attachment y study report - oatioasis.com · attachment y study report draft february 6, 2017 ......
TRANSCRIPT
Cleco Power LLC
Teche Unit #3: 335 MW, Gas
Retirement Date
04/01/2017
ATTACHMENT Y STUDY
REPORT DRAFT
February 6, 2017
Redacted (Public)
DRAFT 2
EXECUTIVE SUMMARY
An Attachment Y notification submitted by Cleco Power LLC was received by MISO on
September 20, 2016. The request was for retirement of the Teche Unit #3 located in Baldwin,
Louisiana effective April 1, 2017.
MISO performed a transmission system reliability assessment that was discussed and reviewed
with the impacted Transmission Owners (TOs): Cleco Power, Lafayette Utility services and
Entergy. The analysis determined that there are four (4) unresolved reliability violations on the
Transmission System that are not addressed by available mitigation measures.
After being reviewed for power system reliability impacts as provided for under Section 38.2.7
of MISO’s Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”),
MISO determined that the retirement of Teche Unit 3 will result in violations of applicable
reliability criteria. Therefore, Teche Unit 3 may be designated as a System Support Resource
(“SSR”) unit as defined in the Tariff until previously approved transmission project for
Terrebone-Bayou Vista 230 kV transmission line (MTEP ID: 7988; ISD: 06/01/2018) is in
service.
MISO will initiate the open stakeholder process to review Attachment Y reliability study results
and discuss potential alternatives to avoid the need for an SSR agreement. In the event the open
stakeholder process determines that previously identified mitigation plans are not feasible and
that an appropriate alternative is not identified, Teche Unit 3 will be designated as SSR units.
DRAFT 3
Contents I. Introduction ............................................................................................................................. 4
II. Study objectives ....................................................................................................................... 5
III. Models and Assumptions......................................................................................................... 6
3.1 Study Models ................................................................................................................ 6
3.2 Model Assumptions ...................................................................................................... 6
3.3 Table of Models ............................................................................................................ 7
IV. Steady State Study Criteria and Methodology ........................................................................ 8
4.1. TO Transmission Planning criteria ............................................................................... 8
4.2 MISO Transmission Planning BPM - SSR Criteria ...................................................... 9
4.3 Steady State Performance Analysis Parameters ........................................................... 9
V. Study Results ......................................................................................................................... 10
VI. SSR Alternative Analysis ...................................................................................................... 12
6.1 New Generation or Generation Re-dispatch ............................................................... 12
6.2 System Reconfiguration and Operation Guidelines .................................................... 12
6.3 Demand Response or Load Curtailment ..................................................................... 12
6.4 Transmission Projects ................................................................................................. 12
VII. SSR Agreement Cost allocation ............................................................................................ 14
VIII. Conclusion ...................................................................................................................... 15
IX. Appendices ............................................................................................................................ 16
DRAFT 4
I. INTRODUCTION
On September 20, 2016, Cleco Energy LLC submitted an Attachment Y notice to MISO to retire
the Teche Unit 3 effective April 1, 2017.
Teche Unit 3 is a natural gas fired generator with a capacity of 335 MW interconnected to the
Cleco 138kV transmission system. The plant is located in Baldwin, Louisiana.
Table 1: Units Requesting Retirement
Power Flow Area Unit
Description
Net
Reduction
(MW)
Start Date of
Retirement
Cleco Teche Unit 3 335 04/01/2017
Figure 1: General Location of Teche Unit 3
DRAFT 5
II. STUDY OBJECTIVES
The procedures under Section 38.2.7 of the MISO Tariff provide a mechanism for MISO to
assess reliability impact of retirement or suspension of a Generation Resource or Synchronous
Condenser Unit (SCU) and enter into an agreement with the Market Participants (MP) that own
or operate the Generation Resource or SCU that are required to maintain system reliability.
The principal objective of an Attachment Y reliability study is to determine if the unit(s) for
which a change in status is requested is necessary for system reliability based on the criteria set
forth in the MISO Transmission Planning Business Practice Manual. The study work includes
monitoring and identifying the steady state branch/voltage violations on transmission facilities
due to the unavailability of the Generation Resource or SCU. The relevant MISO Transmission
Owner and/or regional reliability criteria are used for monitoring such violations.
DRAFT 6
III. MODELS AND ASSUMPTIONS
3.1 Study Models
Studies were performed using the following power flow models:
2017 SP (Source: MTEP16 – 2018 Summer Peak model)
2017 SH (Source: MTEP16 – 2021 Summer Shoulder model)
2021 SP (Source: MTEP16 – 2021 Summer Peak model)
The Attachment Y study models were created in accordance with the MISO Transmission
Planning Business Practice Manual (BPM-020-r15) Section 6.2.2. This includes creating a set of
Security Constrained Economic Dispatch (SCED) models from each source model in which the
units being studied are taken out of service to represent the “After” retirement scenario. The
models are used to create “Before” retirement scenario by dispatching the unit under study at
maximum capability and scaling down generation in MISO footprint outside of Cleco area.
3.2 Model Assumptions
a. Generation
Previously approved Generation Retirements and new Generators with signed
Interconnection Agreement were modelled as per their respective effective dates.
b. Load Growth
MTEP16-2021SH case load values were scaled down to create 2017SH case.
Additionally, inputs from TOs were incorporated for load values
c. Transmission
All MTEP Appendix A approved projects were included in the study base case.
d. Monitor
Following areas were monitored for thermal and voltage violations.
EES (351) Area 69 kV – 999 kV and zones 385, 386, 387, 388, 389
CLECO (502) Area 69 kV – 999 kV and zones 500, 501, and 502
LAGN (332) Area 69 kV – 999 kV and zone 310
LAFA Area 503, zone 512
e. Contingencies
NERC Category P1, P2, P4, P5, P7 contingencies and selected P3, P6 contingencies that
were determined to be impacting the study area* in the CLECO, LAFA, and EES areas
were evaluated.
Category P3 and P6 contingencies were created from a subset of Category P1 events in
the nearby area and units above 50MW.
DRAFT 7
3.3 Table of Models
S.no Source Case Teche Unit 3 Contingency Categories
1 2017 SP ON P1, P2, P3, P4, P5, P6, P7
2 2017 SP OFF P1, P2, P3, P4, P5, P6, P7
3 2017 SH ON P1, P2, P3, P4, P5, P6, P7
4 2017 SH OFF P1, P2, P3, P4, P5, P6, P7
5 2021 SP ON P1, P2, P3, P4, P5, P6, P7
6 2021 SP OFF P1, P2, P3, P4, P5, P6, P7
DRAFT 8
IV. STEADY STATE STUDY CRITERIA AND METHODOLOGY
4.1. TO Transmission Planning criteria
Entergy Transmission Owners Planning Criteria
Entergy Transmission Planning Criteria applied for the thermal analysis:
For NERC Category P0 contingencies, all thermal loadings exceeding 100% of the
normal rating for Entergy System
For NERC Category P1 – P7 contingencies, all thermal loadings exceeding 100% of the
normal rating for Entergy System
Entergy Transmission Planning Criteria applied for the voltage analysis:
For NERC Category P0 contingencies
o KV>=300 - all substation voltages less than 97.5% or above 105%
o 100 < KV< 300 – all substation voltages less than 95% or above 105%
For NERC Category P1- P7 contingencies
o KV >300 – all substation voltages less than 95% or above 105%
o 100 < KV< 300 - all substation voltages less than 92% or above 105% for load or
gen bus
o 100 < KV< 300 - all substation voltages less than 90% or above 105% for non
load or non gen bus
o all substation voltages less than 90% or above 105% for non BES facilities
CLECO Transmission Owners Planning Criteria
CLECO Transmission Planning Criteria applied for the thermal analysis:
For NERC Category P0 contingencies, all thermal loadings exceeding 100% of the
normal rating for CLECO System
For NERC Category P1 – P7 contingencies, all thermal loadings exceeding 100% of the
emergency rating for CLECO System
CLECO Transmission Planning Criteria applied for the voltage analysis:
For NERC Category P0 contingencies, all substation voltages less than 95% or above
105%
For NERC Category P1 – P7 contingencies, all substation voltages less than 90% or
above 105%
LAFA Transmission Owners Planning Criteria
LAFA Transmission Planning Criteria applied for the thermal analysis:
DRAFT 9
For NERC Category P0 contingencies, all thermal loadings exceeding 100% of the
normal rating for LAFA System
For NERC Category P1 – P7 contingencies, all thermal loadings exceeding 100% of the
emergency rating for LAFA System
LAFA Transmission Planning Criteria applied for the voltage analysis:
For NERC Category P0 contingencies, all substation voltages less than 95% or above
105%
For NERC Category P1 – P7 contingencies, all substation voltages less than 90% or
above 105%
4.2 MISO Transmission Planning BPM - SSR Criteria
Per MISO BPM-020 r15 under Category P2 through P7 contingencies, for the valid thermal and
voltage violations as specified above, generation re-dispatch, system reconfiguration, and/or load
shedding are considered.
System Support Resource criteria for determining if an identified facility is impacted by the
generator change of status are:
Under Category P0 (system intact) and Category P1 (single event) contingencies, branch
thermal violations are only valid if the flow increase on the element in the “after”
retirement scenario is equal to or greater than:
a) Five percent (5%) of the “to-be-retired” unit(s) MW amount (i.e. 5% PTDF) for a
“base” violation compared with the “before” retirement scenario, or
b) Three percent (3%) of the “to-be-retired” unit(s) amount (i.e. 3% OTDF) for a
“contingency” violation compared with the “before” retirement scenario.
Under Category P0 (system intact) and Category P1 (single event) contingencies, high
and low voltage violations are only valid if the change in voltage is greater than 1% as
compared to the “before” retirement voltage calculation.
4.3 Steady State Performance Analysis Parameters
PSSE and TARA were used to perform steady state AC contingency analysis. Cases were solved
with automatic control of LTCs, phase shifters, DC taps, switched shunts enabled (regulating),
and area interchange disabled. Contingency analysis was performed on before and after cases.
The results were compared to find if there were any criteria violations due to the unit(s) change
of status
DRAFT 10
V. STUDY RESULTS
Thermal Results (Appendix A)
Appendix A shows contingent conditions causing branch criteria violations without Teche
Unit 3 where the unit impact on the affected facilities exceeded 3% OTDF or 5% PTDF.
