att 1 to qms sec 101 quality program schedule 050309

31
Page 1 of 2 16.11.07 REV. 0 QMS-F101-001 QUALITY MANAGEMENT SYSTEM MANUAL MAKATI OFFICE/SITE OFFICE QUALITY PROGRAM SCHEDULE FY 2009 AS OF September 2009 PROGRAMS 2009 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-10 Nov-10 Dec-10 Plan 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 A QA/QC Meetings 1 Kick off meeting Q 2 Closing Meeting Q 3 Weekly Managers Meeting 4 Monthly Managers Meeting 5 Meeting with Owner/Consultant B 1 2 Monthly QA/QC Audit Seminars 1 Prepared by: Noted by: Note : Remarks: Kickoff meeting and closing meeting schedule is reflected on each project schedule Q - Programmed Schedule will base on the owners/consultant time availability or as per suggested/recommended s QA/QC Engineer PMS Manager (Color Shaded) ITEM NO. Target no. of Staff/ Project Manpower/ Project/ Times Actua l Quality Inspections and Quality Audit DAILY QA/QC Inspection by QA/QC Engineer Monthly Seminar for special course and training ACTUAL Q

Upload: prokjong

Post on 24-Dec-2015

215 views

Category:

Documents


0 download

DESCRIPTION

Quality Program Schedule Form Sample

TRANSCRIPT

Page 1: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

MAKATI OFFICE/SITE OFFICE

QUALITY PROGRAM SCHEDULE FY 2009AS OF September 2009

PROGRAMS

2009

Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-10 Nov-10 Dec-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4A QA/QC Meetings

1 Kick off meeting QQ2 Closing Meeting QQ3 Weekly Managers Meeting

4 Monthly Managers Meeting

5 Meeting with Owner/Consultant

B Quality Inspections and Quality Audit

1

2 Monthly QA/QC Audit

Seminars

1

Prepared by: Noted by: Note : Remarks:

Kickoff meeting and closing meeting schedule is reflected on each project schedule

Q - Programmed Schedule will base on the owners/consultant time availability or as per suggested/recommended schedule.QA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Manpower/ Project/ Times

DAILY QA/QC Inspection by QA/QC Engineer

Monthly Seminar for special course and training

ACTUALQ

Page 2: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

MAKATI OFFICE/SITE OFFICEQUALITY PROGRAM SCHEDULE FY 2009

As of June 2009

PROGRAMS

2009Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-10 Nov-10 Dec-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

C

1 Quality Management System QQ QQ2 Documents and Records Management

3 Procurement

4 Assessment of Supplier/Subcontractor

5 Project Work Process Control

6 Project Quality Plan

7 Control of Technical Documentation

8 Inspection and Testing

9

10 Control of Monitoring Devices

11 System Program Audit

12

Prepared by: Noted by: Note : Remarks:

ACTUAL

- ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Manpower/ Project

Quality Management Manual Training /Orientation

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Seminars, training and briefing will be based on availability of staffs and workers so as not to conflict with project schedule. However, for others specially new staff are scheduled for orientation immediately before deployment to projects.

Q

Q

Page 3: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

Taganito Hydrometallurgical Plant

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 Kick off meeting Q Q Q2 Closing Meeting

3 Handover

4 QQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQ5 Monthly QA/QC Meeting Q Q Q Q Q Q Q Q Q Q6 Q QQ Q Q Q Q Q7 Managers Meeting (Makati) Q Q Q Q Q Q Q Q Q Q8 Weekly Meeting QQQ

1 Q Q Q Q Q Q Q Q Q Q2 Documents and Records Management Q Q Q Q Q Q Q Q Q Q3 Procurement Management Q Q Q Q Q Q Q Q Q Q4 Project Works Process Control Q Q Q Q Q Q Q Q Q Q5 Logistic Management Q Q Q Q Q Q Q Q Q Q6 Q Q Q Q Q Q Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmationAll schedule are subject to change depending on actual site activity.

