business review templates
DESCRIPTION
TRANSCRIPT
SLIDE 1
Business Review Templates
SLIDE 2
SLIDE 3
Guiding Principles
• This set of templates should be used in conjunction with the Business Review Guidance document at ref xxxxxtbc
• The template set is designed to cover business activities across all of the life cycle (CADMID). The selection of which templates are to be used is a decision for the IPTL / DG.
• There should only be one business review of each team.
SLIDE 4
Template Information
• This set of templates comprises 3 sections• General Slides – applies to all reviews• Project related slides • Support related slides
• The template sections differentiate between delivery of projects (including upgrades and UORs) and support (including supply of services) because our business does. A team engaged in both activities will review slides of data from all sections.
SLIDE 5
Section One
• Whole IPT Summary – Slide 7– IYM Summary RDEL, CDEL including CPF– Balance Sheet
• Governance of Business – Slide 8• Other Issues – Slide 9
• Benefits Tracking • Successes, Opportunities, Failings & Threats• People & Collocation
SLIDE 6Summary Slide Guidance
Slide 7. This is principally a financial summary of the whole IPT’s Business and should include all colours of money that the IPT deals with, including the operating cost. The Asset Deliveries are intended to show an aggregate of all deliveries in the IPT but this would not be required if all the delivery information has already been presented in a single large project above. Where IPTs control significant stock movements, the Balance sheet section would be an essential item. However, it may be less useful for projects in an early stage of the CADMID cycle for example. Employ as required.
Slide 8. Is a free text slide where the TL can report on their approach to assurance and any DESIB / IAB submissions and record issues and opportunities for other group / board attendances.
Slide 9. Is a free text contribution which should generally be “by exception” and should be kept as short as possible. The list of subjects may not be relevant to all IPTs and other subjects may be added.
SLIDE 7
NEW EQUIPMENT SUPPORT CAPITAL DEL PROFILE - 2007/08
0.000
2.000
4.000
6.000
8.000
10.000
12.000
14.000
16.000
£M
Allocation Profile Actual Profile
Forecast Profile Forecast
NEW EQUIPMENT SUPPORT DIRECT RESOURCE DEL - 2007/08
0.000
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
10.000
£M
Allocation Profile Actual Profile
Forecast Profile Forecast
Whole IPT Summary Report – Mar 07Whole IPT Summary Report – Mar 07
All Equipments - Deliveries 06/07
-
5,000,000.00
10,000,000.00
15,000,000.00
1 2 3 4 5 6 7 8 9 10 11 12
AP
£
Allocation
AP7
Actual
Balance Sheet
Fixed AssetsCurrent AssetsLiabilitiesNet Assets
SLIDE 8
Governance of Business
• Governance of the Project and Business
• Information on the Assurance Plan
• Approach to Initial Gate / Main Gate / Review Note (if appropriate)
• Comments / information on wider review boards / groups
• Participation in Industry groups etc
Input from IP
TL and BM