2017 Summer Peak
Three (3) NERC Category P4 contingencies result in overloading of eight (8) Transmission
System facilities. Category P4 contingencies are not mitigated by SSR Unit since no
requirement exists for pre-commitment of generation for operational reliability. Hence, these
contingencies are not contributing to Teche Unit 3 designation as SSR.
Forty-two (42) NERC Category P6 contingencies result in thermal overloading of 16
Transmission System facilities. The thermal overloading caused by thirty-nine (39) of the
Category P6 events is addressed by available generation redispatch and load shedding
mitigation that is permitted by the applicable planning criteria (NERC and Transmission
Owner’s planning criteria).
Two NERC Category P6 contingencies result in severe thermal violations (>125%) for
MEAUX to ABBEVILLE 138 kV line which cannot be mitigated sufficiently with available
generation redispatch and presents a significant risk of potential cascading. These
contingencies require Teche Unit 3 to be available for dispatch and are contributing for
Teche 3 to be on SSR. Terrebonne to Bayou Vista 230 kV project (MISO MTEP ID: 7988 In
Service date 06/01/2018) reduces these violations below the limit where load shed is
permitted by the applicable planning criteria (NERC and Transmission Owner’s planning
criteria).
One NERC Category P6 contingencies result in severe thermal violations for MORILSPLT
to DUBOIN to BAYOU_WHSE to IVANHOE4 138kV circuits which cannot be adequately
alleviated with available generation redispatch. These contingency requires Teche Unit 3 to
be available for dispatch and is contributing for Teche 3 to be on SSR. Terrebonne to Bayou
Vista 230 kV project (MISO MTEP ID: 7988 In Service date 06/01/2018) reduces these
violations below the limit where load shed is permitted by the applicable planning criteria
(NERC and Transmission Owner’s planning criteria).
2017 Shoulder Peak
Three (3) NERC Category P4 contingencies result in overloading of seven (7) Transmission
System facilities. NERC Category P4 events are not mitigation by the SSR Unit since no
requirement exists for pre-commitment of the generation. Hence, these contingencies are not
contributing to Teche Unit 3 designation as SSR.
Eighteen (18) NERC Category P6 contingencies results in thermal overloading of twelve (12)
Transmission System facilities. The resulting overloads are mitigated by available generation
re-dispatch and load shedding that is permitted by the applicable planning criteria (NERC
and Transmission Owner’s planning criteria).
DRAFT 11
2021 Summer Peak
Two (2) NERC Category P4 contingencies result in overloading of one (1) thermal overload:
NERC Category P4 events are not mitigation by the SSR Unit since no requirement exists for
pre-commitment of the generation. Hence, these contingencies are not contributing to Teche
Unit 3 designation as SSR.
Twenty-two (24) NERC Category P6 contingencies result in overloading of eleven (11)
facility overloads which are mitigated by available generation re-dispatch option and load
shedding that is permitted by the applicable planning criteria (NERC and Transmission
Owner’s planning criteria).
Further details of the thermal results can be found in Appendix A Table 1.
Bus voltage results (Appendix A)
Appendix A shows contingent conditions causing voltage violations without Teche Unit 3
where the unit impact on the affected facilities exceeded 1% of pre-retirement voltage.
2017 Summer Peak
Two (2) NERC Category P6 contingencies cause voltage violations on area 138 kV
Transmission System buses. These overloads can be mitigated by allowable load shedding
that is permitted by the applicable planning criteria (NERC and Transmission Owner’s
planning criteria).
2017 Shoulder Peak
Two (2) NERC Category P6 contingencies result in voltage violations on 138 kV
Transmission System buses. These violations can be mitigated by allowable generation re-
dispatch of nearby generation resources.
2021 Summer Peak
Two (2) NERC Category P6 contingencies cause voltage violations on 138 kV Transmission
System buses. These violations can be mitigated by allowable load shedding actions. One (1)
NERC Category P6 contingency results in voltage violations on area 115kV Transmission
System buses. These violations can be mitigated by allowable generation re-dispatch of
nearby generation resources.
Further details of the voltage results can be found in Appendix A table 2.
DRAFT 12
VI. SSR ALTERNATIVE ANALYSIS
6.1 New Generation or Generation Re-dispatch
The re-dispatch of available generation resources was evaluated as an alternative solution to
mitigate the identified NERC Category P6 events. The proposed re-dispatch plan was shown to
be effective in reducing thermal overloads for many of the constraints with further mitigating
actions required to completely relieve the constraints. However, generation redispatch did not
fully address the excessive thermal overloading observed for the three (3) contingent events
which remain unresolved and require the need for the SSR Unit. Details about the re-dispatch
can be found in Appendix A table 1.
6.2 System Reconfiguration and Operation Guidelines
No existing operating guide will alleviate the unresolved thermal overloading caused by the three
NERC Category P6 events. System reconfiguration and switching options were investigated in
coordination with participating TOs and confirmed that the excessive overloads caused by the
three (3) contingent events cannot be successfully mitigated by any reconfiguration or switching
option.
Teche Unit 3 resource is a gas fired unit, which needs 18 to 22 hours of notification time. During
normal system operations, any of the first element outages from the set of identified
contingencies will require the unit to be committed to protect against the overloading that results
from the second event. Due to longer notification time, unit commitment needs to be done ahead
of time in anticipation of first element outage for higher load level. Hence, an operating guide is
being developed to commit Teche Unit 3 based on the load levels in the area around Teche plant
(Acadiana load pocket).
6.3 Demand Response or Load Curtailment
No contracted demand response alternative exists to provide load curtailment relief for the
reliability issues identified in the study. Load curtailment analysis was performed to estimate the
maximum amount of load shedding required to alleviate the overloads due to NERC Category P6
contingent events that requires Teche Unit 3 as an SSR Unit. This amount of contracted demand
response needed to provide comparable relief to the SSR Unit was estimated to be 134 MW and
would be required following the first event to avoid risk of cascading outages and resulting
voltage collapse. The results of the analysis are included in Appendix B.
6.4 Transmission Projects
Following planned projects will help removing all the constraints identified in the study.
Terrebone-Bayou Vista 230 kV transmission line (MTEP ID: 7988; ISD: 06/01/2018): This
project provides sufficient mitigation to bring the overloading to levels where further load
shedding is permissible by the applicable planning criteria and eliminate the need for Teche 3
SSR.
DRAFT 13
Hopkins (Cleco) Breaker Addition (MTEP ID: 10983; ISD: 05/01/2017): This project will
eliminate Category P4 contingencies resulting in constraints MORILSPLT to DUBOIN to
BAYOU_WHSE to IVANHOE4. This project need is not a requirement to avoid the Teche 3
SSR.
North ALP (MTEP ID: 12112; ISD: 12/1/2021), East ALP (MTEP ID: 12101; ISD: 06/01/2023):
These projects will help eliminate some of the constraints caused by Category P6 contingencies
in Appendix A table 1 for year 2021. This project need is not a requirement to avoid the Teche 3
SSR.
Segura (Cleco) Bus re-configuration (ISD: TBD): This project will eliminate Category P4
contingencies resulting in constraints MORIL to KIRK to CECILIA to BONIN 4 and MEAUX
to ABBEVILLE to LEBLANC. This project need is not a requirement to avoid the Teche 3
SSR. Cleco will submit this project in the next MTEP cycle.
DRAFT 14
VII. SSR AGREEMENT COST ALLOCATION
MISO conducted preliminary cost allocation analysis in accordance with the approved SSR Cost
Allocation Methodology. Costs for maintaining the SSR generation are allocated to LSE’s that
benefit from the operation of the SSR Unit. Analysis is performed to identify the loads that
contribute to constraints identified in the Attachment Y reliability study, and the associated
LSE’s are assigned a share of the cost responsibility based on their monthly peak energy
withdrawals. The method for cost allocation is filed with the associated SSR Agreement for
approval by FERC.
The methodology addresses the thermal and voltage related reliability issues that require the
continued operation of the SSR unit. Each of the unresolved constraints was evaluated to
determine the cost responsibility and allocation of the costs to the loads based on the calculation
of load distribution factors using linear power flow techniques. Voltage issues require additional
steps to analyzed the voltage constrained area and establish an appropriate proxy interface that
represents a constraint for the import of replacement power to the area of voltage decline.
The three (3) NERC Category P6 events identified in the reliability study were determined to
cause severe thermal overloads (>125) with a potential risk of cascading outages that result in
voltage collapse of the area. Cascading analysis indicated that following the contingent event,
the subsequent trip of the overloaded facility due to the excessive overloading causes further
cascading overloads and a decline of area voltages due to heavy import of power into the load
pocket. With the severity of the overloading and consequential risk of voltage instability
following the cascading trip, the cost allocation was based on the analysis of voltage constraints.
The affected area was determined by conducting voltage stability analysis and identifying
separation points in the transmission system to define the proxy interface. Load distribution
factors were calculated for the interface and mapped to the associated EPNodes defined in the
MISO Commercial Model.
The results of the preliminary SSR Cost allocation identifying the impacted EPNodes are
contained in Appendix C.
DRAFT 15
VIII. CONCLUSION
The results of Attachment Y reliability study for retirement of the Teche Unit 3 were assessed for
potential reliability impacts on the Transmission System and documented in this report.
Constraints were found in the models with the Teche Unit 3 offline. Some of the identified
overloads can be mitigated through existing generation re-dispatch and planned projects in
future. There are four (4) unresolved thermal violations on the Transmission System caused by
the retirement of Teche Unit 3.
After review of the power system reliability impacts as provided for under Section 38.2.7 of the
MISO’s Open Access Transmission, Energy & Operating Reserve Markets Tariff (“Tariff”),
MISO has determined that Teche Unit 3 will be required as an SSR unit until the completion of
the Terrebone-Bayou Vista project unless feasible alternative(s) are identified and implemented
prior to the retirement date.
MISO will initiate the open stakeholder process to review Attachment Y reliability study results
and previously identified solutions to avoid the need for an SSR agreement. If the open
stakeholder process determines that a feasible alternative solution can be implemented prior the
retirement date, Teche Unit 3 will not be designated as SSR unit.
