berwyn wastewater facility plan 2014 (city and depot district)

194
IEPA - Facilities Planning Submittal Checklist Page 1 of 2 Before the Agency will begin review of a Facilities Plan, ALL of the items below comprising the basic minimum requirements of a Facilities Plan must be included and the page number(s) of ALL items noted. If any of the basic information is not provided the planning and loan application will be returned. Facilities planning should contain all pertinent information detailed in Ill Adm. Code 35 Section 365.520(e). Loan Applicant should be familiar with their planning responsibilities as detailed in Section 365.520 and 530. Loan Applicant: Agency Use: L17 Consulting Engineer: Phone: Project Description: Page(s) Loan applicant's background information including location, historical population, makeup of customer base, conditions affecting growth, and 20 year design population/customer base. Map(s) of existing FPA boundaries and discussion of any necessary modifications. Note: FPA boundary modifications entail additional requirements, review and sign-offs. Detailed description of the EXISTING collection system and treatment facilities, along with a clear identification for the need of the proposed project(s). Where applicable, information regarding an anti-degradation analysis pursuant to Ill. Adm. Code 35 Section 302.105 for a new or modified NPDES Permit. Discussion of existing and proposed NPDES Permit limits. Detailed discussion of the chosen alternative's capability to maintain compliance with all applicable laws and regulations in addition to addressing the identified system need(s). Basis of Design for Chosen Alternative. The preliminary engineering data should include, to the extent appropriate, flow diagrams, unit process descriptions, detention times, flow rates, unit capacities, etc. to demonstrate that the proposed project will be designed in accordance with 35 Ill. Adm Code 370. City of Berwyn TERRA Engineering LTD 312-467-0123 The proposed project will provide a new connection to the MWRD Intercept, provide additional detention, as well as repairs and improvements to the existing system. 2-4 7 4-10 NA 5 10-12 13

Upload: berwyn-residents

Post on 01-Jul-2015

140 views

Category:

Government & Nonprofit


4 download

DESCRIPTION

An assessment of Berwyn’s Wasterwater Facility Plans, including a project proposal for development of the Berwyn Depot District. Published July 2014.

TRANSCRIPT

Page 1: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

IEPA - Facilities Planning Submittal Checklist Page 1 of 2

Before the Agency will begin review of a Facilities Plan, ALL of the items below comprising the basicminimum requirements of a Facilities Plan must be included and the page number(s) of ALL items noted.If any of the basic information is not provided the planning and loan application will be returned.

Facilities planning should contain all pertinent information detailed in Ill Adm. Code 35 Section 365.520(e).Loan Applicant should be familiar with their planning responsibilities as detailed in Section 365.520 and 530.

Loan Applicant: Agency Use: L17

Consulting Engineer: Phone:

Project Description:

Page(s)Loan applicant's background information including location, historical population, makeup ofcustomer base, conditions affecting growth, and 20 year design population/customer base.

Map(s) of existing FPA boundaries and discussion of any necessary modifications.Note: FPA boundary modifications entail additional requirements, review and sign-offs.

Detailed description of the EXISTING collection system and treatment facilities, alongwith a clear identification for the need of the proposed project(s).

Where applicable, information regarding an anti-degradation analysis pursuant to Ill. Adm.Code 35 Section 302.105 for a new or modified NPDES Permit.

Discussion of existing and proposed NPDES Permit limits.

Detailed discussion of the chosen alternative's capability to maintain compliance with all applicable laws and regulations in addition to addressing the identified system need(s).

Basis of Design for Chosen Alternative. The preliminary engineering data should include,to the extent appropriate, flow diagrams, unit process descriptions, detention times, flow rates, unit capacities, etc. to demonstrate that the proposed project will be designedin accordance with 35 Ill. Adm Code 370.

City of Berwyn

TERRA Engineering LTD 312-467-0123

The proposed project will provide a new connection to the MWRD Intercept,provide additional detention, as well as repairs and improvements to the existing system.

2-4

7

4-10

NA

5

10-12

13

Page 2: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

IEPA - Facilities Planning Submittal Checklist Page 2 of 2

Page(s)Inventory of environmental impacts of chosen alternative and a discussion of the measuresrequired during design and construction to mitigate or minimize negative environmentalimpacts. The discussion should address at a minimum; rare and endangered species,historic and cultural resources, prime agricultural land, air and water quality, recreationalareas, wetlands, floodplains and other sensitive environmental areas.

Note: The IEPA Loan Applicant Environmental Checklist must be signed by the loanapplicant's authorized representative and submitted to the Agency with all applicablesign-offs before a final Planning approval can be issued.

Reproducible 8.5 x 11 inch map(s) showing the project(s) location(s) relative to the community.

Detailed cost estimate for the alternative selected, including both capital and O, M & R costsover the 20-year planning period. The estimate should include cost items for design engineering, construction engineering, bidding, legal, construction and contingency.

Implementation plan for the proposed project including the anticipated construction schedule, the financial schedule, including necessary financial arrangements for assuring adequateannual debt service and O,M & R coverage requirements and a description of the dedicatedsource of revenue necessary for loan repayment. List any other funding involved in the project.

Detailed description of the existing residential rate structure, average water consumption or the basis for billing, current average monthly residential bill, any proposed rate changesand the proposed average monthly residential bill as a result of the project(s).

Three Copies of the Facilities Plan and related documents should be submitted to:

Infrastructure Financial Assistance Section (IFAS)Illinois Environmental Protection Agency1021 North Grand Ave. EastP.O. Box 19276Springfield, IL 62794-9276

IFAS will distribute the planning documents to the appropriate Agency staff for review, comment and approval. IFAS will contact the loan applicant if further information is needed.

14-15

7

14

15

15

Page 3: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

   

      

Wastewater Facility Plan  

City of Berwyn Cook County, Illinois 

 July 2014 

  

                         Prepared by:  TERRA Engineering LTD 225 West Ohio Street 4th Floor Chicago, IL 60654

Page 4: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

i  

Table of Contents I.  EXECUTIVE SUMMARY ..................................................................................................................... 1 

II.  INTRODUCTION ...............................................................................................................................  2 

A.  Community Information ............................................................................................................... 2 

B.  Population and Demographics ..................................................................................................... 3 

C.  Employment Analysis ................................................................................................................... 4 

D.  Conditions affecting growth ......................................................................................................... 4 

III.  Existing Conditions ....................................................................................................................... 4 

A.  Description of Existing Wastewater Collection System ................................................................. 4 

B.  Project Area: ................................................................................................................................ 6 

C.  Project Need: ...............................................................................................................................  9 

IV.  Description of Proposed Project ................................................................................................. 10 

A.  Design Alternatives .................................................................................................................... 10 

1.  New Connection to MWRD Interceptor .................................................................................. 10 

2.  Relief Sewers to Improve System Balance .............................................................................. 11 

3.  Line Existing Sewers ............................................................................................................... 11 

4.  Permeable Pavers .................................................................................................................. 11 

B.  Basis for Design of Preferred Alternative .................................................................................... 13 

C.  Project Probable Opinion of Costs .............................................................................................. 13 

V.  Environmental Impacts .................................................................................................................. 14 

A.  Rare and Endangered Species .................................................................................................... 14 

B.  Historic and Cultural Resources .................................................................................................. 14 

C.  Prime Agricultural Land .............................................................................................................. 14 

D.  Air and Water Quality ................................................................................................................ 14 

E.  Recreational Areas ..................................................................................................................... 14 

F.  Wetlands ................................................................................................................................... 14 

G.  Other Sensitive Environmental Areas ......................................................................................... 15 

VI.  Implementation Plan ................................................................................................................. 15 

VII.  Rate Structure ............................................................................................................................ 15 

 

Page 5: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

ii  

List of Tables  Table 1 Land Use Inventory Table 2 Population and Household Change, 2000‐2010 Table 3 Observed Storm Events Causing Flooding Table 4 Area and Flow Adjustments Table 5 Estimate of Construction Costs  

List of Figures  Figure 1 Location Map Figure 2 Existing Sewer Network Figure 3 MWRD Network Figure 4 New Conveyance Sewer to MWRD Interceptor  

List of Appendices  Appendix A MWRD Historical Flows Appendix B City of Berwyn Usage Charges Report Appendix C Hydraulic Reports – Existing Appendix D Hydraulic Reports ‐ Proposed Appendix E Record of Environmental Concerns Appendix F Combined Sewer Operational & Maintenance Plan Appendix G Anticipated Project Revenues/Expenses

Page 6: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

1  

I. EXECUTIVE SUMMARY  The City of Berwyn,  Illinois  is  located  in west suburban Cook County approximately  ten miles west of 

Chicago. The City of Berwyn uses a combined storm and sanitary sewer system which was built between 

75 – 90  years ago and has deteriorated with need  for  rehabilitation. The  current  local  system has a 

capacity for less than a 2‐year storm event. The local combined sewers discharge into the Metropolitan 

Water Reclamation District (MWRD) West Town Outlet and Northwest Interceptor sewers. These sewers 

ultimately flow to the Stickney Water Reclamation Plant and Chicago Sanitary and Ship Canal. 

During  storm  events,  the West  Town Outlet  Interceptor was  designed  to  overflow  directly  into  the 

Chicago  Sanitary  and  Ship  Canal whenever  flows  exceeded  the  capacity  of  the  treatment  plant.  To 

reduce the  frequency of harmful discharge  into the waterway, the MWRD has developed a  long‐term 

plan consisting of deep tunnels and reservoirs. The plan, known as the Tunnel and Reservoir Plan (TARP), 

is intended to provide temporary storage of the combined sanitary and storm flows so that they can be 

treated prior to discharge into the waterway. At this time, Phase I, the deep tunnel portion of the plan, 

has been constructed and functions to  intercept flows that exceed the capacity of the treatment plant 

until the large tunnels are filled.  

Phase II of the TARP project involves the construction of flood control reservoirs. The McCook Reservoir 

will serve the City of Berwyn. The MWRD plans to complete construction the first half of the reservoir by 

2017. Since it has not yet been constructed, the tunnels fill approximately 20 times per year resulting in 

significant upstream surging of the interceptors and local sewer, while simultaneously overflowing into 

the Chicago Sanitary and Ship Canal. During these events, the Berwyn sewer system also backs up into 

residential basements. Upon completion of the first half of the reservoir, combined sewer overflows into 

the Chicago Sanitary and Ship Canal will be reduced to approximately 2‐3 events per year. The remaining 

half  of  the  McCook  Reservoir  is  not  scheduled  for  completion  until  2029.  When  the  reservoir  is 

ultimately finished, it will have a total capacity of 10 billion gallons. 

Although the full benefit of the proposed Depot District sewer  improvements will not be realized until 

the TARP  reservoir  is 100%  complete,  the  community will materially benefit  from  the  improvements 

provided by having better balanced local sewer systems. The water quality of the Chicago Sanitary and 

Ship  Canal  will  also  benefit  from  the  reduced  overall  peak  demand  from  the  local  sewer  system 

associated with the detention volume provided by the project. 

This Facilities Plan summarizes the existing community system, identifies sewer system limitations, and 

recommends  proposed  improvements  located within  a  central  business  area  known  as  the  Berwyn 

Depot District. It also evaluates the improvements effects on the surrounding community. The proposed 

project will provide a new connection to the MWRD Interceptor, provide additional detention to reduce 

surface  flooding  and  peak  discharge  to  the  Interceptor,  redistribute  flows  to  better  balance  system 

capacity, and incorporate repairs to deteriorated pipes and structures. 

The estimated project cost including engineering and construction is $3,000,000. 

 

kellypage
Highlight
kellypage
Highlight
Page 7: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

2  

II. INTRODUCTION 

A. Community Information The City of Berwyn is located within ten miles of downtown Chicago, situated between 

the  Stevenson  (I‐55) and Eisenhower  (I‐290) Expressways and  is  in  close proximity  to 

Midway and O’Hare Airports. It is serviced by the BNSF Metra Rail line and four Pace bus 

routes.   Berwyn  is known  for  its  stock of Chicago‐style bungalow homes, multi‐modal 

infrastructure, and a diversity of stores and restaurants. The City is home to a stretch of 

Historic  Route  66  (Ogden  Avenue),  well‐maintained  parks,  good  schools,  and  an 

assortment  of  recreational  and  cultural  institutions.    Due  to  its  prime  location  and 

availability of affordable housing, the City has seen an increase in population, traffic and 

urban density over the past several decades. 

The City’s  land area  is 3.9 square miles with a population of 56,657  in which 72% are 

over the age of 18.  This equates to a population density of 14,527 per square mile; 20% 

higher than that of Chicago’s.  

Berwyn’s single family housing stock represents the largest total acreage of any land use in the City (70% of the City). A majority of the single family homes are located south of Cermak Road. The parcels are generally small in size with limited options for additions.  North  of  Cermak  Road  and within  the  Depot  District  are  located  the  City’s multiple family units.   Multiple  family units account  for approximately 10 % of  the City’s  total land area.  

Berwyn’s  commercial  uses  are  lined  along major  thoroughfares  running  through  the community or along its municipal boundaries. These include Harlem Avenue, Roosevelt Road, Cermak Road, 26th Street, and Ogden Avenue. These commercial parcels account for 11% of  the City’s  land area with  close  to 80% of businesses being  locally owned.  Despite  the  large  number  of  retailers  throughout  the  City,  commercial  vacancies  are relatively low at around 8%. 

Being a landlocked community with relatively small parcel sizes, Berwyn has had limited opportunities  to  attract  industrial  businesses.  This  is  corroborated  by  the  fact  that industrial land constitutes only 1% of the City’s total area. 

Berwyn  is  home  to  a  number  of  educational  institutions  located within  three  school districts. District 98 and District 100 are K‐8 school districts while District 201 serves the City’s only high school. North Berwyn School District 98 contains three elementary and one middle school. South Berwyn District 100 contains six elementary schools and two middle schools within its jurisdiction. 

Institutional uses make up approximately 5% of Berwyn’s land area. MacNeal Hospital is one  of  the  largest  landowners  and  employers  in  Berwyn with  a  number  of  facilities located throughout the City and in adjacent communities. The hospital is located at the center of the Berwyn Depot District. 

 

Page 8: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

3  

Table 1 Land Use Inventory 

Land Use Classification  Area (acres) Area (Percentage) 

Single Family Residential 1753.8 70.3%

Multi‐Family Residential 245.9 9.8%

Commercial/Mixed Use  266.2 10.7%

Open Space  50.1 2.0%

Manufacturing  19.9 0.9%

Institutional  112.6 4.9%

Utilities/Transportation  32.5 1.4%

 

B. Population and Demographics Created  in  1856,  the  first  “Berwyn”  was  part  of  an  area  then  known  as  LaVergne.  LaVergne’s  founding  fathers  soon  recognized  the  need  to  invest  in  infrastructure improvements  to  attract  additional  residents  and  investors.  To  accomplish  this,  the latter  half  of  the  19th  century  saw  widespread  construction  of  railroad  tracks,  City streets, and landscaping. Following completion of the railroad and opening of the area’s first train station, developers built several residential units along the rail line. At the turn of the century, the City of Berwyn was carved out of the LaVergne area as a separate municipality.  Through  acquisition,  the  City  expanded  towards  the  north  and incorporated  developments  that  had  stronger  connections  to  Oak  Park.  The  newly founded City saw a tremendous growth in its housing stock through the 1920s, earning it the name “City of Homes”. Simultaneously, the City also saw a growth in diversity of its residents with the influx of over 40,000 Czech, Italian, Greek, Polish, and Yugoslavian workers (Source: Berwyn Preservation Plan). The growth can mainly be attributed to the movement of industries and businesses outside of the City of Chicago in search of larger undeveloped parcels of land. 

Berwyn  can  be  characterized  generally  as  a  moderate  income  community,  with significant  pockets  of  middle‐class  and  working‐class  family  households.  Berwyn’s housing stock is a balanced mix of single‐family homes and multifamily structures, with most  of  those  being  in  the  2‐6  unit  range.  The  average  household  size  in  Berwyn  is relatively high compared  to  the County and Chicago  region. Additionally,  the City has seen a significant increase in its average household size in the past decade. The change is even more significant when compared to the County’s decrease in size of households. The Chicago Metropolitan Agency  for Planning  (CMAP) projects that  if  its GO TO 2040 plan is implemented, it could boost the population of Berwyn to 58,648 by 2040. 

Table 2 Population and Household Change, 2000‐2010   Berwyn Cook County Chicago Region 

  2000 2010 2000 2010 2000  2010

Population  54,016 56,657 5,018,056 5,194,675 8,146,264  8,431,386

Households  19,702 18,910 1,974,181 1,966,356 2,925,723  3,088,156

Population Change 2000‐2010 

 4.6% 

 ‐3.4% 

 1.3% 

Household Change 2000‐2010 

 9.5% 

 ‐3.0% 

 0.4% 

Source: 2000 U.S. Census; 2010 U.S. Census 

Page 9: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

4  

 The median age of Berwyn residents in 2010 was 32.9, lower than that of Cook County (35.3). The median age of Berwyn residents declined by more than five percent between 2000 and 2010, while the median age increased by three percent in Cook County. 

Hispanics constitute the majority of residents in Berwyn, and achieved that status in the last decade. As of 2010, Hispanics were 59 percent  of Berwyn  residents, up  from 38 percent in 2000.  The number of whites fell considerably, from 56 percent to 31 percent. The  most  significant  increase  was  among  black  residents,  quintupling  in  size  and increasing from one percent to five percent in the last decade. Asians and those of other racial and ethnic groups comprise the remainder of the population. 

Although Berwyn closely matches the region in terms of its labor force participation, the unemployment  rates  are  higher.  Berwyn’s  and  Cook  County’s  unemployment  rate  is 9.3%, compared to the Chicago Region’s 8.2%.   This  is no surprise as a majority of the City’s  residents work  outside  Berwyn within  Cook  County, which  has  experienced  a similar unemployment rate due to current economic and fiscal constraints. 

C. Employment Analysis According  to  the  Illinois Department  of  Employment  Security,  the  number  of  jobs  in Berwyn decreased from 11,290 to 10,599 between 2002 and 2009, a loss of six percent. Job loss has had a significant impact on Berwyn, but it is consistent with similar data for both  Cook  County  and  the  region.  During  the  same  period,  jobs  declined  by  three percent in Cook County, and by one‐tenth of a percent throughout the Chicago region. It is assumed that employment will be stable for the foreseeable future. 

D. Conditions affecting growth The deep and prolonged recession has presented a major challenge. Unemployment  is 

well above normal  levels and  real median household  income has declined by  ‐12.99% 

since  2000.  The  combination  of  these  two  economic  factors  has  put more  stress  on 

homeowners  and  renters  alike.  Not  surprisingly,  foreclosure  filings,  due  to  the 

availability  of  high‐risk  adjustable  rate mortgage  products  and  rising  unemployment, 

have risen sharply and are at  levels that exceed those of Cook County and the region 

overall.  Foreclosures  have  not  just  impacted  single‐family  homes.  They  have  also 

directly  affected  the  important  multi‐family  rental market.      While  the  number  of 

auctioned  foreclosed properties appears  to be declining,  there  is evidence  to  suggest 

that  this  is  the  result  of  prolonged  processing  due  to  a  backlog  at  county  courts. 

Foreclosure activity has, in turn, led to a steady decrease in home sale prices in the City. 

Because  Berwyn  is  predominantly  residential,  the  decrease  in  residential  property 

values has adversely impacted its tax base. 

III. Existing Conditions 

A. Description of Existing Wastewater Collection System Berwyn,  as  an  urban  infill  community,  has  active  Combined  Sewer  Overflow  (CSO) 

problems and  recognizes  the environmental and health  risks  that are associated with 

CSO. The City’s combined sewer system is nearing 100 years old and incapable, at times, 

of  handling  the  increased  capacity  required,  especially  during  a  storm.   Much  of  the 

Page 10: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

5  

combined  sewer  system  was  designed  to  handle  small  one  story  structures  when 

pervious green areas were much  larger.   While  the population and density of Berwyn 

has  grown  over  the  last  century,  the  combined  sewer  system  has  remained  largely 

untouched.  The sewer usage charges for the City of Berwyn are listed in Appendix A. 

The  City’s  current  stormwater  management  system  is  a  combined  sewer  system 

comprised of a conveyance system nearly 100 miles in length and storm laterals totaling 

19 miles. Stormwater runoff and sewage are collected into a single pipe and ultimately 

discharged  into  the  large  interceptors of  the MWRD where  it  is eventually  treated at 

their Stickney Treatment Plant.   The Stickney Plant has the capacity to treat 1.2 billion 

gallons of wastewater per day, serving a 260 square mile area with 2.5 million people.  

This  area  encompasses  parts  of  Chicago  and  43  suburban  communities.    Many  of 

Berwyn’s  neighboring  communities which  are  serviced  by  the  Stickney Plant  are also 

built  out,  land  locked  communities  with  aging  infrastructure.    The MWRD  operates 

under  NPDES  Permit  No.  IL0028053  and  is  required  to monitor  112  CSO  outfalls  in 

accordance with Special Condition 10.11. 

The  City  of  Berwyn  is  located  within  the  Lower  Des  Plaines  River  watershed.    This 

watershed covers over 228,000 acres of predominately urban and industrial uses within 

DuPage, Cook and Will Counties. Within  this watershed,  the Depot District  in Berwyn 

drains to the Chicago Sanitary and Ship Canal. The Chicago Sanitary and Ship Canal is an 

impaired,  man‐made  waterway  with  high  amounts  of  polychlorinated  biphenyls, 

phosphorus,  and  low  amounts  of  dissolved  oxygen.  Combined  sewer  overflows  and 

urban runoff are listed as two of the causes for this impairment. 

Planning  efforts  are  currently  underway  to  reduce  combined  sewer  overflows.  The 

MWRD  TARP  is  currently  underway  to  increase  the  region’s  capacity  to  contain  and 

direct  combined  sewer  flows  to  water  reclamation  plants  for  treatment  instead  of 

discharging  into  rivers  and  lakes.  CSO  communities  are  also  implementing  long‐term 

control plans and aggressive pollution prevention strategies to minimize pollutant loads 

entering the combined sewer systems. 

Berwyn  in particular  is  taking a multifaceted approach  to addressing CSO.   The City  is 

slowly acquiring blighted property and constructing green space called “pocket parks.” 

