PT PLN (PERSERO) Off-Grid Islands Electricity Workshop Rizki Asikin New and Renewable Energy Division Bunaken, Nov 4 th 2015

Upload: smart-villages

Post on 18-Jan-2017

59 views

Category:

Government & Nonprofit


1 download

TRANSCRIPT

PT PLN (PERSERO)

Off-Grid Islands Electricity Workshop

Rizki Asikin

New and Renewable Energy Division

Bunaken, Nov 4th 2015

PLN BUSSINESSES

Generation

Controls approximately

43,457 MW of installed

generating capacity, over

85% of Indonesia’s total

Owns and operates 1,267

generation plants

Main purchaser of

electricity from

Independent Power

Producers (IPPs)

Transmission

Sole provider of power

transmission in Indonesia

Approximately 52,134

kmc of transmission lines

90,342 MVA of

transmission transformer

capacity

PLN Business Segments:

Distribution

Sole distributor of

electricity to end

customers in Indonesia (1)

Approximately 833,902

kmc of distribution lines

and 45,024 MVA of

transformer capacity

Serving approximately

56 million customers

PLN is the state-owned enterprise of power utility in Indonesia.

NEW & RENEWABLE ENERGY DIVISION OF PT PLN (Persero)

• It is under the Corporate Planning Directorate • Main task covers the development of new and renewable

energy, either by PLN or Independent Power Producer (IPP). • There are 3 sub-divisions:

a. Hydro b. Geothermal c. Alternative (Biomass, Wind, Solar PV, Ocean, Nuclear,

Coal Slurry, Hydrogen, etc.)

3

DIESEL 49,7 %

GAS 20,1 % COAL

24,5 %

RE

5,7%

DIESEL 25%

GAS 22%

COAL 30%

RE 23%

JUNE 2015

Average Energy Consumption 7% per Year

RE in National Energy Mix 5%

Increase of RE to 23% in 2015

TARGET OF 2025

(PP No. 79 Tahun 2014 about

Kebijakan Energi Nasional)

Gas

Geothermal

Hydro

LNG

HSD MFO

Coal

1. President regulation No. 4/2010 instructed PLN to

accelerate the RE development

2. GOI has set a goal that 23 % of national energy

mixed in 2025 shall come from RE

3. GOI set a target to increase electrification ratio 99,5

% by 2025

4. GOI introduced Feed in Tariff for small RE ≤ 10 MW

5. PLN is obliged to purchase the electricity from RE

power generation (take and pay)

POLICY AND TARGET

6

PLN EXPERIENCE(S) IN

OFF-GRID DEVELOPMENT

INTRODUCTION

BACKGROUND:

• The major domination of diesel generator in remote islands.

• Cost of electricity fuel/diesel based is expensive .

• Challenge in fuel supply (transportation)

GOALS:

• Reduce the diesel consumption

• Increase the ratio of electrification

• Increase the development of new and renewable energy.

• Reduce the cost of electricity.

CONSIDERATIONS

MAIN PRIORITY FOR REGIONS WITH:

• High diesel/fuel consumption

• Remote or isolated areas / islands

• Expensive cost of electricity production

• Limited alternative of energy sources to produce electricity

• No electricity access whatsoever

• Limited availability of electricity (up to 12 hours per day)

STRATEGY

STRATEGY:

• Work with local government in land relinquishment

• Prioritize the use of Diesel – Solar PV Hybrid by using the existing diesel

engine

• Options of either on-grid connection, off-grid, or hybrid depending on the

existing grid on the site

• Limit the penetration of intermittent sources (PV, Wind, etc.) up to 20% of

daytime peak load (especially for on-grid)

• Provide electricity of up to 12 hours in areas where no access to electricity

• Increase the electricity availability for up to 24 hours in area where electricity

access is limited

• Open for IPP scheme or assigned by EBTKE

PLTS ON GRID

GRID PLTS ON GRID

PANEL PV INVERTER TRAFO

PLTS OFF GRID (PV + BAT; MICRO GRID)

GRID

PLTS

PLTS OFF GRID

PANEL PV INVERTER TRAFO CHARGE

CONTROLLER

PLTS HYBRID (MICRO GRID)

PLTS HYBRID

PANEL PV TRAFO

INVERTER CHARGE

CONTROLLER

JAR. DIST. 20 kV

BATTERY

GENERTOR

DIESEL

GRID

PLTS

SOLAR PV DEVELOPMENT IN INDONESIA

PLTS 6

TOURISTIC ISLANDS

(6 locations; 0,92 MWp)

PLTS 11

FRONTIER ISLANDS

(5 locations; 1,35 MWp

4 lokasi batal)

PLTS 100 PULAU IT

(36 locations; …….MWp.

