CMP).

coarse-grained soils, 7-37, See also strength profile, coarse-grained soils.operations, 7-26

cold climates, hydraulic criteria, 6-102

compaction, 5-4clays that lose strength, 5-6select materials, 5-9silts, 5-6subbase materials, 5-9swelling soils, 5-7

Index - 3

Page 475: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1

Condensed Army Mobility Modeling System (CAMMS), 7-1

cone index (CI), 7-2range, 7-5requirements, equipment, D-1

cone penetrometer, 7-4

constructionairfield, 1-2

Air Force responsibilities 1-2Army responsibilities, 1-2

drainage, 6-1methods, 9-49operations, 5-15

blending and mixing, 5-16compacting, 5-16fine grading, 5-15finishing, 5-17hauling: placing, and spreading, 5-16watering base materials, 5-16

road, 1-2

construction stakes, 3-3alignment, 3-3centerline, 3-3culvert, 3-6finish-grade, 3-5hub, 3-3offset, 3-5reference, 3-6slope, 3-4

construction surveys, 3-1bench marks, 3-6earthwork estimation, 3-6final location, 3-2

horizontal control, 3-2vertical control, 3-2

layout, 3-2preliminary, 3-2reconnaissance, 3-2

coral, See maintenance, coral surfaces.

corduroy. See roads, corduroy-surfaced.

corrugations, 8-6

cutbacks, 9-45

covered-aggregate surface treatment. See surface treatments, covered aggregate,

critical layer, 7-3depth variations, 7-3

critical slope, 6-77

crowned section, 9-25

culverts, 6-59alignment, 6-60

Index - 4

Page 476: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

assembling nestable CMP, 6-59backfill, 6-70bedding (foundations), 6-68concrete box, 6-60concrete pipe, 6-59corrugated metal pipe (CMP), 6-59cover, 6-63depth of fill, 6-63design, 6-73

with submerged inlets, 6-77with unsubmerged inlets, 6-78

erosion control, 6-72headwalls, wing walls, and aprons, 6-71hydraulics, 6-73maximum permissible cover for CMP, 6-68maximum permissible cover for corrugated alumin urn-alloy pipe, 6-69slope, 6-62types and designs, 6-59

construction, 6-60design, 6-73expedient, 6-60permanent, 6-59

curves1-degree method, 9-8, F-1compound, 9-7horizontal, 9-7

design, 9-10point of curvature (PC), 9-7point of intersection (PI), 9-7point of tangent (PT), 9-7

reverse, 9-6simple, 9-6spiral, 9-7vertical, 9-19

allowable rate of change of grade (r), 9-20change of grade (AG), 9-20design, 9-20

elements, 9-19frequency of placing survey stakes, 9-20length determination, 9-20length factor (k), 9-20sight distance (S), 9-20

types, 9-19using metric units, 9-25

curve tables, F-1

cut operation, 3-20

DDBH. See tree diameters at breast height (DBH)

designindex, 9-59

Index - 5

Page 477: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

pneumatic-tired vehicles, 9-59life, 9-60special considerations, 9-75

frost, 9-75stabilized soil, 9-75

design CBRbase course, aggregate surfaces, 9-63base course, flexible pavement, 9-70values

selection, 5-10subsoil, 5-7subgrade, 5-7

design considerations, 5-1pavement structures, 5-1

design hourly volume (DHV), 9-4

detention. See drainage, hydrology, detention.