SLIDE 9Team, Stakeholders and wider Issues
Data to enable review of the following as appropriate:1. Benefits Tracking2. Successes, Opportunities, Failings & Threats3. Staff issues, People & Collocation etc4. Meetings and Visits5. Stakeholder engagement issues6. Wider issues requiring the DG attention
Input from IP
TL and BM
SLIDE 10
Section Two
• Management of Projects (Upgrades & UORs)– Position against the project plan – slides 11 - 13 – EVM report – slide 14– Risk report – slide 15 – Finance and Approvals – slides 16 – 17– UOR data (if applicable) – slide 18
SLIDE 11
VT BuildVT Build
Bat
ch 2
Bat
ch 2
Bat
ch 1
Bat
ch 1
Stage 1.2 Harbour Trials Stage 1.2 Harbour Trials
Eq
uipm
ent P
rogr
amm
eLi
nes
of
De
velo
pmen
tD
e-R
iski
ng
Pro
gram
mes
2010200820072006 20112009
Note: Stage 2 Trials reflect the original DFM scope & strategy
First of Class
(Daring)
Ship 02
Ship 03
Ship 04
Ship 05
Ship 06
Other
SOC Update
FoC Training IDR Complete
Deliver FoC TrainingDeliver FoC Training
TrancheTranche 11 TrancheTranche 33 TrancheTranche 4 4 FoC Crew Build-up
Outfit, STW & Stage 1 TrialsOutfit, STW & Stage 1 Trials Stage 2 TrialsStage 2 Trials
PAAMS FoC DeliveriesPAAMS FoC Deliveries
LaunchLaunch
Dry DockDry Dock Main Wet DockingMain Wet Docking
Harbour/Basin Trials Harbour/Basin Trials
Specification & Integration Completion Specification & Integration Completion
Stage 2 TrialsStage 2 Trials
AAD/AAD/ISDISD
AAD/AAD/ISDISD
System Linking & Integration Phase 1 System Linking & Integration Phase 1
Stage 1 Sea Trials Stage 1 Sea Trials
PO2 Outfitting and Ship Completion ActivitiesPO2 Outfitting and Ship Completion Activities
PAAMS & LRR Integration Starts
PAAMS & LRR Acceptance & NWHT PAAMS & LRR Acceptance & NWHT
Fabrication, Block Build & Shaft AlignmentFabrication, Block Build & Shaft Alignment
50% 50% ISDISD
90% 90% ISDISD
Stage 2 TrialsStage 2 Trials
ISDISD50% 50% ISDISD
90% 90% ISDISD
ISDISD
Outfit, STW & Stage 1 TrialsOutfit, STW & Stage 1 Trials
Fabrication, Block Build & Shaft AlignmentFabrication, Block Build & Shaft Alignment Outfit, STW & Stage 1 TrialsOutfit, STW & Stage 1 Trials
11
22
LaunchLaunch
Start Stage 2 TrialsStart Stage 2 Trials
11
11
22
2 2
MFR Delivery
MFR Delivery
Outfit, STW & Stage 1 TrialsOutfit, STW & Stage 1 Trials
Fabrication, Block Build & Shaft AlignmentFabrication, Block Build & Shaft Alignment
Fabrication, Block Build & Shaft AlignmentFabrication, Block Build & Shaft Alignment
Fabrication, Block Build & Shaft AlignmentFabrication, Block Build & Shaft Alignment
11
11
11
Sustainability
MISC
CDF
STP-2
Install & STW PAAMSInstall & STW PAAMS PAAMS TrialsPAAMS Trials
C2 Mk4 available to MISC
Install & STW CSE & PAAMSInstall & STW CSE & PAAMS Firing TrialsFiring Trials
Firing F1 Firing F4
MFR Delivered
MFR Delivered
STW CSE/PAAMSSTW CSE/PAAMS CS System & General Integration TrialsCS System & General Integration Trials
PAAMS & LRR Integrated
C2 Mk3.2 & CMSr2.3 Integrated C2 Mk4 & CMSr2.3 Integrated
Develop & Contract Support SolutionDevelop & Contract Support Solution
In-Service Support Bus Case Issued
