Dear Resident MAJOR CONSTRUCTION WORKS IN THE PORT MELBOURNE AREA FOR WEST GATE FREEWAY UPGRADE: JUNE TO OCTOBER 2016 We are writing to inform you about noisy major construction works, including bored piling, taking place in your area over the coming months as part of the CityLink Tulla Widening project. These works are in preparation to build an additional lane on the West Gate Freeway. As you may be aware, work on the CityLink Tulla Widening project is underway and involves adding lanes and other measures to improve the flow of traffic across the 24 kilometre section of freeway from the CityLink tunnels to Melbourne Airport. The project will also provide travel time savings per trip between Melbourne Airport and the West Gate Freeway during peak periods. Generally, an additional lane is being added in each direction, as well as upgrades at key interchanges including Bell Street, Mount Alexander Road/Flemington Road and on the Bolte Bridge to West Gate Freeway entry ramp. CPB Contractors is the construction contractor for the Bulla Road to Power Street section of the project. When works will occur From June to October 2016, work hours for construction will be 7am to 6pm Monday to Saturday. What the works involve We will be undertaking bored piling works to build an additional lane on the West Gate Freeway. Bored piling works involve: Using a bored piling rig to bore into the ground and install protective sheets of steel to cover underground services (e.g. telecommunications, gas, electricity) during construction works Using a bored piling rig to install permanent freeway barriers and supports for new overhead signage structures, known as gantries, that will be installed at a later date Reinstating our work areas when piling works are complete Where we will be working

Upload: duongtruc

Post on 24-Mar-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: citylinktullawidening.vic.gov.aucitylinktullawidening.vic.gov.au/__data/assets/word_doc…  · Web viewUsing a bored piling rig to bore into the ground and install protective sheets

Dear Resident

MAJOR CONSTRUCTION WORKS IN THE PORT MELBOURNE AREA FOR WEST GATE FREEWAY UPGRADE: JUNE TO OCTOBER 2016

We are writing to inform you about noisy major construction works, including bored piling, taking place in your area over the coming months as part of the CityLink Tulla Widening project. These works are in preparation to build an additional lane on the West Gate Freeway.

As you may be aware, work on the CityLink Tulla Widening project is underway and involves adding lanes and other measures to improve the flow of traffic across the 24 kilometre section of freeway from the CityLink tunnels to Melbourne Airport. The project will also provide travel time savings per trip between Melbourne Airport and the West Gate Freeway during peak periods.

Generally, an additional lane is being added in each direction, as well as upgrades at key interchanges including Bell Street, Mount Alexander Road/Flemington Road and on the Bolte Bridge to West Gate Freeway entry ramp.

CPB Contractors is the construction contractor for the Bulla Road to Power Street section of the project.

When works will occur From June to October 2016, work hours for construction will be 7am to 6pm Monday to Saturday.

What the works involve We will be undertaking bored piling works to build an additional lane on the West Gate Freeway. Bored piling works involve: Using a bored piling rig to bore into the ground and install protective sheets of steel to cover underground

services (e.g. telecommunications, gas, electricity) during construction works Using a bored piling rig to install permanent freeway barriers and supports for new overhead

signage structures, known as gantries, that will be installed at a later date Reinstating our work areas when piling works are complete

Where we will be workingOver the coming months, bored piling works will occur along the West Gate Freeway from the Bolte Bridge exit ramp to the Lorimer Street exit ramp, as shown in red on the map below.

Page 2: citylinktullawidening.vic.gov.aucitylinktullawidening.vic.gov.au/__data/assets/word_doc…  · Web viewUsing a bored piling rig to bore into the ground and install protective sheets

What to expect Traffic management including barriers, signage and personnel to safely guide motorists and pedestrians

around our work areas Changed road conditions and temporary removal of car parking spaces at 329-349 Ingles Street,

underneath the Ingles Street bridge and on Boundary Road, as shown in yellow on the map above Noise from heavy machinery and trucks in use and construction site vehicles Noise from piling works during normal construction hours only Varying levels of vibration that may be felt during construction activities

This work may be rescheduled in the event of unsuitable weather or other unavoidable circumstances. We apologise for any inconvenience and appreciate your understanding as we undertake these important works.

We are committed to keeping residents informed and minimising the impacts during construction, while keeping the community and our workers safe at all times. Managing and protecting the environment is also important to us and we are working with local and state government adhering to environmental laws to ensure any impact to the natural ecosystem is minimised.

If you have any questions or concerns regarding this notification, please phone 1300 783 947 and select 1 or email us at [email protected]

131 450

Yours sincerely,

Community Relations TeamCPB ContractorsCityLink Tulla Widening: Bulla Road to Power Street01/06/2016, Ref: 0084 S02

Ingles StreetBoundary Street Hartley Street

West Gate Freeway

Piling works area

Site compound

Changed parking/traffic conditions