78 location is cancelled)

PLTS 1000 ISLANDS (REEP Project)

(94 lokasi di NTT; 20 MWp. Consultant Procurement)

2010 02/2012 06/2012 2015 2013

EXAMPLE: PLTS AIR MAMA, ALOR

PROJECT:

- Name : PLTS Air Mama

- Capacity: 125 kWp

- Population: 190.026 people ( ±500 residentials)

- Average Sun Irradiation : 5,63 kWh/m2/day

Latar Belakang:

Desa Air Mama has yet no electricity access. Nearest PLTD is in Baranusa with

operational hours up to 12 hours. The closest diesel supply (Pertamina’s depot) is ± 125

km away in Kalabahi with transportation cost Rp. 780 /litre by motor boat (total fuel tank

storage of 20.000 litre). PLTS Air Mama will be connected to distribution lines of MV 20

kV and LV 220 V of ±10 kmc and ±12 kmc, respectively). This scheme will increase the

electricity supply for up to 24 hours.

1. The potential of RE development in Indonesia is

challenging and promising, therefore Indonesia is

attractive for RE industries

2. PV Development is aimed to increase the

electrification ratio and to reduce the diesel fuel

consumption in remote areas/island

CLOSING REMARKS

THANK YOU

17

KELEBIHAN DAN KEKURANGAN TIAP KONFIGURASI PLTS

ASPEK ON GRID OFF GRID HIBRID (PLTD+PLTS)

KEUNTUNGAN

- Investasi rendah

- Biaya O&M sangat rendah

- LCOE (levelized cost of

electricity) rendah

- Tidak butuh BBM

- Tujuan mengurangi BBM

- CF tinggi

- Daya Stabil

- Manfaat langsung ke masyarakat

- Biaya O&M rendah

- Operasi bisa 24 jam

- Daya stabil

- Manfaat langsung masyarakat

- Investasi sedang

- Biaya O&M sedang

- Opoerasi 24 jam

- LCOE sedang

KELEMAHAN

- Daya Tidak Stabil (Butuh Grid)

- Manfaat langsung hanya untuk

PLN

- Hanya operasi siang

- Investasi tinggi

- LCOE sangat tinggi

- Operasi bisa 24 jam

- Biaya penggantian batere tinggi

- CF rendah

- Masih butuh BBM (terbatas)

- Kontrol lebih kompleks

- DG harus disiapkan dari awal

rencana

- CF sedang

Tarif Jual Listrik dari Pembangkit EBT

Jenis Pembangkit EBT Tarif jual listrik Rp/KWh

1 PLTBiomass 1150-1840

2 PLTMH 940-1500

3 PLTA 700-1000

4 PLTP 1000 Sd 1400

5 PLTS 2600 - 2900

6 PLTBayu 1500

Rata-rata tarif dasar listrik 980

19

Regulasi Pemerintah Tentang Energi Baru Terbarukan

Peraturan Presiden RI No 5 Tahun 2005: tentang Kebijakan Energi Nasional . Menjelaskan tentang jenis energi yang termasuk energi baru dan terbarukan

Peraturan Menteri ESDM, yang mengatur tentang: • Proses administrasi pengadaan proyek EBT • Kelengkapan dokumen proyek • Harga listrik dari pembangkit EBT • Ijin Usaha Penyediaan Tenaga Listrik

Permen ESDM untuk pembangkit EBT, untuk skala sd 10 MW: Peraturan Menteri ESDM No 4 tahun 2012: tentang harga pembelian tenaga listrik

dari energi terbarukan atau kelebihan tenaga listrik Peraturan Menteri ESDM No 17 tahun 2013 tentang Harga pembelian tenaga listrik

dari PLTS Peraturan Menteri ESDM No 19 tahun 2013 tentang Harga pembelian tenaga listrik

dari PLTSa Peraturan Menteri ESDM No 12 tahun 2014 tentang Harga pembelian tenaga listrik

dari PLTMH Peraturan Menteri ESDM No 27 tahun 2014 tentang Harga pembelian tenaga listrik