Beyond serving as public space, the pocket parks work to  increase the permeability of 

the entire area. Other  improvements  in City parks  include  recently  replacing a 25,580 

square  foot  asphalt  parking  lot  with  permeable  pavers  and  installing  a  StormTrap 

underground  stormwater  storage  system  designed  to  provide  5,507  cubic  feet  of 

underground  storage  in  a  park  in  a  section  of  the  City  that  experiences  flooding 

regularly. 

Commercially,  the  City  is  working  with  three  large  development  projects  that  will 

include onsite detention of stormwater runoff. Similarly, MWRD has a new stormwater 

ordinance  that will  require  detention  on  future  development  projects.  The  City  also 

actively  supports  a  rain  barrel  program  for  its  residents  in  an  effort  to  further  allay 

runoff. The zoning ordinance is in the process of being updated to allow native plantings 

normally found in rain gardens.  

kellypage
Highlight
Page 11: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

6  

B. Project Area: The proposed project focuses on the streets adjacent to the Berwyn Depot District, an area  adjacent  to  the  BNSF  Railroad  extending  from  Harlem  Avenue  on  the west  to Ridgeland Avenue on the east, and along Oak Park Avenue from 30th Street on the north to Ogden Avenue on the south. See Location Map – Figure 1.  

The Berwyn Depot District  is drained  through a  series of  roadway drainage structures that  connect  to  the City of Berwyn's  combined  sewer and  relief  sewer network.   The greater  part  of Windsor  Avenue  and  Stanley  Avenue  roadway  drainage  is  collected through 12"‐15" sewers.  In general, most developed  lots fronting Windsor Aveune and Stanley Avenue  have  sewer  connections made  through  the  alleyways.  Therefore,  the sewers  within Windsor  and  Stanley  are  predominantly  handling  only  the  roadway's drainage  area.   However,  these  sewers  are  cross‐connected with  the  alley  sewers  so they  will  experience  water  backing  up  through  the  system  as  the  sewer  becomes surcharged.  The city's existing sewer network is dated, for instance the trunk line down Oak Park Avenue is constructed out of brick, and many areas are in need of repair.  

Figure 2: Existing Sewer Network depicts the main trunk  lines of the City’s conveyance sewers. It also delineates the various drainage area boundaries within the Depot District area and gives those area outlet pipe sizes. Areas A and B encompass the largest portion of the Depot project area, draining over 220 acres. 

The project area generally slopes east and south, there  is a drainage divide created at the  BNSF  railroad  tracks,  elevated  approximately  3.0'  above  the  adjacent  Stanley Avenue and Windsor Avenue roadways.  The Depot District sewers connect to multiple discharge outlets, the most prominent outlet being the 14.0' x 12'‐6" MWRD West Town Outlet Interceptor, draining south along East Avenue.  This MWRD Interceptor is cross‐connected at  five  locations with the City of Berwyn's 24" sewer,  flowing north,  in East Avenue, See Figure 3.  

Area A drains south along Oak Park Avenue across Ogden Avenue to 37th Street, where it travels  eastward  through  a  5’  sewer  to  connect with  the MWRD West  Town Outlet Interceptor. Surcharging along  this  system affects not only Area A but  the area  south and east of Ogden Avenue. In addition, an undefined area from the Village of Riverside will overflow into Area A during storm events in excess of 10‐years. The remaining areas discharge into a 7'‐6" sewer flowing southeast along the IC Railroad (Areas C, D, E, & G).  

Other restrictions within the Depot District area include the 36” brick sewer that crosses under the BNSF railroad flowing south along Oak Park Avenue. Televising of the existing sewer under the railroad was infeasible because of severe deterioration in the pipe and connecting  structures.  Due  to  the  grade  differences  that  the  railroad  creates, stormwater runoff is incapable of following any overland natural drainage pattern to the south.  If  the  sewer  under  the  railroad  is  not  functioning,  ponded  stormwater  runoff must be captured and drained by cross connections  into Area G. This north system  in Area  B  includes  all  of  the  sewers  west  of  Oak  Park  Avenue  running  along  Stanley Avenue, which are currently routed from Kenilworth Avenue up to 32nd Street.  

 

   

kellypage
Highlight
kellypage
Highlight
kellypage
Highlight
Page 12: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

´1 inch = 2,000 feetBerwyn Depot District Streetscape

Location Map - Figure 1

LegendProject LimitsBerwyn Limits

Page 13: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

F311TERRA I • ENGINEERING LTD. 225 W. Ohio Street, 4th Floor Chicago, Illinois 60654 (312) 467-0123 (312) 467-0220 fax

24" SEWER TRIBUTARY TO 5.0' BRICK SEWER.

CROSS-CONNECTED WITH MWRD INTERCEPTOR.

30" SEWER TRIBUTARY TO 5.0' BRICK SEWER.

CROSS-CONNECTED WITH MWRD INTERCEPTOR.

AREA = 6.8 ACRES

AREA = 32.9 ACRES

v 12'-0" x 13'-4" MWRD

l ~WEST TOWNS

I INTERCEPTOR

DROP MH CROSS-CONNECT vI TO MWRD ~ INTERCEPTOR {TYP) G) .....__ _____ __. ~

z 0

~

DROP MH FOR 15" CROSS-CONNECTS TO MWRD INTERCEPTOR (TYP)