DRAFT 16
IX. APPENDICES
Appendix A: Steady-State AC Contingency Results
Table 1 Thermal violations
Table 2 Voltage violations
Appendix B: SSR alternative analysis for Demand Response
Appendix C: SSR Cost allocation
Cleco Power LLC
Teche Unit #3: 335 MW, Gas
Attachment Y Study Report
Appendix A
AC Contingency Analysis Results
Table 1 Thermal Violations
Table 2 Voltage Violations
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 312.3 124 134.03 203.8 87 87.47 108.5 35.46
SSR Needed;Post re‐dispatch Overload >125 %. Terrebonne ‐
Bayou Vista 230 kV project is needed to reduce overloads below
125%
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 312.4 124 134.08 203.7 87 87.42 108.7 35.52
SSR Needed;Post re‐dispatch Overload >125 %. Terrebonne ‐
Bayou Vista 230 kV project is needed to reduce overloads below
125%
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 216 74.8 192.86 31.2 20.3 27.86 184.8 60.39
SSR Needed;Post re‐dispatch Overload >125 %. Terrebonne ‐
Bayou Vista 230 kV project is needed to reduce overloads below
125%
2017SP [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 191 54.2 131.72 46.4 34.9 32 144.6 47.25
SSR Needed;Post re‐dispatch Overload >125 %. Terrebonne ‐
Bayou Vista 230 kV project is needed to reduce overloads below
125%
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 193.9 57.4 173.12 41.2 29.4 36.79 152.7 49.9
SSR Needed;Post re‐dispatch Overload >125 %. Terrebonne ‐
Bayou Vista 230 kV project is needed to reduce overloads below
125%
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 162.1 95.6 111.79 116.6 76.2 80.41 45.5 14.87
Not SSR issue; Redispatch Morgan City 4 & Acadia, and load shed
of [REDACTED] MW
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 168.4 61 111.52 96.5 34.1 63.91 71.9 23.5
Not SSR issue; Redispatch Morgan City 4 & Acadia, and load shed
of [REDACTED] MW
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 309 116.4 128.22 304.6 98.5 126.39 4.4 1.44 Not SSR Issue; Teche 3 does not help in reducing the overload.
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 309 116.4 128.22 304.5 98.5 126.35 4.5 1.47 Not SSR Issue; Teche 3 does not help in reducing the overload.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 165.8 57.8 109.8 91 31.9 60.26 74.8 24.44
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 281.4 117.4 120.77 173.1 80.2 74.29 108.3 35.39
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 156.9 37 103.91 75.1 25.2 49.74 81.8 26.73
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 161.8 89.5 111.59 113.8 70.4 78.48 48 15.69
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
Page 1 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 161.6 89.5 111.45 114 70.4 78.62 47.6 15.56
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 165.2 57.8 109.4 90.6 31.9 60 74.6 24.38
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 156 37 103.31 74.4 25.2 49.27 81.6 26.67
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 279.8 117.4 120.09 172.3 80.2 73.95 107.5 35.13
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SH [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 205.7 69.8 183.66 22.4 15.1 20 183.3 59.9
Not SSR Issue;MISO Project 10983 ISD‐06/01/2017. N/A , Breaker
contingencies are typically not used for commitment and dispatch
in Day‐Ahead and Real‐time.
2017SH [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 177.9 47.8 122.69 41.5 31.8 28.62 136.4 44.58
Not SSR Issue;MISO Project 10983 ISD‐06/01/2017. N/A , Breaker
contingencies are typically not used for commitment and dispatch
in Day‐Ahead and Real‐time.
2017SH [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 183.2 51.7 163.57 35.4 25.5 31.61 147.8 48.3
Not SSR Issue;MISO Project 10983 ISD‐06/01/2017. N/A , Breaker
contingencies are typically not used for commitment and dispatch
in Day‐Ahead and Real‐time.
2017SH [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 188.9 47.9 102.11 136.9 33.3 74 52 16.99
Not SSR Issue;Turn Teche 4 to [REDACTED] MW, Morgan city to
[REDACTED] MW and reduce generation at Bonin 3 by the same.
2017SH [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 289.6 145.5 100.91 237.9 131.1 82.89 51.7 16.9
Not SSR Issue;Turn Teche 4 to [REDACTED] MW, Morgan city to
[REDACTED] MW and reduce generation at Bonin 3 by the same.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 249.7 106 103.61 197.2 85.1 81.83 52.5 17.16
Not SSR Issue;Turn Teche 4 to [REDACTED] MW, Morgan city to
[REDACTED] MW and reduce generation at Bonin 3 by the same.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 152.2 89.5 104.97 112.7 70.4 77.72 39.5 12.91
Not SSR Issue;Turn Teche 4 to [REDACTED] MW, Morgan city to
[REDACTED] MW and reduce generation at Bonin 3 by the same.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 252.5 106 104.77 246.2 85.1 102.16 6.3 2.06
Not SSR Issue;Reduce Bonin3 by [REDACTED] MW and shed
[REDACTED] MW load at ABBEVILLE.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 152.2 89.5 104.97 112.7 70.4 77.72 39.5 12.91
Not SSR Issue;Redispatch Teche4 to [REDACTED] MW Morgancity
to [REDACTED] MW and reduce Bonin 3 by the same.
Page 2 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SH [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 188.9 47.9 102.11 136.9 33.3 74 52 16.99
Not SSR Issue;Redispatch Teche4 to [REDACTED] MW Morgancity
to [REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 249.7 106 103.61 197.1 85.1 81.78 52.6 17.19
Not SSR Issue;Redispatch Teche4 to [REDACTED] MW Morgancity
to [REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 289.6 145.5 100.91 237.9 131.1 82.89 51.7 16.9
Not SSR Issue;Redispatch Teche4 to [REDACTED] MW Morgancity
to [REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303152 4SEMERE 138 1 130 147.8 56 113.69 103.9 39.8 79.92 43.9 14.35
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Cecelia, Parks and Loanfl2.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 152.2 89.5 104.97 112.7 70.4 77.72 39.5 12.91
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 188.9 47.9 102.11 136.9 33.3 74 52 16.99
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 249.7 106 103.61 197.1 85.1 81.78 52.6 17.19
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 289.6 145.5 100.91 237.9 131.1 82.89 51.7 16.9
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 174.5 57.8 115.56 98.2 31.9 65.03 76.3 24.93
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcrambre.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 168.1 37 111.32 82.7 25.2 54.77 85.4 27.91
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcrambre.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 292.5 117.4 125.54 183.2 80.2 78.63 109.3 35.72
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcrambre.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 167 89.5 115.17 119.3 70.4 82.28 47.7 15.59
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcrambre.
2017SH [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 253.5 84.5 101 145.6 48.7 58.01 107.9 35.26
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcrambre.
Page 3 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 161.8 89.5 111.59 113.8 70.4 78.48 48 15.69
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 and
Labbe1 to [REDACTED] MW, Morgan City to [REDACTED] MW;
Shed load at Abbeville.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 281.4 117.4 120.77 173.1 80.2 74.29 108.3 35.39
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 and
Labbe1 to [REDACTED] MW, Morgan City to [REDACTED] MW;
Shed load at Abbeville.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 156.9 37 103.91 75.1 25.2 49.74 81.8 26.73
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 and
Labbe1 to [REDACTED] MW, Morgan City to [REDACTED] MW;
Shed load at Abbeville.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 165.8 57.8 109.8 91 31.9 60.26 74.8 24.44
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 and
Labbe1 to [REDACTED] MW, Morgan City to [REDACTED] MW;
Shed load at Abbeville.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303152 4SEMERE 138 1 130 147.9 56 113.77 104 39.8 80 43.9 14.35
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Cecelia, Parks and Longfl2.
2017SH [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 253.4 84.5 100.96 145.5 48.7 57.97 107.9 35.26
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcamgre.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 292.3 117.4 125.45 183.2 80.2 78.63 109.1 35.65
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcamgre.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 167.1 89.5 115.24 119.3 70.4 82.28 47.8 15.62
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcamgre.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 168.1 37 111.32 82.8 25.2 54.83 85.3 27.88
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcamgre.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 174.5 57.8 115.56 98.2 31.9 65.03 76.3 24.93
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Morgan City to [REDACTED] MW; Shed load at
Abbeville and Delcamgre.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 165.8 57.8 109.8 91.1 31.9 60.33 74.7 24.41
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MWat Abbeville.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 281.2 117.4 120.69 173 80.2 74.25 108.2 35.36
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MWat Abbeville.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 161.9 89.5 111.66 113.8 70.4 78.48 48.1 15.72
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load at Abbeville.
Page 4 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 156.9 37 103.91 75.2 25.2 49.8 81.7 26.7
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MW at Abbeville.
2017SH [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 171.8 47.8 118.48 46.1 31.8 31.79 125.7 41.08
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Hargis 1 and
2 to [REDACTED] MW, Bonin 2 and 3 to [REDACTED] MW, and
Morgan city to [REDACTED] MW; Shed load of [REDACTED] MW at
Duboin, Bayou Whesel, Ivanhoe, and Julien.
2017SH [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 176.8 51.7 157.86 39.3 25.5 35.09 137.5 44.93
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Hargis 1 and
2 to [REDACTED] MW, Bonin 2 and 3 to [REDACTED] MW, and
Morgan city to [REDACTED] MW; Shed load of [REDACTED] MW at
Duboin, Bayou Whesel, Ivanhoe, and Julien.
2017SH [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 199.1 69.8 177.77 21.7 15.1 19.38 177.4 57.97
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Hargis 1 and
2 to [REDACTED] MW, Bonin 2 and 3 to [REDACTED] MW, and
Morgan city to [REDACTED] MW; Shed load of [REDACTED] MW at
Duboin, Bayou Whesel, Ivanhoe, and Julien.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 156.5 57.8 103.64 85.2 31.9 56.42 71.3 23.3
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Acadia 1 to
[REDACTED] MW, and Morgan city to [REDACTED] MW; Shed load
of [REDACTED] MW at Delcambre, texas_erath, Jungle gard,
internatial, new iberia, billeaud, St Martin, longfl2.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 150.3 89.5 103.66 105.2 70.4 72.55 45.1 14.74
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Acadia 1 to
[REDACTED] MW, and Morgan city to [REDACTED] MW; Shed load
of [REDACTED] MW at Delcambre, texas_erath, Jungle gard,
internatial, new iberia, billeaud, St Martin, longfl2.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 156.6 57.8 103.71 85.2 31.9 56.42 71.4 23.33
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Acadia 1 to
[REDACTED] MW, and Morgan city to [REDACTED] MW; Shed load
of [REDACTED] MW at Delcambre, texas_erath, Jungle gard,
internatial, new iberia, billeaud, St Martin, longfl2.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 150.3 89.5 103.66 105.2 70.4 72.55 45.1 14.74
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Acadia 1 to
[REDACTED] MW, and Morgan city to [REDACTED] MW; Shed load
of [REDACTED] MW at Delcambre, texas_erath, Jungle gard,
internatial, new iberia, billeaud, St Martin, longfl2.
