Page 1: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

1

BIM Application inHong Kong Housing Authority

BIM in Project ManagementBIM in Project Management2 April 20142 April 2014

Speaker :

Mr. Lawrence K.W. CHUNG

Assistant Director of Housing

(Development & Construction Division)

HKIPM-HKIBIM Joint ConferenceHKIPM-HKIBIM Joint Conference

Page 2: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

2

Contents(I) Introduction to Housing Authority (HA) and

Information and Communication Technology (ICT) in HA

(II) Concept of Building Information Modelling (BIM) Application and BIM in Current Projects

(III) Integration of BIM and GIS

(IV) Change Management

(V) Way Forward and Conclusion

Page 3: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

3

• The Hong Kong Housing Authority (HA) is a statutory body established in April 1973 under the Hong Kong Housing Ordinance. The Housing Department is HA’s executive arm.

• HA develops and implements a public housing programme to meet the housing needs of people who cannot afford private housing.

• Approximately 30% of the Hong Kong population is now living in public rental housing units.

• The HA has an existing stock of about 730,000 rental flats.

• We build 79,000 new PRH flats for five years from 2012/13 to 2016/17 and build 100,000 new PRH flats for the five years starting from 2018.

• We build 17,000 new HOS flats for four years from 2016/17 to 2019/20 and thereafter 5,000 new HOS flats a year.

Hong Kong Housing AuthorityHong Kong Housing Authority(I) Introduction to HA and ICT in HA

Page 4: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Information & Communication Technology (ICT)

4

Page 5: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

5

(II) Concept of BIM & Application of BIM in Current Projects

Modelling

Page 6: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

6

BIM’s Versatility

Rendering

Performance Analysis

Collision Check

2D Drawings

Material Quantities

BIM Models

Simulation

Visual Impact

Construction Design

Page 7: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Ecotect(Performance Analysis)

Cost X(Material Quantities)

Navisworks (Collision Check)

BIM Software

Revit(BIM Modeling)

Navisworks (4D Simulation)

Solibri(Code Checking)

ETABS/ ORION (Structural Analysis)

3D Max (Photo-realistic Rendering)

Civil 3D(CE/GE Design)

7

DIALux(Lighting Analysis)

IES(Energy Simulation)

Page 8: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

ARCHITECTURALMODEL

CIVIL INFRASTRUCTURE

BUILDING SERVICES MODEL

LIGHTINGDESIGN

BIM Server BIM Server

BIM ServerBIM Server

SOLARSTUDY

GIS

4D PROGRAMME

CLASH DETECTION

GLARE ANALYSISOF PV PANEL

VISUALISATION THERMALCOMFORT

SITECONTEXT

DESIGNREVIEW

6D ASSETMANAGEMENT

ENERGYSIMULATION & C-FOOTPRINT

Model checker

5D COSTPLAN

STRUCTURALANALYSIS

LandsD 3D SpatialData Viewer

E-Submission SCHEDULING

STRUCTURAL MODEL

CONSTRUCTION SIMULATIONSAFETY

MANGEMENT

BIM SoftwareBIM Software

BIMServer

Page 9: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

HA’s Project Development Life Cycle

Completion, Management and Maintenance

Feasibility studies and Conceptual layout

Scheme Design and Project Budget

Detailed Design and Specification

Tender Construction of Foundation / Building

Design Options Building Design and Performance Documentation Quality Control Facility Management

Design Design OptimizationOptimization

Construction Construction SimulationSimulation

Life Cycle Life Cycle ManagementManagement

Project Life Cycle

9

Page 10: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

10Assembly of Standard Modular Flats to forma Domestic Block

Quick Assembly of Domestic Blocks

Page 11: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Enhance Quality of Design

Daylight Analysis

Sunlight & Shadow Studies

XX XX

Anderson Road Site D

Wind flow Studies 11

Page 12: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

12

► Excavation volume► Excavation volume► CUT / FILL volume of each Mass

Fill

Enhance Cost Control andEnvironmental Protection

Tung Tau Cottage Area East Site Formation

Balancing of Cut and Fill volume

Page 13: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

13

Clashes Detection3D Model of Underground Services

Clash Analysis in Congested Area

Sheung Shui Area 36

Page 14: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

14

BIM Virtual ModelActual Construction

Better Building Services Co-ordination

Yau Lai Shopping Centre Building Services Installation

Page 15: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

15

Optimize Lighting Design for Energy Saving

Development of more energy efficient lighting operation mode.