DHV. See design hourly volume (DHV).

dips, 6-111

dissipators, 6-125

ditchesdesign considerations, 6-45

location, 6-45proposed lining, 6-45quantity of runoff (Q), 6-45slope (S), 6-45

design techniques, 6-46steps, 6-46

diversion, 6-38interceptor, 6-38longitudinal slope or grade (S), 6-43nonsymmetrical, 6-39side, 6-38side-slope

back, 6-39ditch, 6-39front, 6-39nonsymmetrical, 6-39ratio, 6-39symmetrical, 6-39

trapezoidal, 6-39triangular, 6-39types of flow, 6-40

continuous, 6-40laminar, 6-40open channel, 6-40steady, 6-40turbulent, 6-40uniform, 6-40

V-type, 6-39velocity of flow (V), 6-42

ditching, 6-3

Index - 6

Page 478: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

interception, 6-3drags, 8-4

drainage. See also construction, drainage.base, 6-92design in arctic and subarctic regions, 6-102hydrology, 6-4

detention, 6-4infiltration, 6-4intercepting, 6-92interception, 6-4precipitation, 6-4runoff, 6-4, 6-8storms, 6-4subgrade, 6-92transpiration, 6-4weather data, 6-6

drainage-system design, 6-11available resources, 6-11design data requirements, 6-11meteorological data, 6-11procedures, 6-11

delineating watersheds, 6-13designing for maximum runoff, 6-19determining area contributing runoff, 6-12determining size, 6-17establishing drainage-structure locations, 6-12estimating quantity of runoff, 6-19

soil characteristics, 6-11topographical information, 6-11

drop inlets and gratings, 6-89construction, 6-89maintenance, 6-91

dry season, 7-27

dust control, 8-5

dustproofing, 9-51

Eearthwork, 2-3

operations, 2-3

earthwork volume sheet, 3-18

edge raveling, 8-8

emulsions, 9-47

end-area-determination methods, 3-7computer -aided design (CAD), 3-13double-meridian triangle, 3-10planimeter, 3-12stripper, 3-9trapezoidal, 3-7

Index - 7

Page 479: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

engineering fabrics, 9-77.

engineering study, 1-3

entrances. See entrances, exits, and segments.

entrances, exits, and segments, 9-60.

environmental conditions, 4-1

EOD, See explosive ordnance disposal (EOD).

equivalency factors, application, 9-75

erosion control, 6-54, 6-114. See also culverts, erosion control,culvert outlets, 6-124culvert transitions, 6-124plain outlets, 6-124stilling basins, 6-125

estimating runoff. See rational method of estimating runoff.

exits. See entrances, exits, and segments.

explosive ordnance disposal (EOD), 4-17

external distance, 9-9

F

fabrics, 9-77

field identification, 9-41

fill operation, 3-20

fine-grained soils, 7-36. See also strength profile, fine-grained soils.

flexible-pavement structure, 9-69bituminous-pavement mix, 9-71bituminous-pavement thickness requirement, 9-71compaction requirements, 9-71materials, 9-70minimum base-course thickness, 9-71select materials and subbase, 9-70supply sources, 9-70typical flexible-pavement section, 5-1

flight-way obstructions, 2-4glide angle, 2-4

flow. See ditches, types of flow.

fords, 6-107, See also road maintenance, fords and bridges.approaches, 6-110bottom material, 6-108channel condition, 6-110construction, 6-110cross section, 6-110flood flow 6-110high-water determination, 6-109maintenance, 6-111marking. 6-111reconnaissance, 6-108requirements, 6-108

Index - 8

Page 480: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

stream velocity, 6-110

forest clearing considerations, 4-4airfield approach zones, 4-6camouflage, 4-4disposal, 4-5permafrost, 4-4safety, 4-4temporary drainage, 4-4timber salvage, 4-4waste areas, 4-5

burning, 4-5burning pits, 4-5clearing and piling stumps, 4-6dumps, 4-5fire control, 4-5log piles, 4-6off-site areas, 4-5revetments, 4-5

forest types, 4-1. See also climate classifications of forests.