2017SH [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 279.8 117.4 120.09 172.3 80.2 73.95 107.5 35.13
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MW at Abbeville.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 156 37 103.31 74.4 25.2 49.27 81.6 26.67
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MWat Abbeville.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 161.6 89.5 111.45 114 70.4 78.62 47.6 15.56
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MW at Abbeville.
2017SH [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 165.2 57.8 109.4 90.6 31.9 60 74.6 24.38
Not SSR Issue;Redispatch Tech 4 to [REDACTED] MW, Bonin 3 to
[REDACTED] MW, Labbe 1 to [REDACTED] MW and Morgan city to
[REDACTED] MW; Shed load of [REDACTED] MW at Abbeville.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 152.2 89.5 104.97 112.7 70.4 77.72 39.5 12.91 Not SSR Issue; Shed [REDACTED] MW at Leblanc 138kV.
Page 5 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 249.7 106 103.61 197.2 85.1 81.83 52.5 17.16 Not SSR Issue; Shed [REDACTED] MW at Leblanc 138kV.
2017SH [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 289.6 145.5 100.91 237.9 131.1 82.89 51.7 16.9
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 188.8 47.9 102.05 136.9 33.3 74 51.9 16.96
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 252.5 106 104.77 246.2 85.1 102.16 6.3 2.06
Not SSR Issue;Decrease Bonin 3 by [REDACTED] MW and shed load
at Abbeville by the same.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 161.6 89.5 111.45 123.6 70.4 85.24 38 12.42
Not SSR Issue;Turn on Teche 4 to [REDACTED] MW; Morgan city to
[REDACTED] MW and reduce Bonin 3 by the same.
2017SH [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 146.6 89.5 101.1 110.1 70.4 75.93 36.5 11.93 Not SSR Issue; Shed [REDACTED] MW at Leblanc 138kV.
2017SH [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 262.1 106 108.76 197.6 85.1 81.99 64.5 21.08 Not SSR Issue; Shed [REDACTED] MW at Leblanc 138kV.
2017SH [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 202 47.9 109.19 136.6 33.3 73.84 65.4 21.37
Not SSR Issue;Turn on Morgan City Unit 4 to [REDACTED] MW and
reduce Coughlin unit 6 by same amount. Shed [REDACTED] MW
load at Leblanc 138kV, [REDACTED] MW at Morilsplit and
[REDACTED]MW at Delcambre 138kV to remove violation. .
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 167.2 39.6 110.73 85.8 27.5 56.82 81.4 26.6
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 296.5 124 127.25 193.6 87 83.09 102.9 33.63
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 262.4 91.7 104.54 156.8 56.5 62.47 105.6 34.51
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 174.3 95.6 120.21 126.6 76.2 87.31 47.7 15.59
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 177.1 61 117.28 102.4 34.1 67.81 74.7 24.41
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
Page 6 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 300.5 124 128.97 192.7 87 82.7 107.8 35.23
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 262.5 91.7 104.58 156 56.5 62.15 106.5 34.8
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 178.3 61 118.08 102 34.1 67.55 76.3 24.93
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 173.7 95.6 119.79 123.3 76.2 85.03 50.4 16.47
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 170.5 39.6 112.91 85 27.5 56.29 85.5 27.94
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 223.7 74.8 199.73 34.2 20.3 30.54 189.5 61.93
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. MISO
Project 10983‐ ISD 06/01/2017 mitigates the issue.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 201.1 57.4 179.55 38.6 29.4 34.46 162.5 53.1
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. MISO
Project 10983‐ ISD 06/01/2017 mitigates the issue.
2017SP [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 197.8 54.2 136.41 42.6 34.9 29.38 155.2 50.72
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. MISO
Project 10983‐ ISD 06/01/2017 mitigates the issue.
2017SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 201.2 48 108.76 149.1 33.1 80.59 52.1 17.03
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Load shed of
[REDACTED] MW at Leroy, Delcambre, Duboin, Cecelia, Moril,
Hopkins 138 kV mitigates the violations.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.4 111.8 111.37 216 91.4 89.63 52.4 17.12
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Load shed of
[REDACTED] MW at Leroy, Delcambre, Duboin, Cecelia, Moril,
Hopkins 138 kV mitigates the violations.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 312.7 155.1 108.95 260.4 139.7 90.73 52.3 17.09
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Load shed of
[REDACTED] MW at Leroy, Delcambre, Duboin, Cecelia, Moril,
Hopkins 138 kV mitigates the violations.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 163.8 95.6 112.97 124.3 76.2 85.72 39.5 12.91
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Load shed of
[REDACTED] MW at Leroy, Delcambre, Duboin, Cecelia, Moril,
Hopkins 138 kV mitigates the violations.
2017SP [REDACTED] 335413 4YOUNGSVIL% 138 ‐ 500330 FLANDR 4 138 1 289 290.6 132.5 100.55 192.7 84.6 66.68 97.9 31.99
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville,Cecelia, Moril,
Hopkins 138 kV.
Page 7 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335388 4MORIL! 138 ‐ 500774 SEGURA4 138 1 458 486.4 231 106.2 323.6 181.4 70.66 162.8 53.2
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Delcambre.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 275.7 111.8 114.4 269.1 91.4 111.66 6.6 2.16
Not SSR Issue; Shed [REDACTED] MW of load at Leroy, Abbeville &
Leblanc to mitigate the violations.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 314.6 155.1 109.62 282.2 139.7 98.33 32.4 10.59
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW and Morgan city to [REDACTED]
MW; Shed load of [REDACTED] MW at Scott.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 167.3 74.8 149.38 37.6 20.3 33.57 129.7 42.39
Not SSR Issue;Redispatch Bonin 2 to [REDACTED] MW, Houma 3 to
[REDACTED] MW and Morgan city to [REDACTED] MW; Shed load
of [REDACTED] MWat Duboin and Bayou whse.
2017SP [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 149.3 54.2 102.97 74.9 34.9 51.66 74.4 24.31
Not SSR Issue;Redispatch Bonin 2 to [REDACTED] MW, Houma 3 to
[REDACTED] MW and Morgan city to [REDACTED] MW; Shed load
of [REDACTED] MWat Duboin and Bayou whse.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 150.1 57.4 134.02 66.1 29.4 59.02 84 27.45
Not SSR Issue;Redispatch Bonin 2 to [REDACTED] MW, Houma 3 to
[REDACTED] MW and Morgan city to [REDACTED] MW; Shed load
at Duboin and Bayou whse.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 170.9 74.8 152.59 34.8 20.3 31.07 136.1 44.48
Not SSR Issue;Redispatch Morgancity 4 & Acadia. Shed
[REDACTED] MW of load at Duboin, Bayou Warehouse 138 kV
substations.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 153.4 57.4 136.96 63.2 29.4 56.43 90.2 29.48
Not SSR Issue;Redispatch Morgancity 4 & Acadia. Shed
[REDACTED] MW of load at Duboin, Bayou Warehouse 138 kV
substations.
2017SP [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 152.5 54.2 105.17 71.9 34.9 49.59 80.6 26.34
Not SSR Issue;Redispatch Morgancity 4 & Acadia. Shed
[REDACTED] MW of load at Duboin, Bayou Warehouse 138 kV
substations.
2017SP [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 188 54.2 129.66 47.2 34.9 32.55 140.8 46.01
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, and Bayou whse.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 190.7 57.4 170.27 41.5 29.4 37.05 149.2 48.76
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, and Bayou whse.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 212.4 74.8 189.64 28.8 20.3 25.71 183.6 60
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, and Bayou whse.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 163.8 95.6 112.97 124.3 76.2 85.72 39.5 12.91
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville,Cecelia, Moril,
Hopkins 138 kV.
Page 8 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335413 4YOUNGSVIL% 138 ‐ 500330 FLANDR 4 138 1 289 290.7 132.5 100.59 192.7 84.6 66.68 98 32.03
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville,Cecelia, Moril,
Hopkins 138 kV.
2017SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 201.2 48 108.76 149.1 33.1 80.59 52.1 17.03
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville,Cecelia, Moril,
Hopkins 138 kV.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 312.6 155.1 108.92 260.4 139.7 90.73 52.2 17.06
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville,Cecelia, Moril,
Hopkins 138 kV.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.4 111.8 111.37 216 91.4 89.63 52.4 17.12
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville,Cecelia, Moril,
Hopkins 138 kV.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303152 4SEMERE 138 1 130 158.8 60.3 122.15 114.9 44.4 88.38 43.9 14.35
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 233.4 124 100.17 158.5 87 68.03 74.9 24.48
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 257.9 124 110.69 177.6 87 76.22 80.3 26.24
Not SSR Issue;Redispatch Bonin 3 to [REDACTED] MW, Labbe 1 to
[REDACTED] MW and Morgan city to [REDACTED] MW; Shed load
at Abbeville.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 151.3 95.6 104.34 113.3 76.2 78.14 38 12.42
Not SSR Issue;Redispatch Bonin 3 to [REDACTED] MW, Labbe 1 to
[REDACTED] MW and Morgan city to [REDACTED] MW; Shed load
at Abbeville.
2017SP [REDACTED] 335413 4YOUNGSVIL% 138 ‐ 500330 FLANDR 4 138 1 289 290.7 132.5 100.59 192.7 84.6 66.68 98 32.03
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville,
Cecelia 138 kV substations.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.4 111.8 111.37 216 91.4 89.63 52.4 17.12
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville,
Cecelia 138 kV substations.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 163.8 95.6 112.97 124.3 76.2 85.72 39.5 12.91
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville,
Cecelia 138 kV substations.
2017SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 201.2 48 108.76 149.1 33.1 80.59 52.1 17.03
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville,
Cecelia 138 kV substations.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 312.6 155.1 108.92 260.4 139.7 90.73 52.2 17.06
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville,
Cecelia 138 kV substations.