FIGURE 2: EXISTING SEWER NETWORK

12" SEWER TRIBUTARY TO 7'-6" BRICK SEWER, FLOWING SOUTHEAST AREA = 4.8 ACRES

~~~~~-r~!. SEWER TRIBUTARY TO 7'-6" BRICK SEWER, FLOWING SOUTHEAST AREA = 54.2 ACRES

1

1.-...----

DROP MH CROSS-CONNECT TO MWRD INTERCEPTOR (TYP)

CITY OF BERWYN

Page 14: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

9  

The  MWRD  West  Town  Outlet  Interceptor  sewer  was  constructed  in  1936.    The interceptor  is a 12'‐6" x 14.0' reinforced concrete sewer and sits approximately twenty feet below grade.   At the time of design the sewer's capacity was estimated to be 920 CFS near the City of Berwyn.  A cross connection exists in Cermak Avenue that allows for stormwater  to  be  diverted  from  the  West  Town  Outlet  Interceptor  east  to  the Northwest  Number  3‐A  Outlet,  located  in  Lombard  Avenue.    This  cross‐connection occurs north of the Depot District. 

 

  Figure 3 MWRD Network  

C. Project Need:   As  discussed  in  the  existing  conditions  section,  Berwyn’s  stormwater  and  sanitary 

sewage  is  conveyed  to  the MWRD  interceptor  system. Most  of  these  City  collection 

Approximate Depot 

District Drainage Area 

West Town Outlet 

Interceptor  

Northwest Outlet 

Interceptor 

Cermak Ave Cross 

Connection  

Page 15: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

10  

sewers have a very limited capacity to convey stormwater runoff due to their small size 

and  long distances to the MWRD  interceptor. During heavy rainfall events, MWRD has 

been forced to close the sluices gates to their system and excess flows are diverted into 

the surrounding waterways untreated.  

The  City  has  experienced  several  instances  of  damaging  flooding  over  the  past  few 

years, resulting in hundreds of thousands of dollars in damage and the displacement of 

residents  from  their  homes.  The  following  storm  events  have  caused  flooding  in  the 

Berwyn community: 

Table 3 ‐ Observed Storm Events Causing Flooding 

Date Inches Duration

Aug 2, 2001 6” 24‐hour

Sept 13, 2008 6.64” 24‐hour

Jun 23, 2010 3.41” 45‐min

Jul 24, 2010 7.20” 8‐hour

Jul 23, 2011 6.86” 3‐hour

Apr 18, 2013 6.50” 24‐hour

 

The City’s combined  sewers are outdated and were not originally designed  to  sustain 

the demands of a growing urban area. Furthermore,  the aging system  is experiencing 

infiltration through joints, damaged pipes, and issues related to root penetration. 

MWRD  performed  flow metering  in  West  Town  Outlet  1  at  42nd  and  East  Avenue 

structure  in 2008. This outlet  is downstream of  the project area.  The  sewer  reached 

capacity  once  during  the  four  months  of  flow  metering,  which  is  consistent  with 

observations in the community, that surcharging has been observed a couple times each 

year. See Appendix B for details. 

IV. Description of Proposed Project Berwyn is limited in design alternatives due to restrictions from MWRD to add capacity into the 

downstream  system.  The  project  focused  on  providing  the  maximum  allowable  additional 

capacity as well as detention and infiltration. 

A. Design Alternatives 

1. New Connection to MWRD Interceptor Providing  a  new  conveyance  sewer  routed  to  the MWRD  Interceptor  along 

Stanley Avenue in the northwest quadrant would provide additional capacity to 

an area that is currently without an overland flow path and subject to additional 

upstream  tributary  flow  from  the  Village  of  Riverside.    This  is  a  crucial 

improvement  for  this  area  of  the  Depot  District  that  would  decrease  the 

frequency of flooding conditions to this drainage area. 

This new connection would allow for the existing brick sewer running along Oak 

Park Ave under the BNSF railroad to be capped and abandoned. This segment of 

kellypage
Highlight
Page 16: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

11  

the  sewer  is  severely  damaged  and  not  functioning  properly.  Replacing  this 

sewer  would  cost  the  City  of  Berwyn  considerable  expense  related  to 

constructability issues.  

The diversion of  the area north of  the BNSF  to  the MWRD  Interceptor would 

increase available capacity  in the existing sewer on Oak Park Avenue south of 

the railroad and would allow for a new sewer connection along Windsor Avenue 

from  Kenilworth  Ave  to  Oak  Park  Ave.  This  connection  would  help  reduce 

observed flooding along Windsor Avenue and would reduce Tributary A, which 

flow south to Ogden Avenue. This connection would also aid in the reallocation 

of Berwyn’s  sewer divides  in order  to balance  the different  systems and  their 

respective outlet capacities. 

See Figure 4: New Conveyance Sewer to MWRD Interceptor. 

2. Relief Sewers to Improve System Balance This  alternative  involves  providing  a  new  connection  along Windsor  Avenue 

between Euclid Avenue and Wesley Avenue as well as upsizing the pipes  from 

Wesley Avenue  to  the  connection  at  East Avenue.  This will  divert  some  area 

from Network B, which aids in balancing the different system outlet capacities. 

3. Line Existing Sewers 

Relining is chosen for rehabilitation when the sewer pipe is currently structurally 

sound, but is showing signs of initial failure such as longitudinal cracking, or pipe 

elongation.  And  ongoing  root  infiltration  problem  can  also  be minimized  or 

eliminated  by  relining  the  pipe and  sealing  the  joints  between  pipe  sections. 

Pipe joints are the main source of entry for roots. 

Relining  is  the  least  inconvenient  for  the  Public  since  there  is  no  restoration 

involved.  Construction  consists  of  working  from  manhole  to  manhole  and 

pulling  a  flexible  polyester  pipe  liner  through  the  existing  pipeline.  Steam  is 

pumped through the  line in order to expand the  lie, then cold water  is flushed 

through  to  harden  the  line,  and  finally  the  laterals  are  cut‐out  by  using  a 

specially designed cutting/camera instrument. 

The  result of  relining  is a  joint‐free pipe with no digging or  replacement. The 

cost of  relining  is  substantially more  than  spot  repairing but  slightly  less  than 

complete  replacement.  The  benefit  is  a  brand  new  pipe  from  manhole  to 

manhole without inconveniencing the public. The City of Berwyn expects to line 

over 400 LF of existing storm sewer within the project area. 

4. Permeable Pavers 

Permeable pavers will be used along Windsor and Stanley Avenues under  the 

parking  lanes  in  order  to  divert  and  store  stormwater  runoff.  These 

improvements  will  be  part  of  another  construction  contract  specific  to 

streetscape  improvements  but  will  work  in  conjunction  with  the  proposed 

sewer design.   

Page 17: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

F311TERRA I • ENGINEERING LTD. 225 W. Ohio Street, 4th Floor Chicago, Illinois 60654 (312) 467-0123 (312) 467-0220 fax

30" SEWER TRIBUTARY TO 5.0' BRICK SEWER.

CROSS-CONNECTED WITH MWRD INTERCEPTOR.

AREA = 6.8 ACRES

24" SEWER TRIBUTARY TO 5.0' BRICK SEWER.

CROSS-CONNECTED WITH MWRD INTERCEPTOR.

AREA = 27.5 ACRES

-s

NEW DROP MH TO MW~ ~ INTERCEPTOR

12'-0" x 13'-4" MWRD v WESTTOWNS

I~ INTERCEP_T_O_R _ ___,

DROP MH CROSS-CONNECT TO MWRD INTERCEPTOR (TYP)

12" SEWER TRIBUTARY TO 7'-6" BRICK SEWER, FLOWING SOUTHEAST AREA = 4.8 ACRES

24" SEWER TRIBUTARY TO 7'-6" BRICK SEWER,

'"'-..,.._..;:~::-; FLOWING SOUTHEAST

48" SEWER TRIBUTARY TO MWRD INTERCEPTOR, FLOWING SOUTH AREA = 44.3 ACRES

DROP MH FOR 15" CROSS-CONNECTS TO MWRD INTERCEPTOR (TYP)

12'-4~" x 13'-9" MWRD WEST TOWNS INTERCEPTOR

AREA = 54.2 ACRES

1.-.--

DROP MH CROSS-CONNECT TO MWRD INTERCEPTOR (TYP)

FIGURE 4: NEW CONVEYANCE SEWER TO MWRD INTERCEPTOR CITY OF BERWYN

Page 18: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

13  

B. Basis for Design of Preferred Alternative Autodesk Storm and Sanitary Analysis  (SSA), a microsimulation modeling package, was 

used  to  analyze  both  the  existing  and  proposed  systems.  It  is  based  on  EPA  SWMM 

engine  and  uses  the  rainfall  parameters  set  forth  by  IDOT  related  to  Northeastern 

Illinois  to  calculate  stormwater  runoff  using  the  Rational Method.  Because  Berwyn’s 

stormwater receiving system is MWRD and is limited to the additional capacity that can 

be added to the MWRD’s system, the program was used as a comparative analysis for 

improvements that can be made to the system to help reduce flooding. 

The current sewer network is currently inadequate to support a 2‐year storm event. The 

proposed improvements to the system will easing flooding in the Depot District area by 

reallocating  existing  drainage  areas  and  providing  better  connectivity  to  the MWRD 

system. It is not possible to use the existing connection to the MWRD Interceptor south 

of Windsor Avenue because it is too small and its inverts are too high. Therefore, a new 

connection north of the railroad at Stanley Avenue is proposed. 

By  implementing Alternatives 1 and 2,  the overall  system become more efficient and 

additional  runoff  is  conveyed  into  the MWRD  Interceptor.  Areas  A,  B,  C,  and  F  are 

affected by the proposed  improvements. The  following table highlights the changes  in 

the areas and flow rate for the 2‐year storm event. 

Table 4 Area and Flow Adjustments 

Drainage Area 

Existing Area (AC) 

Proposed Area (AC) 

Existing Flow (cfs) 

Proposed Flow (cfs) 

A  99.1  96.4 74.80 75.33 

B  121.0  44.3 114.39 90.65 

C  32.9  27.5 50.20 50.26 

F  50.0  47.4 54.43 52.91 

X    87.4 75.10 

 

Significant  impacts can be  seen  in Area B. The existing area north of  the  railroad was 

funneled  into  a  single  pipe  that  crossed  the  railroad  along  Oak  Park  Avenue.  The 

capacity of that system  is constrained by the downstream pipes. By diverting the area 

away  from  the  downstream  constricting  pipe  network,  the  outlet  capacity  of  the 

downstream  pipes  is  not  significantly  altered,  however  the  contributing  area  is 

significantly decreased thereby increasing the efficiency of the system. Therefore, even 

though the contributing area  in Drainage Area B was reduced by 63%, the system flow 

was only reduced by 21%. Flooding at inlets will be reduced as demand on the system is 

also reduced. 

Overall, the system capacity will be increased by 50.4 cfs, or 14.3%, for the same total 

acreage. Existing and proposed hydraulic reports can be found in Appendices C and D. 

C. Project Probable Opinion of Costs Estimate of construction costs for the project can be broken down in the following table: 

Page 19: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

14  

Table 5 Estimate of Construction Costs 

    Estimated Cost  

Design Engineering   $               170,000  

Construction Engineering   $               232,500  

Construction   $           2,325,000  

Contingency (10%)   $               272,500  

TOTAL   $           3,000,000  

 

V. Environmental Impacts A  Preliminary  Environmental  Site  Assessment  (PESA)  was  conducted  to  identify  potential 

environmental  impacts  in  the  project  area.  An  environmental  survey  is  being  conducted  to 

formally  document  possible  impacts  related  to;  rare  and  endangered  species,  historic  and 

cultural resources, prime agricultural  land, air and water quality, recreational areas, wetlands, 

floodplains and other sensitive environmental areas.  

A. Rare and Endangered Species Rare  and  endangered  species  do  not  currently  inhabit  the  City’s  Depot  District; 

therefore no significant environmental impact is expected for this category. 

B. Historic and Cultural Resources The Depot District is comprised of residential and commercial buildings, many of which 

are  over  50  years  old.  The majority  of  the  proposed  construction work  is within  the 

existing City right‐of‐way and below grade. Significant impacts upon the existing historic 

buildings are not anticipated. 

C. Prime Agricultural Land Berwyn  is a  landlocked non‐agricultural community zoned  for business and residential 

purposes.  There  is  no  prime  agricultural  land;  therefore  no  significant  environmental 

impact is expected for this category. 

D. Air and Water Quality The proposed  improvements pose no  significant environmental  impacts upon  air  and 

water quality in the Depot District. 

E. Recreational Areas There  is a pocket park  located on the southeast corner at the  intersection of Windsor 

Avenue and Kenilworth Avenue. Sewer improvements at this intersection will be located 

within  the  street  right‐of‐way below grade and no  significant environmental  impact  is 

expected for this category. 

F. Wetlands Wetlands are not currently delineated within the Depot District; therefore no significant 

environmental impact is expected for this category. 

Page 20: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Wastewater Facility Plan City of Berwyn, IL 

15  

G. Other Sensitive Environmental Areas Several  recognized  environmental  conditions  (RECs)  were  found  along  the  project 

corridor. These  include auto  repair  facilities, underground  storage  tanks, dry cleaners, 

and a printing shop.  

A  Preliminary  Site  Investigation  (PSI) will  be  conducted  in  the  detailed  design  phase  of  the 

project in order to determine the nature of disposal of special or non‐special wastes generated 

during  linear excavation or the extent of additional required site remediation,  if any, required. 

See Appendix E  for  table and map of RECs  from  the PESA. Adequate measures will be  taken 

during  the  design  and  construction  that  will  mitigate  or  minimize  negative  environmental 

impacts. The disposal of construction debris will  follow guidelines and regulations specified by 

the Illinois Environmental Protection Agency.  

VI. Implementation Plan The Depot District Sewer  Improvements project  is expected to begin construction  in March of 

2015 and completed by October of 2015.  

The project area has undergone  sewer  televising,  sewer cleaning, and  root cutting  in  sewers, 

catch  basing  and  manhole  debris  removal  in  2014.    Regular  maintenance  in  this  area  is 

scheduled again in 2024 and 2034. Costs would be $26,300 in 2024 and $29,500 in 2034.   Sewer 

spot repairs and manhole/catch basin repairs will continue to be addressed as needed and as 

deemed necessary after cleaning and televising of the area. 

The City has currently identified approximately $8 million in proposed water and sewer system 

projects  to  take place  in 2015 and 2016.   This Facilities Plan only details  the proposed  sewer 

improvements.  The Anticipated Project Expenditures table outlines a 20 year period of loans to 

be obtained  from  the  IEPA’s Revolving  Fund Program which would  fund both  the water and 

sewer system projects scheduled for the City of Berwyn. 

The Anticipated Project Expenditures  table outlines  the  financial  schedule  for  the duration of 

the  loan.    Loan  payments  and  O,M&R  costs  will  be  through  the  City’s  Utilities  Fund.  The 

Operational & Maintenance Plan for the City of Berwyn can be found in Appendix F. 

VII. Rate Structure The  City  of  Berwyn’s  sewer  charge  system  can  be  found  in  Chapter  1048  of  its  codified 

ordinances.     Sewer charges are a standard rate  for residential dwellings, rendered  four times 

per year.  Rates for residential units are broken up into four classes; one to four dwelling units.  

Commercial and Religious or Educational  sewer  service  charges  shall be  rendered monthly  in 

conjunction with the water billing.   The commercial rate  is a minimum charge of $1.68 for the 

first 1,000 cubic foot plus $0.16 per 100 cubic feet per month. 

Per City ordinance, each and every rate and figure contained in the sewer charge chapter shall 

be adjusted annually by 5%, to be effective on January 1 of each fiscal year. 

See Appendix G for the rate structure approved per ordinance for the duration of the loan.  

Page 21: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix A  

MWRD Historical Flows    

Page 22: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

0.00

50.00

100.00

150.00

200.00

250.00

300.00

350.00

400.00

Tim

e

West Towns Flow at 42nd and East Ave

Page 23: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

0.00

1.00

2.00

3.00

4.00

5.00

6.00

Dep

th

Date

West Towns Flow at 42nd and East Ave

Page 24: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix B  

City of Berwyn Usage Charges Report    

Page 25: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

01/02/2014 11:40 7087498520 WATER PAGE 01/El2

Usage Charges Report Billing Date Range 10/01/12,· 09/30/13

All RepotMg Profiles Sumr·t;>ry Ustlng

Met~·~T~yps~~~------------------------------------------~~~a~u~~•~r.~~~~~·l'7m~p~tlo~n~----------------~B~IU~ed~Co~n~5i' ~~p~u~o~n _________________ -~~'~~~~-! 1/ l .- M~~r !00• 160,8!;1 16,085,100 729,517.70 I ' MO)~er IIJOx 79,200 7,9'-0,000 3GO.ll9.15 2" Mt! :~ IOOx 102,758 10,279,000 ~~. 198.52 l " Mt•:f)< 100• 59.~02 5,990,200 258,!04.67 JW ~ IC!ter !IJOx 229,Dl8 2t983,800 1,003,76858 ~· M1t-cr 10M• 12,395 9,606,900 ~ 7.0. 783.80 5/8' ~lcter JOOa g81,4Sl 98,345,100 4,330,979.7'. r,•· M1~ cr IOOO• 1,803 1,903,000 59,110 96 Oth<'nfJ>.'t'OCS • 7.39,622.10

>l~~r TypP. Tt~nl•. 1,(>30,198 173,093,100 F ,B58,315.80 C:onSlmotlctl Mtustm<!ntJ ------------"'!"'!~~0

Net 1,630,198

~iYQ~7--~--------------------------------------------~~~u~~c~on~'.~um~~e~~------------------~N~I~~d~C~on~w~m~~~~~·----------------- ---~C~~~~~~~~ """"""'2 Fi~t 47,606.16 Sl!wet:3 fl8l 19,985.84 :;,.W(II·4 F13t M51.35 ~•C:~Jmmertk"'i ~30,877 52.952,200 9~7.47.76

5tWCI~Sir\llk: F"'"ll.:,v ____________________ _.----------- 16&,376. 10 watP.I!f..orN•orell>l 413,326 ~9,69~.500 l,241,739.J8 w.,tr.o•fln-\1 W~tehMunll:loal W~ttr~~l'~":td~I\H.,f

W;~tr.ttSc~s.Patk!, lc Clllltthr:~ UllmniJ:r'led Con~~ptlon ,., .•

158 1 ~.8GO 619.36 5,~90 559,000 21,916.72

1,181,736 l\8,!73,600 5.152,299.12 20,7.67. 3,732,600 110,0?3.41 9 120 912 000 1).00

Rol'e Type T~~·''~ N/11 •• N/A •• $7,858,315.80 s•nce any ~lven r.onQ •nntloo '"" ,,., wou!Jh multiple oMr<. ltr,ll':n~ltlg nn your r.ann9u"'tlon, til'! conunpltM numb'!rs In rhls se(\lnll m11y 11<1( ~ O<lt t'l Nhcr s~tlon s or otto·< ~Pill ts.

• • • IJnrMtchEd con~.,mtllli'-"' n~=-c•t.s ~onsumpnons tMti\Jinu ''"' melt'.1 trne I meMu....,,•nf typ<: fl1to:r; ~nd can 1~ cll,piil'(<:ll wt~<:n d1~ fotlnwl119 v.cn~rfos o<Xur. 1. Unlliii<:<J r,nn&llmPOOn exist~. Unl~lk'<l CM~olonptJun or.<:• II'S v1hen •n AC1111P. "~'(:!'~~~~chad to IMrtiY~ '~"'~ 1 ~ctount rt'JI!It•r.. •r:otl!le nnd Is alowed Vlr'tluql> l~lll o lg . This <ill> be au<Hf<!/1. l. Some lllstorlc.,l tx/1\\>I"'Diillns (fl1e / .0) could not oe '"~"""-''to ch~roes you Oft' r~-r.!UOlJ. 1111s lo mo!ri'; ttue I<> bill cala.li!tiOI" U.'!"'J P?~d cv~n tltOI"ll> d>'-Y were •J'rly rllc it:lual Mn:;umD\kln thilt was b>:led WM l~llt•rl, ~nrl l h~ t'lrn!tt coosumotron w~~ •lev<'f ~i'llculote<l . 3. 1'11e~ were (.nf\'IJIII(IIIo~s t~~t matt:hea tM sellv.tcO met~r l.y,.: I nv:~sorem~nt W~P. n~~r::. but wcte not tit~lto (.~ol!)es t11at m•rrlled u-:: ..:tcctr.~ ~~m 1 t)l~r~• CAII!!I"'Y !l~rs.

Run b~.Woggc. Mole on 11/l~/2013 I~ :U:J9 PM P~a- I or 2

Page 26: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

01/02/2014

~~c CareaOIV Sewt 'l '

wa~.--

llnm< '-'~•11 Co!1sumr>t10n ·•-•

11:40 7087498520

Aaual Consumr"o" ~Jo,an

1,621,072 9 120

NIA • •

WATER PAGE 02/02

Usage Charges R1eport Billing Date Range 10/0l/12, · 09/ 30/13

All Rcport:-ng Profiles Sumn tary Listing

Slned r.onS<•mrtlon 52,952.200

1.72, 180,500 912,000

N/A -.•

331,667.51 7,5Z6,648.2g

0.00 $7.858,315 .80

· • · 1Jnrnatdl'!f.l t'.l~;u•n~Uon tl!prev.n~ r.oM11mp11ons tMt fv\11111 t11e mct~r tvpe I •Y~r.·l~"l'<:"'"ut typ~ nners ~nd t <l' l rx: ~llilleVflO wntn 1M foll<lWintj '"''""'o~ .,.;r.u r: .I. lillhl lt.<l con!'<lmptlon O'IStt,. lJ110Uied consurT'()tiQn nCC~Jrs wMn ~n •.11:lj•~ llleH'J mt.1c11ed to lnilCtlvr. ~~·"'''~ 1 acrDunt re91stcr.; 11:;.:19~ nnd IS allow~d l11rot!9h billing. Th~ C~ ll 110 ""~'ten 2. ~.ome hlstoriGII c ~••:"'"lfll!On~ (pe 7 .0) c~u~l nm lle m• tchr.<l '" t;hllr~ you ~1e re<~uc~~f>;l. Thl:: I< mo•Uy <luo to hiH '"'" ''~~'11\' bc!lng posttn! •:""-nlhlluol• t~I!:Y w~ dirt\'. The actll~l consumptb)J' thnt ..YO!\ o~lt!rJ wos f;~lletJ. MKJ the m r";(t f.Of'\f Ur'll l)tlo" ~as M ur.:r rcC:i' lr.ulnttd. ~- , ,...., were CD~'IJmptlt'll.'\ lhA( matched tlr. l'l':lo!<:IIXI meter typr. / lnr.-l ~llrP.mfflt rm• nilE! I , but W<;<'l: Mt dcd to Cl1a!'fji!S th ~t m~~Md 11 '1<! !.elected R., te I 01~(91! c~roqnr, 11111:~ .

~fed COnSilmPtll;'" by Met.erType I II "' Mtn:r l iXl• 2' ~>~tr:r .tOO. m ···M-.tt<r lOOx SIO' ' Moter !Oillr

.1\au~! CoMtln1pUon 93

292 -1n1 ~31

l)n~ltl il/1 consumptoo r~·~lt; 629

Consumpti<Jn Atllt~lrt!t!lt~------------~~0 Net ~7.9

Page 27: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix C  

Hydraulic Reports ‐ Existing    

Page 28: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel A.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 29: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.60 0.9000 0.36 0.32 0.19 2.33 0 00:05:002 Sub-02 1.40 0.9000 0.36 0.32 0.45 5.44 0 00:05:003 Sub-03 0.65 0.9000 0.36 0.32 0.21 2.53 0 00:05:004 Sub-05 27.00 0.8200 0.82 0.67 18.14 72.62 0 00:15:005 Sub-06 32.90 0.7000 0.82 0.57 18.88 75.54 0 00:15:006 Sub-08 11.70 0.8200 0.61 0.50 5.80 34.84 0 00:10:007 Sub-09 13.30 0.8200 0.61 0.50 6.60 39.60 0 00:10:008 Sub-10 11.50 0.7000 0.61 0.42 4.88 29.23 0 00:10:00

Page 30: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-09 375.44 605.90 0.00 604.90 0.00 1.00 0.2700 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-10 335.73 604.90 0.00 604.75 0.00 0.15 0.0400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-11 343.34 604.75 0.00 604.16 0.00 0.59 0.1700 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-12 648.04 604.16 0.00 603.90 0.00 0.26 0.0400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-13 171.93 603.90 0.00 603.50 0.00 0.40 0.2300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-14 158.76 603.50 0.00 603.16 0.00 0.34 0.2100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-15 498.16 603.16 0.00 602.08 0.00 1.08 0.2200 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-16 586.33 602.08 0.00 601.49 0.00 0.59 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-17 68.28 601.49 0.00 601.42 4.51 0.07 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 31: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-09 3.82 0 01:31 1.84 2.08 4.86 1.29 1.00 1.00 101.00 SURCHARGED2 Link-10 7.08 0 01:18 1.37 5.19 5.77 0.97 1.25 1.00 92.00 SURCHARGED3 Link-11 11.59 0 01:09 4.35 2.66 6.56 0.87 1.50 1.00 86.00 SURCHARGED4 Link-12 25.28 0 00:19 4.53 5.58 8.05 1.34 2.00 1.00 66.00 SURCHARGED5 Link-13 26.81 0 00:59 10.91 2.46 8.53 0.34 2.00 1.00 66.00 SURCHARGED6 Link-14 52.80 0 00:20 18.98 2.78 10.76 0.25 2.50 1.00 60.00 SURCHARGED7 Link-15 48.84 0 00:25 19.10 2.56 9.95 0.83 2.50 1.00 60.00 SURCHARGED8 Link-16 52.45 0 00:20 16.78 3.13 8.83 1.11 2.75 1.00 53.00 SURCHARGED9 Link-17 74.80 0 00:10 16.93 4.42 12.68 0.09 2.68 0.98 0.00 > CAPACITY