French drain. See subsurface drainage, techniques, French drains.

frostboils, 8-16heaves, 8-16special considerations, 5-15

frost action potential, 5-10

frost design for roads, G-1

frost susceptibility of subgrade, 5-8

future expansion, 2-5

Ggabions, 6-119

installation, 6-120uses, 6-122

geofabrics, 9-77

geologic and permafrost conditions, 4-2hardpan or rock, 4-2inundated, marshy, and boggy areas, 4-2permafrost, 4-2

geology, 2-2rock outcropping, 2-2sedimentary rocks, 2-2

geometric design process, 9-1

geometric formulas, B-1

geotextiles, 9-77

glide angle. See flight-way obstructions, glide angle,

grade determination, 9-19

Index - 9

Page 481: Army Construction Manual FM5 430 Vol1 Entire

FM 5--430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

grade line, 5-4

grader. See clearing, stripping, and grubbing; clearing with equipment,

gradation requirements, 9-29

grasses. See characteristics of gasses.

grating, 6-89

ground cover, 2-4

gunite lining, 6-115

H

horizontal-curve elements. See curves, horizontal.

hydrophobic, 9-48

hydraulic criteria for cold climates. See cold climates, hydraulic criteria.

hydraulic gradient, 6-74

hydraulic radius (R), 6-45calculating, 6-46

hydraulics of culverts. See culverts, hydraulics.

hydraulic tables and curves, C-l

hydrography construction, 6-10

hydrologic tables and curves, C-1

hydrology. See drainage, hydrology.

I

I variable. See rational method of estimating runoff, formula variables, I variable.

ice control. See also airfield and heliport maintenance, ice control and road maintenance,winter, surface ice control,

abrasives, 8-15calcium chloride, 8-15mechanical removal, 8-15salts, 8-15

ice road. See roads, snow and ice.

icing, 6-105ground, 6-106, 6-107measures against, 6-107river, 6-106, 6-107spring, 6-107types, 6-105

infiltration. See drainage, hydrology, infiltration.

intensity-duration curves. See standard rainfall intensity-duration curves.

interception. See drainage, hydrology, interception and drainage, interception.

Index-10

Page 482: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

L

lag time, 6-9

laminar flow. See ditches, types of flow, laminar.

land clearing, 4-1

landing mats. See roads, landing mats.

layout techniques, 9-15

length of curve (L), 9-9

level terrainall-wheeI drive vehicles, 7-12, 7-25self-propelled vehicles, 7-12tracked vehicles, 7-12, 7-24vehicles towing inoperable, powered vehicles, 7-17, 7-18vehicles towing other vehicles, 7-14

load distribution, 5-2

LOC. See preconstruction phase, location factors, lines of communication (LOC).

Mmacadam, 5-14

applying screenings, 5-17compacting, 5-17preparing subgrade, 5-17special procedures for base, 5-17spreading, 5-17

maintenancebituminous surfaces, 8-7

inspection, 8-7patches, 8-7maintenance of shoulders, 8-7temporary repairs, 8-7

coral surfaces, 8-8crater repair, 8-8drainage, 8-2

culverts, 8-3ditches, 8-3shoulders, 8-3surface, 8-3

gravel surfaces, 8-5repair of potholes, 8-6treatment of corrugations, 8-6use of calcium chloride, 8-7

inspections, 8-2drainage, 8-2surface, 8-2

materials, 8-2nonpaved surfaces, 8-3oiled surfaces, 8-5processed material surfaces, 8-7rigid pavements, 8-8

Index - 11

Page 483: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

stabilized soil surfaces, 8-8potholes, 8-8ravels, 8-8

maintenance and repair of surfaces, 8-1, 9-58activities, 8-1bituminous inspection, 9-58guidelines, 8-1operations, 8-2patches, 9-58shoulders, 9-58temporary repairs, 9-58

Manning’s velocity of flow, 6-42

mapsgeologic, 7-29soils, 7-29topographic, 7-29

marginal material, 2-4

mass diagram, 3-19construction, 3-20limitations, 3-28properties, 3-20, 3-21

maximum haul distance, 3-22

metric conversions, A-1

MI. See mobility index (MI).

middle ordinate, 9-9

mobility index (MI), 7-19calculating, 7-20limitations, 7-23

mud con trol. See airfield and heliport maintenance, mud control.

multiple surface treatment. See surface treatment, multiple.

