asset management plan update - northpower

38
March 2020 Asset Management Plan Update 2020 - 2030

Upload: others

Post on 21-Mar-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

March 2020

Asset Management Plan Update

2020 - 2030

© COPYRIGHT 2020 Northpower Limited.

All rights reserved. This document is protected by copyright vested in Northpower Limited (Northpower). Any breach of Northpower’s copyright may be prevented by legal proceedings seeking remedies including injunctions, damages and costs. Any material prepared in breach of Northpower’s copyright must be delivered to Northpower immediately upon request by Northpower.

DISCLAIMER The information in this document is provided in good-faith and represents Northpower’s opinion as at the date of publication. Northpower does not make any representations, warranties or undertakings either express or implied, about the accuracy or the completeness of the information provided; and the act of making the information available does not constitute any representation, warranty or undertaking, either express or implied. This document does not, and is not intended to; create any legal obligation or duty on Northpower. To the extent permitted by law, no liability (whether in negligence or other tort, by contract, under statute or in equity) is accepted by Northpower by reason of, or in conjunction with, any statement made in this document or by any actual or purported reliance on it by any party. Northpower reserves all rights to alter, in its absolute discretion, any of the information provided in this document.

northpower.com

Asset Management Plan Update

2020 - 2030

Table of Contents

1. Asset Management Plan Update 12. Material Changes 5

2.1 Material changes to Network Development Plan2.2 Material changes to Life Cycle Asset Management Plan2.3 Material changes to Asset Management Practices2.4 Material changes to Expenditure Forecasts

3. Schedules 133.1 Schedule 11a: Report on Forecast Capital Expenditure3.2 Schedule 11b: Report on Forecast Operational Expenditure3.3 Schedule 12a: Report on Asset Condition3.4 Schedule 12b: Report on Forecast Capacity 3.5 Schedule 12c: Report on Forecast Network Demand 3.6 Schedule 12d: Report on Forecast Interruptions and Duration3.7 Schedule 14a: Mandatory Explanatory Notes on Forecast Information

4. Director Certification 31

Section 1: Asset Management

Plan Update

Northpower Limited | Asset Management Plan Update 2020-2030 Page 1

Section 1: Asset Management Plan Update

1 Asset Management Plan Update This supplement to our Asset Management Plan published in March 2018 (for the period 2018-2028) provides an update to Northpower’s approach to managing its assets and delivering the planned programmes of capital and operational spend, as well as planned maintenance work for the period 1 April 2020 to 31 March 2030.

Northpower’s 2018 Asset Management Plan is available from Northpower’s website at: http://northpower.com/about/disclosures/asset-management-plan. This update should be read in conjunction with the 2018 AMP (and subsequent 2019 AMP Update) and outlines how we are managing our Network assets for the efficient and reliable delivery of electricity to consumers.

Covered in this update are:

1. Material changes to the network development plans disclosed in the last AMP;

2. Material changes to the lifecycle asset management (maintenance and renewal) plans disclosed in the last AMP;

3. Material changes to Northpower’s asset management practices; and

4. An outline of the reasons for material changes to the previous disclosures in the Report on Forecast Capital Expenditure set out in Schedule 11a and Report on Forecast Operational Expenditure set out in Schedule 11b.

Stakeholder FeedbackNorthpower encourages feedback to enable continued improvement in meeting the needs of its consumers and stakeholders.

Feedback should be addressed to:

Roy HamiltonAsset Investment and Strategy Manager

NorthpowerPrivate Bag 9018Whangarei Mail CentreWhangarei 0148

Email: [email protected]

Section 2: Material Changes

Northpower Limited | Asset Management Plan Update 2020-2030 Page 5

Section 2: Material Changes

2 Material Changes

2.1 Overview Since the 2019 AMP Update we have continued to review the existing Asset Management Plan for the electricity business and our approach to investment and maintenance with a focus on continual improvement. The key inputs into this review have included:

• A full review of forecast changes in investment need relating to aging major items of plant and load growth for the 10-year planning period FY21-FY30.

• A full review of unit costs associated with our investment programmes, noting a general trend to increased delivery costs across all work delivery streams.

• Reviewing security of supply criteria against updated load and growth forecasts for high growth areas (primarily Mangawhai and Bream Bay).

• A review of Opex and Capex programs to ensure SAIDI and SAIFI remain in line with long-term averages, taking into account an aging asset base, increases in planned work and ongoing vegetation challenges.

This 2020 AMP Update summarises the resulting changes to our Asset Management Plan.

2.2 Material Changes to Network Development Plan

Overall $18.0M increase in the 10-year Network Development profile compared with the 2019 Asset Management Plan Update1

We have reviewed the Network development investments for the next 10-year period and revisited growth assumptions to validate investment need. As a result, some projects have been deferred out of the 10-year planning period.

Counteracting this deferment outcome, and to ensure security of supply to areas experiencing high residential and industrial growth, we have brought forward two significant projects in Mangawhai and Bream Bay and made a number of other targeted changes as set out in the table below.

Material Changes to Network Development Plan2

Year Change ($) Description of Change Reasons for change

FY21 - FY24 +10.5M Second Maungaturoto - Mangawhai sub-transmission line

To address high levels of growth in the area, and to meet Northpower’s security of supply standards.

FY20 - FY29 +4.9M Provision for growth in customer connections

Updated forecasts in line with recent growth trends.

FY21 - FY25 +4.5M Provision for Bream Bay area development (second transformer, switchboards)

Revision of residential and commercial growth forecasts for the area indicate a need to revisit and consolidate investment plans.

FY20 - FY29 +2.7M Increase in overhead to underground relocations in specific coastal areas

To address asset corrosion, improve reliability and extend asset lifecycles.

FY20 - FY29 +1.3M Increase distribution transformer relocation from overhead platforms

Acceleration of targeted safety programme.

FY20-FY29 +3.9M Buildings, civil and electrical contractor cost increases

Reflects uplift in costs across industry, following cost validation exercise.

FY19 - FY29 -12.3M Project deferrals Largely due to revision of growth forecasts deferring investment need out of the planning period.

The resulting investment profile sees an uplift in investment related to Network Development compared with our 2019 AMP Update, particularly in the first five years of the planning period.

1 For the comparison period FY20 to FY292 Includes the following investment categories: consumer connections, system growth, asset relocations, reliability,

safety & environment)

Page 6 Northpower Limited | Asset Management Plan Update 2020-2030

10-Year Network Development Investment Profile (2020 AMP vs. 2019 AMP) - $M

Legend

0

2

4

6

8

10

12

14

FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29

0

5

10

15

20

25

FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29

-

5

10

15

20

25

30

35

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Network Development - 2020 AMPNetwork Development - 2019 AMP

Asset Life Cycle - 2020 AMPAsset Life Cycle - 2019 AMP

2019 OPEX Forecast

2020 OPEX Forecast

2019 CAPEX Forecast

2020 CAPEX Forecast

2.3 Material Changes to Asset Life Cycle Management

Overall $24.7M increase in the 10-year Asset Life Cycle Management profile compared with the 2019 Asset Management Plan Update.3

Our latest review of our Asset Life Cycle Management Plan noted a material increase in building, civils and electrical contractor market rates. We have validated that these increases are real and likely to persist into the future even with competitive pressure. We will continue to look at options available to ensure these project works are delivered in the most cost effective manner.

We have also revised and improved our overhead inspection standard to improve the quality of inspection data received, which in turn enables enhanced asset condition assessments and replacement decisions. The key changes proposed are set out in the table below:

Material Changes to Asset Life Cycle Management Plan4

Year Change ($) Description of Change Reason for change FY22 - FY23 +2.5M New mobile substation To enhance restoration of supply in fault

situations and enable supply to be maintained during rural substation maintenance.

FY20 - FY29 +2.3M Oil filled RMUs Increase in rate of replacement of RMUs as a result of condition based assessments.