Q - Programmed QA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Taget No. of Staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly Coordination Meeting with Owner/Consultant

Quality Management System Manual Training and Orientation

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Page 4: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

Taganito Hydrometallurgical Plant

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Seminars

1 Q Q Q Q Q Q Q Q Q Q

Quality Inspections and Quality Audit

1 QQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQ2 Monthly QA/QC Audit Q Q Q Q QQ Q Q Q Q Q

Remarks:

Q - Schedule for confirmation All schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer

Page 5: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

Taganito Hydrometallurgical Plant

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

4

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly PQP Training for Taganito Mining Project

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Page 6: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

Sakamoto Orient Chemical Corp. Area-2 Expansion 08

QUALITY PROGRAM SCHEDULE FY 2009As of June 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 Kick off meeting

2 Closing Meeting Q2 Handover Q3 Q Q Q Q Q Q Q Q Q Q4 Monthly QA/QC Meeting Q Q Q Q Q Q Q Q Q Q Q Q Q5 Q6 Managers Meeting (Makati) Q Q

Quality Management System Manual

1 Q Q Q Q QDocuments and Records Management Q Q Q Q QProcurement Management Q Q Q Q QProject Works Process Control Q Q Q Q QLogistic Management Q Q Q Q Q

Q Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly Coordination Meeting with Owner/Consultant

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Q

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

Q Q Q

ACTUAL

Page 7: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

Sakamoto Orient Chemical Corp. Area-2 Expansion 08

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Seminars

1 Q Q Q Q Q Q

Quality Inspections and Quality Audit

1 Q Q Q Q Q Q Q Q Q2 Monthly QA/QC Audit Q Q

Prepared by: Noted by: Note : Remarks:

All schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO. Target no.

of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer Q Q Q Q Q Q QQ QQ Q Q Q

Q

Q

Q Q

Page 8: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

WYETH DRYER 3 PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 Closing Meeting

2 Handover Q3 Q Q4 Monthly QA/QC Meeting Q5

6 Managers Meeting (Makati)

Quality Management System Manual

1

Documents and Records Management

Procurement Management

Project Works Process Control

Logistic Management

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmationAll schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly Coordination Meeting for Wyeth Dryer 3 Expansion Project (JES PMS Group)-Weekly

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Page 9: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

WYETH DRYER 3 PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Seminars

1 Q

Quality Inspections and Quality Audit

1 Q Q2 Monthly QA/QC Audit

Remarks:

Q - Schedule for confirmation All schedule are subject to change depending on actual site activity.

ITEM NO. Target no.

of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer

Page 10: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

Page 11: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

WYETH DRYER 3 PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

4 Monthly PQP Training for Wyeth Project

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Page 12: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

AGAS AGAS PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 Closing Meeting Q2 Handover Q3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q4 Monthly QA/QC Meeting Q Q Q Q Q Q Q Q5 Monthly Coordination Meeting Q Q Q Q6 Managers Meeting (Makati) Q Q Q Q

Quality Management System Manual

1 Q Q Q QDocuments and Records Management Q Q Q QProcurement Management Q Q Q QProject Works Process Control Q Q Q QLogistic Management Q Q Q Q

Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmationAll schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Page 13: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

AGAS AGAS PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Seminars

1 Q Q Q Q

Quality Inspections and Quality Audit

1 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q2 Monthly QA/QC Audit Q Q Q Q

Remarks:

Q - Schedule for confirmation All schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer

Page 14: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

AGAS AGAS PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

4

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly PQP Training for Bangui Bay Wind Power Project Phase 2

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Page 15: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

SUPERNATANT PIPE PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 Kick off meeting Q2 Closing Meeting Q2 Handover Q3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q4 Monthly QA/QC Meeting Q Q Q Q Q Q Q Q Q Q Q5 Q Q Q Q Q6 Managers Meeting (Makati) Q Q Q Q Q

Quality Management System Manual

1 Q Q Q Q Q QDocuments and Records Management Q Q Q Q Q QProcurement Management Q Q Q Q Q QProject Works Process Control Q Q Q Q Q QLogistic Management Q Q Q Q Q Q

Q Q Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmationAll schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly Coordination Meeting with Owner/Consultant

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Page 16: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