Page 9 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 250.4 124 107.47 164.3 87 70.52 86.1 28.14
Not SSR Issue;redispatch Bonin 3 to [REDACTED] MW and Morgan
city to [REDACTED] MW; Shed load at Abbeville and holiday.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 246.6 124 105.84 157.1 87 67.42 89.5 29.25
Not SSR Issue;Redispatch Acadia 1 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Abbeville.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 186.6 61 123.58 109.6 34.1 72.58 77 25.16
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW, Labbe
1 to [REDACTED] MW, and Morgan city to [REDACTED] MW; Shed
load at Abbeville, Delcambre, Moril split, Texas_erath, Youngsvil,
and Hopkins.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 180.2 39.6 119.34 93.5 27.5 61.92 86.7 28.33
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW, Labbe
1 to [REDACTED] MW, and Morgan city to [REDACTED] MW; Shed
load at Abbeville, Delcambre, Moril split, Texas_erath, Youngsvil,
and Hopkins.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 179.2 95.6 123.59 128.4 76.2 88.55 50.8 16.6
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW, Labbe
1 to [REDACTED] MW, and Morgan city to [REDACTED] MW; Shed
load at Abbeville, Delcambre, Moril split, Texas_erath, Youngsvil,
and Hopkins.
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 274.1 91.7 109.2 166.7 56.5 66.41 107.4 35.1
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW, Labbe
1 to [REDACTED] MW, and Morgan city to [REDACTED] MW; Shed
load at Abbeville, Delcambre, Moril split, Texas_erath, Youngsvil,
and Hopkins.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 167.2 39.6 110.73 85.8 27.5 56.82 81.4 26.6
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 177.1 61 117.28 102.4 34.1 67.81 74.7 24.41
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 296.5 124 127.25 193.6 87 83.09 102.9 33.63
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Load Shed of
[REDACTED] MW at Leblanc, Abbeville, Duboin, Cecelia, Hopkins
138 kV. N/A ‐ Mitigation is acceptable
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 262.4 91.7 104.54 156.8 56.5 62.47 105.6 34.51
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 174.3 95.6 120.21 126.6 76.2 87.31 47.7 15.59
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303152 4SEMERE 138 1 130 158.9 60.3 122.23 115 44.4 88.46 43.9 14.35
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 233.4 124 100.17 158.5 87 68.03 74.9 24.48
Not SSR Issue; Redispatch Morgan City 4 & Acadia generation.
Shed [REDACTED] MW of load at Semere, Cecelia 138 kV.
Page 10 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 257.5 124 110.52 177.6 87 76.22 79.9 26.11
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 151.4 95.6 104.41 113.3 76.2 78.14 38.1 12.45
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 246.5 124 105.79 157.1 87 67.42 89.4 29.22
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 186.8 61 123.71 109.7 34.1 72.65 77.1 25.2
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 180.1 39.6 119.27 93.5 27.5 61.92 86.6 28.3
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 274.1 91.7 109.2 166.6 56.5 66.37 107.5 35.13
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 179.4 95.6 123.72 128.5 76.2 88.62 50.9 16.63
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 171.7 39.6 113.71 85.8 27.5 56.82 85.9 28.07
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 179.5 61 118.87 102.4 34.1 67.81 77.1 25.2
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 174 95.6 120 126.6 76.2 87.31 47.4 15.49
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 264.1 91.7 105.22 156.7 56.5 62.43 107.4 35.1
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Hargis 1 to [REDACTED] MW, Houma 3 to [REDACTED] MW and
Morgan city to [REDACTED] MW; Shed load at Duboin, Ivanhoe 4,
Julien 4, Morbhan, Teche 1, New Iberia, 2billeaud, dixe, 2parks, St
martin and Bayou whse.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 302.1 124 129.66 193.5 87 83.05 108.6 35.49
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Leblanc, Abbeville, Duboin,Cecelia,
Moril 138 kV. N/A ‐ Mitigation is acceptable
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 149.1 95.6 102.83 111.1 76.2 76.62 38 12.42 Not SSR Issue;Redispatch Morgan City 4 & Acadia.
Page 11 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 252.7 124 108.45 172.2 87 73.91 80.5 26.31
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Cecelia & Abbeville 138 kV.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 148.7 95.6 102.55 111.1 76.2 76.62 37.6 12.29
Not SSR Issue;Redispatch Acadia 1 to [REDACTED] MW, Labbe 1 to
[REDACTED] MW, Morgan city4 to [REDACTED] MW, and Bonin 3
to [REDACTED] MW; Shed load at Abbeville.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 252.2 124 108.24 172.2 87 73.91 80 26.14
Not SSR Issue;Redispatch Acadia 1 to [REDACTED] MW, Labbe 1 to
[REDACTED] MW, Morgan city4 to [REDACTED] MW, and Bonin 3
to [REDACTED] MW; Shed load at Abbeville.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 246.6 124 105.84 162.8 87 69.87 83.8 27.39
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Abbeville & Cecelia.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 150.8 95.6 104 109.1 76.2 75.24 41.7 13.63
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Abbeville & Cecelia.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 150.7 95.6 103.93 109.2 76.2 75.31 41.5 13.56
Not SSR Issue;Rediaptch Labbe 1 to [REDACTED] MW, Morgan
city4 to [REDACTED] MW, and Bonin 3 to [REDACTED] MW; Shed
load at Abbeville.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 246.4 124 105.75 162.7 87 69.83 83.7 27.35
Not SSR Issue;Rediaptch Labbe 1 to [REDACTED] MW, Morgan
city4 to [REDACTED] MW, and Bonin 3 to [REDACTED] MW; Shed
load at Abbeville.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 116.5 57.4 104.02 33.5 29.4 29.91 83 27.12
Not SSR Issue;Rediaptch Morgan city4 to [REDACTED] MW, and
Bonin 3 to [REDACTED] MW; Shed load at Duboin.
2017SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 136.6 74.8 121.96 31.3 20.3 27.95 105.3 34.41
Not SSR Issue;Rediaptch Morgan city4 to [REDACTED] MW, and
Bonin 3 to [REDACTED] MW; Shed load at Duboin.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 252.2 124 108.24 152.7 87 65.54 99.5 32.52
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Morgan city
4 to [REDACTED] MW; Shed load at Abbeville.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 147.6 95.6 101.79 102.5 76.2 70.69 45.1 14.74
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Morgan city
4 to [REDACTED] MW; Shed load at Abbeville.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 158.7 39.6 105.1 79.5 27.5 52.65 79.2 25.88
Not SSR Issue; Redispatch Morgan City 4 & Acadia and load shed
of [REDACTED] MW at Holiday , [REDACTED] MW at Cecelia.
2017SP [REDACTED] 335413 4YOUNGSVIL% 138 ‐ 500330 FLANDR 4 138 1 289 304.7 132.5 105.43 189.5 84.6 65.57 115.2 37.65
Not SSR Issue;Redispatch Morgan City 4 & Acadia and load shed of
[REDACTED] MW at Holiday , [REDACTED] MW at Cecelia.
Page 12 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335413 4YOUNGSVIL% 138 ‐ 500330 FLANDR 4 138 1 289 304.7 132.5 105.43 189.5 84.6 65.57 115.2 37.65
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Morgan city
4 to [REDACTED] MW; Shed load at Delcambre, Duboin, Moril
Split, Texas Erath, Jungle gard, Internatial, New Iberia, Billeaud, St
Martin, Hopkins4 and Longfl 2.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 162.2 95.6 111.86 116.6 76.2 80.41 45.6 14.9
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Morgan city
4 to [REDACTED] MW; Shed load at Delcambre, Duboin, Moril
Split, Texas Erath, Jungle gard, Internatial, New Iberia, Billeaud, St
Martin, Hopkins4 and Longfl 2.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 158.7 39.6 105.1 79.5 27.5 52.65 79.2 25.88
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Morgan city
4 to [REDACTED] MW; Shed load at Delcambre, Duboin, Moril
Split, Texas Erath, Jungle gard, Internatial, New Iberia, Billeaud, St
Martin, Hopkins4 and Longfl 2.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 168.4 61 111.52 96.5 34.1 63.91 71.9 23.5
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Morgan city
4 to [REDACTED] MW; Shed load at Delcambre, Duboin, Moril
Split, Texas Erath, Jungle gard, Internatial, New Iberia, Billeaud, St
Martin, Hopkins4 and Longfl 2.
2017SP [REDACTED] 500410 HOPKINS4 138 ‐ 500774 SEGURA4 138 1 382 446.6 184.8 116.91 290.1 85.9 75.94 156.5 51.14
Not SSR Issue;Rediaptch Acadia 1 to [REDACTED] MW, Labbe 1 to
[REDACTED] MW, Morgan city4 to [REDACTED] MW; Shed load at
Hopkins.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 300.5 124 128.97 192.7 87 82.7 107.8 35.23
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 173.7 95.6 119.79 123.3 76.2 85.03 50.4 16.47
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 178.3 61 118.08 102 34.1 67.55 76.3 24.93
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335386 4ABBEVILLE 138 ‐ 303150 4LEBLANC! 138 1 251 262.5 91.7 104.58 156 56.5 62.15 106.5 34.8
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 335384 4KIRK! 138 ‐ 335388 4MORIL! 138 1 151 170.5 39.6 112.91 85 27.5 56.29 85.5 27.94
Not SSR Issue;Redispatch Bonin 2 and 3 to [REDACTED] MW,
Houma 3 to [REDACTED] MW, and Morgan city to [REDACTED]
MW; Shed load at Abbeville, Delcambre, Moril split, Texas_erath,
and Hopkins.
2017SP [REDACTED] 500410 HOPKINS4 138 ‐ 500774 SEGURA4 138 1 382 436.7 184.8 114.32 262.5 85.9 68.72 174.2 56.93
Not SSR Issue;Redispatch Acadia 1 to [REDACTED] MW, Morgan
city4 to [REDACTED] MW and Labee1 to [REDACTED] MW; Shed
load at Hopkins4.
2017SP [REDACTED] 500410 HOPKINS4 138 ‐ 500774 SEGURA4 138 1 382 446.5 184.8 116.88 290.1 85.9 75.94 156.4 51.11
Not SSR Issue;Redispatch Acadia 1 to [REDACTED] MW, Morgan
city4 to [REDACTED] MW and Labee1 to [REDACTED] MW; Shed
load at Hopkins4.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.5 111.8 111.41 216 91.4 89.63 52.5 17.16
Not SSR Issue;Shed [REDACTED] MW load at Cecilia, Moril, Duboin,
Leroy, Abbeville 138 kV stations. Increase Morgan City 4 &
Decrease Acadia generation.
Page 13 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 163.8 95.6 112.97 124.3 76.2 85.72 39.5 12.91
Not SSR Issue;Shed [REDACTED] MW load at Cecilia, Moril, Duboin,
Leroy, Abbeville 138 kV stations. Increase Morgan City 4 &
Decrease Acadia generation.