N

NATO Reference Mobility Model (NRMM), 7-1, 7-26

NRMM. See NATO Reference Mobility Model (NRMM).

node, 3-20

0

obstacle crossings, 2-3

obstacles, 7-10, 7-11

off-road speed map, 7-31

Office of the Chief of Engineers, 2-7

one-pass performance, 7-12

open channels. See also ditches, types of flow, open channel.design equations, 6-42

Index - 12

Page 484: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

continuity, 6-42Manning’s velocity of flow, 6-42roughness coefficient (n), 6-42

design factors, 6-38cross section, 6-38location, 6-38

open storage area, special considerations, 9-75

organic-soil areas, 7-10

P

paving, 6-115

peak flow, 6-10

performance categories, 7-19

permafrost, special considerations, 5-15. See also forest clearing considerations,permafrost and geologic and permafrost conditions.

plank-tread road. See roads, plank-tread.

planning considerations, 1-1

plastic grid. See sand grid, plastic grids.

pending, 6-84advantages, 6-89analysis, 6-87areas, 6-84

potential landing zone, 7-32

precipitation. See drainage, hydrology, precipitation,

preconstruction phase, 2-1location factors, 2-1

existing facilities, 2-1lines of communication (LOC), 2-1location and design, 2-1minimum rehabilitation, 2-1soil characteristics, 2-2soil investigation prior to construction, 2-2

preswelling, 5-7

prime coat, 9-49base preparation, 9-49materials, 9-49

R

radius of curvature, 9-9

rating cone index (RCI), 7-2, 7-9

rational method of estimating runoff, 6-22application, 6-28assumptions, 6-22estimating flow time for multiple cover, 6-28estimating flow time for single cover, 6-26

Index - 13

Page 485: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

formula, 6-22formula variables, 6-22

C variable, 6-22determining TOC, 6-24I variable, 6-24time of concentration, 6-24

RCI. See rating cone index (RCI).

reconnaissance, 2-5air, 2-8airfield, 2-14, 2-15

air, 2-15ground, 2-17

airfield-siting template, 2-15, 2-16briefing, 2-6engineer, 2-14existing roads, 2-11glide-angle requirements, 2-15ground, 2-8ground reconnaissance report, 2-19

undeveloped airfield site, 2-19captured enemy airfield, 2-21

location, 2-11map and air studies, 2-9new airfields, 2-15party, 2-5personnel suitable, 2-9planning, 2-6preliminary study, 2-7preparation, 4-2reporting, 2-8route and road, 2-11selecting runway location, 2-15steps, 2-6

referencing point, 3-6

remolding index (RI), 7-1

repair of runways, 8-19

required areas, 2-4

revetments. See forest clearing considerations, waste areas, revetments,

RI, See remolding index (RI).

ripper. See clearing, stripping, and grubbing; clearing with equipment; ripper.

riprapdesign, 6-118placement, 6-116protection, 6-116size selection, 6-116

road design, 9-1geometric process, 9-1grade and alignment, 9-6

road maintenance, 8-9fords and bridges, 8-16. See also fords and bridges,

Index - 14

Page 486: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

patrols, 8-10repair crews, 8-10winter, 8-12

snow-removal equipment, 8-13, 8-14surface ice control, 8-15

with traffic, 8-11. See also baton method.

road tars, 9-47

roadsaggregate-surfaced, 9-62

base course, 9-63CBR requirements, 9-63compaction criteria, 9-63compaction requirements, 9-64design curves, 9-65design steps, 9-66materials, 9-62select and subbase materials, 9-63

Army track, 9-32chespaling, 9-31classes, 9-59corduroy-surfaced, 9-30

heavy, 9-30standard, 9-30types, 9-30with stringers, 9-30

expedient -surfaced, 9-30landing mats, 9-32plank-tread, 9-32snow and ice, 9-35unsurfaced, 9-61wire-mesh, 9-35

Rome plow. See clearing, stripping, and grubbing, clearing with equipment; Rome plow.

roughness, 6-77

rubble, 5-15

runoff. See drainage, hydrology, runoff.