Integration of neighborhood, building and surrounding lighting contribution to achieve optimum site lighting design.

Accurate simulation of 3D lighting level.

Sheung Shui Area 36

Page 16: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

16

Check and ensurePV Panels are not located in Shading Area

Sun Path Simulation

Shading Analysis on PV Panel

Sheung Shui Area 36

Page 17: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

17

No Glare Nuisance to Nearby Buildings

Glare Analysis of PV Panel

Glare Analysis of PV Panel

Sheung Lok Street HOS

Page 18: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

18

Simulated Pattern of Daily Cooling Load Required

Solar Heat Gain SimulationUsing 3D BIM Model

Energy Simulation

HOS Development at Sha Tsui Road

Page 19: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

19

As-fitted Drawing Linked to BIM ModelBIM FM Model

BIM in Facility Management

Sharing equipment inventory / maintenance record through dialogue

between two systems

BIM FM ModelBIM FM Model As-fitted Drawing Linked to BIM ModelBIM FM Model

Linking BIMto RFID??

Page 20: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

20

3D Printing Triggers Innovative Ideas

Kwai Chung Tai Pak Tin Street - Simulation of Construction Site Planning

Sheung Shiu Area 36 – Coordination of Building Services

Page 21: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

21

HOS at Wang Yip Street West, Yuen Long

Simulate the Construction Sequence of ELSW & Buoyancy Raft

Illustrate Geological Profile of the Site

Geological Profile & 4D Model for ELS

Page 22: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

22

BIM as a Value Management ToolHin Tin Street, Shatin Area 31

Page 23: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Shui Chuen O Phase 1, Shatin, Hong Kong :

5D BIM Model

Reveals actual and predicted cash flow of the project.

Better understanding of project cash flow.

Cash flow simulation has been created by the integration of extracted quantities from BIM model, construction programme and cost information.

23

Page 24: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

24

Tung Tung Cottage Area East, Kowloon City, Kowloon

Construction Management

Site Layout Planning Clashes Study

Virtual Rehearsal : Six-day Cycle for Typical Floor Rebars Fixing & Services Installation Collaboration

24

Page 25: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

25

Site Safety Planning

Lower Ngau Tau Kwok Estate - Simulation of Site Safety Planning

Page 26: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

26

Construction Site Planning

Kwai Chung Tai Pak Tin Street - Simulation of Construction Site Planning 26

Page 27: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

27

6-Day Construction Cycle

Kwai Chung Tai Pak Tin Street - Simulation of 6 Day Construction Cycle 27

Page 28: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

28

(III) Integration of BIM and GIS

Page 29: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Development of Geographic Information System & Application in HA

Web based 2D GPIS for Planning Studies

3D GIS for Feasibility Studies, & Design

2009 2012

Desktop GPIS for Planning Studies

2005

3D GIS for Facilities Manage-ment

2013

Site Feasibility Study Visual Impact Analysis (Sightline & Corridor)

Terrain Modelling

Building HeightRidgeline

DCD EMD

29

Page 30: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

GIS Applications – Contextual Study

30

Page 31: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

GIS Applications – Spatial Planning

Study the connection between proposed buildings, external works, open space and landscape areas for the project 31

Page 32: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Proposed Buildings

Selected Viewpoint at Shing Mun River, No. 2 Promenade Rest Garden

GIS Applications – Ridge Line Analysis

32

Page 33: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Skyline Surface for checking the visual impact on the ridge lines

GIS Applications – Ridge Line Analysis

33

Page 34: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

GIS Applications – Schemes Comparison Fo Tan Cottage Area, Shatin

34

Page 35: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Airflow Analysis Trial at Tai Wo Hau Road, Kwai Chung

• Existing spatial data directly used in airflow simulation for a proposed project at Kwai Chung

• Quantitative simulation results are visualized and as input to further spatial analysis.