2017SP [REDACTED] 335413 4YOUNGSVIL% 138 ‐ 500330 FLANDR 4 138 1 289 290.6 132.5 100.55 192.7 84.6 66.68 97.9 31.99
Not SSR Issue;Shed [REDACTED] MW load at Cecilia, Moril, Duboin,
Leroy, Abbeville 138 kV stations. Increase Morgan City 4 &
Decrease Acadia generation.
2017SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 201.2 48 108.76 149.1 33.1 80.59 52.1 17.03
Not SSR Issue;Shed [REDACTED] MW load at Cecilia, Moril, Duboin,
Leroy, Abbeville 138 kV stations. Increase Morgan City 4 &
Decrease Acadia generation.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 312.7 155.1 108.95 260.4 139.7 90.73 52.3 17.09
Not SSR Issue;Shed [REDACTED] MW load at Cecilia, Moril, Duboin,
Leroy, Abbeville 138 kV stations. Increase Morgan City 4 &
Decrease Acadia generation.
2017SP [REDACTED] 335388 4MORIL! 138 ‐ 500774 SEGURA4 138 1 458 486.3 231 106.18 323.6 181.4 70.66 162.7 53.17
Not SSR Issue;Shed [REDACTED] MW load at Hopkins 138 kV &
[REDACTED] MW load at Moril 138 kV.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 275.8 111.8 114.44 269.1 91.4 111.66 6.7 2.19
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Judice, Leroy, Abbeville 138 kV.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 314.5 155.1 109.58 282.2 139.7 98.33 32.3 10.56
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Load shed of
[REDACTED] MW at Judice.
2017SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 250.3 124 107.42 164.2 87 70.47 86.1 28.14
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Holiday & Abbeville.
2017SP [REDACTED] 335060 4CARLYSS! 138 ‐ 335070 6CARLYSS% 230 1 243 274.9 125.9 113.13 261.2 124.6 107.49 13.7 4.48
Not SSR Issue;Shed [REDACTED] MW of load at Citgo 138 kV,
Arizona 138 kV, Certainteed 138 kV, Citcon 138 kV.
2017SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 281.6 111.8 116.85 215.4 91.4 89.38 66.2 21.63
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville 138
kV substations.
2017SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 306.8 155.1 106.9 248.2 139.7 86.48 58.6 19.15
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville 138
kV substations.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 157.4 95.6 108.55 121 76.2 83.45 36.4 11.9
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville 138
kV substations.
2017SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 215.1 48 116.27 149.7 33.1 80.92 65.4 21.37
Not SSR Issue;Redispatch Acadia & Morgan City 4 generation.Shed
[REDACTED] MW of load at Judice, Leblanc, Leroy, Abbeville 138
kV substations.
Page 14 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 155 95.6 106.9 108.5 76.2 74.83 46.5 15.2 Not SSR Issue;Redispatch Morgan City 4 & Acadia.
2017SP [REDACTED] 335391 4CECELIA! 138 ‐ 502404 BONIN 4 138 1 145 154.9 95.6 106.83 108.5 76.2 74.83 46.4 15.16
Not SSR Issue;Redispatch Morgan City 4 & Acadia. Shed
[REDACTED] MW of load at Cecelia 138 kV.
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 263.7 119.9 113.18 183 88.7 78.54 80.7 26.37
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 262.1 119.9 112.49 182.2 88.7 78.2 79.9 26.11
Not SSR Issue, Breaker contingencies are typically not used for
commitment and dispatch in Day‐Ahead and Real‐time. Cleco to
reconfigure line position at Segura.
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.9 116.4 111.58 227.4 98.5 94.36 41.5 13.56 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 190.9 41.5 103.19 149.8 28.6 80.97 41.1 13.43 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 314.4 162 109.55 273 147.4 95.12 41.4 13.53 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 325.6 162 113.45 298.3 147.4 103.94 27.3 8.92
Not SSR Issue;Shed [REDACTED] MW load at SEMERE and
[REDACTED] MW load at JUDICE.
2021SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 128.5 55.4 114.73 28.1 15.4 25.09 100.4 32.81
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Shed [REDACTED] MW load at DUBOIN.
2021SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 190.9 41.5 103.19 149.8 28.6 80.97 41.1 13.43 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 314.5 162 109.58 272.9 147.4 95.09 41.6 13.59 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.9 116.4 111.58 227.4 98.5 94.36 41.5 13.56 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303152 4SEMERE 138 1 130 153.9 60.3 118.38 117.9 46.8 90.69 36 11.76
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at 4SEMERE .
Page 15 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 238.3 119.9 102.27 174.3 88.7 74.81 64 20.92
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins.
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 314.5 162 109.58 272.9 147.4 95.09 41.6 13.59 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 190.9 41.5 103.19 149.8 28.6 80.97 41.1 13.43 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.9 116.4 111.58 227.4 98.5 94.36 41.5 13.56 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 274.2 119.9 117.68 193.8 88.7 83.18 80.4 26.27
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 156.1 51.4 103.38 97.2 29.6 64.37 58.9 19.25
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 263.7 119.9 113.18 183 88.7 78.54 80.7 26.37
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303152 4SEMERE 138 1 130 154 60.3 118.46 117.9 46.8 90.69 36.1 11.8
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335384 4KIRK! 138 ‐ 335391 4CECELIA! 138 1 151 156.1 51.4 103.38 97.2 29.6 64.37 58.9 19.25
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 274.1 119.9 117.64 193.7 88.7 83.13 80.4 26.27
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 263.6 119.9 113.13 183 88.7 78.54 80.6 26.34
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins
and [REDACTED] MW load at Youngsville .
2021SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 112.7 39 100.63 55.4 36 49.46 57.3 18.73
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Shed [REDACTED] MW load at DUBOIN.
2021SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 131.5 55.4 117.41 27.1 15.4 24.2 104.4 34.12
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Shed [REDACTED] MW load at DUBOIN.
Page 16 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 238.2 119.9 102.23 174.3 88.7 74.81 63.9 20.88
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed 30 MW load at Hopkins.
2021SP [REDACTED] 500410 HOPKINS4 138 ‐ 500774 SEGURA4 138 1 382 415.8 149.9 108.85 285 73.5 74.61 130.8 42.75
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed 60 MW load at Hopkins .
2021SP [REDACTED] 335380 4MEAUX! 138 ‐ 335386 4ABBEVILLE 138 1 233 262.1 119.9 112.49 182.2 88.7 78.2 79.9 26.11
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Load shed [REDACTED] MW load at Hopkins .
2021SP [REDACTED] 500410 HOPKINS4 138 ‐ 500774 SEGURA4 138 1 382 415.7 149.9 108.82 284.9 73.5 74.58 130.8 42.75
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Shed [REDACTED] MW load at Hopkins .
2021SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 190.9 41.5 103.19 149.8 28.6 80.97 41.1 13.43 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 314.3 162 109.51 273 147.4 95.12 41.3 13.5 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 268.9 116.4 111.58 227.4 98.5 94.36 41.5 13.56 Not SSR Issue; [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 325.6 162 113.45 298.3 147.4 103.94 27.3 8.92
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. Shed [REDACTED] MW load at Judice.
2021SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335394 4MORILSPLT! 138 1 112 183.7 55.4 164.02 52.9 15.4 47.23 130.8 42.75
Not SSR Issue; Turn on Morgan City U4 to [REDACTED] MW, Turn
on Houma to [REDACTED] MW. Reduce Panda by [REDACTED]
MW. Load Shed of [REDACTED] MW.
2021SP [REDACTED] 335390 4BAYOU_WHSE!138 ‐ 500440 IVANHOE4 138 1 145 151.3 37.2 104.34 50.9 43.5 35.1 100.4 32.81
Not SSR Issue;Turn on Morgan City U4 to [REDACTED] MW, Turn
on Houma to [REDACTED] MW. Reduce Panda by [REDACTED]
MW.
2021SP [REDACTED] 335389 4DUBOIN! 138 ‐ 335390 4BAYOU_WHSE!138 1 112 157.4 39 140.54 48.9 36 43.66 108.5 35.46
Not SSR Issue;Turn on Morgan City U4 to [REDACTED] MW, Turn
on Houma to [REDACTED] MW. Reduce Panda by [REDACTED]
MW.
2021SP [REDACTED] 335378 4SCOTT_2! 138 ‐ 335379 4SCOTT_1! 138 Z1 287 300.8 162 104.81 255.2 147.4 88.92 45.6 14.9
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 335383 4MEAUXSPLT! 138 ‐ 303132 4JUDICE! 138 1 185 196 41.5 105.95 145 28.6 78.38 51 16.67
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. [REDACTED] MW Load Shed at Leblanc .
Page 17 of 20
Appendix A, Table 1 ‐ Thermal Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Thermal Violations
Redacted
Contingency
Year Load Contingency Description ** From bus ** ** To bus ** CKT Rating MVA ContMW BaseFlow Loading% ContMW BaseFlow Loading%
MW_Off‐
MW_On
PTDF
(>5 %)
OTDF (>3
%) Comments
Limiting Element Teche 3 OFF Teche 3 ON Unit Impact
2021SP [REDACTED] 335379 4SCOTT_1! 138 ‐ 303132 4JUDICE! 138 1 241 273.5 116.4 113.49 221.3 98.5 91.83 52.2 17.06
Not SSR Issue;Turn on Houma to [REDACTED] MW. Turn on
Morgan City U4 to [REDACTED] MW. Reduce Panda by
[REDACTED] MW. [REDACTED] MW Load Shed at Leblanc .
2021SP [REDACTED] 336042 6RACLND! 230 ‐ 336154 6WATFRD% 230 1 535 635.8 390.4 118.84 569.3 349.5 106.41 66.5 21.73
Not SSR Issue;Turn on Morgan City U4 to [REDACTED] MW, Turn
on Houma to [REDACTED] MW. Reduce Panda by [REDACTED]
MW. Load shed [REDACTED] MW at 6RACLND, [REDACTED] MW at
3RACLND, [REDACTED] MW AT 6LANDRY.