Ssafe-slope ratios, 2-2

salts. See ice control, salts.

sand grid, 9-36installation, 9-37plastic grids, 9-36

scour, types of, 6-73

sediment control, 6-54

segments. See entrances, exits, and segments.

select materials, 5-8, 5-9

shoulders and similar areas, 9-75

shrinkage, 3-17

Index - 15

Page 487: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430--00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

single surface treatment. See surface treatments, single.

site selection and reconnaissance, 2-1drainage, 2-2location factors, 2-1

slipperiness, 7-2, 7-10

slope, 7-10

slope negotiations, 7-11, 7-12all-wheel-drive vehicles, 7-11self-propelled vehicles, 7-11tracked vehicles, 7-11vehicles towing inoperable, powered vehicles, 7-18vehicles towing other vehicles, 7-15vehicles towing trailers, 7-14

snow and ice road. See roads, snow and ice.

snow removal. See airfield and heliport maintenance, snow removal and road maintenance,winter, snow-removal equipment.

soil characteristics. See drainage-system design, soil characteristics.

soil classification, 5-1, 7-29

soil conditions, mapping manually, 7-30

soil strength, 7-2

soil topography, 7-29

soil trafficabilitytest set, 7-3, E-1classification, 7-36, 7-37

species of trees and root systems, 4-3

sprayed asphalt with covered-aggregate. See surface treatments, sprayed aggregate with.

sprayed asphalt with single and multiple surface treatments. See surface treatments,sprayed aggregate with.

sprayed treatments, 9-41

St. Anthony Falls Hydraulic Laboratory, 6-125

stabilizedchemically, 5-7mechanically, 5-7

station adjustments, 9-13

stationing equations, 9-13

stakes. See construction stakes.

standard rainfall intensity-duration curves, 6-9

standards of trafficability, 2-11

stickiness, 7-2, 7-10

stilling basins. See erosion control, stilling basins.

storms. See drainage, hydrology, storms.

strength profile, 7-8coarse-grained soils, 7-9fine-grained soils, 7-8remoldable sands, 7-8

Index - 16

Page 488: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

stripping, 9-48

stripping test, 9-48

structural design, 9-27earth, 9-28gravel, 9-29processed materials, 9-30sand clay, 9-29stabilized soil, 9-28treated surface, 9-28

subbase compactionnormal cases, 5-6special cases, 5-6

subbase course, 5-8

subbase materials, 5-9

subgrades, 5-4

subgrade stabilization, 5-7

submerged inlets. See culverts, design, with submerged inlets,

subsurface drainage, 6-92filter design steps, 6-100filter material, 6-98

selection, 6-100pipe-laying criteria, 6-96system installation, 6-101techniques, 6-92

blind drabs, 6-94combination drainage systems, 6-95deep ditches, 6-92French drains, 6-94natural drainage channels, 6-93subsurface pipe, 6-94

successive areas, 6-33estimating runoff, 6-34

sunlit slopes, 2-4

superelevation, 9-25

surface treatments, 9-41covered aggregate, 9-54multiple, 9-54requirements, 9-53single, 9-52sprayed asphalt with, 9-51

surveys. See construction surveys.

swell test, 9-48

swelling, 5-7. See also compaction, swelling soils,

Ttack coat, 9-50

tactical considerations, 2-5

Index - 17

Page 489: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1FM 5-430-00-1/AFPAM 32-8013, Vol 1

camouflage, 2-5. See also forest clearing considerations, camouflage.defense, 2-5defilade, 2-5

tangents, 9-6distance, 9-9

terracing, 6-115

thickness requirements. See flexible-pavement structure, bituminous-pavement thicknessrequirements; unsurfaced soil thickness requirements; and flexible-pavement structure,minimum base-course thickness.

timber cruising, 4-4

lime of concentration (TOC), 6-10. See also rational method of estimating runoff, formulavariables, time of concentration.