SDP on Contract CLS Contracted
Support to Test & TrialsSupport to Test & Trials
Dockyard Facility Upgrade (Portsmouth & Devonport)Dockyard Facility Upgrade (Portsmouth & Devonport)
FoC Enters PortsmouthDockyard facilities in place
22
Batch 2 Contract Let
CMS 2.3 Release
PADPADPADPAD
Current Current Approved Approved 50% ISD50% ISD
Nov 07Nov 07
Current Current Approved Approved 50% ISD50% ISD
Nov 07Nov 07Nov 07Nov 07
Contractual Contractual Acceptance Acceptance
DateDate
Sep 08Sep 08
Contractual Contractual Acceptance Acceptance
DateDate
Sep 08Sep 08Sep 08Sep 08
Latest Latest Public FoC Public FoC
50% ISD50% ISD
May 09May 09
Latest Latest Public FoC Public FoC
50% ISD50% ISD
May 09May 09
Ship 02Ship 02CADCAD
Jun 09Jun 09
Ship 02Ship 02CADCAD
Jun 09Jun 09
Ship 03Ship 03CADCAD
Dec 09Dec 09
Ship 03Ship 03CADCAD
Dec 09Dec 09Dec 09Dec 09
MFR Installation, STW & NWHT MFR Installation, STW & NWHT
PADPAD
PADPAD
22
50% 50% ISDISD
90% 90% ISDISD
Stage 2 TrialsStage 2 Trials22
ISDISD
Outfit, STW & Stage 1 TrialsOutfit, STW & Stage 1 Trials11
Stage 2 TrialsStage 2 Trials22
T42-1 FNOD
T42-2 FNOD
T42-3 FNOD T42-4
FNOD
T42-5 FNOD T42-6
FNOD
T42-7 FNOD
Ship 01 Ship 01 EP07EP07
Feb 10Feb 10
Ship 01 Ship 01 EP07EP07
Feb 10Feb 10Feb 10Feb 10
Steady State Training Ready for Training Date
2 2
Steady State Training Media Accepted
Note:Note: Dates reflect PAAMS IC-A programme (Gate 4 JIS draft M)Integration Ph 2Integration Ph 2
PAAMS Delivery
PAAMS Delivery
PAAMS Delivery
PAAMS Delivery
MFR Delivered
MFR STW
IntegrationIntegrationC2 Mk4 / CMSr2.3 decisionC2 Mk4 available at CDF
IntegrationIntegration
Hor
izon
(PP
O
real
istic
pla
n)
HRZ-01
HRZ-02
BuildBuild
BuildBuildC2/VLS
SimInstalled
Stage 1 STStage 1 ST Stage 2 ST & FiringsStage 2 ST & FiringsCADCAD
Stage 1 STStage 1 ST Stage 2 ST & FiringsStage 2 ST & FiringsCADCAD
LRR STW VLS STW
MFR STW C2 & SCE
STW
LRR STW
VLS STW
MFR STW
C2 & SCE STW
HRZHRZ--03 03 CADCAD
HRZHRZ--04 04 CADCAD
VT BuildVT Build
VT BuildVT Build
Pre CST Dry Dock
TrancheTranche 22
Note:Note: Confidence dates (Post mitigation) taken from Joint TRA Mar 06, but amended to take account of the PCO Apr 06 Level 1 plan update.
Programme – Baseline Level 0 Plan (Programme – Baseline Level 0 Plan (DateDate) EXAMPLE ) EXAMPLE
SLIDE 12Programme – Equipment ReportProgramme – Equipment Report
ISD & Anchor Milestone Tracking Chart
•PerformanceKUR2&3 - Shown as at risk as IC minus A delivers less than the planned capability at FOC ISD. Full capability is delivered in ship 3.
•TimeLatest TRA shows significant increase in risk to ISD, due primarily to the inclusion of PRU related risks (Power Systems, S/W, PAAMS, Safety). The forecast 50% ISD is now November 10. The implications of this analysis and the potential mitigation of Test & Trials duration are still being quantified. Therefore, a revision to, or confirmation of, the December 09 CMIS ISD is not expected before negotiations have matured i.e. by the end of the year. Anchor Milestone forecasts related to Power Systems have also been impacted by the consideration of PRU related risks.