FY21 - FY29 +1.3M New allocation corrective Capex - 110kV towers & equipment

To reflect increased need following condition assessments.

FY21 - FY27 +1.2M New network clearances 3D model (LiDAR)

To enable enhanced management of vegetation priorities and asset clearances.

FY22 - FY24 +1.2M Asset management system replacement

Replacement of end of life system.

FY21 - FY29 +2.5M Provision for overhead switch replacements

Increased need based on emerging defect rates in existing overhead switches.

FY20 - FY29 +15.7M Buildings, civil and electrical contractor cost increases

Reflects existing uplift in costs across industry, following cost validation exercise.

FY19 - FY29 -6.0M Targeted deferrals Result of validation of asset condition and resulting amendments to the asset’s Health Indices.

Section 2

3 For the comparison period FY20 to FY294 Includes the following investment categories: asset replacement and renewal, non-network assets

Northpower Limited | Asset Management Plan Update 2020-2030 Page 7

The resulting investment profile sees an uplift in investment relating to Asset Lifecycle Management, compared with our 2019 AMP Update across the planning period.

10-Year Asset Life Cycle Management Investment Profile (2020 AMP vs. 2019 AMP) - $M

Legend

0

2

4

6

8

10

12

14

FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29

0

5

10

15

20

25

FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29

-

5

10

15

20

25

30

35

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Network Development - 2020 AMPNetwork Development - 2019 AMP

Asset Life Cycle - 2020 AMPAsset Life Cycle - 2019 AMP

2019 OPEX Forecast

2020 OPEX Forecast

2019 CAPEX Forecast

2020 CAPEX Forecast

2.4 Material Changes to Expenditure Forecasts (Schedule 11a and 11b)Compared to the 2019 AMP Update we are forecasting an increase across both Capex and Opex expenditure.

Forecast expenditure 2019 AMP Update vs. 2020 AMP Update

Legend

0

2

4

6

8

10

12

14

FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29

0

5

10

15

20

25

FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29

-

5

10

15

20

25

30

35

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Network Development - 2020 AMPNetwork Development - 2019 AMP

Asset Life Cycle - 2020 AMPAsset Life Cycle - 2019 AMP

2019 OPEX Forecast

2020 OPEX Forecast

2019 CAPEX Forecast

2020 CAPEX Forecast

Section 2

Page 8 Northpower Limited | Asset Management Plan Update 2020-2030

Capex Expenditure Forecast The 10-year forecast capital expenditure is $243.0M, up $42.7M compared with the 2019 Asset Management Plan Update.5

We expect it to return to similar levels as the 2019 AMP in the second half of the planning period.

Capital Expenditure Forecast (FY21-FY30) $M

0

5

10

15

20

25

30

35

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Reliability, Safety and Environment

Asset Relocations

System Growth

Consumer Connection

Non-Network Assets

Asset Replacement & Renewal

2019 AMP Update

0

5

10

15

20

25

30

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Service interruptions and emergencies Vegetation management

Asset replacement and renewal

Routine and corrective maintenance and inspection

System operations and network support Business support

2019 AMP Update

Capital Expenditure Forecast (FY21-FY30) $M

Operating Expenditure Forecast (FY21-FY30) $M

Opex Expenditure Forecast The 10-year forecast operating expenditure is $279.4M, up $31.0M compared with the 2019 Asset Management Plan Update.6

Operating Expenditure Forecast (FY21-FY30) $M

0

5

10

15

20

25

30

35

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Reliability, Safety and Environment

Asset Relocations

System Growth

Consumer Connection

Non-Network Assets

Asset Replacement & Renewal

2019 AMP Update

0

5

10

15

20

25

30

FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

Service interruptions and emergencies Vegetation management

Asset replacement and renewal

Routine and corrective maintenance and inspection

System operations and network support Business support

2019 AMP Update

Capital Expenditure Forecast (FY21-FY30) $M

Operating Expenditure Forecast (FY21-FY30) $M

Section 2

5 For the comparison period FY20 to FY29 6 For the comparison period FY20 to FY29

Northpower Limited | Asset Management Plan Update 2020-2030 Page 9

Responding to service interruptions and emergencies

+$2.11M Uplift to address aging network and an allowance for increased faults due to more significant weather events stressing end of life overhead assets.

Vegetation management +$4.80M An uplift in vegetation management to deliver a 5-year vegetation management cycle (better aligned with tree growth rates).

Routine and corrective maintenance and inspection activities

+$5.47M Increase in quantities of corrective maintenance to ensure focus remains on ensuring timeliness of rectifying defects and enhancing maintenance programmes, as well as an increase in contractor costs.

Asset replacement and renewal

+$573k Impact of contractor rates review for asset replacement and renewal activities.

System operations and network support

+$2.13M Reflects ongoing investment in ADMS and maintaining supporting systems, as well as enhanced operational capability and resiliency.

Business support +$15.94M Reflects increases in direct and indirect costs to support the network.

2.5 Material Changes to Asset Management PracticesThe 2019 AMP Update outlined a number of initiatives aimed to improve our asset management processes. Further refinement over the last year includes:

• Revision of our Network organisational structure to improve focus and outcomes in asset management and delivery of capital and maintenance works. This is supplemented by additional resources to support the asset strategy, delivery and operations functions.

• Refresh of the overhead inspection standards to facilitate better information capture, and ultimately asset management decisions.

• We have further developed our Asset Health Indices and Asset Criticality processes and framework. Several assets have had condition assessments undertaken (including some sub-transmission conductors and zone sub-station transformers), resulting in a re-classification of the asset’s Health Indices (and an adjustment to the investment plan).

Section 2 Section 2

Page 10 Northpower Limited | Asset Management Plan Update 2020-2030

Northpower Limited | Asset Management Plan Update 2020-2030 Page 11

Section 3: Schedules

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 13

CommerceCommissionInformationDisclosureTemplate

NPAMPYBDisclosureSchedules2020v1.4.xlsx 1 CoverSheet

EDBInformationDisclosureRequirementsInformationTemplates

forSchedules11a–13

CompanyName NorthpowerLtd

DisclosureDate 31March2020

AMPPlanningPeriodStartDate(firstday) 1April2020

TemplatesforSchedules11a–13(AssetManagementPlan)TemplateVersion4.1.Prepared21December2017

Section 3

Page 14 Northpower Limited | Asset Management Plan Update 2020-2030

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

4S11a.Cap

exForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11a

:REP

ORT

ON

FO

RECA

STC

APIT

ALE

XPEN

DITU

RE

sch

ref

7Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

CY+6

CY+7

CY+8

CY+9

CY+1

0

8fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

31M

ar2

631

Mar

27

31M

ar2

831

Mar

29

31M

ar3

0

911

a(i):

Exp

endi

ture

on

Asse

tsF

orec

ast

$000

(in

nom

inal

dol

lars

)