Page 18 of 20
Appendix A, Table 2 ‐ Voltage Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Voltage Violations
Redacted
Unit Impact
Year Load Contingency Description Bus Number Bus Name Area Low Limit High Limit Cont. Volt Base Volt Cont. Volt Base Volt
Voff‐Von (< ‐
1%) Comments
2021SP [REDACTED] 335380 4MEAUX! 138.00 351 0.92 1.05 0.8753 0.9826 0.8995 0.9914 ‐2.42 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335385 4LEROY 138.00 351 0.92 1.05 0.8718 0.9795 0.8962 0.9883 ‐2.44 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 303150 4LEBLANC! 138.00 332 0.92 1.05 0.9028 0.9645 0.9316 0.9784 ‐2.88 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335386 4ABBEVILLE 138.00 351 0.92 1.05 0.8894 0.975 0.9161 0.9866 ‐2.67 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 303132 4JUDICE! 138.00 332 0.92 1.05 0.8588 0.9801 0.8836 0.9856 ‐2.48 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335395 4CONRAD 138.00 351 0.92 1.05 0.9029 0.9645 0.9317 0.9784 ‐2.88 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335383 4MEAUXSPLT! 138.00 351 0.92 1.05 0.8753 0.9826 0.8995 0.9914 ‐2.42 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335387 4DELCAMBRE 138.00 351 0.92 1.05 0.9102 0.9669 0.9393 0.9812 ‐2.91 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 303132 4JUDICE! 138.00 332 0.92 1.05 0.8583 0.9801 0.8835 0.9856 ‐2.52 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335395 4CONRAD 138.00 351 0.92 1.05 0.9025 0.9645 0.9316 0.9784 ‐2.91 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335386 4ABBEVILLE 138.00 351 0.92 1.05 0.8889 0.975 0.9159 0.9866 ‐2.7 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335383 4MEAUXSPLT! 138.00 351 0.92 1.05 0.8748 0.9826 0.8994 0.9914 ‐2.46 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335385 4LEROY 138.00 351 0.92 1.05 0.8713 0.9795 0.8961 0.9883 ‐2.48 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335387 4DELCAMBRE 138.00 351 0.92 1.05 0.9097 0.9669 0.9392 0.9812 ‐2.95 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335381 6MEAUX! 230.00 351 0.92 1.05 0.8748 0.988 0.8994 0.9961 ‐2.46 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 303150 4LEBLANC! 138.00 332 0.92 1.05 0.9023 0.9645 0.9315 0.9784 ‐2.92 Shed [REDACTED] Load at Judice
2021SP [REDACTED] 335380 4MEAUX! 138.00 351 0.92 1.05 0.8748 0.9826 0.8994 0.9914 ‐2.46 Shed [REDACTED] Load at Judice
2017SH [REDACTED] 303132 4JUDICE! 138.00 332 0.92 1.05 0.9047 0.9888 0.9289 0.9961 ‐2.42
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335383 4MEAUXSPLT! 138.00 351 0.92 1.05 0.9171 0.9933 0.9408 1.0038 ‐2.37
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335385 4LEROY 138.00 351 0.92 1.05 0.9144 0.9908 0.9383 1.0014 ‐2.39
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335380 4MEAUX! 138.00 351 0.92 1.05 0.9171 0.9933 0.9408 1.0038 ‐2.37
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335381 6MEAUX! 230.00 351 0.92 1.05 0.9169 0.9961 0.9407 1.0062 ‐2.38
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 303132 4JUDICE! 138.00 332 0.92 1.05 0.9046 0.9888 0.9288 0.9961 ‐2.42
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335380 4MEAUX! 138.00 351 0.92 1.05 0.9169 0.9933 0.9407 1.0038 ‐2.38
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335383 4MEAUXSPLT! 138.00 351 0.92 1.05 0.9169 0.9933 0.9407 1.0038 ‐2.38
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SH [REDACTED] 335385 4LEROY 138.00 351 0.92 1.05 0.9143 0.9908 0.9382 1.0014 ‐2.39
Redispatch Morgan city and Neson unit 6
by [REDACTED]
2017SP [REDACTED] 335380 4MEAUX! 138.00 351 0.92 1.05 0.8977 0.9902 0.937 0.9987 ‐3.93 Shed [REDACTED] Load at Judice
Teche 3 OFF Teche 3 ONLimiting ElementContingency
Page 19 of 20
Appendix A, Table 2 ‐ Voltage Analysis Results
MISO Attachment Y Study Results ‐ Teche 3 ‐ Voltage Violations
Redacted
Unit Impact
Year Load Contingency Description Bus Number Bus Name Area Low Limit High Limit Cont. Volt Base Volt Cont. Volt Base Volt
Voff‐Von (< ‐
1%) Comments
Teche 3 OFF Teche 3 ONLimiting ElementContingency
2017SP [REDACTED] 335385 4LEROY 138.00 351 0.92 1.05 0.8947 0.9876 0.9342 0.9961 ‐3.95 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335386 4ABBEVILLE 138.00 351 0.92 1.05 0.9105 0.984 0.9483 0.9949 ‐3.78 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335383 4MEAUXSPLT! 138.00 351 0.92 1.05 0.8977 0.9902 0.937 0.9987 ‐3.93 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 303132 4JUDICE! 138.00 332 0.92 1.05 0.8837 0.986 0.9237 0.9912 ‐4 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335386 4ABBEVILLE 138.00 351 0.92 1.05 0.9102 0.984 0.9481 0.9949 ‐3.79 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335385 4LEROY 138.00 351 0.92 1.05 0.8945 0.9876 0.9341 0.9961 ‐3.96 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335380 4MEAUX! 138.00 351 0.92 1.05 0.8974 0.9902 0.9369 0.9987 ‐3.95 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335383 4MEAUXSPLT! 138.00 351 0.92 1.05 0.8974 0.9902 0.9369 0.9987 ‐3.95 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 303132 4JUDICE! 138.00 332 0.92 1.05 0.8835 0.986 0.9236 0.9912 ‐4.01 Shed [REDACTED] Load at Judice
2017SP [REDACTED] 335381 6MEAUX! 230.00 351 0.92 1.05 0.8974 0.9936 0.9369 1.0019 ‐3.95 Shed [REDACTED] Load at Judice
Page 20 of 20
Cleco Power LLC Teche Unit #3: 335 MW, Gas
Attachment Y Study Report
Appendix B
SSR Alternative Analysis - Demand Response
Appendix B SSR Alternative analysis Demand Response needed
1
Load curtailment analysis was performed to estimate the maximum amount of load shedding required
to alleviate some of the overloads due to NERC Category P6 contingent events. Following three
contingencies were used to identify the need of contracted load curtailment to reduce the loading on
the constrained elements below allowable system adjustment limits
1. Contingency 1 – Curtailing load at ABBEVILLE reduces the overload on the branch MEAUX to
ABBEVILLE, where further system adjustments are applicable.
SENSITIVITY FACTORS OF BRANCH FLOW (MW) ON 335380 4MEAUX! 138.00 TO 335386
4ABBEVILLE 138.00
<----- - LOAD BUS -------> LOAD(MW) MW-SENS Flow Impact
335386 4ABBEVILLE 138.00 34.01 -0.6201 -21.089601
335387 4DELCAMBRE 138.00 23.5 -0.3606 -8.4741
335388 4MORIL! 138.00 0 -0.141 0
335389 4DUBOIN! 138.00 26.04 -0.1398 -3.640392
335390 4BAYOU_WHSE!138.00 7.16 -0.1345 -0.96302
335394 4MORILSPLT! 138.00 14.04 -0.141 -1.97964
335395 4CONRAD 138.00 0 -0.4118 0
500030 BELPLA 4 138.00 14.25 -0.134 -1.9095
500050 BSALES 4 138.00 0 -0.114 0
500060 BVISTA 4 138.00 42.7 -0.1016 -4.33832
500290 ELPTAP 4 138.00 15 -0.1067 -1.6005
500410 HOPKINS4 138.00 94.37 -0.1353 -12.768261
500440 IVANHOE4 138.00 6.37 -0.1318 -0.839566
500450 JULIEN 4 138.00 0.1 -0.1299 -0.01299
500460 JULTAP 4 138.00 0 -0.1299 0
500580 MORBHAN4 138.00 53.85 -0.134 -7.2159
500630 N.BEND 4 138.00 14.91 -0.1142 -1.702722
500660 PATOUT 4 138.00 5.44 -0.1315 -0.71536
500774 SEGURA4 138.00 0 -0.1322 0
500820 TECHE 4 138.00 0 -0.1266 0
500890 WAXLAKE4 138.00 17.86 -0.1085 -1.93781
335275 2LAKE_ARTHUR69.000 6.76 0.1462 0.988312
335276 2KLONDIKE 69.000 2.94 0.1453 0.427182
335330 2LINE-270_TP69.000 0 0.1432 0
335331 2GUEYDAN 69.000 5.38 0.1434 0.771492
335332 2MORSE 69.000 1.99 0.1436 0.285764
335333 2CAMPBELL 69.000 5.7 0.1429 0.81453
335334 2LINE-610_TP69.000 0 0.1368 0
335335 2DUHON 69.000 22.7 0.139 3.1553
335336 2HUNTER 69.000 1.57 0.1371 0.215247
335337 2MEAUX! 69.000 0 0.1307 0
335342 2AVERICO_TP 69.000 0 0.1013 0
335343 2AVERICO 69.000 7.99 0.1018 0.813382
335380 4MEAUX! 138.00 1.8 0.1782 0.32076
335383 4MEAUXSPLT! 138.00 0 0.1782 0
335385 4LEROY 138.00 20.7 0.1789 3.70323
2. Contingency 2 - Curtailing loads at IVANHOE, JULIEN MORBHAN, BELPLA, PATOUT, and TECHE 1
reduces overloads on branches DUBOIN to BAYOU_WHSE, DUBOIN to MORILSPLT, and
BAYOU_WHSE to IVANHOE, where further system adjustments are applicable.
SENSITIVITY FACTORS OF BRANCH FLOW (MW) ON 335389 4DUBOIN 138.00 TO 335394
4MORILSPLT! 138.00 1
<----- - LOAD BUS -- -----> LOAD(MW)MW-SENS Flow Impact
500440 IVANHOE4 138 6.37 -0.6984 -4.448808
Appendix B SSR Alternative analysis Demand Response needed
2
500450 JULIEN 4 138 0.1 -0.6696 -0.06696
500580 MORBHAN4 138 53.85 -0.6227 -33.532395
500030 BELPLA 4 138 14.25 -0.6227 -8.873475
500660 PATOUT 4 138 5.44 -0.6205 -3.37552
500830 TECHE 1 34.5 51.78 -0.6199 -32.098422
500630 N.BEND 4 138 14.91 -0.56 -8.3496
500890 WAXLAKE4 138 17.86 -0.5324 -9.508664
500050 BSALES 4 138 0 -0.5591 0
500290 ELPTAP 4 138 15 -0.5237 -7.8555
500060 BVISTA 4 138 42.7 -0.4994 -21.32438
500090 BERWIC 4 138 0.1 -0.4761 -0.04761
500100 BERWKTP4 138 0 -0.4761 0
500740 RAMOS 4 138 23.08 -0.4343 -10.023644
336030 4GIBSON 138 0 -0.3897 0
336031 3GIBSON 115 13.32 -0.3481 -4.636692
336032 3HUMPHY! 115 6.23 -0.2298 -1.431654
336033 3TEREBN! 115 33.68 -0.1136 -3.826048
335389 4DUBOIN! 138 0 0.1315 0
335390 4BAYOU_WHSE! 138 7.16 0.2601 1.862316
3. Contingency 3– Curtailing load at ABBEVILLE reduces the overload on the branch MEAUX to
ABBEVILLE, where further system adjustments are applicable.