•CostPosition against KT3
Key Target 1 – PERFORMANCE Key Target 2 – TIME
NARRATIVE Key Target 3 – COST
KUR01PAAMS
Current
KUR02Force anti-air warfare situational awareness
Current
Previous Previous
KUR03Aircraft Control
Current
KUR04Aircraft operation
Current
Previous Previous
KUR05Embarked military force
Current
KUR06Naval diplomacy
Current
Previous Previous
KUR07Range
Current
KUR08Growth potential
Current
Previous Previous
Oct-05
Mar-07
Jul-08
Dec-09
Apr-11
Oct-05
Jan-06Apr-0
6Jul-06
Oct-06
Jan-07Apr-0
7Jul-07
Oct-07
Jan-08Apr-0
8Jul-08
Oct-08
Jan-09Apr-0
9Jul-09
Oct-09
Jan-10Apr-1
0Jul-10
Oct-10
FoC Actual Acceptance Date (PCO L1 Deterministic Plan)
50% FoC ISD (Latest CMIS date)
10% FoC ISD (Latest IPT TRA Forecast)
50% FoC ISD (Latest IPT TRA Forecast)
90% FoC ISD (Latest IPT TRA Forecast)
90% IAB Approval
Anchor: Complete MFR trials at CDF (FY05/06 - Target 31/03/06) (Latest CMIS date)
Anchor: FoC Gas Turbines run successfully at sync idle (Latest CMIS date)
Anchor: FoC Propulsion drive/motor unit commissioning complete (Latest CMIS date)
Anchor: MFR delivered to FoC (Latest CMIS date)
2500
3350
4200
5050
5900
6750
1 Apr 06 50%Baseline
Current CIMIS Current Forcast(PRU 6 BPT)
£M
CMIS Input
Input from PMO
Input from FC
Input from RM, P
MO
and FC
SLIDE 13
Dec-02
Aug-03
Apr-04
Dec-04
Aug-05
May-06
J an-07
Sep-07
May-08
J an-09
Oct-09
J un-10
Dec-02Jun-03
Dec-03Jun-04
Dec-04Jun-05
Dec-05Jun-06
Dec-06Jun-07
Dec-07Jun-08
Dec-08Jun-09
Dec-09Jun-10
Dec-10
FoC Stage 1 Sea Trials (PCO L1 Deterministic Plan)
FoC Stage 2 Sea Period 2.1 (PCO L1 Deterministic Plan)
FoC Fleet Platform Acceptance Date (PCO L1 Deterministic Plan)
FoC Actual Acceptance Date (PCO L1 Deterministic Plan)
50% FoC ISD (Latest CMIS date)
Programme – Support Report (If applicable)Programme – Support Report (If applicable)
FoC Key Milestone Tracking Chart
• PerformanceSupport solution and upkeep cycle for 6 ships meets requirements of KUR9
• TimeSupport Solution work remains on track but a challenging timescale to meet BC submission to IAB scrutineers end Mar 07 and end Jun to IAB 4* Committee.Concerns with those materiel delivery dates at risk (IPLs and Tech Docs) being pursued through PCO.
• CostThis is the first year the IPT will incur expenditure against the DLO/STP. Budget (STP05) of £3.755m comprises £0.055m RDEL and £3.7m CDEL. Expenditure is for long lead items/spares. No variance between forecast and budget.
PERFORMANCE TIME
NARRATIVE COST
IYMSTP
10 YearSTPProfile
KUR09Availability
Current Current
Previous Previous
Current Current
Previous Previous
Current Current
Previous Previous
Current Current
Previous Previous
NOTE: Additional Support Milestones will be
considered for inclusion once a fully integrated
programme is developed
IYM 0607 Near Cash - Budget v Forecast
00.5
1
1.52
2.53
3.54
Apr 06 May06
June06
July06
Aug06
Sept06
Oct06
Nov06
Dec06
Jan 07 Feb07
Mar07
Month
£m
Budget (STP05)
Forecast
Cumulative Spendto date
CMIS Input
Input from PMO
Input from RM, P
MO
and FC
Input from FC
SLIDE 14EVM Schedule/Cost Variance
QUESTIONS
Earned Value ManagementEarned Value Management
Typical Earned Value graph showingSchedule and Cost Variances
5 months
PV
EV
AC
TIME
5,000
sv
cv
£
schedule variance = EV - PV = negative numbercost variance = EV - AC = negative number
behind schedule,over cost
Five Basic Performance Data Questions & Answers
QUESTIONQUESTION
How much work How much work shouldshouldbe done?be done?How much work How much work isis done? done?How much did that work How much did that work actuallyactually cost? cost?What was the total job What was the total job supposedsupposed to cost? to cost?What do we What do we now expectnow expect the total job to cost?the total job to cost?
