1 Asbestos Management 2020 EIC Training

Upload: others

Post on 30-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    Asbestos Management

    2020 EIC Training

  • 2

    Asbestos Management

    Trainer

    Jonathan Bass, Environmental Specialist

    Office of Construction

  • 3

    Standard Specifications Section 210

    Removal and Disposal of Asbestos-Containing Materials (Buildings, Bridges & Highways)

    ✓ Buildings – Thermal Insulations, Siding, Roofing, Caulks, Sealers,

    Flooring, Plasters, Ceiling Tile, etc.

    ✓ Bridges/Culverts – Bond Breakers, Joint Fillers, Caulks, Suspended

    & Encased Utilities, Steel Coatings, Masonry Coatings, etc.

    ✓ Highways – Buried Utilties, Sidewalk Joint Filler, etc.

  • 4

    Thermal System Insulation

  • 5

    Thermal System Pipe Insulation

  • 6

    Transite Siding

  • 7

    Asbestos Roofing

  • 8

    Asbestos Floor Tile & Mastic

  • 9

    Asbestos Ceiling Tile

  • 10

    BEARING PADS

  • 11

    Suspended Transite Pipes

  • 12

    Suspended Coated Utility

  • 13

    Steel Coating – Up Close

  • 14

    Steel Coatings – Outside Bays

  • 15

    Masonry Coating

  • 16

    Route 30 Mine Kill Masonry Coating Abatement

  • 17

    Mazur Furniture – I287 Westchester Masonry Coating

  • 18

    Railbed Curbing

  • 19

    Railbed Curbing – Close up

  • 20

    Defunct Residency – Copper Salvage

  • 21

    Sheetpacking

  • 22

    Transite Expansion Joint Housing

  • 23

    Joint Filler

  • 24

    Culvert Coatings

  • 25

    NYSDOT Blanket Variance 14

    • Statewide Application to Bridges and Highways

    • Applies to Non-friable Asbestos-Containing Materials (ACMs) on

    Bridges and Highways (no application to buildings).

    • Applicable to NYSDOT, Thruway, Canal Corp. and County Highway

    Projects (can also be used by private sector or municipal utility

    companies working within listed agency, authority or county right-of-

    way)

    • Cities, Townships and Villages Can Use as Model for Site Specific

    Variance Applications

    • Requires Renewal by Department Every Three Years

  • 26

    Project/Air Monitoring

    • Provided through Asbestos Term Agreement Consultant Forces

    • Three (3) Zonal Agreements (Upstate East, Upstate West & Downstate)

    • Managed by Main Office Consultant Management Bureau

    • Acts as EIC Inspection Staff for All Asbestos Abatement Work

    • Request for Use Made by Regional Construction Environmental

    Coordinator or Regional Environmental Unit

  • 27

    Section 210-3 Construction Details

    “The Contractor shall schedule a coordination meeting

    between the Asbestos Subcontractor and the

    Department Contracted Asbestos Project Monitor to be

    held at least two (2) weeks before the start of any

    asbestos abatement work.”

  • 28

    Recordkeeping

    • Project Record Documentation is Generated by Both the Asbestos

    Abatement Contractor and Project Monitoring Firms

    • Following Completion of Asbestos Abatement Work, Copies of All

    Asbestos Abatement Documentation is Retained by the Department

    for Project Record

    • Asbestos Bridge Abatement Project Records are Particularly

    Important Because of Future Rehabilitation and Demolition Work

  • 29

    Waste Disposal

    • All Friable Asbestos Waste Must Be Transported Under a Waste

    Shipment Record and Disposed of at a Waste Disposal Facility

    Permitted to Accept Friable Asbestos Waste (NYSDEC maintains

    a current list of permitted NYS facilities)

    • Friable Asbestos Waste Transport Also Requires a NYSDEC

    Permitted Hauler

    • Non-Friable Asbestos Waste May Be Disposed of at Sites

    Approved to Accept Construction & Demolition (C&D) Debris

    • Non-Friable Asbestos Waste Does Not Require A Waste

    Shipment Record or a NYSDEC Permitted Hauler for Transport.