10Co

nsum

ercon

nection

5,13

05,64

43,92

14,04

54,17

34,30

54,44

24,58

34,72

94,87

95,03

511

System

growth

4,50

92,77

53,55

64,60

84,64

73,27

882

042

360

44,42

74,03

712

Assetrep

lacemen

tand

rene

wal

11,452

14

,885

16

,385

18

,033

18

,152

18

,476

15

,857

13

,443

16

,647

10

,116

14

,412

13

Assetrelocations

490

945

965

984

1,00

41,02

41,04

41,06

51,08

71,10

81,13

014

Reliability,sa

fetyand

enviro

nmen

t:15

Qua

lityofsu

pply

--

--

--

--

--

-16

Legisla

tivean

dregu

latory

--

--

--

--

--

-17

Otherre

liability,sa

fetyand

enviro

nmen

t1,54

495

51,37

81,49

462

739

042

726

520

739

935

318

Tota

lrel

iabi

lity,

safe

tya

nde

nviro

nmen

t1,54

495

51,37

81,49

462

739

042

726

520

739

935

319

Expe

nditu

reo

nne

twor

kas

sets

23,125

25

,204

26

,206

29

,165

28

,603

27

,473

22

,590

19

,779

23

,273

20

,929

24

,967

20

Expe

nditu

reonno

n-ne

tworkassets

1,98

73,45

42,95

13,12

954

726

022

785

722

032

833

521

Expe

nditu

reo

nas

sets

25,112

28

,658

29

,157

32

,295

29

,150

27

,733

22

,816

20

,636

23

,492

21

,258

25

,302

22 23pl

usCo

stoffinan

cing

126

143

146

161

146

139

114

103

117

106

127

24le

ssVa

lueofcap

italcon

tributions

4,30

04,38

42,63

02,72

22,81

92,91

83,02

13,12

83,23

83,35

23,47

125

plus

Valueofvestedassets

--

--

--

--

--

-26 27

Capi

tale

xpen

ditu

refo

reca

st20

,938

24

,417

26

,673

29

,734

26

,477

24

,954

19

,909

17

,611

20

,372

18

,012

21

,958

28 29Assetscom

miss

ione

d19

,263

22

,464

24

,539

27

,355

24

,359

22

,957

18

,317

16

,202

18

,742

16

,571

20

,201

30Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

CY+6

CY+7

CY+8

CY+9

CY+1

031

fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

31M

ar2

631

Mar

27

31M

ar2

831

Mar

29

31M

ar3

0

32$0

00(i

nco

nsta

ntp

rices

)33

Con

sumercon

nection

5,79

55,64

43,84

13,88

43,92

93,97

44,01

94,06

64,11

34,16

04,20

934

Systemgrowth

4,87

32,77

53,48

34,42

54,37

53,02

574

237

552

53,77

53,37

535

Assetre

placem

enta

ndre

newal

9,88

114

,885

16

,048

17

,316

17

,088

17

,052

14

,348

11

,925

14

,478

8,62

512

,047

36

Assetre

locatio

ns25

594

594

594

594

594

594

594

594

594

594

537

Reliability,sa

fetyand

enviro

nmen

t:38

Qua

lityofsu

pply

--

--

--

--

--

-39

Legisla

tivean

dregu

latory

--

--

--

--

--

-40

Otherre

liability,sa

fetyand

enviro

nmen

t1,05

795

51,35

01,43

559

036

038

623

518

034

029

541

Tota

lrel

iabi

lity,

safe

tya

nde

nviro

nmen

t1,05

795

51,35

01,43

559

036

038

623

518

034

029

542

Expe

nditu

reo

nne

twor

kas

sets

21,861

25

,204

25

,667

28

,005

26

,927

25

,356

20

,440

17

,546

20

,241

17

,845

20

,871

43

Expe

nditu

reonno

n-ne

tworkassets

2,41

13,45

42,89

03,00

551

524

020

576

019

128

028

044

Expe

nditu

reo

nas

sets

24,272

28

,658

28

,557

31

,010

27

,442

25

,596

20

,645

18

,306

20

,432

18

,125

21

,151

45 46Su

bcom

pone

ntso

fexp

endi

ture

on

asse

ts(w

here

kno

wn)

47En

ergyefficien

cyand

dem

andsid

eman

agem

ent,redu

ctionofene

rgylosses

85

85

185

185

185

85

85

85

85

85

85

48Overheadtound

ergrou

ndcon

version

-55

055

055

055

055

055

055

055

055

055

049

Researchand

develop

men

t50

50

50

50

60

70

80

85

90

10

010

0

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastexpen

ditureonassetsfo

rthe

currentdisc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.Also

requ

iredisaforecast

ofth

evalueofcom

miss

ione

dassets(i.e.,thevalueofRAB

add

ition

s)

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollarforecastsofe

xpen

ditureonassetsinSched

ule14

a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 15

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

5S11a.Cap

exForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11a

:REP

ORT

ON

FO

RECA

STC

APIT

ALE

XPEN

DITU

RE

sch

ref

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastexpen

ditureonassetsfo

rthe

currentdisc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.Also

requ

iredisaforecast

ofth

evalueofcom

miss

ione

dassets(i.e.,thevalueofRAB

add

ition

s)

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollarforecastsofe

xpen

ditureonassetsinSched

ule14

a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

50 51Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

CY+6

CY+7

CY+8

CY+9

CY+1

052

fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

31M

ar2

631

Mar

27

31M

ar2

831

Mar

29

31M

ar3

053

Diffe

renc

ebe

twee

nno

min

ala

ndc

onst

antp

rice

fore

cast

s$0

00

54Con

sumercon

nection

(665

)-

81

161

245

332

423

517

616

719

826

55Systemgrowth

(364

)-

73

183

272

253

78

48

79

652

662

56Assetre

placem

enta

ndre

newal

1,57

10

337

717

1,06

41,42

41,50

91,51

82,16

91,49

12,36

457

Assetre

locatio

ns23

5-

20

39

59

79

99

120

142

163

185

58Re

liability,sa

fetyand

enviro

nmen

t:59

Qua

lityofsu

pply

--

--

--

--

--

-60

Legisla

tivean

dregu

latory

--

--

--

--

--

-61

Otherre

liability,sa

fetyand

enviro

nmen

t48

7-

28

59

37

30

41

30

27

59

58

62To

talr

elia

bilit

y,sa

fety

and

env

ironm

ent

487

-28

59

37

30

41

30

27

59

58

63

Expe

nditu

reo

nne

twor

kas

sets

1,26

40

539

1,16

01,67

62,11

72,15

02,23

33,03

23,08

44,09

664

Expe

nditu

reonno

n-ne

tworkassets

(424

)-

61

124

32

20

22

97

29

48

55

65Ex

pend

iture

on

asse

ts84

00

600

1,28

41,70

82,13

72,17

12,32

93,06

13,13

34,15

166 67

CY+1

CY+2

CY+3

CY+4

CY+5

6811

a(ii)

:Con

sum

erC

onne

ctio

nfory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

69Co

nsum

erty

pesd

efin

edb

yED

B*$0

00(i

nco

nsta

ntp

rices

)

70Ca

pitalcon

tributions(N

etwork)

500

505

510

515

520

526

71Ca

pitalcon

tributions(C

ustomer)

4,30

04,38

42,57

62,61

42,65

32,69

372

Tran

sformerAcquisitionCo

st1,04

080

080

080

080

080

073

Tran

sformerCreditsfrom

Upg

rade

s(130

)(130

)(130

)(130

)(130

)(130

)74

Ripp

lere

laypu

rcha

ses

85

85

85

85

85

85

75

*inc

lude

add

ition

alro

wsi

fnee

ded

76Co

nsum

erc

onne

ctio

nex

pend

iture

5,79

55,64

43,84

13,88

43,92

93,97

477

less

Capitalcon

tributionsfu

ndingconsum

ercon

nection

4,30

04,38

42,57

62,61

42,65

32,69

378

Cons

umer

con

nect

ion

less

cap

italc

ontr

ibut

ions

1,49

51,26

01,26

51,27

01,27

51,28

1

7911

a(iii

):Sy

stem

Gro

wth

80Subtransmiss

ion

-50

02,50

04,00

02,00

01,50

081

Zone

substatio

ns4,74

81,65

050

030

02,00

01,40

082

Distrib

utionan

dLVline

s-

--

--

-83

Distrib

utionan

dLVcab

les

--

--

--

84Distrib

utionsubstatio

nsand

tran

sformers

50

550

300

50

300

50

85Distrib

utionsw

itchg

ear

--

108

--

-86

Othernetworkassets

75

75

75

75

75

75

87Sy

stem

gro

wth

exp

endi

ture

4,87

32,77

53,48

34,42

54,37

53,02

588

less

Capitalcon

tributionsfu

ndingsystem

growth

--

--

--

89Sy

stem

gro

wth

less

cap

italc

ontr

ibut

ions

4,87

32,77

53,48

34,42

54,37

53,02

5

90

Curr

entY

earC

Y

Section 3

Page 16 Northpower Limited | Asset Management Plan Update 2020-2030

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

6S11a.Cap

exForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11a

:REP

ORT

ON

FO

RECA

STC

APIT

ALE

XPEN

DITU

RE

sch

ref

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastexpen

ditureonassetsfo

rthe

currentdisc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.Also

requ

iredisaforecast

ofth

evalueofcom

miss

ione

dassets(i.e.,thevalueofRAB

add

ition

s)