SUPERNATANT PIPE PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Seminars

1 Q Q Q Q Q

Quality Inspections and Quality Audit

1 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q2 Monthly QA/QC Audit Q Q Q Q Q

Remarks:

Q - Schedule for confirmation All schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO. Target no.

of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer

Page 17: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

SUPERNATANT PIPE PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

4

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly PQP Training for Sakamoto Project

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Page 18: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

TAILINGS DAM PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 Kick off meeting

2 Closing Meeting Q2 Handover Q3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q4 Monthly QA/QC Meeting Q Q Q Q Q Q Q Q Q5 Q Q Q Q6 Managers Meeting (Makati) Q Q Q Q

Quality Management System Manual

1 Q Q Q Q QDocuments and Records Management Q Q Q Q QProcurement Management Q Q Q Q QProject Works Process Control Q Q Q Q QLogistic Management Q Q Q Q Q

Q Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmationAll schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly Coordination Meeting with Owner/Consultant

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Page 19: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

TAILINGS DAM PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Seminars

1 Q Q Q Q

Quality Inspections and Quality Audit

1 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q2 Monthly QA/QC Audit Q Q Q Q

Remarks:

Q - Schedule for confirmation All schedule are subject to change depending on actual site activity.

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO. Target no.

of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer

Page 20: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

TAILINGS DAM PROJECT

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

4

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly PQP Training for Sakamoto Project

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Page 21: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

Projects Actual Quality Program

QUALITY PROGRAM SCHEDULE FY 2009 (ACTUAL)

PROGRAMSManhour

JANUARY-MARCH 2009SAKAMOTO 08 WYETH AGAS-AGAS TAILINGS DAM

Jan-09 Feb-09 Mar-09 Jan-09 Feb-09 Mar-09 Jan-09 Feb-09 Mar-09 Jan-09 Feb-09 Mar-09Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

QA/QC Meetings

1 Kick off meeting Q Q2 Closing Meeting Q2 Handover

3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q4 Monthly QA/QC Meeting Q Q Q Q Q Q5

6 Managers Meeting (Makati) Q Q Q Q Q Q Q Q Q

Quality Management System Manual

1

Documents and Records Management

Procurement Management

Project Works Process Control

Logistic Management

Prepared by: Noted by: Note : Remarks:

All schedule are subject to change depending on actual site activity.

Q - ActualQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Daily Coordination Meeting (with staffs and subcons)

Monthly Coordination Meeting with Owner/Consultant

Monthly QMS briefing and orientation for all staffs

Project Audit, Corrective and Preventive Action

Page 22: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 2

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

Projects Actual Quality Program

QUALITY PROGRAM SCHEDULE FY 2009 (ACTUAL)

PROGRAMSManhour

JANUARY-MARCH 2009SAKAMOTO 08 WYETH AGAS-AGAS TAILINGS DAM

Jan-09 Feb-09 Mar-09 Jan-09 Feb-09 Mar-09 Jan-09 Feb-09 Mar-09 Jan-09 Feb-09 Mar-09Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Seminars

1

Quality Inspections and Quality Audit

1 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q2 Monthly QA/QC Audit Q Q Q Q Q Q Q Q

Remarks:

All schedule are subject to change depending on actual site activity.

Q - ActualQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO. Target no.

of Staff/ Project

Monthly Seminar for special course and training

DAILY QA/QC Inspection by QA/QC Engineer

Page 23: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 3

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

Sakamoto Orient Chemical Corp. Area-2 Expansion 08

QUALITY PROGRAM SCHEDULE FY 2009

PROGRAMSManhour

2009-2010Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

Plan Actual 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

4

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Target no. of Staff/ Project

Monthly PQP Training for Sakamoto Project

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive Action

Page 24: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 1 of 4

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

QUALITY PROGRAM FY 2009 (ACTUAL)

PROGRAMS

2009

Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 QQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQ

2 QQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQ

3 Q Q Q Q Q Q Q Q Q Q Q Q

4 Q Q Q Q Q5 Q Q Q Q Q Q6 Q Q Q Q Q Q Q Q Q Q Q Q

7 Q Q Q Q Q Q Q Q Q Q Q Q

9 Q Q Q Q Q Q Q Q Q Q Q Q10 Q Q Q Q Q Q Q Q Q Q Q Q

11 Q Q Q Q Q Q Q Q Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Quality Inspections and Quality Audits

DAILY QA/QC Inspection by Safety Officer (for new projects)

Weekly Safety Inspection by Subcontractor Trade Supervisors (for new projects)

Monthly QA/QC Inspection with Client PMS Representative (all on-going projects)

Monthly QA/QC Audit for WYETH Dryer 3 Project

Monthly QA/QC Audit for Coral Bay 7 Project

Monthly QA/QC Audit for Coral Bay 8 Project (schedule to be confirmed once project starts)Monthly QA/QC Audit for Coral Bay 9 Project (schedule to be confirmed once project starts)

Monthly QA/QC Audit for Bangui Bay Wind Power Phase 2 Project

Monthly QA/QC Audit for Package V Agas-Agas Bridge Project

Monthly QA/QC Audit for JGC Ethanol Project (schedule to be confirmed once project starts)

Monthly Managers Meeting in Makati office (Every 3rd week of the month)

Page 25: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 2 of 4

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUALAPPENDIX 3G

QUALITY PROGRAM SCHEDULE FY 2008

PROGRAMS

2009Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4QA/QC Meetings

1 QQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQ2 QQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQQ3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q4

Q Q Q Q Q Q5

Q Q Q Q Q Q6

Q Q Q Q Q Q Q Q Q Q Q Q7

Q Q Q Q Q Q Q Q Q Q Q Q8

Q Q Q Q Q Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

ITEM NO.

Kick-Off Meeting with Client (schedule to be confirmed)

Kick-Off Meeting with Subcontractors (schedule to be confirmed)

Daily Coordination Meeting (all on-going projects)

Monthly QA/QC Meeting for Wyeth Dryer 3 Expansion Project (SMCC PMS Group)

Monthly Coordination Meeting for Wyeth Dryer 3 Expansion Project (JES PMS Group)

Monthly QA/QC Meeting for Package V Agas-Agas Bridge Project (SMCC PMS Group)

Monthly QA/QC Meeting for Bangui Bay Wind Power Project Phase 2 (SMCC PMS Group)

Monthly QA/QC Meeting for Coral Bay 7 Project (SMCC PMS Group)

Page 26: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Page 3 of 4

16.11.07 REV. 0

QMS-F101-001QUALITY MANAGEMENT SYSTEM MANUAL

APPENDIX 3G

QUALITY PROGRAM SCHEDULE FY 2008

2007 - 2008Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Quality Management Manual Training

1

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QControl and Testing Q

2

Quality Management System QDocuments and Records Management QProcurement QAssessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan QControl of Technical Documentation QInspection and Testing Q

QControl of Monitoring Devices QSystem Program Audit Q

Q3

Quality Management System QDocuments and Records Management QProcurement Q

ITEM NO.

PROGRAMS

Monthly PQP Training for Wyeth Dryer 3 Expansion Project

Monthly PQP Training for Package V Agas Agas Bridge Project

Handling Storage and Preservation / Identification and traceability

Control of Non conforming Products/Corrective and Preventive ActionMonthly PQP Training for Coral Bay 7 Project

Page 27: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Assessment of Supplier/Subcontractor QProject Work Process Control QProject Quality Plan Q

Prepared by: Noted by: Note : Remarks:

Q - Schedule for confirmation

Q - ProgrammedQA/QC Engineer PMS Manager (Color Shaded)

Page 28: Att 1 to QMS Sec 101 Quality Program Schedule 050309

Run on 7/18/2009 15:13

Minor loss of fidelity # of occurrences

8

Compatibility Report for QMS F-101-01 Quality Program Schedule 050309.xls

The following features in this workbook are not supported by earlier versions of Excel. These features may be lost or degraded when you save this workbook in an earlier file format.

Some cells or styles in this workbook contain formatting that is not supported by the selected file format. These formats will be converted to the closest format available.