    However, recent Part 360 revision does now require registration

    and tracking for C&D

    • C&D Disposal Receipts are Required

  • 30

    EB 16-048 – Section 210 CIM

    II. Procedure (Project Monitor Responsibilities)

    1. Reviewing & Approving Asbestos Contractor Pre-Abatement Submittals

    2. Maintaining Daily Asbestos Abatement Project Documentation for the EIC

    3. Ensuring Regulatory and Contractual Compliance by the Asbestos Contractor

    4. Conducting Any Necessary Compliance Air Monitoring & Lab Analysis

    5. Conducting Any Necessary Additional Bulk Sampling & Lab Analysis

    6. Performing All Final Clearance Inspections (authorizing 75% item payment)

    7. Verifying and Documenting All Removal Quantities for the EIC

    8. Reviewing & Approving Asbestos Contractor Post-Abatement Submittals

    9. Compiling All Asbestos Project Documentation for EIC Into Electronic File

    (includes waste disposal documentation and authorizing final 25% item

    payment)

  • 31

    EB 16-048 – Section 210 CIM

    III. Documentation Retention

    • Retain All Interim Daily Asbestos Abatement Project Documentation as

    Attachments to Corresponding DWRs. Together With Approved Pre-

    Abatement Submittals, This Represents the Project Record.

    • Final Electronic Asbestos Abatement Close-Out File(s) Received From

    the Project Monitor Shall be Retained for Long-Term Storage on

    Corresponding Project-Wise Folders. Construction Environmental

    Coordinator (CEC) Responsibility.

  • 32

  • 33

  • 34

  • 35

    I81 State Street Demo

  • 36

    I81 State Street Demo

  • 37

    Region 7 Masonry Coating Abatement

  • 38

    Region 7 Masonry Coating Abatement

  • 39

    Region 9 Route 17 Steel Coating Abatement

  • 40

    Masonry Coating Shrouded Tool Abatement

  • 41

    Steel Coating Shrouded Tool Abatement

  • 42

    More Steel Coating Shrouded Tool Abatement

  • 43

    Cross Westchester Transite Pipe Abatement

  • 44

    Cross Westchester Transite Pipe Abatement

  • 45

    Cross Westchester Transite Pipe Abatement

  • 46

    North-South Arterial

    Controlled Demolition

  • 47

    North South Arterial Controlled Demolition

  • 48

    North South Arterial Controlled Demolition

  • 49

    Questions???

  • 50

    Poll Question #1

    NYSDOT Blanket Variance 14 is not applicable to

    Asbestos Abatement for which Government Entity(s)?

    1. NYSDOT

    2. NYS Thruway

    3. NYS Canal Corp.

    4. County Highways

    5. City, Town & Villages

  • 51

    #1 Answer

    5. City, Town & Villages

    * Mention NYC Asbestos Regulations & NYSDOT Applicability (Region 11 and NYC Watershed)

  • 52

    Poll Question #2

    According to Standard Specification 210, the Contractor

    is responsible for coordinating an asbestos abatement

    start-up meeting between the Asbestos sub-contractor

    and the Department Project Monitor a minimum of how

    many weeks prior to the start of abatement work?

    1. One

    2. Two

    3. Three

    4. Four

  • 53

    #2 Answer

    2. Two Weeks

  • 54

    Poll Question #3

    Non-Friable Asbestos Waste Transport and Disposal

    Requires NYSDEC Permitted Haulers and Waste

    Shipment Records.

    TRUE OR FALSE?

  • 55

    #3 Answer

    FALSE

  • 56

    Poll Question #4

    The Department-Contracted Asbestos Project Monitor

    Acts as Separate Inspection Staff for the EIC and is

    Responsible for the Following:

    1. Pre-abatement Submittal Review & Approval

    2. Regulatory and Contractual Compliance by the

    Asbestos Abatement Sub-contractor

    3. Verification/Documentation of All Removed Asbestos

    Material Quantities

    4. Final Asbestos Close-out Reporting

    5. All of the Above

  • 57

    #4 Answer

    5. All of the Above

  • 58

    Poll Question #5

    Long Term Retention of Asbestos Abatement

    Documentation in Project Wise is the Responsibility of

    Who?

    1. EIC

    2. Project Monitor

    3. Asbestos Abatement Sub-contractor

    4. Construction Environmental Coordinator (CEC)

    5. None of the Above

  • 59

    #5 Answer

    4. Construction Environmental Coordinator