BMSB Renovation and Teaching Facilities: Where Are We?. Hector Sun-On Chan. BMSB renovation: Construction works started in mid June 2012. Phase I - Works on LG/F, 1/F, 2/F and 6/F were completed in 3 Sept 2012 and the TEACHING AREAS on these floors were reopened. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/1.jpg)
BMSB Renovation and Teaching Facilities:
Where Are We?
Hector Sun-On Chan
![Page 2: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/2.jpg)
BMSB renovation:1. Construction works started in mid June 2012.
2. Phase I - Works on LG/F, 1/F, 2/F and 6/F were completed in 3 Sept 2012 and the TEACHING AREAS on these floors were reopened.
3. Phase II - Construction work is still on-going at the other floors and non-teaching areas (G/F, 3/F, 4/F and 5/F). Expected completion date is 9 Dec 2012.
![Page 3: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/3.jpg)
New Dissecting Laboratorywith ventilated dissecting tablesand surgical light
![Page 4: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/4.jpg)
Embalming Tables
Temporary storage refrigerator
![Page 5: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/5.jpg)
Mortuary cold room for 90 cadavers
![Page 6: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/6.jpg)
Tutorial and Specimen Room of Dissecting Laboratory
![Page 7: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/7.jpg)
Demonstration on Upper Limb on 18 Sept 2012
![Page 8: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/8.jpg)
Demonstration on Upper Limb
![Page 9: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/9.jpg)
3 Teaching Laboratories and 2 Tutorial Rooms on 1/F, 2/F and 6/F
![Page 10: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/10.jpg)
2 Computer Laboratories with 120 workstations
![Page 11: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/11.jpg)
Phase II Works
![Page 12: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/12.jpg)
Entrance of BMSB on G/F
![Page 13: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/13.jpg)
New Lobby with two elevators
![Page 14: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/14.jpg)
Conference Room on G/F
![Page 15: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/15.jpg)
Student Learning Commons of 480 m2
![Page 16: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/16.jpg)
Student Learning Commons with Catering Services
![Page 17: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/17.jpg)
7 Tutorial Rooms on 3/F
![Page 18: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/18.jpg)
11 Teaching Laboratories, 2 Tutorial Rooms and 2 Computer Laboratories on 4/F and 5/F
![Page 19: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/19.jpg)
BMSB renovation:1. Users should enter the building through the lift
lobby and Staircase 2 on LG/F, and Staircase 1 on G/F (adjacent to the Medic Canteen).
2. Only users of the 6/F can use the lift on LG/F within blocked time slots (Mon and Tue: 2:00pm-6:00pm; Thur: 9:00am-6:00pm). Users of other floors, please should use the staircases.
3. Construction work is still on-going at the other floors and non-teaching areas. Entrance to these floors and areas is strictly PROHIBITED.
![Page 20: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/20.jpg)
Entrance to BMSBRenovation of BMSB:
![Page 21: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/21.jpg)
Entrance to BMSB
Renovation of BMSB:
![Page 22: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/22.jpg)
Clinical Skill Learning Centre Extension:1) Renovate the Medical
Record/OT Changing Room into a teaching area (264.8 m2).
2) Funding was secured from Minor Works Fund and Kai Chong Tong.
3) Work started on 19 September 2012.
4) Expected Completion Date: End of November 2012.
![Page 23: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/23.jpg)
23
Budget: about 2 milSource: Minor Works Committee
![Page 24: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/24.jpg)
Project Start Date
Completion Date
Funding Source
Spatial Reorganization of 2/F Clinical Sciences Bldg, PWH (Lecture Theatre, Medical Library, Seminar Room, MIT, CSLC)
May 2011 Aug 2011 UGC ($20.6M), Minor Works (0.28M)
Spatial Reorganization of Basic Medical Sciences Building
Mid June 2012
9 Dec 2012 UGC ($21M), CUHK ($9M and Loan $16M)
Clinical Skills Learning Centre Expansion, Clinical Service Block, PWH
19 Sept 2012
End of Nov 2012
Kai Chong Tong (2.5M), Minor Works (1M)
Renovation of LG/F of BMSB (1 Teaching Laboratory and 3 Tutorial Rooms)
- - Possible source: Minor Works (2M)
Spatial reorganization of BMSB Extension and Science Centre East Block
2013/14 - UGC (21M), pending approval of Legislative Council
Development Plan for Upgrading Teaching Facilities inFaculty of Medicine
![Page 25: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/25.jpg)
Hey guy, that’s a really nice working environment.
![Page 26: BMSB Renovation and Teaching Facilities: Where Are We?](https://reader037.vdocument.in/reader037/viewer/2022110215/5681685d550346895dde9cd0/html5/thumbnails/26.jpg)
AcknowledgementsUGCCUHKKai Chong TongPrince of Wales HospitalCampus Development Office; Estate
Management OfficeFaculty Office, Clinical Science Administration,
Planning Office, MDL, MIT, CSLC, Medical Library
Teaching Facilities CommitteeDean