Planned Planned ValueValue
PVPV
Earned ValueEarned Value EVEV
Actual CostActual Cost ACAC
Budget at CompletionBudget at Completion BACBAC
Estimate at CompletionEstimate at Completion EACEAC
ANSWERANSWER ACRONYMACRONYM
•Planned Value (PV) indicated by the Blue line is the agreed plan and represents what the project should achieve.
•Earned Value (EV) represented by the green line shows what has actually been achieved or Earned. In this example the EV curve is diverging from the PV curve indicating that at the given time, the project has achieved less than planned.
•Actual Cost (AC) represented by the red curve shows the actual cost of the EV. In this example the AC has exceeded the costs of the PV.
•Cost Variance (CV) expresses the cost difference between the EV and the AC.Remember it is the difference between EV and AC that gives the variance. Comparisons of AC against PV is misleading.
•Schedule Variance (SV) expresses the schedule difference between the EV and PV.
PERFORMANCE STATUS...Key Things to Track
Use Data for Decision Making
• To realise the benefit of EVM it is essential that you have confidence in the data, that you take heed of the information it gives you and that you act appropriately on that information.
•If the graph used in this tutorial was an actual output on your project. What questions would arise and what actions might you take?
- How critical is my schedule? E.g. could adjustments be made? - Can additional resources be applied? e.g to work overtime - Can any tasks be completed concurrently? - Are there technical innovations which could speed up the process? - Can the requirement be reduced? E.g. remove “gold plating”. - Would a schedule risk assessment expose the impact to project? - Could any tasks be re-scheduled? E.g. Time phasing - Could less costly facilities be employed? - Are there tasks which can be deleted? Comment - This list is not intended to be exhaustive..
SLIDE 15
£0 k
£50,000 k
£100,000 k
£150,000 k
£200,000 k
£250,000 k
£300,000 k
£350,000 k
£400,000 k
Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06
Remaining EP05 Risk Budget
Post-Mgt 50% Cost Exposure
Pre-Mgt 10% Cost Exposure
Pre-Mgt 50% Cost Exposure
Pre-Mgt 90% Cost Exposure
Programme – Risk ReportProgramme – Risk Report
KEY RISKS SUPPORTSUPPORT CONTINGENCY
KEY RISKS EQUIPMENTEQUIPMENT CONTINGENCY
STP Risk Budget & Exposure
Will show an analysis of 10%, 50%, 90% exposure against STP Risk Budget, when STP Risk data is sufficiently mature
STP Affordability
An IAB Information Note, to be issued through CDP mid Oct, concludes that affordability against existing budget levels in average annualised cost terms can be achieved for a class of 8 ships or less. More work will be necessary to achieve a
more acceptable RDEL/CDEL balance during the development of the support solution although the full scale of
the issue cannot be resolved without external Project assistance.
EP Risk Budget & Exposure
NOTE: Increased exposure reflects proposed Stage 2
Trials over-budget risk
Critical path for Ship 2 is availability of engine change tooling due Mar 07, currently on track.
Potential delay of up to one month currently forecast for Ship 4.
PAAMS IC-A being pursued – joint working, CMS 2.2.1 & 2.3, PAAMS contract realignment.
Intend to proceed with IC-A on a staged basis. The IA and Business Case for Stage 1 raised at a cost of £9M.
MISC activities continue to de-risk Combat System.
Work continues to review Test & Trials approach across the whole class.
SIT de-risking on track. Due to complete Apr 07.
FOC Critical Path is GTA STW due mid Nov 06.