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollarforecastsofe

xpen

ditureonassetsinSched

ule14

a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

91Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

92fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

9311

a(iv

):As

setR

epla

cem

enta

ndR

enew

al$0

00(i

nco

nsta

ntp

rices

)

94Subtransmiss

ion

500

-30

02,00

035

0-

95Zone

substatio

ns3,16

17,13

87,92

87,42

88,63

88,63

896

Distrib

utionan

dLVline

s5,02

05,34

95,44

95,64

95,84

96,04

997

Distrib

utionan

dLVcab

les

260

390

400

410

410

430

98Distrib

utionsubstatio

nsand

tran

sformers

565

541

594

571

624

591

99Distrib

utionsw

itchg

ear

300

1,06

81,09

397

897

81,01

310

0Othernetworkassets

75

400

286

281

241

333

101

Asse

trep

lace

men

tand

rene

wal

exp

endi

ture

9,88

114

,885

16

,048

17

,316

17

,088

17

,052

10

2le

ssCa

pitalcon

tributionsfu

ndingassetrep

lacemen

tand

rene

wal

--

--

--

103

Asse

trep

lace

men

tand

rene

wal

less

cap

italc

ontr

ibut

ions

9,88

114

,885

16

,048

17

,316

17

,088

17

,052

104

105

Curr

entY

earC

YCY

+1CY

+2CY

+3CY

+4CY

+510

6fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

107

11a(

v):A

sset

Rel

ocat

ions

108

Proj

ecto

rpro

gram

me*

$000

(in

cons

tant

pric

es)

109

Minorcap

italexpen

diture(relocation)

55

55

55

55

55

55

110

Road

ingworksassetre

locatio

ns10

050

50

50

50

50

11

1Overheadtound

ergrou

ndcon

version

-55

055

055

055

055

011

2Grou

ndm

ountingof2/4poledistrib

utiontran

sformers

100

290

290

290

290

290

114

*inc

lude

add

ition

alro

wsi

fnee

ded

115

Allotherprojectorp

rogram

mes-assetrelocations

--

--

--

116

Asse

trel

ocat

ions

exp

endi

ture

255

945

945

945

945

945

117

less

Capitalcon

tributionsfu

ndingassetrelocations

--

--

--

118

Asse

trel

ocat

ions

less

cap

italc

ontr

ibut

ions

255

945

945

945

945

945

119

120

Curr

entY

earC

YCY

+1CY

+2CY

+3CY

+4CY

+512

1fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

122

11a(

vi):

Qua

lity

ofS

uppl

y12

3Pr

ojec

torp

rogr

amm

e*$0

00(i

nco

nsta

ntp

rices

)12

4[Descriptio

nofm

aterialprojectorp

rogram

me]

125

[Descriptio

nofm

aterialprojectorp

rogram

me]

126

[Descriptio

nofm

aterialprojectorp

rogram

me]

127

[Descriptio

nofm

aterialprojectorp

rogram

me]

128

[Descriptio

nofm

aterialprojectorp

rogram

me]

129

*inc

lude

add

ition

alro

wsi

fnee

ded

130

Allotherprojectso

rprogram

mes-qu

ality

ofsup

ply

131

Qua

lity

ofsu

pply

exp

endi

ture

--

--

--

132

less

Capitalcon

tributionsfu

ndingqu

ality

ofsup

ply

133

Qua

lity

ofsu

pply

less

cap

italc

ontr

ibut

ions

--

--

--

134

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 17

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

7S11a.Cap

exForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11a

:REP

ORT

ON

FO

RECA

STC

APIT

ALE

XPEN

DITU

RE

sch

ref

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastexpen

ditureonassetsfo

rthe

currentdisc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.Also

requ

iredisaforecast

ofth

evalueofcom

miss

ione

dassets(i.e.,thevalueofRAB

add

ition

s)

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollarforecastsofe

xpen

ditureonassetsinSched

ule14

a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

135

Curr

entY

earC

YCY

+1CY

+2CY

+3CY

+4CY

+513

6fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

137

11a(

vii):

Leg

isla

tive

and

Regu

lato

ry13

8Pr

ojec

torp

rogr

amm

e*$0

00(i

nco

nsta

ntp

rices

)13

9[Descriptio

nofm

aterialprojectorp

rogram

me]

140

[Descriptio

nofm

aterialprojectorp

rogram

me]

141

[Descriptio

nofm

aterialprojectorp

rogram

me]

142

[Descriptio

nofm

aterialprojectorp

rogram

me]

143

[Descriptio

nofm

aterialprojectorp

rogram

me]

144

*inc

lude

add

ition

alro

wsi

fnee

ded

145

Allotherprojectso

rprogram

mes-legisla

tivean

dregu

latory

146

Legi

slat

ive

and

regu

lato

rye

xpen

ditu

re-

--

--

-14

7le

ssCa

pitalcon

tributionsfu

ndinglegisla

tivean

dregu

latory

148

Legi

slat

ive

and

regu

lato

ryle

ssc

apita

lcon

trib

utio

ns-

--

--

-

149

150

Curr

entY

earC

YCY

+1CY

+2CY

+3CY

+4CY

+5

151

11a(

viii)

:Oth

erR

elia

bilit

y,S

afet

yan

dEn

viro

nmen

tfory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

152

Proj

ecto

rpro

gram

me*

$000

(in

cons

tant

pric

es)

153

Zone

Sub

stationsRisk

Mitigatio

n13

415

0-

--

-15

4Zone

Sub

stationsSecurity

Improvem

ent

65

75

90

90

75

-15

5Wha

kapa

raFee

derE

xpressLinetoHikuran

gi-

-70

0-

--

156

New

Reclosers

-55

-

-55

-

157

Wha

ngareiCity

add

ition

al11kVRM

U's

--

50

--

-11

KVAutom

ationatm

idand

end

pointoffee

der

-18

018

018

018

018

011

kVfe

ederbackstopp

ingim

provem

ents

--

-85

-

-DS

UBMDIM

eters(CB

D)10

065

-

--

-LVAutom

ation

-30

30

30

30

30

SM

ARTDistrib

utionsystem

(loa

dmon

itorin

g)-

50

100

100

100

-Ra

dioTran

smiss

ionsiteRe

silience

--

50

--

-Provision

forfibre

658

250

50

50

50

50

Minorcap

italexpen

diture(reliability,sa

fety,enviro

nmen

t)10

010

010

010

010

010

0Ru

awaiTransform

erRep

lacemen

t-

--

800

--

158

*inc

lude

add

ition

alro

wsi

fnee

ded

159

Allotherprojectso

rprogram

mes-othe

rreliability,sa

fetyand

enviro

nmen

t-

--

--

-16

0O

ther

relia

bilit

y,sa

fety

and

env

ironm

ente

xpen

ditu

re1,05

795

51,35

01,43

559

036

016

1le

ssCa

pitalcon

tributionsfu

ndingothe

rreliability,sa

fetyand

enviro

nmen

t-

--

--

-16

2O

ther

relia

bilit

y,sa

fety

and

env

ironm

entl

essc

apita

lcon

trib

utio

ns1,05

795

51,35

01,43

559

036

016

3

164

Curr

entY

earC

YCY

+1CY

+2CY

+3CY

+4CY

+516

5fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

166

11a(

ix):