Page 32: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel A.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 33: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.60 0.9000 0.54 0.49 0.29 3.50 0 00:05:002 Sub-02 1.40 0.9000 0.54 0.49 0.68 8.17 0 00:05:003 Sub-03 0.65 0.9000 0.54 0.49 0.32 3.79 0 00:05:004 Sub-05 27.00 0.8200 1.21 0.99 26.78 107.16 0 00:15:005 Sub-06 32.90 0.7000 1.21 0.85 27.87 111.47 0 00:15:006 Sub-08 11.70 0.8200 0.90 0.74 8.62 51.72 0 00:10:007 Sub-09 13.30 0.8200 0.90 0.74 9.80 58.79 0 00:10:008 Sub-10 11.50 0.7000 0.90 0.63 7.23 43.39 0 00:10:00

Page 34: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-09 375.44 605.90 0.00 604.90 0.00 1.00 0.2700 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-10 335.73 604.90 0.00 604.75 0.00 0.15 0.0400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-11 343.34 604.75 0.00 604.16 0.00 0.59 0.1700 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-12 648.04 604.16 0.00 603.90 0.00 0.26 0.0400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-13 171.93 603.90 0.00 603.50 0.00 0.40 0.2300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-14 158.76 603.50 0.00 603.16 0.00 0.34 0.2100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-15 498.16 603.16 0.00 602.08 0.00 1.08 0.2200 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-16 586.33 602.08 0.00 601.49 0.00 0.59 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-17 68.28 601.49 0.00 601.42 4.51 0.07 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 35: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-09 4.00 0 02:03 1.84 2.17 5.10 1.23 1.00 1.00 137.00 SURCHARGED2 Link-10 7.83 0 01:45 1.37 5.73 6.38 0.88 1.25 1.00 127.00 SURCHARGED3 Link-11 14.64 0 00:30 4.35 3.36 8.28 0.69 1.50 1.00 120.00 SURCHARGED4 Link-12 34.39 0 00:20 4.53 7.59 10.95 0.99 2.00 1.00 90.00 SURCHARGED5 Link-13 27.44 0 01:18 10.91 2.51 8.73 0.33 2.00 1.00 89.00 SURCHARGED6 Link-14 68.69 0 00:21 18.98 3.62 13.99 0.19 2.50 1.00 82.00 SURCHARGED7 Link-15 59.84 0 00:26 19.10 3.13 12.19 0.68 2.50 1.00 81.00 SURCHARGED8 Link-16 63.43 0 00:20 16.78 3.78 10.68 0.91 2.75 1.00 73.00 SURCHARGED9 Link-17 91.51 0 00:12 16.93 5.40 15.41 0.07 2.75 1.00 10.00 SURCHARGED

Page 36: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel A.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 37: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.60 0.9000 0.91 0.82 0.49 5.90 0 00:05:002 Sub-02 1.40 0.9000 0.91 0.82 1.15 13.76 0 00:05:003 Sub-03 0.65 0.9000 0.91 0.82 0.53 6.39 0 00:05:004 Sub-05 27.00 0.8200 2.05 1.68 45.39 181.55 0 00:15:005 Sub-06 32.90 0.7000 2.05 1.44 47.21 188.85 0 00:15:006 Sub-08 11.70 0.8200 1.52 1.25 14.58 87.44 0 00:10:007 Sub-09 13.30 0.8200 1.52 1.25 16.57 99.40 0 00:10:008 Sub-10 11.50 0.7000 1.52 1.06 12.22 73.37 0 00:10:00

Page 38: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-09 375.44 605.90 0.00 604.90 0.00 1.00 0.2700 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-10 335.73 604.90 0.00 604.75 0.00 0.15 0.0400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-11 343.34 604.75 0.00 604.16 0.00 0.59 0.1700 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-12 648.04 604.16 0.00 603.90 0.00 0.26 0.0400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-13 171.93 603.90 0.00 603.50 0.00 0.40 0.2300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-14 158.76 603.50 0.00 603.16 0.00 0.34 0.2100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-15 498.16 603.16 0.00 602.08 0.00 1.08 0.2200 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-16 586.33 602.08 0.00 601.49 0.00 0.59 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-17 68.28 601.49 0.00 601.42 4.51 0.07 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 39: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-09 4.19 0 03:02 1.84 2.28 5.34 1.17 1.00 1.00 201.00 SURCHARGED2 Link-10 9.19 0 00:50 1.37 6.73 7.49 0.75 1.25 1.00 190.00 SURCHARGED3 Link-11 19.91 0 00:33 4.35 4.57 11.27 0.51 1.50 1.00 180.00 SURCHARGED4 Link-12 50.44 0 00:21 4.53 11.13 16.06 0.67 2.00 1.00 137.00 SURCHARGED5 Link-13 26.81 0 01:54 10.91 2.46 8.53 0.34 2.00 1.00 133.00 SURCHARGED6 Link-14 99.38 0 00:21 18.98 5.24 20.25 0.13 2.50 1.00 125.00 SURCHARGED7 Link-15 78.96 0 00:28 19.10 4.13 16.09 0.52 2.50 1.00 122.00 SURCHARGED8 Link-16 81.37 0 00:24 16.78 4.85 13.70 0.71 2.75 1.00 108.00 SURCHARGED9 Link-17 122.52 0 00:14 16.93 7.24 20.63 0.06 2.75 1.00 35.00 SURCHARGED

Page 40: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel B.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 41: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.78 0.9000 0.36 0.32 0.25 3.03 0 00:05:002 Sub-02 0.66 0.9000 0.36 0.32 0.21 2.57 0 00:05:003 Sub-03 1.01 0.9000 0.36 0.32 0.33 3.93 0 00:05:004 Sub-04 0.90 0.9000 0.36 0.32 0.29 3.50 0 00:05:005 Sub-05 0.61 0.9000 0.36 0.32 0.20 2.37 0 00:05:006 Sub-06 1.20 0.9000 0.36 0.32 0.39 4.67 0 00:05:007 Sub-07 3.70 0.8200 0.36 0.30 1.09 13.11 0 00:05:008 Sub-08 1.50 0.9000 0.36 0.32 0.49 5.83 0 00:05:009 Sub-09 13.50 0.8200 0.61 0.50 6.70 40.19 0 00:10:00

10 Sub-10 8.70 0.7000 0.61 0.42 3.69 22.11 0 00:10:0011 Sub-11 10.10 0.8200 0.61 0.50 5.01 30.07 0 00:10:0012 Sub-14 8.50 0.7000 0.61 0.42 3.60 21.60 0 00:10:0013 Sub-15 7.60 0.8200 0.36 0.30 2.24 26.92 0 00:05:0014 Sub-16 9.20 0.7000 0.36 0.25 2.32 27.82 0 00:05:0015 Sub-17 41.40 0.8200 0.82 0.67 27.82 111.35 0 00:15:0016 Sub-18 3.80 0.7000 0.61 0.42 1.61 9.66 0 00:10:0017 Sub-19 7.30 0.8200 0.36 0.30 2.15 25.86 0 00:05:0018 Sub-20 0.58 0.9000 0.36 0.32 0.19 2.26 0 00:05:00

Page 42: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 366.85 605.00 0.00 604.16 0.00 0.84 0.2300 CIRCULAR 12.000 12.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-02 389.30 604.16 0.00 603.60 0.00 0.56 0.1400 CIRCULAR 15.000 15.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-03 882.80 603.60 0.00 602.50 0.00 1.10 0.1200 CIRCULAR 18.000 18.000 0.0150 0.5000 0.5000 0.0000 0.00 No 14 Link-04 361.55 602.50 0.00 602.25 0.00 0.25 0.0700 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 15 Link-05 351.60 602.25 0.00 601.16 0.00 1.09 0.3100 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 16 Link-06 648.01 601.16 0.00 597.50 0.00 3.66 0.5600 CIRCULAR 33.000 33.000 0.0150 0.5000 0.5000 0.0000 0.00 No 17 Link-07 299.06 597.50 0.00 597.30 0.00 0.20 0.0700 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 18 Link-08 247.32 597.30 0.00 597.08 0.00 0.22 0.0900 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 19 Link-09 765.08 597.08 0.00 596.34 0.00 0.74 0.1000 CIRCULAR 48.000 48.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

10 Link-10 188.87 596.34 0.00 596.16 0.00 0.18 0.1000 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 111 Link-11 1136.68 596.16 0.00 594.67 0.00 1.49 0.1300 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 112 Link-13 166.95 601.42 0.26 601.16 -0.26 0.26 0.1600 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 113 Link-14 320.84 601.92 0.50 601.42 -0.50 0.50 0.1600 CIRCULAR 27.000 27.000 0.0130 0.5000 0.5000 0.0000 0.00 No 114 Link-15 347.90 602.47 0.55 601.92 -0.55 0.55 0.1600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 115 Link-16 324.63 604.50 0.00 602.88 0.63 1.62 0.5000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 116 Link-17 37.53 594.67 0.00 594.50 13.50 0.17 0.4500 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 43: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 3.05 0 00:05 1.48 2.06 3.88 1.58 1.00 1.00 51.00 SURCHARGED2 Link-02 5.46 0 00:05 2.12 2.57 4.68 1.39 1.25 1.00 54.00 SURCHARGED3 Link-03 3.66 0 00:05 3.21 1.14 2.08 7.07 1.50 1.00 55.00 SURCHARGED4 Link-04 15.75 0 00:05 3.61 4.36 7.52 0.80 1.75 1.00 56.00 SURCHARGED5 Link-05 16.40 0 00:04 7.65 2.15 6.82 0.86 1.75 1.00 57.00 SURCHARGED6 Link-06 46.42 0 00:03 34.45 1.35 8.07 1.34 2.75 1.00 56.00 SURCHARGED7 Link-07 47.84 0 00:04 14.95 3.20 6.77 0.74 3.00 1.00 58.00 SURCHARGED8 Link-08 53.04 0 00:04 17.24 3.08 7.50 0.55 3.00 1.00 54.00 SURCHARGED9 Link-09 94.95 0 00:05 38.72 2.45 8.49 1.50 4.00 1.00 14.00 SURCHARGED

10 Link-10 90.43 0 00:06 44.34 2.04 7.94 0.40 4.00 1.00 12.00 SURCHARGED11 Link-11 114.39 0 00:08 52.01 2.20 10.61 1.79 4.00 1.00 7.00 SURCHARGED12 Link-13 48.22 0 00:03 1.00 48.04 9.86 0.28 2.50 1.00 56.00 SURCHARGED13 Link-14 42.32 0 00:29 0.55 77.40 10.64 0.50 2.25 1.00 57.00 SURCHARGED14 Link-15 49.57 0 00:22 0.38 129.25 15.78 0.37 2.00 1.00 57.00 SURCHARGED15 Link-16 4.69 0 00:57 2.52 1.87 5.98 0.90 1.00 1.00 57.00 SURCHARGED16 Link-17 114.08 0 00:08 96.68 1.18 9.54 0.07 3.60 0.90 0.00 > CAPACITY

Page 44: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel B.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 45: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.78 0.9000 0.54 0.49 0.38 4.55 0 00:05:002 Sub-02 0.66 0.9000 0.54 0.49 0.32 3.85 0 00:05:003 Sub-03 1.01 0.9000 0.54 0.49 0.49 5.89 0 00:05:004 Sub-04 0.90 0.9000 0.54 0.49 0.44 5.25 0 00:05:005 Sub-05 0.61 0.9000 0.54 0.49 0.30 3.56 0 00:05:006 Sub-06 1.20 0.9000 0.54 0.49 0.58 7.00 0 00:05:007 Sub-07 3.70 0.8200 0.54 0.44 1.64 19.66 0 00:05:008 Sub-08 1.50 0.9000 0.54 0.49 0.73 8.75 0 00:05:009 Sub-09 13.50 0.8200 0.90 0.74 9.95 59.67 0 00:10:00

10 Sub-10 8.70 0.7000 0.90 0.63 5.47 32.83 0 00:10:0011 Sub-11 10.10 0.8200 0.90 0.74 7.44 44.64 0 00:10:0012 Sub-14 8.50 0.7000 0.90 0.63 5.35 32.07 0 00:10:0013 Sub-15 7.60 0.8200 0.54 0.44 3.37 40.38 0 00:05:0014 Sub-16 9.20 0.7000 0.54 0.38 3.48 41.73 0 00:05:0015 Sub-17 41.40 0.8200 1.21 0.99 41.07 164.31 0 00:15:0016 Sub-18 3.80 0.7000 0.90 0.63 2.39 14.34 0 00:10:0017 Sub-19 7.30 0.8200 0.54 0.44 3.23 38.79 0 00:05:0018 Sub-20 0.58 0.9000 0.54 0.49 0.28 3.38 0 00:05:00

Page 46: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 366.85 605.00 0.00 604.16 0.00 0.84 0.2300 CIRCULAR 12.000 12.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-02 389.30 604.16 0.00 603.60 0.00 0.56 0.1400 CIRCULAR 15.000 15.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-03 882.80 603.60 0.00 602.50 0.00 1.10 0.1200 CIRCULAR 18.000 18.000 0.0150 0.5000 0.5000 0.0000 0.00 No 14 Link-04 361.55 602.50 0.00 602.25 0.00 0.25 0.0700 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 15 Link-05 351.60 602.25 0.00 601.16 0.00 1.09 0.3100 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 16 Link-06 648.01 601.16 0.00 597.50 0.00 3.66 0.5600 CIRCULAR 33.000 33.000 0.0150 0.5000 0.5000 0.0000 0.00 No 17 Link-07 299.06 597.50 0.00 597.30 0.00 0.20 0.0700 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 18 Link-08 247.32 597.30 0.00 597.08 0.00 0.22 0.0900 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 19 Link-09 765.08 597.08 0.00 596.34 0.00 0.74 0.1000 CIRCULAR 48.000 48.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

10 Link-10 188.87 596.34 0.00 596.16 0.00 0.18 0.1000 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 111 Link-11 1136.68 596.16 0.00 594.67 0.00 1.49 0.1300 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 112 Link-13 166.95 601.42 0.26 601.16 -0.26 0.26 0.1600 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 113 Link-14 320.84 601.92 0.50 601.42 -0.50 0.50 0.1600 CIRCULAR 27.000 27.000 0.0130 0.5000 0.5000 0.0000 0.00 No 114 Link-15 347.90 602.47 0.55 601.92 -0.55 0.55 0.1600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 115 Link-16 324.63 604.50 0.00 602.88 0.63 1.62 0.5000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 116 Link-17 37.53 594.67 0.00 594.50 13.50 0.17 0.4500 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 47: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 3.69 0 01:34 1.48 2.50 4.70 1.30 1.00 1.00 97.00 SURCHARGED2 Link-02 5.88 0 00:04 2.12 2.77 5.03 1.29 1.25 1.00 96.00 SURCHARGED3 Link-03 7.24 0 01:25 3.21 2.25 4.10 3.59 1.50 1.00 91.00 SURCHARGED4 Link-04 15.67 0 00:04 3.61 4.34 7.58 0.79 1.75 1.00 88.00 SURCHARGED5 Link-05 18.36 0 01:20 7.65 2.40 7.63 0.77 1.75 1.00 79.00 SURCHARGED6 Link-06 49.23 0 00:24 34.45 1.43 8.38 1.29 2.75 1.00 76.00 SURCHARGED7 Link-07 68.23 0 00:20 14.95 4.56 9.65 0.52 3.00 1.00 79.00 SURCHARGED8 Link-08 72.85 0 00:20 17.24 4.23 10.31 0.40 3.00 1.00 75.00 SURCHARGED9 Link-09 110.73 0 00:04 38.72 2.86 9.44 1.35 4.00 1.00 19.00 SURCHARGED

10 Link-10 107.92 0 00:05 44.34 2.43 9.99 0.32 4.00 1.00 17.00 SURCHARGED11 Link-11 130.50 0 00:06 52.01 2.51 10.91 1.74 4.00 1.00 12.00 SURCHARGED12 Link-13 52.22 0 00:02 1.00 52.02 10.75 0.26 2.50 1.00 76.00 SURCHARGED13 Link-14 51.50 0 00:31 0.55 94.19 12.95 0.41 2.25 1.00 76.00 SURCHARGED14 Link-15 63.82 0 00:22 0.38 166.41 20.32 0.29 2.00 1.00 76.00 SURCHARGED15 Link-16 5.09 0 01:24 2.52 2.02 6.48 0.83 1.00 1.00 89.00 SURCHARGED16 Link-17 122.89 0 00:12 96.68 1.27 10.19 0.06 3.67 0.92 0.00 > CAPACITY

Page 48: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel B.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 49: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.78 0.9000 0.91 0.82 0.64 7.67 0 00:05:002 Sub-02 0.66 0.9000 0.91 0.82 0.54 6.49 0 00:05:003 Sub-03 1.01 0.9000 0.91 0.82 0.83 9.93 0 00:05:004 Sub-04 0.90 0.9000 0.91 0.82 0.74 8.85 0 00:05:005 Sub-05 0.61 0.9000 0.91 0.82 0.50 6.00 0 00:05:006 Sub-06 1.20 0.9000 0.91 0.82 0.98 11.79 0 00:05:007 Sub-07 3.70 0.8200 0.91 0.75 2.76 33.13 0 00:05:008 Sub-08 1.50 0.9000 0.91 0.82 1.23 14.74 0 00:05:009 Sub-09 13.50 0.8200 1.52 1.25 16.82 100.90 0 00:10:00

10 Sub-10 8.70 0.7000 1.52 1.06 9.25 55.51 0 00:10:0011 Sub-11 10.10 0.8200 1.52 1.25 12.58 75.49 0 00:10:0012 Sub-14 8.50 0.7000 1.52 1.06 9.04 54.23 0 00:10:0013 Sub-15 7.60 0.8200 0.91 0.75 5.67 68.05 0 00:05:0014 Sub-16 9.20 0.7000 0.91 0.64 5.86 70.33 0 00:05:0015 Sub-17 41.40 0.8200 2.05 1.68 69.59 278.37 0 00:15:0016 Sub-18 3.80 0.7000 1.52 1.06 4.04 24.24 0 00:10:0017 Sub-19 7.30 0.8200 0.91 0.75 5.45 65.37 0 00:05:0018 Sub-20 0.58 0.9000 0.91 0.82 0.48 5.70 0 00:05:00

Page 50: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 366.85 605.00 0.00 604.16 0.00 0.84 0.2300 CIRCULAR 12.000 12.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-02 389.30 604.16 0.00 603.60 0.00 0.56 0.1400 CIRCULAR 15.000 15.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-03 882.80 603.60 0.00 602.50 0.00 1.10 0.1200 CIRCULAR 18.000 18.000 0.0150 0.5000 0.5000 0.0000 0.00 No 14 Link-04 361.55 602.50 0.00 602.25 0.00 0.25 0.0700 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 15 Link-05 351.60 602.25 0.00 601.16 0.00 1.09 0.3100 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 16 Link-06 648.01 601.16 0.00 597.50 0.00 3.66 0.5600 CIRCULAR 33.000 33.000 0.0150 0.5000 0.5000 0.0000 0.00 No 17 Link-07 299.06 597.50 0.00 597.30 0.00 0.20 0.0700 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 18 Link-08 247.32 597.30 0.00 597.08 0.00 0.22 0.0900 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 19 Link-09 765.08 597.08 0.00 596.34 0.00 0.74 0.1000 CIRCULAR 48.000 48.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

10 Link-10 188.87 596.34 0.00 596.16 0.00 0.18 0.1000 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 111 Link-11 1136.68 596.16 0.00 594.67 0.00 1.49 0.1300 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 112 Link-13 166.95 601.42 0.26 601.16 -0.26 0.26 0.1600 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 113 Link-14 320.84 601.92 0.50 601.42 -0.50 0.50 0.1600 CIRCULAR 27.000 27.000 0.0130 0.5000 0.5000 0.0000 0.00 No 114 Link-15 347.90 602.47 0.55 601.92 -0.55 0.55 0.1600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 115 Link-16 324.63 604.50 0.00 602.88 0.63 1.62 0.5000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 116 Link-17 37.53 594.67 0.00 594.50 13.50 0.17 0.4500 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 51: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 4.03 0 00:02 1.48 2.73 5.30 1.15 1.00 1.00 172.00 SURCHARGED2 Link-02 6.68 0 02:28 2.12 3.15 5.59 1.16 1.25 1.00 171.00 SURCHARGED3 Link-03 7.79 0 02:26 3.21 2.42 4.41 3.34 1.50 1.00 159.00 SURCHARGED4 Link-04 16.65 0 00:03 3.61 4.61 7.54 0.80 1.75 1.00 144.00 SURCHARGED5 Link-05 20.59 0 01:54 7.65 2.69 8.56 0.68 1.75 1.00 118.00 SURCHARGED6 Link-06 58.15 0 00:45 34.45 1.69 9.79 1.10 2.75 1.00 111.00 SURCHARGED7 Link-07 71.16 0 00:33 14.95 4.76 10.07 0.49 3.00 1.00 117.00 SURCHARGED8 Link-08 79.92 0 00:28 17.24 4.64 11.31 0.36 3.00 1.00 111.00 SURCHARGED9 Link-09 127.58 0 00:03 38.72 3.30 10.67 1.20 4.00 1.00 64.00 SURCHARGED

10 Link-10 117.44 0 00:04 44.34 2.65 10.71 0.29 4.00 1.00 40.00 SURCHARGED11 Link-11 142.92 0 00:14 52.01 2.75 11.37 1.67 4.00 1.00 21.00 SURCHARGED12 Link-13 64.81 0 00:43 1.00 64.56 13.20 0.21 2.50 1.00 111.00 SURCHARGED13 Link-14 65.24 0 00:35 0.55 119.33 16.41 0.33 2.25 1.00 111.00 SURCHARGED14 Link-15 89.78 0 00:23 0.38 234.07 28.58 0.20 2.00 1.00 111.00 SURCHARGED15 Link-16 5.24 0 02:11 2.52 2.08 6.68 0.81 1.00 1.00 143.00 SURCHARGED16 Link-17 142.92 0 00:14 96.68 1.48 11.65 0.05 3.77 0.94 0.00 > CAPACITY

Page 52: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel C.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 53: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-03 0.95 0.9000 0.36 0.32 0.31 3.69 0 00:05:002 Sub-08 0.95 0.9000 0.36 0.32 0.31 3.69 0 00:05:003 Sub-11 11.10 0.7000 0.36 0.25 2.80 33.57 0 00:05:004 Sub-13 9.60 0.8200 0.82 0.67 6.45 25.82 0 00:15:005 Sub-14 5.20 0.8200 0.36 0.30 1.53 18.42 0 00:05:006 Sub-15 1.60 0.9000 0.61 0.55 0.87 5.23 0 00:10:007 Sub-16 3.50 0.9000 0.69 0.62 2.18 10.93 0 00:12:00

Page 54: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-04 173.05 601.91 0.00 601.83 0.00 0.08 0.0500 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-05 450.97 601.83 0.00 600.83 0.00 1.00 0.2200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-06 174.19 600.83 0.00 600.66 0.00 0.17 0.1000 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-08 701.48 606.25 4.34 604.50 -1.75 1.75 0.2500 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-16 413.03 600.66 0.00 600.27 0.00 0.39 0.0900 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-19 18.99 600.27 0.00 600.25 0.03 0.02 0.1100 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-20 46.01 600.27 0.00 595.73 17.35 4.54 9.8700 Rectangular 60.000 51.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 55: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-04 22.43 0 00:03 4.86 4.61 7.14 0.40 2.00 1.00 21.00 SURCHARGED2 Link-05 20.87 0 00:02 10.65 1.96 7.98 0.94 2.00 1.00 21.00 SURCHARGED3 Link-06 26.49 0 00:10 7.07 3.75 8.43 0.34 2.00 1.00 25.00 SURCHARGED4 Link-08 2.15 0 00:04 0.04 50.51 2.74 4.27 1.00 1.00 16.00 SURCHARGED5 Link-16 29.39 0 00:06 6.95 4.23 12.06 0.57 1.45 0.72 0.00 > CAPACITY6 Link-19 20.81 0 00:07 3.41 6.10 13.77 0.02 1.20 0.80 0.00 > CAPACITY7 Link-20 50.20 0 00:07 836.88 0.06 16.24 0.05 0.73 0.15 0.00 Calculated

Page 56: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel C.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 57: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-03 0.95 0.9000 0.54 0.49 0.46 5.54 0 00:05:002 Sub-08 0.95 0.9000 0.54 0.49 0.46 5.54 0 00:05:003 Sub-11 11.10 0.7000 0.54 0.38 4.20 50.35 0 00:05:004 Sub-13 9.60 0.8200 1.21 0.99 9.52 38.10 0 00:15:005 Sub-14 5.20 0.8200 0.54 0.44 2.30 27.63 0 00:05:006 Sub-15 1.60 0.9000 0.90 0.81 1.29 7.76 0 00:10:007 Sub-16 3.50 0.9000 1.03 0.92 3.23 16.18 0 00:12:00

Page 58: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-04 173.05 601.91 0.00 601.83 0.00 0.08 0.0500 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-05 450.97 601.83 0.00 600.83 0.00 1.00 0.2200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-06 174.19 600.83 0.00 600.66 0.00 0.17 0.1000 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-08 701.48 606.25 4.34 604.50 -1.75 1.75 0.2500 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-16 413.03 600.66 0.00 600.27 0.00 0.39 0.0900 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-19 18.99 600.27 0.00 600.25 0.03 0.02 0.1100 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-20 46.01 600.27 0.00 595.73 17.35 4.54 9.8700 Rectangular 60.000 51.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 59: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-04 23.94 0 00:02 4.86 4.92 7.65 0.38 2.00 1.00 24.00 SURCHARGED2 Link-05 25.72 0 00:02 10.65 2.41 8.68 0.87 2.00 1.00 24.00 SURCHARGED3 Link-06 32.07 0 00:13 7.07 4.54 10.21 0.28 2.00 1.00 27.00 SURCHARGED4 Link-08 2.56 0 00:23 0.04 60.26 3.28 3.56 1.00 1.00 20.00 SURCHARGED5 Link-16 31.59 0 00:07 6.95 4.54 12.77 0.54 1.47 0.73 0.00 > CAPACITY6 Link-19 21.18 0 00:08 3.41 6.21 13.77 0.02 1.22 0.81 0.00 > CAPACITY7 Link-20 52.77 0 00:08 836.88 0.06 16.33 0.05 0.76 0.15 0.00 Calculated

Page 60: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel C.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 61: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-03 0.95 0.9000 0.91 0.82 0.78 9.34 0 00:05:002 Sub-08 0.95 0.9000 0.91 0.82 0.78 9.34 0 00:05:003 Sub-11 11.10 0.7000 0.91 0.64 7.07 84.85 0 00:05:004 Sub-13 9.60 0.8200 2.05 1.68 16.14 64.55 0 00:15:005 Sub-14 5.20 0.8200 0.91 0.75 3.88 46.56 0 00:05:006 Sub-15 1.60 0.9000 1.52 1.37 2.19 13.13 0 00:10:007 Sub-16 3.50 0.9000 1.74 1.56 5.47 27.38 0 00:12:00

Page 62: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-04 173.05 601.91 0.00 601.83 0.00 0.08 0.0500 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-05 450.97 601.83 0.00 600.83 0.00 1.00 0.2200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-06 174.19 600.83 0.00 600.66 0.00 0.17 0.1000 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-08 701.48 606.25 4.34 604.50 -1.75 1.75 0.2500 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-16 413.03 600.66 0.00 600.27 0.00 0.39 0.0900 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-19 18.99 600.27 0.00 600.25 0.03 0.02 0.1100 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-20 46.01 600.27 0.00 595.73 17.35 4.54 9.8700 Rectangular 60.000 51.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 63: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-04 27.78 0 00:02 4.86 5.71 8.84 0.33 2.00 1.00 28.00 SURCHARGED2 Link-05 29.41 0 00:16 10.65 2.76 9.36 0.80 2.00 1.00 28.00 SURCHARGED3 Link-06 33.52 0 00:28 7.07 4.74 10.67 0.27 2.00 1.00 28.00 SURCHARGED4 Link-08 2.72 0 00:30 0.04 64.06 3.82 3.06 1.00 1.00 27.00 SURCHARGED5 Link-16 36.86 0 00:08 6.95 5.30 14.41 0.48 1.52 0.76 0.00 > CAPACITY6 Link-19 21.93 0 00:08 3.41 6.43 13.78 0.02 1.27 0.85 0.00 > CAPACITY7 Link-20 58.78 0 00:08 836.88 0.07 16.66 0.05 0.83 0.17 0.00 Calculated

Page 64: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel D.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 65: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.80 0.9000 0.36 0.32 0.26 3.11 0 00:05:002 Sub-02 4.00 0.9000 0.36 0.32 1.30 15.55 0 00:05:00

Page 66: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 705.83 605.90 0.00 604.49 0.00 1.41 0.2000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-02 85.87 604.49 0.00 604.32 3.65 0.17 0.2000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 67: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 2.80 0 00:02 1.59 1.76 3.63 3.24 1.00 1.00 1436.00 SURCHARGED2 Link-02 7.16 0 00:07 1.59 4.51 9.11 0.16 1.00 1.00 1439.00 SURCHARGED