Mitigation Success / Progress
Install Enclosures at earliest opportunity
Fit Gas Turbines via removal route
Fit un-FATed Gas Turbines
L M MMedFurther WR21 delays for Ship 2 onwards
Max use of trials facilities such as Longbow and MISC.
Implement PAAMS IC-A
M H MMedPAAMS Integration
Maximise use of MISC with MISC Augmentation (NavRadar)
Pragmatic Test & Trials approach
M H HMedCombat System Integration and Trials
Re-instate use of SIT @ ESTDM H HHighProblem with Power & Propulsion Systems STW and Integration
RAGProposed MitigationImpact
P C T
ProbRisk
Critical path for Ship 2 is availability of engine change tooling due Mar 07, currently on track.
Potential delay of up to one month currently forecast for Ship 4.
PAAMS IC-A being pursued – joint working, CMS 2.2.1 & 2.3, PAAMS contract realignment.
Intend to proceed with IC-A on a staged basis. The IA and Business Case for Stage 1 raised at a cost of £9M.
MISC activities continue to de-risk Combat System.
Work continues to review Test & Trials approach across the whole class.
SIT de-risking on track. Due to complete Apr 07.
FOC Critical Path is GTA STW due mid Nov 06.
Mitigation Success / Progress
Install Enclosures at earliest opportunity
Fit Gas Turbines via removal route
Fit un-FATed Gas Turbines
L M MMedFurther WR21 delays for Ship 2 onwards
Max use of trials facilities such as Longbow and MISC.
Implement PAAMS IC-A
M H MMedPAAMS Integration
Maximise use of MISC with MISC Augmentation (NavRadar)
Pragmatic Test & Trials approach
M H HMedCombat System Integration and Trials
Re-instate use of SIT @ ESTDM H HHighProblem with Power & Propulsion Systems STW and Integration
RAGProposed MitigationImpact
P C T
ProbRisk
Significant savings identified - team have completed Support Affordability Statement
Establish support solution affordability team
M H MLowSupport solution for ship, PAAMS & WR21 proves unaffordable
IPT Business Case for spares is currently being prepared (value £7-10m).
However, delay caused by on-going commercial dispute means that time-line for procurement of some items may have been compromised
Affordability of core engineering synthetic media may require prioritisation/de-scoping
Uncertainty over PAAMS maintainer training solution (GFE vs Synthetic)
MCTS 7 month delay requires interim solution to be identified
Support Solution Team involved all key stakeholders, hence Customer involved in defining solution
Mitigation Success / Progress
FoC spares package to be developed ahead of In-Service Support Solution
L H HMedLack of agreement for procurement & funding of spares to support FoC commissioning & trials programme
Investigate alternatives
Prioritise training
Engage stakeholders to scrutinise current proposals
Seek training opportunities within the trials programme
M M LMedInability to develop and deliver training within budget / timescale constraints
Establish support solution affordability team
M H MMedInability to gain customer approval for affordable support solution
RAGProposed MitigationImpact
P C T
ProbRisk
Significant savings identified - team have completed Support Affordability Statement
Establish support solution affordability team
M H MLowSupport solution for ship, PAAMS & WR21 proves unaffordable
IPT Business Case for spares is currently being prepared (value £7-10m).
However, delay caused by on-going commercial dispute means that time-line for procurement of some items may have been compromised
Affordability of core engineering synthetic media may require prioritisation/de-scoping
Uncertainty over PAAMS maintainer training solution (GFE vs Synthetic)
MCTS 7 month delay requires interim solution to be identified
Support Solution Team involved all key stakeholders, hence Customer involved in defining solution
Mitigation Success / Progress
FoC spares package to be developed ahead of In-Service Support Solution
L H HMedLack of agreement for procurement & funding of spares to support FoC commissioning & trials programme
Investigate alternatives
Prioritise training
Engage stakeholders to scrutinise current proposals
Seek training opportunities within the trials programme
M M LMedInability to develop and deliver training within budget / timescale constraints
Establish support solution affordability team
M H MMedInability to gain customer approval for affordable support solution
RAGProposed MitigationImpact
P C T
ProbRisk
Input from PMO
SLIDE 16Programme – Programme – Financial ReportFinancial Report
EP07 is for 8 ships based on the PRU ‘BTP risk adjusted’ cost of £????m (£????m near cash) with cost growth compared to EP05 of £???m (near cash).