Non

-Net

wor

kAs

sets

167

Rout

ine

expe

nditu

re16

8Pr

ojec

torp

rogr

amm

e*$0

00(i

nco

nsta

ntp

rices

)16

9Networkstrategicsparesstore

--

--

-40

17

0Re

searchand

Develop

men

t(compo

nentte

sting)

30

30

30

30

30

50

Section 3

Page 18 Northpower Limited | Asset Management Plan Update 2020-2030

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

8S11a.Cap

exForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11a

:REP

ORT

ON

FO

RECA

STC

APIT

ALE

XPEN

DITU

RE

sch

ref

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastexpen

ditureonassetsfo

rthe

currentdisc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.Also

requ

iredisaforecast

ofth

evalueofcom

miss

ione

dassets(i.e.,thevalueofRAB

add

ition

s)

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollarforecastsofe

xpen

ditureonassetsinSched

ule14

a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

171

Aeria

lImagery(GIS)

--

40

--

-17

2En

gine

eringha

rdware/Software

-50

-

--

55

173

Researchand

Develop

men

t(ne

wte

chno

logy)

50

50

50

50

60

70

AMS(W

ASPreplacem

enta

ndCBR

Mso

ftware)

--

700

1,40

040

0-

ADMS(Advan

cedDistrib

utionMan

agem

entS

ystem)

2,20

61,65

91,04

5-

--

SalesForceEnh

ancemen

ts-

325

--

--

Gentrack

-15

0-

--

-FaultsM

anagem

entS

ystem

-30

0-

--

-LiDA

Rfore

ntire

network

-60

0-

--

-ESRIGeo

spatialToo

lSets

-16

5-

--

-Mob

ilesu

bstatio

n/StepUp/Statcom

--

1,00

01,50

0-

-Minorcap

italexpen

diture(n

on-networkassets)

25

25

25

25

25

25

LVnetworkop

erationa

lman

agem

entsystem

100

100

--

--

174

*inc

lude

add

ition

alro

wsi

fnee

ded

175

Allotherprojectso

rprogram

mes-routineexpe

nditu

re-

--

--

-17

6Ro

utin

eex

pend

iture

2,41

13,45

42,89

03,00

551

524

0

177

Atyp

ical

exp

endi

ture

178

Proj

ecto

rpro

gram

me*

179

[Descriptio

nofm

aterialprojectorp

rogram

me]

180

[Descriptio

nofm

aterialprojectorp

rogram

me]

181

[Descriptio

nofm

aterialprojectorp

rogram

me]

182

[Descriptio

nofm

aterialprojectorp

rogram

me]

183

[Descriptio

nofm

aterialprojectorp

rogram

me]

184

*inc

lude

add

ition

alro

wsi

fnee

ded

185

Allotherprojectso

rprogram

mes-atypicalexpen

diture

186

Atyp

ical

exp

endi

ture

--

--

--

187

188

Expe

nditu

reo

nno

n-ne

twor

kas

sets

2,41

13,45

42,89

03,00

551

524

0

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 19

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

9S11b

.Ope

xForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11b

:REP

ORT

ON

FO

RECA

STO

PERA

TIO

NAL

EXP

ENDI

TURE

sch

ref

7Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

CY+6

CY+7

CY+8

CY+9

CY+1

08

fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

31M

ar2

631

Mar

27

31M

ar2

831

Mar

29

31M

ar3

0

9O

pera

tiona

lExp

endi

ture

For

ecas

t$0

00(i

nno

min

ald

olla

rs)

10Serviceinterrup

tionsand

emergencies

2,81

92,15

02,19

52,23

92,28

42,32

92,37

62,42

42,47

22,52

12,57

211

Vegetatio

nman

agem

ent

2,82

02,82

02,87

92,93

72,99

63,05

53,11

73,17

93,01

33,07

33,13

412

Routinean

dcorrectiv

emainten

anceand

inspectio

n3,32

63,32

03,41

03,45

83,52

73,61

93,66

93,74

33,84

13,89

43,97

213

Assetrep

lacemen

tand

rene

wal

2,99

42,73

42,79

22,84

82,90

52,96

33,02

22,63

12,68

42,73

82,79

214

Net

wor

kO

pex

11,959

11

,024

11

,276

11

,481

11

,711

11

,967

12

,184

11

,977

12

,009

12

,226

12

,470

15System

ope

ratio

nsand

networksupp

ort

2,66

33,39

63,46

73,53

73,60

83,68

03,75

33,82

83,90

53,98

34,06

316

Busin

esss

uppo

rt13

,182

13

,710

13

,998

14

,278

14

,563

14

,855

15

,152

15

,455

15

,764

16

,079

16

,401

17

Non

-net

wor

kop

ex15

,845

17

,106

17

,465

17

,815

18

,171

18

,534

18

,905

19

,283

19

,669

20

,062

20

,464

18

Ope

ratio

nale

xpen

ditu

re27

,804

28

,130

28

,742

29

,296

29

,882

30

,501

31

,089

31

,260

31

,678

32

,288

32

,934

19Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

CY+6

CY+7

CY+8

CY+9

CY+1

020

fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

31M

ar2

631

Mar

27

31M

ar2

831

Mar

29

31M

ar3

0

21$0

00(i

nco

nsta

ntp

rices

)22

Serviceinterrup

tionsand

emergencies

2,81

92,15

02,15

02,15

02,15

02,15

02,15

02,15

02,15

02,15

02,15

023

Vegetatio

nman

agem

ent

2,82

02,82

02,82

02,82

02,82

02,82

02,82

02,82

02,62

02,62

02,62

024

Routinean

dcorrectiv

emainten

anceand

inspectio

n3,32

63,32

03,34

03,32

03,32

03,34

03,32

03,32

03,34

03,32

03,32

025

Assetrep

lacemen

tand

rene

wal

2,99

42,73

42,73

42,73

42,73

42,73

42,73

42,33

42,33

42,33

42,33

426

Net

wor

kO

pex

11,959

11

,024

11

,044

11

,024

11

,024

11

,044

11

,024

10

,624

10

,444

10

,424

10

,424

27System

ope

ratio

nsand

networksupp

ort

2,66

33,39

63,39

63,39

63,39

63,39

63,39

63,39

63,39

63,39

63,39

628

Busin

esss

uppo

rt13

,182

13

,710

13

,710

13

,710

13

,710

13

,710

13

,710

13

,710

13

,710

13

,710

13

,710

29

Non

-net

wor

kop

ex15

,845

17

,106

17

,106

17

,106

17

,106

17

,106

17

,106

17

,106

17

,106

17

,106

17

,106

30

Ope

ratio

nale

xpen

ditu

re27

,804

28

,130

28

,151

28

,131

28

,131

28

,151

28

,131

27

,731

27

,551

27

,531

27

,531

31Su

bcom

pone

ntso

fope

ratio

nale

xpen

ditu

re(w

here

kno

wn)

32 33 34Directbilling*

35Re

searchand

Develop

men

t36

Insurance

37*

Dire

ctb

illin

gex

pend

iture

by

supp

liers

that

dire

ctb

illth

em

ajor

ityo

fthe

irco

nsum

ers

38 39Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

CY+6

CY+7

CY+8

CY+9

CY+1

040

fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

31M

ar2

631

Mar

27

31M

ar2

831

Mar

29

31M

ar3

0

41Di

ffere

nce

betw

een

nom

inal

and

real

fore

cast

s$0

0042

Serviceinterrup

tionsand

emergencies

--

45

89

134

180

226

274

322

372

422

43Ve

getatio

nman

agem

ent

--

59

117

176

235

297

359

393

453

514

44Ro

utinean

dcorrectiv

emainten

anceand

inspectio

n-

-70

13

820

727

934

942

350

057

465

245

Assetrep

lacemen

tand

rene

wal

--

57

113

170

228

288

297

350

403

458

46N

etw

ork

Ope

x-

-23

245

768

692

21,15

91,35

21,56

51,80

12,04

6

47System

ope

ratio

nsand

networksupp

ort

--

71

141

211

284

357

432

509

587

667

48Bu

sinesss

uppo

rt-

-28

856

885

31,14

51,44

21,74

52,05

42,36

92,69

1

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastope

ratio

nalexpen

diturefo

rthe

disc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollaro

peratio

nalexpen

diturefo

recastsinSche

dule14a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

Energyefficien

cyand

dem

andsid

eman

agem

ent,redu

ctionof

energylosses

Section 3

Page 20 Northpower Limited | Asset Management Plan Update 2020-2030

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

10S11b

.Ope

xForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

11b

:REP

ORT

ON

FO

RECA

STO

PERA

TIO

NAL

EXP

ENDI

TURE

sch

ref

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnoffo

recastope

ratio

nalexpen

diturefo

rthe

disc

losureyeara

nda10yearplann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

P.The

forecastisto

beexpressedinbothconstantpric

ean

dno

minaldollarterms.