Page 68: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel D.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 69: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.80 0.9000 0.54 0.49 0.39 4.67 0 00:05:002 Sub-02 4.00 0.9000 0.54 0.49 1.94 23.33 0 00:05:00

Page 70: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 705.83 605.90 0.00 604.49 0.00 1.41 0.2000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-02 85.87 604.49 0.00 604.32 3.65 0.17 0.2000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 71: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 3.18 0 00:02 1.59 2.00 4.22 2.79 1.00 1.00 1437.00 SURCHARGED2 Link-02 7.87 0 00:08 1.59 4.96 10.02 0.14 1.00 1.00 1439.00 SURCHARGED

Page 72: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel D.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 73: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.80 0.9000 0.91 0.82 0.66 7.86 0 00:05:002 Sub-02 4.00 0.9000 0.91 0.82 3.28 39.31 0 00:05:00

Page 74: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 705.83 605.90 0.00 604.49 0.00 1.41 0.2000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-02 85.87 604.49 0.00 604.32 3.65 0.17 0.2000 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 75: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 2.98 0 00:01 1.59 1.87 4.20 2.80 1.00 1.00 1437.00 SURCHARGED2 Link-02 9.34 0 00:08 1.59 5.89 11.89 0.12 1.00 1.00 1439.00 SURCHARGED

Page 76: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel E.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 77: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.60 0.9000 0.36 0.32 0.19 2.33 0 00:05:002 Sub-02 0.53 0.9000 0.36 0.32 0.17 2.06 0 00:05:003 Sub-03 0.45 0.9000 0.36 0.32 0.15 1.75 0 00:05:004 Sub-04 32.90 0.7000 0.93 0.65 21.48 64.48 0 00:20:005 Sub-06 11.90 0.7000 0.36 0.25 3.00 35.99 0 00:05:006 Sub-07 5.10 0.8200 0.36 0.30 1.50 18.07 0 00:05:007 Sub-08 0.80 0.7000 0.36 0.25 0.20 2.42 0 00:05:008 Sub-09 1.90 0.7000 0.36 0.25 0.48 5.75 0 00:05:00

Page 78: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 820.68 604.50 0.00 602.45 0.00 2.05 0.2500 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-02 243.09 602.45 0.00 601.84 0.26 0.61 0.2500 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-03 675.67 601.58 0.00 601.16 0.00 0.42 0.0600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-04 37.80 601.16 0.00 601.00 1.75 0.16 0.4200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-05 345.32 602.83 1.25 601.58 -0.34 1.25 0.3600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-06 694.10 601.92 0.00 601.67 0.00 0.25 0.0400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-07 354.54 601.67 0.00 601.16 0.00 0.51 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 79: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 5.12 0 00:04 3.23 1.59 4.42 3.09 1.25 1.00 1434.00 SURCHARGED2 Link-02 15.50 0 00:03 5.26 2.95 9.38 0.43 1.50 1.00 1437.00 SURCHARGED3 Link-03 17.35 0 00:02 5.64 3.08 5.73 1.97 2.00 1.00 1438.00 SURCHARGED4 Link-04 41.88 0 00:01 14.72 2.85 13.90 0.05 2.00 1.00 1439.00 SURCHARGED5 Link-05 27.41 0 00:23 11.61 2.36 8.72 0.66 2.00 1.00 1437.00 SURCHARGED6 Link-06 22.02 0 00:24 4.29 5.13 7.01 1.65 2.00 1.00 1438.00 SURCHARGED7 Link-07 18.45 0 00:32 8.58 2.15 6.14 0.96 2.00 1.00 1438.00 SURCHARGED

Page 80: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel E.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 81: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.60 0.9000 0.54 0.49 0.29 3.50 0 00:05:002 Sub-02 0.53 0.9000 0.54 0.49 0.26 3.09 0 00:05:003 Sub-03 0.45 0.9000 0.54 0.49 0.22 2.62 0 00:05:004 Sub-04 32.90 0.7000 1.38 0.96 31.68 95.08 0 00:20:005 Sub-06 11.90 0.7000 0.54 0.38 4.50 53.98 0 00:05:006 Sub-07 5.10 0.8200 0.54 0.44 2.26 27.10 0 00:05:007 Sub-08 0.80 0.7000 0.54 0.38 0.30 3.63 0 00:05:008 Sub-09 1.90 0.7000 0.54 0.38 0.72 8.62 0 00:05:00

Page 82: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 820.68 604.50 0.00 602.45 0.00 2.05 0.2500 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-02 243.09 602.45 0.00 601.84 0.26 0.61 0.2500 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-03 675.67 601.58 0.00 601.16 0.00 0.42 0.0600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-04 37.80 601.16 0.00 601.00 1.75 0.16 0.4200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-05 345.32 602.83 1.25 601.58 -0.34 1.25 0.3600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-06 694.10 601.92 0.00 601.67 0.00 0.25 0.0400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-07 354.54 601.67 0.00 601.16 0.00 0.51 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 83: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 5.09 0 01:13 3.23 1.58 4.24 3.23 1.25 1.00 1434.00 SURCHARGED2 Link-02 15.16 0 00:03 5.26 2.88 9.43 0.43 1.50 1.00 1437.00 SURCHARGED3 Link-03 20.26 0 00:35 5.64 3.59 6.45 1.75 2.00 1.00 1438.00 SURCHARGED4 Link-04 43.49 0 00:35 14.72 2.96 13.89 0.05 2.00 1.00 1439.00 SURCHARGED5 Link-05 37.27 0 00:24 11.61 3.21 11.86 0.49 2.00 1.00 1438.00 SURCHARGED6 Link-06 29.06 0 00:25 4.29 6.77 9.25 1.25 2.00 1.00 1438.00 SURCHARGED7 Link-07 23.23 0 00:35 8.58 2.71 7.40 0.80 2.00 1.00 1438.00 SURCHARGED

Page 84: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel E.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 85: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.60 0.9000 0.91 0.82 0.49 5.90 0 00:05:002 Sub-02 0.53 0.9000 0.91 0.82 0.43 5.21 0 00:05:003 Sub-03 0.45 0.9000 0.91 0.82 0.37 4.42 0 00:05:004 Sub-04 32.90 0.7000 2.33 1.63 53.73 161.20 0 00:20:005 Sub-06 11.90 0.7000 0.91 0.64 7.58 90.96 0 00:05:006 Sub-07 5.10 0.8200 0.91 0.75 3.80 45.67 0 00:05:007 Sub-08 0.80 0.7000 0.91 0.64 0.51 6.12 0 00:05:008 Sub-09 1.90 0.7000 0.91 0.64 1.21 14.52 0 00:05:00

Page 86: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 820.68 604.50 0.00 602.45 0.00 2.05 0.2500 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-02 243.09 602.45 0.00 601.84 0.26 0.61 0.2500 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-03 675.67 601.58 0.00 601.16 0.00 0.42 0.0600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-04 37.80 601.16 0.00 601.00 1.75 0.16 0.4200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-05 345.32 602.83 1.25 601.58 -0.34 1.25 0.3600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-06 694.10 601.92 0.00 601.67 0.00 0.25 0.0400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-07 354.54 601.67 0.00 601.16 0.00 0.51 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 87: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 5.61 0 01:42 3.23 1.74 4.57 2.99 1.25 1.00 1435.00 SURCHARGED2 Link-02 16.23 0 00:03 5.26 3.08 9.32 0.43 1.50 1.00 1437.00 SURCHARGED3 Link-03 26.74 0 00:38 5.64 4.74 8.51 1.32 2.00 1.00 1438.00 SURCHARGED4 Link-04 58.46 0 00:38 14.72 3.97 18.61 0.03 2.00 1.00 1439.00 SURCHARGED5 Link-05 55.67 0 00:26 11.61 4.79 17.72 0.32 2.00 1.00 1438.00 SURCHARGED6 Link-06 42.39 0 00:26 4.29 9.87 13.49 0.86 2.00 1.00 1438.00 SURCHARGED7 Link-07 31.72 0 00:38 8.58 3.70 10.10 0.59 2.00 1.00 1439.00 SURCHARGED

Page 88: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel F.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 89: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 29.20 0.7000 0.82 0.57 16.76 67.04 0 00:15:002 Sub-06 4.60 0.7000 0.61 0.42 1.95 11.69 0 00:10:003 Sub-07 6.90 0.8200 0.36 0.30 2.04 24.44 0 00:05:004 Sub-12 9.30 0.8200 0.36 0.30 2.74 32.94 0 00:05:00

Page 90: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 138.98 602.83 0.00 602.62 0.00 0.21 0.1500 CIRCULAR 20.040 20.040 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-15 19.13 602.05 0.04 602.01 -0.04 0.04 0.2100 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-17 402.16 602.62 0.57 602.05 -0.57 0.57 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-18 22.64 602.00 -0.05 600.00 18.80 2.00 8.8300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 91: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 35.05 0 00:21 5.41 6.48 16.07 0.14 1.67 1.00 42.00 SURCHARGED2 Link-15 40.85 0 00:06 1.64 24.98 13.00 0.02 2.00 1.00 7.00 SURCHARGED3 Link-17 31.88 0 00:27 0.36 89.36 10.24 0.65 2.00 1.00 6.00 SURCHARGED4 Link-18 54.43 0 00:06 68.07 0.80 19.36 0.02 1.68 0.84 0.00 Calculated

Page 92: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel F.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 93: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 29.20 0.7000 1.21 0.85 24.73 98.93 0 00:15:002 Sub-06 4.60 0.7000 0.90 0.63 2.89 17.36 0 00:10:003 Sub-07 6.90 0.8200 0.54 0.44 3.06 36.66 0 00:05:004 Sub-12 9.30 0.8200 0.54 0.44 4.12 49.42 0 00:05:00

Page 94: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 138.98 602.83 0.00 602.62 0.00 0.21 0.1500 CIRCULAR 20.040 20.040 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-15 19.13 602.05 0.04 602.01 -0.04 0.04 0.2100 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-17 402.16 602.62 0.57 602.05 -0.57 0.57 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-18 22.64 602.00 -0.05 600.00 18.80 2.00 8.8300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 95: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 44.44 0 00:22 5.41 8.22 20.37 0.11 1.67 1.00 55.00 SURCHARGED2 Link-15 49.54 0 00:06 1.64 30.29 15.77 0.02 2.00 1.00 44.00 SURCHARGED3 Link-17 37.78 0 00:29 0.36 105.90 12.02 0.56 2.00 1.00 32.00 SURCHARGED4 Link-18 61.08 0 00:08 68.07 0.90 21.05 0.02 1.74 0.87 0.00 Calculated

Page 96: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel F.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 97: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 29.20 0.7000 2.05 1.44 41.90 167.61 0 00:15:002 Sub-06 4.60 0.7000 1.52 1.06 4.89 29.35 0 00:10:003 Sub-07 6.90 0.8200 0.91 0.75 5.15 61.79 0 00:05:004 Sub-12 9.30 0.8200 0.91 0.75 6.94 83.28 0 00:05:00

Page 98: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 138.98 602.83 0.00 602.62 0.00 0.21 0.1500 CIRCULAR 20.040 20.040 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-15 19.13 602.05 0.04 602.01 -0.04 0.04 0.2100 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-17 402.16 602.62 0.57 602.05 -0.57 0.57 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-18 22.64 602.00 -0.05 600.00 18.80 2.00 8.8300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 99: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 61.30 0 00:23 5.41 11.34 28.10 0.08 1.67 1.00 76.00 SURCHARGED2 Link-15 74.19 0 00:07 1.64 45.36 23.62 0.01 2.00 1.00 66.00 SURCHARGED3 Link-17 48.77 0 00:33 0.36 136.71 15.52 0.43 2.00 1.00 61.00 SURCHARGED4 Link-18 63.61 0 00:05 68.07 0.93 21.66 0.02 1.77 0.88 0.00 Calculated

Page 100: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix D  

Hydraulic Reports ‐ Proposed    

Page 101: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel A_Proposed.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 102: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 27.00 0.8200 0.82 0.67 18.14 72.62 0 00:15:002 Sub-06 32.90 0.7000 0.82 0.57 18.88 75.54 0 00:15:003 Sub-08 11.70 0.8200 0.61 0.50 5.80 34.84 0 00:10:004 Sub-09 13.30 0.8200 0.61 0.50 6.60 39.60 0 00:10:005 Sub-10 11.50 0.7000 0.61 0.42 4.88 29.23 0 00:10:00

Page 103: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-13 171.93 603.90 0.00 603.50 0.00 0.40 0.2300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-14 158.76 603.50 0.00 603.16 0.00 0.34 0.2100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-15 498.16 603.16 0.00 602.08 0.00 1.08 0.2200 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-16 586.33 602.08 0.00 601.49 0.00 0.59 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-17 68.28 601.49 0.00 601.42 4.51 0.07 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 104: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-13 29.05 0 00:24 10.91 2.66 9.25 0.31 2.00 1.00 63.00 SURCHARGED2 Link-14 61.81 0 00:21 18.98 3.26 12.59 0.21 2.50 1.00 62.00 SURCHARGED3 Link-15 54.10 0 00:27 19.10 2.83 11.02 0.75 2.50 1.00 61.00 SURCHARGED4 Link-16 54.15 0 00:20 16.78 3.23 9.12 1.07 2.75 1.00 59.00 SURCHARGED5 Link-17 75.33 0 00:10 16.93 4.45 12.76 0.09 2.69 0.98 0.00 > CAPACITY

Page 105: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel A_Proposed.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 106: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 27.00 0.8200 1.21 0.99 26.78 107.16 0 00:15:002 Sub-06 32.90 0.7000 1.21 0.85 27.87 111.47 0 00:15:003 Sub-08 11.70 0.8200 0.90 0.74 8.62 51.72 0 00:10:004 Sub-09 13.30 0.8200 0.90 0.74 9.80 58.79 0 00:10:005 Sub-10 11.50 0.7000 0.90 0.63 7.23 43.39 0 00:10:00

Page 107: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-13 171.93 603.90 0.00 603.50 0.00 0.40 0.2300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-14 158.76 603.50 0.00 603.16 0.00 0.34 0.2100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-15 498.16 603.16 0.00 602.08 0.00 1.08 0.2200 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-16 586.33 602.08 0.00 601.49 0.00 0.59 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-17 68.28 601.49 0.00 601.42 4.51 0.07 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 108: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-13 36.84 0 00:25 10.91 3.38 11.73 0.24 2.00 1.00 81.00 SURCHARGED2 Link-14 79.78 0 00:21 18.98 4.20 16.25 0.16 2.50 1.00 80.00 SURCHARGED3 Link-15 66.15 0 00:28 19.10 3.46 13.48 0.62 2.50 1.00 80.00 SURCHARGED4 Link-16 65.26 0 00:20 16.78 3.89 10.99 0.89 2.75 1.00 78.00 SURCHARGED5 Link-17 92.06 0 00:12 16.93 5.44 15.50 0.07 2.75 1.00 10.00 SURCHARGED

Page 109: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel A_Proposed.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 110: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 27.00 0.8200 2.05 1.68 45.39 181.55 0 00:15:002 Sub-06 32.90 0.7000 2.05 1.44 47.21 188.85 0 00:15:003 Sub-08 11.70 0.8200 1.52 1.25 14.58 87.44 0 00:10:004 Sub-09 13.30 0.8200 1.52 1.25 16.57 99.40 0 00:10:005 Sub-10 11.50 0.7000 1.52 1.06 12.22 73.37 0 00:10:00

Page 111: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-13 171.93 603.90 0.00 603.50 0.00 0.40 0.2300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-14 158.76 603.50 0.00 603.16 0.00 0.34 0.2100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-15 498.16 603.16 0.00 602.08 0.00 1.08 0.2200 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-16 586.33 602.08 0.00 601.49 0.00 0.59 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-17 68.28 601.49 0.00 601.42 4.51 0.07 0.1000 CIRCULAR 33.000 33.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 112: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-13 50.76 0 00:27 10.91 4.65 16.16 0.18 2.00 1.00 113.00 SURCHARGED2 Link-14 113.32 0 00:22 18.98 5.97 23.09 0.11 2.50 1.00 112.00 SURCHARGED3 Link-15 86.61 0 00:30 19.10 4.54 17.64 0.47 2.50 1.00 112.00 SURCHARGED4 Link-16 84.53 0 00:35 16.78 5.04 14.23 0.69 2.75 1.00 110.00 SURCHARGED5 Link-17 123.24 0 00:14 16.93 7.28 20.75 0.05 2.75 1.00 51.00 SURCHARGED

Page 113: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel B_Proposed.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 114: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-08 1.50 0.9000 0.36 0.32 0.49 5.83 0 00:05:002 Sub-09 13.50 0.8200 0.61 0.50 6.70 40.19 0 00:10:003 Sub-10 8.70 0.7000 0.61 0.42 3.69 22.11 0 00:10:004 Sub-11 10.10 0.8200 0.61 0.50 5.01 30.07 0 00:10:005 Sub-19 7.30 0.8200 0.36 0.30 2.15 25.86 0 00:05:006 Sub-20 0.58 0.9000 0.36 0.32 0.19 2.26 0 00:05:007 Sub-21 1.40 0.9000 0.36 0.32 0.45 5.44 0 00:05:008 Sub-22 0.65 0.9000 0.36 0.32 0.21 2.53 0 00:05:009 Sub-23 0.60 0.9000 0.36 0.32 0.19 2.33 0 00:05:00

Page 115: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-08 247.32 597.30 0.00 597.08 0.00 0.22 0.0900 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-09 765.08 597.08 0.00 596.34 0.00 0.74 0.1000 CIRCULAR 48.000 48.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-10 188.87 596.34 0.00 596.16 0.00 0.18 0.1000 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-11 1136.68 596.16 0.00 594.67 0.00 1.49 0.1300 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-17 37.53 594.67 0.00 594.50 13.50 0.17 0.4500 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-19 375.44 605.90 0.00 604.90 0.00 1.00 0.2700 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-20 335.73 604.90 0.00 604.75 0.00 0.15 0.0400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-21 343.34 604.75 0.00 604.16 0.00 0.59 0.1700 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-22 338.90 604.16 0.00 603.25 0.00 0.91 0.2700 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

10 Link-24 321.73 603.25 0.00 602.00 4.70 1.25 0.3900 CIRCULAR 36.000 36.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 116: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-08 17.52 0 00:08 17.24 1.02 2.48 1.66 3.00 1.00 11.00 SURCHARGED2 Link-09 47.04 0 00:07 38.72 1.21 4.38 2.91 4.00 1.00 6.00 SURCHARGED3 Link-10 42.33 0 00:13 44.34 0.95 3.70 0.85 4.00 1.00 7.00 SURCHARGED4 Link-11 90.65 0 00:10 52.01 1.74 7.34 2.58 3.99 1.00 0.00 > CAPACITY5 Link-17 85.72 0 00:11 96.68 0.89 7.54 0.08 3.39 0.85 0.00 Calculated6 Link-19 3.67 0 00:03 1.84 2.00 4.68 1.34 1.00 1.00 7.00 SURCHARGED7 Link-20 5.10 0 00:04 1.37 3.74 4.58 1.22 1.25 1.00 6.00 SURCHARGED8 Link-21 6.88 0 00:05 4.35 1.58 5.37 1.07 1.25 0.83 0.00 > CAPACITY9 Link-22 6.21 0 00:07 21.25 0.29 5.06 1.12 0.97 0.39 0.00 Calculated

10 Link-24 9.02 0 00:12 41.57 0.22 3.74 1.43 1.62 0.54 0.00 Calculated

Page 117: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel B_Proposed.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 118: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-08 1.50 0.9000 0.54 0.49 0.73 8.75 0 00:05:002 Sub-09 13.50 0.8200 0.90 0.74 9.95 59.67 0 00:10:003 Sub-10 8.70 0.7000 0.90 0.63 5.47 32.83 0 00:10:004 Sub-11 10.10 0.8200 0.90 0.74 7.44 44.64 0 00:10:005 Sub-19 7.30 0.8200 0.54 0.44 3.23 38.79 0 00:05:006 Sub-20 0.58 0.9000 0.54 0.49 0.28 3.38 0 00:05:007 Sub-21 1.40 0.9000 0.54 0.49 0.68 8.17 0 00:05:008 Sub-22 0.65 0.9000 0.54 0.49 0.32 3.79 0 00:05:009 Sub-23 0.60 0.9000 0.54 0.49 0.29 3.50 0 00:05:00

Page 119: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-08 247.32 597.30 0.00 597.08 0.00 0.22 0.0900 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-09 765.08 597.08 0.00 596.34 0.00 0.74 0.1000 CIRCULAR 48.000 48.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-10 188.87 596.34 0.00 596.16 0.00 0.18 0.1000 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-11 1136.68 596.16 0.00 594.67 0.00 1.49 0.1300 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-17 37.53 594.67 0.00 594.50 13.50 0.17 0.4500 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-19 375.44 605.90 0.00 604.90 0.00 1.00 0.2700 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-20 335.73 604.90 0.00 604.75 0.00 0.15 0.0400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-21 343.34 604.75 0.00 604.16 0.00 0.59 0.1700 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-22 338.90 604.16 0.00 603.25 0.00 0.91 0.2700 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

10 Link-24 321.73 603.25 0.00 602.00 4.70 1.25 0.3900 CIRCULAR 36.000 36.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 120: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-08 46.30 0 00:06 17.24 2.69 6.55 0.63 3.00 1.00 15.00 SURCHARGED2 Link-09 73.05 0 00:05 38.72 1.89 5.93 2.15 4.00 1.00 12.00 SURCHARGED3 Link-10 69.99 0 00:06 44.34 1.58 5.64 0.56 4.00 1.00 12.00 SURCHARGED4 Link-11 120.22 0 00:10 52.01 2.31 9.87 1.92 4.00 1.00 8.00 SURCHARGED5 Link-17 120.24 0 00:10 96.68 1.24 10.00 0.06 3.65 0.91 0.00 > CAPACITY6 Link-19 3.97 0 00:02 1.84 2.16 5.15 1.22 1.00 1.00 18.00 SURCHARGED7 Link-20 6.41 0 00:16 1.37 4.70 5.22 1.07 1.25 1.00 14.00 SURCHARGED8 Link-21 10.71 0 00:15 4.35 2.46 6.07 0.94 1.50 1.00 8.00 SURCHARGED9 Link-22 31.16 0 00:14 21.25 1.47 6.35 0.89 2.50 1.00 6.00 SURCHARGED

10 Link-24 36.08 0 00:07 41.57 0.87 6.73 0.80 3.00 1.00 6.00 SURCHARGED

Page 121: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel B_Proposed.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 122: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-08 1.50 0.9000 0.91 0.82 1.23 14.74 0 00:05:002 Sub-09 13.50 0.8200 1.52 1.25 16.82 100.90 0 00:10:003 Sub-10 8.70 0.7000 1.52 1.06 9.25 55.51 0 00:10:004 Sub-11 10.10 0.8200 1.52 1.25 12.58 75.49 0 00:10:005 Sub-19 7.30 0.8200 0.91 0.75 5.45 65.37 0 00:05:006 Sub-20 0.58 0.9000 0.91 0.82 0.48 5.70 0 00:05:007 Sub-21 1.40 0.9000 0.91 0.82 1.15 13.76 0 00:05:008 Sub-22 0.65 0.9000 0.91 0.82 0.53 6.39 0 00:05:009 Sub-23 0.60 0.9000 0.91 0.82 0.49 5.90 0 00:05:00

Page 123: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-08 247.32 597.30 0.00 597.08 0.00 0.22 0.0900 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-09 765.08 597.08 0.00 596.34 0.00 0.74 0.1000 CIRCULAR 48.000 48.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-10 188.87 596.34 0.00 596.16 0.00 0.18 0.1000 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-11 1136.68 596.16 0.00 594.67 0.00 1.49 0.1300 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-17 37.53 594.67 0.00 594.50 13.50 0.17 0.4500 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 16 Link-19 375.44 605.90 0.00 604.90 0.00 1.00 0.2700 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 17 Link-20 335.73 604.90 0.00 604.75 0.00 0.15 0.0400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-21 343.34 604.75 0.00 604.16 0.00 0.59 0.1700 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-22 338.90 604.16 0.00 603.25 0.00 0.91 0.2700 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

10 Link-24 321.73 603.25 0.00 602.00 4.70 1.25 0.3900 CIRCULAR 36.000 36.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 124: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-08 73.44 0 00:21 17.24 4.26 10.39 0.40 3.00 1.00 23.00 SURCHARGED2 Link-09 92.56 0 00:20 38.72 2.39 7.37 1.73 4.00 1.00 19.00 SURCHARGED3 Link-10 109.87 0 00:20 44.34 2.48 8.74 0.36 4.00 1.00 17.00 SURCHARGED4 Link-11 136.67 0 00:13 52.01 2.63 10.88 1.74 4.00 1.00 14.00 SURCHARGED5 Link-17 136.67 0 00:13 96.68 1.41 11.19 0.06 3.74 0.93 0.00 > CAPACITY6 Link-19 4.02 0 00:02 1.84 2.19 5.17 1.21 1.00 1.00 43.00 SURCHARGED7 Link-20 7.53 0 00:29 1.37 5.52 6.14 0.91 1.25 1.00 34.00 SURCHARGED8 Link-21 12.83 0 00:24 4.35 2.95 7.26 0.79 1.50 1.00 22.00 SURCHARGED9 Link-22 44.20 0 00:23 21.25 2.08 9.00 0.63 2.50 1.00 18.00 SURCHARGED

10 Link-24 75.94 0 00:22 41.57 1.83 10.76 0.50 3.00 1.00 17.00 SURCHARGED

Page 125: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel C_Proposed.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 126: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-11 11.10 0.7000 0.36 0.25 2.80 33.57 0 00:05:002 Sub-13 9.60 0.8200 0.82 0.67 6.45 25.82 0 00:15:003 Sub-14 5.20 0.8200 0.36 0.30 1.53 18.42 0 00:05:004 Sub-15 1.60 0.9000 0.61 0.55 0.87 5.23 0 00:10:00