Commitment Against Approval
ASSET DELIVERIES - No planned asset deliveries during FY06/07First Asset deliveries planned during FY07/08 (PAAMS Missiles & Training equipment)
EQUIPMENT PLAN – FORECAST AGAINST APPROVAL NARRATIVE
IN_YEAR MANAGEMENT NARRATIVE
Equipment PlanForecast £558m (control total £616m). No from AP5 forecast.
Risk Analysis
Op CostsForecast £?????m compared to Budget of £????m, variance of £????m.No change from AP5 forecast.
2500
3350
4200
5050
5900
6750
7600
EP07 Committed Approval
Ships 7&8
6 ships
EP FORECAST
0100200300400500600700
£m
Control Total Accruals Forecast
OP COST IN-YEAR FORCAST
0
250
500
750
1000
1250
Time
£K
Control Total Accruals Forecast
Input from FC
SLIDE 17MPR/Approvals Forecast SummaryMPR/Approvals Forecast Summary
• MPR/NAO– Draft MPR06 Audit report received from NAO. Shows in-year cost growth of £???M (to £????M)
and delay of +7 months (to Dec 09). Re-statement of MPR05 figures (adding a further cost growth of £??M) not shown against MPR06. Also shows 3 KURs at risk due to potential reduction in capability on FOC at ISD. Proposed text amendment to reflect accurately the progressive demonstration of capability.
– The cost growth reported in MPR06 enabled the DPA to achieve Key Target 3 and the PSA target for 2005/06. There may be sensitivity in reporting all the 2006/07 potential cost growth, within CMIS, so soon after the NAO agreeing the MPR06 figure in June 2006. The proposed course of action is to update CMIS once negotiations with Industry have reached a mature and stable position, planned for 1st Qtr 2007.
• PCT SUMMARY
FORECAST HISTORY
PRU RECOMMENDATIONS
COST VARIATIONS
Original MG
approval (90%)
MPR05 MPRO6 Current CIMIS Forecast (50%)
6 ship BTP Risk adjusted
6 ship Baseline Cautious
Delta on MPR06 (PRU BTP-MPR)
Delta on MPR06 (PRU Baseline-MPR)
Cost (£m) £????m £???m £???m £???m £????m £????m +£???m +£????m
ISD Nov 07 May 09 Dec 09 Dec 09 Sep 10 Nov 10 KURs 9/9 9/9 9/9 9/9 9/9 9/9
Input from BM/FC
SLIDE 18
P9 Name Forecast
Main Gate Main Gate Achieved
Approved Cost 50%
(£m)
Forecast Cost 50%
(£m)
Approved ISD 50%
Forecast ISD 50%
ISD Achieved
P9003040 0.5” Blank Firing Barrel (BFB) and Blank Ammunition (BA)
0.452 0.304 Aug 2005 Aug 2005
P9003043 60mm Mortar 0.017 0.015 Sep 2005 Sep 2005
P9003041 8.6mm Ammo 0.500 0.495 Jun 2007 Jun 2007
P9258500 ALDS 11.950 9.410 Jul 2006 Jan 2007
P9000866 Artillery Fire Control Trainer - Full Task (AFCT-FT) BGTI/Digitisation Upgrade
3.080 2.804 Feb 2008 Dec 2007
P9000867 Artillery-Fire Control Trainer - Part Task (AFCT-PT) Upgrade
0.550 0.503 Sep 2006 Nov 2006
P9002781 AS90 Lt Gun CEP 17.110 17.110 Oct 2011 Oct 2011
P9000297 AS90 Training System (TS)