• Optimize the design with aid of iterative simulation.

• Benchmarking tests in progress

Geo-spatial Simulation Airflow Impact Analysis

GIS Applications - Micro-climate Studies

35

Page 36: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

BIM (Graphics & Attributes) GIS

Autodesk Revit

BIMserver & BIMsurfer (Viewer)with JRE Update 7

FME

Batch Conversion of Floor Plans and Attributes using ArcPy and Data Interoperability

Extension in ArcGIS

Floor Plans in BIM

Geo-database in ArcGIS Attributes

and all other related

Information in BIM

Geo-reference Floor Plans in

BIM

Export to IFC Format

Export to Excel Format

INTEGRATION

Method 1

Method 2

FME = Feature Manipulation Engine

Geo-spatial Simulation

Page 37: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

GIS +BIM Applications – Colour Scheme Study

37

Page 38: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

GIS +BIM Applications – Geotechnical Study

Geotechnical Study (Design Cut Slopes, Fill Slopes, Retaining

Wall and Screen Wall in Civil 3D environment)

Perform 3D Visualization and

animation in GIS environment

38

Page 39: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

39

(IV) Change Management

Page 40: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

40

BIM is not just a tool,BIM is not just a tool,it brings transformationit brings transformation

to construction industry…to construction industry…

Page 41: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Transformation Process

BIM 3D modelling, Analysis, 3D printer, RFID, GIS, R&DTechnologies

Upfront design process, re-engineering, office procedures, disciplines practices, industry practices

Processes

Tighter team formation, multi-disciplinary team, supporting team structureOrganization

Collaboration among project team, consultants, contractors and subcontractors.

Partnership

BIM skill, think ahead, teamwork, change management, industry practitioners, academia, workforce

People

We

tran

sfor

m

ours

elve

s in

us

e of

BIM

BIM

tr

ansf

orm

s ou

r bu

sine

ss

41

Page 42: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

42

Challenges - BIM ProcessShifts the Design Curve

Patrick MacLeamy, CEO of HOK

Page 43: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Transformation – Organization & People

Year 20102009 2011

BIM Project Steering Committee

BIM Working Group

BIM Centre & BIM Service Team

Experience Sharing; SeminarsExperience Sharing; Seminars

Training; WorkshopsTraining; Workshops

Site Team BIM Working Group

Change Management

Training & Seminars

43

Page 44: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

44

Centralized BIM Team

Training

Discussion

Hardware and software support

BIM Central Support -BIM Services Team and BIM Centre

Act as in-house consultant team to provide support, collect feedback, arrange training and facilitate knowledge & experiences sharing (~2000 users)

44

Page 45: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

HA BIM Standards & User Guides

http://www.housingauthority.gov.hk/en/businesspartners/buildinginfomodel45

Page 46: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

HA Standard Library

Revit MEP Families

Revit Architectural Families

Revit Structural Families

46

Page 47: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

47

Training to HA Staff (includes professionals & technical staffs)

Our Goal Apply BIM to all new projects from design stage by 2014/15

About 1,360 staffs(about 70%)*

* As at the end of December 2013

• Architects• Building Services

Engineers• Civil Engineers • Geotechnical Engineers• Land Surveyors• Landscape Architects• Planners• Quantity Surveyors• Structural Engineers• Site StaffTentatively, it will be more than 85% in 2015

Page 48: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

48

We Walked the Extra Mile

Promote to our Professional Service Providers (e.g. Promote to our Professional Service Providers (e.g. architects, engineers & surveyors…) and contractorsarchitects, engineers & surveyors…) and contractors

Promote to academia e.g. HKU, PolyU, CUHK, CityU, Promote to academia e.g. HKU, PolyU, CUHK, CityU, HKUST etc.HKUST etc.

