case study - trane · 2020-05-23 · case study. optimizing resources, maintaining project...
TRANSCRIPT
ChallengeThe aging infrastructure at the Lakota Wastewater Treatment
Plant was in critical need of upgrade. Due to the inefficient,
outdated systems, the plant required twice the horsepower in
aeration equipment and was reliant upon chemical-aided
treatment in order to comply with National Pollutant
Discharge Elimination System permit limits. Lakehaven Utility
District sought to upgrade its Lakota plant to improve
efficiency, reduce energy consumption and mitigate the risk
of a potential plant failure.
SolutionFinancing and managing critical upgrades
Trane proposed that Lakehaven Utility District consider using
the State of Washington Design/Build Energy Savings
Performance Contracting Program (ESPC), authorized under
state law and managed by the Washington State Department
of Enterprise Services, as an option to help finance its needed
upgrades. The district reviewed the proposal and, based on
Trane’s leading performance in the wastewater treatment
plant industry and positive references, selected Trane as its
ESPC partner to manage the entire upgrade process.
Lakota Wastewater Treatment PlantPerformance contracting upgrades result in $850,000 energy andoperational savings • Federal Way, Washington
The Lakota Wastewater Treatment Plant, located on twenty-three acres, is Lakehaven Utility District’s largesttreatment plant. The district encompasses an area of approximately thirty-five square miles with a service populationof approximately 112,000 people. Seventy-five percent of the service is currently to single-family residential dwellings,but in the past it has been up to 50 percent from commercial businesses and restaurants. The Lakota plant is fed byabout 150 miles of collection system piping and thirteen lift stations.
Performance contracting is a funding option that provides
measurable organizational results to support strategic
objectives. It allowed Lakota Wastewater Treatment Plant to
use future energy and operational savings to finance
infrastructure improvements upfront. Working with Trane, the
performance contract enabled the Lakehaven Utility District
to secure a third party muni-loan at an attractive rate,
allowing them to allocate their limited capital to other areas.
The Lakota Wastewater Treatment Plant used the State of Washington
Design/Build Energy Savings Performance Contracting Program to
secure financing for needed upgrades.
October 2014Case study
Optimizing resources, maintaining project ownership
By using Trane, one of a small group of firms prequalified by
the State of Washington as a preferred energy services
company (ESCO), Lakehaven Utility District saved the time
and resources required to bid out the project. The partnership
with Trane allowed the Lakehaven Utility District to make the
best use of its limited staff, while utilizing Trane’s expertise.
The partnership also enabled the district to maintain
ownership of the project, selecting the equipment that they
preferred and choosing the contractors and consultants that
best fit their needs, with a Trane performance contract
guaranteeing the cost and performance.
Reducing costs, mitigating risks
Upgrades at the Lakota Wastewater Treatment Plant included
a complete replacement and optimization of its secondary
treatment aeration system. The treatment process
evaluation/optimization maximizes energy and operational
savings, while ensuring Department of Ecology code
compliance and risk mitigation. The upgrades improve current
process instability issues, lower operational and maintenance
costs, reduce power consumption, and offset capital repairs.
The improvements also allow for future biological nutrient
removal air demand to be met for future nitrogen control.
ResultsOriginally seeking to upgrade the outdated equipment and
infrastructure at the Lakota Wastewater Treatment over
several years, through the Energy Savings Performance
Contracting Program, the Lakehaven Utility District was able
to fund the complete replacement and optimization of its
secondary treatment system aeration at one time with the
guidance of Trane and assistance through the ESPC. The
upgrades have greatly reduced the treatment plant’s risk of
failure and compliance violations.
The plant upgrade has achieved $850,000 in energy and
operational savings for the Lakehaven Utility District. The
project, which included a 30 percent reduction in chemical
costs, along with a one-time revenue grant of $602,000,
delivered a positive cash flow return to the district in less than
one year.
“We’re pleased that we were able to fund critical
improvements through energy and operational savings," said
Chris McCalib, wastewater operational manager for
Lakehaven Utility District. “We’re also pleased that we could
complete the project in less than a year, and delighted that
we can realize a return on our investment early on.”
Upgrades at the Lakota Wastewater Treatment Plant, which included the
replacement and optimization of its secondary treatment aeration
system, delivered a positive cash flow return in less than a year.
Ingersoll Rand (NYSE:IR) advances the quality of life by creating comfortable, sustainable and efficient environments. Our people and our family of brands—including Club Car®, Ingersoll Rand®, Thermo King® and Trane®—work together to enhance the quality and comfort of air in homes and buildings; transport and protect food and perishables; and increase industrial productivity and efficiency. We are a global business committed to a world of sustainable progress and enduring results.
ingersollrand.com
We are committed to using environmentally conscious print practices. ©2014 Ingersoll Rand CASE-SLX384-EN October 01, 2014