Page 127: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-05 450.97 601.83 0.00 600.83 0.00 1.00 0.2200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-06 174.19 600.83 0.00 600.66 0.00 0.17 0.1000 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-16 413.03 600.66 0.00 600.27 0.00 0.39 0.0900 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-19 18.99 600.27 0.00 600.25 0.03 0.02 0.1100 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-20 46.01 600.27 0.00 595.73 17.35 4.54 9.8700 Rectangular 60.000 51.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 128: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-05 21.04 0 00:03 10.65 1.98 8.11 0.93 2.00 1.00 20.00 SURCHARGED2 Link-06 25.84 0 00:10 7.07 3.66 8.23 0.35 2.00 1.00 23.00 SURCHARGED3 Link-16 29.44 0 00:06 6.95 4.24 12.08 0.57 1.45 0.72 0.00 > CAPACITY4 Link-19 20.82 0 00:07 3.41 6.11 13.77 0.02 1.20 0.80 0.00 > CAPACITY5 Link-20 50.26 0 00:07 836.88 0.06 16.24 0.05 0.73 0.15 0.00 Calculated

Page 129: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel C_Proposed.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 130: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-11 11.10 0.7000 0.54 0.38 4.20 50.35 0 00:05:002 Sub-13 9.60 0.8200 1.21 0.99 9.52 38.10 0 00:15:003 Sub-14 5.20 0.8200 0.54 0.44 2.30 27.63 0 00:05:004 Sub-15 1.60 0.9000 0.90 0.81 1.29 7.76 0 00:10:00

Page 131: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-05 450.97 601.83 0.00 600.83 0.00 1.00 0.2200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-06 174.19 600.83 0.00 600.66 0.00 0.17 0.1000 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-16 413.03 600.66 0.00 600.27 0.00 0.39 0.0900 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-19 18.99 600.27 0.00 600.25 0.03 0.02 0.1100 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-20 46.01 600.27 0.00 595.73 17.35 4.54 9.8700 Rectangular 60.000 51.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 132: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-05 25.43 0 00:02 10.65 2.39 8.53 0.88 2.00 1.00 23.00 SURCHARGED2 Link-06 32.11 0 00:13 7.07 4.54 10.22 0.28 2.00 1.00 26.00 SURCHARGED3 Link-16 31.62 0 00:07 6.95 4.55 12.78 0.54 1.47 0.73 0.00 > CAPACITY4 Link-19 21.18 0 00:08 3.41 6.21 13.77 0.02 1.22 0.81 0.00 > CAPACITY5 Link-20 52.80 0 00:08 836.88 0.06 16.33 0.05 0.76 0.15 0.00 Calculated

Page 133: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel C_Proposed.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 134: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-11 11.10 0.7000 0.91 0.64 7.07 84.85 0 00:05:002 Sub-13 9.60 0.8200 2.05 1.68 16.14 64.55 0 00:15:003 Sub-14 5.20 0.8200 0.91 0.75 3.88 46.56 0 00:05:004 Sub-15 1.60 0.9000 1.52 1.37 2.19 13.13 0 00:10:00

Page 135: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-05 450.97 601.83 0.00 600.83 0.00 1.00 0.2200 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-06 174.19 600.83 0.00 600.66 0.00 0.17 0.1000 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-16 413.03 600.66 0.00 600.27 0.00 0.39 0.0900 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-19 18.99 600.27 0.00 600.25 0.03 0.02 0.1100 CIRCULAR 18.000 18.000 0.0130 0.5000 0.5000 0.0000 0.00 No 15 Link-20 46.01 600.27 0.00 595.73 17.35 4.54 9.8700 Rectangular 60.000 51.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 136: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-05 29.42 0 00:16 10.65 2.76 9.36 0.80 2.00 1.00 27.00 SURCHARGED2 Link-06 33.52 0 00:28 7.07 4.74 10.67 0.27 2.00 1.00 28.00 SURCHARGED3 Link-16 36.87 0 00:08 6.95 5.30 14.42 0.48 1.52 0.76 0.00 > CAPACITY4 Link-19 21.93 0 00:08 3.41 6.43 13.78 0.02 1.27 0.85 0.00 > CAPACITY5 Link-20 58.79 0 00:08 836.88 0.07 16.66 0.05 0.83 0.17 0.00 Calculated

Page 137: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel F_Proposed.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 138: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 29.20 0.7000 0.82 0.57 16.76 67.04 0 00:15:002 Sub-06 4.60 0.7000 0.61 0.42 1.95 11.69 0 00:10:003 Sub-07 6.90 0.8200 0.36 0.30 2.04 24.44 0 00:05:004 Sub-12 6.70 0.8200 0.36 0.30 1.98 23.73 0 00:05:00

Page 139: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 138.98 602.83 0.00 602.62 0.00 0.21 0.1500 CIRCULAR 20.040 20.040 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-15 19.13 602.05 0.04 602.01 -0.04 0.04 0.2100 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-17 402.16 602.62 0.57 602.05 -0.57 0.57 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-18 22.64 602.00 -0.05 600.00 18.80 2.00 8.8300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 140: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 35.02 0 00:21 5.41 6.48 16.05 0.14 1.67 1.00 42.00 SURCHARGED2 Link-15 38.42 0 00:06 1.64 23.49 12.23 0.03 2.00 1.00 7.00 SURCHARGED3 Link-17 31.68 0 00:27 0.36 88.81 10.18 0.66 2.00 1.00 6.00 SURCHARGED4 Link-18 52.91 0 00:06 68.07 0.78 18.96 0.02 1.66 0.83 0.00 Calculated

Page 141: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel F_Proposed.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 142: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 29.20 0.7000 1.21 0.85 24.73 98.93 0 00:15:002 Sub-06 4.60 0.7000 0.90 0.63 2.89 17.36 0 00:10:003 Sub-07 6.90 0.8200 0.54 0.44 3.06 36.66 0 00:05:004 Sub-12 6.70 0.8200 0.54 0.44 2.97 35.60 0 00:05:00

Page 143: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 138.98 602.83 0.00 602.62 0.00 0.21 0.1500 CIRCULAR 20.040 20.040 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-15 19.13 602.05 0.04 602.01 -0.04 0.04 0.2100 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-17 402.16 602.62 0.57 602.05 -0.57 0.57 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-18 22.64 602.00 -0.05 600.00 18.80 2.00 8.8300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 144: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 44.56 0 00:22 5.41 8.24 20.43 0.11 1.67 1.00 54.00 SURCHARGED2 Link-15 45.02 0 00:06 1.64 27.53 14.33 0.02 2.00 1.00 42.00 SURCHARGED3 Link-17 37.48 0 00:30 0.36 105.05 11.93 0.56 2.00 1.00 29.00 SURCHARGED4 Link-18 58.17 0 00:07 68.07 0.85 20.32 0.02 1.71 0.86 0.00 Calculated

Page 145: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel F_Proposed.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 146: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-05 29.20 0.7000 2.05 1.44 41.90 167.61 0 00:15:002 Sub-06 4.60 0.7000 1.52 1.06 4.89 29.35 0 00:10:003 Sub-07 6.90 0.8200 0.91 0.75 5.15 61.79 0 00:05:004 Sub-12 6.70 0.8200 0.91 0.75 5.00 59.99 0 00:05:00

Page 147: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 138.98 602.83 0.00 602.62 0.00 0.21 0.1500 CIRCULAR 20.040 20.040 0.0130 0.5000 0.5000 0.0000 0.00 No 12 Link-15 19.13 602.05 0.04 602.01 -0.04 0.04 0.2100 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 Link-17 402.16 602.62 0.57 602.05 -0.57 0.57 0.1400 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 14 Link-18 22.64 602.00 -0.05 600.00 18.80 2.00 8.8300 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 148: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 61.37 0 00:23 5.41 11.35 28.13 0.08 1.67 1.00 76.00 SURCHARGED2 Link-15 64.64 0 00:07 1.64 39.52 20.57 0.02 2.00 1.00 66.00 SURCHARGED3 Link-17 48.64 0 00:33 0.36 136.34 15.48 0.43 2.00 1.00 61.00 SURCHARGED4 Link-18 63.61 0 00:06 68.07 0.93 21.66 0.02 1.77 0.88 0.00 Calculated

Page 149: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel Y.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 150: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 2.25 0.9000 0.36 0.32 0.73 8.75 0 00:05:002 Sub-02 2.25 0.9000 0.36 0.32 0.73 8.75 0 00:05:00

Page 151: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 PRY-1 345.15 603.50 0.00 601.00 0.00 2.50 0.7200 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 PRY-2 343.21 601.00 0.00 599.50 0.00 1.50 0.4400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 PRY-3 346.06 599.50 0.00 598.50 0.00 1.00 0.2900 CIRCULAR 21.000 21.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 152: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 PRY-1 3.03 0 00:02 3.03 1.00 10.34 0.56 1.00 1.00 13.00 SURCHARGED2 PRY-2 4.27 0 00:02 4.27 1.00 8.57 0.67 1.25 1.00 19.00 SURCHARGED3 PRY-3 4.75 0 00:22 8.52 0.56 4.82 1.20 0.88 0.50 0.00 Calculated

Page 153: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel Y.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 154: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 2.25 0.9000 0.54 0.49 1.09 13.12 0 00:05:002 Sub-02 2.25 0.9000 0.54 0.49 1.09 13.12 0 00:05:00

Page 155: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 PRY-1 345.15 603.50 0.00 601.00 0.00 2.50 0.7200 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 PRY-2 343.21 601.00 0.00 599.50 0.00 1.50 0.4400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 PRY-3 346.06 599.50 0.00 598.50 0.00 1.00 0.2900 CIRCULAR 21.000 21.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 156: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 PRY-1 3.03 0 00:02 3.03 1.00 10.34 0.56 1.00 1.00 20.00 SURCHARGED2 PRY-2 4.27 0 00:02 4.27 1.00 8.86 0.65 1.25 1.00 30.00 SURCHARGED3 PRY-3 4.75 0 00:32 8.52 0.56 4.83 1.19 0.88 0.50 0.00 Calculated

Page 157: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel Y.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 158: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 2.25 0.9000 0.91 0.82 1.84 22.11 0 00:05:002 Sub-02 2.25 0.9000 0.91 0.82 1.84 22.11 0 00:05:00

Page 159: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 PRY-1 345.15 603.50 0.00 601.00 0.00 2.50 0.7200 CIRCULAR 12.000 12.000 0.0130 0.5000 0.5000 0.0000 0.00 No 12 PRY-2 343.21 601.00 0.00 599.50 0.00 1.50 0.4400 CIRCULAR 15.000 15.000 0.0130 0.5000 0.5000 0.0000 0.00 No 13 PRY-3 346.06 599.50 0.00 598.50 0.00 1.00 0.2900 CIRCULAR 21.000 21.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

Page 160: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 PRY-1 3.03 0 00:01 3.03 1.00 10.34 0.56 1.00 1.00 35.00 SURCHARGED2 PRY-2 4.27 0 00:01 4.27 1.00 9.10 0.63 1.25 1.00 51.00 SURCHARGED3 PRY-3 4.75 0 00:53 8.52 0.56 4.84 1.19 0.88 0.50 0.00 Calculated

Page 161: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel Z.SPF

Rainfall Details2 year(s)

File Name .............................................................................

Return Period........................................................................

Page 162: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.78 0.9000 0.36 0.32 0.25 3.03 0 00:05:002 Sub-02 0.66 0.9000 0.36 0.32 0.21 2.57 0 00:05:003 Sub-03 1.01 0.9000 0.36 0.32 0.33 3.93 0 00:05:004 Sub-04 0.90 0.9000 0.36 0.32 0.29 3.50 0 00:05:005 Sub-05 0.61 0.9000 0.36 0.32 0.20 2.37 0 00:05:006 Sub-06 1.20 0.9000 0.36 0.32 0.39 4.67 0 00:05:007 Sub-07 3.70 0.8200 0.36 0.30 1.09 13.11 0 00:05:008 Sub-14 8.50 0.7000 0.61 0.42 3.60 21.60 0 00:10:009 Sub-15 7.60 0.8200 0.36 0.30 2.24 26.92 0 00:05:00

10 Sub-16 9.20 0.7000 0.36 0.25 2.32 27.82 0 00:05:0011 Sub-17 41.40 0.8200 0.82 0.67 27.82 111.35 0 00:15:0012 Sub-18 3.80 0.7000 0.61 0.42 1.61 9.66 0 00:10:0013 Sub-21 3.50 0.9000 0.36 0.32 1.13 13.61 0 00:05:00

Page 163: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 366.85 605.00 0.00 604.16 0.00 0.84 0.2300 CIRCULAR 12.000 12.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-02 389.30 604.16 0.00 603.60 0.00 0.56 0.1400 CIRCULAR 15.000 15.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-03 882.80 603.60 0.00 602.50 0.00 1.10 0.1200 CIRCULAR 18.000 18.000 0.0150 0.5000 0.5000 0.0000 0.00 No 14 Link-04 361.55 602.50 0.00 602.25 0.00 0.25 0.0700 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 15 Link-05 351.60 602.00 0.84 601.00 -1.25 1.00 0.2800 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 16 Link-06 648.01 601.16 0.00 597.50 0.00 3.66 0.5600 CIRCULAR 33.000 33.000 0.0150 0.5000 0.5000 0.0000 0.00 No 17 Link-13 166.95 601.42 0.26 601.16 -0.26 0.26 0.1600 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-14 320.84 601.92 0.50 601.42 -0.50 0.50 0.1600 CIRCULAR 27.000 27.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-15 347.90 602.47 0.55 601.92 -0.55 0.55 0.1600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

10 Link-16 339.45 601.00 -1.25 600.00 -4.50 1.00 0.2900 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 111 Link-18 324.27 600.00 -4.50 599.00 0.00 1.00 0.3100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 112 Link-19 369.33 597.30 -1.70 596.50 -0.80 0.80 0.2200 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 113 Link-20 344.95 596.50 -0.80 595.50 0.00 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 114 Link-21 345.47 595.50 0.00 594.50 0.00 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 115 Link-22 343.71 594.50 0.00 593.50 593.50 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 116 Link-23 366.85 597.50 0.00 597.30 -1.70 0.20 0.0500 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

Page 164: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 3.08 0 00:05 1.48 2.08 3.92 1.56 1.00 1.00 13.00 SURCHARGED2 Link-02 5.43 0 00:05 2.12 2.56 4.68 1.39 1.25 1.00 41.00 SURCHARGED3 Link-03 5.34 0 00:07 3.21 1.66 3.02 4.87 1.50 1.00 45.00 SURCHARGED4 Link-04 9.76 0 00:05 3.61 2.70 4.84 1.25 1.75 1.00 49.00 SURCHARGED5 Link-05 17.53 0 00:04 3.66 4.79 7.77 0.75 1.75 1.00 49.00 SURCHARGED6 Link-06 46.62 0 00:03 34.45 1.35 7.96 1.36 2.75 1.00 49.00 SURCHARGED7 Link-13 48.20 0 00:03 1.00 48.02 9.86 0.28 2.50 1.00 49.00 SURCHARGED8 Link-14 44.62 0 00:29 0.55 81.61 11.22 0.48 2.25 1.00 50.00 SURCHARGED9 Link-15 51.91 0 00:22 0.38 135.34 16.52 0.35 2.00 1.00 50.00 SURCHARGED

10 Link-16 20.81 0 00:07 33.39 0.62 5.41 1.05 1.83 0.73 0.00 Calculated11 Link-18 23.38 0 00:07 53.42 0.44 6.09 0.89 1.83 0.73 0.00 Calculated12 Link-19 70.35 0 00:07 97.45 0.72 7.49 0.82 2.96 0.74 0.00 Calculated13 Link-20 68.09 0 00:08 103.76 0.66 7.78 0.74 3.16 0.79 0.00 Calculated14 Link-21 66.06 0 00:09 77.28 0.85 6.46 0.89 3.34 0.83 0.00 Calculated15 Link-22 64.42 0 00:11 77.48 0.83 6.81 0.84 2.82 0.70 0.00 Calculated16 Link-23 50.51 0 00:05 36.96 1.37 8.74 0.70 3.00 1.00 1.00 SURCHARGED

Page 165: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel Z.SPF

Rainfall Details10 year(s)

File Name .............................................................................

Return Period........................................................................

Page 166: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.78 0.9000 0.54 0.49 0.38 4.55 0 00:05:002 Sub-02 0.66 0.9000 0.54 0.49 0.32 3.85 0 00:05:003 Sub-03 1.01 0.9000 0.54 0.49 0.49 5.89 0 00:05:004 Sub-04 0.90 0.9000 0.54 0.49 0.44 5.25 0 00:05:005 Sub-05 0.61 0.9000 0.54 0.49 0.30 3.56 0 00:05:006 Sub-06 1.20 0.9000 0.54 0.49 0.58 7.00 0 00:05:007 Sub-07 3.70 0.8200 0.54 0.44 1.64 19.66 0 00:05:008 Sub-14 8.50 0.7000 0.90 0.63 5.35 32.07 0 00:10:009 Sub-15 7.60 0.8200 0.54 0.44 3.37 40.38 0 00:05:00

10 Sub-16 9.20 0.7000 0.54 0.38 3.48 41.73 0 00:05:0011 Sub-17 41.40 0.8200 1.21 0.99 41.07 164.31 0 00:15:0012 Sub-18 3.80 0.7000 0.90 0.63 2.39 14.34 0 00:10:0013 Sub-21 3.50 0.9000 0.54 0.49 1.70 20.41 0 00:05:00

Page 167: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 366.85 605.00 0.00 604.16 0.00 0.84 0.2300 CIRCULAR 12.000 12.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-02 389.30 604.16 0.00 603.60 0.00 0.56 0.1400 CIRCULAR 15.000 15.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-03 882.80 603.60 0.00 602.50 0.00 1.10 0.1200 CIRCULAR 18.000 18.000 0.0150 0.5000 0.5000 0.0000 0.00 No 14 Link-04 361.55 602.50 0.00 602.25 0.00 0.25 0.0700 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 15 Link-05 351.60 602.00 0.84 601.00 -1.25 1.00 0.2800 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 16 Link-06 648.01 601.16 0.00 597.50 0.00 3.66 0.5600 CIRCULAR 33.000 33.000 0.0150 0.5000 0.5000 0.0000 0.00 No 17 Link-13 166.95 601.42 0.26 601.16 -0.26 0.26 0.1600 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-14 320.84 601.92 0.50 601.42 -0.50 0.50 0.1600 CIRCULAR 27.000 27.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-15 347.90 602.47 0.55 601.92 -0.55 0.55 0.1600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

10 Link-16 339.45 601.00 -1.25 600.00 -4.50 1.00 0.2900 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 111 Link-18 324.27 600.00 -4.50 599.00 0.00 1.00 0.3100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 112 Link-19 369.33 597.30 -1.70 596.50 -0.80 0.80 0.2200 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 113 Link-20 344.95 596.50 -0.80 595.50 0.00 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 114 Link-21 345.47 595.50 0.00 594.50 0.00 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 115 Link-22 343.71 594.50 0.00 593.50 593.50 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 116 Link-23 366.85 597.50 0.00 597.30 -1.70 0.20 0.0500 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

Page 168: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 3.30 0 00:03 1.48 2.23 4.20 1.46 1.00 1.00 48.00 SURCHARGED2 Link-02 6.08 0 00:04 2.12 2.86 5.04 1.29 1.25 1.00 57.00 SURCHARGED3 Link-03 5.44 0 00:09 3.21 1.69 3.08 4.78 1.50 1.00 60.00 SURCHARGED4 Link-04 10.85 0 00:06 3.61 3.01 4.96 1.21 1.75 1.00 64.00 SURCHARGED5 Link-05 18.45 0 00:03 3.66 5.04 8.17 0.72 1.75 1.00 64.00 SURCHARGED6 Link-06 48.19 0 00:12 34.45 1.40 8.20 1.32 2.75 1.00 64.00 SURCHARGED7 Link-13 53.39 0 00:35 1.00 53.18 10.88 0.26 2.50 1.00 64.00 SURCHARGED8 Link-14 54.93 0 00:30 0.55 100.47 13.82 0.39 2.25 1.00 65.00 SURCHARGED9 Link-15 65.49 0 00:22 0.38 170.76 20.85 0.28 2.00 1.00 65.00 SURCHARGED

10 Link-16 26.63 0 00:06 33.39 0.80 6.45 0.88 2.00 0.80 0.00 Calculated11 Link-18 30.43 0 00:06 53.42 0.57 7.21 0.75 2.00 0.80 0.00 Calculated12 Link-19 81.94 0 00:07 97.45 0.84 7.66 0.80 3.46 0.87 0.00 Calculated13 Link-20 78.25 0 00:07 103.76 0.75 7.90 0.73 3.80 0.95 0.00 Calculated14 Link-21 75.98 0 00:07 77.28 0.98 6.59 0.87 3.88 0.97 0.00 Calculated15 Link-22 76.99 0 00:09 77.48 0.99 7.13 0.80 3.21 0.80 0.00 Calculated16 Link-23 58.77 0 00:05 36.96 1.59 9.32 0.66 3.00 1.00 9.00 SURCHARGED

Page 169: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Project DescriptionModel Z.SPF

Rainfall Details100 year(s)

File Name .............................................................................

Return Period........................................................................

Page 170: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Subbasin SummarySN Subbasin Area Weighted Total Total Total Peak Time of

ID Runoff Rainfall Runoff Runoff Runoff ConcentrationCoefficient Volume

(ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss)1 Sub-01 0.78 0.9000 0.91 0.82 0.64 7.67 0 00:05:002 Sub-02 0.66 0.9000 0.91 0.82 0.54 6.49 0 00:05:003 Sub-03 1.01 0.9000 0.91 0.82 0.83 9.93 0 00:05:004 Sub-04 0.90 0.9000 0.91 0.82 0.74 8.85 0 00:05:005 Sub-05 0.61 0.9000 0.91 0.82 0.50 6.00 0 00:05:006 Sub-06 1.20 0.9000 0.91 0.82 0.98 11.79 0 00:05:007 Sub-07 3.70 0.8200 0.91 0.75 2.76 33.13 0 00:05:008 Sub-14 8.50 0.7000 1.52 1.06 9.04 54.23 0 00:10:009 Sub-15 7.60 0.8200 0.91 0.75 5.67 68.05 0 00:05:00

10 Sub-16 9.20 0.7000 0.91 0.64 5.86 70.33 0 00:05:0011 Sub-17 41.40 0.8200 2.05 1.68 69.59 278.37 0 00:15:0012 Sub-18 3.80 0.7000 1.52 1.06 4.04 24.24 0 00:10:0013 Sub-21 3.50 0.9000 0.91 0.82 2.87 34.40 0 00:05:00

Page 171: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe InputSN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of

ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate BarrelsElevation Offset Elevation Offset Height

(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)1 Link-01 366.85 605.00 0.00 604.16 0.00 0.84 0.2300 CIRCULAR 12.000 12.000 0.0150 0.5000 0.5000 0.0000 0.00 No 12 Link-02 389.30 604.16 0.00 603.60 0.00 0.56 0.1400 CIRCULAR 15.000 15.000 0.0150 0.5000 0.5000 0.0000 0.00 No 13 Link-03 882.80 603.60 0.00 602.50 0.00 1.10 0.1200 CIRCULAR 18.000 18.000 0.0150 0.5000 0.5000 0.0000 0.00 No 14 Link-04 361.55 602.50 0.00 602.25 0.00 0.25 0.0700 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 15 Link-05 351.60 602.00 0.84 601.00 -1.25 1.00 0.2800 CIRCULAR 21.000 21.000 0.0150 0.5000 0.5000 0.0000 0.00 No 16 Link-06 648.01 601.16 0.00 597.50 0.00 3.66 0.5600 CIRCULAR 33.000 33.000 0.0150 0.5000 0.5000 0.0000 0.00 No 17 Link-13 166.95 601.42 0.26 601.16 -0.26 0.26 0.1600 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 18 Link-14 320.84 601.92 0.50 601.42 -0.50 0.50 0.1600 CIRCULAR 27.000 27.000 0.0130 0.5000 0.5000 0.0000 0.00 No 19 Link-15 347.90 602.47 0.55 601.92 -0.55 0.55 0.1600 CIRCULAR 24.000 24.000 0.0130 0.5000 0.5000 0.0000 0.00 No 1

10 Link-16 339.45 601.00 -1.25 600.00 -4.50 1.00 0.2900 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 111 Link-18 324.27 600.00 -4.50 599.00 0.00 1.00 0.3100 CIRCULAR 30.000 30.000 0.0130 0.5000 0.5000 0.0000 0.00 No 112 Link-19 369.33 597.30 -1.70 596.50 -0.80 0.80 0.2200 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 113 Link-20 344.95 596.50 -0.80 595.50 0.00 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 114 Link-21 345.47 595.50 0.00 594.50 0.00 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 115 Link-22 343.71 594.50 0.00 593.50 593.50 1.00 0.2900 CIRCULAR 48.000 48.000 0.0130 0.5000 0.5000 0.0000 0.00 No 116 Link-23 366.85 597.50 0.00 597.30 -1.70 0.20 0.0500 CIRCULAR 36.000 36.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

Page 172: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Pipe ResultsSN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported

ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number ConditionOccurrence Ratio Total Depth

Ratio(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)

1 Link-01 4.03 0 00:02 1.48 2.73 5.31 1.15 1.00 1.00 77.00 SURCHARGED2 Link-02 6.67 0 00:03 2.12 3.14 5.54 1.17 1.25 1.00 84.00 SURCHARGED3 Link-03 6.12 0 00:03 3.21 1.90 3.46 4.25 1.50 1.00 87.00 SURCHARGED4 Link-04 11.16 0 00:03 3.61 3.09 5.11 1.18 1.75 1.00 91.00 SURCHARGED5 Link-05 22.36 0 00:13 3.66 6.11 9.30 0.63 1.75 1.00 91.00 SURCHARGED6 Link-06 55.16 0 00:13 34.45 1.60 9.29 1.16 2.75 1.00 91.00 SURCHARGED7 Link-13 69.01 0 00:38 1.00 68.75 14.06 0.20 2.50 1.00 91.00 SURCHARGED8 Link-14 70.34 0 00:34 0.55 128.64 17.69 0.30 2.25 1.00 92.00 SURCHARGED9 Link-15 90.97 0 00:23 0.38 237.18 28.96 0.20 2.00 1.00 92.00 SURCHARGED

10 Link-16 30.06 0 00:10 33.39 0.90 6.66 0.85 2.50 1.00 3.00 SURCHARGED11 Link-18 37.22 0 00:06 53.42 0.70 7.81 0.69 2.50 1.00 3.00 SURCHARGED12 Link-19 99.63 0 00:05 97.45 1.02 8.10 0.76 4.00 1.00 15.00 SURCHARGED13 Link-20 94.14 0 00:06 103.76 0.91 7.95 0.72 4.00 1.00 16.00 SURCHARGED14 Link-21 93.34 0 00:06 77.28 1.21 7.57 0.76 4.00 1.00 11.00 SURCHARGED15 Link-22 108.99 0 00:07 77.48 1.41 9.19 0.62 3.58 0.89 0.00 > CAPACITY16 Link-23 66.18 0 00:05 36.96 1.79 11.75 0.52 3.00 1.00 48.00 SURCHARGED

Page 173: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix E  

Record of Environmental Concerns  

Page 174: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

SiteiD SiteiD

1 1 2 2 3 3 4 4

5 5 6 6 7 7 8 8

9 9 10 10 11 11

12 12 13 13

14 14 15 15 16 16 17 17 18 18

19 19

20 20 21 21 22 22

23 23 24 24 25 25 26 26 27 27

28 28

29 29 30 30 31 31 32 32

33 33 34 34 35 35 36 36

37 37 38 38 39 39 40 40 41 41

Table 1 - Recognized Environmental Conditions

Environmental Condition

Auto repair shop

Construction site - 7 former USTs (6800 Stanley LLC)

Filling station and greasing- 3 gas tanks (Off-site nearby)

300-gallon gasoline UST- shown in ROW

Filling station- 3 gas tanks Filling station and Auto Repair (Capital Auto Body)

Printing shop

Exron Capital, Inc- LUST case (AM STAR gas station)

Printing shop (Former paint shop)

Gas tank - shown in ROW

Fill ins station and greasing, 5 USTs, LUST case (DMJ Auto.)