48

Page 49: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

49

HK BIM Awards for five consecutive years 2009 -2013 2009: Towards Customization with Standard Modular flats

in Mass Housing Design

2010: Transforming the whole Delivery Practice 2011: Versatile BIM / What You See is What You Can Do

2012: Pioneering 5D BIM for Quantity Surveying 2013: Fast-track HOS and Site Coordination in a PRH

project: Hin Tin Street HOS & Wang Ip Street HOS, and Tung Tau Cottage Area East

. Meritorious award for Civil Service Outstanding Service

Award Scheme 2011

HK ICT Awards 2012 – Silver

49

Page 50: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

50

(V) Way Forward &

Conclusion

Page 51: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

51

Local Universities & Academia

• Prevalent research topics.• BIM courses.

Professional Service Providers• BIM models support submissions.

Construction Industry• Enhance collaboration among design team, contractors, sub-contractors & suppliers.• Contractors have set up their own BIM working teams.

Major Government Departments

Construction Industry Council

• BIM Task Force in the Construction Industry Council of Hong Kong• Chaired by Ms. Ada Fung with members from academia, professional institutes,

developers associations, government departments, etc.• Develop a BIM roadmap for HK Construction Industry

Impact for Hong Kong

Page 52: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Completion, Management and Maintenance

Feasibility studies and Conceptual layout

Scheme Design and Project Budget

Detailed Design and Specification

Tender

HA’s Proposed BIM R&D Items

Construction of Foundation / Building

Design Options Building Design and Performance Documentation Quality Control Facility Management

1. Assist Feasibility Studies

2. Environmental Studies

3. BIM Model - Drawings Integration

6. Integration with Specification

7. ICU Submission

4. Design/Analysis Software Integration

8. Building Code Checking

9. Construction Planning and Site Safety

10. Facility Management

BIM R&D Items

Design Design OptimizationOptimization

Construction Construction SimulationSimulation

Life Cycle Life Cycle ManagementManagement

Project Life Cycle

52

5. Energy Performance

Page 53: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Design Options Building Design and Performance Documentation Quality Control Facility Management

SitePlanning Programme Project Contract PaymentBudget Cabin Sr. ExecutiveKnowledge Management

ProjectManagement

GIS (Geo-spatial Database Infrastructure)

Geo-Spatial

ProjectLife Cycle

Feasibility studies and Conceptual layout

Scheme Design and Project Budget

Detailed Design and Specification

Tender Evaluation

Completion, Management and Maintenance

Construction of Foundation / Building

BIM (Building Information Modelling)

Convergence

Housing COnstruction Management Enterprise System (HOMES)

BuildingInformation

Enhancement of HOMES:Integration of RFID into HOMES construction module

Choice of materials Site material tracking &monitoringRFID

Study on Integration of GIS, BIM, HOMES & RFID

53

Page 54: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

As-built Survey (From Point Cloud to BIM)3D Realistic Point Cloud

Model from Laser Scanning

Floor / Area Plan

Point CloudBIM System

Import Point Cloud into BIM

54

Page 55: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Who get the benefit?

General Public

Public Housing Tenants

Building ServicesEngineer

Planner

Housing Authority

BIMBIM

Structural Engineer Architect

Contractor

Worker

Supplier

Business Partner

Sub-contractor

Environmental Economic Social

Sustainability 55

Page 56: BIM Application in Hong Kong Housing Authority by Mr. Lawrence K.W. CHUNG

Thank YouThank You

Let’s join hands to use BIM and construction IT systems.