2.198 2.116 Sep 2005 Sep 2005
P9003044 Automatic Lightweight Grenade Launcher (ALGL)
2.889 2.909 Feb 2007 Apr 2007
P9004170 Automatic Lightweight Grenade Launcher (ALGL) Support Fleet
1.550 1.546 Mar 2007 Mar 2007
UOR – Summary Data
KEY DATAKEY DATA
SLIDE 19
Section Three
• Support and Service Delivery– Performance against CSA or JBA – slide 20– Availability / Operating Hours – Slide 21– Customer Wait time / Safety Risks – Slide 22 – Supply Chain Issues – Slide 23
SLIDE 20Performance against User CSA / JBA / OSP outputs 11Month of data assessed eg, APR 07
• State overall FFP and comment on individual metrics if showing AMBER or RED– Comment factors contributing to metrics that have previously
been AMBER or RED but are now YELLOW or GREEN
Example:-• FFP - YELLOW
– FE@R - RED - commentary– ABORTS - AMBER - commentary
SLIDE 21Performance against User CSA / JBA / OSP outputs 2
Month of data assessed eg, APR 07
Availability / Operating hours chart etc to be inserted here if applicable
SLIDE 22CUSTOMER WAIT TIME (As appropriate)CUSTOMER WAIT TIME (As appropriate)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
DUES OUTSUCCESSESKEY: PEPS Range Target: 98%Equipment [Day 1] as at 28 Feb 07
CLS Referred Non-PEPS Range Target: 50%REFERRALS
100%PEPS9.22%11.36%
1.36% 100%PEPSNon PEPS 78.06%
PEPS 10.00%
5.11%20.61%
PEPSNon PEPS
PEPS
60.26% 14.02%
10.00%
7.43%12.91%79.66%
PEPS
PEPSNon PEPS
Non PEPS 9.12%9.12%
PEPS
PEPS81.76%
7.28%
PEPSNon PEPS
PEPS
61.35% 31.36%
63.99% 22.12%
PEPSNon PEPS 13.88%
As at 18 Oct 06
Summary of Safety Related Risks - Cat A&B Funded/Unfunded …quarterly
0
00
GFA
0
0
4
810
0
0
0
15
2
11
20 0
Overall Total 0 18
0 0 0
0 0 0
4.3180.000
1 0.180 0.000
£M 3.514 0.000
r r
Previo
us
Curre
nt
0.000
0
UNFUNDED
0.040
3.600
0.0000.000 0.000
Cost of reducing Risk to "As Low As Reasonably Practicable" (ALARP) - £M
FUNDED
2
FY 07/08 IPT Total FY 06/07 FY 07/08 FY 08/09FY 06/07 FY 09/10IPT Total FY 08/09
1
FY 09/10
0.000
Outwith
0.0000.004
5 0.0000.000 0.0000.040
IPT Outwith
0.000 0.0000.0040 0 0 13
ALARP Funded
CAT "B" RISKCAT "A" RISK
Funded Unfunded Unfunded
0
0.6900
3
2.600 0.000
0.690
08
0 1.380
0.000 0.000
0.0000.000
2.600
0.000
0 00
ONO IPT
DRS
TAS
EHM
JEG 0 0 0.0000.000 0.000 0.000
MET
00
0.2940.000
0.804
0.000 0.000
0.0000.114
0.000 3.600
0.000
6 3.735
0.000
0.000 0.0000.000
0.000 0.000 0.000
0.0000.000 0.000
0.270
0.000 0.000
10.700
0.000
3.600 3.500
0.000
0.135
10.9703.635
0.135
SAFETY RISKSSAFETY RISKS
SLIDE 23Supply Chain Performance
Month of data assessed eg, APR 07
Insert details of any known demand failure trends or supply chain issues with details – by exception only
If EVM is being operated for support details should be included here