    Capital Plan 2016-2017Presentation by Town Manager

    February 22, 2016

  • 7/24/2019 Capital Budget FY17 Proposal

    2/16

    y ,

    What is Capital?

    Capital projects defined as: Equipment andinfrastructure with net cost of $10,000 or more and

    life of 5 or more years

    Included: components of larger infrastructure, such as

    computers, peripherals and major software

    Excluded: Police cruisers (life less than 5 years)

  • 7/24/2019 Capital Budget FY17 Proposal

    3/16

    Priorities for Ranking: Policy Adopted 2013

    1. Risk to safety

    2. Risk to property

    3. Federal or state mandates

    4. Routine replacement

    5. Operational improvement

    6. Coordination of projects

    7. Equitable services to special populations

    8. Economic development9. Natural resources preservation

    10. New/expanded facilities

    11. Program changes

  • 7/24/2019 Capital Budget FY17 Proposal

    4/16

    Result

    Five year plan coordinated across several

    departments.

    Funding source this year is $ 857,801 Free

    Cash, plus carryover balances from completed

    capital projects = $918,880.

  • 7/24/2019 Capital Budget FY17 Proposal

    5/16

    Recent Capital Projects Completed

    Replacement indoor track and cafeteria at MS/HS

    Doyon School Boiler repair

    School Security improvements

    DPW Dump Truck

    Carpet replacement in Library and Town Hall

    Jaws of Life

    HVAC units in Town Hall

    Generator at Police Station

    Sewer plant upgrade completed

    Water plant improvements & Equipment replacement

  • 7/24/2019 Capital Budget FY17 Proposal

    6/16

    Highlights of 2016-2017 Capital Plan

  • 7/24/2019 Capital Budget FY17 Proposal

    7/16

    Information Technology

    Computer replacement

    Town $13,000

  • 7/24/2019 Capital Budget FY17 Proposal

    8/16

  • 7/24/2019 Capital Budget FY17 Proposal

    9/16

    Town Hall Carpeting Replacement: Last Phase $36,000

    Library Exterior Stairs (Matching funds, added 2-11-16) $20,000

    Police Station Carpet Replacement $15,000

    Central Fire Generator Replacement $48,000

    Highway Garage: Install wash bay $105,000

    Replace Overhead Doors (Phase 1 of 2): $ 24,000

    FacilitiesTown Buildings

  • 7/24/2019 Capital Budget FY17 Proposal

    10/16

    Dump Truck (Year 1 of 5): $29,500

    Dump Truck (Year 2 of 5): $35,108

    DPW Loader (Year 3 of 5): $ 35,605

    Dump truck with Wing Plow (Year 3 of 5): $ 36,567

    Cemetery & Parks (Sale of Lots fund) 1 ton Dump Truck : $45,000

    Equipment - DPW

    DPW Dump Truck (Year 1 of 5)

  • 7/24/2019 Capital Budget FY17 Proposal

    11/16

  • 7/24/2019 Capital Budget FY17 Proposal

    12/16

    Police:

    Firearms replacement: $20,000

    New Antennae (5): $15,000

    Security Cameras: $15,000

    Animal Control:

    Replace Van: $25,000

    Harborsfrom Waterways Funds:

    Pump out boat: $25,000Work Boat Engine: $15,000

    2 Fire Pumps: $12,000

    Pick-up Truck: $35,000

    EquipmentPolice, Animal Control & Harbors

  • 7/24/2019 Capital Budget FY17 Proposal

    13/16

    Wayfinding Signage (Year 2 of 3) Implementation: $29,100

    Economic Development

  • 7/24/2019 Capital Budget FY17 Proposal

    14/16

    Water infrastructure

    Meters (for completion in FY2018): $150,000

    Well Upgrades (year 2 of 5 year program): $20,000

    Dump Truck: $120,000

    Solar Bee Reservoir Mixer: $70,000

    Water System Study (year 1 of 2): $100,000

    Sewer infrastructure and buildings Sewer Operating

    Meters (for completion FY2018): $50,000

    SCADA System Design (Multi-year): $60,000

    Dump Truck: $120,000

    Water & Wastewater

  • 7/24/2019 Capital Budget FY17 Proposal

    15/16

    $35,000 in Free Cash to paint classrooms in MS/HS

    Non Capital Projects

  • 7/24/2019 Capital Budget FY17 Proposal

    16/16

    Free Cash is uncertain from year to year.

    There is a continued need for an on-going general fund

    source dedicated to capital projects of approximately

    $1,000,000 per year.

    Challenges