TOC. See time of concentration (TOC) and rational method of estimating runoff, formulavariables, time of concentration,

topography, 2-2. See also drainage-system design, topographical information and soilstopography.

map, 7-29

traffic categories, 9-59tracked vehicles and forklifts, 9-60

trafficabilitybasic factors, 7-2characteristics of fine-grained soils and remoldable sand in wet weather, 7-35classifications of dry-to-moist, coarse-grained soils, 7-38estimating, 7-27evaluation factors, 7-10instruments and tests, 7-3mapping manually, 7-30measurements, 7-3, 7-5photomap, 7-28procedures in fine-grained soils and remoldable sands, 7-11standards, 2-11test data form, 7-7with weather, 7-2

transition point, 3-20

transpiration, See drainage, hydrology, transpiration,

tree diameters at breast height (DBH), 4-4

tuff, 5-15

turbulent flow. See ditches, types of flow, turbulent.

turfing, 6-115

U

Unified Soil Classification System (USCS), 5-4,

unsubmerged inlets. See culverts, design, with unsubmerged inlets.

unsurfaced roads. See roads, unsurfaced.

unsurfaced-soil thickness requirements, 9-62

Index - 18

Page 490: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFPAM 32-8013, Vol 1 FM 5-430-00-1/AFPAM 32-8013, Vol 1

USCS. See Unified Soil Classification System (USCS).

USCS soil-type description, 7-35

utilities, 2-4

UXO. See clearing, stripping, and grubbing; removing buried explosives; unexplodedordnance (UXO).

vVCI. See vehicle cone index (VCI).

VCI determination for new or unlisted vehicles, 7-19

vegetation, 7-10

vehicle classes, 7-19

vehicle cone index (VCI), 7-2calculating, 7-20, 7-26limitations, 7-23

velocity relationships, 6-45

vertical alignment, 9-18

volumecompacted, 3-17in-place, 3-17loose, 3-17of flow 6-10

volume-determination methods, 3-13average end area, 3-13average depth of cut or fill, 3-13grid, 3-15prismoldal formula, 3-13

V-type ditch. See ditches, V-type.

wwashboarding, 8-4

watersheds. See drainage-system design, procedures, delineating watersheds,

weather conditions, 7-27

wet season, 7-29

wet-weather trafficability characteristics, 7-35

wier notch, 8-3

windrowing. See clearing, stripping, and grubbing; clearing with equipment, windrowing.

wire-mesh road. See roads, wire-mesh.

witnessing point, 3-6

work, 3-23

world isohyetal map, 6-7

Index - 19

Page 491: Army Construction Manual FM5 430 Vol1 Entire

FM 5-430-00-1/AFJPAM 32-8013, VOL I26 AUGUST 94

By Order of the Secretary of the Army:

Official:

MILTON H. HAMILTONAdministrative Assistant to the

Secretary of the Army06955

GORDON R. SULLIVANGeneral, United States Army

Chief of Staff

By Order of the Secretary Air Force:

MERRILL A. McPEAKGeneral United States Air Force

Chief of Staff

Official:

JAMES E. McCARTHY, Maj General, USAFThe Civil Engineers

DISTRIBUTION:

Active Army, USAR, and ARNG: To be distributed in accordance with DA Form12-11E, requirements for FM 5-430-00-1, Vol I, Planning and Design of Roads,Airfields, and Heliports in the Theater of Operations - Road Design (Qty rqr. blockno. 0759).

U.S. GOVERNMENT PRINTING OFFICE:1994-528-027/20039