SENSITIVITY FACTORS OF BRANCH FLOW (MW) ON 335380 4MEAUX! 138.00 TO 335386
4ABBEVILLE 138.00 1
<----- - LOAD BUS -------> LOAD(MW) MW-SENS Flow Impact
335386 4ABBEVILLE 138.00 34.01 -0.6201 -21.089601
335387 4DELCAMBRE 138.00 23.5 -0.3606 -8.4741
335388 4MORIL! 138.00 0 -0.141 0
335389 4DUBOIN! 138.00 26.04 -0.1398 -3.640392
335390 4BAYOU_WHSE!138.00 7.16 -0.1345 -0.96302
335394 4MORILSPLT! 138.00 14.04 -0.141 -1.97964
335395 4CONRAD 138.00 0 -0.4118 0
500030 BELPLA 4 138.00 14.25 -0.134 -1.9095
500050 BSALES 4 138.00 0 -0.114 0
500060 BVISTA 4 138.00 42.7 -0.1016 -4.33832
500290 ELPTAP 4 138.00 15 -0.1067 -1.6005
500410 HOPKINS4 138.00 94.37 -0.1353 -12.768261
500440 IVANHOE4 138.00 6.37 -0.1318 -0.839566
500450 JULIEN 4 138.00 0.1 -0.1299 -0.01299
500460 JULTAP 4 138.00 0 -0.1299 0
500580 MORBHAN4 138.00 53.85 -0.134 -7.2159
500630 N.BEND 4 138.00 14.91 -0.1142 -1.702722
500660 PATOUT 4 138.00 5.44 -0.1315 -0.71536
500774 SEGURA4 138.00 0 -0.1322 0
500820 TECHE 4 138.00 0 -0.1266 0
500890 WAXLAKE4 138.00 17.86 -0.1085 -1.93781
335275 2LAKE_ARTHUR69.000 6.76 0.1462 0.988312
335276 2KLONDIKE 69.000 2.94 0.1453 0.427182
335330 2LINE-270_TP69.000 0 0.1432 0
335331 2GUEYDAN 69.000 5.38 0.1434 0.771492
335332 2MORSE 69.000 1.99 0.1436 0.285764
335333 2CAMPBELL 69.000 5.7 0.1429 0.81453
335334 2LINE-610_TP69.000 0 0.1368 0
335335 2DUHON 69.000 22.7 0.139 3.1553
335336 2HUNTER 69.000 1.57 0.1371 0.215247
335337 2MEAUX! 69.000 0 0.1307 0
335342 2AVERICO_TP 69.000 0 0.1013 0
335343 2AVERICO 69.000 7.99 0.1018 0.813382
335380 4MEAUX! 138.00 1.8 0.1782 0.32076
335383 4MEAUXSPLT! 138.00 0 0.1782 0
335385 4LEROY 138.00 20.7 0.1789 3.70323
Cleco Power LLC Teche Unit #3: 335 MW, Gas
Attachment Y Study Report
Appendix C
SSR Cost Allocation
SSR Cost Allocation EPNode Distribution FactorsTeche Unit 3 ‐ Preliminary
The information contained in this document has been redacted to remove Critical Energy Infrastructure (CEII)
Information for public posting.
Full details of the analysis are available on the MISO secure FTP site which is subject to appropriate NDA
restrictions.
Column descriptions:
EP Node ‐ Registered load EP Node name in the MISO Commercial model for the period analyzed
Season ‐ Seasonal conditions (eg. Summer, Shoulder) for which the constraint occurs
Constraint ‐ Thermal or voltage proxy constraint which was identified to require the need for the SSR unit
Ctg Type ‐ The contingency category defined by NERC Reliability Standards
Ctg ‐ The contingency event causing the thermal or voltage constraint ‐ REDACTED for public posting
Dist Factor ‐ The load distribution factor calculated for the load EP Node
Teche 3 (Preliminary Cost Allocation EP Nodes)
EPnode Season Constraint Ctgtype Ctg Dist Factor
L CLEC BERWIC T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC BERWIC T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC BERWIC T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC BUVIS LT2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC BUVIS LT2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC BUVIS LT2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC BUVIS T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC BUVIS T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC BUVIS T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC DUBON7 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC DUBON7 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC DUBON7 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC ELPTAP4 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC ELPTAP4 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC ELPTAP4 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC ERATH_CL ERATH_CL 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC ERATH_CL ERATH_CL 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC GEYD_C GEYD_C 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC GEYD_C GEYD_C 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC HOPKIN HOPKN_XFMR1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC HOPKIN HOPKN_XFMR1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC HOPKIN HOPKN_XFMR2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC HOPKIN HOPKN_XFMR2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC HOPKIN HOPKN_XFMR3 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC HOPKIN HOPKN_XFMR3 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC IVANHO T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC IVANHO T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC IVANHO T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC IVANHO T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC IVANHO T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC IVANHO T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC JULIEN4 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC JULIEN4 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC JULIEN4 T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC LNGFLW T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC LNGFLW T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC LNGFLW T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC LNGFLW T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC MORBHN 4A 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC MORBHN 4A 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC MORBHN 4A 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC MORBHN 4B 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC MORBHN 4B 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC MORBHN 4B 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC MORBHN BELPLA_4 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC MORBHN BELPLA_4 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC MORBHN BELPLA_4 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC NORBND C_CARBON 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC NORBND C_CARBON 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC NORBND C_CARBON 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC NORBND S_BEND 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC NORBND S_BEND 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC NORBND S_BEND 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC PATOUT T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC PATOUT T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC PATOUT T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC PATOUT T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC PATOUT T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC PATOUT T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC RAMOS XFLD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC RAMOS XFLD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC RAMOS XFLD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC TECHE1 BALDWIN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
Teche 3 (Preliminary Cost Allocation EP Nodes)
EPnode Season Constraint Ctgtype Ctg Dist Factor
L CLEC TECHE1 BALDWIN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC TECHE1 BALDWIN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC TECHE1 FRANKLIN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC TECHE1 FRANKLIN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC TECHE1 FRANKLIN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC TECHE1 GEN_AUX1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC TECHE1 GEN_AUX1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC TECHE1 GEN_AUX1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC TECHE1 GEN_AUX2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC TECHE1 GEN_AUX2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC TECHE1 GEN_AUX2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC TECHE1 JEANETTE 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC TECHE1 JEANETTE 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC TECHE1 JEANETTE 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC TECHE1 N_BEND 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC TECHE1 N_BEND 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC TECHE1 N_BEND 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC WAXLKE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC WAXLKE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC WAXLKE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L CLEC WAXLKE T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L CLEC WAXLKE T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L CLEC WAXLKE T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L EES ABBEVL T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES ABBEVL T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES ABBEVL T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES ABBEVL T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES ANSELA T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES ANSELA T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES AVERIC T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES AVERIC T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES BILEAU T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES BILEAU T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES BILEAU T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES BILEAU T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES BWH T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES BWH T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES BWH T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L EES CECELA T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES CECELA T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES CECELA T3 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES CECELA T3 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES CLN T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES CLN T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES DELCAM T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES DELCAM T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES DELCAM T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES DELCAM T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES DUB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES DUB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES DUB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L EES DXB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES DXB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES FPT T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES FPT T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES GIBSN4 S4175_LOAD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES GIBSN4 S4175_LOAD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES GIBSN4 S4175_LOAD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L EES GIBSN4 S8020_LOAD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES GIBSN4 S8020_LOAD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES GIBSN4 S8020_LOAD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L EES HLA T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES HLA T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
Teche 3 (Preliminary Cost Allocation EP Nodes)
EPnode Season Constraint Ctgtype Ctg Dist Factor
L EES HUMPY4 T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES HUMPY4 T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES HUMPY4 T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L EES HUN T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES HUN T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES INN T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES INN T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES JUNGRD T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES JUNGRD T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES LFB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES LFB T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES LFB T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES LFB T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES LKA T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES LKA T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES LKA T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES LKA T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES MAU T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES MAU T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES MAU T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES MAU T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES MOR T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES MOR T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES MORIL 1B 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES MORIL 1B 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES NEWIBE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES NEWIBE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES PARKS T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES PARKS T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES ST_MAR T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES ST_MAR T2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES TXE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES TXE T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L EES YOUNGV T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L EES YOUNGV T1 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN BLOU BLOU 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN BLOU BLOU 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN BLOU BLOU 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L LAGN DUHN DUHN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN DUHN DUHN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN GEKO GEKO 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN GEKO GEKO 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN GEYD GEYD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN GEYD GEYD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN GRWD GRWD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN GRWD GRWD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN GRWD GRWD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L LAGN KLON KLON 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN KLON KLON 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN KPL2 KPL2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN KPL2 KPL2 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN LBLK LBLK 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN LBLK LBLK 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN LEBL LEBL 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN LEBL LEBL 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN MELC MELC 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN MELC MELC 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN RAMO RAMO 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN RAMO RAMO 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN RAMO RAMO 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994
L LAGN SEMR SEMR 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LAGN SEMR SEMR 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LAGN STJN STJN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
Teche 3 (Preliminary Cost Allocation EP Nodes)
EPnode Season Constraint Ctgtype Ctg Dist Factor
L LAGN STJN STJN 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LEPA MRGNCTY4 MRGNCTY_LD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_1 P6 [REDACTED] 0.9994
L LEPA MRGNCTY4 MRGNCTY_LD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_2 P6 [REDACTED] 0.9994
L LEPA MRGNCTY4 MRGNCTY_LD 2017 Summer Peak 9997‐TECHESSR_VoltageStability_3 P6 [REDACTED] 0.9994