chapter 6 capital budgeting techniques © 2005 thomson/south-western

30
Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

Upload: dwight-ethelbert-kelly

Post on 16-Dec-2015

229 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

Chapter 6

Capital BudgetingTechniques

© 2005 Thomson/South-Western

Page 2: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

2

What is Capital Budgeting?

The process of planning and evaluating expenditures on assets whose cash flows are expected to extend beyond one yearAnalysis of potential additions to fixed assets

Long-term decisions

Decision that involve large expenditures

Very important to firm’s future

Page 3: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

3

Generating Ideas for Capital Projects

A firm’s growth and its ability to remain competitive depend on a constant flow of ideas for new products, ways to make existing products better, and ways to produce output at a lower cost.

Procedures must be established for evaluating the worth of such projects.

Page 4: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

4

Project Classifications Replacement Decisions:Replacement Decisions: whether to

purchase capital assets to take the place of existing assets to maintain or improve existing operations

Expansion Decisions:Expansion Decisions: whether to purchase capital projects and add them to existing assets to increase existing operations

Independent Projects:Independent Projects: Projects whose cash flows are not affected by decisions made about other projects

Mutually Exclusive Projects:Mutually Exclusive Projects: A set of projects where the acceptance of one project means the others cannot be accepted

Page 5: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

5

Similarities between Capital Budgeting and Asset Valuation

Uses same steps as in general asset valuation1. Determine the cost, or purchase price, of the asset.

2. Estimate the cash flows expected from the project.

3. Assess the riskiness of cash flows. [Note that we will

explicitly address the risk issue in the next chapter. For

now, risk is taken as given.]

4. Compute the present value of the expected cash flows to

obtain as estimate of the asset’s value to the firm.

5. Compare the present value of the future expected cash

flows with the initial investment.

Page 6: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

6

Net Cash Flows for Project S and Project L

1,5001,200

800300

400900

1,3001,500

^Net Cash Flows, CFt

r e dp AEx cte fte -Tax

Year (T) Project S Project L0a $(3,000) $(3,000)1234

Page 7: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

7

What is the Payback Period?

The length of time before the original cost of an investment is recovered from the expected cash flows or . . . How long it takes to get our money back.

yearrecovery -full

during flowcash Totalyearrecovery -full of

startat cost cov

investment original

ofrecovery

before years of eredUnre

full

Number

PBPayback

Page 8: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

8

Payback Period for Project S

=PaybackS 2 + 300/800 = 2.375 years

Net Cash Flow

Cumulative Net CF

1,500

-1,500

800

500

1,200

-300

-3,000

-3,000

300

800

PBS0 1 2 3 4

Page 9: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

9

=PaybackL 3 + 400/1,500 = 3.3 years

Net Cash Flow

Cumulative Net CF

400

- 2,600

1,300

- 400

900

- 1,700

- 3,000

- 3,000

1,500

1,100

PBL0 1 2 3 4

Payback Period for Project L

Page 10: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

10

Strengths of Payback:Strengths of Payback:• Provides an indication of a

project’s risk and liquidity• Easy to calculate and understand

Weaknesses of Payback:Weaknesses of Payback: • Ignores TVM• Ignores CFs occurring after the

payback period

Strengths and Weaknesses of Payback:

Page 11: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

11

Net Present Value: Sum of the PVs of Inflows and Outflows

NPV = PV inflows - Cost= Net gain in wealth.

Rule: Accept project if NPV > 0.

Choose between mutually exclusive projects on basis of higher NPV: Which project adds the most value?

Page 12: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

12

Calculator Solution, NPV for S :

NPVS = 161.33 = NPVS

Enter in CF for S:

I

-3,000

1500

1200

800

300

10%

CF0

CF1

CF2

CF3

CF4

Page 13: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

13

Calculator Solution, NPV for L :

NPVL = 108.67 = NPVL

Enter in CF for L:

I

-3,000

400

900

1,300

1,500

10%

CF0

CF1

CF2

CF3

CF4

Page 14: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

14

Using NPV method, which project(s) should be accepted?

If Projects S and L are mutually exclusive

accept S because NPVS > NPVL

If Projects S & L are independentaccept both since NPV > 0.