Filling station- 2 gas tanks

LUST case, multiple former USTs (MacNeal Hospital)

Filling station and greasina:- 3 gas tanks

300-gallon gasoline UST

Filling station (Off-site nearby)

Auto repair shop- (Off-site nearby)

Filling station and greasing- 2 gas tanks

Auto sales and service, USTs (Currently Walgreens)

Filling station- 3 gas tanks (Off-site nearby)

Filling station/auto repair, LUST case (BP gas station)

Auto repair shop, LUST case (Xander Auto Shop)

Coal yard

Filling station and greasing- 2 gas tanks

Electrical sub-station (CornEd)

Auto repair shop (Brakes Plus)

1,000-gallon heating oil UST (United Color Company)

LUST/Spills case (Apartment building)

Filling station and greasing, LUST, multiple USTs (Deece Auto.)

Auto repair shop (Fox Auto Body)

120-gallon gasoline tank- shown in ROW

Lust case (Expert Heating and Cooling)

LUST case (Jain Mohain)

Dry cleaner (O'Brien The Cleaner)

SOD-gallon heating ofl UST (Roger Peterson)

LUST case (George Spiro) LUST case, 3 USTs (Vacant lot)

Auto repair shop

1,000-gallon UST (Depot Development)

Dry cleaner (SUper Cleaners) Filling station and greasine (Currently Quem's Oasis)

Notes:

R =Property Reconnaisance

S =Sanborn Map (earliest notation)

D = Env. Database Report Listing

Address

6809 32nd Street 6820 32nd Street

6836 32nd Street 3208 Elliot (now Grove Ave.)

3201 Grove Ave.

3244 Grove Ave.

6212 Grove Ave.

3346 Harlem Ave.

3216 Kenilworth 3145 Oak Park Ave.

3146 Oak Park Ave.

3156 Oak Park Ave. 3249 Oak Park Ave.

3301 Oak Park Ave. 3147 Oak Park Ave. 6732 Ogden Ave.

6738 Ogden Ave.

6750 Ogden Ave. 6800 Ogden Ave.

6814 Ogden Ave. 6749 Ogden Ave.

3101 Ridgeland Ave.

3117 Ridgeland Ave. 6401 Stanley Ave.

6449 Stanley Ave.

6509 Stanley Ave.

6515 Stanley Ave.

6525 Stanley Ave.

6545 Stanley Ave.

6639 Stanley Ave.

6725 Stanley Ave.

6837 Stanley Ave.

6837 Stanley Ave.

6915 Stanley Ave.

6945 Stanley Ave. 6822 Windsor Ave.

6846 Windsor Ave,

6906 Windsor Ave.

6910 Windsor Ave.

6930 Windsor Ave.

7148 Windsor Ave.

Source Information Comments

s (1951) Shown as part of filling station on 1975 map

0 7 former USTs- 550 to 2,000 gallons- various products, last use 1973

6 (1951) Nearby site, 3 gas tanks, east of ally fronting W, 32nd 6 (1919) Appears to be in street ROW, not shown on 1929 map

5 (1929) 3 gas tanks- SE corner Grove and W. 32nd, shown on 1951 map, not present on 1975 map

S (1929), 0, R 2 gas tanks, current auto repair shop- Capitol Auto Body

s (1975) North of Stanley Ave., possible solvent storage and use for equipment cleaning

O,R Current AMSTAR gas station- SW corner Harlem and Quincy (Texor is owner)

s (1929) Paint shop in 1929 and converted to print shop by 1951, possible solvent storage and use

s (1929) Appears to be in street ROW, shown on 1951 map, not present on 1975 map

s (1929),0 Sanborn shows 4 sas tanks, NW corner Oak Park and W. 32nd, on 1951 and 1975 maps, OMJ Automotive

5 (1929) 2 gas tanks- SW corner Oak Park and W. 32nd, shown on 1951 map, shown as vacant on 1975 map

0 LUST case- fuel oil, Multiple historic USTs

5 (1951) 3 gas tanks, SE corner of W. 33rd and Oak Park, not shown on 1975 map

s (1919) Northwest corner of Stanley and Oak Park, not shown on 1929 map

s (1975) Nearby site

5 (1975) Nearby site

s (1929) 2 gas tanks, SE corner Ogden and Oak Park, present on 1951 and 1975 map

s (1951),0 Currently Walgreens, SW corner Ogden and Oak Park, 2 historic USTs, shown on 1975 map

s (1951) Nearby site, 3 gas tanks, shown on 1975 map

S (1929), 0, R 3 gas tanks, current BP station, NE corner Ogden and Oak Park, LUST case, Shown on 1951 and 1975 maps

S (1951), 0, R current location of auto repair shop, LUST case -1,000 gallon gasoline UST, shown on 1975 map

5 (1929) Portion C.M~ Moline Coal Yard, NE corner Ridgeland and Park, shown on 1951 and 1975 maps

s (1929) 2 gas tanks, across tracks from Lavergne Station, present on 1975 map

S (19S1), R, Still present

S (1975), 0 Historic and current auto repair shop

0 UST last used 1973 - 1,000 gallon heating oil

0 550 gallon heating oil UST

S (1929), 0, R 3 gas tanks, current auto repair shop (DEECE), 6 USTs, LUST case, shown on 1951 and 1975 maps

0 Historic and current auto body shop

s (1919) Appears to be in street ROW, not present on 1925 map

0 LUST case- 550 gallon heating oil

0 LUST case- unknown petroleum, related to Expert Heating and Cooling

5 (1951), 0, R Historic and current dry cleaner (O'Brien The Cleaner), shown on 1975 map

0 UST last used 1960- SOD gallon heating oil- apartment bldg

0 LUST case- 2 tanks, gasoline, 1,000 gallons each

0 LUST case- 3 tanks, heating oil, 300 or 500 gallons, see I EPA NFR letter in Section 3.8 of PESA text

s (1929) Not shown on 1951 map

0 UST last used 1973- 1,000 gallon fuel oil

0 Current business

5 (1929) 3 eas tanks. not present on 1975 map, current Quan's Oasis

Page 175: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

LEGEND:

G) AUTO REPAIR FACILITY

&. UST OR MISCELLANEOUS TANK SITE

~ FILLING STATION

@ LUST CASE SITE

® DRY CLEANER FACILITY

OTHER

1. OFF-SITE NEARBY RECs ARE ILLUSTRATED IN WHITE

2. IMAGE OBTAINED FROM ESRI.

0 600

SCALE, FEET

1200 Depot District Streetscape Berwyn, Illinois

City of Berwyn

Auto repair shop

Construction site· 7 former USTs (6800Stanley uq Filling station and greasing· 3 gas tanks (Off-site nearby)

4 300-gallon gasoline UST • •hown in ROW 5 Filling station • 3 gas tanks

6 Filling station and Auto Repair (capital Auto eody) 7 Printing shop 8 Exron Capital , Inc - LUST case (AM STAR gas station)

9 Printing shop (Former paint shop) 10 Gas tank- shown in ROW

U Filling station and greasing, 5 USTs, l UST case (OMJ Auto.) 12 Filling station • 2 gas tanks

13 LUST case, multiple former USTs (MacNeal Hospita l)

14 Filling station and greasing- 3 gas tanks 15 300-galion gasoline UST

16 Filling station (Off-site nearby)

17 Auto repair shop· (Off-site nearby) 18 Filling station and greasing- 2 gas tanks

19 Auto sales and service, USTs (Currently Walgreens)· 20 Filling station· 3 gas tank.s (Off·slte nearby)

21 Filling station/auto repair, LUST case (BP gas stat ion) 22 Auto repairshop, LUST case (xander Auto Shop)

23 Coal yard 24 Filling station and greasing- 2 gas tanks

2S Electrical sub-station (CornEd) 26 Auto repalrshop (Brake s Plus)

27 1,000.galion heating oil UST (United Color Company) 28 LUST/Spil ls case (Apartment building)

Z9 Filling station and greasing, LUST, multiple USTs (Deece Auto.) 30 Auto repair shop (Fo• Auto eody) 31 120-gallon gasoline tank- shown In ROW

32 lust case (Expert Heating and Cooling)

33 LUST case (Jain Mohain) 34 Dry cleaner (O'Brien The Cleaner)

6820 32nd Street

6836 32nd Street 3208 Elliot (now Grove Ave.) 3201 Grove Ave.

3244 Grove Ave. 6212 Grove Ave. 3346 Harlem Ave.

3216 Kenilworth

3145 Oak Park Ave.

3146 Oak Park Ave. 3156 Oak Park Ave.

3249 Oak Park Ave.

3301 Oak Park Ave. 3147 Oak Park Ave.

6732 Ogden Ave.

6738 Ogde n Ave.

6750 Ogden Ave. 6800 Ogden Ave. 6814 Ogden Ave.

6749 Ogden Ave. 3101 Ridgeland Ave.

3117 Ridgela nd Ave. 6401 Stanley Ave.

6449 Stanley Ave. 6509 Stanley Ave.

6515 Stanley Ave. 6525 Stanley Ave.

6545 Stanley Ave. 6639 Stanley Ave. 6725 Stanley Ave.

6837 Stanley Ave.

6837 Stanley Ave. 6915 Stanley Ave.

35 500-gallon heating oil UST (Roger Peterson) 6945 Stanley Ave.

36 LUST case (George Spiro) 6822 Windsor Ave.

37 LUST case, 3 USTs (Vacant lot) 6846 Windsor Ave. Auto repair shop 6906 Windsor Ave.

1,000.galion UST (Depot Development) 6910 Windsor Ave.

PROPERTY FEATURES DIAGRAM

March 2014 Fig. 2 C:\Users\cmann\Documents\Mann\Projects\Chicago Supporl\Berwyn\CAD\Berwyn PESA Figures2

Page 176: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix F  

Combined Sewer Operational & Maintenance Plan  

    

Page 177: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

CITY O F BERWYN, CO O K CO UNTY, ILLINO IS

COMBINED SEWER

OPERATIONAL & MAINTENANCE PLAN

MAY 20 14

Page 178: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

TABLE OF CONTENTS

OVERVIEW

1.0 OPERATIONAL PLAN

1.1 Introduction

1.2 Background

1.3 Sensitive Areas

1.4 Objectives

1.5 Maintenance Procedures

1.6 Inspection and Monitoring Procedures

1.7 Sewer System

1.8 Catch Basins and Manholes

1.9 Inspection and Reporting After Significant Rainfall Event

1.10 Record Keeping

1.11 Safety

1.12 Rehabilitation Work

2.0.0 POLLUTION PREVENTION PLAN

2.1 Policy and Services

2.2 Street Cleaning

2.3 Fertilizers and Pesticides

2.4 Water Conservation

2.5 Solid Waste Collection

2.6 Illegal Dumping

2.7 Bulk Refuse

2.8 Hazardous Waste

Page 179: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

1

OVERVIEW

Berwyn, as an urban infill community, has active Combined Sewer Overflow (CSO) problems

and recognizes the environmental and health risks that are associated with CSO. The City’s

combined sewer system is nearing 100 years old and incapable, at times, of handling the

increased capacity required, especially during a storm. Much of the combined sewer system was

designed to handle small one story structures when pervious green areas were much larger.

While the population and density of Berwyn has grown over the last century, the combined

sewer system has remained largely untouched. The City’s current stormwater management

system is a combined sewer system comprised of a conveyance system nearly 100 miles in

length and storm laterals totaling 19 miles. Stormwater runoff and sewage are collected into a

single pipe and ultimately discharged into the large interceptors of the Metropolitan Water

Reclamation District of Greater Chicago (MWRDGC) where it is eventually treated at their

Stickney Treatment Plant. The Stickney Plant has the capacity to treat 1.2 billion gallons of

wastewater per day, serving a 260 square mile area with 2.5 million people. This area

encompasses parts of Chicago and 43 suburban communities. The MWRD operates under

NPDES Permit No. IL0028053 and is required to monitor 112 CSO outfalls in accordance with

Special Condition 10.11.

The City of Berwyn is located within the Lower Des Plaines River watershed. This watershed

covers over 228,000 acres of predominately urban and industrial uses within DuPage, Cook and

Will Counties. Within this watershed, the Depot District in Berwyn drains to the Chicago

Sanitary and Ship Canal. The Chicago Sanitary and Ship Canal is an impaired, manmade

waterway with high amounts of polychlorinated biphenyls, phosphorus, and low amounts of

dissolved oxygen. Combined sewer overflows and urban runoff are listed as two of the causes for

this impairment. Planning efforts are currently underway to reduce combined sewer overflows.

Since combined sewers carry both sewage and storm water in the same conduit, flow rates are

greatly increased during periods or storm water runoff. During a significant storm event, when

the flows exceed the capacity of the City’s sewer system, flow is directed into the MWRD

Tunnel and Reservoir Project (TARP); flows in excess of TARP capacity are discharged directly

into the Chicago Sanitary and Ship Canal and Des Plaines River as CSOs. The MWRD TARP

is currently underway to increase the region’s capacity to contain and direct combined sewer

flows to water reclamation plants for treatment instead of discharging into rivers and lakes. CSO

Page 180: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

2

communities are also implementing long-term control plans and aggressive pollution prevention

strategies to minimize pollutant loads entering the combined sewer systems.

The City of Berwyn Combined Sewer Operation and Maintenance Plan and the Pollution

Prevention Plan, outlines proper maintenance, regulation, inspection, and monitoring of the

combined sewer system to ensure that control requirements are in place to minimize the impacts

on the environment and public health by CSO occurrences. A Proper Operations & Maintenance

(O&M) plan for the combined sewer system and CSOs has been developed, and is currently

being implemented. This is on file at the City Public Works Department. The O&M plan

includes:

1. Collection system inspections.

2. Sewer and catch basin cleaning and maintenance.

3. Collection system replacement, where necessary.

By adhering to the objectives in this plan the City intends to; maximize storage within system,

minimize CSO discharges including floatables and solids, and optimize flow to MWRD for

treatment.

The City also will be implementing other controls and policies that will benefit the system, such

as:

1. Require new construction to be designed to minimize and/or delay inflow to the

combined sewer.

2. Require that inflow sources on the combined sewer be connected to a storm sewer within

a reasonable amount of time, if a storm sewer becomes available.

3. Implementation of pollution prevention objectives.

4. Creation of an electronic Sewer system map, detailing the system.

1.0 OPERATIONAL PLAN

1.1 INTRODUCTION

Page 181: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

3

This manual is a combined sewer and CSO Operations and Maintenance (O&M) Plan prepared

to provide the staff of the City of Berwyn Public Works Department with the information needed

to operate and maintain the combined sewer system and to minimize the occurrence of system

surcharging resulting in basement backups and combined sewer overflows.

1.2 BACKGROUND

The City of Berwyn is served by a combined sewer system throughout the entire community. A

combined sewer system is a system in which both sanitary waste and storm water is discharged

into the same pipe. The collected sewage ultimately discharges in the large interceptor sewers of

the Metropolitan Water Reclamation District of Greater Chicago (MWRDGC), where it is

eventually treated at their Stickney treatment plant.

The City’s piping network is made up of over 528,000 feet or 100 miles of sewer pipe, ranging in

size from 8” to 7’-6” in diameter.

The majority of the City’s sewers were constructed over 90 years ago and consist of vitrified clay

tile with cement mortar joints. Vitrified clay tile sewers are typically brittle and susceptible to

cracking under impact loading. However they are also considered to be strong under the steady

pressure of the surrounding earth and are not likely to deteriorate as a result of the chemical or

abrasive action to which they are subjected to under most of the local conditions. The City also

is serviced by a small percentage of brick sewers. These sewers were constructed by hand using

brick and mortar over 100 years ago. The bricks used to construct these manholes have a

tendency to dislodge over time in which the manholes partially collapse causing infiltration of

water, sand and soil.

The majority of the manholes are also over 90 years in age and are constructed out of bricks.

The newer manholes within the City comprise about 25% of the total and are constructed with

concrete block or precast concrete.

1.3 NETWORK CAPACITY

Combined sewers convey both sanitary and storm flows, but it is the storm flows that are a much

larger component of the overall flow and much more critical to pipe design and analysis. Sewer

Page 182: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

4

pipe capacity is directly proportional to the volume of storm water expected to enter the system.

Combined sewers were not designed for extreme storm conditions. This would lead to bigger

pipes at more expense and potential for excess hazardous methane gas buildup in pipes during

periods of low flow.

The design of the City’s existing sewer network was based on design theory and rainfall data

which existed for the area at the time of installation nearly 100 years ago. Calculations

performed on small areas of the City’s sewer system have resulted in a system sized for a 2 year

storm. A 2 year storm means that the system in that area is likely to be overloaded at least every

two years. Whether these sample areas are proper representation of the entire City, is not

determined at this time. However, with this in mind and historical rainfall data combined with

sewer back-up reports, the City has made strides toward the creation of a Stormwater

Management Plan and stormwater improvement projects.

The system conveys sanitary sewage and storm water runoff to the MWRD interceptor. Drop

pipe assembly diversion structures allow for the maximum diversion into the interceptor. The

interceptor lines are at a lower elevation than from the sewer lines. Flow from the City sewer

drops in to the interceptor during normal conditions. When the interceptor is full, the connection

will fill up and prevent inflow from the City sewers. The flow then bypasses the connection to

the interceptor. The flow continues downstream to the next connection point. If all the

interceptor diversion structures are full, the flow will back up and spill over into the relief sewer

system and eventually drain to TARP or the CSOs.

1.4 OBJECTIVES

The objective of this plan is to maintain the sewer network so that it can perform as best as

possible by; correcting forms of inflow and infiltration (I/I) caused by root intrusion, leaking

joints, structural cracks, and grit buildups; maintain proper conveyance by reducing blockages

and grit buildups; all while reducing pollutant loads from entering the combined sewer system,

especially during flooding events. The objectives of this plan can be achieved through regular

maintenance, inspection, and monitoring procedures of the City’s combined sewers, catch basins

and manholes.

Page 183: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

5

1.5 MAINTENANCE PROCEDURES

The City of Berwyn Public Works Department is responsible for maintaining the sewer system.

Proper maintenance is required for the system to perform at an optimum level with a minimum

occurrence of CSOs. An effective preventive maintenance program attempts to predict the

problems that will be encountered and what preventative measures must be scheduled.

Preventive maintenance schedules must be flexible and should be periodically modified based on

their effectiveness and the ability to accomplish maintenance objectives. This section contains

information on standard procedures to be followed to maintain the system components.

All sewers are to be cleaned on a 10-year program. Problem areas that are addressed during

inspection may need to be cleaned more frequently or replaced if inspection of the line reveals

severe problems. Some of the older sewers may have significant root infiltration and debris and

may require additional cleaning. Newly constructed sewers will require less frequent cleaning.

Frequency of cleaning should be adjusted over time such that a minimum of maintenance is

required to prevent blockages.

All drainage structures are to be cleaned on the same sewer cleaning schedule within the same

area for the sewers scheduled to be cleaned. Structures are to be cleaned using a Vac-All truck.

During periods of rainfall, particularly during the fall season, catch basin operation and surface flooding

conditions are monitored and extra cleaning is conducted to ensure proper operation. All inspection and

maintenance data will be recorded on City work tickets.

Street cleaning reduces debris that may be washed into the combined sewer system. The City of

Berwyn conducts street cleaning following standard operating procedures for street cleaning.

Street cleaning will be conducted year round, weather dependent. Additional need for street

cleaning to remove leaves during the fall months (September through November) will be

evaluated on a monthly basis and conducted as needed. The no parking schedule for street

cleaning is followed during the winter months for snow removal and street maintenance

purposes.

The interceptors are operated and maintained by the MWRDGC; the City is not allowed access

to these sewer lines or manholes. The connections to the TARP drop shafts and the control

structures are all maintained by the District.

Page 184: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

6

1.6 INSPECTION AND MONITORING PROCEDURES

The following inspection program is an important means to ensure that the collection system is

operating as to optimize transport of wastewater flows and minimize CSO discharges.

Inspection procedures are an essential part of preventive maintenance which is the primary

means of implementing the objectives of this plan. The defects identified during a continuous

inspection program can be scheduled for routine repair before it becomes necessary to make

expensive emergency repairs.

Inspections will reveal blockages, identify structural defects and potential hazards, locate sources

of inflow and infiltration (I/I), and identify maintenance needs. A continuous inspection

program serves to identify potential system failures that may lead to CSOs and basement

backups.

1.7 SEWER SYSTEM

As the sewer system becomes older, the pipes are subject to deterioration and damage. Several

such reasons are poor construction practices during installation, improper connection of private

service laterals, corrosion, poor maintenance, high live loads, and freeze thaw cycles. Sewers are

inspected on a routine basis. The frequency of inspection is required due to the age of the system.

Sewer inspections can be done by looking into a sewer segment from inside a manhole, by

walking through the line if the pipe is large enough, or by pulling a closed circuit television

camera through. Visual inspections may be adequate for short term inspections or to indicate if

infiltration or blockages exist, but visual inspections is limited to segments adjacent to manholes

and warrants periodic televising of the entire system.

Closed circuit television (CCTV) inspection is the most effective means of inspection and gives

permanent visual record of the sewer conditions. A TV camera is pulled through the sewer pipe

while the picture is shown on a monitor and observed at ground level. CCTV inspection is

applicable to sewers four to forty-eight inches in diameter. Light sewer cleaning is usually

required prior to inspection to allow the camera to pass freely through each line giving an

unobstructed view. The tape should be provided with an audio portion in order that the

technician may record and comment on pipe conditions. Otherwise all comments should be

written during the televising and submitted with the sewer tapings.

Page 185: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

7

This method allows inspection of the structural conditions and observations of pipe or joint

separations, drops, ruptures, leaks, service connections, obstructions, corrosion, misalignments,

and root intrusion. Damage can be identified that may have occurred during construction or

excavation on other utilities, roads, or buildings. This also provides a means for determining

flow rates of I/I, recording illegal connections, examination of newly installed segments, and

helps to evaluate the effectiveness of corrective measures. An important part of every sewer

inspection is the set up procedure of all observations on the inspection record. The following

information should be recorded:

The date, weather conditions, ground water level if applicable, type of ground surface

above the sewer line, and the name of the technician.

The length, size, type, depth of invert, and structural condition of the sewer main as well

as all service lateral connections, and other tap-ins. Provide an estimate of the amount of

work required or preventive maintenance needed.

The depth of flow for assessment of pipe capacity, and detection of extraneous inflow of

water.

Extent of root intrusion and suggested control techniques.

Type and depth of deposits and recommended cleaning methods.

The location and estimated flow rate of I/I sources such as open or misaligned joints,

cracked pipes, and mineral deposits.

Any special problems or conditions such as collapsed pipe, sagging sewers, and

corrosion.

1.8 CATCH BASINS AND MANHOLES

Catch basins and manholes are subject to a variety of forces which cause them to structurally

deteriorate over time allowing for I/I to enter the system. The most common sources of

deterioration include traffic vibration, freeze-thaw cycles, and ground settlement. A common

problem is the deterioration of brick manholes where bricks become loose and fall into the

sewer, causing blockages. Manholes and catch basins will be routinely inspected. In areas subject

to heavy traffic, inspections should be completed more frequently. Use confined space entry

procedures if a person has to enter the catch basin or manhole structure for any reason.

Inspection of catch basins and manholes require entry into the manhole. Use the following

Page 186: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

8

inspection procedures to identify defects:

• Check the area around the lid for proper drainage away from the lid for a manhole and

proper drainage into the inlet for cases of catch basins. Use a straight edge to see if the

rim is at proper elevation and grade with the surrounding ground. Note defects in the lid

that may prohibit a tight fit.

• Check for combustible gases inside the catch basin before removing the manhole cover.

• Inspect all surfaces and joints inside for cracks, breaks, offsets, misalignments, root

intrusions, corrosion, or other sources of I/I.

• Inspect for grease accumulation around the arch or inside of sewers.

• Inspect for gravel and debris in the invert, on the shelf, and steps.

• Check the condition of the steps, grout bed of the frame, frame seal, and grade rings.

• Note any backed up water or sluggish flows. Compare flows between adjacent manholes

and catch basins. If low flow is found downstream of a structure that has greater flows,

this may indicate a blockage.

• With a sounding pole, check the structure for an accumulation of grit in the catch basin.

There should be no accumulation of grit within one foot of the bottom of the orifice.

Excessive floating material in the catch basin that reaches the orifice inlets should be

removed.

• Note any condensation on the walls that may indicate the ground water level.

• Clean the ledge of the manhole ring and inspect for cracks in the metal parts.

Every manhole or catch basin requires a detailed inspection record on which the following

typical information should be recorded:

• Structure identification and location, date of inspection, weather conditions, and name of

the inspector.

• Materials and conditions of the manhole / catch basin including construction type, cover,

ring, frame seal, cone, chimney, wall, steps, lift holes, benches, and channels.

• Depth below grade, structure size, the number and size of holes in the lid, and the

alignment of the frame grade. I/I sources, evidence of leaks or backups, level of high

water marks (for manholes only), ground water level, description of debris found, and

any specific problems.

• Any significant rainfall events, as characterized as an event that produces at least one

Page 187: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

9

inch of rain in a 24-hour period.

1.9 INSPECTION AND REPORTING AFTER SIGNIFICANT RAINFALL EVENT

The City staff will monitor which storm events that are producing CSOs. Frequency (number of

discharges per month), duration (estimate in hours), and date of each CSO, will be recorded for

City records. Estimates of storm duration and total rainfall shall also be provided for each storm

event. All discharges from the same storm or occurring within 24 hours shall be reported as one.

1.10 RECORD KEEPING

Record keeping is important to the short term and long term operational and financial

performance of the combined sewer system. Records are useful to the Public Works personnel,

City officials, consulting engineers, and regulatory agencies. For this reason, all records must be

accurate and complete.

Daily operational reports should summarize maintenance and/or inspections performed that day

and any special or unusual occurrences. All complaints and resident concerns should be

addressed in order that repairs and/or adjustments are made to decrease the likelihood of any

CSO occurrence during wet or dry conditions. These reports should be used in conjunction with

the inspection and maintenance records used by public works.

Daily reports should be combined into a monthly summary along with the monthly CSO

monitoring and kept on file at the City Public Works. The monthly report should include the

following information:

• Identify any collapsed or blocked sewers and any other abnormal collection system

problems. Record the date of discovery, location and segment identification, and the

means by which the collapse or block was discovered. Describe when and how the sewer

was repaired or replaced.

• Identify basement backups and any other abnormal collection system complaints. Record

date, time, and weather conditions. Note any other collection system problems that the

complaint may have alerted City staff to; for example, a backed up basement may have

alerted to a collapsed or blocked sewer.

• Record abnormal street flooding (other than designed street ponding). Record date,

Page 188: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

10

location, and weather conditions. Record course of action taken to correct the problem.

• All failing inspections of street berms, ponding areas, and all sewer components.

Describe locations, etc., and corrective measures taken.

• Record date, locations and identification of all passing inspections.

• Record all CSO occurrences.

1.11 SAFETY

The City of Berwyn Public Works Department follows standard safety procedures when

performing maintenance on facilities. Topics of concern that should be reviewed by all workers

performing maintenance procedures include:

• Traffic Control

• Worksite Safety

• Confined Space Entry

• Safety Equipment

• Emergencies, First Aid, and Hygiene

1.12 REHABILITATION WORK

The rehabilitation work determined to be necessary as a result of inspections and investigations

is to be scheduled and budgeted by the Director of Public Works. Rehabilitation methods

employed reflect current standards, conventions and regulations.

SEWER REHABILITATION

Sewer rehabilitation involves the replacement or lining of existing sewers based upon the

findings of a televised inspection. The replacement methodology is used to correct sewer

segments with structural deficiencies or leakage problems. The lining methodology is applied

where feasible to minimize surface disruption while improving functional capacity. Sewer lining

preserves the structural integrity, reduces maintenance requirements, and improves flow capacity

by eliminating root intrusion through joints and reducing friction losses along pipe walls due to

its extremely smooth surface. Through the lining process a resin-saturated, polyester felt tube is

inverted or pulled into a designated segment of sewer. Hot water or steam is then pumped into

the tube to cure the resin and form a tight-fitting, jointless and corrosion-resistant replacement

pipe. Service laterals connections are reinstated by internally cutting openings at the catalogued

service locations. The sewer is then inspected by a sewer televising system to verify that the

Page 189: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

11

lining was successful and that all services are restored.

MANHOLE REHABILITATION

Manhole rehabilitation involves the replacement, repair, or lining of existing manholes.

Replacement involves the excavation and removal of the defective manhole structure and the

installation of a new precast concrete manhole meeting current standards of fabrication. Repair

involves the removal or improvement of only a portion of the manhole structure such as grade

rings, cast iron frame and lid, and steps. Manhole lining extends the life of those brick and block

structures that are still structurally sound but are exhibiting signs of distress that could eventually

fail and require complete removal and replacement. Many manholes exhibit distress within the

top 24 inches of the structure as a result of the climatic conditions associated with repetitive

freeze-thaw cycles and as a result of traffic loads. If a manhole exhibits distress at a depth

greater than 24 inches, but is still structurally functional, then the full depth of the manhole is

lined using either a cement or polyurea coating system. Manholes that are severely distressed, or

are within the boundary of a sewer replacement project are typically replaced.

2.0 POLLUTION PREVENTION PLAN

2.1 POLICY AND SERVICES

The City of Berwyn has implemented policies, programs and services to limit the amount of

floatables and contamination of CSO. Programs include; a street cleaning program, mulching in

substitute of fertilizers, minimization of herbicide use, and public education.

2.2 STREET CLEANING

The City’s street sweeping program runs year round. During this period the entire City is swept

on a routine basis, within a week. Sweeping rids streets of residue salt and removes significant

amount of leaves, debris, and fluids leaked from parked vehicles. The result is a significant

reduction in floatables and contamination during significant rainfall events.

The City also has a policy prohibiting residents from dumping leaves onto the street in the fall.

Instead residents are instructed to bag leaves, which can be picked up during normal yard waste

collection. This prevents clogging of catch basins and reduces floatables during significant

rainfall events.

Page 190: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

12

After every significant rainfall event City maintenance workers will scan City streets to pick up

downed braches and other debris.

2.3 FERTILIZERS AND PESTICIDES

The City does not use fertilizer for public parkways. Instead cut grass and fallen leaves are

mulched into the lawn. Herbicides are used on a limited basis at the lowest concentration

practicable.

2.4 WATER CONSERVATION

The City has a chapter on water conservation in its codified ordinances. Included in this chapter

are; requirements that car wash facilities are equipped with a water recycling system; owner’s

responsibility to repair water leaks on private property; limitations on sprinkling between June 1

and September 30; and proper use and maintenance of rain barrels. More details can be found in

Chapter 1050 of the City’s codified ordinances.

2.5 SOLID WASTE COLLECTION

The City of Berwyn, in cooperation with Waste Management, provides a recycling, solid waste

and yard waste disposal program. Items that can be recycled include: newspaper, magazines,

junk mail, paper, cardboard (corrugated and non-corrugated), plastic bottles (# 1, 2, 3, 4, 5, and

7), aluminum, glass, and beverage cartons. The collection schedule is available on the City’s

website and is attached to this plan.

2.6 ILLEGAL DUMPING

Illegal dumping is prohibited by City code. Compliance is monitored by both Police and Public

Works personnel. The City has also established the Clean City Committee by ordinance. This

committee also reviews ordinances in regards to litter control and dumping, while providing

suggestions for improvements to these policies and enforcement.

2.7 BULK REFUSE

One bulky item such as an appliance or furniture can be collected per week on a regularly

scheduled collection day at no additional cost. Construction and building materials, loose

materials, or additional bulky items require a special pickup. Residents are instructed to call

Waste Management at (800) 796-9696 or www.wm.com for additional information.

Page 191: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

13

2.8 HAZARDOUS WASTE

The City of Berwyn is a member of the West Cook County Solid Waste Agency (WCCSWA).

The WCCSWA has developed a plan to provide for the efficient and environmentally sound

collection, transportation, transfer, processing, treatment, storage, disposal, recovery, and reuse

of municipal waste. Materials such as pesticides, poisons, cleaning solvents, gasoline, used oil

and automotive fluids, and other flammable, toxic, or corrosive liquid material can be dropped

off at designated locations through the agency. More information is available by contacting

WCCSWA directly by phone (708) 450-0100 or by going to their website at

www.westcook.org/wccswa.

Page 192: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

       

Appendix G  

Anticipated Project Revenues/Expenses  

 

 

Page 193: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

ANTICIPATED PROJECT REVENUES/EXPENSESUTILITIES FUND (Water,Sewer, and Garbage)

ITEM FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34

Operating Revenues 14,445,691                                                14,985,691            15,167,976      15,281,735      15,396,348      15,511,821              15,628,160             15,745,371    15,863,461        15,982,437    16,102,305    16,223,073    16,344,746    16,467,331    16,590,836    16,715,268      16,840,632      16,966,937      17,094,189    17,222,395    17,351,563    17,481,700   

Operating Expenses 13,027,380                                                13,950,000            14,040,332      14,140,777      14,245,181      14,351,459              14,458,904             14,567,281    14,676,514        14,786,580    14,897,477    15,009,207    15,121,776    15,235,189    15,349,453    15,464,574      15,580,558      15,697,412      15,815,143    15,933,756    16,053,260    16,173,659   

Net Operating Revenue 1,418,311                                                  1,035,691               1,127,643        1,140,959        1,151,167        1,160,362                1,169,255               1,178,090      1,186,947          1,195,857      1,204,828      1,213,866      1,222,970      1,232,142      1,241,383      1,250,694        1,260,074        1,269,524        1,279,046      1,288,639      1,298,304      1,308,041     

Interest Income 7,257                                                          10,357                    11,276              11,410              11,512              11,604                      11,693                     11,781            11,869                11,959            12,048            12,139            12,230            12,321            12,414            12,507              12,601              12,695              12,790            12,886            12,983            13,080           

Proposed Loan Revenue ‐                                                              ‐                           8,000,000        ‐                     ‐                     ‐                             ‐                           ‐                   ‐                       ‐                   ‐                   ‐                   ‐                   ‐                   ‐                    ‐                     ‐                     ‐                    ‐                   ‐                   ‐                   ‐                  

Net Income 1,418,311                                                  1,035,691               9,127,643        1,140,959        1,151,167        1,160,362                1,169,255               1,178,090      1,186,947          1,195,857      1,204,828      1,213,866      1,222,970      1,232,142      1,241,383      1,250,694        1,260,074        1,269,524        1,279,046      1,288,639      1,298,304      1,308,041     

Debt Service

  Existing Debt Payments 119,453                                                      160,756                  229,224            329,224            310,056            330,993                    257,275                  276,650          345,525              360,525          274,525          266,525          258,525          250,275          291,775          281,150            345,525            4,275                99,275            99,276            99,277            99,278           

  Proposed IEPA Loan Payments ‐                                                              ‐                           546,411            552,416            544,000            536,000                    528,000                  520,329          512,000              504,000          496,000          488,241          480,000          472,000          464,000          456,153            448,000            440,000            432,000          422,066          416,000          408,000         

Total Debt Service 119,453                                                      160,756                  775,635            881,640            854,056            866,993                    785,275                  796,979          857,525              864,525          770,525          754,766          738,525          722,275          755,775          737,303            793,525            444,275            531,275          521,342          515,277          507,278         

Net Revenue 1,298,858                                                  874,935                  8,352,008        259,319            297,111            293,369                    383,980                  381,111          329,422              331,332          434,303          459,100          484,445          509,867          485,608          513,391            466,549            825,249            747,771          767,297          783,027          800,763         

Debt Service Coverage 11.87                                                          6.44                         1.45                   1.29                   1.35                   1.34                           1.49                         1.48                 1.38                     1.38                 1.56                 1.61                 1.66                 1.71                 1.64                 1.70                   1.59                   2.86                  2.41                 2.47                 2.52                 2.58                

Equipment Replacement ‐                                                              300,000                  303,000            250,000            252,500            255,025                    257,575                  260,151          262,753              265,380          268,034          270,714          273,421          276,156          278,917          281,706            284,523            287,369            290,242          293,145          296,076          299,037         

Anticipated Surplus 1,298,858                                                  574,935                  8,049,008        9,319                44,611              38,344                      126,405                  120,960          66,670                65,952            166,270          188,385          211,024          233,712          206,691          231,684            182,026            537,881            457,529          474,152          486,950          501,726         

Beginning Net Position 26,658,058            27,232,993      27,282,001      27,291,320      27,335,931              27,374,275             27,500,680    27,621,639        27,688,309    27,754,261    27,920,531    28,108,916    28,319,940    28,553,652    28,760,343      28,992,027      29,174,053      29,711,934    30,169,463    30,643,615    31,130,565   

Anticipated Project Expenses ‐                           8,000,000        ‐                     ‐                     ‐                             ‐                           ‐                   ‐                       ‐                   ‐                   ‐                   ‐                   ‐                   ‐                    ‐                     ‐                     ‐                    ‐                   ‐                   ‐                   ‐                  

Ending Net Position 27,232,993            27,282,001      27,291,320      27,335,931      27,374,275              27,500,680             27,621,639    27,688,309        27,754,261    27,920,531    28,108,916    28,319,940    28,553,652    28,760,343    28,992,027      29,174,053      29,711,934      30,169,463    30,643,615    31,130,565    31,632,291   

Operating Revenue and Expenses for FY13 are Final

Operating Revenue for FY14 is projected at: 14,985,691$           

0.65%  to  0.75%  per year

0.75%  per year

Interest Income as a percentage of Net Operating Revenue: 1.00%

Projected Interest Rate for IEPA Revolving Loan Program 2.00%

Repayment Period for IEPA Revolving Loan Program 20 years

Number of Payments per Loan per Year 2

0.75% per year

5.00%compared to FY 

2013

Operating Expenses for FY 19‐ FY 34 are projected to increase about:

Based on the Proposed 17% Water Rate Increases, Operating Revenue for FY15 is 

projected to increase at:

1.22%

compared to 

Projected FY 2014   

or

Operating Expenses for FY 15‐ FY 18 are projected to increase about:

Based on Historical Trends, Operating Revenue is expected increase annually for FY 16‐FY 

34 at:

Page 194: Berwyn Wastewater Facility Plan 2014 (City and Depot District)

Current 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

F1 ‐ One dwelling unit $4.37 $4.59 $4.82 $5.06 $5.31 $5.58 $5.86 $6.15 $6.46 $6.78 $7.12 $7.47 $7.85 $8.24 $8.65 $9.08 $9.54 $10.02 $10.52 $11.04 $11.59 $12.17

F2 ‐ Two dwelling unit $5.61 $5.89 $6.19 $6.49 $6.82 $7.16 $7.52 $7.89 $8.29 $8.70 $9.14 $9.60 $10.07 $10.58 $11.11 $11.66 $12.25 $12.86 $13.50 $14.18 $14.89 $15.63

F3 ‐ Three dwelling unit $7.12 $7.48 $7.85 $8.24 $8.65 $9.09 $9.54 $10.02 $10.52 $11.05 $11.60 $12.18 $12.79 $13.43 $14.10 $14.80 $15.54 $16.32 $17.14 $17.99 $18.89 $19.84

F4 ‐ Four dwelling unit $8.65 $9.08 $9.54 $10.01 $10.51 $11.04 $11.59 $12.17 $12.78 $13.42 $14.09 $14.79 $15.53 $16.31 $17.13 $17.98 $18.88 $19.83 $20.82 $21.86 $22.95 $24.10

Commercial $0.16 $0.17 $0.18 $0.19 $0.19 $0.20 $0.21 $0.23 $0.24 $0.25 $0.26 $0.27 $0.29 $0.30 $0.32 $0.33 $0.35 $0.37 $0.39 $0.40 $0.42 $0.45

min. charge $1.68 $1.76 $1.85 $1.94 $2.04 $2.14 $2.25 $2.36 $2.48 $2.61 $2.74 $2.87 $3.02 $3.17 $3.33 $3.49 $3.67 $3.85 $4.04 $4.25 $4.46 $4.68

Religious/Education $0.16 $0.17 $0.18 $0.19 $0.19 $0.20 $0.21 $0.23 $0.24 $0.25 $0.26 $0.27 $0.29 $0.30 $0.32 $0.33 $0.35 $0.37 $0.39 $0.40 $0.42 $0.45

min. charge $1.68 $1.76 $1.85 $1.94 $2.04 $2.14 $2.25 $2.36 $2.48 $2.61 $2.74 $2.87 $3.02 $3.17 $3.33 $3.49 $3.67 $3.85 $4.04 $4.25 $4.46 $4.68

Sewer Fund Rate Increases 5% Annual Increase