EDBsm

ustp

rovide

explana

torycom

men

tonthediffe

rencebe

twee

nconstantpric

ean

dno

minaldollaro

peratio

nalexpen

diturefo

recastsinSche

dule14a(M

anda

toryExplana

toryNotes).

Thisinform

ationisno

tparto

faud

iteddisclosureinform

ation.

49N

on-n

etw

ork

opex

--

359

709

1,06

51,42

81,79

92,17

72,56

32,95

63,35

750

Ope

ratio

nale

xpen

ditu

re-

-59

11,16

51,75

12,35

02,95

83,52

94,12

74,75

85,40

3

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 21

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

11S12a.AssetCon

ditio

n

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

12a

:REP

ORT

ON

ASS

ETC

ON

DITI

ON

sch

ref

7 8 9

Volta

geAs

setc

ateg

ory

Asse

tcla

ssU

nits

H1H2

H3H4

H5G

rade

un

know

nDa

taa

ccur

acy

(1–4

)

10All

OverheadLine

Concretepoles/stee

lstructure

No.

1.67

%

3.70

%

37.44%

52

.90%

4.29

%

-2

3%

11All

OverheadLine

Woo

dpo

les

No.

13.26%

4.59

%

40.10%

40

.91%

1.14

%

-2

17%

12All

OverheadLine

Otherpoletype

sNo.

30.61%

16

.32%

38

.77%

13

.26%

1.04

%

-2

31%

13HV

Subtransmiss

ionLine

Subtransmiss

ionOHup

to66kVcond

uctor

km-

21.11%

48

.05%

30

.63%

0.21

%

-3

4%

14HV

Subtransmiss

ionLine

Subtransmiss

ionOH11

0kV+

con

ductor

km-

-99

.65%

0.35

%

--

4-

15HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUGup

to66kV(XLPE)

km-

-5.31

%

94.69%

-

-3

-16

HVSubtransmiss

ionCa

ble

Subtransmiss

ionUGup

to66kV(Oilpressurised

)km

--

98.86%

1.14

%

--

426

%

17HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUGup

to66kV(Gaspressurise

d)km

--

--

--

4-

18HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUGup

to66kV(PILC)

km-

--

100.00

%

--

4-

19HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUG11

0kV+

(XLPE)

km-

--

100.00

%

--

4-

20HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUG11

0kV+

(Oilpressurised

)km

--

--

--

4-

21HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUG11

0kV+

(GasPressurise

d)km

--

--

--

4-

22HV

Subtransmiss

ionCa

ble

Subtransmiss

ionUG11

0kV+

(PILC)

km-

--

--

-4

-23

HVSubtransmiss

ionCa

ble

Subtransmiss

ionsubm

arinecable

km-

--

100.00

%

--

4-

24HV

Zone

substatio

nBu

ildings

Zone

substatio

nsupto66kV

No.

5.00

%

-35

.00%

60

.00%

-

-4

-25

HVZone

substatio

nBu

ildings

Zone

substatio

ns110

kV+

No.

--

-10

0.00

%

--

4-

26HV

Zone

substatio

nsw

itchg

ear

22/33kVCB

(Ind

oor)

No.

--

63.33%

36

.67%

-

-4

27%

27HV

Zone

substatio

nsw

itchg

ear

22/33kVCB

(Outdo

or)

No.

--

13.55%

79

.66%

6.79

%

-4

-28

HVZone

substatio

nsw

itchg

ear

33kV

Switch(Groun

dMou

nted

)No.

--

-10

0.00

%

--

4-

29HV

Zone

substatio

nsw

itchg

ear

33kV

Switch(PoleMou

nted

)No.

--

56.32%

40

.80%

2.88

%

-2

-30

HVZone

substatio

nsw

itchg

ear

33kV

RMU

No.

--

-10

0.00

%

--

4-

31HV

Zone

substatio

nsw

itchg

ear

50/66/11

0kVCB

(Ind

oor)

No.

--

--

--

4-

32HV

Zone

substatio

nsw

itchg

ear

50/66/11

0kVCB

(Outdo

or)

No.

--

60.00%

40

.00%

-

-2

-33

HVZone

substatio

nsw

itchg

ear

3.3/6.6/11

/22kVCB

(groun

dmou

nted

)No.

11.72%

15

.17%

18

.62%

54

.49%

-

-4

31%

34HV

Zone

substatio

nsw

itchg

ear

3.3/6.6/11

/22kVCB

(polemou

nted

)No.

--

--

--

4-

35

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0 %o

fass

et

fore

cast

tob

ere

plac

edin

ne

xt5

yea

rs

Asse

tcon

ditio

nat

star

tofp

lann

ing

perio

d(p

erce

ntag

eof

uni

tsb

ygr

ade)

Thissche

dulere

quire

sabreakdo

wnofassetcon

ditio

nbyassetclassasa

tthe

starto

fthe

forecastyear.Th

eda

taaccuracyassessmen

trelatesto

thepe

rcen

tagevalue

sdisc

losedinth

eassetcon

ditio

ncolumns.A

lsore

quire

disaforecastofthe

percentageofunits

tobereplaced

inth

ene

xt5years.A

llinform

ationshou

ldbeconsisten

twith

theinform

ationprovided

inth

eAM

Pan

dtheexpe

nditu

reonassetsfo

recastinSched

ule11

a.Allun

itsre

latin

gtocab

leand

line

assets,th

atareexpressed

inkm,referto

circ

uitlen

gths.

Section 3

Page 22 Northpower Limited | Asset Management Plan Update 2020-2030

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

12S12a.AssetCon

ditio

n

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

12a

:REP

ORT

ON

ASS

ETC

ON

DITI

ON

sch

ref

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

sabreakdo

wnofassetcon

ditio

nbyassetclassasa

tthe

starto

fthe

forecastyear.Th

eda

taaccuracyassessmen

trelatesto

thepe

rcen

tagevalue

sdisc

losedinth

eassetcon

ditio

ncolumns.A

lsore

quire

disaforecastofthe

percentageofunits

tobereplaced

inth

ene

xt5years.A

llinform

ationshou

ldbeconsisten

twith

theinform

ationprovided

inth

eAM

Pan

dtheexpe

nditu

reonassetsfo

recastinSched

ule11

a.Allun

itsre

latin

gtocab

leand

line

assets,th

atareexpressed

inkm,referto

circ

uitlen

gths.

36 37 38

Volta

geAs

setc

ateg

ory

Asse

tcla

ssU

nits

H1H2

H3H4

H5G

rade

un

know

nDa

taa

ccur

acy

(1–4

)

39HV

Zone

Sub

stationTran

sformer

Zone

Sub

stationTran

sformers

No.