Page 15: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

15

Internal Rate of Return: IRR

0 1 2 3

CF0 CF1 CF2 CF3

Cost Inflows

IRR is the discount rate that forces PV inflows to equal the cost.

IRR forces NPV = 0.

Page 16: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

16

What is Project S’s IRR?

NPVS = IRRS = 13.1%Enter CFs in CF register, thenpress IRR:0

(3,000)

IRR = ?0 1 2 3 4

Sum of PVs for CF1-4 = 3,000

1,500 8001,200 300

Page 17: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

17

What is Project L’s IRR?

NPVL =Enter CFs in CF register, thenpress IRR: IRRL = 11.4%0

IRR = ?

400 1300900 1500

0 1 2 3 4

Sum of PVs for CF1-4 = 3,000

(3,000)

Page 18: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

18

How is a Project’s IRRRelated to a Bond’s YTM?

They are the same thing.A bond’s YTM is the IRRif you invest in the bond.

90 109090

0 1 2 10IRR = ?

-1134.20

IRR = 7.08% (use TVM or CF register)

Page 19: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

19

Rationale for the IRR Method:

If IRR (project’s rate of return) > the firm’s required rate of return, k, then some return is left over to boost stockholders’ returns.

Example: k = 10%,IRR = 15%. The project is profitable.

Page 20: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

20

IRR acceptance criteria:

If IRR > k (= the firm’s required rate of return), accept project.

If IRR < k (= the firm’s required rate of return), reject project.

Page 21: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

21

Decisions on Projects S and L per IRR

If S and L are independent, accept both. IRRs > k = 10%.

If S and L are mutually exclusive, accept S because IRRS > IRRL .

Page 22: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

22

Construct NPV ProfilesEnter CFs in your calculator and find NPVL andNPVS at several discount rates (k):

k

0

5

10

15

20

NPVL

1,100

554

109

(259)

(566)

NPVS

800

455

161

( 91)

(309)

Page 23: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

23

IRRL = 11.4%

IRRS = 13.1%

Crossover Point = 8.1%

k

0

5

10

15

20

NPVL

1,100

554

109

(259)

(566)

NPVS

800

455

161

( 91)

(309)

NPV Profiles for Project S and Project L

(800)

(600)

(400)

(200)

0

200

400

600

800

1,000

1,200

0 2 4 6 8 10 12 14 16 18 20

Project L

Project S

Page 24: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

24

NPV and IRR always lead to thesame accept/reject decision forindependent projects:

IRR < kand NPV < 0.

Reject.

NPV ($)

k (%)IRR

IRR > kand NPV > 0

Accept.

Page 25: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

25

Mutually Exclusive Projects

k< 8.1: NPVL> NPVS , IRRL < IRRS

CONFLICT

k> 8.1: NPVS> NPVL , IRRS > IRRL

NO CONFLICT

8.1

NPV

%

IRRs

IRRL

S

L

Page 26: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

26

To Find the Crossover Rate:

1. Find cash flow differences between the projects. See data at beginning of the case (repeated on next slide).

2. Enter these differences in CF register, then press IRR. Crossover rate = 8.11, rounded to 8.1%.

3. Can subtract S from L or vice versa.

4. If profiles don’t cross, one project dominates the other.

Page 27: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

27

Net Cash Flows for Project S and Project L

1,5001,200

800300

400900

1,3001,500

^Net Cash Flows, CFt

r e dp AEx cte fte -Tax

Year (T) Project S Project L0a $(3,000) $(3,000)1234

Page 28: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

28

Two Reasons NPV Profiles Cross:

1) Size (scale) differences.1) Size (scale) differences. Smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so high k favors small projects.

2) Timing differences.2) Timing differences. Project with faster payback provides more CF in early years for reinvestment. If k is high, early CF especially good, NPVS> NPVL.

Page 29: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

29

Reinvestment Rate Assumptions

NPV assumes reinvest at k.

IRR assumes reinvest at IRR.

Reinvest at opportunity cost, k, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.

Page 30: Chapter 6 Capital Budgeting Techniques © 2005 Thomson/South-Western

30

Before Next Class:

1.Review Chapter 6 materials

2.Do chapter 6 homework3.Prepare for Quiz on Ch

64.Read chapter 7