AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS – Photo Report
• Key Plan showing the Camera positions, Click on the Icon to review respective status:
12
3
4
5
6
7
8
9
10 1112 13 14
15
1617
18
19
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 01
• Aurum Villas front entrance
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 02
• Package I – Boundary compound wall in progress
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 03
• Package I – UG drain pipe work in progress
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 04
• Package I – Edge villa compound wall in progress
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 05
• Package I – WMM laying in 12m road
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 06
• LEFT – Package 02 RIGHT – Package 01
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 07
• Package II – Car parking and Elevation granite are in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 08
• Package I – Edge villa compound wall in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 09
• Package I – Waterproofing work in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 10
• Package II – Planter work in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 11
• Package II – Main door polish in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 12
• Package II – Main door polish in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 13
• Package II – UPVC window work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 14
• Package II – Road work preparation in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 15
• Package II – Road WMM work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 16
• Package II – Road work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 17
• Package II – Road WMM work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 18
• Package II – External SWR line in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 19
• Package II – Road preparation work in progress
Key Plan
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS SEWAGE TREATMENT PLANT
• Wall 2nd lift concrete completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS WATER TREATMENT PLANT
• Waterproofing in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS WATERPROOF WORK
• Villa waterproofing 58% completed
AURUM_Photo Report - Villas
Comments :
• Main door polish primary coats 11% completed
AURUM – VILLAS PAINTING WORK
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS INTERNAL ELECTRICAL WORK
• Wall conduit 91% completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS DOOR WINDOWS
• UPVC Window 26% completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS INTERNAL PLUMBING WORK
• UG pipeline 43% completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS ROAD WORK
• WMM work 46% completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS ROAD WORK
• Kerb work 26% completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS EXTERNAL PLUMBING WORK
• SWR pipe line 72% completed
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS EXTERNAL PLUMBING WORK
• DWS pipe line 50% completed
AURUM_Photo Report - Villas
AURUM – VILLAS Aerial View
• .