2.50

%

7.50

%

47.50%

35

.00%

7.50

%

-4

25.64%

40

HVDistrib

utionLine

Distrib

utionOHOpe

nWire

Con

ductor

km2.15

%

3.05

%

36.33%

53

.07%

5.40

%

-4

4.20

%

41HV

Distrib

utionLine

Distrib

utionOHAe

rialCab

leCon

ductor

km-

--

--

-4

-42

HVDistrib

utionLine

SWER

con

ductor

km-

--

--

-4

-43

HVDistrib

utionCa

ble

Distrib

utionUGXLPE

orP

VCkm

0.54

%

0.04

%

4.05

%

85.62%

9.75

%

-3

-44

HVDistrib

utionCa

ble

Distrib

utionUGPILC

km-

-24

.20%

74

.63%

1.17

%

-2

-45

HVDistrib

utionCa

ble

Distrib

utionSubm

arineCa

ble

km-

-10

0.00

%

--

-1

-46

HVDistrib

utionsw

itchg

ear

3.3/6.6/11

/22kVCB

(polemou

nted

)-re

closersa

ndse

ctiona

lisers

No.

9.67

%

--

83.88%

6.45

%

-4

9.68

%

47HV

Distrib

utionsw

itchg

ear

3.3/6.6/11

/22kVCB

(Ind

oor)

No.

--

--

--

4-

48HV

Distrib

utionsw

itchg

ear

3.3/6.6/11

/22kVSw

itche

sand

fuses(po

lem

ounted

)No.

4.48

%

2.41

%

17.21%

67

.93%

7.97

%

-2

3.39

%

49HV

Distrib

utionsw

itchg

ear

3.3/6.6/11

/22kVSw

itch(groun

dmou

nted

)-excep

tRMU

No.

14.28%

47

.61%

33

.33%

-

4.78

%

-3

66.67%

50

HVDistrib

utionsw

itchg

ear

3.3/6.6/11

/22kVRM

UNo.

0.96

%

0.48

%

8.17

%

81.25%

9.14

%

-4

7.21

%

51HV

Distrib

utionTran

sformer

PoleM

ounted

Transform

erNo.

6.80

%

3.29

%

17.72%

62

.62%

9.57

%

-3

7.32

%

52HV

Distrib

utionTran

sformer

Grou

ndM

ounted

Transform

erNo.

3.10

%

4.94

%

21.66%

60

.12%

10

.18%

-

35.56

%

53HV

Distrib

utionTran

sformer

Volta

gere

gulators

No.

--

20.00%

50

.00%

30

.00%

-

410

.00%

54

HVDistrib

utionSubstatio

nsGrou

ndM

ounted

Sub

stationHo

using

No.

14.87%

10

.74%

23

.14%

48

.76%

2.49

%

-4

12.40%

55

LVLVLine

LVOHCo

nductor

km1.00

%

2.97

%

39.10%

53

.36%

3.57

%

-4

2.36

%

56LV

LVCab

leLVUGCa

ble

km0.04

%

0.15

%

10.05%

76

.04%

13

.72%

-

20.31

%

57LV

LVStree

tligh

ting

LVOH/

UGStreetlightcirc

uit

km13

.48%

6.93

%

39.14%

35

.78%

4.67

%

-2

-58

LVCo

nnectio

nsOH/

UGconsum

erse

rviceconn

ectio

nsNo.

--

-19

.81%

80

.19%

-

30.26

%

59All

Protectio

nProtectio

nrelays(e

lectromecha

nical,solidstatean

dnu

meric)

No.

2.10

%

0.30

%

21.08%

75

.30%

1.22

%

-2

13.55%

60

All

SCAD

Aan

dcommun

ications

SCAD

Aan

dcommun

icationsequ

ipmen

tope

ratin

gasasing

lesy

stem

Lot

-10

0.00

%

--

--

410

0.00

%

61All

Capa

citorB

anks

Capa

citorsinclud

ingcontrols

No.

--

-10

0.00

%

--

46.90

%

62All

Load

Con

trol

Centralised

plant

Lot

33.33%

33

.33%

16

.66%

16

.68%

-

-4

50.00%

63

All

Load

Con

trol

Relays

No.

26.72%

11

.00%

32

.56%

28

.53%

1.19

%

-3

2.96

%

64All

Civils

CableTu

nnels

km-

--

--

-N/A

-

Asse

tcon

ditio

nat

star

tofp

lann

ing

perio

d(p

erce

ntag

eof

uni

tsb

ygr

ade)

%o

fass

et

fore

cast

tob

ere

plac

edin

ne

xt5

yea

rs

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 23

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

13S12b

.Cap

acity

Forecast

Com

pany

Nam

eN

orth

pow

erL

tdAM

PPl

anni

ngP

erio

d1

Apr

il20

20–

31

Mar

ch2

030

SCHE

DULE

12b

:REP

ORT

ON

FO

RECA

STC

APAC

ITY

sch

ref

712

b(i):

Sys

tem

Gro

wth

-Zo

neS

ubst

atio

ns

8

Exist

ing

Zone

Sub

stat

ions

Curr

entP

eak

Load

(MVA

)

Inst

alle

dFi

rm

Capa

city

(MVA

)

Secu

rity

ofS

uppl

yCl

assi

ficat

ion

(typ

e)Tr

ansf

erC

apac

ity(M

VA)

Util

isat

ion

of

Inst

alle

dFi

rm

Capa

city

%

Inst

alle

dFi

rm

Capa

city

+5

year

s(M

VA)

Util

isat

ion

of

Inst

alle

dFi

rm

Capa

city

+5

yrs

%

Inst

alle

dFi

rmC

apac

ity

Cons

trai

nt+

5ye

ars

(cau

se)

Expl

anat

ion

9Alexan

derS

tree

t13

15

N-1

13

88%

15

90%Noconstraintwith

in+5years

Load

tran

sferto

new

Mau

nuSub

station

10BreamBay

4-N

1-

--Other

SecurityOfSup

ply

11Da

rgaville

11

15N-1

176

%

15

82%Noconstraintwith

in+5years

12Hikurang

i6

5N-1Switcha

ble

312

5%

10

69%Noconstraintwith

in+5years

New

tran

sformers

13Ka

iwaka

2-N-1Switcha

ble

2-

--Noconstraintwith

in+5years

14Ka

mo

12

15N-1

782

%

15

93%Noconstraintwith

in+5years

15Kioreroa

12

20N-1

858

%

20

69%Noconstraintwith

in+5years

16Man

gawha

i7

-N

2-

--Other

SecurityOfSup

ply

17Mareretu

3-N

2-

--Noconstraintwith

in+5years

18Mau

ngatap

ere

78

N-1

692

%

10

63%Noconstraintwith

in+5years

Load

tran

sferto

new

Mau

nuSub

station

19Mau

ngaturoto

68

N-1

285

%

887

%Noconstraintwith

in+5years

20Ngu

nguru

3-N

3-

--Other

SecurityOfSup

ply

21One

rahi

815

N-1Switcha

ble

655

%

15

58%Noconstraintwith

in+5years

22Pa

ruaBa

y3

-N

3-

--Other

SecurityOfSup

ply

23Po

roti

3-N-1Switcha

ble

3-

--Noconstraintwith

in+5years

24Ru

akaka

710

N-1

571

%

10

78%Noconstraintwith

in+5years

25Ru

awai

3-N

3-

--

Noconstraintwith

in+5years

26Tikipu

nga

15

20N-1

13

76%

20

82%Noconstraintwith

in+5years

27Wha

ngareiSou

th12

10

N-1

10

119%

10

11

4%Noconstraintwith

in+5years

Load

tran

sferto

new

Mau

nuSub

station

29¹

Exte

ndfo

reca

stcap

acity

tabl

eas

nec

essa

ryto

disc

lose

all

capa

city

by

each

zone

subs

tatio

n

Thissche

dulere

quire

sabreakdo

wnofcurrentand

forecastcap

acity

and

utilisa

tionfore

achzone

substatio

nan

dcurren

tdistrib

utiontran

sformercap

acity

.The

dataprovided

shou

ldbeconsisten

twith

theinform

ationprovided

inth

eAM

P.In

form

ation

provided

inth

istableshou

ldre

lateto

theop

erationofth

ene

tworkinitsn

ormalsteadystateconfiguration.

Section 3

Page 24 Northpower Limited | Asset Management Plan Update 2020-2030

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

14S12c.Dem

andForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

d

SCHE

DULE

12C

:REP

ORT

ON

FO

RECA

STN

ETW

ORK

DEM

AND

sch

ref

712

c(i):

Con

sum

erC

onne

ctio

ns8

Num

bero

fICP

scon

nect

edin

yea

rby

cons

umer

type

9Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

10fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

11Co

nsum

erty

pesd

efin

edb

yED

B*12

Verylargeindu

stria

l-

--

--

-13

Commercialand

Indu

stria

l(de

man

dba

sedND9

)-

11

11

114

Massm

arket

941

960

979

999

1,01

91,03

917

Conn

ectio

nsto

tal

941

961

980

1,00

01,02

01,04

018

*inc

lude

add

ition

alro

wsi

fnee

ded

19Di

strib

uted

gen

erat

ion

20Num

bero

fcon

nections

169

200

200

200

200

200

21Ca

pacityofd

istrib

uted

gen

erationinstalledinyear(MVA

)1

11

11

1

2212

c(ii)

Sys

tem

Dem

and

23Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

24M

axim

umc

oinc

iden

tsys

tem

dem

and

(MW

)fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

25GX

Pde

man

d17

318

318

519

019

219

426

plus

Distrib

uted

gen

erationou

tputatH

Van

dab

ove

44

44

44

27M

axim

umc

oinc

iden

tsys

tem

dem

and

176

187

189

194

196

198

28le

ssNettran

sfersto(from

)otherEDB

satH

Van

dab

ove

--

--

--

29De

man

don

syst

emfo

rsup

ply

toc

onsu

mer

s'co

nnec

tion

poin

ts17

618

718

919

419

619

8

30El

ectr

icity

vol

umes

car

ried

(GW

h)31

Electricity

supp

liedfrom

GXP

s1,11

31,13

61,16

01,18

51,20

91,23

532

less

Electricity

exportsto

GXP

s-

--

--

-33

plus

Electricity

supp

liedfrom

distrib

uted

gen

eration

19

22

22

22

22

22

34le

ssNetelectric

itysu

ppliedto(from)o

therEDB

s-

--

--

-35

Elec

tric

itye

nter

ing

syst

emfo

rsup

ply

toIC

Ps1,13

21,15

81,18

21,20

71,23

11,25

736

less

Totalene

rgyde

livered

toIC

Ps1,10

01,12

21,14

41,16

71,19

11,21

437

Loss

es32

36

38

39

41

42

38 39

Load

fact

or73

%

71%

72%

71%

72%

72%

40Lo

ssra

tio2.8%

3.1%

3.2%

3.3%

3.3%

3.4%

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Num

bero

fcon

nect

ions

Thissche

dulere

quire

safo

recastofn

ewcon

nections(b

yconsum

erty

pe),pe

akdem

andan

den

ergyvolum

esfo

rthe

disc

losureyeara

nda5yearp

lann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

Pas

wellasthe

assum

ptionsusedindevelop

ingtheexpe

nditu

refo

recastsinSche

dule11aand

Sched

ule11

ban

dthecapa

cityand

utilisa

tionforecastsinSche

dule12b

.

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 25

CommerceCom

miss

ionInform

ationDisclosureTem

plate

NPAM

PYB

Disc

losureSched

ules202

0v1.4.xlsx

15S12d

.ReliabilityForecast

Com

pany

Nam

eAM

PPl

anni

ngP

erio

dNet

wor

k/S

ub-n

etw

ork

Nam

e

SCHE

DULE

12d

:REP

ORT

FO

RECA

STIN

TERR

UPT

ION

SAN

DDU

RATI

ON

sch

ref

8Cu

rren

tYea

rCY

CY+1

CY+2

CY+3

CY+4

CY+5

9fory

eare

nded

31M

ar2

031

Mar

21

31M

ar2

231

Mar

23

31M

ar2

431

Mar

25

10SA

IDI

11ClassB

(plann

edinterrup

tionsonthene

twork)

114.0

100.0

100.0

100.0

100.0

100.0

12ClassC

(unp

lann

edinterrup

tionsonthene

twork)

151.0

105.0

105.0

100.0

100.0

100.0

13SA

IFI

14ClassB

(plann

edinterrup

tionsonthene

twork)

0.46

0.50

0.50

0.50

0.50

0.50

15

ClassC

(unp

lann

edinterrup

tionsonthene

twork)

3.15

2.75

2.75

2.75

2.75

2.75

Nor

thpo

wer

Ltd

1A

pril

2020

–3

1M

arch

203

0

Thissche

dulere

quire

safo

recastofSAIFIand

SAIDIfo

rdisc

losureand

a5yearp

lann

ingpe

riod.The

forecastss

houldbe

con

sistentwith

thesupp

ortin

ginform

ationseto

utinth

eAM

Paswellasthe

assum

edim

pactofp

lann

ed

andun

plan

nedSA

IFIand

SAIDIontheexpe

nditu

resforecastp

rovide

dinSched

ule11

aan

dSche

dule11b

.

Section 3

Northpower Limited | Asset Management Plan Update 2020-2030 Page 27

Electricity Distribution Information Disclosure Determination 2012 – (consolidated in 2015)

1. This Schedule requires EDBs to provide explanatory notes to reports prepared in accordance with clause 2.6.6.

2. This Schedule is mandatory—EDBs must provide the explanatory comment specified below, in accordance with clause 2.7.2. This information is not part of the audited disclosure information, and so is not subject to the assurance requirements specified in section 2.8.

Commentary on difference between nominal and constant price capital expenditure forecasts (Schedule 11a)

3. In the box below, comment on the difference between nominal and constant price capital expenditure for the disclosure year and 10 year planning period, as disclosed in Schedule 11a.

Box 1: Commentary on difference between nominal and constant price capital expenditure forecasts The differences between nominal and constant prices is based on the application of an escalation factor using Reserve Bank economic projections.

Commentary on difference between nominal and constant price capital expenditure forecasts (Schedule 11b)

4. In the box below, comment on the difference between nominal and constant price operational expenditure for the disclosure year and 10 year planning period, as disclosed in Schedule 11b.

Box 2: Commentary on difference between nominal and constant price operational expenditure forecasts The differences between nominal and constant prices is based on the application of an escalation factor using Reserve Bank economic projections.

Schedule 14a: Mandatory Explanatory Notes on Forecast Information

Page 26 Northpower Limited | Asset Management Plan Update 2020-2030

Northpower Limited | Asset Management Plan Update 2020-2030 Page 27

Section 4: Director Certification

We, Richard Booth and Mark Trigg, being Directors of Northpower Limited certify that, having made all reasonable enquiry, to the best of our knowledge:

a) The following attached information of Northpower Limited prepared for the purposes of clauses 2.6.1, 2.6.3, 2.6.6 and 2.7.2 of the Electricity Distribution Information Disclosure Determination 2012 in all material respects complies with that determination.

b) The prospective financial or non-financial information included in the attached information has been measured on a basis consistent with regulatory requirements or recognised industry standards.

c) The forecasts in Schedules 11a, 11b, 12a, 12b, 12c and 12d are based on objective and reasonable assumptions, which both align with Northpower Limited’s corporate vision and strategy and are documented in retained records.

Director Director

Date: 25/03/2020 Date: 25/03/2020

Director Certification

Northpower Limited | Asset Management Plan Update 2020-2030 Page 31

Section 4: Director Certification

Head Office:Northpower Ltd28 Mt Pleasant Road,Raumanga, Whangarei 0110,New Zealand

Postal Address:Northpower LtdPrivate Bag 9018,Whangarei Mail Centre 0148,New Zealand

Ph: 09 430 1803Fax: 09 430 1804Email: [email protected]: northpower.com